Report of Visit To Bihar To Review Implementation of Important Schemes and Programmes Executive Summary
Report of Visit To Bihar To Review Implementation of Important Schemes and Programmes Executive Summary
1
Under the National Drinking Water Mission, the state has a huge opening balance of
Rs. 414 crore. The expenditure in 2008-09 was only Rs. 165 crore against the
allocation of Rs. 425 crore.
The state has made considerable progress under Sarva Shiksha Abhiyan and 98%
habitations have primary schools within a radius of one km. However, the drop-out
rate at the primary level is 51% compared to the national average of 25%. This
programme should be accorded the highest priority of the state.
The progress of JNNURM has been very slow as the projects took a long time to be
prepared and approved. This programme requires greater attention.
Bihar’s Plan performance has improved in the past 4 years and the Plan expenditure
has increased from Rs. 4465 crore in 2005-06 to Rs. 12,511 crore in 2008-09.
Kosi Floods Reconstruction and Rehabilitation Package: Bihar’s claim for a Package
of Rs. 14,800 crore should be considered.
Handlooms: Not even a single Mega cluster has been given to Bihar even though
Bihar has a large number of minority handloom weavers in and around Bhagalpur.
Agriculture: Bihar has launched an Agriculture Road Map. The Credit Deposit ratio
is very poor and hence only 2% of the credit programme will reach Bihar. Hence the
credit needs need to be taken care of.
Food Security: Poor households in Bihar number 1.50 crore which is more than
double the GOI estimate of 65 lakh households. Unless the manner in which
poverty is measured is sorted out, the food security scheme will leave half of the
poor population uncovered.
FRBM Act: The states should be permitted flexibility of 1.5% over the prescribed
target of 4% for fiscal deficit.
Devolution of Central taxes: As a result of tax reliefs in the budget, Bihar faces a
possible reduction of Rs. 4616 crore as its share of Central taxes.
Coal blocks must be allocated for the Twelfth Plan as investors in the power sector
would not come forward without this vital linkage.
Conclusion
Bihar deserves to be treated on a special footing, in view of its resource base, very
low level of human development, and the severe deprivation of majority of its
population. Against this context, most of the issues raised by the state government
require special consideration.
If Sarva Siksha Abhiyan(SSA) is one of the better implemented flagship programmes
in the state; implementation of JNNURM appears to be on the other end of the
spectrum. There is a need for a special Task Force for monitoring the
implementation of flagship and other important programmes.
2
REPORT OF VISIT TO BIHAR TO REVIEW IMPLEMENTATION OF
IMPORTANT SCHEMES AND PROGRAMMES
1. INTRODUCTION
The state of Bihar with an area of 94,163 sq. km. accounts for about 3% of the total
geographical area of the country. It has a population of 82.88 million which accounts for
8% of the population of the country. The adverse land-man ratio is reflected in the high
density of population, which is 880 per sq. km. The decadal growth of population for
1991-2001 is 28.43% which is the highest in the country. According to 2001 census, the
literacy rate in the state is 47.53% and is the lowest in the country. The Scheduled Caste
population comprises 15.47% whereas tribal population constitutes a mere 0.91% of the
total population. The economy of the state is characterized by high incidence of poverty,
low literacy rate, unemployment and low per capita income. The human development
indicators are also very poor. Some of the important developmental indicators of Bihar
are given below:
The Human Development Index for Bihar is the lowest at 0.367 in 2001, which
however, is an improvement over the earlier years (1981: 0.237, 1991: 0.308).
The state’s per capita income in 2008-09 is Rs. 12,643 at current prices against the
national average of Rs. 37,490.
The average annual growth rate of Gross State Domestic Product between 2005-06
to 2008-09 has been 13.68% compared to the national average of 8.48%.
Percentage of population below poverty line in 2004-05 is 41.4 against the national
average of 27.5.
The literacy rate of the state is 47.53% in 2001 compared to the All India average of
65.38% while the female literacy rate is 33.57% (All India 54.28%).
3
The birth rate per thousand in the state is 29.4 (2007) compared to 23.1 for the
country as a whole.
The death rate per thousand in the State is 7.5 (2007) compared to 7.4 for the
country as a whole.
The estimated Infant Mortality Rate is 58 per thousand in 2007 compared to the
national average of 55.
The population density in the state as per 2001 census is 880 per sq. km. against the
national figure of 324.
● 89.60% of the population lives in rural areas.
Eleventh Plan and Annual Plan 2007-08, 2008-09 and 2009-10: Outlays
Planning Commission has indicated a tentative estimate of Rs. 60,631.00 crore for
the Eleventh Five Year Plan. An outlay of Rs.10,200.00 crore was approved for Annual
Plan 2007-08 against which the State Government has reported an expenditure of
Rs.9,652.30 crore which is 94.63% of the approved outlay. For Annual Plan 2008-09, an
outlay of Rs.13,500.00 crore was approved and the State Government has reported an
expenditure of Rs. 12,510.78 crore. The approved outlay for 2009-10 is Rs.16,000 crore.
2. IMPLEMENTATION OF FLAGSHIP PROGRAMMES OF GOVERNMENT OF NDIA
2.1. National Rural Employment Guarantee Act (NREGA)
During 2009-10, 24.83 lakh households have been provided employment, with a total of
647.71 lakh persondays and 26 average persondays per household. Funds to the tune of
4
Rs. 50,333.69 lakh have been released by the centre, and Rs.3386.71 lakh by the state till
date in the current year. A total expenditure of Rs. 93,253.46 lakh has been incurred till
date(Source: MORD Website).
Field Visit
Mud road and construction of culvert from NH-30 to railway line in village Maujipur, Fatua:
The work involved a cost of Rs. 3.90 lakh and 3400 mandays. Wage rate is reported to be
about Rs. 89/- per day. The quality of mud road was not up to the mark and is likely to
be washed away in heavy rain. Only the culvert, made by a labour contractor, seems to
be of some quality. Two families with about 7-8 children were found to be working near
the site on brick-making. They came from a distant village where the children were
reportedly going to anganwadi centre/school. The BDO/PO was directed to ensure that
the parents sent their children to the anganwadi centre/school, near the site till they are
engaged in brick making work there.
Against a central allocation of Rs. 2,24,039.39 lakh, an amount of Rs. 99,535.53 lakh has
been released upto 31st August, 2009. State’s contribution is of the order of Rs. 33,178.51
lakh. During 2009-10 , Rs. 1,33,844.95 lakh have reportedly been utilized.
Against a target of 10,98,001 houses, 3,08,072 houses were constructed during 2009-10.
Thus the achievement is 28.06 %.The State gets about 26% of the country’s IAY funds.
Fund utilisation is 59.46% while in physical terms the achievement is 34.75%. As per an
interim report of the study being conducted by CBRI, the quality of construction is a
matter of concern.
Field Visit
5
During 2009-10, against an allocation of Rs.61,680.00 lakh, Rs. 52,836.00 lakh have been
released till 5.11.2009 and Rs. 25,499.40 lakh have been utilized. The utilization has been
very poor.
Progress
69,246 Accredited Social Health Activists (ASHAs) have been selected out of which
57,362 ASHAs have been trained with first module of training. However, no ASHAs
are in position with drug kits.
• Out of total 8,858 Sub-centres, 5,880 are functional with two ANMs. In total, 5,896
ANMs have been appointed on contract at various levels.
• Out of the total of 1641 PHCs, 533 are working 24x 7 as on date, 3 staff nurses have
been positioned in 105 PHCs.
• During 2008-09, 11.00 lakh beneficiaries under Janani Suraksha Yojana for institutional
deliveries were reported by the state as against 1.14 lakh beneficiaries during 2006-07.
In the current year, 3 lakh beneficiaries were reported till 31st August, 2009.
• The Special Component head under NRHM could be allowed to be utilized for other
essential purposes also such as enhancing the salary of Government doctors and
other para medical staff; hospital maintenance and provision of facilities such as
canteen etc so that PHCs can function 24x7 more effectively.
6
• Reappropriation of funds in the Programme Implementation Plan(PIP) may be
allowed as in the current year additional funds are required for items such as
ambulance services, bio-metric system for attendance, etc.
• The number of Auxiliary Nurse Mid-wife(ANMs) needs to be increased.
• The infrastructure fund may be separated from Part(B) in NRHM additionalities as
districts are unable to spend funds under infrastructure.
• The provision under Rogi Kalyan Samitis needs to be enhanced in view of the
increase in patient load and the need to upgrade facilities.
Field Visit
As per latest MHRD reports (PAB-2009-10), 98% habitations in Bihar are served
with primary schools within 1 km radius. Of the 85,229 habitations eligible for primary
school, 1,457 habitations are without primary schools. The state is yet to operationalize
358 PS and 1,318 UPS sanctioned upto 2008-09. Bhagalpur, East Champaran, Kaimur,
Munger and Muzaffarpur together have yet to operationalize over 350 primary schools.
East Champaran, Madhepura, Aurangabad, Muzaffarpur, Sheohar, Sitamarhi and
Vaishali together have yet to operationalize over 800 UPS. A total number of 6,018
habitations do not have UPS within 3 kms.
Dropout Rates, Out of School Children (OoSC) : Selected Educational Statistics (SES)
2006-07 has reported high incidence of dropout at primary (51.63%) and elementary
(76.71%). As per latest MHRD reports, the state enrolled 5.28 lakh OoSC children in the 6-
14 age-group in schools/EGS/AIE centres during 2008-09. The total number of remaining
OoSC is 5.23 lakh, constituting 2.5% of the total child population of the relevant age-
group, is targeted to be enrolled in 2009-10. Districts like Darbhanga, East & West
Champaran, Nawada, Nalanda, Katihar, Aurangabad and Begusarai have large number
of OoSC.
7
Quality Improvement: As per DISE (2007-08), Pupil Teacher Ratio (PTR) for primary
classes has improved to 54:1 (national ratio 46:1), as compared to 65:1 in 2006-07.
Similarly, PTR for upper primary classes has increased to 59:1 (national ratio 34:1), as
compared to 67:1 in 2006-07. 2.52 lakh teachers posts were sanctioned under SSA upto
2007-08, Against this ,the backlog of teacher vacancies (38,152 under SSA and 47,642
under state budget) is likely to be cleared soon.
A matter of grave concern is the large number of untrained teachers (1.46 lakh).
During 2008-09, against 67,721 teachers only 9481 (14%) have been given induction
training. The state govt is getting these teachers trained with the help of IGNOU through
a 2-year distance education diploma course in primary education. The state govt is
planning to enrol about 60,000 teachers in IGNOU in the current year ( 2009-10).
Allocations and Expenditure under SSA
(Rs. Crore)
Special Focus: A total number of 34 out of 38 districts in the state are special focus
districts identified by the MHRD, including 17 districts with more than 25,000 out of
school children. Araria, Darbhanga, Katihar, Purnea, Sitamarhi and West Champaran are
the 7 minority-concentration districts with their population above 20%.
Kasturba Gandhi Balika Vidyalaya (KGBV): Out of 391 KGBVs (residential upper
primary schools for girls) sanctioned, 369 are operational with 27,963 girls enrolled (SC-
8
49%; ST-7%; OBC-25%; Minority-16%; and BPL-4%). The progress of construction of
hostels has been very slow, as only 57 are completed, 285 are in progress, and 56 are yet
to start. The availability and acquisition of land has been a problem, so hostel buildings
were hired on rent. Low resource absorption capacity in the state was also reflected in the
expenditure under KGBV during 2007-08. Out of an outlay of Rs.130 crore, only Rs.41
crore (32%) could be spent amounting to a shortfall of Rs.89 crore. Similarly, spill over
during 2008-09 amounted to Rs.73.12 crore.
Civil Works: The spill-over amount under civil works is Rs.837.52 crore in the current
year. In the past four years spill-over amounts have been high (Rs.166.06 crore in 2005-06,
Rs.163.46 crore in 2006-07, Rs.466.09 crore in 2007-08, and Rs.614.70 crore in 2008-09). It
reflects the constraint in the capacity of the state to execute and complete sanctioned civil
works in time. The state has to complete a large number of civil works which have been
sanctioned so far. Since the state has shown constraints in capacity to execute large
amount of civil works, this component was limited to 21.54% (Rs.1209.46 crore) of the
outlay in 2008-09. Further, 6286 school buildings carry forward a deferred liability of 75%
funds (Rs.421.85 crore) for 2009-10, and also for 541 NPS buildings sanctioned as new
schools in 2008-09 for which construction is to take place in 2009-10. Thus an amount of
Rs.470.08 crore is already a deferred liability for civil works in the State for 2009-10.
Therefore, the state needs to complete all pending civil works. The state has also not
undertaken third party evaluation of civil works despite a specific commitment in this
regard.
9
percentage of Muslim population in the state is 16.53 and the enrolment of Muslim
children is 11.27% at PS and 8.22% at UPS, as per DISE 2007-08.
• There is a gap of 2,08,367 classrooms for classes I-VIII against which, only 1,39,236
classrooms have been sanctioned under SSA. The large number of classrooms is also
required as the number of out of school children has been reduced from 45,75,692 in
2001-02 to 10,10,730 in 2008-09.
• The sliding scale of central share has been an issue of concern. The state government’s
budget for elementary education in the last 4 years has registered an increase from
Rs.4260 crore to Rs.8061 crore. This problem will be compounded with the coming
into force of the Right to Education Act which would further increase the financial
burden on the state. Hence, the sharing pattern under SSA needs to be reconsidered
for a state like Bihar.
Field Visits
Primary schools (Rajkiya Prathmic Kanya Vidyalaya Wajitpur, Vaishali district; Middle school,
Harpur, Samastipur; and Middle school, Vishambhar Ailat, Samastipur):
Learning levels were relatively satisfactory, copies had been checked, and the schools
were generally neat. The girls were in school uniform and many had been taught judo as
well. There was general satisfaction about the mid day meal scheme.
10
as the girls seemed to be well disciplined and happy at the same time. One major
problem is what these girls would do after they pass class VIII as the scheme is only up to
class VIII.
MDMS was initially launched in the state on 1 st September, 2004, with an initial
coverage of about 1 lakh children. The cooked mid-day meals are being served in all the
primary schools of the state from January 2005. Coverage under the scheme increased
gradually and all children in classes I-V, including those in EGS / AIE centres, were
covered from April 2005. The MDMS was introduced in UPS in all the 530 EBBs since
March 2008. The state government is paying @60 paisa per child and the Central Govt.
gives Rs.1.50 per child per day. From 2008-09, the scheme is covering UPS in all blocks of
the State.
11
8 Central assistance released for 2009-10 (upto 4.9.2009)Total allocation- 2009-10: Rs.467.80 cr.
Releases: Rs.159.48 cr.
(i) Cost of Foodgrains paid to FCI (i) Rs.42.53 cr.
(ii) Cooking cost (ii) Rs.108.84 cr.
(iii) Transport Subsidy (iii) Rs.5.35 cr.
(iv) MME @ 1.8%: (iv) Rs.2.76 cr.
10 Total Central allocation for cooking cost for 2009-10: Rs.435.35 crore.
Minimum Mandatory State Contribution for cooking Re.0.50 paise per child per school day
cost:-
11 Calorific Value PS: 450 calories with 12 gm. of protein.
UPS: 700 calories with 20 gm of
protein.
12 Weekly menu Sabji/Rajma/Rice/Dal/Rice-Dal-
Sabji, Khichri-Chokha, Daliya, Egg
Curry
13. Constitution of Steering-Cum-Monitoring committees Yes / Yes / Yes. But their functions
at State level / District level / Block level seem to be ineffective.
Field Visits
During field visits, it was observed that MDMS is popular and widely known. All the
children spoken to informed that food is served in their schools - although there were
general complaints about quality.
The opening balance as on 1.4.2009 was Rs. 1,932.13 lakh. An outlay of Rs. 3,825.00
lakh was approved in AP 2009-10. An expenditure of Rs. 417.33 lakh was incurred during
2009-10 till 26.8.2009, leaving an unspent balance of Rs. 1,514.80 lakh for the remaining
part of AP 2009-10.
12
• Lack of strong market link–up continues to riddle NHM. Efforts at loosening the grips
of the regulated markets by amending the APMC Act and opening to larger private
participation have not met with much enthusiasm, as was envisaged.
• There is need for concurrent evaluation of NHM in order to obtain a feedback on its
implementation. The outcome of NHM should be assessed in order to know the
economic benefits that accrue to a farmer and not get carried away by the mere hype
of increasing coverage by NHM in the country.
• Revision of schedule of rates for Sprinkler and Drip irrigation system under centrally
sponsored Micro Irrigation scheme: Government of India decides the schedule of
rates for Sprinkler and Drip irrigation system and on that basis 50% subsidy (Central
share 40% and 10% State share) is provided under provisions of the scheme. State
government has decided to provide 10% additional subsidy from its own resources.
However, the scheme is still not popular. One of the important reasons for its slow
progress is the low and unrealistic schedule of rates for the above irrigation systems.
The current market rate for laying Drip Irrigation system in one hectare area at 1x1
meter spacing is around Rs. 88,000 whereas Government of India schedule rate is only
Rs. 57,600. For the sprinkler irrigation system current market rate is around Rs. 27,500
for one hectare area whereas Government of India rate is only Rs. 14,270. These rates
should be realistically revised upwards.
• Under the Rashtriya Krishi Vikas Yojana, the methodology used for calculating the
amount of grant under the scheme as percentage of plan outlay is not suited to Bihar.
The plan size of the state is increasing at a very fast pace and it would be better if the
Ministry of Agriculture could base the calculation of grant on the absolute amount of
funding for the agriculture sector.
13
(covering districts)
10th Plan = 26 (25)
11th Plan = 17 (13)
Total cost of projects sanctioned
(including service charges of CPSUs, if any) = 10th Plan Rs 1495.80 Crore
11th Plan Rs.1480.09 Crore
Funds released = Rs. 2387.41 Crore
11th Plan
No. of un-electrified villages to be electrified under the project = 6086
No. of electrified villages to be covered (for household elec.) = 6651
Status of progress
(i) Notice Inviting tenders issued : 42 projects
(ii) No. of projects for which contracts awarded: 42 projects
(iii) Physical achievements so far: 17,085 unelectrified villages were electrified.
Free electricity connections were provided to 6,92,370 BPL households.
(iv) In August, 2005 and July, 2006, Quadripartite and Tri-partite agreements
had been signed.
(v) Notification of rural areas is done by the state. This is required as per
Section 14 of Electricity Act 2003.
(vi) Franchisees are deployed in the state to cover 5250 villages so far as
required under RGGVY conditionality.
• The uniform benchmark of Rs.4 lakh per village was too small to cover the
large sized villages in Bihar. They would require at least Rs. 7-8 lakh more
per village.
• RGGVY provisions need to be amended to include three-phase connectivity
Year-wise Allocation, Release & Expenditure under PMGSY : 2006-07 to 2009-10 (upto
May, 2009)
(Rs. in crore)
2007-08 2008-09 2009-10
Allocation Release Expend Alloca Release Expenditur Release Expen
14
iture tion e diture
337.00 701.15 580.68 337.00 1022.62 1067.54 308.34 162.03
The progress under PMGSY in the state has been slow. The programme was being
implemented by five Central Agencies. The state government has now strengthened its
own agencies and the works being approved in the last few years are being implemented
by the state government’s agencies.
15
2.13 Drinking Water Mission (ARWSP)
The State has a huge opening balance of Rs. 414 crore. The Department of Drinking
Water will release the second instalment if the state furnishes the reports online. The state
needs to take urgent action in this regard.
Two components of BRGF are being implemented in Bihar. These components are:
(a) Special Plan for Bihar(being handled by the Planning Commission); and (b) Districts
Component covering 36 districts of Bihar(being handled by the Ministry of Panchayati
Raj).
An allocation of Rs.1000 crore per annum was being made for the Special Plan
during the Tenth Plan period. The same allocation is being made during the Eleventh
Plan period.
The details of the projects included in the Special Plan for Bihar showing the
estimated cost and the funds released till date are as follows:
(Rs. in crore)
Name of the Project Estimated Funds Funds Total Fund
Project released up released in released till
Cost to 2008-09 2009-10 date
1. Million Shallow Tubewell Programme 544.64* 544.64 0.00 544.64
(MSTP) (Subsidy Component)
2. Restoration of Eastern Gandak Canal 294.00 51.98 48.00 99.98
16
3. Development of Horticulture (Subsidy Dropped 18.18 0.00 18.18
Component)
4.1 The average persondays of employment under NREGA in 2008-09 was 26 only
compared to the National Average of 48 days. This could be improved by
generating awareness about the scheme so that demand for employment
increases.
17
4.2 The state receives about 26% of the total national allocation (Rs. 2,240 crore out of
Rs.8,495 crore in the current year) under the Indira Awaas Yojana. There is
demand for this programme, and the state has to mount all efforts to ensure its
proper implementation.
4.3 The Power Supply position is very erratic and small towns reportedly receive
power for less than 10-12 hours a day. Large scale upgradation of infrastructure
is being carried out under the Special Plan and RGGVY. The state needs to
ensure that BSEB takes over the assets and the lines are charged, otherwise
expensive equipment and lines may be stolen.
4.4 Planning Commission has recently approved the revised cost estimates of Rs.
1053 crore for the Barauni and Muzaffarpur Thermal Power Stations under the
Special Plan for Bihar under the Backward Regions Grant Fund.
4.5 The state can capitalize on its demographic dividend only by upgradation of skill
sets. It has not yet set up the State Skill Development Mission. The number of
ITIs is very small compared to the population size and there are 2000 persons in
the age group 15-30 years for every ITI seat. ITIs and other Institutes may be set
up in partnership with industrial houses/software companies. The state should
be geared up to take full advantage of the Centre’s initiative in this regard.
4.6 Under the National Drinking Water Mission, the state has a huge opening
balance of Rs. 414 crore. The expenditure in 2008-09 was only Rs. 165 crore
against the allocation of Rs. 425 crore. In the current year, against the allocation
of Rs. 372.21 crore, an amount of Rs. 186.11 core has been released so far.
4.7 The state has made considerable progress under Sarva Shiksha Abhiyan and
98% habitations have primary schools within a radius of one km. However, the
drop-out rate at the primary level is 51% compared to the national average of
25%. This programme should be accorded the highest priority of the state.
4.8 The progress of JNNURM has been very slow as the projects took a long time to
be prepared and approved. This programme requires greater attention.
4.9 Bihar’s Plan performance has improved in the past 4 years and the Plan
expenditure has increased from Rs. 4465 crore in 2005-06 to Rs. 12,511 crore in
2008-09.
5. OTHER ISSUES
5.1 Special Task Force on Bihar
A Special Task Force on issues relating to the state of the economy of Bihar, its
finances, governance and possible development strategies was constituted on 4 th January,
18
2006 under the Chairmanship of Dr. Satish C. Jha. The terms of reference included inter
alia analyzing issues related to the state of the economy of Bihar and sources of finances to
fund the development of the State; outlining measures for expeditious implementation of
on-going and news schemes; examination of issues pertaining to governance; identifying
constraints and suggesting improvements for effective implementation, recommending
possible development strategies and developing a mechanism for effective dialogue
between Government of India and Government of Bihar. The task force has done a
thorough job and produced the following reports:
This Task Force was wound up on 20 th July, 2009. The findings of the
Reports of the Task Force are being integrated into the normal work of the State
Plan division of the Planning Commission. The state and the concerned Central
Ministries should work together to examine the roadmap prepared for various
sectors for the timely approval and effective implementation of the
schemes/projects contained in the reports.
19
Bihar has made a claim for Special Category status.
The Power Sector is an area of concern. The State has two thermal power
plants namely, Muzaffarpur and Barauni. Muzaffarpur had been shut down in
2003, while Barauni was operating at about 10% PLF. The renovation and
modernization of these Power Stations is being carried out under the Special Plan
for Bihar and the revised cost estimate has recently been approved. The state
government has been requesting that the coal linkages for the 12 th Plan be decided
at an early date so that generation in the private sector could be possible. The
strengthening of the sub-transmission system is also being taken up under the
Special Plan. One critical issue here is the management capability of BSEB to take
over the created assets and manage them efficiently. The average cost of supply
was estimated to be about Rs.6.33 per unit in 2008-09 as compared to the average
tariff of Rs.3.06 per unit. The T&D losses are projected to be about 35% in 2009-10.
The reasons for high cost of supply are the high level of AT&C losses and the
higher cost on establishment. This has adversely affected the financial viability of
the sector. The commercial losses of BSEB are projected to be Rs.1818.36 crore in
2009-10.
Kosi Floods Reconstruction and Rehabilitation Package: Bihar’s claim for a Package
of Rs. 14,800 crore should be considered.
Handlooms: Not even a single Mega cluster has been given to Bihar even though
Bihar has a large number of minority handloom weavers in and around Bhagalpur.
20
Agriculture: Bihar has launched an Agriculture Road Map. The Credit Deposit ratio
is very poor and hence only 2% of the credit programme will reach Bihar. Hence the
credit needs need to be taken care of.
Food Security: Poor households in Bihar number 1.50 crore which is more than
double the GOI estimate of 65 lakh households. Unless the manner in which
poverty is measured is sorted out, the food security scheme will leave half of the
poor population uncovered.
FRBM Act: The states should be permitted flexibility of 1.5% over the prescribed
target of 4% for fiscal deficit.
Devolution of Central taxes: As a result of tax reliefs in the budget, Bihar faces a
possible reduction of Rs. 4616 crore as its share of Central taxes.
Coal blocks must be allocated for the Twelfth Plan as investors in the power sector
would not come forward without this vital linkage.
6. CONCLUSION:
Bihar deserves to be treated on a special footing, in view of its resource base, very
low level of human development, and the severe deprivation of majority of its
population. Against this context, most of the issues raised by the state government
require special consideration.
If Sarva Siksha Abhiyan(SSA) is one of the better implemented flagship
programmes in the state; implementation of JNNURM appears to be on the other
end of the spectrum. There is a need for a special Task Force for monitoring the
implementation of flagship and other important programmes.
21