For Information: West Offaly Power
For Information: West Offaly Power
Project:
Revision remarks
Revision: Revision date: Modified information: Initials:
(a) 6 June 2003 According to MOM#8 H.M.
(b) 1 July 2003 PID KKS code changed H.M.
(c) 19 Sept. 2003 Correct typograghical error H.M.
(d) 22 Oct. 2003 Revised according to FW comment H.M.
For Information
Prepared by:
S1M____-BDB2501d-2
CONTENTS
1.0 TURBINE SYSTEM
Attachment:
Cross Reference List for System Description and
Pre-Commissioning/Commissioning Item
S1M____-BDB2501d-3
The 150 MW steam turbine is reheat, condensing and two casings type
and operates at 3000rpm.
Design steam condition at the main steam inlet flange is 165 bar
absolute at 560oC with exhaust pressure of 0.028 bar absolute.
Two main stop valves equipped with hydraulic actuators are fully
opened to supply steam to the turbine or fully closed to stop to supply
steam to the turbine. Two governor controlled main control valves are
fitted downstream of the stop valves, which modulate under governor
action to control the steam flow and subsequent turbo generator
output.
1.1.1 Turbine
Drain lines are provided on main steam control valves, HIP turbine
casing and reheat steam stop valves to remove drain. Drain is led to
condenser through flash chamber by opening motor operated valve
automatically at start up and shut down.
S1M____-BDB2501d-4
The check valves are provided on cold reheat steam line and extraction
steam line to prevent the turbine from over speed at turbine load
rejection and to prevent the turbine from damage due to reverse flow of
drain and/or cold steam at feed water heater tube leakage.
These check valves have a pneumatic actuator and are forced to close
when turbine trip, water level in feed water heater emergency high.
The steam turbine is equipped with the electrical turning device which
prevents any bending of the rotor and casing during start up, shut down
and standstill. The turning device can be operated both automatically
and manually.
The turning device is installed on the No.1 bearing pedestal.
In order to prevent air from getting into a line that is a vacuum condition
during normal operation, seal water is injected to the gland for valves
being more than 65mm and equal diameter.
Valves having bellows seal at the gland are applied for smaller valves
because such seal water boss can not be provided.
The turbine lube oil system provides oil to the turbine and generator for
lubrication and cooling of the bearings and jacking up of turbine and
generator rotor at start up and shut down.
The main oil pump is a vertical mounted single suction centrifugal type.
The pump is fitted to supply lubricating oil to the each bearing.
A check valve in the main oil pump outlet prevents a back flow through
the pump when the pump is not running.
The standby oil pump is started automatically when discharge pressure
of operating pump is detected as low.
An axial piston type high-pressure oil pump supplies oil to the turbine
and generator bearings. The high-pressure oil lifts (jacks) the turbine
and generator rotor off the bearings and allows the turning gear to
move the rotor.
This pump is used at all times when the turbine is turning. Operation of
the pump is automatic with starting and stopping being initiated by the
turning gear start and stop.
The jacking oil pump can be supplied from the main oil tank or the
bearing lubricating oil supply line after the filters.
There are two 100% duty plate type oil coolers to cool the lube oil by
water supplied from the auxiliary cooling water system. The oil
temperature is regulated by the action of the oil flow control valves.
There are two transfer valves for changing over the duty cooler.
The duplicate type oil filter is fitted with a transfer valve for changing
over the duty filter. The transfer valve ensures that the correct valve
operation occurs during filter change over. The oil filters should be
changed over and the fouled filter change over when the differential
pressure exceeds an allowable limit.
The lubricating oil flow to each bearing can be regulated by action of
the throttle valve fitted in each bearing oil supply pipe.
The turbine control fluid system provide fluid to the servo motor control
of the position main stop valves, main control valves, reheat stop
valves and reheat control valves and some protective devices of the
turbine.
.
Control fluid is of fire-resistant type.
The Control fluid pump is an axial piston pump. The pump is fitted to
supply control fluid to the actuators for main stop valves, main control
valves, reheat stop valves and reheat control valves.
The standby pump is started automatically when discharge pressure of
operating pump is detected as low.
There is a heating pump that raises the control fluid temperature in the
tank up to 40oC by re-circulation of the control fluid.
There are two 100% duty finned type coolers to cool the control fluid by
air.
The both suction and discharge filters are fitted to each control fluid
pump. The control fluid pump should be changed over and the fouled
filter cleaned when the differential pressure exceeds an allowable limit.
4.2.1 Generator
Type Totally enclosed air to water cooled,
3 phase AC synchronous generator
Rating Continuous
Output 181,700 kVA
Voltage 11,500 V
Current 9,122 A
Number of phase 3 phase
Power factor 0.85 (lagging)
Frequency 50 Hz
Rotating speed 3,000 rpm
Excitation method Brushless
Insulation class F
Temperature rise B
5.1.1 Condenser
The surface condenser is tube and shell type. The cooling water flows
through the cooling tubes where indirect contact of the exhaust steam
and cooling water occurs. As the steam is condensed, the condensate
is collected in the main condenser hotwell and delivered to the
deaerator through LP heaters by the condensate pump.
Non-condensable gases not absorbed into the condensate are
extracted from the condenser by the vacuum pump system to maintain
0.028 bara. of vacuum pressure at the design conditions.
The condenser has two separate cooling water chambers allowing tube
blocking during operation if tube leakage is occurred.
LP bypass nozzle with necessary erosion protection is located at the
condenser neck.
The purpose of the liquid ring type vacuum pump system is to remove
air accumulated in the top of condenser cooling water chamber.
The mixture of air with water is extracted by the vacuum pump through
vacuum tank to prevent the pump from water induction. Water is led to
drain funnel through a barometric tank while air is released to
atmosphere through a separator.
S1M____-BDB2501d-14
5.2.1 Condenser
Type Surface type
Internal Pressure 0.028 bara
Cooling water Inlet temperature 12 oC
Cooling water outlet temperature 19.96 oC
Cooling Water Flow Rate 17,511 m3/hr
Size of cooling tube 23mm (outer dia.), 0.7mm (thick)
Number of Cooling Tube 12,764
Total cooling surface 10,744 m2
Number of Pass 2
Material of Cooling Tube Stainless steel type 304
Vacuum Pumps
Quantity One
Type Liquid ring vacuum pump
Speed 1500 rpm
Seal Water 19 l/min
Separator
Quantity One
Type Vertically cylindrical
S1M____-BDB2501d-15
The LP feed water heater No.1 is tube and shell type. The condensate
from condensate pump outlet flows through the cooling tubes where
indirect contact of the extraction steam and cooling water occurs. As
the steam is condensed, the condensate is collected to the condenser.
The heater is installed in the condenser neck. The extraction steam
piping from LP turbine casing to the heater is installed in the condenser.
Heater drain is led to the condenser through U-seal piping to
compensate differential pressure between heater internal pressure and
condenser internal pressure.
The purpose of the liquid ring type vacuum pump system is to remove
non-condensable gases from the main condenser that accumulates as
the incoming steam condenses.
The non-condensable gases are taken separately off the gas cooling
zones of the main condenser. The non-condensable gas from the main
condenser gas cooling zones flows first through vacuum pump.
7.2.2 Separator
Quantity Two (one for operation, one for standby)
Type Vertically cylindrical
S1M____-BDB2501d-17
Reference Document ;
An output from the above loops is given to the CV position control loop
as its setting. Consequently, it adjusts CV position in accordance with
its characteristic curves respectively.
This portion outputs opening command to the Electro-hydraulic (E/H)
converter mounted on each CV separately. Due to each E/H
converter having two magnet coils, two separate signal (±10V) lines
are connected to them.
Reference Document ;
Turbine protection device are arrange to actuate trip solenoid valve for
main steam stop valve /reheat stop valve, and operate to close these
emergency valves.
In case the following faults is occurred in turbine and the around,
turbine would be stopped automatically.
9.2 Function
(1) Overall
The turbine shall be provided with duplicated independent over
speed protection channels.
Over speed protection system is mainly composed of Bentry
Nevada 3500/53 over speed system, speed sensor, proximittor.
The speed signal (pulse signal) detected by 6 pieces of speed
sensors is transmitted to 3500/53 system.
In case of over speed, 3500/53 system output-relay operates,
and the trip signal is processed by duplex 2 out of 3 voting
hardwired circuit.
These devices shall be entirely separate from the regulating
governor and shall be capable of effecting immediate closure of
S1M____-BDB2501d-21
Alarm : ± 0.5 mm
Trip : ± 1.0 mm
Alarm : 90 deg.C
Trip : 110 deg.C
The alarm will be issued when monitoring signal of lube oil pressure fall
less than alarm value.
The trip signal is made by 2 out of 3 logic circuit in turbine protection
system.
S1M____-BDB2501d-24
In the event of boiler trip, turbine shall be tripped in order to prevent the
damage of turbine body by wet steam getting into the turbine.
In the event of EHG controller heavy fault such as cut of control power,
controller fault and loss of turbine speed signal, the speed control is
impossible and then safe operation is impossible, so turbine shall be
tripped.
Reference Document ;
The main areas of application of the REG216 system are the protection
of generator.
The REG216 belongs to the generation of fully digital generator
protection devices, i.e. analogue to digital conversion of the input
variables takes place immediately after the input transformers and all
further processing of the digital signals is performed by
microprocessors and controlled by programs. Provision is thus made
for the exchange of data such as reaction less reporting of binary
states, events, measurements and protection parameters or the
activation of a different set of settings by higher level control systems.
The availability of a device, i.e. the ratio between its mean operating
time without failure and its total life, is most certainly its most important
characteristic. As a consequence of the continuous supervision of its
functions, this quotient in the case of REG216 is typically always close
to 1.
The menu-based HMI (human machine inter-face) makes the tasks of
connection, configuration and setting simplicity itself. A maximum of
flexibility, i.e. the ability to adapt the protection for application in a
particular power system or to coordinate with, or replace units in an
existing protection scheme, is provided in REG216 by ancillary
software functions and the assignment of input and output signals via
the HMI.
REG216’s reliability, selectivity and stability are backed by decades of
experience in the protection of transmission and distribution systems.
Digital processing ensures consistent accuracy and sensibility
throughout its operational life.
These functions can be activated within the scope of the CPU capacity.
One or the other function may be applied in accordance with the PT
connections (e.g. three phase for minimum impedance or single phase
S1M____-BDB2501d-26
10.2 Function
10.2.2 Measuring
for
System Description and Pre-
Pre-Commissioning/Commissioning Item
MUH-031022 (1/6)
System Description Commissioning Item
1.0 Mechanical :
Turbine System M-14 : Gland steam condenser exhauster operation test
M-21 : HP stop valve & reheat stop valve operation test
M-22 : Adjustment of HP steam control valve and reheat
intercept valve
M-23 : Reheat check valve & Extraction check valve
operation test
M-26 : Turning gear operation test
M-51 : No-load operation test of turbine and generator
M-54 : Partial and rated load operation test
M-57 : Heat run test
Electrical :
See common
Control & Instrument :
10 : Interlock test
11 : Vibration monitoring loop test
12 : Eccentricity monitoring loop test
13 : Zero speed monitoring loop test
14 : Shaft position monitoring loop test
15 : Expansion monitoring loop test
2.0 Mechanical :
Lube Oil System M-1 : Adjustment of oil level of main oil tank
M-3 : Setting of pressure switches
M-4 : Gas charge for Accumulator
M-5 : Main Oil tank vapor extractor operation test
M-6 : Main oil pump operation test
M-7 : Emergency oil pump operation test
M-8 : Jacking oil pump operation test
M-9 : Oil purifier operation test
M-17 : Main oil pump automatic starting test
M-18 : Emergency oil pump automatic starting test
M-20 : Adjustment of bearing oil pressure
M-24 : Change over test of oil line equipment and oil
pump
M-25 : Jack up test
MUH-031022 (2/6)
Electrical :
See common
Control & Instrument :
See common
3.0 Mechanical :
Control Fluid System M-2 : Adjustment of oil level of control fluid tank
M-3 : Setting of pressure switches
M-4 : Gas charge for Accumulator
M-10 : Control fluid pump operation test
M-11 : Control fluid heating pump operation test
M-12 : Control fluid cooler fan operation test
M-13 : Control fluid circulation pump operation test
M-19 : Control oil pump automatic starting test
M-24 : Change over test of oil line equipment and oil
pump
Electrical :
See common
Control & Instrument :
See common
4.0 Mechanical :
Generator System M-51 : No-load operation test of turbine and generator
M-54 : Partial and rated load operation test
M-57 : Heat run test
Electrical :
6 : Main circuit test
8 : Synchronizing circuit adjustment and test
11 : Measurement of generator insulation
12 : Shaft Voltage measurement
13 : Zero speed monitoring loop test
14 : Shaft position monitoring loop test
15 : Expansion monitoring loop test
Control & Instrument :
11 : Vibration monitoring loop test
5.0 Mechanical :
Condenser System M-16 : Cooling water air evacuation pump operation test
M-61 : Condensate oxygen content test
MUH-031022 (3/6)
Electrical :
See common
Control & Instrument :
See common
6.0 Mechanical :
LP Feed Water Heater System See common
Electrical :
See common
Control & Instrument :
See common
7.0 Mechanical :
Vacuum Pump System M-15 : Vacuum pump operation test
M-29 : Vacuum up test
M-30 : Vacuum pump automatic starting test
M-60 : Vacuum tightness test
Electrical :
See common
Control & Instrument :
See common
8.0 Mechanical :
Turbine Control system M-27 : ATS simulation test
M-51 : No-load operation test of turbine and generator
M-55 : Load rejection test
M-56 : Valve test during load operation
M-58 : House load operation test
M-59 : Load change test
M-62 : Main steam pressure control test
M-63 : Main steam limit pressure control test
M-64 : Vacuum unloading test
M-65 : Turbine start up test by ATS at cold, warm, hot
mode condition
Electrical :
15 : Turbine & Generator regulating system (TGR)
Control & Instrument :
16 : Control valve operation check
17 : DCS interface test
MUH-031022 (4/6)
9.0 Mechanical :
Turbine Protection System M-28 : Turbine Trip interlock test
M-31 : Low Vacuum trip test
M-52 : Master trip test
M-53 : Over speed trip test
M-56 : Valve test during load operation
Electrical :
10 : Interlock test
Control & Instrument :
10 : Speed monitoring loop test
11 : Vibration monitoring loop test
12 : Eccentricity monitoring loop test
14 : Shaft position monitoring loop test
15 : Expansion monitoring loop test
10.0 Mechanical :
Generator Protection System See common
Electrical :
2 : PT & CT secondary circuit test
4 : Protection relay setting & test
13 : Generator open circuit test
14 : Generator short circuit test
16 : Neutral grounding transformer cubicle test
Control & Instrument :
8 : Temperature monitoring loop test
11 : vibration monitoring loop test
Common Mechanical :
None
Electrical :
1 : Panel installation and cable connection inspection
3 : Calibration of measuring instruments
5 : Measurement of insulation resistance
7 : Motor load operation test
9 : Sequence test
10 : Interlock test
MUH-031022 (5/6)
Control & Instrument :
2 : Visual structure inspection
3 : Power supply check and setup
4 : Calibration of pressure switch
5 : Calibration of level switch
6 : Instrument & instrument circuit test
7 : Pressure monitoring loop test
8 : Temperature monitoring loop test
9 : Level monitoring loop test
MUH-031022 (6/6)