GOVERNMENT OF KERALA
Abstract
Finance Department ~ implementation of PRICE Software — Phase II — Orders
issued
FINANCE (INDUSTRIES & PUBLIC WORKS - B) DEPARTMENT
G.O.(Rt)No. 2997/2019/Fin. Dated, Thiruvananthapuram, 11.04.2019
1) G.0.(Rt) No. 1482/2012/PWD dated 18.08.2012
2) G.O.(RU) No. 1729/2016/PWD dated 20.12.2016
3) G.O.(RY) No. 122/2017/PWD dated 02.02.2017
4) Letter No. CE/Admin/IT/PRICE/2016-17 dated 16.02.2019 from the
Chief Engineer, PWD (NH & Admin).
*& 5) Minutes of the Meeting held in the Chamber of Additional Chief
Secretary (Finance) on 08.04.2019
Government vide Order referred 1“ above, had entrusted the Project
Director, KSTP to develop an application software for computerizing the estimate
preparation, AS and TS Sanctioning, tendering, bill payment ete in PWD. The
software was later named as PRICE and NIC was selected as agency for software
deyelopment. Thereafter, the first phase of the project was completed which
cluded online estimate preparation, submission with approval modules and the
same was used successfully in all wings of Public Works Department. Later,
Government decided to implement PRICE Software in all engineering departments
and public sector units. Presently, PRICE Software 1" phase is being used by
engineering departments and PSUs / other agencies. As per the reference cited 2"
above, Government entrusted the Executive Engineer (IT, GIS & RMMS Cell) as
the Administrator of PRICE in the Public Works Department under the overallsupervision of the Chief Engineer (Administration), Public Works Department. As
per Government Order read 3" above, Administrative Sanction was accorded for
the implementation of the 2“ phase of PRICE Software in the engineering
departments and to entrust this work to National Informatics Centre, Kerala,
subject to certain conditions.
Vide letter cited above, the Chief Engineer, PWD (NH & Administration) has
submitted proposal for making the PRICE Software 2" Phase live in Public Works
Department with facilities for Asset Database Generation with Electronic Asset
Registers, Automatic Bid Document Generation, E-Measurement Book, E-Level
Field Book, Automatic Bill Generation, Revised estimate preparation, EMIT
integration and Contractor's portal and requested to approve the proposal.
Government have examined the matter in detail and are pleased to issue the
following guidelines for the implementation of PRICE Software Phase
4) The second phase of PRICE Software will be made live with effect from the
1* of June 2019.
2) The asset details shall be tagged with each and every maintenance work
estimate, For this, the Asset Register (roads, buildings, bridges, culverts etc)
in PRICE shall be made up to date, All Executive Engineers and their
Subordinate Officers in charge of assets shall ensure that the details of
assets (roads, buildings, bridges, culverts etc) under their control as per the
hard copy of Asset Register of the Division shall be entered, verified and
approved in PRICE Software. From 1" of July 2019, all maintenance
estim
ates in PRICE-PWD can only be prepared after selecting the asset on
which the maintenance work is proposed to be carried out. The details of
roads shall include chainage of roads also.
3) From 1 June 2019 onwards, the NIT and Bid Document for tendering of all
works shall be generated through PRICE Software only. The Tender Inviting
Authorities shall ensure that all the details required for generating the NIT
and Bid Document shall be correctly entered, verified and approved. The4)
6)
‘Tender Inviting Authority and his concerned Subordinate Officers shall be
responsible for any incorrect / incomplete bid document generated from
PRICE Software due to incorrect data
Integration of PRICE Software with E-portal for tendering shall be done at
the earliest to eliminate erroneous entry of quantities while tendering /
omission of bid conditions.
The date of recording measurement / check measurement shall be captur
and no provision to record measurement on a back date shall be
entertained. The measurement entries in E-Measurement book shall be
completed within 10 days after the time of completion of that item of work
and check measurements shall be done within another 7 days in case of
visible measurements. In case of hidden measurements all
pre-measurements shall be entered by Assistant Engineer and check
measurement / super check shall be completed before executing the nex
tem. In case of works exceeding the Technical Sanction power of Assistant
Executive Engineer, super check on 10% of value of work shall be done by
Executive Engineer.
For works costing more than Rupees five crores, the contractor shall record
the measurements. A definite time frame has to be fixed within which
sistant Engineer has to verify the measurements and for both Assistant
Executive Engineer and Executive Engineer to conduct and record check
measurements and super check. If Assistant Engineer is not verifying the
meat
‘ements entered by contractor within 7 working days, there should be
an alert message to Agreement Authority and the Assistant Executive
Engineer regarding the same. Assistant Engineer has to complete the
verification of measurement within 15 days after the time of completion of
that item of work and check measurements shall be done within another 10
days in case of visible measurements. In case of hidden measurements , all
pre-measurements shall be entered and check measurements / super check
3shall be completed before executing the next item. Assistant Engineer /
Assistant Executive Engineer shall ensure and certify that required periodic
tests by the quality control wing are conducted and complied as a criteria
before the bill is submitted for passing.
7) Bills for all works shall be generated through the E-Bill facility of PRICE
Software for all works for which measurements are entered in the
E-Measurement Book of PRICE Software.
8) The Contractor shall also has to accept / reject the measurement within 7
days of recording of measurement by the Assistant Engineer. Assistant
Engineer shall intimate the contractor regarding the recorded measurement
within the above period. Beyond this period, it will be deemed that the
contractor has accepted the measurement. The bid conditions may be
modified to that extent
PRICE,
4.9) Revised estimates for all works shall be prepared and approved
Software for all works which are not started as on 01.06.2019 or there is
measurement entered in E-Measurement Book. The above clause shall be in
compliance with all Government directions, For works requiring
Government sanction, the approval of Revised estimate shall be done only
after getting the same,
10) Currently the bill copies (KPWD Form No. 23) submitted to the Accountant
General / Treasury is being signed by the concerned Assistant
ineer,
Assistant Executive Engineer and Executive Engineer. For those bill copies
v
ich will be generated through the PRICE Software, signature of the
Passing Authority along with digital signatures of Assistant Engineer and
Assistant Executive Engineer are necessary for the submission of bill copies
to the Accountant General / Treasury.
11) The market rates values in approved observed data (approved by the Chief
Engineer's Committee) should not be treated as similar to the departmentalschedule of rates since the rates of approved observed data are included
based on a prevailed local market rate
12) Negotiations shall be done with overall lowest quoted bidder (1) only to
reduce the high quoted rates so as to explore the possibility for bringing
them within DSR + 10% tolerance limit or LMR, whichever is lower.
13) In case of quantities exceeding the agreement schedule quantities and up
25% limit that are necessitated for proper completion of work, the
contract rates of corresponding item shall apply.
14) For excess quantities, ie, quantities in excess of 25% over agreement
schedule quantities and whose rates are above the Technical Sanctioned
estimate rate modified by overall tender excess / tender deficit, the
admissible rates shall be limited to Technical Sanctioned estimate rate
modified by overall tender excess / tender deficit, as the case may be,
subject to a maximum of PWD local market rates prevailing at the time of
smorderinge =e seene ne
15) For percentage rate contracts, the rate for extra item shall be arrived at by
applying the percentage tender excess or tender deduction to the
departmental data rate excluding the cost of departmental material and
as per the original schedule on which the tender is
nvited. Also, for percentage rate contract, in case of variation in quantity
over 25% of agreed quantity, no change in rate will be permitted under any
circumstances.
extra
As per Para 39.5.2 and 39.5.3 of Standard Bid Document, in case of
ns for which similar items do not exist in the contract and rate exists in
the prevailing departmental data rate, the rate shall be arrived at on the
basis of departmental data rate at the time of issuing Technical Sanction
modified by overall tender excess / deduction except on the cost of
departmental material subject to a maximum of LMR at the time of ordering
the item.®
17) The approved Standard Bid Document for works stands modified up to
these extents
18) For those bills of works generated and passed through PRICE Software, the
corresponding entries in EMLI Software shall be done through the PRICE
Software either by the Divisional Accountant or the Head Clerk (for
Sub-division works)
By Order of the Governor,
MANOJ JOSHI
Additional Chief Secretary (Finance)
The Principal Accountant General (A&E) Kerala, Thiruvanathapuram
The Principal Accountant General (G&SSA) Kerala, Thiruvanathapuram
The Accountant General (E&RSA) Kerala, Thiruvanathapuram
he Principal Accountant General (Audit) Kerala, Thiruvanathapuram,
All Heads of Departments and Offices
| Departments of Secretariat
The Nodal Officer, www. finance.kerala.gov.in
Stock file/ Office Copy (E-1128429)
Forwarded/By Order
dager]
Section Officer