Sohar Report2
Sohar Report2
This document has been prepared for the above titled project and it should not be relied upon or used
for any other project without the prior written authority of HMR Environmental Engineering
Consultants. HMR Environmental Engineering Consultants accepts no responsibility or liability for this
document to any party other than the client for whom it was commissioned.
Table of Contents
1 INTRODUCTION ........................................................................................................................... 1-1
1.1 Background ............................................................................................................................ 1-1
1.2 Objectives of the EIA Report ................................................................................................. 1-3
1.3 EIA Study Methodology ........................................................................................................ 1-3
1.3.1 Overview..................................................................................................................... 1-3
1.3.2 MECA’s Comments on Scoping.................................................................................. 1-4
1.3.3 Document Review ....................................................................................................... 1-4
1.3.4 Environmental Data Gathering.................................................................................. 1-5
1.3.5 Impact Assessment...................................................................................................... 1-5
1.3.6 Development of EMP.................................................................................................. 1-5
1.3.7 Structure of the EIA report ......................................................................................... 1-5
2 ENVIRONMENTAL REGULATORY FRAMEWORK................................................................ 2-1
2.1 Environmental Legislations in Oman..................................................................................... 2-1
2.2 Applicable Environmental Permits......................................................................................... 2-4
2.3 Regional and International Conventions and Protocols ......................................................... 2-4
2.4 International Guidelines and Best Practices ........................................................................... 2-5
2.5 Integrated Pollution Prevention and Control Directive .......................................................... 2-6
2.6 Seveso-II Directive................................................................................................................. 2-6
3 PROJECT DESCRIPTION.............................................................................................................. 3-1
3.1 Overview ................................................................................................................................ 3-1
3.2 Process Description ................................................................................................................ 3-1
3.3 Refinery Dry Gas Treatment Unit .......................................................................................... 3-3
3.4 NGL Treating and Fractionation Unit (NGLT)...................................................................... 3-3
3.5 Steam Cracker Unit ................................................................................................................ 3-4
3.6 Methyl Tertiary Butyl Ether (MTBE) Unit ............................................................................ 3-9
3.7 Butene-1 Recovery Unit ....................................................................................................... 3-10
3.8 Polyethylene Unit ................................................................................................................. 3-13
3.9 Polypropylene Unit............................................................................................................... 3-17
3.9.1 Pre-contacting and Pre-polymerization ................................................................... 3-17
3.9.2 Liquid Monomer Polymerization.............................................................................. 3-18
3.9.3 Gas Phase Copolymerization ................................................................................... 3-18
3.9.4 Polymer Drying ........................................................................................................ 3-19
3.9.5 Extrusion .................................................................................................................. 3-19
3.9.6 Pellets homogenization............................................................................................. 3-19
3.10 Pygas Hydrotreater Unit (PGHYD).................................................................................. 3-21
3.10.1 First Stage Reaction Section .................................................................................... 3-21
3.10.2 First Stage Distillation Section ................................................................................ 3-22
3.10.3 Second Stage Reaction Section................................................................................. 3-22
3.10.4 Second Stage Distillation Section............................................................................. 3-23
3.11 Utilities ............................................................................................................................. 3-25
List of Tables
Table 1-1: Project Focal Point................................................................................................................ 1-2
Table 1-2: MECA/SEU’s Feedback on Scoping Report ........................................................................ 1-4
Table 2-1: Applicable Environmental Laws and Regulations................................................................ 2-2
Table 2-2: Permit Responsibility Matrix................................................................................................ 2-4
Table 2-3: International Conventions and Protocols .............................................................................. 2-5
Table 3-1: Main Wet Flare Connections .............................................................................................. 3-27
Table 3-2: Equipment’s connected to Flaring System ......................................................................... 3-28
Table 3-3: Type of Pressurized Sewer System and Stream Disposal/Treatment ................................. 3-32
Table 3-4: Utilities Consumption – Normal and Maximum Flow Rate ............................................... 3-39
Table 3-5: Sourcing of Construction Material...................................................................................... 3-48
Table 3-6: Tentative Project Schedule ................................................................................................. 3-50
Table 4-1: Coordinates of the Project Site ............................................................................................. 4-1
Table 4-2: Meteorological Conditions at Sohar 2011-2013 ................................................................... 4-4
Table 4-3: CAAQMS Monitoring Methods for Parameters................................................................... 4-6
Table 4-4: CAAQMS Monitoring Location Co-ordinates ..................................................................... 4-6
Table 4-5: AAQMS Results (Units in g/m3 unless otherwise specified) ............................................ 4-7
Table 4-6: Ambient Dust Levels – Location Coordinates and Measured Values .................................. 4-9
Table 4-7: Maximum 24-hr avg. Dust Levels at the Site ....................................................................... 4-9
Table 4-8: Ambient Noise Level .......................................................................................................... 4-10
Table 4-9: Soil Sampling Location ...................................................................................................... 4-12
Table 4-10: Results of Laboratory Analysis of Soil Samples .............................................................. 4-12
Table 4-11: Groundwater Analysis Result ........................................................................................... 4-15
Table 5-1: Air Emissions during Construction Phase ............................................................................ 5-2
Table 5-2: DG Emissions from Construction Phase............................................................................... 5-3
Table 5-3: Dust Emissions from Vehicle on Unpaved area within Site after water spraying ................ 5-4
Table 5-4: Gaseous Emission from Vehicle Travelling at Site .............................................................. 5-4
Table 5-5: Wastewater Stream during Construction Phase .................................................................... 5-5
Table 5-6: Waste Generation during Construction Phase ...................................................................... 5-7
Table 5-7: Typical Noise Level.............................................................................................................. 5-8
Table 5-8: Emission Rate of Pollutants from Stacks............................................................................ 5-10
Table 5-9: Storage Tank Details and Expected Emissions................................................................... 5-13
Table 5-10: Wastewater Generated during Operation Phase................................................................ 5-15
Table 5-11: Solid Waste Generation during Operation Phase.............................................................. 5-17
Table 5-12: Noise Generation During Operational Phase .................................................................... 5-18
Table 7-1: GHG Emission from DG Set ................................................................................................ 7-3
Table 7-2: Detailed GHG Emission Calculation from Stationary Combustion Sources........................ 7-3
Table 7-3: GHG Emissions from Mobile Combustion........................................................................... 7-4
Table 7-4: Detailed GHG Emission Calculation for Mobile Combustion Sources................................ 7-4
Table 7-5: GHG Emission from Industrial Process................................................................................ 7-5
Table 7-6: Detailed GHG Emission Calculation from Industrial Process Combustion ......................... 7-6
Table 7-7: Total GHG Emissions (TPA)................................................................................................ 7-8
Table 7-8: Climate Change Matrix......................................................................................................... 7-9
Table 8-1: Potential Impacts from Construction Phase ........................................................................ 8-17
Table 8-2: Potential Impacts from Operation Phase............................................................................. 8-18
Table 8-3: Summary of Impacts during the Construction Phase.......................................................... 8-25
Table 8-4: Model Set Up ...................................................................................................................... 8-26
Table 8-5: Air Emissions from Operation Phase.................................................................................. 8-27
Table 8-6: Predicted GLC Values ........................................................................................................ 8-28
Table 8-7: Summary of Impacts during the Operation Phase .............................................................. 8-31
List of Figures
Figure 3-1: Overall Plot Plan of the Petrochemical Plant ...................................................................... 3-2
Figure 3-2: RDG Unit – Flow Diagram ................................................................................................. 3-3
Figure 3-3: NGL Treating and Fractionation Unit ................................................................................. 3-4
Figure 3-4: SCU Flow Diagram ............................................................................................................. 3-5
Figure 3-5: Flow Diagram –NGL Treatment and SCU.......................................................................... 3-7
Figure 3-6: Plot Plan of Steam Cracker Unit.......................................................................................... 3-8
Figure 3-7: MTBE and BUT-1 Unit Plot Plan ..................................................................................... 3-12
List of Attachment
Attachment 1: Process Description – NGLT, RDG, SCU.........................................................................H
Attachment 2: Chemical Reaction Kinetics for Steam Cracker Unit ........................................................ I
Attachment 3: Steam Cracker Heat and Material Balance ......................................................................... J
Attachment 4: Process Description of Butene-1 .......................................................................................K
Attachment 5: Process Description Pygas Hydrotreater Unit ................................................................... L
Attachment 6: Process description for Flares........................................................................................... M
Attachment 7: Process Description for Incinerators..................................................................................N
Attachment 8: Process Description – Potable & Service Water Unit........................................................O
Attachment 9: Process description for Seawater Desalination System ......................................................P
Attachment 10: Process description for Fuel Gas and Natural Gas System..............................................Q
Attachment 11: Process description for Cooling Water System ............................................................... R
Attachment 12: Process Description for Nitrogen System.........................................................................S
Attachment 13: Process Description Steam System.................................................................................. T
Attachment 14: Process description for Instrument and Plant Air system ................................................U
Attachment 15: Process Description WWTP ............................................................................................ V
Attachment 16: Process description and BAT for Spent Caustic Selection Process ................................ W
Attachment 17: Tie-ins and Interconnecting lines.....................................................................................X
HFC Hydrofluorocarbons
HMR HMR Environmental Engineering Consultants
HP NG High pressure natural gas
HRSG Heat Recovery Steam Generator
HSEMS Health Safety and Environmental Management System
IAM Impact Assessment Matrix
IG Inert Gas
IPCC Intergovernmental Panel on Climate Change
IPPC Integrated Pollution Prevention and Control
ISBL Inside Battery Limit
ISLM Integrating and Logging Sound Level Meter
IUCN International Union for the Conservation of Nature and Natural Resources
Km kilometer
kTA Kilo tones per annum
LDC Less developed countries
LLOD Last Line of Defense
LLDPE Linear low density polyethylene
LP Low Pressure
LPIC Liwa Plastic Industries Complex
m3 Cubic meter
m3/h Cubic meter per hour
MAF Mina Al Fahal
MECA Ministry of Environment and Climate Affairs
MED Muti effect distillation
MISC Majis Industrial Services Company
MRMWR Ministry of Regional Municipalities and Water Resources
Mg milligram
MSBE Methyl Secondary Butyl Ether
MTBE Methyl tertiary butyl ether
NG Natural gas
NGL Natural gas liquids
NGLE Natural gas liquid extraction
NGLT NGL Treating & Fractionation Unit
NOL No Objection Letter
O3 Ozone
OCB Oil Contaminated Basin
ODS Ozone Depleting Substances
OETC Oman Electricity Transmission Company
OPP Oman Polypropylene
Opex Operational Expenditure
ORPC Oman Refineries and Petrochemicals Company
Orpic Oman Oil Refineries and Petroleum Industries Company
OSBL Outside Battery Limit
OWS Oily Water Sewer
PEP Preliminary Environmental Permit
PGHYD Pygas hydrotreater unit
PM Particulate Matter
PM10 Particular Matter less than 10 micron
PMC Project Management Consultancy
G-S000-5240-003 HMR Consultants
June 2015 xii
Orpic, Sultanate of Oman Environmental Impact Assessment Report
CB&I, Netherlands Petrochemical Plant, Sohar
Executive Summary
Background
Oman Oil Refineries and Petroleum Industries Company (Orpic) is planning to set up a project Liwa
Plastic Industries Complex (LPIC) which will include a nominal 863,000 t/y ethylene cracking plant,
high density polyethylene (HDPE) plant, linear low density polyethylene (LLDPE) plant, new
polypropylene plant, methyl tertiary butyl ether (MTBE) plant, Butene-1 plant and associated utilities
and offsite facilities.
The LPIC Petrochemical Complex will be integrated with the Sohar Refinery, Aromatics Plant and
Polypropylene Plant. One of the feed-stocks is Natural Gas Liquids (NGL) i.e. C2+, which is
extracted from natural gas at Fahud, about 250 km southwest of Muscat, and transported to the Sohar
via pipeline. The NGL extraction plant and the pipeline will also be part of LPIC.
The proposed Petrochemical Complex is categorized under Group 1, ‘Industrial Projects’ sub
categorized as ‘Chemical and Petrochemical Project’, requiring to conduct an Environmental Impact
Assessment (EIA), accordingly CB&I has commissioned HMR to undertake an EIA study for the
Petrochemical Complex in Sohar.
The EIA scoping report for the project was submitted to MECA on 18th December 2014.
Subsequently, SEU/MECA provided their comments on the scoping report on 11th January 2015
(Appendix A) which are addressed in this EIA. Suggestions and comments provided by MECA on
EIA scoping report has been addressed in this EIA report.
Project Overview
The process units included in the Petrochemical Complex are:
MTBE Unit;
HDPE Unit;
PP Unit.
150 MW
Flaring System
Incinerators (2 incinerators)
Drainage systems
Steam systems
In addition to the above, the buildings such as the Main Control Room, Satellite Instrument Houses,
Substations, Main Substation and Analyser Houses will also be constructed in the petrochemical
complex.
Petrochemical Location
The project site for the Petrochemical Complex will be spread on two plots and located adjacent to
SRIP in Sohar Industrial Port Area (SIPA) which is a dedicated industrial area. The Petrochemical
Complex will be integrated with the Sohar Refinery, Aromatics Complex and Polypropylene Plant.
SIPA is spread over an area of 132km2 and located on Al Batinah coast about 20km north of Sohar
and 220km from Muscat.
During the operation phase of the Petrochemical Complex, 500 personnel will be working in the
Petrochemical Complex. The Petrochemical Complex will be operated in three shifts. The employees
will be accommodated in rented apartments/accommodations available in Sohar.
Environmental Baseline
The project site is located within the SIPA, which has been developed as a dedicated industrial area.
The project site has not been occupied since the establishment of the SIPA. The site was an
agricultural land, and was also used for livestock rearing and bee-farming. Earlier presence and
activities of humans are evident from the various crumbles shelters, grave and wells within the project
site.
In order to develop environmental baseline status primary information collected through various site
visits and surveys, secondary information collated from various published documents were used.
Information on topography and landscape, climate and meteorology, geology, hydrology,
hydrogeology, and social environment are collected from published data and from concerned
authorities.
Ambient air quality at 3 locations for 45 days was measured using the Continuous Ambient Air
Quality Monitoring Station (CAAQMS). Some meteorological parameters were also measure by the
CAAQMS. The ambient air quality was found to be compliant with the Omani (Provisional) Ambient
Air Quality Standards and USEPA National Ambient Air Quality Standards, except PM10. This high
concentration of PM10 is contributed to heavy construction going in the area and is also contributed by
natural winds.
Dust and noise were also measured at different locations using hand held measuring devices. Dust
levels along the eastern, central and southern boundaries of the project site were higher than the
corresponding standards; and this may due to the construction works on plots located towards the
northwest of the project site. Ambient noise levels within the project site were well within the limit of
70 dB(A) for industrial area prescribed in MD 79/94.
No marine survey was conducted as the project does not discharge any waste directly into the marine
environment.
Soil and groundwater samples were also collected from the site and analysed. The soil quality was
found to be compliant with the limits given in USEPA’s Site Notification Standards for Industrial
Soils. The groundwater quality was found compliant with the Omani Drinking Water Standards,
except for sodium, nickel, chromium, Iron and magnesium. It can be noted from the above results that
the levels of sodium and magnesium in the groundwater sample is significantly above the limits
applicable for drinking water. Iron, chromium and nickel levels are also marginally above the
standard limits. However, the hydrocarbon and VOC levels are below the detection limits.
Overall the environmental condition of the project site is good. Further the terrestrial ecological
survey of the project site revealed that the birds observed in the site are mainly composed of highly
resilient species that can easily adapt to human induced habitat modifications. No reptiles or mammals
were recorded, which could be due to the fact that the site has already been subjected to habitat
alteration in the past. The tree species at the site serve as foraging, roosting and nesting sites for the
birds recorded in the area. None of the plant species recorded in the site are listed in the 2011 Red List
of the International Union for Conservation of Nature and Natural Resources.
Environmental Releases
The primary air emissions during the construction phase of the Project will be from the construction
machinery, diesel generators, construction vehicles, earthworks and fuel storage. The emissions will
include pollutants like NOX, SO2, CO, unburnt hydrocarbons, and PM10. Air emissions during the
operation phase will be mainly from the 14 stationary point sources of the Petrochemical Complex.
These sources will emit pollutants like NOX, SO2, CO, unburnt hydrocarbons, and PM10. The other
G-S000-5240-003 HMR Consultants
June 2015 xvi
Orpic, Sultanate of Oman Environmental Impact Assessment Report
CB&I, Netherlands Petrochemical Plant, Sohar
emission sources will be the storage tanks which will release fugitive emissions of hydrocarbons, and
the mobile sources like vehicles, trucks, etc.
The major wastewater streams that can be expected during the construction phase will be machinery,
vehicle and floor washings, hydrotest water, chemical cleaning solutions, sewage wastewater from
site and accommodation camps, and surface run-off. During the operation phase, the Petrochemical
Complex is expected to release process wastewater (sampling point effluents, sour water, boiler
blowdowns and condensates, spent caustic, laboratory effluent , Benzene/MTBE containing
wastewater, decoking quench water, spent caustic, various process drainages and floor washings) and
seawater effluents (brine rejects and cooling water), bottom sediments and water from storage tanks,
sewage wastewater, firefighting water and water and firefighting foam mixture/water-foam emulsion
and surface run-off.
Solid wastes during the construction phase will be typical wastes like excavated soil, office wastes,
construction waste, food wastes, metal and plastic scraps, waste paints and chemicals, radioactive
wastes, waste batteries, empty drums, sludge, etc. During the operation phase of the Petrochemical
Complex more hazardous wastes are expected than the non-hazardous wastes. These wastes will
include spent oily sludge from the storage tank, DGF skimming, Benzene/MTBE WWCT, Coke from
cracking ethylene unit, polyethylene and polypropylene powder catalysts, spent filter media
(flammable) and oil absorbents and solvents, disposable filters, etc.
Noise during both phases will be from moving and rotating equipment. The main noise sources during
construction phase will be the diesel generators, and construction machineries and vehicles. During
the operation phase the noise sources will be gas turbines, boilers, pumps, blowers and compressors,
and flares.
Accidental releases of hazardous gases and liquids are possible from the storage tanks, especially
pressurized storage tanks. The potential for accidental releases is higher during the operation phase
than the construction phase, as there will be a higher number of tanks. During the construction phase
the storage facilities to be used will be diesel storage tanks and gas cylinders.
Environmental Impacts
The assessment of potential impacts has been carried out utilizing qualitative (Impact Assessment
Matrix) as well as quantitative (mathematical modeling) methods. In the qualitative method, impacts
are rated as ‘low’, ‘medium’ or ‘high’ depending on the severity of the impact and the duration /
likelihood of the impact. The impacts ratings for the project construction and operation phases are
presented in Table ES-1 and Table ES-2, respectively.
Table ES-1: Summary of the Construction Phase Environmental Impact Ratings
audit and monitoring program has been recommended, as a part of EMP, for the construction as well
as operation phases of the project in order to mitigate anticipated impacts and to ensure compliance
with Omani regulations.
Conclusions
Through the effective implementation of the proposed EMP, and careful design, engineering,
planning, construction and operation considerations, the associated impacts will be minimized.
Consequently, these impacts are not expected to cause any significant, long term and irreversible
change on the environment and the local community. It is concluded that the impacts from the
Petrochemical Complex acceptable from an environmental and social standpoint within the context of
the local and internationally comparable environmental standards including EHS guidelines.
1 INTRODUCTION
1.1 Background
Oman Oil Refineries and Petroleum Industries Company (Orpic) is created the integration of three
companies - Oman Refineries and Petrochemicals Company LLC (ORPC), Aromatics Oman LLC
(AOL) and Oman Polypropylene (OPP). Orpic currently operates two oil refineries (Muscat and
Sohar) an Aromatics Plant and a Polypropylene Plant. The Sohar Refinery, Aromatics Plant and the
Polypropylene Plant are located at the Sohar Industrial Port Area (SIPA). Sohar Refinery includes a
115,000 barrels per stream day (BPSD) crude distillation unit, an 80,000 BPSD residue fluid catalytic
crac king unit (RFCC) that operates in a maximum olefins mode, an indirect alkylation unit, a TAME
process unit and various hydro processing and treating units. The Aromatics Plant processes naphtha
and produces 820,000 tons per year (t/y) of Paraxylene and 200,000 t/y of Benzene. The
Polypropylene Plant processes the propylene produced in the RFCC unit and can produce 350,000 t/y
of polypropylene.
Orpic is currently executing a major project for improvement of the existing refinery, which is
referred to as the Sohar Refinery Improvement Project (SRIP). The project involves the installation of
a new crude distillation unit, vacuum distillation unit, hydrocracking unit, delayed coking unit,
isomerization unit, hydrogen plant and Sulphur recovery facilities. SRIP project is currently in the
detailed engineering phase and is expected to be fully operational by the end of 2016.
The Liwa Plastic Industries Complex (LPIC) will be Orpic’s latest expansion, and will include a
nominal 863,000 t/y ethylene cracking plant, high density polyethylene (HDPE) plant, linear low
density polyethylene (LLDPE) plant, new polypropylene plant, methyl tertiary butyl ether (MTBE)
plant, Butene-1 plant and associated utilities and offsite facilities. The LPIC petrochemical plant will
be integrated with the Sohar Refinery, Aromatics Plant and Polypropylene Plant. One of the feed-
stocks is Natural Gas Liquids (NGL) i.e. C2+, which is extracted from natural gas at Fahud, about 250
km southwest of Muscat, and transported to the Sohar refinery by pipeline. The NGL extraction plant
and the pipeline will also be part of LPIC. Other feed-stocks are mixed Liquefied Petroleum Gas
(LPG) produced in the refinery and aromatics complex, dry gas produced in the RFCC unit and new
delayed coking unit that is included in the SRIP, and condensate (light naphtha) imported from Oman
LNG by marine tanker. Some of the materials produced in the petrochemical complex, including
hydrogen, MTBE, pyrolysis fuel oil and hydro-treated pyrolysis gasoline will be returned to the Sohar
Refinery, Aromatics Plant and existing Polypropylene Plant.
This report focuses on one of the three components of LPIC project i.e. Petrochemical Plant located
in SIPA. The LPIC has the following components:
MTBE Plant;
Polypropylene Plant; and
Pygas Hydrotreater Unit (PGHYD)
Orpic, through a competitive bidding process, awarded the Project Management Consultancy (PMC)
contract to Engineers India Limited, New Delhi (EIL) and the Front End Engineering Design (FEED)
contract to Chicago Bridge and Iron Co (CB&I), The Hague, Netherlands. Benefiting from parallel
supply of gas from Fahud and naphtha from the Sohar Refinery, Orpic and CB&I have selected a
mixed steam cracker to produce ethylene, propylene, by-products and derivatives. With a capacity of
863,000 t/y ethylene, this mixed cracker will produce:
As per the categorization of projects by Ministry of Environment and Climate Affairs (MECA), the
proposed Petrochemical Plant is categorized under Group 1, ‘Industrial Projects’ sub categorized as
‘Chemical and Petrochemical Project’, requiring to conduct an Environmental Impact Assessment
(EIA) study entailing detailed evaluation of the potential environmental impacts, identification of
appropriate control measures to mitigate significant impacts and a detailed management plan to obtain
the Preliminary Environmental Permit (PEP) to commence the project construction.
Accordingly, CB&I has commissioned HMR Environmental Engineering Consultants (HMR) for
undertaking the EIA study for the proposed Petrochemical Plant in Sohar. This EIA study is carried
out during the FEED phase of the proposed Petrochemical Plant. As mentioned earlier, the NGL
extraction plant in Fahud and the pipeline between the NGL plant and the Petrochemical Plant in
SIPA are not within the scope of the present EIA.
The focal points of the project proponent and the consultants (FEED and EIA) and their contact
details are provided in Table 1-1.
Table 1-1: Project Focal Point
The scope of work for this EIA was developed in line with the requirements of the Guidelines on
Environmental Impact Assessment issued by MECA and the Guidance Note on Requirements for EIA
issued by SEU1. Accordingly, the present EIA report has the following objectives:
Desktop reviews and field studies for describing the current status of the environment at
project site;
Identification and assessment of potential environmental and social impacts from the project
primarily during construction and operation and determination of significant impacts;
Preparation of the EIA and EMP report for review by Director General of Environmental
Affairs (DGEA)/Director General of Climate Affairs (DGCA) - MECA and SEU.
1.3.1 Overview
The EIA study for the Project commenced in September 2014 and continued till February 2014. As
mentioned in Section 1.2, the overall EIA methodology was based on MECA’s and SEU’s guidance
notes.
1
REP-386-13–DJ Version July 2013
G-S000-5240-003 HMR Consultants
June 2015 1-3
Orpic, Sultanate of Oman Environmental Impact Assessment Report
CB&I, Netherlands Petrochemical Plant, Sohar
The main issues raised by MECA on the scoping report are summarized in Table 1-2 along with the
indication of the sections of the EIA where, each of the issues or concerns has been addressed.
Table 1-2: MECA/SEU’s Feedback on Scoping Report
The scoping has not detailed the MTBE and Butene units that mentioned
Chapter 3 of this EIA
1 in the document. It is required to elaborate further in the description of the
report
process and the products line of each unit and their impacts.
It is required to include a clear waste management plan for all wastes Addressed in
2 streams and the overall project risk assessment and the project Environmental
environmental management system. Management plan
The company has to consider the nearby community that is not yet
Addressed in Chapter 6
3 transferred and what are the steps that will be taking to reduce the adverse
and 7 of EIA report
impact of the project.
4 NGLE and Pipeline parts shall be included in the EIA Study Noted
The company shall not import huge quantities of chemicals until ensure
5 Noted
their suitability in the process
The company shall consider in the EIA a separate section about the Noted, Chapter 7 of this
6
climate affairs report is Climate Affairs
In case the company will use piping networks for receiving or discharging
Detailed in Chapter 3 of
7 directly to the sea the cooling water or the desalination unit the piping
this EIA report
size, discharge temperature and the dilution process shall be mentioned
Environmental baseline information from previous studies in the area was reviewed to plan
acquisition of primary data through field studies, considering the interaction of the project
components with various environmental elements. Field studies mainly focused on potential areas of
significance with regard to the environmental and social impacts of the project development.
Chapter 1 : Introduction
Presents the background and objective of the EIA report with the methodology.
Also provides a summary of SEU/MECA’s comments on the EIA scoping report.
Chapter 2 : Regulatory Framework
Presents the applicable environmental legislative and institutional requirements;
Chapter 3 : Project Description
Describes the various process units, utilities, project facilities and activities of the
PC Plant. Further, the construction methodology and resources required during
construction phase are described in this chapter.
Chapter 4 : Environmental Baseline
Provides description of the existing environmental settings at the project site.
Chapter 5 : Environmental Releases
Discusses the environmental releases from the PC Plant during construction and
operation phases. The handling, treatment and disposal philosophies proposed for
the releases are also presented in this chapter.
Chapter 6 : Climate Affairs
Identifies the type of ODS used in the project and presents an estimate of the
GHG emissions from the project construction and operation. Further, the chapter
assesses the influence of the project on climate change, and conversely, the
vulnerability of the plant to climate change;
Chapter 7 : Analysis of Alternatives
Analyzes the alternatives for the critical technology and processes, utilities,
project site etc. from environmental standpoint. Also, the BAT as per Integrated
Pollution Prevention and Control (IPPC) directives will also be considered.
Chapter 8 : Environmental Impact Assessment
Identifies and discusses potential impacts on the environment due to the PC Plant
primarily during construction and operation.
Chapter 9 : Conclusion
Presents the conclusions of the EIA study for the PC Plant
An EMP, including the recommendations for environmental mitigation and monitoring, based on the
impact identification and assessment are detailed in a separate document as per SEU’s requirement.
Moreover Rapid Risk Assessment (RRA) for the PC has been prepared and will be submitted as
separate document to SEU.
For areas where Omani regulations are not available, applicable international regulations such as
those contained in the environmental standards provided by the European Union (EU) and the United
States Environmental Protection Agency (USEPA) will be used to ensure that the technology,
equipment and operations selected for the project are capable of meeting national and international
environmental requirements. In addition, the Project will follow the requirements of international
engineering standards and codes as per contractual agreement with the technology providers and the
EPC contractor. The following sections detail the various national and international environmental
regulations and standards that are applicable to the present project.
In addition to various RDs and MDs, SEU has issued guidelines for management of materials and
wastes, industrial safety and EIA study for the industries within SIPA, which are also referred to.
Furthermore, this EIA study has considered the requirements of the IPPC Directive as well as the
Seveso-II Directive to assess the BAT for the various units of the proposed plant in order to reduce
and control environmental pollution, and to highlight measures for safety of the Petrochemical Plant
from major accidents / incidents during the operation phase.
The responsibility for the implementation of these laws rests with MECA, which issues regulations,
standards and guidelines through MDs. Within MECA, the authority responsible for environmental
permitting, inspection and control in the Sultanate of Oman is DGEA) whereas, DGCA is the
authority to assess the potential aspects of the Project with regards to climate change. Further, since
the Project is located within SIPA, it needs to adhere to the guidance notes issued by SEU (an integral
part of MECA) which ensures that the organizations works in compliance with the Omani regulations
and in addition, encourages to adopt the Beyond Regulatory Control (BRC) mechanism through
implementation of BAT.
The Omani environmental laws and regulations and SEU’s guidance notes applicable to the proposed
project, are listed in Table 2-1.
Table 2-1: Applicable Environmental Laws and Regulations
SEU has compiled the Omani environmental laws and regulations into a single document and issued it
under the title “Advanced Regulatory Wiki Application: Omani Environmental Regulations
International References Documents” (ARWA). Brief descriptions of some of the environmental laws
and regulations applicable to the proposed plant are presented in Appendix B. The clauses and
standards presented are based on information provided in ARWA, second edition, issued in July 2013.
Permits Responsibility
Preliminary Environmental Permit from MECA/SEU Orpic
Final environmental permit from MECA/SEU EPC Contractor/ Orpic
Permit for storage, handling, transportation and disposal of hazardous
EPC Contractor/ Orpic
wastes during construction and operation from MECA and ROP
Permit for storage, handling and transportation of chemicals and fuel used at
EPC Contractor/ Orpic
site during construction and operation from MECA and ROP
Permit for operating stationary combustion sources from Air Pollution
EPC Contractor/ Orpic
Department, MECA
Permit for disposal of hydro-test water from MECA EPC Contractor
Permit for installing onsite sewage treatment plant (STP) and
reuse/discharge of treated wastewater or Approval for discharging sewage to EPC Contractor/ Orpic
municipal STP, as applicable, from MECA and concerned authorities
Permit for import, transportation, usage and storage of radioactive material
and explosives, if required (mainly during construction phase) from MECA EPC contractor
and ROP
Permit for use of industrial / laboratory gas cylinders from MECA EPC Contractor
Temporary approval for setting up of labor camp & offices, if required, from
EPC Contractor
Liwa Municipality and/or SIPC
NOL from SEU for storage of hazardous wastes at Liwa site EPC Contractor/ Orpic
NOL from SEU for storage of non-hazardous wastes at Sohar waste
EPC Contractor/ Orpic
collection site or for any other solution proposed by Orpic
RD 90/91 – Sanctioning the Accession of the Sultanate of Oman to the Marine Environment Protection
Protocol;
RD 57/94 – Sanctioning the Accession of the Sultanate of Oman to two Protocols on Environment
Protection;
RD 119/94 – Sanctioning the Accession of the Sultanate of Oman to Basel Convention on the Control of
the Trans-boundary Movement of Hazardous Wastes and their disposal, the United Nations Framework
Convention on Climate Change and Convention on Biological Diversity;
RD 73/98 – Sanctioning the Accession of the Sultanate of Oman to the Vienna Convention for the
Protection of the Ozone Layer and the Montreal Protocol on Substances that Deplete the Ozone Layer;
RD 24/2002 – Sanctioning the Protocol on the Trans-boundary Movement of Hazardous Wastes and
Other Wastes and their Disposal;
RD 106/2004 – Sanctioning Montreal and Beijing Amendments to Montreal Protocol on Substances that
deplete the Ozone Layer; and
RD 107/2004 – Sanctioning Kyoto Protocol to the United Nations Framework Convention on Climate
Change.
# Convention Description
Vienna convention on the protection of the Acts as a framework for the international efforts to protect
4
ozone layer, 1985 the ozone layer
# Convention Description
As discussed earlier, this expansion project falls under IPPC Annex 1 industries and therefore is
needed to comply with the requirements of the directives. A summary of the applicable requirements
for the proposed project is listed below:
Use appropriate pollution-prevention measures, namely the BAT (which produce the least
waste, use less hazardous substances, energy recovery, enable the recovery and recycling of
substances generated, etc.);
Avert all large-scale pollution (reduction of NOx, SO2 and VOC emissions, control of liquid
effluent discharge quantities);
consequences of such accidents not only for people (safety and health aspects) but also for the
environment (environmental aspect). Both aims should be followed with a view to ensuring high
levels of protection throughout the community in a consistent and effective manner and shall form the
basis for Orpic to develop a comprehensive Health Safety and Environmental Management System
(HSEMS) for proposed petrochemical Plant at Sohar.
The Seveso-II Directive deals solely with the presence of dangerous substances in establishments. It
covers both, industrial activities as well as the storage of dangerous chemicals. The directive follows a
two tier approach viz. lower threshold quantities and higher threshold quantities and can be viewed as
inherently providing proportionate controls in practice, where larger quantities mean more controls.
Establishments that hold larger quantities of dangerous substance (above the higher threshold
quantities) contained in the directive will be covered by all the requirements contained within the
directive. Based on review of the presently available information, the petrochemical Plant will be
classified as a ‘Seveso-II’ project due to processing and storage of flammable substances such as
NGLs, LPG, Propylene, Naphtha, fuel oil, gasoline and others in excess of quantities given in Annex
1 of Seveso-II Directive (the assessment of the storage capacities against the thresholds given in
Seveso-II Directive will be included in the EIA).
3 PROJECT DESCRIPTION
3.1 Overview
This chapter describes the process units and associated facilities to be provided as part of the
proposed PC Plant. The proposed PC Plant will be located adjacent (site coordinates are provided in
Chapter 4) to SRIP that will include a 863 kTPA ethylene cracking plant, HDPE Plant, LLDPE Plant,
PP Plant, MTBE Plant, butene-1 Plant and associated utilities and offsite facilities. The main feed-
stock for the petrochemical Plant is NGL (Natural Gas Liquids, C2+) which will be extracted from
natural gas. Extraction will be done in the proposed natural gas liquid extraction (NGLE) Plant near
the existing Fahud Compressor Station (FCS), located near Fahud about 300km south of the new
complex at Sohar. NGL product will be transported to the Petrochemical Plant via a new pipeline.
The NGLE Plant and the NGL pipeline are part of the LPIC. NGL will be transported to the
Petrochemical Plant in the pipeline in a liquid phase.
The Petrochemical Plant is scheduled for completion in 2018, which will enable Orpic to produce
polypropylene (in addition to the existing polypropylene plant) and, for the first time, polyethylene,
the plastic most in demand globally, which will boost Oman’s export earnings. At the same time and
with the production of one million tonnes of plastics, the country’s downstream plastics industry will
have the opportunity to grow, with the promise of more downstream industries, increased
employment, and overall additional in-country value. The overall plot plan is shown in Figure 3-1.
For detailed information and for layout clarity please refer to Map 1, Map 2 and Map 3 also
printed in A1 size.
MTBE Unit;
HDPE Unit;
PP Unit
PE/PP Steam
Plot_Plot 10
Cracker
Plot_Plot 10
Separated ethane and ethane recycled from the RDG unit and NGL will be sent to the cracking furnaces
to produce ethylene by pyrolysis. Ethane feed along with unconverted reactants will be first preheated in
the furnace convection section and humidified with dilution steam to reduce coke formation and enhance
the conversion of ethane to ethylene. A small amount of dimethyl disulphide will also be added to the
feed stream to reduce carbon monoxide and coke formation during cracking in the radiant section of the
furnace.
Cracked gas will not only contain ethylene but also ethane, acetylene, methane, hydrogen, heavier
hydrocarbons and pyrolysis gasoline (called “pygas”). Hydrogen and methane fractions are separated
and used as a fuel gas in the furnaces. Any additional fuel gas required will be supplied from the natural
gas header.
The gas mixture coming out of cracking furnaces will first be cooled in transfer line exchangers and then
further cooled in a quench tower. Cracked gas from quench tower overheads is compressed in three
stages. The discharge vapour from each stage is cooled with water. The compressed cracked gas is
forwarded to the Caustic Wash System for removal of CO2 and H2S.
The cold section starts with the de-ethanizer, followed by the de-methanizer and C2 splitter. While de-
ethanizer system separates ethane and lighter components from the propylene and heavier components,
de-methanizer removes methane and hydrogen from the C2 mixture. The C2 splitter separates the feed
into ethylene as an overhead product and ethane in the bottoms. The unconverted ethane will be recycled
to the cracking furnaces as feed. Ethylene vapour will be compressed and condensed using propylene
refrigerant. Ethylene produced from the ethylene cracker will be polymerized in polyethylene plants to
manufacture both LLDPE and HDPE pellets.
Since polymerization of ethylene is highly exothermic, a large amount of heat will be generated. As
temperature of polymerization will be higher than the melting point of polyethylene, growing
polyethylene molecules will stay in solution as one phase. The product stream containing polyethylene
will be fed from the reactor system to the devolatilization section of the process. The devolatilization
section will separate the polyethylene/solvent solution. The polyethylene stream will enter the next
vessel at a high vacuum to flash most of the remaining solvent from polyethylene. The solvent that will
be recovered in the devolatilization section will be condensed, purified, and recycled back to the reactor.
The pellets will be air conveyed to the packaging section of the plant where finished product will be
packaged into either bags or bulk containers.
All by-products formed in the MTBE reaction and remaining with the MTBE product are gasoline
compatible components and include tertiary butyl alcohol (TBA), methyl secondary butyl ether
(MSBE) and di-isobutylene (DIB). Dimethyl ether (DME) is formed in the MTBE synthesis and
removed with the C4 raffinate in MTBE/C4 fractionation.
The following represents the chemistry of the main reaction and side reactions:
Main Reaction
Side Reaction
Mixed C4 feed-stock from the upstream Selective C4 Hydrogenation unit is first water-washed where
water soluble impurities such as nitriles are removed. The washed C4 stream is collected in the mixed
C4 Feed Surge Drum with a coalescer to remove any residual free water. From here, it is transported
to the MTBE reaction system. The combined mixed C4 feed from the mixed C4 feed surge drum is
mixed with a fresh and recycled methanol stream and preheated if feed temperature is lower than
40°C. Low Low Pressure (LLP) steam supplies the necessary heat to the feed preheater. The
preheated mixed C4 feed is then sent to the primary reactor. Flow diagram is given in Figure 3-7.
The etherification reaction is exothermic and dilution of the inlet stream limits the temperature rise
across the reactor, and prevents vaporization at the reactor outlet. The temperature of the primary
reactor is thus controlled thus extending the catalyst life and avoiding fouling. The cooled recycle
effluent provides the necessary dilution requirement at the inlet.
The rest of the effluent is cooled via the Secondary Reactor Feed Cooler and then fed to the secondary
reactor. The primary and secondary reactors operate in series. The secondary reactor effluent is
preheated via the CD Reaction Column Bottoms/Feed exchanger and then fed to the CD Reaction
Column where the MTBE conversion is further increased and the product MTBE is separated from
the unreacted C4. The CD Reaction Column with Catalytic Distillation is operated in exactly the same
way as a conventional distillation column, with an external reboiler (using LP steam) and an overhead
condenser.
Above the feedpoint are catalyst beds containing etherification catalyst structures. Methanol, although
a high boiling component in this system, forms a minimum-boiling azeotrope with the C4s. This
azeotrope carries the methanol into the catalyst structures where the reaction proceeds. The MTBE
product is removed from the reaction zone by distillation. MTBE leaves the CD Reaction Column as
the bottom product together with a small amount of reaction by-products. Excess methanol distills
overhead with the unreacted C4s and is routed to the Methanol Recovery Section. Feed components
heavier than C4s will appear with the MTBE as the bottom product.
The C4 distillate stream is washed in the Methanol Extraction Column with a countercurrent stream of
water to extract the methanol. The methanol/water mixture from the bottom of the Methanol
Extraction Column is sent to the Methanol Recovery Column and the recovered methanol is blended
with fresh methanol and sent to the MTBE reaction section. The overhead stream from the Methanol
Extraction Column is the C4 raffinate 2 which is sent to the B-1 Recovery Unit for the recovery of
butene-1.
Recovery of butene-1 from the raffinate stream entails only physical separation by distillation. C4
Raffinate-2 is sent to the first of the two Heavies Columns to separate the higher boiling Butene-2 and
n-Butane product from the rest of the raffinate. Heavies Column #1 works in tandem with Heavies
Column #2 (i.e. together the two columns function as one larger column).
Heavies Column #1 operates at a slightly lower pressure than Heavies Column #2 and does not
require reboiling because the combined enthalpy of the feeds (i.e. Raffinate 2 from MTBE effluent
and the overhead vapor from Heavies Column #2) is sufficient to provide the required tray traffic. The
bottoms stream from the Heavies Column #1 is pumped to Heavies Column #2 as reflux. Heavies
Column #2 is reboiled with LLP steam.
The overhead vapor from Heavies Column #1 is condensed and accumulated in the Reflux Drum. The
condensate is pumped and a portion is returned as reflux to the B-1 Heavies Column #1 as reflux
while the rest is sent to B-1 Lights column for final recovery of the butene-1 and isobutane products.
The bottoms stream from Heavies Column #2 is sent to the battery limits as the Butene-2/n-Butane
product. In a similar manner to the Heavies columns, the B-1 Lights Column #1 works in tandem with
G-S000-5240-003 HMR Consultants
June 2015 3-10
Petrochemical Plant Sohar Environmental Impact Assessment Report
Orpic and CB&I HMR #3817
Lights Column #2 (i.e. together the two columns function as one larger column). Lights Column #1
operates at a slightly lower pressure than Lights Column #2. The bottoms stream from the Lights
Column #1 is pumped to Lights Column #2 as reflux. Lights Column #2 is also reboiled with LLP
steam. The overhead vapor from Lights Column #1 is condensed and accumulated in the Reflux
Drum. The condensate is pumped and a portion is returned as reflux to the B-1 Lights Column #1
while the rest is sent to battery limits as the isobutane product. Finally, the Lights Column #2 Bottoms
stream is pumped and sent to battery limits as the highly purified butene-1 product.
The ethylene supply is preheated in the ethylene interchanger with ethylene from the ethylene CO
removal vessel and then through the preheater where it is heated to 90°C before entering the ethylene
deoxo vessel. The deoxo vessel contains a fixed bed of free copper catalyst, which removes oxygen
from the ethylene stream by oxidation of the catalyst to copper oxides. The ethylene then passes
through the CO removal vessel which contains a fixed bed of copper oxides supported on zinc oxide,
which removes carbon monoxide from the ethylene stream by chemisorption. Refer to Figure 3-8 for
the plot plan of the PE unit.
Ethylene is then cooled before passing through the ethylene dryer which contain activated alumina
(Selexsorb CD and Selexorb COS), to remove water, methanol, other polar impurities and trace
amounts of carbon dioxide from the ethylene stream by physical adsorption and chemisorption.
During the product discharge cycle, some of the entrained reaction gas is transferred to the other
discharge system. This temporarily stored reaction gas is indirectly returned to the reactor during the
next discharge cycle, thereby minimizing the reactor gas released from the reaction system. Various
modifiers are also added to the reactor to obtain specific characteristic of the final product.
The reaction system consists of a reactor, a cycle gas cooler and cycle gas compressor. The gaseous
reactants (a mixture of ethylene, butene or hexene, and hydrogen) and inerts are continuously cycled
by the cycle gas compressor through a fluidized bed of resin containing small quantities of catalyst.
The heat of polymerization is transferred to the cycle gas and removed in the external cycle gas
cooler. A perforated distributor plate supports the bed of granular resin and distributes gas flow into
the bottom of the bed.
The granular polyethylene resin is charged into the reactor to provide a reaction bed before start up.
The reactor expanded section serves to disengage resin fines.
The polymerization reaction can be stopped or slowed down by the kill system. The kill system
consists of cylinder bottles containing Modifier C and a system of distribution piping and air operated
valves designed to inject the Modifier C into the cycle gas piping when the kill system logic is
actuated. The kill system logic provides several options as follows:
Type 1 Kill: Automatically or manually actuated with continued cycle gas circulation.
Type 2 Kill: Automatically actuated with no cycle gas flow and a small reactor blowdown.
Type 3 Kill: Automatically or manually actuated with reduced cycle gas circulation and small
reactor blow down.
Auto Mini-Kill: Manually actuated from the control room for small reduction in reactor rate.
Mini-Kill: Manually actuated in the field for small reduction in reactor rate.
Each reactor has two, two-stage product discharge systems (PDS). Both discharge systems operate in
a "cross-tied, alternating sequence" mode. However, each system may be operated by itself while
maintenance is being done on the other. Each PDS consists of product chambers (PC) and product
blow tanks (PBT). Granular resin and reaction gas are discharged intermittently to the PC from the
reactor. The resin and gas separate in the PC and gas is vented to the top of the reactor as it is
displaced by additional resin. The resin flows by gravity to the PBT, from which it is high pressure
conveyed (dense phase) to the product purge bin.
Granular resin and solid and liquid additives are fed through mixer feed hopper and vent filter into the
continuous mixer where they are melted and mixed. The molten polymer discharges through the melt
screen unit and the die plate of an underwater pelletizer. The pellet/water slurry from the Underwater
Pelletizer is fed to the agglomerate remover for separation of any agglomerates or clumps of pellets,
and then to the centrifugal pellet dryer. Dried pellets are fed to the pellet screener. Dried pellets flow
through the pellet screener where both over- and undersized material are separated from the main
pellet stream. The pellet streams are then delivered to product conveying system.
Finished pellets from the pelleting unit will be fed by gravity into the surge hopper. The surge hopper
rotary feeder feeds the pellets to a dilute phase conveying system which conveys the pellets to one of
the ten blending bins. Only one bin can be filled at a time.
While in circulation mode the pellets are fed by gravity from the blender to the dedicated conveying
system to the top of the same blending bin. Transfer between different bins can be applied, e.g. to
upgrade off-spec material. The blenders are designed and equipped with appropriate internals in a way
that material being discharged at the blender outlet is a representative mixture of the entire bin
content. Once the blending is finished the product is sent to the bagging facility. Since the bagging
silo has the same size as the blending bin one complete homogenized batch can be transferred to one
bagging silo. The pneumatic system will have a discharge air filtration system to remove dust.
The blending bin rotary feeders are located under each blending bin to discharge the pellets from the
blending bins. Pellets flow by gravity from the rotary feeders to the pellet blending/transfer systems.
For pellet transfer to bagging area the conveying air is generated by a dedicated blower and an after
cooler cools the conveying air prior to the pellet pickup point. Pellets from each blending bin can be
transferred to bagging silos or bulk loading silo according the selected diverter valve position.
Homopolymer;
Impact Copolymer.
The PP unit consists of the following units as discussed in subsequent sections and as shown in
Figure 3-9.
3.9.1.1 Pre-contacting
The catalyst system consists of three components - Titanium catalyst supported on MgCl2 (solid),
Triethyl aluminum (TEAL) (liquid) and Donor (liquid). The three components are fed separately to a
pre-contacting pot, where they are contacted and then fed to the reaction system. Catalyst, donor, and
TEAL are fed through metering pumps to the pre-contacting pot which is a constantly stirred vessel
with chilled water circulating in the jacket to maintain the temperature at 10C. The Donor and TEAL
supply lines are joined into a common line and cooled by using chilled water, in order to achieve a
better temperature control. The catalyst mud enters the pre-contacting pot through a separate dip tube.
The feed streams enter the pot from the top through dip tubes. The pot is operated full of liquid to
prevent gas pockets; the overflow feeds the pre-polymerization reactor. Catalyst mixture leaving the
pre-contacting pot is injected into a stream of cold propylene, which feeds the pre-polymerization
reactor.
Propylene is filtered to retain particles bigger than 10µm. Propylene is cooled down to 10°C and
mixed with catalyst mixture. The slurry is fed to a pre-polymerization reactor where reaction takes
place at low kinetics. Propylene is polymerized under controlled conditions of temperature (20°C),
pressure and residence time (at least 10-15 minutes) in the pre-polymer reactor. A very small amount
of propylene also polymerize through the flush line between the pre-contacting pot and the pre-
polymer reactor. The aim of pre-polymerization is to slowly form a shell of polymer around the
catalyst particles which is acting as a protection in the subsequent polymerization stage.
3.9.1.2 Pre-polymerization
The pre-polymerization reaction is carried out in a small loop reactor at 20 °C and 34-45 Barg. The
reactor is operated with cooled liquid propylene with about 200-300 g of propylene polymerized for
each gram of catalyst fed. The purpose of the pre-poly reactor is to slowly encapsulate, or form a shell
of polypropylene around the catalyst particle. This shell protects the catalyst when it enters the loop
reactor. If the catalyst is directly fed to the loop without encapsulation the catalyst particles would not
be strong enough, resulting in excessive production of fines. The pre-contacting pot, pre-polymerizer,
and loop reactor are operated continuously, in series.
Reduced reaction temperature (60°C) is required during terpolymer (propylene + ethylene + butene
polymer) production to cope with the increased reactivity of the system and the lower melting point of
polymer. Liquid propylene (and propane) is used as the carrier fluid. The loop reactor has a circulating
pump, which continuously recirculates the contents of the loop and which is critical for maintaining
uniform temperature and pressure through the reactor. The pressure of the prepoly reactor and loop
reactor is controlled by the reactor surge drum. The pressurization drum is equipped with a steam
heated propylene vaporizer.
Monomers contact the catalyst within the polymer granules and polymerize.
The temperature of the upward flowing gas increases, while removing heat of reaction.
Ethylene and propylene (and hydrogen for molecular weight control) are fed at constant flow rate and
in suitable ratios to meet the required properties of the copolymer products. Normal operating
conditions of gas phase reactor are 14 bar(g) and 75-80°C with an average bed density of 300-350
kg/m³
The copolymer produced is discharged from the reactor bottom for degassing. The reactive polymer
granules must be kept in constant motion to reduce the risk of plugging the reactor which is caused by
polymer fusion. To prevent such problems at the GPR bottom, continual rapid movement of the
polymer away from the bottom outlet is assured with a “fast loop” which is a loop pipe that takes the
majority of the GPR bottom discharge and allows it to flow by means of a pneumatic transport from
the bottom of the GPR near the top, dumping its content back into the reactor. Slurry discharged from
the reactor consists of about 53% wt polymer and 47% wt liquid propylene + propane mix. The slurry
from the reactor is discharged to the flash pipe at the temperature up to 90°C for homopolymer run.
PP polymer, discharged from the dryer is sent to the intermediate silos by nitrogen pneumatic haulage.
The silos are equipped with bag type filter and operate under nitrogen atmosphere. The solid
additives, coming from unloading stations are discharged into the screw feeder while the other
additive is discharged directly into the extruder hopper. A liquid peroxide metering station is provided
for special polymer grades production. The surge drum and the metering pumps are used to feed the
liquid peroxide into the extruder feed hopper. The equipment and lines in peroxide service are
maintained at temperature less than 40 C. For safety reasons the peroxide station will be located in a
separate room with explosion proof walls.
3.9.5 Extrusion
Additives and polymer mixture from the suction system are fed to the extruder through the feeding
hopper. Nitrogen is also fed to this hopper to prevent oxygen entering the extruder itself. Liquid
additives like organic peroxide and Atmer 163 are injected directly into the extruder hopper. PP
polymer powder and additives are homogenized, extruded and granulated by an under-water pelletizer
in the extruder. Granulation occurs in an underwater pelletizer. In the extruder, the melted polymer is
pushed against a die plate and cut into pellets by a set of rotating knives as soon as it emerges as
strands from the die plate.
Pellets are then transported by a water stream. Pellets and water stream leaving the underwater
pelletizer are conveyed to the dryer, via a separator. Water is separated from the pellets by gravity and
by centrifugal force. The pellets take a spiral path from the bottom to the top of the dryer. Final drying
is accomplished by the flow of dry air through the pellets. Dried pellets are conveyed by gravity to the
vibrating screen which separates fines and coarse from pellets. Coarse and fines are sent to off-size
pellets recovery package, while the on-spec pellets are discharged in the pneumatic transport hopper.
Finished PP pellets from the extrusion unit are collected by means of a pneumatic haulage in blender
silos.
Raw pyrolysis gasoline originating from the debutanizer column in the SCU or from atmospheric
storage tank and hydrogen originating from the Pressure Swing Adsorption (PSA) of the SCU will be
the main feed-stock for the pygas hydro-treating unit. The pygas hydro-treating Unit will produce
Hydrogenated C5, C6-C7 Cut, C8-C9 Cut and C10+. The various units and process description are
presented in the following sections. Overall process description for Pygas Hydrotreater Unit id
provided in Attachment 5.
The reactions (diolefins and alkenyl aromatics hydrogenation) occur in mixed phase (mainly liquid) in
a fixed bed type down flow reactor. As the catalyst activity decreases during the catalyst cycle, the
feed temperature of 1st Stage 1st Reactor increase from 60°C to 120°C. 1st Stage 1st Reactor effluent is
mixed with the quench stream coming from Hot Separator in a static mixer and routed to 1st Stage 2nd
Reactor. Second reactor inlet temperature will be such that the overall temperature rise in 1st Stage
reactor is maintained below 60°C. The reactors effluent is flashed into the Hot Separator Drum. Part
of the liquid from this is recycled through the 1st stage recycle pump and the remaining is sent under
cascaded level-flow control to stabilizer.
1st Stage Reactors are also designed to stand in-situ activation and regeneration of the catalyst. Due to
the use of nickel-based catalyst, an additional passivation step is performed to prevent high
hydrogenation rates of the feed with potential loss of aromatics and unbearable exotherm in 1st Stage
reactors. The active compound during passivation shall be Di Methyl Sulfide (DMS) which will be
injected in the closed loop from the DMS injection package.
3.10.2.1 Stabilizer
The Stabilizer has 30 trays and the feed enters the column at tray 18. The Stabilizer first stabilize the
first stage reactors product by removing the hydrogen and the light components and fractionate the C5
product as side-draw from the C6+ cut which is removed as the bottom product. The light gasoline cut
recovered as overhead product is routed to 2nd Stage Feed Surge Drum under flow control cascaded.
The C6+ cut leaving the tower bottoms feeds the Rerun Tower under flow control cascaded by the
level in the Stabilizer bottom.
The rerun tower has 24 trays and the feed enters the column at tray 14. The rerun tower purpose is to
fractionate the C6-C10 overhead cut from the C10+ cut (Heavy Cut) which is removed as the bottoms
product. The overhead vapor of the tower is partially condensed in the Rerun Tower Air Cooler and
the Rerun Tower Condenser and collected in the Rerun Tower Reflux Drum. Vapor phase from reflux
drum is sent to the rerun tower vacuum package. A part of the liquid is sent back as column reflux to
the top of the tower and the remaining liquid is sent to the 2nd stage feed surge drum. The heavy cut
leaving the tower bottom is pumped in the heavy cut pumps, cooled down in heavy cut air cooler and
sent to the PFO tank, under flow control cascaded by tower level controller.
The hydrocarbons and hydrogen mixture is preheated in the 2nd stage feed/effluent exchangers against
2nd stage hydrogenation reactor effluent. The reactor feed is then heated to the required reactor inlet
temperature in the 2nd stage feed heater. The reactor is divided into three beds. In the upper two beds
of the reactor, mainly olefins hydrogenation occurs and in the lower bed (loaded with a different
catalyst) mainly desulphurization occurs. The combination of two catalysts enables to keep the loss of
aromatics low.
The effluent from the 2nd stage hydrogenation reactor is cooled and sent to 2nd stage separator drum.
The liquid hydrocarbon from this is split into two streams: one is sent to the 2nd stage stabilizer feed /
deheptanizer bottom exchanger and the other is pumped and recycled either directly to 2nd Stage
Reactor (quench streams), or to reactor feed preheat train (diluent stream). 2nd Stage reactor catalyst
activation is different from 1st stage reactors. Catalyst needs to be sulfided prior to being used.
Sulfiding will be performed by circulating hydrogen mixed with H2S inside the reactor in closed loop
through the normal operation lines. H2S will be generated in-situ by injecting Di Methyl Di Sulfide
(DMDS) from DMDS Injection Package at 2nd Stage reactor inlet, which will decompose in H2S at the
sulfiding step conditions.
3.10.4.1 Stabilizer
Second Stage effluent is preheated in the 2nd Stage Stabilizer Feed / Deheptanizer Bottom Exchanger
and fed into the 2nd Stage Stabilizer. 2nd Stage Stabilizer has 30 trays and the feed enters the column at
tray 25. The Stabilizer stabilizes the second stage reactor liquid product by removing the H2S and the
light hydrocarbons dissolved in the column feed.
3.10.4.2 Depentanizer
The depentanizer has 55 trays and the feed enters the column at tray 26. The depentanizer recover a
C5 cut at overhead (Hydrogenated C5 cut). The overhead vapor of the tower is condensed in the
depentanizer condenser and collected in reflux drum. A part of this is routed back to the column as a
reflux while the remaining is sent to storage after being cooled down in the hydrogenated C5 trim
cooler.
3.10.4.3 Deheptanizer
The Deheptanizer has 43 trays and the feed enters the column at tray 26. The purpose of Deheptanizer
is to recover a C6-C7 cut at overhead and a C8-C10 cut in the bottoms. These streams will be routed
to Sohar Refinery
3.11 Utilities
The various utilities required during operation phase of the Petrochemical Plant are described in
subsequent sections of this chapter.
Integration of Power Plant with the Steam System of the Olefins Complex.
Integration options with the steam system of the Olefins complex are found to be unreliable with
respect to the occurrence of trips, resulting in unacceptable production losses at the Olefins complex,
even with a reliable connection to the external power grid for back-up power. In addition, investment
cost will be increased due to the use of super high pressure (121 barg) steam as generated in the
Olefins complex.
Orpic after careful consideration of various options has proposed the use of two GTCC units including
connection with Oman Electricity Transmission Company (OETC) grid for back-up power as shown
in Figure 3-11.
The proposed configuration is without any steam integration, because the steam integration:
Increases opex, notably due to more natural gas consumption and lower thermal efficiency.
Reduces operability due to more complexity and to many mutual influences between the
power plant and the Olefins complex.
Each unit has a gas turbine with a steam generator. Natural gas is used to drive the gas turbine, and the
hot exhaust is sent to the Heat Recovery Steam Generator (HRSG) possibly via an intermediate stack
with damper. The steam turbine expands the superheated steam to wet vacuum. The steam turbine
drives an independent generator.
Both units are fully independent and hence the reliability is high. Also it is possible to shut down one
unit for inspection and maintenance, while the other unit remains in full operation together with the
connection to the OETC grid. The reliability of power supply is increased by connecting to the
external power grid. The steam system of each unit is fully independent from the other unit. Further,
both units are also fully independent of the steam system of the Olefins complex.
The wet flare system will handle wet vapor relief loads from safety valves and vent gases which are
above 0°C at atmospheric pressure or, when the relieved flow contains significant amounts of water
vapor. It shall consist of a branched header discharging into the wet flare KO drum which is located
near the flare stack.
Any liquid accumulated will be routed to the quench tower drain drum. Only during shutdown of the
SCU; the pumped liquid is routed to the wastewater collection tank (WWCT). The vapors flow
through the wet flare seal drum to the stack. Service water flows continuously through an orifice into
the seal drum to ensure adequate water seal level. The continuous overflow is sent to the Oily Water
Sewer (OWS). The function of the seal drum is to prevent ingress of air into flare header. Ingress of
air is not allowed into the flare header as it can result in an explosive mixture in the header.
The inlet to the flare stack and the flare sub-headers will be purged with fuel gas to ensure a positive
flow from the flare system to the flare stack. Fuel gas is used as pilot gas and purge gas. Natural gas is
used as back-up for fuel gas. Medium Pressure (MP) steam is routed to the flare tip to ensure
smokeless flaring at low relief loads. The main equipment connected to this system is presented in
Table 3-1.
Table 3-1: Main Wet Flare Connections
In case the main wet flare is taken out of operation, all wet storage area vents and relief will be routed
to spare storage wet flare. From the main wet flare header the reliefs will be routed to the spare
storage wet flare KO Drum which is located near the flare stack. Any liquid accumulated will be
pumped to the liquid outlet line to be routed then to the quench tower drain drum. The main
equipment connected to this are pressurized storage for mixed C4, butene-1, butene-2 and Iso-butane,
Hydrogenated C4, and Hydrogenated C5.
Dry/cold reliefs from the petrochemical Plant process units will be collected in dry/cold primary
knock KO drums located at each process unit. Any liquid accumulated in the these KO drums will be
either vaporized in the assigned drum vaporizer using low pressure steam or pumped back to the
process unit.
The vapor streams from these KO drums will be directed to a common header and routed to the Flare
KO drum. Any liquid ethylene and propylene, accumulated will be vaporized by the main cold flare
vaporizer using low pressure steam. The main equipment connected to this flaring system is provided
in Table 3-2.
Table 3-2: Equipment’s connected to Flaring System
In case the main cold flare is taken out of operation, all storage area dry/cold vents are routed to spare
storage set flare. The cold reliefs from the pressurized storage are directed from the common cold
header to the spare storage cold flare KO Drum. Any liquid accumulated will be vaporized by the
spare storage cold flare vaporizer using low pressure steam. The capacity will be set to vaporize the
accumulated liquid in two hours. The cold flare sub-headers will be purged with fuel gas to ensure a
positive flow from to the flare stack. The main equipment connected to this header is:
High pressure equipment and piping of cryogenic ethylene and propylene storage; and
3.11.3 Incinerators
The waste streams produced in the petrochemical Plant will be incinerated using three different type
of incinerator system as follows:
Vent gases with toxic components or odour will be routed to the Vent Gas Incinerator;
The possibility to combine the liquid waste and solid waste incinerator will be considered during the
detailed designing stage. Overall process description for Incinerator is provided in Attachment 7.
The vent gases of the following storage tanks will be routed to the vent gas incinerator as these
contain nitrogen with toxic components. The following storages will be connected to vent gas
incinerator:
The vapor flows from the storage tanks are the result of pumping in and thermal out breathing during
the day. Blowers will be installed to transfer the vent gases from the storage tanks to the incinerator.
The second stream to be processed originates from the WWTU. Vapors formed during the thermal out
breathing and pumping in will be routed to the incinerator via a blower. This line is usually active and
can contain hydrocarbons in traces.
The third stream will be incinerated is the spent air stream from the spent caustic oxidation unit. This
air stream has a continuous flow rate and contains traces of hydrocarbons.
The fourth stream will be processed is the vent gas from the PGHYD, when it is not routed to the
cracking heaters, containing hydrocarbons. During shut down of the SCU, the PGHYD waste gas flow
(stream 4) and the Spent Oxidation Unit waste gas flow (stream 3) is zero, whereas the vapor flow
from other sources (streams 1 and 2) continues. The vent gas incinerator is specially designed for high
hydrocarbon conversion efficiency.
Flame arrestors will be provided to prevent fire in case of back flow from the incinerators into the
vent gas line. In case the vent gas incinerator is not available and during the start-up of the blowers,
the vent gases are routed to the atmosphere at safe location via vent gas stack, which will only be for
shorter duration of time. The flue gas is routed via a stack to the atmosphere. The incinerator is fired
by means of fuel gas with natural gas as back-up.
The waste liquid streams from the process and utilities units will be collected in waste liquid hold-up
drum, all streams are considered intermittent. The fluids will be transported by tank car or drums and
contents mixed by pumping before it is routed to the liquid incineration unit. The following liquid
waste streams will be handled in this unit:
The solid waste will be transported by means of trucks and is dumped in a waste feed hopper part of
the solid waste incineration. A feeder charges the solids into the combustion chamber. The solids will
be converted into flue gas and solid effluent. This effluent shall be transported to a landfill. The fly
ash shall be removed from the flue gas and shall be stored in silos. The incinerator will handle the
following streams:
Reliefs from the cryogenic ethylene and propylene storage tanks will be routed to the cryogenic low
pressure flare A/B which consists of flare tip, flare ignition system and molecular seal.
One system will be in operation and one in stand-by mode. MP steam will be routed to the flare tip to
ensure smokeless flaring at low relief load. Fuel gas will be used as pilot gas and purge gas and
natural gas as back-up for fuel gas. The cryogenic flare sub-headers will be purged with fuel gas to
ensure a positive flow from to the flare stack.
Draining system shall comprise of piping, valves, drain funnels, catch (inlet) basins, manholes and
open drain channels, combined with fire and sand traps based on the type of drainage.
Non pressurized systems operate under gravity. Equipment drainage and/ or surface water run-off,
with the exception of the storage tank areas, is collected upon discharge. In the storage tank area, the
area within the dikes is drained either preceding the next rain shower or during a period of rainfall, all
depending on the rainfall intensity, after verification of the water composition. The area shall also be
drained when a tank farm is subject to firefighting, cooling and extinguishing.
Thus the surface water from the area subject to fire fighting and possible contamination, as well as the
tank and roof drainage can be contained in the catchment area, while the other catchment areas can be
drained via the normally closed isolation valve. Volatile, combustible, toxic, viscous materials or hot
materials that may be drained during shutdown should be kept out of the atmospheric sewers, as such
materials might polymerize or react when they contact with air. The curbed area shall have a sump
where any spillage can be collected and neutralized and afterward removed by vacuum truck or routed
to clean water sewer. To collect flushing medium and surface run off in the PC, the following open
(non-pressurized) systems are proposed:
AOC collects surface water run-off from areas where contamination sources may be present during
equipment drainage in ISBL/OSBL areas. AOC is water which may be hydrocarbon contaminated.
AOC water will be routed to Last Line of Defense (LLOD). Main flows contributing to the system
are:
Rain, wash or firewater falling onto the hard paved areas where hydrocarbon spillage and
leakages are anticipated.
Drainage from equipment containing water, which may be accidentally contaminated (i.e.
pumps containing water).
The surface water run-off from the paved area of the MTBE area, where hydrocarbon leakage may
occur, shall be checked for contamination before routing to AOC sewer system. In case of high
hydrocarbon contamination surface run-off shall be collected by vacuum truck and transferred to
Benzene/ MTBE contaminated WW collection tank.
OWS is all continuously oil contaminated wastewater from rotary equipment base plate in ISBL/
OSBL areas. OWS will be sent to WWTU in order to separate the water and the oil. Main flows
contributing to the system are:
Contaminated water and/or flushing effluent from equipment via open funnels;
Surface water from concrete paved areas subject to constant contamination and dike areas, if
contaminated. Gasoline and MTBE drains, which need to be routed to the respective drain
systems.
This system collects surface water run-off from areas where contamination sources or leakages/spills
are not present, including fire and rainwater coming from:
LPG and hydrogen storage areas via a sealed sump, sand trap and atmospheric sewer;
Storage tank area via normally closed isolation valve (when clean);
This is clean water and will be discharged to common outfall after treating in water clarifier.
Sanitary sewer
Domestic wastewater from buildings will be routed by gravity to the domestic effluent lift station,
where solid and liquid waste will be transferred by pump to OSBL (MISC) for further treatment. Main
flows contributing to the sanitary sewer are toilets, urinals, kitchen sinks, showers (not safety shower)
and the likes in buildings.
Each system, except for the casing drain drums, shall discharge into respective below ground drip and
drain vessel as secondary containment in case of leakage, which will be located in a concrete pit. The
drain headers shall be directly connected to the drip and drain vessel to ensure that complete draining
is achieved. All concrete pits shall be provided with a drain pipe to the surface which is connected to
an installed ejector to allow emptying the rainwater from pit.
All drip and drain vessels are provided with nitrogen/fuel gas purge connection and shall have an open
connection to the flare in order to release vapors. Drain vessels are provided with a pump to transfer
the contents back into the process/treatment units
Desalinated water from desalination unit will be stored in tanks and used as service water after
chemical injection. Desalinated water is routed to the Demineralized (DM) water unit, potable water
tank, utilities stations, buildings and irrigation. The major user out of all is the DM water unit. Before
distributing to the service water end users (other units) several chemicals like 30% Calcium Chloride,
15% Sodium Carbonate and a blended corrosion inhibitor are injected to prevent corrosion in service
water. The service water is distributed to NGLT, RDG, SCU, Selective C4 Hydrogenation Unit
(SLC4HY), MTBE, Butene Recovery Unit (BUT) and PGHYD. Overall process description for
service water and potable water system is provided in Attachment 8.
A part of the service water will be fed into the potable water system and stored in the tank after salt
addition via salt solution unit and chlorination via hypochlorite injection unit. The potable water tank
is an atmospheric spherical tank, sized for a residence time of 24 hours based on normal flow rate and
installed at a sufficient elevation for distribution by gravity. Potable water shall be used for safety
showers, eye washer, etc
Fire water will be made up from desalination water and will be stored in the Fire Water Storage Tanks
for distribution. The fire water distribution network will be a closed loop to ensure multi-directional
flow in the system. Isolation valves shall be provided in the network. The fire water pumps and
distribution system shall be designed for a minimum residual pressure of 7 bar (g).
Desalination system will be based on MED technology which consist of two identical trains (one
operating, one on stand-by) in which Low Low Pressure Steam (LSS) is used to evaporate sea water
in multi effects. Seawater is provided by means of sea water pumps and filtered to remove undesirable
particles before feeding into the desalination process. Sea water flows through tube bundles in MED
the condenser as cooling media. Condensed water from all effects is collected in the last chamber
called condenser where non-condensable gases are removed by means of an ejector and desalinated
water is pumped as product to tanks. Total sea water return and brine reject will be discharged in one
common header to the sea water outfall. It is to be noted that the seawater intake and outfall system
are not part of the Petrochemical Plant scope.
Part of the stored desalinated water will be pumped from the desalinated water tanks to the DM water
unit to produce DM water. The DM water package shall consist of two Electro De-Ionization (EDI)
trains (one operating, one on stand-by) to remove undesirable salts and components by conventional
ion exchange from the feed desalinated water. Demineralized water shall be produced with the
required specification. The concentrated waste stream (reject water) will be recycled back to the
desalination unit.
The collected gas will be routed to a fuel gas drum operating at 4.5 bar (g). From there the fuel gas is
distributed to the various units. In case the SCU is short in fuel gas, high pressure natural gas at 31 bar
(g) will be routed to the Cracking Heaters. The SCU shall have its own independent fuel gas drum and
pressure let down system. Overall process description for Fuel Gas and Natural Gas System is
provided in Attachment 10.
3.11.7.1 FG Collection
Off gases produced in the new process units will be collected in one common header from the SCU.
The following streams will be the main off gas producers:
The split fuel gas serves the cracking units and the FG system. The fuel gas stream containing mainly
methane, minorities of heavier hydrocarbons and some inerts at about 4.5 bar(g) is mixed with the
natural gas stream from Sohar Refinery. The Static Mixer assures the continuous mixing of both
gases. The fuel gas will be further directed to the LP fuel gas drum which provides liquid droplet
separation, if present any.
3.11.7.3 FG distribution
Pressure of the Fuel Gas System is regulated by the pressure controller located on the outlet of Fuel
Gas Mixing Drum, adjusting the intake of NG to the drum. The mixture of FG and NG is distributed
to all process and utility consumers in the Petrochemical Plant:
Auxiliary steam system includes two utility boilers each of 250 t/hr steam generation capacity. Both
boilers will be normally in operation at reduced capacity. Fuel gas is used for firing of the boilers and
pilot burners. Auxiliary steam boiler unit receives super high pressure boiler feed water and produces
Super High Pressure Steam (SHS) at 121.3 bar(g) and 522 °C. Steam generated is sent to SHS header.
Overall Process description for Steam System is provided in Attachment 13. Following are the
various type of steam that will be used during operation of various process units within PC Plant:
Super High Pressure Steam - Super High Pressure Steam (SHS) is produced by SCU cracking
heaters and by Auxiliary Steam Boiler unit at 121.3 bar(g) and 522 °C and sent to the SHS
header. SHS is mainly used to drive charge gas compressor turbine and propylene refrigerant
compressor turbine (PRCT). Furthermore, SHS is intermittently used by the DPG First Stage
Reactor for regeneration and by DPG Second Stage Feed Heater.
High Pressure Steam - High Pressure Steam (HS) is produced by extraction from CGCT and
PRCT. HS is mainly used to drive some steam turbines in the process and utility units HS steam
is also used intermittently by Regeneration Gas Heater, RDG Oxygen Converter Feed Heater and
for the regeneration system of SCU, SHU and RDG unit reactors. Furthermore there is
continuous HS supply to the PE and PP Unit. HS header normal operating conditions are 42.3
bar(g) and 385 °C.
Medium Pressure Steam - The Medium Pressure Steam (MS) header is fed by the extraction from
PRCT, exhaust from Hydrogen Compressor Turbine, outlet of DPG 2nd stage reactor feed heater
in the PGHYD Unit, flash steam from blowdown and flash drums. MS is used for heating,
stripping and other use in process units and for driving PW stripper feed pump, gasoline
fractionator reflux pump, PW stripper bottoms pump, demin water pump turbine, LNG C2+
transfer pump turbine, for dilution steam, and smokeless flaring.
Low Pressure Steam - The Low Pressure Steam (LS) header is fed by steam extraction from the
Binary Refrigerant Compressor Turbine (BRCT). LS is used for the column reboiler in the
PGHYD unit, regeneration of DPG first stage reactor and regeneration system of SCU, SHU and
RDG unit reactors. LS header normal operating conditions are 10.6 bar(g) and 220 °C.
Low Low Pressure Steam - The LLS is used for heating, stripping and other use in process units,
for heating in utility and storage units, for smothering steam, steam tracing and in de-aerator unit.
Excess LLS is condensed in excess LP steam condenser to avoid too high pressure in the LLS
header. LLS header normal operating conditions are 3.5 bar(g) and 180 °C.
BFW will be produced in the deaerator which has two sections, a degassing section and a storage
section (which provides the liquid hold up). Deaeration is achieved in the degassing section of a
deaerator by breaking the water into as many small droplets as possible, and surrounding these
droplets with an atmosphere of steam. This releases the dissolved gases, which will be carried with the
excess steam to atmosphere. The deaerated water then falls to the storage section of the vessel.
Demineralized water mainly recovered condensate, is pumped and heated up in a series of Heat
Exchangers prior to entering the deaerator. Demineralized water is required for producing BFW,
making up water losses caused by steam stripping, blowdown and etc.
Water is heated up to saturation temperature in the deaerator by direct spraying of LLS to the
degassing section. In order to meet BFW quality specification, amine solution (neutralizing amine)
and oxygen scavenger are added to BFW. Amine solution is injected to BFW downstream of the
deaerator and oxygen scavenger is injected into the storage section of the deaerator. Upstream of the
amine injection point there is a BFW take-off line to the MTBE unit. The BFW to MTBE unit will be
cooled by the BFW cooler.
Instrument air will be used for pneumatic-operated instrumentation such as control valves, on/off
valves, for purging / cooling of essential instruments such as burner flame scanners and for pilot
burner flame front generation of the flare(s). Plant air will be used for maintenance activities, as purge
and as tool air for industrial users. Plant Air will be also used as a peak demand for catalyst
regeneration (one day per year). Decoking air is used for steam/air decoking of Cracking Heaters and
TLE heat exchangers. Overall Process description for Instrument and Plant Air system is provided
in Attachment 14. The Air facilities can be divided in two sections:
The compressed air system consists of the compressed air and the air dryer unit. The Compressed Air
unit mainly consists of the air compressors and the cooler. Air from ambient will be drawn in via Air
Inlet Filters. The compressed air is cooled by air finned coolers. Because the continuous air demand is
relatively low compared to peak air demand and in order to obtain sufficient controllability of the
compressor system, (2+1) equally sized compressors of 50% capacity required are installed in
parallel.
The continuously operating compressors will be steam turbine driven machine, the stand-by
compressor is electrical motor driven to increase the reliability of the system. The design capacity of
the air dryer unit is10,200Nm³/h of supply dried air to instrument air header and that of compressors
will be 6,600Nm³/h. Normal operating pressure of instrument air and plant air is 7 bar(g).
Plant air will be also needed for regenerations of catalyst beds of the following units. All the processes
are on intermittent basis and lasting no longer than 48 hours and are not likely to be performed at the
same time.
SLC4HY 1st stage and 2nd stage Reactor Regeneration requires about 1400kg/hr and 600kg/hr
at max flow, respectively;
PGHYD 1st Reactor & 2nd reactor regeneration requires about 650kg/hr and 5950kg/hr at max
flow respectively
The decoking air is produced by the air compressors. During normal operation, scheduled decoking
will be for one furnace at the time. Because the decoking air is required on intermittent basis, both the
compressors will be motor-driven to avoid so called “blow-off”. Both compressors will be provided
with variable speed. The compressed air is routed to the Cracking Heater. The pressure in the header
is controlled by venting to the atmosphere, and the decoking air is controlled by flow to the cracking
heaters.
Flow Rate
# Unit Description Unit
Normal Maximum
1 Secondary Cooling Water tph 73,500 88,200
2 Deminerized Water kg/h 125,000 185,000
3 Potable Water kg/h 5,000 30,000
4 Service Water kg/h 50,000 110,000
5 SHP Steam kg/h 657,600 686,700
6 HP Steam kg/h 407,700 413,400
7 MP Steam kg/h 183,500 213,800
8 LLP Steam kg/h 251,400 264,000
9 Boiler Feed Water kg/h 701,200 730,200
10 Natural Gas kg/h 54,800 79,400
11 Instrument Air kg/h 7,000 14,200
12 Plant Air kg/h 4,650 6,850
13 Decoke Air kg/h 28,400 41,000
14 Nitrogen kg/h 8,050 23,354
For the proposed petrochemical Plant the wastewater collection system has been designed taking into
consideration the following criteria:
All liquid waste streams coming from process, utility and storage areas that could be
contaminated with hydrocarbon are collected and treated before disposal;
Non-contaminated (clean) surface water run-off shall be kept separate from polluted or
potentially polluted run-offs;
High benzene / MTBE contaminated wastewater shall be kept separate from low or non-
benzene / MTBE contaminated effluent streams; and
All chemical effluents shall be neutralized inside the process unit’s battery limit and not to be
sent to sewer system.
The wastewater treatment unit (WWTU) for the proposed plant will consist of physical, chemical, and
biological treatment units as described below:
The inlet compartments of OCB and FOB are equipped with Oil Skimmer and Sludge Scraper. The
collected sludge will be sent to Oily Sludge Collection Tank. Taking into account the above
considerations, the following effluent collection system is designed for various waste streams:
Equipment oily drains pump base plates, hydrocarbon sampling points and surface water run-off from
the paved area where hydrocarbon leakage expected to have occurred shall be collected by oily water
sewer system and routed by gravity to OCB. The collected oily water is then transferred to the
wastewater collection tank for appropriate treatment. The inlet compartment of OCB is equipped with
floating type oil skimmer. The skimmed oil is sent to Skimmed Oil Vessel.
G-S000-5240-003 HMR Consultants
June 2015 3-40
Petrochemical Plant Sohar Environmental Impact Assessment Report
Orpic and CB&I HMR #3817
The quality of surface water run-off from the paved area where benzene / MTBE spillage may occur
shall be checked before routing to sewer system. In case of high benzene / MTBE contamination,
surface water run-off shall be collected by vacuum truck and sent to benzene / MTBE contaminated
wastewater pretreatment unit.
The AOC sewer system collects equipment drains and surface water run-off which is polluted neither
by benzene / MTBE nor by high concentration of other hydrocarbons and routes the collected effluent
to FFB through AOC water screen. The purpose of screening is to remove large objects such as rags,
plastics, paper, metals, and the likes and protect downstream equipment from damage or clogging.
The inlet compartment of FFB is equipped with a portable floating type oil skimmer to collect
skimmed oil if any. The skimmed oil is sent to Skimmed Oil Vessel. FFB is designed to hold rain
water run-off from potentially hydrocarbon polluted area during first 30 minutes of rain. After this
period, FFB is filled and the surface water run-off overflows to POB. It is expected that the
contamination level of surface water run-off collected in POB is diluted to such an extent that can
bypass biological treatment and be treated only by Induced Air Floatation (IAF) unit. If the quality of
collected run-off in POB is far from outfall water specification (high BOD / high COD), the collected
run-off shall be treated along with first flush water collected in FFB in biological treatment unit. In
addition, the POB is used as surge basin in case of cooling water oil contamination.
During normal plant operation, it is expected that good housekeeping keeps surface water run-off
collected in FFB clean enough (low BOD / low COD) to be treated only by an IAF unit for removing
any residual oil or suspended solids. The treated surface run-off will be sent to the treated effluent
tank for final check and settled sludge will be pumped directly to Sludge dewatering unit. However, if
the quality of collected water in FFB is off-spec due to high BOD / high COD, the water will be sent
to wastewater collection tank for further treatment in the WWTU.
This system is a clean water sewer, collecting surface water run-off from non-contaminated areas
where source of hydrocarbon leakage/spillage does not exist. The collected run-off will be routed by
gravity to the Non-Contaminated Surface Run-Off Clarifier where suspended solids will be separated
and settled. The clarified run-off is then sent to treated effluent tank and the collected sludge will be
transferred to sludge dewatering unit.
This collects domestic wastewater from toilets, kitchen facilities, sinks, showers and the like from
buildings and shelters. Domestic effluent from kitchen facilities shall be equipped with grease traps.
Domestic effluents are routed by a sloped gravity underground pipe system into the centralized
Domestic Lift Station where the solid and liquid wastes will be transferred by pump to Majis
Industrial Services Company (MISC) for further treatment.
Demineralized water spent regenerants, condensate polishing spent regenerants and spent chemical
shall be kept separate from surface water run-offs. To meet outfall water specification, the spent
chemicals shall be neutralized first. The neutralized spent chemical will be sent to the cooling water
outfall without further treatment.
First flush surface water run-off collected in LLOD, in case contaminated with
benzene/MTBE; and
Surface water run-off from paved area where source of benzene / MTBE leakage/spillage is
envisaged.
The benzene/MTBE contaminated wastewater pre-treatment unit consists of the following sections:
The WWCT collects all the wastewater streams before treatment in the wastewater steam stripper.
Since the wastewater contains benzene and/or MTBE, the tank is provided with a nitrogen blanket and
connected to the vent gas incinerator. The tank is equipped with a tangential inlet and oil skimming
facilities to remove the separated free oil. From the tank, wastewater is pumped at a controlled flow to
the wastewater steam stripper. If necessary, the pH is adjusted by means of caustic or sulfuric acid
dosing upstream the steam stripper.
The collected wastewater is preheated in Steam Stripper Feed/Effluent Heat Exchanger and fed to the
top of the steam stripper. At the bottom of this column, LP steam is supplied which strips the
hydrocarbons out of the influent. Vapors at the top of the column are condensed and collected in the
overhead reflux drum. In this vessel, the condensed liquid will separate to a water layer and a thin oil
layer, which flows over the installed weir into the hydrocarbons compartment. The water in the vessel
is pumped as reflux to the column. The recovered hydrocarbons are routed to the Skimmed Oil
Vessel. Vapors are vented to the wet flare system.
Nitrogen will be used in order to maintain sufficient pressure in the overhead system of the column to
allow venting to the flare. Some nitrogen is required in case insufficient hydrocarbons (non-
condensable) are present in the wastewater feed stream.
The steam stripped effluent collected from the bottom of the column is pumped to the collection tank
after heat recovery in Feed/Effluent Heat Exchanger and cooling down in Stripped WW Trim Cooler
to below 40°C using cooling water. In case of high benzene and/or MTBE contamination of the steam
stripped effluent, it is manually routed back to the WWCT. If the stripped effluent is on-spec
according to benzene/MTBE contamination level but off-spec due to high TOC, the stripped
wastewater shall be sent to WWCT and to be treated by Dissolved Gas Floatation (DGF) Unit.
Wastewater WWCT;
DGF; and
The WWCT is used to store the process wastewater awaiting the DGF treatment. The tank is equipped
with tangential inlet and skimming facilities to remove any separated free oil. From the tank, the
wastewater is pumped to DGF. Wastewater pH is adjusted by means of caustic or sulphuric acid
dosing upstream DGF unit. The DGF package should be sized such that to provide sufficient
operating flexibility to allow effluent quality to be maintained in acceptable range by considering the
expected variations in the influent characteristics.
Wastewater passes sequentially through coagulation, flocculation and floatation compartments of the
DGF unit. Cationic polymer solution is dosed into the influent upstream of the DGF unit to enhance
removal of free/emulsified oil and suspended solids. The system forces nitrogen gas into effluent by
means of hydraulic eductors. The nitrogen bubbles will adhere to the oil particles and form flocs and
help these particles to float to the water surface of each flotation compartment.
The floating scum layer is removed by means of a surface skimmer mechanism and sent to the
Skimmed Oil Vessel. The treated wastewater will overflow via the effluent weir into the DGF clear
well compartment and is pumped to the equalization tank. The Skimmed Oil Vessel collects the
following streams:
Skimmed oil from the steam stripper overhead reflux drum; and
DGF skimming
Equalization Tank;
Bio-treater; and
The wastewater equalization tank receives the wastewater streams to be treated in the biological
treatment unit. The following streams are routed to the equalization tank:
Equalization tank has a buffering and homogenization function for the feed stream to the Bio-treater,
thus minimizing fluctuations in flow rate and composition. In the Bio-treater, BOD and COD are
reduced by activated sludge using dissolved oxygen. Bio-treater will receive feed streams from
Contact Tank where the equalized wastewater will be mixed with the recycled activated sludge and
nutrients (urea and H3PO4).
After pH adjustment, the mixed stream is routed to the Aeration Tank where required amount of air is
supplied. Aerated stream will be routed to clarifier on gravity flow via degassing tank. In the clarifier,
the settled activated sludge is separated from the clean water. Part of the activated sludge is recycled
to the contact tank and the excess activated sludge is sent to the sludge digester followed by sludge
thickener. The clarified water is routed to the tertiary treatment to meet the outfall water specification.
Thickened excess bio-sludge from sludge thickener is sent to sludge dewatering unit where polymer
solution is added for conditioning of the sludge. Dewatered bio-sludge is collected in a mobile bio-
sludge cake container, which is trucked out for disposal by incineration. The decanted water from
Sludge Dewatering unit is recycled to the WWCT.
Oily sludge will be kept separate from bio-sludge. The oily sludge from LLOD basins, WWCT and
wastewater DGF will be sent to oily sludge storage tank where it will be pumped to sludge dewatering
unit. The dewatered oily sludge is collected in a mobile oily sludge container for incineration. The
reject stream will be sent to WWCT for further processing.
Disinfection Unit;
In order to meet discharge water specification, chlorine gas will be used for chlorination of clarified
water in Chlorination compartment of Chlorination/De-chlorination basin followed by SO2 injection
for de-chlorination in de-chlorination compartment. For removal of remaining suspended solids, the
de-chlorinated water is routed to the continuous sand filter. The unit consists of two continuously
regenerated sand filters, each designed for 70% of total capacity. The continuous backwash stream
from the sand filters is recycled to WWCT.
The clean effluent from sand filters will flow on gravity into the filtrate basin, where the treated
effluent quality is continuously monitored by means of a flow, turbidity, temperature, TDS and pH
measurement. It is expected that sand filter clear water can meet the outfall water quality. However, in
case of hydrocarbon contamination, the effluent can be sent to activated carbon filters for final
polishing. The treated wastewater will be sent to the treated effluent tank. Additional information
related to WWTP is provided in Attachment 15.
In WAO process, air is brought into close contact with an aqueous solution and dispersion of organic
material at an elevated temperature and pressure is performed. During oxidation, the organic
compounds convert to CO2 plus water or organic acids and the sulfides to thiosulfates or sulfates.
Oxidation of sulfides to thiosulfates and sulfates happens according to the following exothermic
reactions:
The oxidized Spent caustic is neutralized with concentrated Sulfuric Acid. The neutralization
reactions are given below:
Spent caustic waste stream from the Caustic/Water Wash Tower combined with spent caustic from the
caustic/water wash tower of the RDG is routed to spent caustic coalescer followed by spent gasoline
coalescer as a pretreatment step. Wash gasoline from quench water settler is added to spent caustic in
order to remove entrained oils and some dissolved organic compounds. The coalescer effluent is sent
to spent gasoline coalescer where the spent caustic and spent gasoline is separated. Then spent caustic
is sent to spent caustic storage tank from where it is pumped to the oxidation unit.
The spent caustic oxidation unit will be designed to treat the spent caustic stream in a WAO process.
The oxidized spent caustic is neutralized to a pH in the range of 7 to 9 with concentrated sulfuric acid.
The net neutralized spent caustic is sent to the SCO effluent tank where after homogenization, it will
be sent to WWTU. Additional information on Spent Caustic system is provided in Attachment 16.
Minimum quantities of soil are expected to be excavated during the plant construction as the site is
within the SIPA and is already leveled. Excavation of soil will be required for laying foundations for
various structures and plant equipment, pipelines and buildings. The excavated soil will be stored near
the excavation areas or in a dedicated storage area and will be used for backfilling, wherever possible.
The top soil layer that will contain roots, etc., will be transported outside the site to the Sohar waste
collection site for dumping, upon consent from the SEU. It must be noted that a soil investigation has
been carried out as part of the SEU requirement and PC project. During the piling for the foundation
dewatering will have to be carried out which needs to be in line with the MECA wastewater discharge
requirements.
Significant concrete work will be involved for the construction of plant and equipment foundations
and buildings. Further dewatering operations may be utilized to provide a dry work area. Asphalting
work will be required for the facility internal roads. Different concrete mixes may be used for
different requirements. Aggregate sources will be investigated by the contractor in order to ensure
adequate quality of aggregates. The aggregates and water required will be obtained from approved
sources so as to negate any significant adverse impact/stress on the environment. The EPC contractor
will consider the possibility of obtaining ready mix concrete and bitumen as opposed to engaging
concrete mixers and bitumen mixers onsite so as to minimise air emissions and other wastes.
The equipment to be used for the construction works will include excavators, shovels, dumpers,
tippers, vibrators, compactors, mobile cranes, water tankers, trailers and Diesel Generators (DGs).
Most of the equipment will be operated during the day time hours only. The types of materials
required for the construction work are described in the following section.
Mechanical and electrical works will be typical of any industrial plant construction. Use of any
radioactive materials will be limited to NDT of plant equipment, pipelines and storage tanks using
sealed radioactive sources. Subcontractors with approvals from MECA and other concerned
authorities will be used for the NDT. Required permits will be obtained from MECA and other
concerned authorities for storage and handling of radioactive materials, as required.
3.13.1.1 Power
Power for the construction phase of the facility is expected to be sourced from existing grid or
alternatively will be met through portable DG units. Since the project is in its initial stages details on
the specifics such as number of DG sets required during project construction, their approximate
capacities etc. are not know at present. However it is expected that a DG sets of 450 kVA will be
needed for the power requirements during the construction phase.
3.13.1.2 Water
The potable water requirements during the construction phase are expected to be met by supplies from
approved local contractors through tanker supplies. Assuming a per capita potable water consumption
of approximately 240L/day the total freshwater requirements for the construction site and
accommodation facilities are estimated to be approximately 240m3/d2. In addition the water
requirement during the construction phase is expected to be 100m3/day. Some of the requirements at
construction site such as dust suppression will be met through utilizing treated wastewater. The total
water requirement during the construction phase is estimated to be approximately 340m3/day
3.13.1.3 Fuel
Diesel oil will be used as fuel for the DG units, various construction equipment, heavy vehicles and
some of the passenger vehicles used during construction. Diesel oil will be sourced from local
suppliers and stored onsite in dedicated storage tank with all regulatory requirements and approvals
from MECA and ROP.
It is expected that a maximum of about 20,000 L/month (8,000 L/month for the DG sets and 12,000
L/month for equipment and vehicles) of diesel fuel will be required during the construction period and
the fuel storage tank will be sized accordingly. Diesel would be stored in above ground tanks resting
on concrete foundations inside an adequate containment area. Diesel would be dispensed via a fuel
pump. The whole filling station would be fenced with restricted access. Fire- fighting equipment and
warning signs will be available at all times. Gasoline for light vehicles will be sourced from local
retail suppliers. Oils for DG units and equipment will be obtained from approved suppliers. They will
be stored in appropriate storage spaces provided at the site. Permits for storage and use will be
obtained from MECA, as appropriate.
2
Assuming an average workforce of 1000 people for construction phase.
G-S000-5240-003 HMR Consultants
June 2015 3-47
Petrochemical Plant Sohar Environmental Impact Assessment Report
Orpic and CB&I HMR #3817
Fill Materials and Aggregates Local Quarries by tippers On-site in lay down area
Metal and Wood Local and external Suppliers On-site in a designated area
Paints and other surface coating Local and external Suppliers In temporary stock containers
materials by trucks on site
Porta-cabins will be erected on-site for accommodating the project office and to provide the on-site
catering and sanitation facilities for the project staff. The EPC contractor staff will most likely be
lodged in rented accommodation facilities near the project site. With regards to the sub-contractor
staff, it is likely that the local Omani staff will have their own local accommodation facilities. For the
accommodation of the non-local Omani staff and the non- Omani staff, the sub-contractors will either
utilize the existing labour camps or construct new labour camps.
The EPC contractor will select the location for the labour camp and organize to establish it. Since
selection of the EPC contractor for the project is to be done after completion of the FEED, the
location and number of construction camps is not known at present. However, following will have to
be considered while deciding to set-up labour camps:
For any new labour camps, select the locations which will fully comply with local town
planning requirements;
Provide all the basic facilities such as power supply, water supply, sanitation, security and
general hygiene; and
Implement the environment, health and safety management plan set out in this report.
The accommodation facility for the crew shall have the following facilities at a minimum-
All camp facilities shall be constructed to provide protection against pests and adverse weather
conditions;
Water for drinking, cooking, washing and toilets shall be provided from approved sources. A
minimum water supply of 250 l/person shall be provided;
If water is trucked in, the tanker truck shall be licensed in accordance with ROP requirements;
Water supplied to camps shall comply with the chemical and bacteriological limits specified in
Omani Standard 8/2012. Bacteriological limits in water storage tanks shall be checked
monthly and the tanks shall be cleaned annually;
Air conditioning should be by means of windows or split units and should include cooling and
heating system;
Toilet and washing facilities shall be provided in, or adjacent to, living quarters, work place
and recreation areas;
Adequate drainage from all sanitary facilities must be maintained to maintain hygiene
standards;
Sewage effluent and domestic waste shall be managed/transported and disposed in accordance
with MECA specification; and
General cleanliness and good housekeeping of camps and surroundings shall be maintained as
the primary method of pest control.
• Suggest viable options for addressing concerns related to traffic associated with construction
activities.
Orpic is responsible for the implementation of this plan. Orpic will guide the construction contractor
to ensure that this procedure is brought to the attention of all employees at site and the content of this
plan is implemented as required and appropriate. The application of this plan will be verified at
appropriate intervals to avoid any health and safety concerns; and the contractor will ensure that the
workers and subcontractors over whom they have direct control comply with this procedure and that
subcontractors are managed accordingly. The preparation of the detailed TMP will be carried out
considering the site specific requirements in consultation with Royal Oman Police. The local
community may be involved to formulate the TMP with due considerations of the local traffic
concerns and safety of livestock.
Upon completion of FEED, the Engineering, Procurement and Construction (EPC) contractor for the
project will be selected through a competitive bidding process. The selected EPC contractor will
undertake the detailed engineering, construction and commissioning of the plant facilities. The EPC
contractor will typically engage subcontractors for various construction activities, some of whom are
expected to be local (Omani) companies.
Orpic acknowledges its obligation of maximizing where ever possible the use of Omani Goods and
Services in full support of the aspiration of the Government of Sultanate of Oman to maximize the
involvement of Omani nationals and Omani companies in the execution of its contracts. As part of its
active support, Orpic encourages its contractors and vendors, wherever possible, to utilize Omani
goods and Omani services in performance of the work on behalf of it.
4 ENVIRONMENTAL BASELINE
4.1 Overview
The following sections present a description of the environmental settings of the proposed PC site and
its surroundings. A comprehensive environmental baseline study through primary surveys, monitoring
and secondary data collection was conducted during the EIA study. The proposed project is located
within SIPA and during the master-planning of the SIPA development a comprehensive
environmental baseline study has been conducted. Further HMR has carried out environmental
baseline studies for various industries within the SIPA. Consequently a large amount of data is
available with regard to the physical, biological and social environment in the area. This information
was reviewed to extract relevant secondary information on the proposed PC Plant site. In addition
primary information on the project site has been collected through site surveys and baseline
monitoring conducted during November/December 2014. These surveys were planned based on the
available information and were conducted with the intention of data validation and augmentation, as
required.
A part of the PP is located on the southern boundary of the SIPA while the other is located on the
south eastern end. Plot 1 of the PP will have interphase with the aromatics complex on eastern side
and polypropylene facility on the northern side. Plot 2 is located on the southeast side of the SRIP
plant. The site location is shown in Figure 4-1. The UTM coordinates of plant boundary are
summarized in Table 4-1 and is shown in Figure 4-2. Additional informative maps are provided as
Map 1 through Map 6.
Table 4-1: Coordinates of the Project Site
Plot-18
Plot-10
The plant site elevation is about 0-1 m above mean sea level (amsl) for Plot 1 and 4-9 m above mean
sea level (amsl) for plot 2. The site is not fully leveled and is sparsely vegetated. As mentioned in the
previous section, SIPA, prior to development, was a flat farmland and was similar to other
undeveloped areas along the Al Batinah coast.
SIPA area is situated within a coastal area featuring coastal dunes and belts of scrub starting
approximately 300m inland. Aeolian sand dunes extend 0.5km from the shoreline and reach up to 3m
in height. Further from the shoreline, featureless ‘Sabkah’ with sparse vegetation is seen up to 1.5km.
Dense natural vegetation dominated by Acacia is seen along the wadi plains and in the agricultural
areas associated with the settlements at the outer limits of SIPA.
Batinah is characterized by a high variability and diversity in watershed characteristics. Two distinct
seasons are prevailing namely, winter (November to April), and summer (May to October), affected
by various meteorological mechanisms. During the period from January to March and November to
December, the controlling features of rainfall occurrence over the area are mainly due to the middle
latitude low pressure systems moving from west to east with thunderstorm activities. During the
months of May and October rainfall activities over the area is mainly due to cyclonic storms and
depressions. During September, the area gets rain partly due to monsoon and partly due to cyclones
and depressions. During the months of June, July and August, the monsoon season, the local climate
is more or less continuously raining. The meteorological/climate data for the project area is sourced
from the meteorological station located at Majis. The station is operated and maintained by
Department of Meteorology. A summary of the meteorological data for Sohar area CY 2011 through
2013 is presented in Table 4-2.
Table 4-2: Meteorological Conditions at Sohar 2011-2013
From the above table it is seen that the mean ambient temperature in the region around Majis follows
a similar trend during CY 2011 through 2013, varying between 18 and 36 ºC. The temperature peaks
during the summer months of June and July; while the ambient temperature dips during the months of
December and January. The maximum and minimum recorded ambient temperature at Sohar during
2011 through 2013 are 45.6ºC (July 2012) and 11.2 ºC (December 2013).
highway. Several environmental studies have been conducted by HMR from 2000 through to 2014 in
the industrial area, which included monitoring of the ambient air quality. The monitoring was largely
carried out by deploying passive diffusion tubes for a period of 3 to 4 weeks to measure the ground
level concentrations (GLCs) of various primary pollutants. However in recent years Continuous
Ambient Air Quality Monitoring Station (CAAQMS) has been preferred by the regulators for ambient
air quality monitoring. As part of the baseline survey for a project in SIPA in 2011, a CAAQMS was
installed at the project site at four locations. From these studies it has been observed that the GLCs of
NOx ranges from 3.7 to 26.8μg/m3, the GLCs of SO2 ranges from 4.4 to 12.3μg/m3, and the GLCs of
O3 range from 66 to 83μg/m3.
As part of the baseline study for PC Plant a CAAQMS was installed at three locations within the
project site. The locations were selected based on the wind direction and the ease of accessibility for
the trucks carrying the CAAQMS and the DG for the power supply. The DG was positioned at about
100 m downwind from the CAAQMS to prevent capturing of the DG emissions by the CAAQMS.
The monitoring methods for each parameter in the CAAQMS are presented in Table 4-3. The UTM
Coordinates of the locations and duration of monitoring at the locations are presented in Table 4-4.
Prior to commencement of monitoring, the analyzers were calibrated using zero air and subsequently
subjected to span calibration using the calibration gases from the cylinders housed within the
CAAQMS container.
Table 4-3: CAAQMS Monitoring Methods for Parameters
At the end of the monitoring campaign, the ambient air quality monitoring data was downloaded and
the 1-hr, 3-hr, 8-hr and 24-hr averages were calculated, as applicable. The maximum of the calculated
averages were compared to the OAAQS and USEPA NAAQS limits. These are presented in Table
4-5.
The ambient dust levels were measured at various locations within the project site on 4th December
2014, for 15 -20 min at each location. The UTM Coordinates of these locations and the dust levels
measured are presented in Table 4-6 and indicated on Google Earth imagery in Figure 4-3. The
measured dust levels were compared with corresponding limits for PM10 in OAAQS (125μg/m3) and
USEPA NAAQS (150μg/m3).
Table 4-6: Ambient Dust Levels – Location Coordinates and Measured Values
UTM Co-ordinates
Location PM10(μg/m3)
Northing Easting
Plot 1
FL-1 459387 2708600 13
FL-2 459651 2708174 15
FL-3 460060 2708369 13
FL-4 459683 2708762 18
FL-5 460282 2708507 16
FL-6 459972 2709011 45
Plot 2
FL-1 461107 2705614 121
FL-2 462546 2705205 88
FL-3 461707 2704688 15
FL-4 462213 2705352 51
On comparison of the measured dust levels with the OAAQS and USEPA NAAQS, it is observed that
the dust levels measured at all locations within Plot 1 and Plot 2 are well below the OAAQS and
USEPA NAAQS limits. In addition, ambient dust levels were also measured by the CAAQMS at the
three monitoring locations. The maximum 24-hr averages for the three locations are compared with
the limits prescribed by OAAQS and USEPA NAAQS in Table 4-7.
Table 4-7: Maximum 24-hr avg. Dust Levels at the Site
From the above table it is seen that the dust levels measured by the CAAQMS for all 3 locations are
within the USEPA NAAQS limits while there are slight exceedances when compared with the
OAAQS.
Weather conditions were normal and there was no excess wind during the measurements. Wind
speeds were measured using a hand-held anemometer simultaneously with noise measurements to
ensure that the wind speeds were less, as high wind speeds would lead to errors in the measured noise
levels. The ambient noise levels during daytime, evening and night are presented in Table 4-8.
Table 4-8: Ambient Noise Level
3
Ambient noise standards issued under MD 79/94 from industrial sources applicable to the proposed plant (Industrial and Commercial) as
the project lies within a dedicated industrial area
From the table it is observed that the measured during all the three instances (Daytime, Evening and
Night time) are well beyond the applicable Omani standard. The daytime noise level could be
attributed to the various industrial activities in the area.
4.6 Geology
Sohar area forms a part of the Batinah plain, which comprises of piedmont and coastal zones where
late tertiary-quaternary alluvial deposits dominate. The piedmont zone comprises of the slightly
elevated Batinah plain that extends between the coastal plain and the foothills of the western Al-Hajar
Mountains. The un-cemented alluvial wadi sediments in the recent wadi channels typically consist of
boulders, gravels and silty sands of variable composition. The piedmont areas are composed primarily
of ancient gravel terraces, incised by active wadi channels and subsequently covered with recent
alluvium. These alluvium deposits vary in thickness from a few meters to tens of meters.
The coastal zone comprises of extensive sand and gravel plain extending between the piedmont zone
and the gulf of Oman. The coastal zone is extremely flat and is covered by finer sediments (sand and
silt). Immediately adjacent to the coast, aeolian sands of recent to sub-recent age predominate.
However, intermingled deposits of clay and silt are common. A thin veneer of beach sand stretches
along the foreshore.
4.7 Soil
The surface soil in SIPA has been modified as part of the development of the industrial estate as the
area has been levelled and elevated to sufficient height.
The soils along the Batinah coast in Sohar are regarded as moderately to highly suitable for
agriculture. With depth, the soils tend to exhibit higher percentage of organic matter. According to the
Ministry of Agriculture and Fisheries, the land in Sohar is classified as S1, which means that land has
either no significant limitation or moderately significant limitation for sustained irrigated agriculture.
The Sohar area is known for its agricultural produce, which include dates, citrus fruits and vegetables.
Generally the agricultural zone does not extend to the coastline because of saline water intrusion.
Within the sand and gravel plains, the soil cover is extremely thin and low in organic matter.
The grab samples were collected from about 30cm depth and then mixed to form the composite
samples. The composite samples were collected in different wide-mouth glass jars and submitted at
Haya Laboratories in Muscat for analyses. The coordinates and the results of the analysis are
presented below in Table 4-9 and
Table 4-10 respectively. In the absence of Omani standards for soil quality, the analysis result is
compared with USEPA Site Notification Standards for Industrial Soil. A copy of the analysis report is
attached as Appendix C.
Table 4-9: Soil Sampling Location
4
USEPA Site Notification Standards for Industrial Soil (12th September 2008)
On comparison of the parameters in the soil samples from the project site with the corresponding
standard limits prescribed in the USEPA Site Notification Standards, it is seen that the parameter
levels are below the specified limits. The soil at the site is neither acidic not alkaline, high chloride
level at LS1 might be an effect of seawater intrusion. There is no evidence of any Hydrocarbon (HC)
contamination of the soil samples. The appreciable levels of magnesium and iron could be due to the
presence of minerals such as chromite in the region.
The natural surface drainage extends from the western Al Hajar Mountains towards the sea providing
variable infiltration throughout the region. Typically, alluvial deposits found in wadi channels will
allow surface water to quickly dissipate.
The agriculture practice in the Batinah area is limited to a narrow strip along the coast of Al Batinah
region which is less than 5km where the groundwater occurs in shallow condition. The national well
inventory has confirmed that the current level of abstraction on the coastal plain exceeds the natural
recharge to the groundwater in the area. Groundwater levels in the Batinah area are the principal
source of information about the hydrologic stresses acting on aquifers and in turn how these stresses
affect ground-water recharge, storage, and discharge. The groundwater level data for 85 wells
obtained from the MRMWR monitoring division department indicate that the average depth to
groundwater in the Al Batinah Region varies from 5m bgl at nearshore areas and upto 60m bgl near
the foothills.
It can be noted from the above results that the levels of Sodium and Magnesium in the groundwater
sample is significantly above the limits applicable for drinking water. Iron, chromium and Nickel
levels are also marginally above the standard limits. However, the hydrocarbon and VOC levels are
below the detection limits.
The results show that the groundwater in the area is highly saline and hard. The presence of
Chromium and Magnesium could be attributed to the leaching of these metals from local geological
formations. The high salinity could be attributed to saline water intrusion at the coastal area.
However, it is to be noted that the groundwater in the project area will neither be used for drinking
water nor for project requirements.
As part of baseline studies for the proposed plant in SIPA, a rapid flora and fauna assessment was
conducted in September 2014 at the project site to verify and update findings from previous
ecological studies conducted in the area. The detailed ecological assessment is included in Appendix
E.
From the survey it is observed that the project site is a degraded and altered ecosystem as indicated by
the composition and current status of vegetation. Most of the area is covered by salt bush thickets and
a large number of thickets have dried up or desiccated. About 75% of the vegetation is represented by
dry and desiccated Suaeda and Salsola bushes. The proposed site does not have any plant species or
communities that are rare or threatened or endangered in Oman and the Arabian Peninsula. All
species found at the site are of common occurrence across the country and none have restricted
distribution.
Further the project site does not harbor any reptile or mammal fauna of great ecological or
conservation significance. The geckos and birds that were observed at the site during the study are
common species, which have wide ranging distribution across the country. Various ecological impacts
due to the proposed project will include loss of vegetation and loss of habitat for existing floral and
faunal assemblage. However these would not be significant since the site does not have any unique or
endemic flora or fauna.
rock crabs (Grapsus sp.). The density and distribution of various species was observed to be very low
among the boulders close to the mouth area of the outfall. Relatively very small rocky embankment
and wide sandy intertidal area was exposed during the low tide in the outfall region. No sensitive
biota was identified in these tidal regions. Large amount of dead bivalves like Callista erycina, Tivela
ponderosa, Phaphia undulate, Anadara sp., Cardites bicolour and gastropods shells Murex sp,
Cypraea sp, Strombus sp., Bulla amppulla, Oliva sp were observed at the nearshore region of the
outfall.
The subtidal environment in the common intake region of SIPA comprised very cohesive, fine
sediment, covered with an algal mat. The sediment was observed to be fine, rich in organic matter and
rapidly hypoxic below the algal mat which may be primarily due to the existing breakwater that
typically promotes stagnant waters when compared to coastal areas where sediments tend to
accumulate rapidly. The maximum depth was recorded at 6m, with visibility about 1m due to the
murky water at the bottom. Relatively high populations of polychaetes were observed. A few
gastropods-Bulla ampulla were found foraging in the sediment. Few pelagic fishes like sardines were
observed in the area.
The proposed petrochemical Plant does not have any direct interaction with the marine environment.
There is no seawater intake envisaged for the project and only treated water that complies with MD
159/2005 is discharged into the common outfall canal. Accordingly, no dedicated seawater intake or
outfall facilities are expected to be provided for the Project. Since the Project has only indirect
impacts on near-shore through various service providers, no marine ecological survey was undertaken
as part of the EIA for the Project.
The project site falls under the North Al Batinah Governorate, which lies between Khatmat Malahah
in the North and Al Musanaah in the South and confined between the Al Hajar Mountains to the West
and the Gulf of Oman to the East. It is located within SIPA, which comes under the Wilayat Liwa and
characterized under industrial land use. There are 10 villages lying within a 5km radius of the project
sites as presented Appendix F.
4.12.1 Connectivity
The Muscat - Batinah highway serves as the main linkage for the project influence area. Running
parallel to the main highway is the service road, which seizes the local traffic spills, reduces pressure
on the main highway and facilitates movement between villages. However, connectivity at village
level is by means of internal or primary roads which traverse and connect each village.
A coastal highway is also being constructed between SIPA and the existing Batinah highway (Figure
4-4) which would increase connectivity between SIPA and other regions of Batinah and Muscat
Governorates. Other major transport infrastructure development including the rail link (which would
connect the United Arab Emirates (UAE) and Gulf Cooperation Council (GCC) countries eventually),
in the Batinah region.
5 ENVIRONMENTAL RELEASES
The project interaction with the environment during the construction and operation phase will be
primarily by way of consumption of resources, release of various waste streams and accidental
releases/spills of hazardous materials. In the following sections, potential releases to the environment
during construction and operation phases of the project are presented. The environmental releases will
be identified and quantified using empirical equations and mathematical models, such as AP-42
emissions factors, AERMOD, TANKS etc. It must be noted that the quantification of various wastes
from the proposed plant will be limited by the availability of engineering data on the activities. Where
sufficient data are not available, suitable assumptions are made based on the previous experience and
engineering rules of thumb.
Releases during the decommissioning phase are expected to be similar to that of construction phase
but for a shorter duration, and hence are not discussed separately. The waste streams are classified
based on their physical and chemical nature, as below:
Air emissions;
Stationary point source emissions;
Area and fugitive source emissions; and
Mobile source emissions.
Wastewater;
Process / industrial wastewater;
Sanitary wastewater (sewage); and
Surface runoffs and liquid hazardous wastes
Solid wastes;
Non-hazardous industrial solid wastes;
Domestic wastes including kitchen wastes; and
Hazardous wastes - Solid hazardous wastes
Noise; and
Accidental Releases
Gaseous Releases into the atmosphere; and
Liquid spills and leaks on land.
The construction and operation phases of the Project are discussed with regard to waste generation,
handling, storage, treatment and disposal. The waste management plan including the
recommendations for environmental mitigation and monitoring is included in the EMP, which is
presented as a separate document, as per SEU requirements.
The environmental releases during the construction phase will include emissions from the DG units,
emissions from construction equipment and vehicle, movement of transport vehicles, dust generation
from earthworks, sewage generated at site and camp, waste chemicals generated at site, maintenance
wastes, and metal, wooden and plastic scraps, etc. These releases are discussed in the following
sections.
5.1.1.1 Sources
Major sources of air emissions during the construction phase include land clearing activities,
excavation, DG units used at site for power generation, construction equipment, vehicles and the fuel
storage tanks. Pollutants released from these sources include NOx, SO2, CO, unburned HC (UHC),
PM and VOCs. The air emissions sources and the nature of air emissions due to the various
construction activities are presented below in Table 5-1.
Table 5-1: Air Emissions during Construction Phase
As described in the table, the main source of air emissions during the construction phase is the
combustion of diesel, which will be used in the construction machinery, DG units and vehicles. CO2,
will be the major product of this combustion along with CO, UHC, NOx, SO2, and PM10. CO and
UHC are a result of partial combustion of diesel, as no engines are 100% efficient. NOx occurs as a
result of the thermal oxidation of nitrogen present in the air as well as diesel. About 90 to 95 % of the
sulphur in the diesel will be oxidized to SO2, while the rest may get further oxidized to SO3, which
may subsequently be converted into sulphate. PM10 is formed due to the ash content in the fuel as well
as any particles, such as soot, etc. during combustion.
Due to the complexity and variety of construction activities, quantification of the pollutants that will
be emitted during various construction activities is difficult at present. However, based on theoretical
assumptions and using USEPA AP-42 emissions factors, air emissions from stationary and mobile
sources are calculated. The expected emissions from the DG units are given in Table 5-2 below. A
summary of the assumptions made during the calculations are as given below:
One DG with a rating of 450 kVA would be working for a period of 8 to 10 hours/day during the
entire construction period; and
The exhaust gas flow rate and temperature and stack dimensions for the above DG sets are taken
from specifications for Caterpillar DG sets5.
6
Table 5-2: DG Emissions from Construction Phase
As per the recent US EPA guidelines (April 2006), the particulate matter estimation (using
conventional AP-42 vehicular emission factors) does not fully account the emissions of dust. It has to
be estimated separately using AP-42 emission factors when the vehicles move on paved/unpaved road
within the project site.
Particulate emissions occur whenever vehicles travel over a paved surface such as a road or parking
lot. Particulate emissions from paved roads are due to direct emissions from vehicles in the form of
exhaust, brake wear and tire wear emissions and re-suspension of loose material on the road surface.
Re-suspended particulate emissions from unpaved roads originate from, and result in the depletion of,
the loose material present on the surface (i.e., the surface loading). In turn, that surface loading is
continuously replenished by other sources. Since the project is within a developed industrial area
movement of traffic over unpaved road is minimum and will be restricted to areas within the project
site.
Dust emissions (PM2.5, PM10 and Total Suspended Particular Matter) were calculated as per the
USEPA AP-42 emission factors. The average dust generation at project site due to project related
traffic during 10 hour per day working scenario is given in Table 5-3 and the detailed calculation is
given in Appendix G.
5
http://www.cat.com/cda/files/319291/7/C27+680+ekw+Prime+T2_EMCP4.pdf
6
http://www.epa.gov/ttnchie1/ap42/ch03/final/c03s04.pdf
Table 5-3: Dust Emissions from Vehicle on Unpaved area within Site after water spraying
For other pollutants, the vehicular emissions at project site are estimated using AP-428 emission
factors, (Appendix H) and the results are presented in Table 5-4.
Table 5-4: Gaseous Emission from Vehicle Travelling at Site
It is to be noted that the above releases are very negligible and short term in nature and will be present
only for limited periods when the associated activities, as discussed above, are performed.
The engines and road vehicles will be maintained in accordance with the manufacturer’s
specifications and the emissions will be limited by ensuring equipment usage only when necessary.
Engines for construction machinery and vehicles will be of standard design and the engine emissions
will be released into the atmosphere through standard exhaust pipes. The emission rates of pollutants
will be controlled through proper engine tune-up. Similarly, the DG sets used will also be of standard
design. The dust risings will depend on the nature of the surface and the weather conditions. Water
sprinkling will be done to reduce dust emission. Excavated soil and rocks will be primarily used for
backfilling within the project site. Excess soil will be transported to nearest municipal dump site
(Sohar). Stockpiling for an extended period of time is not envisioned during the construction period.
The washings may contain some SS, O&G, and traces of chemicals and organic compounds; while
waste oil, oil sludge and chemical cleaning solutions etc. are hazardous liquid wastes. The sewage
generated from the domestic use of water on-site and off-site will contain both suspended solids and
dissolved solids (TDS), with relatively high biochemical and chemical oxygen demand (BOD / COD).
7
Dust Concentration is kg/d after water spraying on roads
8
http://www.epa.gov/oms/models/ap42/ap42-h7.pdf
The liquid effluent sources, their nature and typical characteristics for the construction phase are
summarized below in Table 5-5. With respect to the characteristics of the effluents, it is difficult to
determine the chemical composition of the various effluent streams. Therefore, first order
approximations for the characteristics (before any treatment) are presented in the same table.
Table 5-5: Wastewater Stream during Construction Phase
Nature of Expected
Wastewater Source of Generation Expected Quantity
Wastewater Composition
Kitchen, toilets and Continuous SS<250 mg/L
Sewage – On-
wash rooms located Contains SS, O&G< 100 mg/L
site and Off- ~220m3/d9
onsite; construction O&G, BOD and BOD< 200 mg/L
site
camps located off-site COD COD< 500 mg/L
Virtually free of
Spent Hydro Hydro testing of pipes
One occurrence any NA
test Water and process vessels
contaminants;
Periodic water-washing
Intermittent;
Machinery of construction SS < 100 mg/L;
May contain grit, Cannot be estimated
washings machinery, vehicles and O&G < 100mg/L
SS and O&G
floors
Chemicals, e.g.,
Chemical
Washing of machineries acids, alkalis,
cleaning COD < 400 mg/L Cannot be estimated
with cleaning solutions detergents,
solutions
solvents, etc.
Rarely
Drainage of rain water Free of pollutants
No pollutants
Surface runoff over area within the unless accidentally Depends on Rainfall
expected unless
project site contaminated
contaminated
The following measures will be implemented for the segregation, treatment and disposal of the above
wastewater streams.
Washings: Construction equipment and vehicles will be periodically water-washed to remove any
accumulated dirt. No detergents will be used. Washing will be carried out in a designated area at site
and the wash water will be collected in a sedimentation tank. The clarified effluent will be sent to the
municipal STP for treatment and disposal. Alternatively, the contractors may wash their machinery
and vehicles in their established garages located off-site.
Hydrotest Water: Hydrotesting will be carried out for identifying and eliminating any leakages /
opening in the process vessels, pipeline framework and the plumbing and chemical additives such as
corrosion inhibitor, oxygen scavenger, etc. may be added to the hydrotest water to prevent internal
corrosion. However, biodegradable additives with low toxicity will be used. Consequently, the spent
hydrotest water may contain traces of oil, SS and chemicals. The used hydrotest water will be
collected and reused for multiple tests, as far as practicable. Further, the hydrotesting procedure will
be planned such that the test water is allowed to remain inside the vessel or pipeline for minimal time;
thus reducing the requirement of using additives in the hydrotest water.
The spent hydrotest water from the final test will be collected in a tank or a lined evaporation pond
and checked for compliance with Standard A-2 prescribed in RD 115/2001. If the water complies with
9
Assuming an average manpower of 1000 and per capita waste generation of 220L//day
the standard then it will be used for land discharge activities on obtaining requisite approvals from
MECA; else it will be let to dry out in a lined evaporation pond. After the water has evaporated , the
lining will be folded and sent for disposal to Orpic’s Hazardous waste facility. The hydrotest water
disposal plan will need to be submitted to MECA well ahead of the activity to obtain the requisite
approvals
Sewage: Sewage generated from the various on-site toilets, kitchens and wash rooms located in the
project site will be collected through underground pipes into a holding tank. From the holding tank,
the sewage will be routed to the STP operated by Majis Industrial Services (Majis).
In addition to on-site sewage, off-site sewage will also be generated from labour camps where the
sub-contractor staff involved with the project construction will be accommodated. Sewage generated
in each labour camp will be transferred to the municipal STP.
Surface run-off: Storm water, unless contaminated, will be allowed to flow out from the construction
area. All areas where hazardous materials and wastes are stored will be appropriately bunded to avoid
surface run-offs to prevent accidental contamination. Normally, runoffs from hazardous substance /
waste storage area will be collected within the secondary containment that will be provided around the
area. This potentially contaminated run-off will be routed to a collection sump from where it will be
pumped out for transport to the municipal WWTP.
Solid and liquid hazardous wastes include spent oils, wastes from on-site fabrication such as surface
blasting materials, paints, etc., , containers of paints/solvents/oils, used batteries, contaminated soil
from oil spills, hazardous waste spillage, etc. Most of these cannot be recycled and will need to be
stored / disposed to a licensed off site location.
Contaminated soils generated due to accidental spillage/leakage of oils, liquid chemicals, solvents and
paints will be stored in bunded areas and on impervious flooring to prevent leaching of hazardous
materials and contamination of land and water. Unused paints, chemicals and miscellaneous materials
such as batteries will be considered for returning to supplier, recycling or reuse either onsite or offsite.
Contaminated containers/packaging material such as oil drums, paint drums and chemical packaging
materials will be sent to authorized recyclers. Such quantities cannot be estimated, however,
experienced contractors typically include provisions (as per the MSDS and waste characteristics) for
safe handling and storage of such wastes. The details on the type, handling, storage and disposal of
solid waste are presented in Table 5-6.
Table 5-6: Waste Generation during Construction Phase
5.1.4 Noise
The main sources of noise and vibration on site during the construction period will be construction
machineries such as bull-dozers, excavators, compactors, which generate significantly high noise
level. In addition, DGs used for power supply also produce high noise level. The vehicles used for the
transport of materials and men to the site will also generate significant noise along the route. Table
5-7 below presents the typical noise levels expected from various construction machinery and
activities along with the duration of operations.
Table 5-7: Typical Noise Level
It is difficult to quantify noise emissions during construction activities as the type and numbers of
potential noise sources are not available at present. However noise level will be maintained in
compliance with MD 79/94 (Regulations for Noise Pollution in Public Environment) and MD 80/94
(Regulations for Noise Pollution in Work Environment). If the workers are likely to be exposed to
continuous noise level exceeding 85dB(A), they will be provided with appropriate personal protective
equipment (PPEs) such as ear plugs and ear muffs, as required by MD 80/94. Machineries will be
provided with suitable noise dampening agents like mufflers, enclosures, etc. to minimise noise at
source. High noise generating activities will be carried out in the day time to the extent possible.
The clean-up of accidental spills generates contaminated soils, rags, etc. Contractors typically provide
adequate spill containment systems, remediation plans and maintain proper practices of storage and
handling of materials, which minimizes accidents. The hazardous materials will be stored in
segregated, enclosed and protected areas in such a way as to store materials, which are flammables,
corrosives, toxic, etc., separately, as per guidance in the MSDS. Such materials will be stored in
enclosed and roofed storage areas to the extent feasible in order to prevent from rains and runoffs
from storage areas.
5.2.1.1 Sources
The significant sources of air emissions – stationary as well as area – during the PC plant operation
phase are various process units, heaters, incinerators, flare system, power plant, emergency DG, tanks,
pipe fittings, storage tank farm etc,. The emissions from the stationary point sources can be either
continuous or intermittent. It may be noted that during the operation phase of the PC, the stationary
point sources will be the primary contributors to air emissions. The area sources will be less
significant when compared to the stationary point sources, while the mobile sources will be
insignificant.
Air emissions from the stacks attached to combustion systems, which include gas turbines, furnaces,
boilers and flares, are the products of combustion of the fuels and off-gases. While the main products
of combustion are carbon dioxide and water vapour, the emissions will also consist of a number of air
pollutants including NOX, SO2, CO, un-burnt HC and PM10. Among these, NOX, CO and to a lesser
extent HC are expected to be significant. SO2 and PM10 are not expected to be significant since mainly
gaseous fuels with negligible sulphur content are used.
Air emissions from stacks attached to incinerators will also consist of NOX, SO2, CO, un-burnt HC
and PM10. Pollutants such as HCl, HF and dioxins, which are normally associated with incinerators,
will not be released since no halogenated substances are incinerated in any of the incinerators.
As explained in Chapter 3, the proposed PC will have five types of flare systems within the plant viz.
main wet flare, one main cold flare, one spare storage cold flare, one spare storage wet flare and two
cryogenic flares ( A and B) for flaring of different type of vents from different process units. The
vent gases from the raw pyrolysis gasoline, quench water, C6-C7 cut storage tank, wastewater
collection tank spent caustic and effluent tank, benzene contaminated collection tank and waste gas
from SCO unit, DGF unit will be routed to a thermal incinerator as these contain nitrogen with toxic
components, hydrocarbons etc.
5.2.1.2 Quantities
Emissions from the incinerator, GTs, steam boilers and the flare will be products of combustion of FG
(treated off-gas) and NG. While the main product of combustion will be CO2 and water vapour,
several air pollutants including NOX, SO2, CO, UHC and PM10 will also be emitted. Table 5-8 gives
the details of stacks in the process plant and utilities and emission rates of the pollutants in the stacks
considered for the air dispersion modeling. It should be noted that emission scenarios under plant
upset conditions are not considered for assessment of impacts on air quality. Such scenarios exist only
under emergency situations.
Table 5-8: Emission Rate of Pollutants from Stacks
SCU
1 Heater 26.4 3.28 124.2 0.1 3.8 0.2 7.6 0.25 9.5 1.25 47.3
Stack 1
SCU
2 Heater 26.4 2.68 101.5 0.1 3.8 0.2 7.6 0.25 9.5 1.25 47.3
Stack 2
SCU
3 Heater 26.4 3.55 134.5 0.1 3.8 0.2 7.6 0.25 9.5 1.25 47.3
Stack 3
SCU
4 Heater 26.4 3.55 134.5 0.1 3.8 0.2 7.6 0.25 9.5 1.25 47.3
Stack 4
SCU
5 Heater 26.4 3.55 134.5 0.1 3.8 0.2 7.6 0.25 9.5 1.25 47.3
Stack 5
SCU
6 Heater 34 4.37 128.5 0.1 2.9 0.2 5.9 0.25 7.4 1.25 36.8
Stack 6
SCA
7 Incinerator 0.9 0.08 88.9 0.02 22.2 0.03 33.3 0.01 11.1 0.05 55.6
1
SCA
8 Incinerator 0.9 0.08 88.9 0.02 22.2 0.03 33.3 0.01 11.1 0.05 55.6
2
SCA
Power
9 118.4 11 92.9 2.6 22.0 3.7 31.3 0.7 5.9 7.3 61.7
Generator
1st Stack
SCA
Power
10 118.4 11 92.9 2.6 22.0 3.7 31.3 0.7 5.9 7.3 61.7
Generator
2nd Stack
SCA High
Pressure
11 34 0.07 2.1 0.02 0.6 0.4 11.8 0.15 4.4 1.25 36.8
Flare
Stack
SCA Low
Pressure
12 34 0.07 2.1 0.02 0.6 0.4 11.8 0.15 4.4 1.25 36.8
Flare
Stack
13 Pygas 20 0.07 3.5 0.02 1.0 0.04 2.0 0.25 12.5 1.25 62.5
14 Boiler 1 26.4 3.76 142.4 0.1 3.8 0.2 7.6 0.25 9.5 1.25 47.3
15 Boiler 2 26.4 3.76 142.4 0.1 3.8 0.2 7.6 0.25 9.5 1.25 47.3
16 Boiler 3 26.4 3.76 142.4 0.1 3.8 0.2 7.6 0.25 9.5 1.25 47.3
It must be noted that each of the sources mentioned in the above table will have a dedicated stack, i.e.,
will have 14 continuously emitting stacks. Besides point sources, the PC Plant will also have area
emission sources, such as the process area, oil, fuel, chemical storage tanks etc.
NOx emission from the cracking furnaces of the LPP petrochemical complex will have to meet the
requirements of Oman regulation MD/118(2004), i.e. emission limit from boilers and heaters of 150
mg NOx/Nm3.
The cracking furnaces will be capable of operating within an overall 150 mg/Nm3 limit.
For normal cracking modes and normal fuel gas composition, the NOx emission is guaranteed to be
150 mg/Nm3, corrected to 3% O2 and dry basis. This operating mode normally is about 95% of the
furnace operation time, the remaining 5% is required for Decoke mode, TLE Polishing, and Hot
Steam Standby (HSS) mode. The latter mode is to enable sufficient time for furnace switch over.
By nature of the operating mode, NOx actual absolute emission rate will decrease during the Decoke,
TLE Polishing and HSS modes while the NOx concentration corrected to 3% oxygen will increase for
these off-line modes.
NOx emission values from the different furnace types have been evaluated for all operating modes
and are summarized per furnace type, as well as for all furnaces in operation for an average one year
cycle. Scenarios have been developed both for the normal fuel gas composition range as well as for a
fuel gas with hydrogen content up to 50 mol%.
Cracking Operation
Decoke Operation
TLE Polishing (short or long)
G-S000-5240-003 HMR Consultants
June 2015 5-11
Petrochemical Plant Sohar Environmental Impact Assessment Report
Orpic and CB&I HMR #3817
High Steam Standby (HSS) mode; basically an idle mode, including period for
switchover from operation to decoke mode and thereafter back to operation mode.
With a normal furnace run length of 60 days for the cracking mode, the typical overall cycle time is
63-70 days, depending on the number of days the furnace is kept in HSS mode. Examples are given in
this document are based on a total 3 days HSS period, unless indicated otherwise. Total cycle length
for these cases will be 65 days. A typical operation cycle for a cracking furnace is illustrated in below
figure.
For the NOx emission three indicators are shown. The “expected NOx” value is the NOx
concentration at the stack, on a dry basis. The second curve shows the NOx concentration as corrected
to 3% oxygen content to provide a uniform basis.
All these figures are based on dry flue gas; actual measured values will be lower due to presence of
moisture. The off-line operating modes have a high amount of excess air, therefore measured NOx
emission corrected to 3% O2 is high as well.
The third trend is the NOx mass flow. Note that where the NOx concentration increases outside the
normal cracking operation, the mass flow of NOx decreases in these off-line operating modes. The
normal cracking mode of operation thus has the highest NOx emission rate.
The average NOx emission for one full furnace cycle as illustrated above is summarized for both
furnace types as below:
Although during the off-line modes the NOx concentration peaks above the 150 mg/Nm3, the
average concentration for the full (65 days) furnace cycle is well below the 150 mg/Nm3. On a
monthly basis, every other month (i.e. a month that includes the normal decoke/polishing/HSS
sequence peak values) the furnace average NOx emission (at 3%O2) may tip on the 150 mg/Nm3
limit, but the month thereafter the average will be as low as for normal cracking operation mode.
Storage Tanks
The storage tanks will have vents to facilitate release of the VOCs collected within the tank into the
atmosphere. The VOC emissions that are expected from the tank farms, product storage area and
loading areas are presented in Table 5-9. The estimations have been made by using US EPA’s
TANKS 4.0 software tool for estimating emissions from organic liquids in storage tanks.
Table 5-9: Storage Tank Details and Expected Emissions
Total
No. of Dimensions Working
# Source Tank Type Emissions
Tanks m Volume m3
t/y
Feed Storage
1 Methanol 2 Floating roof 17.5 x 12 2,589 14.67
The expected total VOC emissions from the storage tanks are 208.2 t/y. However it is to be noted that
the tanks will be connected either to the flare or the incinerator thus minimizing environmental
impacts from tank emissions.
Transport vehicles for people and material will constitute mobile emission sources. However,
emission contribution from these sources will be negligible in comparison to the other continuous and
fugitive emission sources. Furthermore, the emissions from the mobile sources are difficult to be
quantified or estimated at the present stage of the project.
In order to minimize the air emissions, a number of state-of-the-art technologies will be integrated
into the process. The various pollution control measures that will be incorporated are described below:
Detailed control measures are explained in Chapter 6 – BAT Analysis.
Heaters and Incinerator - The heaters and incinerator will employ the low-NOX burners in order to
minimize the release of NOX into the atmosphere.
Gas Turbine and Steam Boilers - Since NG will be used as fuel, NOX is the major concern with
respect to gas turbines. The fuel will have very low Sulphur content (5ppm), considering this fact SO2
emission will be negligible and is not of concern. High temperature will result in high NOx
concentrations and therefore it is expected to be temperature controlled combustion. However,
sufficient excess air will be maintained which will minimize the CO and UHC concentrations.
Further, fuel will be gas, which will further reduce the chances of UHC emissions. The UHC emission
will not be significant due to the use of gaseous fuel and the nature of combustion and the associated
controls. None of the emissions are expected to exceed the limits prescribed in MD 118/2004. NOX
emissions will be controlled by the use of Dry Low NOx (DLN) combustion system.
Flares - In order to minimize pollution from the flare, it is proposed that the flare will be designed to
ensure that the smoke opacity will not be higher than Ringlemann 1. The flare will have continuous
pilot flame to prevent any cold venting, and will combust more than 99.8 % of HCs. In order to
reduce thermal NOX, the fuel-air ratio will be optimized and will be steam assisted.
Spent caustic wastes containing high COD, TDS, sulfides, mercaptides, free caustic, polymeric
organic compounds and other aromatics will be oxidized to convert organic compounds to CO2 and
sulphates.
Area Sources -The storage tanks for feedstock, product and intermediates will be provided with
nitrogen blanketing and floating roof. Further the vent gas from the storage tanks will be routed
to the vent gas incinerator.
5.2.2 Wastewater
The liquid wastewater sources in the project during normal operation may be classified into groups as
below:
Process water from various utilities in the complex – continuous and contaminated;
Containment water - wastewater from spills, general plant services, GT and other utility
washings, floor washings, fire events, rainwater run-off through process and utility areas, etc.)
– Intermittent release, quantity and quality will vary;
Storm water run-off (segregated from run-off through process and utility areas) – Intermittent
release, quantity and quality will vary;
Sewage;
The exact quantities and characteristics of wastewater that would generate during operation phase are
not known at this stage. Approximate quantities and the characteristics of the continuously flowing
streams are presented below in Table 5-10.
Table 5-10: Wastewater Generated during Operation Phase
The various process stream generated in the PC Plant will be collected in respective sewer system and
routed to the WWTU as discussed in Section 3.11.3 and Section 3.12.
Waste Type Sources of Generation Method of On-site Storage and Final Disposal
Non-Hazardous Waste
Domestic waste, office Onsite non-industrial Collected in waste skips and disposed to the nearest
waste and general waste activities approved landfill site
Non burnable/ non Collected and disposed to the nearest approved
From gas phase PE plant
recyclable waste landfill site
General non-hazardous From Utilities/ Power Collected and disposed to the nearest approved
wastes plants landfill site
Wood Stockpiled and sold to local approved dealers
Metal scrap From plant and workshop Stockpiled and sold to local approved dealers
From solution and gas
phase PE plant
Scrap polymer Sold as low grade polymer
From slurry Polypropylene
and gas phase PE plants
Spent bag filters From silos
Collected and disposed to the approved landfill site
Hazardous Waste
Skimmed oil from
LLOD basin, WWCT,
Intermittent – Hazardous Collected and routed to liquid incinerator unit for
Oily sludge storage tank,
liquid incineration
DGF skimming,
Benzene/MTBE WWCT
Collected in mobile oily sludge container
Dewatered oily sludge WWTU
Incinerated
Sludge generated from Collected and to be sent to be’ah facility
Crystallizer
caustic treatment
Waste Type Sources of Generation Method of On-site Storage and Final Disposal
Miscellaneous solid Intermittent~ •
wastes from all process Hazardous due to Disposed off by incineration in solid waste
plants and utilities hydrocarbons and other incinerator
organic matter
Waste oils and oily
Stored in segregated in bunded areas, waste oil sent
sludge, waste chemicals,
Intermittent to authorized waste oil recyclers
solvents, waste paints,
Hydrocarbon and other Waste solvents and chemicals, if feasible, will be
used cotton waste, etc.
chemicals sent back to the suppliers or disposed of in
from plants and
maintenance workshops accordance with MSDS
Cokes from cracking
SCU Plant
ethylene unit;
Polyethylene and
PE plant,
polypropylene powder;
Collected and transported by truck to solid waste
Dewatering sludge from
incinerator, except Polypropylene and polyethylene
wastewater treatment WWTU
powder will be sold as low polymer grade and do
unit; and
not send to the incinerator for incineration.
Spent activated carbon
from filters.
Cokes from cracking
PE plant
ethylene unit;
Spent filter media
Ethylene and polyethylene
(flammable) and oil Routed to waste incinerator
plants
absorbents
Intermittent - From Sludge collected pumped to sludge dewatering unit;
Sludge from WWTP
dewatering operation Dewatered sludge disposed of by incineration
Disposed at nearby landfill site stored as hazardous
Waste catalysts (non-
PE plant waste. Alternatively, could be sold to catalyst
flammable)
recyclers
Will be stored in enclosed and dedicated storage
Acetylene hydrogenation
Spent catalysts areas at site
catalysts in ethylene plant
Returned to manufacturer / reclaimer
Containers of hazardous Either decontaminated for disposal as non-
Metal and plastic containers
materials (oil drums, hazardous waste or stored on site in a covered area
of hazardous consumables
chemical drums etc.) and disposed at be’ah facility
5.2.4 Noise
The major noise generation sources during the operational phase will be gas turbines, steam
generators, flares, incinerators, WWTU etc. The typical noise levels expected from these sources are
presented in Table 5-12.
Table 5-12: Noise Generation During Operational Phase
Since the equipment and machineries will be of latest technology, it is expected that all the high noise
producing equipment will have inherent noise controls. Moreover, for machineries like GTs, steam
generators and compressors, mufflers, acoustic enclosure and other suitable acoustic treatments will
be employed. All the high noise areas will be identified and workers engaged in those areas will be
provided with either earplug or ear muff, depending on the requirement. Furthermore, Orpic has
planned Green Belt with appropriate mix of trees and shrubs along its site fence line to ensure
additional noise attenuation. Detailed noise mitigation measures and controls including monitoring
requirements have been included in the EMP presented separately.
The storage facilities will be designed to reduce the possibilities of any leakages or failure of the
facilities. Suitable material of constructions will be selected for building the storage tanks and drums.
Furthermore, the storage facilities will be provided with preventive measures such as secondary
containment, firefighting systems, etc. to prevent accidents due to any leakages from the storage
facilities.
Considering the above, the probability of failures / leakages of the storage tanks will be low. The risk
management for accidental release on hazardous substances will be developed based on a quantitative
risk assessment study that will be conducted as part of the project FEED.
6 ANALYSIS OF ALTERNATIVES
The development, design and construction of PC plant in project site involve several major
management and technical decisions, some of which will have significant influence on the
environmental impacts from the project. In this section, the environmentally critical decisions are
identified and the justification for their selection is discussed. For the development and design of the
project, the following aspects are identified to be environmentally significant:
No project alternative
Analysis of BAT.
For the construction phase of the project, the following aspects are identified to be environmentally
significant:
Sourcing of utilities;
Sourcing of fuels;
This Project is part of the Sultanate program to reduce its reliance on the export of crude oil and
natural gas in developing its downstream industry to retain more added value in the country. Further
this project brings to Oman, state-of-the-art petrochemical technology, world-wide operational
expertise and marketing know-how. The construction phase is expected to last for about 24 months.
The operational life span of the project will be 30 years. The Project is also expected to facilitate the
significant development of downstream industries in Oman that convert polyethylene to a range of
industrial and consumer products. This could potentially create further employment opportunities for
local populations.
In the event of no project alternative, the project site will continue to be a plot reserved for future
development by SIPA. Although the no project option will avoid any adverse impacts associated with
the construction and operation of the project, this option will not allow for the potential industrial and
economic prospects of the area. The project will initiate both short and long term employment and
business opportunities along with development in the area. The project contractors and sub-
contractors are expected to have approximately 1000 - 2000 people involved in construction. The
project once in regular operation, is expected to employ over 250-300 persons.
The site is an approved industrial site, free of any settlements, free of any surface or sub-
surface structures, not used for any agricultural or fisheries activity and free of surface or sub-
surface contamination.
The project site is predominantly plain and levelled thus reducing the cost for site preparation.
The site lies at the southeast corner of SIPA, adjacent to Sohar Refinery site and close to the
port and SIA’s common seawater intake and outfall system.
The various utilities required for the development of the plant like power, water, natural gas,
etc are available within the SIPA.
Proximity to the port minimises the costs and environmental impacts associated with import
of materials and export of products.
Proximity to the refinery permits direct pipeline transport of refinery off-gases for use as
auxiliary fuel;
Sohar is an industrial town and as such the need for skilled workers can be easily met from
the available work force in Sohar and other similar units in and around the Arab countries to
some extent.
The industrial area is placed strategically close to proposed Al Batinah Express Way and Al
Batinah Railway, which will ensure great connectivity of the site in future. Further it is
sufficiently connected with the existing Al Batinah High Way, which is traversing through the
southern side of the industrial area as shown below ;
1. Two (2) independent Gas Turbine Combined Cycle (GTCC) units, each with gas turbine and
steam turbine including grid connection for back-up power.
2. An integrated unit, with two (2) gas turbines and single steam turbine.
3. Integrated unit, with import of SHP steam from the auxiliary boilers to produce more power.
4. Integrated unit, with import of SHP steam from the auxiliary boiler to produce more power
via two (2) steam turbines to improve reliability.
5. Integrated unit, with import of SHP steam from the auxiliary boilers and export of extraction
steam back to the Olefins complex steam system.
6.3.1.1 Two Independent GTCC Including Grid Connection for Back-Up Power
Each unit will have a gas turbine with generator. Natural gas is used to drive the gas turbine and the
hot exhaust is sent to the HRSG (heat recovery steam generator). The steam system shall be of
standard design including a condensing steam turbine. The steam turbine expands the superheated
steam to wet vacuum. The steam turbine drives an independent generator.
Because both the units are fully independent, the reliability is the highest in this option. Also it is
possible to stop 1 unit for inspection and maintenance, while the other unit remains in full operation
together with the connection to the OETC grid. This configuration tends to be the most flexible with a
reliable connection to the grid.
6.3.1.2 Two Gas Turbines and Single Steam Turbine with Grid Connection
An alternative option is two (2) gas turbines sharing a single HRSG. A single steam turbine and a
single vacuum condenser is present with a grid connection for back-up power. This configuration is
called the 1 * (2+1) option, which contains 3 machines and 3 generators.
The gas turbines are less reliable and less available than the steam turbine and hence the numbers of
the gas turbines are doubled in this option. The reliability, availability and flexibility are less than the
previous option, but due to partial economy of scale, the equipment costs are lower. However, the
probability of trip of the Olefins complex, due to trip of the single steam turbine and consequently of
the gas turbines, is higher in this option.
Intermediate Stack
An alternative sub-option is with 2 gas turbines, a single HRSG and a single steam turbine and
including a grid connection. This option is without intermediate trip stack. As a result, in case of trip
of the HRSG or steam turbine, the total plant will trip, because the gas turbines also have to be
tripped. In case of presence of an intermediate trip stack, the hot exhaust of the gas turbines can be
sent to atmosphere instead of to the HRSG. As a result the gas turbines can remain in operation at
maximum 107MW. Thus the power only reduces from 150MW to 107MW and the remainder can be
imported via the grid connection, being 43MW. This is less than the anticipated 75MW as in the
previous case. However, a state-of-the-art combined cycle unit has a very reliable steam and
condensate system, including a very reliable steam turbine. This steam system is much more reliable
than the gas turbine which indicates that standard state-of-the-art combined cycle units hardly increase
their reliability with a trip stack.
This integration option makes use of the spare capacity of the SHP steam of the auxiliary boilers of
the Olefins complex with a connection to the external power grid for back-up. Two (2) gas turbines
are present fired by natural gas to maximize reliability. The hot exhaust flows to the HRSG via an
intermediate trip stack. In the HRSG steam is produced with the same quality as the excess SHP from
the auxiliary boilers. This SHP steam is expanded to vacuum conditions and does not need a reheat (in
the HRSG). This steam turbine is more expensive than the 1 * (2+1) configuration, because much
larger capacity steam turbine generator system is required. The main advantage of this configuration
is that more power can be generated.
Two parallel steam turbines, each with its own air cooled vacuum condenser, are more reliable than a
single steam turbine with single vacuum condenser. The total steam turbine capacity is116 MW. Thus
each of the two (2) steam turbines has a capacity of 58MW. In case of tripping of one such steam
turbine, the power plant output could still be 2 * 54 + 58 = 166MW, which is more than the target
capacity of 150MW. Thus tripping of one such steam turbine trip will not trip the Olefins complex. In
case an auxiliary boiler trips, the connection to the external power grid can be used as back-up.
Above described steam integration option is based on import of SHP steam to produce electric power.
It is also possible to import SHP steam and export the extraction steam(s) back to the Olefins
complex. The possible extraction levels are HP, MP and LP. However, exporting HP is the most
effective, because this superheated HP steam could be used for driving even more steam turbines at
the Olefins complex. Evidently the smaller the steam turbine and the lower the pressure and the
superheat, the lower the efficiency will be.
Integration options with the steam system of the Olefins complex are found to be unreliable with
respect to the occurrence of trips, resulting in unacceptable production losses at the Olefins complex,
even with a reliable connection to the external power grid for back-up power. In addition, investment
cost will be increased due to the use of super high pressure (121 barg) steam as generated in the
Olefins complex. After comparison of various options above taking into account capital expenditure
(capex), efficiency, reliability and availability, Orpic is proposing the use of two independent GTCC
with grid connection for back-up as the most optimum configuration
Two alternatives for sourcing desalinated water are available. One is to import from an off-site facility
and the other is to construct an exclusive on-site facility. It is not feasible to source desalinated water
from any existing or under-construction desalination plants. Moreover, in view of fluctuating water
demand and operational flexibility, it is determined that construction of an on-site desalination plant is
the only feasible option.
Membrane separation and evaporation are the only two processes that are suitable for commercial
scale desalination of seawater. In the membrane separation process, a semi-permeable synthetic
membrane is used to filter out the salt ion from the seawater to produce fresh water. The membrane
separation processes for desalination of seawater include reverse osmosis (RO) and electro dialysis.
Generally, electro-dialysis is not suitable for large desalination plants.
In the evaporation process, thermal energy is supplied to evaporate water from brine. Both processes
result in the generation of concentrated seawater (brine reject) as a waste stream. The evaporation
processes for desalination of seawater include multiple-effect distillation (MED), multi-stage flash
evaporation (MSF) and vapour compression (VC).
With reference to environmental aspects, both processes generate concentrated brine as reject water,
which needs to be disposed back into the sea. In membrane processes, the reject stream will be at
ambient temperature while in thermal processes the brine will be heated. In terms of fuel consumption
(direct and indirect) per unit produced water, membrane processes (which use electrical energy)
consume more compared to thermal processes, thus resulting in more emissions
For the proposed project MED technology is determined to be the best option based on capital and
operating costs. MED technology will consist of two identical trains (one operating, one on stand-by)
in which Low Low Pressure Steam (LSS) is used to evaporate sea water in multi effects. Sea water is
filtered to remove undesirable particles before feeding into the desalination process. Sea water flows
through tube bundles in MED the condenser as cooling media. Condensed water from all effects is
collected in the last chamber called condenser where non-condensable gases are removed by means of
an ejector and desalinated water is pumped as product to tanks.
Air cooling;
In air-cooling systems, atmospheric air is passed over the external heat transfer surface to remove the
heat. When direct environmental effects are considered, air-cooling is the best alternative of the three.
However, cooling systems based on air-cooling generally require very large heat transfer area and is
hence unsuitable in many cases.
In re-circulating water cooling systems, freshwater is circulated through a heat exchanger, the warm
outlet water is cooled in cooling towers and then recycled along with required make up water. Make
up water is required to compensate for water loss due to evaporation in cooling towers and cooling
tower blow down. Re-circulating cooling water systems require relatively low heat transfer surface,
but have environmental consequences due to freshwater consumption, use of chemicals (anti-scaling
and anti-corrosion) effluent treatment and disposal.
In once through seawater cooling systems, seawater is passed through a heat exchanger and the warm
outlet water is discharged into the sea. There is no make-up water requirement. The outlet seawater
will be typically at about 10C warmer relative to the receiving water body. This has potential for
marine environmental impacts, especially thermal pollution, and requires careful design of marine
outfall.
The proposed plant utilise a cooling water unit which will be a closed pump around system. The
cooling water returned from the various users will be cooled down against sea water in five plate heat
exchangers. The closed cycle cooling water system will be maintained with minimal water losses.
Therefore, natural gas is selected as the primary fuel for the project. As a backup fuel, diesel oil with
<1.0% sulphur is considered. A tie-in point downstream of the existing gas intake station will be made
to supply HP NG from Sohar Refinery for the PC plant. The HP NG will be heated up in Natural Gas
Receiving Heater prior to the pressure reduction to avoid hydrate and liquid droplets and mist
formation. Diesel oil for back up fuel will be sourced from Sohar Refinery.
Currently, the best practice in the world for minimization of CO2 generation is through source
reduction, which includes
(i) Selection of fuel that contains less carbon content per unit energy content; and
These two principles for CO2 reduction are applied in the design of combustion systems used in PC
Plant. These are highlighted below:
Use of natural gas as the primary fuel, which has the lowest CO2 emission factor among all
fossil fuels.
Low NOx combustion systems will be used for NOx emission control. As discussed in the preceding
section, care should be taken such that NOx reduction is not achieved at the expense of higher CO and
unburnt HC emissions. The following alternatives are available for low NOx emissions:
All the above systems work on the similar principle of reducing the flame temperature to minimise
thermal NOx. Water or steam injected into the combustion system quenches the flame temperature.
While these designs are relatively less expensive compared to DLN design, they require significant
quantities of highly purified water. Considering that there are no natural sources of fresh water at the
project site, DLN burners are selected for all the major combustion systems, viz., gas turbines, steam
generators and furnaces.
Emissions control using DLN burners relies on multiple combustion staging to optimise fuel-air
ratios. This is achieved through premixing fuel and air in various combinations, depending on the
desirable operating temperature. The emission control system regulates the division of the fuel among
the multiple combustion stages according to a schedule that is determined by a calculated value of the
combustion reference temperature. The control system also monitors the actual combustion system
operation to ensure compliance with the required schedule.
The major utilities required during the construction phase of the project are power, non-potable water
and drinking water.
6.5.1 Power
The alternatives that may be considered are import from the local grid or the use of on-site diesel
generators. The first option is better from environmental considerations. Therefore, it is proposed,
when feasible, to source required power from the local grid, which has sufficient generating capacity
to meet the required construction demand. It is however recognised that during the initial stages of
project construction and until power import arrangements are made, on-site power generation may be
needed. Also due to construction activities it may not be practical to run power lines in certain
construction areas. This may continue throughout the project. During these periods, appropriate diesel
generators will be installed at site.
6.5.2 Water
The estimated peak non-potable water demand during construction phase will be 340m3/d, which
includes both construction water and non-potable water at site. Non-potable water at site can be
sourced from local groundwater wells or generated at site using a packaged RO plant. Groundwater
available near the project site has relatively high TDS and is not suitable for potable use but is still
suitable for agriculture. The current total demand of groundwater for agriculture is considered to be in
excess of local groundwater availability. Moreover, groundwater extraction has been rising steadily in
recent times to supply non-potable water for a number of ongoing construction projects in Sohar.
Therefore, the long-term sustainability of the local supply wells is not established. It is therefore
G-S000-5240-003 HMR Consultants
June 2015 6-9
Petrochemical Plant Sohar Environmental Impact Assessment Report
Orpic and CB&I HMR #3817
proposed that either the EPC contractor will install a packaged RO plant at site or procure water by
tanker (depending on operational feasibility) to meet all non-potable water requirements associated
with the project construction.
In addition non-potable is required in labour camps. Labour camps will be located outside the project
site, either in Sohar or Liwa municipal areas. Depending on the exact location of each labour camp,
non-potable water may be sourced from municipal water supply lines or from the RO plant installed
by the contractors or by water tankers (depending on operational feasibility).
For drinking water at project site, it is proposed to use bottled mineral water. This option is considered
to be better in all respects in comparison to the other alternative of treating RO water or municipal
water to meet drinking water standards. For labour camps, either bottled water or treated municipal
water will be used.
6.5.3 Fuels
The fuels used during construction phase are diesel oil and petrol. Heavy construction equipment and
heavy transport vehicles are diesel oil fired, while light vehicles are petrol fired. The fuels will be
sourced from local fuel oil suppliers like Shell, Oman Oil and Al Maha.
The option of using dispensing tankers will be more suitable option for the Project. Such tankers can
be supplied and maintained by the central facilities of the contracting companies. This avoids the need
for onsite fuel storage and related safety protection systems. As the Project is in SIPA which is well
connected by road, the option of using tankers is the most suitable option. However, this will depend
upon the quantity of fuel required during the construction and will be finalised by the EPC contractor
based on the site requirements and logistics.
At this stage, it is not known how many new labour camps will be constructed and where, since the
sub-contractors are not yet identified. The EPC contractor will require the selected sub-contractors to
include the following criteria, while selecting sites for constructing new labour camps:
Use of valves with bellow or double packing seals or equally efficient equipment, Design considerations for
the equipment's are carried out as double packing seals.
Bellow valves are especially recommended for highly toxic services, Polymer plants (PP/PE) do not have
highly toxic chemicals requiring use of bellow valves, It’s may be considered in hot oil system where
temperature reach 250Deg C and pressure of 6 bar, for personnel protection.
Minimization of the number of flanges (connectors), Considered during design special care shall be given
to TEAL handling area.
Closed sampling systems wherever possible, Considered during design, close sampling system for
hydrocarbon and powder are foreseen and on line Hydrocarbon Analyzers whereas continuous monitoring
is requested for process or safety requirements.
Drainage of contaminated effluents in closed systems, Accidental Oil Contamination system and storm
water from process area are closed systems.
Collection of vents and Suitable disposal method, Considered during design: all hydrocarbon vents and
drains are connected to the flare system.
Establish and maintain an equipment monitoring and maintenance (M&M) and/or leak detection and repair
(LDAR) program based on a component and service database in combination with the fugitive loss
assessment and measurement , As per Orpic’s management policy the LDAR programs will be implemented
once the facility is under operation.
Reduce dust emissions with a combination of the following techniques
Use of cyclones and/or filters in the air exhausts of de-dusting units. The use of fabric filter systems is
more effective, especially for fine dust. In Polymer plants (PP/PE) all vessels handling polymer
powders are equipped with cyclone or bag filters (Polypropylene fabric) to avoid dust emission.
Vacuum cleaning system for dust cleaning is foreseen in the additives and extrusion area.
Minimize plant start-ups and stops to avoid peak emissions and reduce overall consumption (e.g. energy,
monomers per ton of product); this has been considered as a part of design.
Secure the reactor contents in case of emergency stops (e.g. by using containment systems) In case of
emergency all the reactor vents are routed to the flare system.
Prevent water pollution by appropriate piping design and materials and facilitate inspection and repair of
effluent water collection systems, As per drainage philosophy separate drainage system will be provided
and will be inspected as per requirement.
Use separate effluent collection systems for: As per drainage philosophy separate drainage system will be
provided for
Contaminated process effluent water system.
Oily water system.
Storm water system.
Treating purge flows coming from blending silos vents with the following technique: activated carbon filter
for adsorptions at all silos vents, if required.
Use flaring systems to treat discontinuous emissions from the reactor system. Flaring of discontinuous
emissions from reactors is only BAT if these emissions cannot be recycled back into the process or used as
fuel: During plants upsets, equipment trips or utility failures the Reactor will be vented to the flare system,
no recycle is possible due to the presence of solids in the streams. During normal operation any venting
from process will be recycled back in to the process.
Re-use the potential waste from a polymer plant; Continuous wastes like extrusions discards, plant sweep
from polymer plant will be sold and reprocessed to external companies.
Treat waste water efficiently. Waste water treatment can be carried out in a central plant or in a plant
dedicated to a special activity. Depending on the waste water quality, additional dedicated pretreatment is
required. Process water will be routed to Central WWTP, hence such requirements should eventually be
imposed to the WWTP located in Plot 18 and included in SCU,U&O scope.
Operate the reactor at the highest possible polymer concentration. By increasing the concentration of the
polymer in the reactor, the overall energy efficiency of the production process is optimized , Unipol and
Spheripol technologies selected are the most efficient currently available on the market for licensing.
Use closed-loop cooling systems. this has been considered as a part of design.
Solvent selection - Low boiling solvents and suspension agents can be removed more easily and with less
consumption of energy from the product leading to a reduction of VOC emissions from the storage; Iso-
pentane is Low Boiling solvent and has been considered in design, no alternatives are currently available
Avoid oxygen intrusion into the Extruder feeding section; this has been considered as a part of design.
Treatment of purge nitrogen from Product Purge Bins. The purged N2 will be Flared at the rate of 1,400
kg/hr with HC content of less then 2%, see above for the considerations currently ongoing to recover
Nitrogen and Hydrocarbons using membranes
maintenance of the combustion system; Considered in Design and will be implemented during
Operation phase
Surface run-off from the plant to be collected separately and re-used only after a sedimentation
step or chemical treatment. NA as Per Drainage Philosophy
NOx emissions from furnaces to be reduced through equipment revisions such as low NOx
burners consider in design during FEED phase of the project and will be implemented during
EPC stage and operation of the plant;
Use of control systems (hardware and software) for the core process and pollution control
equipment to ensure stable operations, high yields and good environmental performance under all
operational modes; consider in design during FEED phase of the project and will be implemented
during EPC stage and operation of the plant additional studies will be carried out for area
monitoring;
Implementation of a waste management system that includes ongoing waste minimization to
identify and implement techniques that reduce emissions and raw material consumption; As per
operation philosophy pre-treatment of feed to remove H2S, less SO2 feed-stock,minimum caustic
as per optimization will be calculated and used;
Minimise energy use and maximize energy recovery optimised furnace design WHR, from flue
gas; Reuse heat from furnace effluent to heat process stream and generate steam, Pressure levels
and refrigerant usage will be minimum as the SCU is optimized, generation of HP steam for
Steam Turbines will be carried from waste heat of the heaters;
Implement LDAR program for detection and minimization of leaks on pipes and equipment; As
per Orpic’s management policy the LDAR programs will be implemented once the facility is
under operation;
Repair pipe and equipment leaks in stages, carrying out immediate minor repairs (unless this is
impossible) on points leaking above some lower threshold and, if leaking above some higher
threshold, implement timely intensive repair. As per Orpic’s management policy the LDAR
programs will be implemented once the facility is under operation;
Providing external floating roof with secondary seals (except for highly dangerous substances) for
storage tanks; Not Applicable;
Providing fixed roof tanks with internal floating covers and rim seals (for more volatile liquids)
and with inert gas blanket (e.g. when needed for safety reasons); Has been considered in design
and is also covered in tankage philosophy;
Providing instrumentation and procedures to prevent overfilling and constructing impermeable
secondary containment with a bund capacity of 110 % of the largest tank; Tankage has
considered the bund capacities in the design;
Recovery of VOCs (by condensation, absorption or adsorption) before recycling or destruction by
combustion in an energy raising unit; Boil off gas recovery system and reuse;
Minimise process water contamination with raw material, product or wastes by the use of:
Plant equipment and effluent collection systems made from corrosion resistant materials to
prevent leaks into wastewater. As per drainage philosophy wastewater will be temporary
stored in the concrete lined pit before sending for treatment and/or disposal Plant equipment
and effluent collection systems made from corrosion resistant materials to prevent leaks into
wastewater, As per drainage philosophy wastewater will be temporary stored in the concrete
lined pit before sending for treatment and/or disposal.
Drum storage on concrete hard-standing that drains to a holding sump, consider in design
during FEED phase of the Project and will be implemented during EPC stage and operation
of the plant;
Providing spill clean-up material at strategic points around the installation and a spill
contingency plans, consider in design during FEED phase of the Project and will be
implemented during EPC stage and operation of the plant;
Providing containment areas for fire-fighting water, consider in design during FEED phase of
the Project and will be implemented during EPC stage and operation of the plant;
Maximizing wastewater re-use by the use of following:
• Identifying options for the wastewater re-use commensurate with the wastewater quality; It
has clearly mentioned in drainage philosophy that the treated wastewater will be sent to
MISC for further use as irrigation or it is based on the MISC to be considered for final usage;
and
• Providing storage tanks for wastewater to balance periods of generation and demand; is part
of MISC
extracting the relevant atmosphere via an alternative odour control system, Backup for vent gas is
going to LP flare, and has been considered in design;
Developing a plan for the prevention, detection and control of fire hazards at the installation, in
particular for waste storage and pre-treatment areas, furnace loading areas, electrical control
systems etc; Active fire protection and fire and gas detection is planned and will be installed;
Use automatic fire detection and warning systems, and a manual or automatic fire intervention
and control system as required according to the risk assessment carried out; Active fire protection
and fire and gas detection is planned and will be installed;
Use of combustion control philosophy, and key combustion criteria and a combustion control
system to monitor and maintain these criteria within appropriate boundary conditions, in order to
maintain effective combustion performance; Controlled and monitored combustion within the
incinerator is part of package and will be optimised based on the material to be incinerated; and
Optimisation and control of combustion conditions by a combination of control of air (oxygen)
supply, distribution and temperature, including gas and oxidant mixing, the control of combustion
temperature level and distribution, and control of raw gas residence time; Controlled and
monitored and optimum residence time has been considered for the incinerator package.
fugitive releases for each substance. Where there are opportunities for reductions, the Permit
may require the updated inventory of fugitive emissions to be submitted. Same has been
calculated using the Tanks Model and estimated fugitive loss as TPA; and
Leak Detection and Repair (LDAR) compromises the detection and reparation of flare pipe
shutoff valves. A portable instrument is used to detect VOC leaks during regularly scheduled
inspections. Leaks are then repaired immediately or scheduled for reparation as quickly as
possible. An LDAR contains the following elements: As per Orpic’s management policy the
LDAR programs will be implemented once the facility is under operation.
Implement procedures to ensure that arms are not operated until inserted fully into the container
to avoid splashing where top loading arms are used; SOP and maintenance philosophy has been
consider in design and will be implemented at EPC and operation phase;
Apply instrumentation or procedures to prevent overfilling; Considered and detailed in tank
design philosophy; and
Install level alarms independent of normal tank gauging system. Considered and detailed in tank
design philosophy and fire and gas detection and control system will be installed.
7 CLIMATE AFFAIRS
This chapter presents the GHG emissions from the proposed construction and operational activities of
the petrochemical plant and discusses the impact on the climate due to the proposed project. A
forecast of the quantities of GHG emissions using the emission factors from the Intergovernmental
Panel on Climate Change (IPCC) Guideline, and data from the design documents is presented in this
chapter. This chapter has been prepared and structured as per the guidelines from the DGCA at
MECA.
Estimates of GHG during the project activity from the sources mentioned above are derived using
emission factors provided in the IPCC 2006 guidelines for National Greenhouse Gas Inventories,
Volume 2. The guidelines provide emission factors for GHG emissions from both stationary
combustion sources and mobile sources. It is to be noted that the mobile sources referred in the IPCC
guidelines cover off road transportation sources including vehicles and mobile machinery used for
construction and maintenance. An estimate of 20,000L/month of diesel fuel (8,000L/month for the
DG sets and 12,000L/month for equipment and vehicles) is expected to be used during the
construction period.
It is expected that a diesel generator of 450 kVA rating will be used to meet power requirements
during the construction period. The construction period is expected to take about 20 months. As
mentioned above it is estimated that approximately 8,000L/m of diesel will be required during the
construction phase for operation of the DG set.
The type and quantities of the GHG emissions during the construction stage of the project are
presented in
Table 7-1. The detailed GHG emission calculations for stationary combustion sources are given in
Table 7-2.
Table 7-1: GHG Emission from DG Set
Table 7-2: Detailed GHG Emission Calculation from Stationary Combustion Sources
During the operation phase the main stationary sources of GHG (i.e., CO2, CH4 and N2O) emissions
will be the various furnaces, the incinerators, the GTs, the steam boilers and the flares. The GHG
emission during operation phase is detailed in Section 7.3.6.
10
Assuming that the construction activit8ies commence in April 2016 and completes in Nov 2017
11
http://www.ipcc-nggip.iges.or.jp/public/2006gl/pdf/2_Volume2/V2_2_Ch2_Stationary_Combustion.pdf
G-S000-5240-003 HMR Consultants
June 2015 7-3
Petrochemical Plant Sohar Environmental Impact Assessment Report
Orpic and CB&I HMR #3817
category includes all the light and heavy-duty vehicles which operate on liquid or gaseous fuels. The
off-road category includes vehicles and mobile machinery used within the plant (including
construction and maintenance).
The GHG emissions from mobile combustion sources (vehicles, machineries and construction
equipment) during construction phase are presented in Table 7-3.
Table 7-3: GHG Emissions from Mobile Combustion
Table 7-4: Detailed GHG Emission Calculation for Mobile Combustion Sources
The mobile combustion sources during the operation phase of the project will be the trucks and other
vehicles used for transporting raw materials/products, shuttling the workers / staff between facility
and accommodation facilities, cars, private vehicles used by employees etc. Since information such as
the number of vehicles and diesel consumption rate of each vehicle, distances travelled by the
vehicles etc., are not available at the time of preparation of the report; the GHG emission for mobile
source during the operation phase is not estimated.
12
Assuming that the construction activit8ies commence in April 2016 and completes in Nov 2017
13
http://www.ipcc-nggip.iges.or.jp/public/2006gl/pdf/2_Volume2/V2_3_Ch3_Mobile_Combustion.pdf
G-S000-5240-003 HMR Consultants
June 2015 7-4
Petrochemical Plant Sohar Environmental Impact Assessment Report
Orpic and CB&I HMR #3817
Fugitive emissions from oil and natural gas systems are often difficult to quantify accurately. This is
largely due to the diversity of the industry, the large number and variety of potential emission sources,
the wide variations in emission-control levels and the limited availability of emission-source data. The
exact quantities of fugitive emissions cannot be estimated at this stage. The emission from the oil and
natural gas system will be calculated and reported during the EPC phase.
GHG's (TPA)
Year
CH4 CO2 N2 O
2018 11.127 624,197.772 1.113
Table 7-6: Detailed GHG Emission Calculation from Industrial Process Combustion
Vent gases with toxic components or smelly fumes will be routed to the Vent Gas Incinerator;
and
Liquid streams and solid waste will be incinerated in Liquid/Solid Waste Incinerator.
Incineration of waste is sources of greenhouse gas emissions, like other types of combustion. Relevant
gases emitted include CO2, CH4 and nitrous oxide N2O. Normally, emissions of CO2 from waste
incineration are more significant than CH4 and N2O emissions.
Solid Waste
14
http://www.ipcc-nggip.iges.or.jp/public/2006gl/pdf/2_Volume2/V2_2_Ch2_Stationary_Combustion.pdf
G-S000-5240-003 HMR Consultants
June 2015 7-6
Petrochemical Plant Sohar Environmental Impact Assessment Report
Orpic and CB&I HMR #3817
CFi – fraction of carbon in dry matter – 50 (default value for industrial waste)
FCFi – fraction of fossil carbon in total carbon – 90 (default value for industrial waste)
i.e. Total CO2 emission is 33.074 Gg/y (33,074.25 tpa) from solid waste incineration
EFi –NO2 emission factor, kg NO2/Gg of waste – 41g NO2/t waste ~0.000041 kg/Gg waste
15
For estimation of methane from incineration semicontineous incineration with stoken technology is assumed
G-S000-5240-003 HMR Consultants
June 2015 7-7
Petrochemical Plant Sohar Environmental Impact Assessment Report
Orpic and CB&I HMR #3817
preparation of the report, the GHG emission from the same is not reported in this study. The total
GHG emission expected from the proposed facility are presented in Table 7-7 below.
Table 7-7: Total GHG Emissions (TPA)
From the above table it is seen that total CO2 emissions from the PC project would be about
32,678,550 t. In terms of global warming potential, the sum of GHG emissions during the project life
cycle would be 32,716,731t of CO216 equivalent
Currently, there is no ceiling limit set for CO2 emissions (mass) rates in Oman. According to the UN
Statistic Division and the Carbon Dioxide Information Analysis Centre (CDIAC) estimates, the
emissions in Oman were about 57,202 thousand tons per annum (tpa) during 2010, i.e. about 156,718
tpd.
In comparison with the estimates, the total CO2 emission from proposed activity is approximately
1,210,317TPA or 3,316TPD which would account for approximately 2%, of the total estimated
quantity of CO2 released each day in Oman.
The proposed PC plant will also contribute to GHG emissions. Cumulative impacts on climate change
will be resultant of other industrial activities in SIPA. In addition, road and sea traffic at the existing
and proposed infrastructure would contribute to GHG emissions and climate impacts. It is expected
that as part of the environmental permitting and reporting procedure in Oman, individual industries
will be monitoring and reporting such information to MECA and therefore, are not included here.
It is possible that an increase in the frequency of severe storm and flooding events could result under
climate change. The overall vulnerability of the project to climate change is low. However, it is not
possible to predict such events or estimate chances of occurrence due to lack of appropriate data. The
PC project has taken into account extreme events such as floods, cyclones, storms and rains.
16
http://www.epa.gov/cleanenergy/energy-resources/calculator.html
G-S000-5240-003 HMR Consultants
June 2015 7-8
Petrochemical Plant Sohar Environmental Impact Assessment Report
Orpic and CB&I HMR #3817
Any disruptions that occur as a result of shutdowns caused by weather events will be short term in
nature. An overall change in climate will not affect the operation of the facilities. From the above
discussion, Climate Affairs Risks Matrix is given in Table 7-8 below.
Table 7-8: Climate Change Matrix
The proposed PC plant is located within a dedicated industrial area, which is expected to have taken
into account the above aspects.
7.6.3 Landslide
According to World Health Organisation atlas (Figure 7-1) landslide hazard index for complete
Oman is between low and very low. Hence, the likelihood of the PC project being affected by
landslide is very unlikely.
7.6.4 Tsunamis
The greatest tsunami threat facing the Omani coastline is expected to be from the Makran subduction
zone in the Gulf of Oman and the Northern Arabian Sea. However, within the Arabian Gulf it is rather
unlikely for large tsunamis to form. Given that the coast is shallow, not prone to landslides, and is
without volcanoes, the likelihood for tsunamis is relatively small. None of the historical or more
recent submarine or coastal earthquakes has generated tsunamis of any significance in the Gulf, with
the exception of the 1008 AD event, which is not conclusive (as it may have been the result of storm
surge).
Figure 7-2 and Figure 7-3 present the seismic areas for the Middle East Region indicated by the
number of earthquakes (all depths) per year and seismic events for the period 1990 to 2006
respectively. While there is a low occurrence of earthquakes within faults in the Northern Oman Hajar
Mountains, this activity would not seem to rest of Oman. This is supported by the fact that no
earthquakes have occurred within Oman from 1990 - 2006. Any activity has been limited to major
tectonic boundaries.
Predicted magnitude of seismic events presented as peak ground acceleration for the Middle East
region has been calculated by the USGS based on a worldwide network of seismic stations (Figure
7-4). Peak ground acceleration is a measure of ground motions as a result of seismic or other
activities. Global Earthquake Hazard Distribution-Peak ground acceleration is a 2.5 minute grid of
global earthquake hazards developed using Global Seismic Hazard Program (GSHAP) data that
incorporate expert opinion in predicting localities where there exists a 10 %chance of exceeding a
peak ground acceleration (pga) of 2m/s/y/s meters per second per second (approximately one-fifth of
surface gravitational acceleration) in a 50 year time span. This data set is the results of collaboration
among the Columbia University Center for Hazards and Risk Research (CHRR) and Columbia
University Center International Earth Science Information Network (CIESIN). As per the above data
set, peak ground acceleration for the concession area is predicted to be in the range of 2.4m/s2 with a
10% probability of exceeding in 50 years.
Figure 7-2: Earthquake Frequency for Middle East Figure 7-3: Seismicity Map for Middle East (1990-2012)
It must be noted that the impacts discussed in this chapter are residual impacts, i.e., the potential
environmental impacts due to the environment releases from project activities containing inherent
design control and safety measures. In other words, the impacts assessed in this chapter will be for
releases with such measures in place. The mitigation and control measures are suggested in a separate
EMP report as per the SEU’s requirement.
8.1 Methodology
The identification and assessment of environmental impacts is based on the guidelines provided in
ISO 14001 series of standards and includes the following steps:
Identification of major activities during the construction and operation phases of the project
based on the discussions on project details provided in Chapter 3;
Identification of potential environmental aspects from the project activities (identified in the
above step) based on discussions in Chapters 3 and 5;
Identification of potential impacts from the project considering the environmental aspects
identified above and various environmental elements / sensitivities (receptors) which are likely to
be impacted due to the project based on discussions presented in Chapter 4; and
Assessment of environmental impacts considering the severity of impact and the duration or
likelihood of its occurrence.
Based on the above, as the first step, each major activities of the project during the construction and
operation phases are identified. The associated environmental aspects are identified based on the
project description and various releases into the environment. The resulting impacts are identified by
combining the above information with the environmental elements / sensitivities.
Whenever interactions exist between the identified aspects and sensitivities, they are further analysed
to determine the potential impacts from the project. Impacts may be classified as beneficial/adverse,
direct/indirect, reversible/irreversible or short/long term. The assessment of potential impacts is
carried out utilizing both qualitative and quantitative assessment techniques. In qualitative assessment
the impacts are rated as ‘negligible’, ‘low’, ‘medium’ or ‘high’.
For impacts arising from planned / expected aspects, this rating is based on two parameters, i.e.,
severity of impact and duration of its occurrence. Severity of any impact will depend on the nature
and size of the activity/aspect and the environmental/social sensitivity. An impact assessment matrix,
as presented in Figure 8-1, is used for combining the two assessment criteria.
Very
Duration Momentary Short Term Medium Term Long Term
Long Term
Severity 1 week < 1 year 1 – 10 years 10 – 50 years
> 50 years
Positive Effect + ++ +++
Slight Effect Negligible
Minor Effect Low Impact
Moderate Effect Medium Impact
Major Effect High Impact
Massive Effect
Figure 8-1: Impact Assessment Matrix for Planned Aspects
For impacts resulting from unplanned and accidental aspects/ activities, the assessment is based on
consideration of the impact severity and the likelihood of it is occurrence. While the impact severity
depends on the nature and size of the activity aspects and the environmental sensitivity, the likelihood
depends upon the nature of the activity/aspect and the control measures in place. An impact
assessment matrix, as presented in Figure 8-2, is used for combining the two assessment criteria, i.e.,
the severity of impact and the likelihood of its occurrence.
Duration Very
Unlikely Likely Very Likely Certain
Severity Unlikely
Slight Effect
Minor Effect Low Impact
Moderate Effect Medium Impact
Major Effect High Impact
Massive
Figure 8-2: Impact Assessment Matrix for Unplanned Aspects
In assessing the impacts, it is to be noted that the project activities, related environmental aspects and
associated impacts are presented together to facilitate subsequent rating. The ratings are primarily
based on qualitative assessment of the situation and its interaction with the environmental elements.
The impacts, which are rated as low are considered to be acceptable or within “As Low As
Reasonably Practicable (ALARP)” levels. Control measures for further mitigation of these impacts
may not be viable. Impacts that are rated as medium and high (significant impacts) will be managed
through mitigation measures and implementation of the environmental and social management plan to
reduce the residual risks / impacts to ALARP levels. Definition of terms used in the matrix is
presented in Appendix I.
The rocks and aggregates that will be used in the civil works will be procured from local quarries.
Quarries not having the required environmental permit as per MD 200/2000 will not be used. Any
fresh/virgin soil required would be procured from local borrow pits, which are approved by the
municipality. These resources are abundantly available, locally, and hence no adverse impacts are
expected. However, some off-site impacts on air quality due to dust generation and public safety and
health due to quarrying activities are expected. These impacts are further discussed in the related
sections.
Diesel oil will be used as fuel for construction machinery and DG sets. It is expected that the local
suppliers of refined petroleum products can adequately supply the required quantities of fuel, without
adversely affecting the local demand-supply balance. The power requirement during the construction
phase is expected to be sourced from the DG sets. Alternatively sourcing power from existing grid
will also be investigated.
The water required for the construction phase will be sourced from local groundwater wells or from
authorized tanker suppliers. If water is sourced from groundwater wells, the wells will be selected
taking into account the existing use and the capacity / yield of the wells in order to minimise impacts
on existing users. Groundwater extracted from the wells located near the project site is mostly used
for agriculture. No current data is available on groundwater extraction, aquifer recharge and variations
in groundwater table. However, it is known that some of the coastal wells are affected by saline
intrusion apparently due to over-exploitation. Therefore, some adverse impacts on the existing users
(farmers) may be expected if groundwater required for the project is extracted from low yielding
wells. It is however envisaged that the water requirement during the construction phase will be
sourced through approved tankers.
Appropriate storage and handling facilities will be established for water and fuel in order to minimise
losses due to leaks and spillages. Further, the consumption of resources will be optimized, minimizing
wastage. The foodstuff and other materials required for the labour camps will be sourced from local
suppliers. The usage / consumption of such materials will be optimized and wastage minimized.
Drainage channels will be provided around the site in order to route the flow in order to avoid
flooding. . It will be ensured that surface flow from areas where hazardous materials and wastes will
be stored will not mix with the uncontaminated surface run-off. As the proposed site is within the
SIPA, aesthetic impacts due to the project construction will be negligible. Based on the above
discussions, the impacts on topography and landscape are rated as below.
Impact Severity Duration Likelihood Impact rating
Impacts on topography & landscape Slight Long Term - Low
Release of SO2, NOx, VOCs and PM from diesel engines of construction machineries,
vehicles and DG units used for power generation;
Welding / metal works, surface cleaning and painting. These activities will release fumes and
VOCs; and
Fugitive emissions from storage of fuels, lube oils and other chemicals releasing VOCs
The dust generation during site preparation activities could be significant onsite. Estimates of dust
generation during excavation are not available. However, such activities lend themselves to a
considerable amount of onsite dust generation which can potentially affect the workforce.
With respect to exhaust emissions from earthmoving equipment and other engines and generator sets
on site, these have been discussed in Section 7.3. The total emission of CO2 and NOx for the whole of
the construction activity is estimated to be about 1,070t and 0.251t respectively.
Material like asbestos etc are also prohibited in industrial application in Oman. Though it is difficult
at this stage to quantify the impacts on air quality, it is reasonable to consider that impacts will be
limited to the nearby environment considering the nature of construction activities and will be for a
period of not more than 20 months. Human receptors are not located within the site boundary. The
control measures to be implemented in order to minimise the adverse impacts on air quality are
discussed in the EMP report. Accordingly, the impacts on ambient air quality are rated as follows:
G-S000-5240-003 HMR Consultants
June 2015 8-21
Petrochemical Plant Sohar Environmental Impact Assessment Report
Orpic and CB&I HMR #3817
With regard to the ambient noise levels, since noise is attenuated by distance (typically noise levels
drop by about 40 dB (A) at 100m distance from the source), the activities on-site are unlikely to affect
the ambient noise levels significantly. However, during night times when the ambient noise levels are
low, the level of perception to noise may be more acute. Noise from transport vehicles will be only
transient for a given location and can be considered as a nuisance during night time through the route
which it passes. Mitigation measures to be implemented in order to minimise impacts on noise levels
are described in the EMP report. Accordingly, the impacts on noise levels are rated as below.
It can be noted from the findings of the rapid ecological survey conducted for the Project, that there
are no species within or around the site that are classified as rare, threatened, endangered or of
significant conservation value. All the terrestrial vertebrates identified/recorded during the survey are
common, highly mobile and resilient species which will likely move to neighboring undisturbed
habitats.
The natural landscape in SIPA is heavily altered due to industrial developments since its inception in
2002. The habitat loss and mortality of flora due to land preparation activities cannot be avoided as
the project site is situated in a parcel of land specifically dedicated for industrial development.
Further the inevitable impact on flora can be minimized by the establishment of green belt using
native plant species in the periphery of proposed plant. In addition, whenever applicable the century
old stands of Ghaf Tree (P. cineraria) should be incorporated in the landscape design within the
footprint of the Project. Accordingly the impacts on terrestrial ecology are rated below.
G-S000-5240-003 HMR Consultants
June 2015 8-22
Petrochemical Plant Sohar Environmental Impact Assessment Report
Orpic and CB&I HMR #3817
The waste and wastewater streams associated with project construction activities are characterized
and quantified in Chapter 5 along with the handling and disposal method for each stream. Improper
collection, handling, storage and disposal or accidental releases of wastewaters, non-hazardous and
hazardous wastes and hazardous substances can lead to contamination of soil and/or groundwater. The
improper handling may be due to absence or lack of proper facilities and methods for handling the
materials and wastes. Adequate provisions will be made for the management of these waste streams in
an environmental friendly manner. The severity of impacts on soil and groundwater is expected to be
‘low’ since environmental impacts will be contained within the project site and construction camps.
Accordingly, the impacts on soil and groundwater are rated as below.
In addition, local suppliers will also be benefited as they will be contracted for the supply of water,
foodstuff etc. Considering the above, beneficial impacts are envisaged from the project on the local
employment and economy. Therefore, it can be concluded that the project will set positive impact on
local livelihood option.
Noise and road congestion from vehicle movement is likely to create some nuisance along the road
network. However, the construction activities will be restricted to SIPA and daytime thereby limiting
the nuisance during night when the perception to noise is the highest. Infrastructure such as access
roads, water, electricity, mosque, healthcare services, recreation facilities, sanitation, and waste
services may be shared with the local community.
Issue Severity Duration Likelihood Impact rating
Local purchase of goods Positive Medium Term - +
Hiring of local people Positive Medium Term - +
Stress on infrastructure Slight Medium Term - Low
Impacts to local communities during the construction phase are also likely from health and safety risk
from waste management activities, transportation / movement of heavy equipment and vehicles,
earthwork such as excavation, dust and gaseous emissions, noise and influx of large number
construction workers to the area. Further, nuisance from increased activities and traffic, stress on road
traffic, groundwater use, etc., are likely to have impacts on local communities in the area. Based on
the above the impact rating is presented below.
Impact Severity Duration Likelihood Impact Rating
Impact on land use Slight Long Term - Low
Impact on settlements from
Slight Medium Term - Low
construction associated activities
Impact on settlements from accidental
Moderate - Unlikely Low
releases
Traffic congestion / accidents Moderate - Likely Medium
The power requirement for the plant will be sourced from the power plant that will be provided in the
facility. The power plant will be run on natural gas. Petrol and diesel will be used as fuels for vehicles
and emergency power generation. Estimates of number of vehicles and run time of emergency DG
sets are not available and hence the fuel consumption cannot be evaluated at this stage. Local
suppliers of refined petroleum products can supply such quantities without causing imbalance on local
demand-supply. In light of the fact that the present project will contribute to the industrial and
economic development of the region which is in line with the overall development plans of the
country and weighing the benefits of such development with the consumption of the above resources,
the impacts can be considered to be low.
Issue Severity Duration Likelihood Impact rating
Stress on power supply Slight Long Term - Low
Stress on fuel supply-demand Slight Long Term - Low
Stress on water supply-demand Moderate Long Term - Medium
Dispersion modelling using AERMOD requires hourly meteorological data and for the Project this
has been sourced from Lakes Environmental (MM5 pre-processed data for CY 2009 to 2013, 5 years).
The model set-up is presented in Table 8-4.
Table 8-4: Model Set Up
The continuous point sources and pollutant emission rates are given in Table 8-5. The AERMOD has
been run for normal operation scenario of all the emission sources (emitting combustion products).
Stack UTM Co-ordinates Stack Details (m) Temp Flow rate NOx SOx CO UHC PM10
Sources
ID Easting Northing Height Diameter K (m3/hr) (g/s) mg/m3 (g/s) mg/m3 (g/s) mg/m3 (g/s) mg/m3 (g/s) mg/m3
1 SCU Heater Stack 1 461955 2705120 40 2.5 450 26.4 3.28 124.2 0.1 3.8 0.2 7.6 0.25 9.5 1.25 47.3
2 SCU Heater Stack 2 461963 2705106 40 2.5 450 26.4 2.68 101.5 0.1 3.8 0.2 7.6 0.25 9.5 1.25 47.3
3 SCU Heater Stack 3 461970 2705093 40 2.5 450 26.4 3.55 134.5 0.1 3.8 0.2 7.6 0.25 9.5 1.25 47.3
4 SCU Heater Stack 4 461977 2705078 40 2.5 450 26.4 3.55 134.5 0.1 3.8 0.2 7.6 0.25 9.5 1.25 47.3
5 SCU Heater Stack 5 461986 2705061 40 2.5 450 26.4 3.55 134.5 0.1 3.8 0.2 7.6 0.25 9.5 1.25 47.3
6 SCU Heater Stack 6 461955 2705046 40 2.5 450 34 4.37 128.5 0.1 2.9 0.2 5.9 0.25 7.4 1.25 36.8
7 SCA Incinerator 1 461498 2705598 20 0.3 443 0.9 0.08 88.9 0.02 22.2 0.03 33.3 0.01 11.1 0.05 55.6
8 SCA Incinerator 2 462363 2705196 20 0.3 443 0.9 0.08 88.9 0.02 22.2 0.03 33.3 0.01 11.1 0.05 55.6
9 SCA Power Generator 1st Stack 462201 2705202 60 1.5 318 118.4 11 92.9 2.6 22.0 3.7 31.3 0.7 5.9 7.3 61.7
10 SCA Power Generator 2nd Stack 462127 2705161 60 1.5 318 118.4 11 92.9 2.6 22.0 3.7 31.3 0.7 5.9 7.3 61.7
11 SCA High Pressure Flare Stack 461961 2705643 170 1.5 443 34 0.07 2.1 0.02 0.6 0.4 11.8 0.15 4.4 1.25 36.8
12 SCA Low Pressure Flare Stack 461581 2705653 60 1.5 443 34 0.07 2.1 0.02 0.6 0.4 11.8 0.15 4.4 1.25 36.8
14 Boiler 1 461832 2705202 40 2.5 450 26.4 3.76 142.4 0.1 3.8 0.2 7.6 0.25 9.5 1.25 47.3
15 Boiler 2 461846 2705180 40 2.5 450 26.4 3.76 142.4 0.1 3.8 0.2 7.6 0.25 9.5 1.25 47.3
16 Boiler 3 461859 2705159 40 2.5 450 26.4 3.76 142.4 0.1 3.8 0.2 7.6 0.25 9.5 1.25 47.3
The estimated maximum GLCs for each pollutant and corresponding distances for the modeled
pollutants are presented in Table 8-6. The GLC isopleths for maximum averages of pollutants are
presented in Appendix K. The contours are presented covering the nearby areas as well as a larger
area up to 20 km distance from the project site.
Table 8-6: Predicted GLC Values
Location of Resultant
Distance to Direction
Max. GLC max. GLC Concentration17
Pollutants max. GLC to max.
(µg/m3) (UTM
(m) GLC*
Coordinates)
Normal E 461322
17.95 671 W
Operation N 2705428
CO
8-hr avg. 6,000
Std. Lt.** (OAAQS); - -
E 461322
NOX Normal 47.8 667 SW
N 2705428
24-hr Operation
avg. 112
Std. Lt. - -
(OAAQS)
E 463133
SO2 Normal 3.88 732 S
N 2704602
24-hr Operation
avg. 125
Std. Lt. - -
(OAAQS)
E 462063
Normal 19.6 665 W
PM10 N 2705718
Operation
24-hr
avg. 125
Std. Lt. (OAAQS); - - -
E 461322
UHC Normal 8.92 675 W
N 2705428
3 hr Operation
avg. 160
Std. Lt. - - -
(OAAQS)
Note: All distances are measured from High Pressure Flare Stack
Further the emissions from storage tanks, which are fugitive in nature, have been quantified using
USEPA’s TANKS 4.0 software model as discussed in Chapter 5. The inputs for the TANKS 4.0
model were taken from the data provided by CB&I. Fugitive emissions from pipelines and fittings are
insignificant compared to the point source emissions. It is seen that the estimated annual fugitive
emissions from the tanks are low. CB&I will provide appropriate measures in the design of the tanks
for minimizing the fugitive emissions from the storage tanks.
17
“Guidelines for air quality dispersion modelling in British Columbia”, Page no 82, for cumulative impacts. (http://www.env.gov.bc.ca/air)
G-S000-5240-003 HMR Consultants
June 2015 8-28
Petrochemical Plant Sohar Environmental Impact Assessment Report
Orpic and CB&I HMR #3817
From the above table it can be seen that the predicted GLC’s of all the pollutants due to the plant
operation are within the OAAQS during the normal operation condition. Based on the above the
impact on ambient air quality can be rated as below
Issue Severity Duration Likelihood Impact rating
Air Quality Moderate Long term - Medium
Greenhouse gas emission Moderate Long-term - Medium
Gaseous Pollutants Moderate Long-term - Medium
In order to determine the impacts of the various noise sources in the facility, a noise modeling using
SoundPLAN software will be conducted during the EPC stage of the project, based on the final
selection of equipment and lay out, the source noise levels and noise attenuation measures adopted.
Storage and handling of hazardous substances such as skimmed oil from LLOD basin,
WWCT, Oily sludge storage tank, DGF skimming, Benzene/MTBE WWCT, dewatered oily
G-S000-5240-003 HMR Consultants
June 2015 8-29
Petrochemical Plant Sohar Environmental Impact Assessment Report
Orpic and CB&I HMR #3817
sludge, waste oils and oily sludge, waste chemicals, solvents, waste paints, used cotton waste,
etc. from plants and maintenance workshops, polyethylene and polypropylene powder;
Containers of hazardous materials (oil drums, chemical drums etc.), spent filter medium,
sludge from WWTU, fuel, chemicals, etc.;
Collection, handling, storage, transportation and disposal or accidental releases of wastewaters, non-
hazardous and hazardous wastes and hazardous substances can lead to contamination of soil and/or
groundwater, if proper facilities and methods for handling are not established.
The domestic sewage generated from toilets, washrooms and kitchen will be connected via pipeline to
the holding tanks and routed to the sewage network operated by MISC in SIPA for treatment in their
STP. The surface run-off water from the process and storage area which may be contaminated will be
routed to a sump from where it will be directed to the WWTU. All effluents (except cooling water,
brine rejectsand boiler blow down) will be segregated and routed to the WWTU for treatment to
marine discharge standards (as per MD 159/2005). There will be no underground storage tanks at the
facility and the material loading and unloading areas will be designed with proper enclosures and
secondary containment on paved surfaces.
The proposed practices on storage and handling of hazardous materials discharge of liquid effluents
and disposal of hazardous wastes are detailed in the EMP and these will ensure to minimise the
resulting impacts. Accordingly, the impacts on soil and groundwater are rated as below.
Impact Severity Duration Likelihood Impact Rating
Impact on soil & groundwater from normal
Moderate Long Term - Medium
wastewater & waste management
Impact on soil and groundwater from
improper handling & disposal of waste & Moderate - Unlikely Low
wastewater
In addition, the local businesses such as fabricators, maintenance service providers, foodstuff
suppliers, transporters, etc., are likely to have business opportunities associated with the operation of
the plant. Based on the above, the impacts are rated as below:
Issue Severity Duration Likelihood Impact rating
Impact from loss of employment
during transition from construction to Slight Long Term - Low
operation phase
Impact on economy through generation Positive Long Term - ++
G-S000-5240-003 HMR Consultants
June 2015 8-30
Petrochemical Plant Sohar Environmental Impact Assessment Report
Orpic and CB&I HMR #3817
The impacts on local communities during the operation phase will be related to health and safety risk
from waste management activities, transportation of hazardous wastes and materials, gaseous
emissions the emissions sources, noise and influx of expatriate operation staff to the area. Further,
nuisance from increased activities and traffic, stress on roads, etc., are likely to have impacts on local
communities and the livestock farms in the area.
The storage, treatment and disposal of hazardous wastes are likely to pose health risk to employees
and the community. Accidental releases of hazardous wastes from storage areas may pose soil and
groundwater contamination, which in turn may pose health risks. Accordingly the impact is rated
below:
Impact Severity Duration Likelihood Impact Rating
Impact on land use Slight Long Term - Low
Impact on health and safety of Very
Major - Low
settlements from accidental releases Unlikely
“The environmental impact assessment process adopted for the Project assesses and evaluates each
impact after application of the proposed controls and mitigation measures applied. These controls
and mitigation measures have been documented in the BAT analysis and associated environmental
management plans (EMP). As such the impacts presented in this Section and as summarized in the
Impact Summary Tables are the residual impact”.
9 CONCLUSION
The EIA study for the petrochemical project concludes that the project will not cause any
significant deterioration of the environmental quality and will in fact generate revenues,
employment and invigorate the economy.
As mentioned in various sections of this report, the project will implement appropriate control and
mitigation measures to minimise the environmental impacts and to ensure compliance with applicable
Omani and International Environmental Regulations and requirements of World Bank Equator
Principles. Through effective implementation of the Environmental and Social Management Plan
(EMP) and careful design, engineering, planning, construction and operation considerations the
associated residual impacts will be minimized. Consequently, these impacts are not expected to cause
any significant, long term and irreversible change on the environment and the local community.
Activity specific management plans shall be developed following the award of tenders to contractors
developing various features of the project. Emphasis on rigorous environmental monitoring of various
aspects as presented in the EMP report needs to be reinforced at the highest level within Orpic so that
distinct trends in adverse impacts can be promptly identified for suitable mitigation in consultation
with experts at SEU/MECA.
From the BAT analysis it is concluded that FEED has considered all applicable BAT criteria for the
proposed Petrochemical Plant.
The proposed project will significantly contribute to the on-going industrial development in Oman
and to the economic growth of the country and pioneer industrial development. It is expected to
provide employment opportunities for Omani people both during construction and operation phases of
the project.
Therefore, the proposed project is considered to be acceptable from an environmental and social
standpoint within the context of local and internationally comparable environmental standards.
RD 114/2001 provides the framework for environmental protection and prevention of pollution in
Oman. Applicable requirements of the above RD are listed below:
Article 7 - It is not allowed to use Oman environment for the disposal of environmental
pollutants in quantities and types that may adversely affect its intactness and its natural
resources or nature conservation areas and the historical and cultural heritage of the Sultanate.
No pollutants shall be disposed of in the natural ecosystems unless in accordance with the
regulations and conditions issued by a decision from the Minister;
Article 9 - No establishment of any source or area of work shall be started before obtaining an
environmental permit confirming its environmental soundness. The permit shall be issued upon
an application to the Ministry. The Minister shall issue a decision specifying procedures
conditions and rules regulating issue, term and renewal of such permit;
Article 10 - The owner shall take the necessary measures and adopt the state-of-the-art
techniques, approved by the, to minimize generation of waste at the source and to use clean
production techniques to prevent pollution of the environment. The owner undertakes to submit
a contingency plan for approval by the Ministry which shall be reviewed periodically;
Article 19 and 22 restrict dumping / disposal of hazardous and non-hazardous wastes into the
environment without any permit; and
Article 41 - Whoever causes environmental damage shall undertake to remove it at his own
expense and shall reinstate the environmental status in addition to payment of necessary
compensation. In the event of failure of the violator to remove reasons of the violation within
the specified period, the Ministry shall have the right to arrange for removal of the same at the
expense of the violator.
MD 187/2001 and its amendments through MD 68/2004 specify the requirements and procedural
process for applying and obtaining an environmental approval/permit prior to commencing any
development activities. The relevant articles promulgated under this regulation in regard to the
proposed project are:
Article 3 – The owner shall apply to MECA on the form approved by the Ministry and in
addition enclose an environmental impact study prepared by a consulting office approved by
the Sultanate, if required by the Ministry;
Article 4 - The Ministry official shall as a preliminary step toward issuance of the
environmental approval, inspect the proposed sites to determine the environmental conditions
that must be fulfilled;
Article 5 – The owner of the establishment shall be bound to implement the required conditions
and shall inform the Ministry of the same after ensuring that all the conditions are implemented
prior to issuance of environmental approval or environmental permit; and
Article 7 – The owner, if the nature of their activities so require as evaluated by the Ministry,
shall be bound to conduct an Environmental Audit by specialized companies approved by the
Sultanate according to the requirements of ISO 14000 series of EMS.
RD 115/2001 provides the framework for protection of potable water sources from pollution. Listed
below are applicable Articles from this RD:
Article 8 - Non-household effluent shall not be discharged in sewage networks unless it is
treated in order to be in conformity with the specifications stated in appendix no. (3) of this
law. No sewage water or any other water pollutants shall be discharged in rainwater drainage
networks;
Article 9 - Solid non-hazardous waste shall only be disposed of in sanitary landfills licensed by
the Ministry. No solid non-hazardous waste shall be mixed with any category of hazardous
waste at any stage;
Article 13 - Every person who pollutes water shall be bound to remove such pollution at his
own expense and pay compensation for the damage. The Ministry shall have the right, in the
event of the failure of the violator to remove the violation within the specified period, to
arrange for removal of the violation at the expense of the violator;
The RD further specifies conditions for treatment discharge and re-use of wastewater.
Omani standards for maximum permissible emission concentrations from stationary sources are
issued under MD 118/2004. Applicable limits for emissions from stationary point sources in the
present project are provided in the table. The key provisions of this regulation as they apply to the
proposed project are presented below:
Article (2): Emission controls have to be provided to all emission sources from the plant in
order to prevent noxious or offensive emissions;
Article (3): Monitoring of emissions from stationary sources have to be conducted and reported
to the Ministry. The Ministry has the right to request to improve the monitoring method and
equipment used in such monitoring;
G-S000-5240-003 HMR Consultants
June 2015 B-2
Petrochemical Plant Sohar Environmental Impact Assessment Report
Orpic and CB&I HMR #3817
Article (4): Necessary action shall be taken by the operator of the facility to eliminate any
harmful effects to public health and nuisance or emission of noxious odours arising from the
work area;
Article (6): The owner shall submit an application to obtain an environmental permit and shall
not commission or operate the plant unless the height of the chimney serving the plant has been
approved by the Ministry that it is sufficient enough to prevent the smoke, grit, dust and toxic
gases from becoming prejudicial to health or nuisance. The minimum stack heights from
ground level shall be as follows:
Power Plants
Plants generated by natural gas 26m
Plants generated by natural gas 35m
Boilers
Boilers generated by natural gas 15m
Boilers generated by natural gas 20m
Incinerators
Medical, municipal and industrial waste 15-20m
For other categories, the chimney height shall be calculated as "2.5 multiplied by the height of
the highest building (in meters) in the concerned establishment complex".
Article (7) – The permit to operate shall be issued for a period of three years, renewable for a
same period within one month from the date of expiry;
Article (10): Any change of ownership or production process of the facility shall be
communicated to DGEA; and
Article (11): Failure to comply with any provisions of this regulation will result in penalties and
the Ministry may close down the establishment if there is prejudice harm to the public health or
environmental damage.
Emission Standards as per MD 118/2004
Pollutant Maximum Permissible limits
General
Grit and dust Dark smoke products of combustion shall not emit smoke
0.050 g/m3
as dark as or darker than shade1 on the Ringlemann scale (20 % opacity)
Flaring
Nitrogen dioxide 0.150 g/m3
Particulates 0.100 g/m3
Unburned Hydrocarbons 0.010 g/m3
Carbon monoxide 0.050 g/m3
Carbon dioxide 5.000 g/m3
Sulphur dioxide 0.035 g/m3
Petrochemical Works
Particulates from catalytic crackers 0.100 g/m3
Sulphur recovery units maximum efficiency 99.9%
Organic compounds from fume recovery units 0.035 g/m3
Hydrogen sulphide 5ppm v/v
Omani regulation issued under MD 421/98 specifies the regulations for septic tanks, soak away pits
and holding tanks in order to protect the land and water resources from pollution, and to achieve
proper health standards. The relevant articles in the regulations are listed below:
Article (3) - Septic Tanks shall only be allowed in institutions and accommodations which
discharge solely domestic wastewater from population equivalents not greater than 150. Any
larger institutions must be served by sewage treatment plants subject to the “Regulations for
Wastewater Re-use and Discharge” of Ministerial Decision Number 145/93;
Article (4) - Septic Tanks may only be installed with the prior approval and consent of the
concerned Municipality;
Article (5) – Septic Tank capacity must be calculated according to the procedures set out in
Annex A and designed according to the criteria given in Annex B of the regulations issued in
MD 421/98;
Article (7) – Septic Tanks must be constructed in such manner and using appropriate materials,
as to ensure that they remain watertight at all times; and
Article (10) – Septic Tanks and Soak away pits must comply with the conditions stipulated in
Article (10) of the regulation MD 421/98.
Presently, there are no Omani standards for ambient air quality. Therefore, MECA recommends the
use of USEPA's National Ambient Air Quality (NAAQ) standards. The NAAQ standards are
presented below.
USEPA National Air Quality Standards
Pollutant Averaging Period Maximum Permissible Limit
Particulates (PM10) 24-hour average 150 µg/m3
24-hour average 35 µg/m3
Particulates (PM2.5)
Annual arithmetic mean 15 µg/m3
3-hour average 0.5 ppm (1300 µg/m3)
Sulphur dioxide (SO2) 24-hour average 0.14 ppm
Annual arithmetic mean 0.03 ppm
Annual arithmetic mean 0.053 ppm (100 µg/m3)
Nitrogen dioxide (NO2)
1-hour average 0.100 ppm
1-hour average 35 ppm (40 mg/m3)
Carbon monoxide (CO)
8-hour average 9 ppm (10 mg/m3)
1-hour average 0.12 ppm
Ozone (O3)
8-hour average 0.075 ppm
Rolling 3-month average 0.15 µg/m3
Lead (Pb)
Quarterly average 1.5 µg/m3
MECA however is currently in the process of developing Omani Ambient Air Quality (OAAQ)
Standards. Although the standards have not yet been promulgated, the provisional standards are
provided as presented in Table.
Ambient Air Quality Standards
Parameters Averaging Period Standard Limits (µg/m3)
NO2 24-hour average 112
SO2 24-hour average 125
CO 8-hour average 6000
H2 S 24-hour average 40
O3 8-hour average 120
HCNM 3-hour average 160
PM10 24-hour average 125
There are no Omani standards for work place air quality. Therefore, United States Occupational
Safety and Health Administration (OSHA) 8-hr limit can be used. The maximum permissible limit
specified by OSHA for respirable particulate matter (PM10) within the workplace is 5,000μg/m3.
The regulations for noise control are applicable to workplace noise levels and ambient noise levels.
The ambient noise standards are issued under MD 79/94 and the limits for ambient noise levels from
industrial sources applicable to the proposed plant (Industrial and Commercial) is summarized in
Table.
Ambient Noise Standard applicable to PC plant
MD 80/94 specifies the regulations for noise pollution control in working environment. These
regulations state that no employee shall be exposed to noise levels exceeding 85 dB (A). If the
workplace noise level exceeds 85 dB (A), suitable ear protection devices shall be provided. The
attenuation of such protection devices shall reduce the noise level to 80 dB (A) or lower.
MD 18/93 specifies the Omani regulations on hazardous waste management. Hazardous waste is
defined as “any liquid or solid waste, which because of its quantity, physical, chemical or infectious
characteristics can result in hazards to human health or the environment when improperly handled,
stored, transported, treated or disposed-off”.
MD 17/93 specifies the Omani regulations for non-hazardous solid waste management.
RD 46/95 provides the framework for the handling and use of chemicals. Relevant articles of this RD
are listed below:
Article 2 states persons involved in manufacture, import, export, transport, handling, storage,
and use of chemicals must satisfy requirements of this RD;
Article 8 states that transport and storage of hazardous chemicals require permits from the
Director General of Civil Defence – Royal Oman Police (ROP);
Article 9 states import, export, transport, or handling of any hazardous chemicals requires
packing in special containers;
Article 11 requires the user of any hazardous chemical to dispose at his expenses empty
container and hazardous wastes, under supervision of the Ministry, per requirements of MD in
force; and
18
Workdays –Daytime: After 7 am up to 6 pm
19
Workdays – Evenings: After 6 pm up to 11 pm
20
Holidays and Night time – After 11 pm up to 7 am
Article 12 requires training and provision of personal protective equipment to staff. It further
requires maintaining records of staff handling hazardous chemicals, quantities, and handling
process.
MD 248/97 provides regulations for the control and management of chemical substances. The
relevant articles promulgated under this regulation are presented below:
Article (2) – Any natural or juridical person who intends to deal with any hazardous chemical
by manufacture, import, export, transport, storage, handling, use or disposal shall apply to the
Ministry, by filling the designated form, obtain the environmental permit after paying the
necessary fees;
Article (4) – Any person dealing with hazardous chemicals shall maintain a valid
environmental permit and chemical safety data as per Annex (2), and shall keep copy of the
permit and the data in a safe place far from where the chemical is kept or transported;
Article (5) – The dealer shall abide to carry out all conditions, follow all procedures specified in
the chemical safety data or any other conditions or procedures required in the environmental
permit or in the Law.
Article (6) – Staff designated by decision of the Minister shall have the powers to examine any
chemical transaction, activity, or conduct necessary tests and investigations to enforce the
provisions of these regulations.
Article (7) – Offenders of the provisions of these regulations shall be liable to penalties stated
in the Law
MD 249/97, amended by MD 281/2003, specifies regulations for the control and management of
radioactive materials. The relevant articles promulgated under this regulation with regard to the
proposed project are listed below:
Article (2) – Any organization intending to import, transport, store or use radioactive materials
or equipment containing radioactive material must apply to the Ministry for a permit;
Article (3) – The organization shall, after Ministry’s approval , provide qualified personnel to
monitor and control radioactive material and ensure that the provisions of this regulation are
complied with;
Article (22) – Permanent storage of radioactive materials shall be permitted only at locations
approved by the Ministry. The organization using these locations should have written
procedures of operations, security facilities, dose rate limitations, notices and labels as per the
specified design model;
B. All radioactive materials shall be adequately shielded, labelled and kept in locked and
secure places to protect them from theft, damage or use by unauthorized persons;
C. Special procedures shall be established for control of the storage facilities keys;
D. Clearly label “Radioactive Materials” both in Arabic and English on each store containing
radioactive materials as per instructions of the Ministry; and
E. The dose rate outside the storage facility shall not exceed 2.5μSv/h.
Waste Management
The basic approach towards SIPA Waste Management prescribed in this Guidance Note is as follows:
Polluter Pays principle;
All generated / transported industrial waste has to be registered by SEU [by Permit or No-
Objection Letter (NOL)];
On-site storage of hazardous wastes is allowed (under Permit or NOL) when off-site solutions
are not available; and
When off-site solutions are available, on-site storage of hazardous wastes is allowed (under
Permit or NOL) for limited time and quantities.
The waste generator is expected to categorize the waste based on best practices for sampling
and analysis. SEU has distinguished four basic categories, viz., household, non-hazardous and
hazardous wastes and construction excavation material / wastes. For the hazardous waste
identification the Basel Convention and the EPA tables are to be used;
Hazardous wastes that are exported from Oman have to follow the ‘Basel route’. The Basel
desk is located in MECA Muscat office; however SEU will be the gateway for application.
SEU identifies the SIPA companies possessing PEP who are generating wastes as responsible
parties for the generated waste. Service providers, subcontractors and transporters can only
formally interact with SEU when they work on behalf of the SIPA company. SIPA companies
will remain responsible as Generators for the waste stored in Liwa and for waste that is
disposed illegally by subcontractors / transporters; and
The transporters of hazardous wastes, hired by the project company, need to possess basic
licenses from MECA, ROP, etc. to be registered. SEU will issue an NOL to transport
consignments to the hazardous waste site at Liwa (Liwa site) if the framework licenses are
present.
This Guidance Note identifies for the waste generator a non-hazardous waste site inside the Sohar
Municipal solid waste facility (that will be called the Sohar waste collection site).
While the Sohar waste collection site is open both during daytime from 7 am to 1 pm and evening
time from 3 pm to 6 pm, SEU allows access only during the daytime. Several areas in the site are
reserved for SIPA companies. The waste generator / transporter must not damage the trees on the site.
Only bagged or properly packed material is only allowed to be dumped at the site. A gate fee of RO
2/- has to be paid. A summary of the guidelines prescribed in this Guidance Notes are listed below:
The type and quantities of the non-hazardous wastes generated within SIPA has to be tracked
for their type and quantities;
The waste generator will have to obtain NOL for every type of non-hazardous waste if the
generator wants to use the Sohar waste collection site or proposes another solution. The NOL
will be valid for a maximum of one year and is not transferrable; and
The Guidance Note further provides templates for the NOL for Disposal of Non-Hazardous Industrial
Waste and for the Manifest for Non-Hazardous Industrial Waste.
Summary of the guideline prescribed in this Guidance Note are listed below:
The waste generator will have to apply for and obtain a Consignment Note (CN) for every
waste type from SEU if the generator wants to use Liwa site. The CN will be valid for a
maximum one year and is not transferrable; SEU accepts only MECA registered transporter
companies that have a permit that is explicitly specific for the consignment under
consideration;
SEU accepts only results from certified laboratories. A parameter passes when the measured
value is within the range of acceptance with a ± 10 % range extension due to measurement
inaccuracies. Results outside the extended acceptance range will be assessed by the SEU on a
case by case basis. Test result reports must include test method, detection limit and accuracy;
Samples that are taken from a consignment need to be representative of that consignment and
are the responsibility of the generator; and
and if the consignment or part of it is not covered by the CN, the waste has to be taken back to
the generator on its costs.
The Guidance Note provides templates for the CN and manifest for registering the transportation of
hazardous industrial waste.
This Guidance Note categorizes the chemicals substances as non-hazardous, hazardous and extremely
hazardous. Summary of the guidelines prescribed in this Guidance Note is listed below:
A chemical permit has to be obtained from MECA for each chemical to be used. Applications
for chemical permit by a SIPA company are to be submitted to the SEU;
In some cases, SEU will include conditions in addition to those already in the chemical permits
issued by MECA. This will be mostly in the case of extremely hazardous substances;
The Guidance Note further provides a comprehensive guideline on chemical storage best practices
during construction and operation and for the storage facilities and equipment.
This Guidance Note lays down the requirements of the Seveso-II Directive to be considered for
analysis of the safety aspects of the industrial project within SIPA. Seveso-II Directive covers all
necessary elements for the prevention of a major accident in an industry. Two kinds of so called
Seveso companies are identified, viz., lower tier / tier 1 and higher tier / tier 2. The difference between
the two tiers is based on the amount of dangerous substances. The tier 2 companies must provide a
safety report to demonstrate that the company controls the chance of a major accident and its potential
consequences.
The Guidance Note also provides Seveso classification for industries in SIPA. SEU has defined two
phases in order to implement the Seveso-II Directive in SIPA. The initial phase will involve the
following:
Development of Major Accident Prevention Policy (MAPP). MAPP will include a definition of
the companies’ own acceptable level of risks and tables for likelihood and severity, including a
risk matrix. MAPP is to be reviewed annually and updated;
Development of a Safety Management System (SMS) to implement the MAPP. SEU suggests
the NTA 8620 as a useful tool for the SMS. This document presented in the Guidance Note and
is also available with SEU. SEU will email a copy of this tool upon request;
Conducting Hazard Identification and Risk Assessment (HIRA) study. Based on the HIRA
study a Maximum Credible Accident (MCA) scenario can be identified;
Development of an Emergency Response Plan (ERP). The ERP will be based on the MCA
scenario. SEU suggests through the Guidance Note that the ERP must be practiced at least
twice a year and one of the exercises to be carried out in coordination with SIPC. Every
exercise must be based on a realistic scenario and must be evaluated; and
Preparation of a list of hazardous substances used in the company (HSL). The up-to-date HSL
must be present at the company to ensure the emergency services have direct access to at least
the current information within an installation of the hazardous substance (list of information to
be displayed or documented is provided in the Guidance Note).
This Guidance Note prescribes requirements related to the EIA study for companies planning new
development or modification in existing facilities within the SIPA. Further, guidelines on
Environmental Review (ER) and requirements of IPPC and Seveso-II are also provided.
SEU will assess the requirements for the PEP when a company establishes a new industrial activity or
will implement major change in its facilities. This process has the following phases:
Initial Assessment resulting in an No Objection Letter (NOL) for proposed activity in the
proposed site;
Screening to verify the need for the EIA and categorize the company as per the IPPC and
Seveso-II Directives;
Scoping, identifying the topics that need to be studied in the EIA (the Terms of Reference for
the EIA) and identifying requirements for IPPC and Seveso-II;
EIA Criteria
The guidelines indicates that all petrochemical and metal sector activities in the SIPA requires an EIA
study as the impact on environment is considered to be significant and industrial safety issues are
involved. It also specifies the need for EIA scoping report. Further an EMP is required to be provided
as a separate document and not as a chapter of the EIA report.
IPPC Criteria
The Guidance Note makes a note that not all companies within SIPA will be IPPC company, i.e., not
all SIPA companies will come under the purview of IPPC. The criteria for IPPC companies are
provided in EU’s IPPC Directive (Directive 2008/1/EC). The directives are provided in Annex I of
Directive 2008/1/EC (refer Section 2.4).
Seveso-II Criteria
The Guidance Note briefly explains the classification of Seveso-II companies, viz., Tier 1 and Tier 2
companies, depending on the amount of particular substances a company has (stores or uses) on site.
In the Tier 2 category, the companies are required to provide a safety report (SR) that describes the
SMS and the MAPP.
The proposed project area is located in SIPA which is designated for industrial development.
Therefore, large part of this area is altered and impacted due to industrial development and other
activities. The proposed project location and its vicinity is highly altered and is covered with
halophytes (plants that can tolerate saline soil conditions) indicating saline soil conditions. The
vegetation is dominated by two main species viz. Suaeda vermiculata and Salsola imbricata of
Chenopodiaceae (Salt Bush) family. These bushes are 2m wide, 1 m high thickets within the site.
Regional Settings
As mentioned the proposed project is located in SIPA near Sohar Port, which is one of the important
commercial ports of North Batinah region in Oman. Al Batinah region is important agriculture area in
Oman known for khwars and mangrove forests of national importance. Most of the khwars and
mangrove forest areas are declared or proposed as National Nature Reserves or National Resource
Reserves. The most prominent of them are the mangroves of Khawr Shinas and Khawr Harmul. The
mangrove forests in the region, characterized by homogenous stand of Avicennia marina, are known to
harbor a population of White-collared Kingfisher (Halcyon chloris kalbaensis) (HMR 2010,
Unpublished report). Apart from mangrove forests, other important habitats found here include large
woodlands of Acacia tortilis and Prosopis cineraria, which also is a home to great diversity of birds
and mammals. The Indian bark gecko (Hemidactylus leschenaultii) was recently reported for the first
time in Arabia and appears to be restricted to mature Acacia tortilis woodlands along Al Batinah coast
(Gardner, 1992).
Local Settings
The proposed site is located within Sohar Industrial Port Area, where natural landscapes and habitats
have undergone transformation due to developmental activities and industrialization. Most of the
habitats are altered and heavily impacted due to industrial development. There are few pockets outside
the port area which support woodlands and open scrub vegetation. The woodlands typically shows
presence of consisting of Acacia tortilis, Ziziphus spina-christi and Prosopis cineraria.
The ecological assessment was carried out at the proposed site and its vicinity during November 2014.
The assessment was undertaken to fulfil following objectives,
To document and enlist flora and fauna
To assess the impact of flora, fauna and associated habitats within study area
Information was gathered by walking through transects covering entire site. Systematic efforts were
made for documentation of flora and fauna present within the site. Wherever possible various floral
and faunal elements were photo-documented.
G-S000-5240-003 HMR Consultants
June 2015 E-1
Petrochemical Plant Sohar Environmental Impact Assessment Report
Orpic and CB&I HMR #3817
Field guides such as Common Birds in Oman, Wild Plants of Oman were used for confirming
identification of the species of birds and plants. Secondary sources of literature were used to
complement findings of the field based assessment.
Terrestrial Flora
During the study 16 species of plants (including trees, shrubs, herbs and grasses), which belong to 11
families were observed within the site and its immediate vicinity. It includes 2 Chenopodiaceae
members’ viz. Suaeda vermiculata and Salsola imbricata which dominate the vegetation. These two
species constitute approximately 80 to 90% vegetation found in the site.
The only tree species present at the site can be either Acacia tortilis or Prosopis juliflora; it could not
be identified since it was completely desiccated. Other species are shrubs or sub-shrubs. A sedge
Cyperus conglomeratus and two Poaceae members (Grass Family) includes Cymbopogon sp. and
Cenchrus sp. Other associate species include Lotus garcinii, Cyperus conglomeratus, Indigofera sp.
However their number is much lower than that of Chenopods. Fagonia indica were also observed
occasionally amongst bushes of Indigofera sp. and Lotus garcinii.
Some parts of the site such as the northern and southern corners appear to have retained some natural /
original vegetation which consists of Aerva javanica, D. glaucum, Heliotropium bacciferum and
Acacia sp. The northern corner has number of D. glaucum bushes. During the study all D. glaucum
plants were in bloom and number of bees was observed on the small yellow flowers.
The site has an embankment on western and southern side. The slopes of the embankment on the
western side also support non-halophytic vegetation. This includes propagules of Acacia or Prosopis
juliflora, Aerva javanica, Cleome austroarabica, tufts of Cymbopogon sp. etc.
A detail list of various species observed during the study is given in a table below with comments
about their abundance and IUCN status.
Terrestrial Fauna
Suaeda and Salsola species provide main vegetation cover for the fauna found at the site. A number of
burrows and indirect evidences of animals were observed during the study. Many of these burrows
were present under large thickets of the salt bushes.
A few Pristrus geckos and 2 or 3 individuals of Lacertid Acanthodactylus were observed during the
study. Apart from direct sightings of reptiles, a number of burrows of various sizes were observed
within the site. It is quite possible that burrows (like the one shown below) are being used by species
of rodents. However there were no other evidences to confirm the species. Apart from these animals
feral dogs may be using this area.
Other fauna includes birds – these are mostly common birds found in this part of the country and are
limited to 5 to 6 species. These include Laughing Dove, Collared Dove, Little Green Bee Eater, House
Sparrow, Rock Dove and Yellow Vented Bulbuls were observed in and around the site. The site does
not support any fauna i.e. mammal or bird or reptile which is of high conservation importance
nationally and globally.
The site is a degraded and altered ecosystem as is indicated by vegetation composition and present
status of the vegetation. Most of the area is covered by salt bush thickets and a large number of
thickets have dried up or desiccated. About 75% vegetation is represented by dry and desiccated
Suaeda and Salsola bushes. The proposed site does not have any plant species or communities that are
rare or threatened or endangered in Oman or within Arabian Peninsula. All species found at the site
are of common occurrence across the country and none has restricted distribution. Some of the species
found are also considered as weeds.
Some parts of the site appear like waste land owing to presence of refuse and debris. The site does not
harbour any reptile or mammal fauna of great ecological or conservation significance. The geckos and
birds that were observed at site during the study are common species, which has wide range of
distribution across the country.
Various ecological impacts due to proposed project will include loss of vegetation and loss of habitat
for existing floral and faunal assemblage. However this will not be significant since site does not have
any unique or endemic flora or fauna.
In general there are no ecological sensitivities at the site that will be lost whilst implementation of the
proposed project. Loss of vegetation can be compensated by planting native tree species during
landscaping work. Measures such as creation of vegetation screen using native vegetation can be
considered during landscaping work. This will add to biodiversity of the area.
References
1. Eriksen H., & Eriksen J., 2005; Common Birds in Oman – an identification guide, Al Royal
Publishing
2. Ghazanfar S. A., 1998; Status of Flora and Plant Conservation in the Sultanate of Oman,
Biological Conservation 85 (1998) 287-295
4. http://www.eoearth.org/view/article/153201
6. Pickering H. & Patzelt A., 2008; Field Guide to the Wild Plants of Oman, Kew Publishing,
Royal Botanical Garden, Kew Winbow C., 2008; The Native Plants of Oman: An
Introduction, Environmental Society of Oman
The project site falls under the North Al Batinah Governorate, which lies between Khatmat Malahah
in the north and Al Musanaah in the south and is confined between the Al Hajar Mountains in the
west and the Oman Sea in the east. It is located within the Sohar Industrial Port Area (SIPA), which is
part of the Wilayat of Liwa and is characterized by the industrial land use.
There are 10 villages lying within 5 km radius of the Project Influence Area (PIA) as presented in
Table below and depicted in the figure. Out of these 10 villages, 7 come under the Wilayat of Liwa
and 3 are part of Wilayat of Sohar. Analysis of all aspects of the socio-economic profile was carried
out at the micro level entailing these individual villages as well as the PIA as a whole.
Villages within PIA
Approximate
# Village Wilayat Direction from Plant
Distance from Plant
1 Harmul 4 N
2 Al Mukhaylif 3.5 NW
3 Uqdat Al Mawani 3 NW
4 Wadi Al Qasab Liwa 2.0 NW
5 Al Hadd 1.1 SW
6 Al Ghuzayyil 1 SW
7 Ghadfan 2.5 S
8 Al Khuwayriah 2.0 E
9 Majees Sohar NE
10 Amq SE
Source: HMR Archives and Google Earth
There are also various industries in the contiguity of the plant as presented in Table below.
PIA – An Overview
The land use in the PIA exhibits agricultural plots, plantations, open and built up areas including
settlements and SIPA alongside a vast fishing ground along the Al Batinah coastline. In addition, there are
limited pastures for animal rearing and areas where fertile soil is utilized for cultivation of vegetables and
plantations.
Agriculture is one of the major sources of employment for people in this area especially cultivation of
date palm, vegetables and citrus fruits. Dug wells are still the main source of irrigation even though most
of these wells and groundwater supplies have been contaminated by salt-water intrusion. As a result, a
considerable number of date palm plantations adjacent to the SIPA have been abandoned due to increased
salinisation. Treated or desalinated water is also used to irrigate some of the agricultural lands in the
vicinity of SIPA.
Some of the local population rears animals like goats mostly for domestic consumption. Although there
are areas within the villages that supports grazing (natural vegetation in the form of shrubs and small
trees), animal fodder is usually purchased from the local market and livestock are fed in temporary sheds
(either in homes or farms).
Fishing is a significant part of the economy as fish is an essential part of the daily diet of the community.
There are number of fishing areas rich in important marine species in the vicinity of the project area.
Some of the chief species found here include Kingfish, mackerels and sardine. Majees and Harmul are
considered as fishing settlements.
Land Ownership
As per the RD 80/2002, approximately 2000 hectares of area was declared as Sohar Industrial Port Area.
Therefore there are no traditional rights over the project site. However, the community has traditional
rights for grazing and fishing.
Settlement Pattern
Most of the settlements are positioned in such a way that they have an easy access to the highway for
connectivity, and simultaneously they are also in the vicinity of marine sources. Majees is situated along
the coast and exhibits fishing village characteristics. Except for Al Khuwayriah, which is isolated from the
rest of the villages, there is no physical demarcation of the boundaries for the villages located along the
main highway. Housings units are placed along the internal roads in such a manner that the units are
located in proximity to each other.
Demographic Profile
The demographic profile of local population is analysed based on parameters including population
numbers and its composition.
Population Distribution
Based on the 2003 Census Al Batinah region is considered as the largest populated region in Sultanate’s
with 27.92% of the total population. As per the census 2003 the total population of Al Batinah region was
653,505. However, in 2010 census the population increased to 772,590 and hence accounts only 27.86%
of the Sultanate’s population after the Muscat Region. During 2003-2010 the population growth rate of Al
Batinah region is 18.22% while the average annual growth rate is recorded as 2.60%.
Out of the twelve Wilayats Sohar acts as a Regional center and is the most populated Wilayat with
18.12% of Region’s total population (Census 2010). However, Liwa, the adjacent Wilayat of Sohar which
conceives the major industrial development of the country (including the project site) has total population
of 34,001 and is considered amongst the sparsely populated Wilayats of the Region. It constitutes less
than 5% of the Region’s population.
Population Distribution of Liwa and Sohar
Population Decennial
Region / Wilayat / No. of Population
Land Area
Town Households Male Female Total Growth
(2003 – 2010)
Batinah Region 12,500 km2 106,465 434,032 338,558 772,590 18.22%
2
Wilayat of Liwa 728 km 4,190 19,999 14,002 34,001 31.91%
Wilayat of Sohar 1728 km² 20,886 85,346 54,660 140,006 34.20%
Demographic aspects of the study area are assessed based on the population figures reported in the 2010
census. The population (M = Male; F = Female; T= Total), the total number of families and the average
family size of the identified settlements within the study area is presented in table below
Human Settlements within 5km Radius from PC
Total 11315 45258 56573 20905 5953 26858 32220 51211 83431 - -
The average family size in the settlements within the study area is around 7 persons / family which lower
than the family size of Wilayat Liwa and Sohar. Since the age wise population information for each
settlements as well as for Region and Wilayat for census 2010 are not available from any of the published
government reports / documents, the regional level and Wilayat level census (2003) information is used to
appraise the age structure of the study area. Reportedly, the Region had almost 38% of its population in
the age group of 0-14 during 2003. The age group of 15-64 years constitutes 59% of the regional
population whilst the ratio of elderly above the age group of 65 years is relatively less (3%).
Social Infrastructure
Housing
Along the existing Batinah Highway and around the Sohar Port area, large numbers of multi-
storeyed buildings with both commercial and residential use have been constructed in recent
years. Within the study area, new / modern villas have come up. Overall, there is a good mix of
old / traditional housing units and new/modern buildings. Ministry of Housing has planned two
locations for future residential development apart from a large planned residential area near the
existing Batinah Highway, just north of the SFZ.
In terms of number of rooms, villas are the largest units, followed by Arabic houses. Apartments
and rural houses are small with 3-4 rooms on an average.
About 87% of the houses in the Liwa are occupied on ownership basis. This indicates a smaller
share of working / migrant population occupying about 13% houses on rental basis. It is about
60% on ownership basis and 40% houses on rental basis in Sohar Wilayat. However, the scenario
may change with significant industrialization and development of Port Sohar. This is also evident
from the construction of many apartment buildings in the area adjacent to the highway.
As per the existing land-use plan for Al Batinah Region, residential land-use in Wilayat Liwa is
about 368 ha and gross residential population density is 84 persons per ha and in Wilayat Sohar it
is about 1105 ha and gross residential population density is 114 persons per ha. However the
concentration is much higher in the settlements located eastern side of the plot within the study
area.
Health
Ministry of Health (MoH) is the main provider of health services; however there are private hospitals and
clinic to provide health services. MoH provides five categories of health services. Sohar hospital is the
nearest regional hospital to the study area and providing the primary and secondary health care for entire
North Al Batinah Governorate. In terms of coverage, Liwa Wilayat has two health centres. However there
are no in-patient facilities available for the entire Wilayat. Available primary health facilities for 10,000
population in the Wilayat is 0.6 which is relatively equal with the national average.
People of the study area have to depend on the health facilities of Sohar for treating critical illness. Health
institutions of Sohar have a provision of almost 28 hospital beds per 10,000 populations, which is above
the global average (27). However, considering that Sohar hospital caters to the region, the availability of
beds is rather limited. Table presents the health facilities in Sohar and Liwa Wilayat.
Health Facilities in Liwa/Sohar Wilayat
Total Hospitals
Year of Facilities Beds for
# Hospital Population No of for 10,000
establishment available 10,000
beds population
1 Liwa Health Center 1984 L, R
29,606 Nil 0.6 0
2 Nabr Health Centre 2007 R, L
Sohar Hospital
3 1973 363 D, R, L
Regional Hospital
4 Wadi Hibi local Hospital 1993 18 D, R, L
5 Wadi Ahin Health Center 1993 0 L
124,643 0.4 28.5
Sohar Extended Health
6 1997 0 R, L
Center
7 Al Multaqa Health Centre 2004 0 R, L
8 Al Uwaynat Health Centre 2007 0 R, L
L-Laboratory, R-Radiological Procedure: Source: Annual Health Report
Private hospitals play a significant role in the health care system. Private hospitals are licensed hospitals
by MoH under the direct supervision of respective regional directorates. Nearest private hospitals is at
Falaj al Qabail. However, private clinics are providing primary health care services.
Education
The fundamental principle of Oman education policy is to achieve equity between its citizens and
expatriates in general education and the provision of a free general education up to grade twelve for all
citizens and Arabic speaking expatriates and to set laws and regulations regarding work in government
and private education institutions.
In Liwa Wilayat, total number of schools available for 10,000 population is 4.2 which is greater than the
national average of 3.7. In Sohar Wilayat, total number of schools available for 10000 population is 3.5
which is lower than the national average. The total enrolment rate of the wilayat is 80% which is lower
than the national and regional average. In the entire wilayat 41 schools are available of which 23% of
schools are providing the first cycle of basic education, 28% of the schools are providing second cycle of
basic education,5% of schools are providing post basic education. 13% of the schools are providing
complete general education and 38% of schools provide mix grade education.
Activities
Camel Racing - This sport has sustained itself and grown since HM The Sultan instituted a number of
measures to encourage it. It has a strong following in the Batinah Region, including Wilayat Liwa. It is
now a spectator sport enjoyed by a large section of the community including expatriates as well as foreign
tourists. However it requires an active local group of camel breeders to sustain it and improve local results
in competitions, which include local camels racing in big events in the UAE. Thus any reduction in
available grazing will reduce the opportunity for local breeders to succeed in the sport.
Places for Rural Recreation. The foothills of Jebel Shaykh have areas of dense pre-Islamic grave clusters
from the Hafeet and Wadi Suq periods, giving a historical dimension to valuable natural landscapes. This
was identified as an important recreational resource in the original Sohar Industrial Master Plan (SIAMP),
although the proposed ‘Green Belt’ areas were shown only with indicative colouring and not included
within the Plan boundaries. This example was chosen to publicly launch a Green Belt Policy for Oman in
the Ministry magazine ‘Man and the Environment’. However, no further action has since been taken to
identify, designate and implement green belt areas. Destruction of the scenic values of such cultural
landscapes leads to a loss of amenity for the inhabitants of the
Northern Batinah Region, especially those in Liwa including expatriate employees. Despite the lack of
formal facilities for local tourists in the region’s countryside, Omanis enjoy taking their families on
outings in the countryside on Thursdays or Fridays.. Much opportunity has already been lost, so it is
doubly important to retain what remains for the general standard of living and amenity of the locals.
Physical Infrastructure
Water Supply
The general groundwater flow in the region is towards the Oman Sea. The groundwater gradient is steady
throughout the Al Batinah Coastal Area. Using the most recent statistics, the World Bank reported that in
year 2000, about 82% of the population of Oman had access to treated water. The ground water is often
the only source of fresh water in this region. Extensive ground water withdrawal along the coastal strip,
mainly for irrigating crops in excess of natural replenishment results in a progressive lowering of the
water table and thus a sustainable water supply is endangered or even impossible.
In the Al Batinah Coastal Area, the water table in coastal aquifer currently declines by a rate 0.5m to 2.0
meters per year. This over-exploitation leads to intrusion of sea water in coastal areas resulting in
increasing salinity of ground water aquifer. Thus not only ground water, but also the quality of ground
water is highly endangered. Despite high evapo-transportation rate, there is still opportunity for
groundwater recharge since rainfall occurs in storms on very few rain days and because the infiltration
capacity of coarse alluvium and fissured rock is high. Oman is also keen to restore the depleted ground
water and therefore have already constructed number of recharge dams in the Al Batinah area. MoWR is
also planning to construct more check dams for recharging, so that the stored ground water is used in case
of emergency through construction of emergency water supply network and storage reservoirs.
Sultanate of Oman had opened up and privatized the power and water sector in 1999. This was considered
part of Omani economic reforms that have taken place since the third and fourth five years plans
instigated by the Government. Due to this initiative power generation plants and desalination plants have
been constructed on Build Own and Operate (BOO) basis. As per the agreements, power and bulk water is
produced at private owned power and desalination plants and is sold in bulk quantities to the respective
authorities based on the fixed tariff rates decided by a regulatory authority.
Sohar Power and Desalination Plant (Sohar – I) was the second plant commissioned. It came to operation
in the year 2007. It is also owned by the private sector. The Project has been constructed on the basis of
BOO agreement. This plant supplies drinking water to Shinas, Liwa, Sohar, Saham, Al Khabourah and
Suwayaq Wilayats of North Al Batinah Governorate. It has four Multi Stage Flash (MSF) desalination
units installed each with a capacity of 37,500 cubic meters per day. Water from the desalination plant is
transmitted to Project Area through transmission mains. The maintenance of the, pump house and
reservoirs is a responsibility of the Public Authority for Electricity and Water (PAEW). The transmission
lines are distributing the water from Sohar and Barka Integrated Water and Power Plant (IWPP) reservoir
to different service reservoirs in planning area. Water from the various desalination plants is transmitted to
residential and commercial areas through transmission mains. The maintenance of the, pump house and
reservoirs are the responsibility of the PAEW. The transmission lines are distributing the water from
Sohar IWPP reservoir to different service reservoirs.
Details of Transmission mains to North Al-Batinah
Transmission Length of the transmission
Wilayat’s covered Connected with
line line in the Project Area (Km)
DN700 &1200 STEEL,
Buraimi line 29.78 Sohar, Liwa (part)
DN 700 MS
DN 600 DI, DN 600, 700
Shinas line 48.6 Liwa (part),Shinas
&1200 DI
Liwa(part),Sohar,Saham, DN 1200 MS, DN 1000
Suwayq line 134.9 Al Khabourah, As MS PIPE, DN 900 MS
Suwayq PIPE
Power Supply
The power sector of Oman has undergone significant structural changes to promote and infuse private
capital. The residential sector is the largest consumer category, which consumes more than half of the
total production. Reportedly, total number of registered electricity customer in Oman was 597,323 in
2008. Major supplier of power in the study area is Sohar Power and Desalination Plant Phase -1. This is a
gas based power generating and desalination project with capacity of 585 MW power generations. Oman
Electricity Transmission Company (OETC) is responsible for transmitting the power from generation
plant to distribution lines. In Oman total power supply system is divided into three division i.e. Main
Interconnected System (MIS), Salalah system and Rural Areas system. MIS has 220kV and 132 kV
capacity lines in the Northern Region of Oman and its service area is approximately 130,000 km2. The
PIA is located under the areas of MIS and serves around 500,000 consumers. The Grid consists of about
686 km of 220 kV circuits, 2,838 km of 132 kV circuits and 38 Grid stations.
Sultanate of Oman provides a considerable subsidy to the electricity sector. Residential customers enjoys
the maximum benefits since it accounts for the largest share with respect to all other customers. To
encourage comprehensive development in the Sultanate of Oman, the government also provides subsidy
to all other customers such as commercial, industrial, agricultural, fisheries, tourism and hotels. The
commercial tariff of 20 baiza per KW/H without maximum consumption limit applies to Showrooms and
Commercial shops and cold stores foodstuff sale, Stores, bakeries, Fabrics and readymade garments sale
shops – pharmacy and fuel filling stations.
Industrial tariff is mandatory for the industrial unit to satisfy the following conditions in order to benefit
from the industrial tariff:
G-S000-5240-003 HMR Consultants
June 2015 F-6
Petrochemical Plant Sohar Envi
Orpic and CB&I
Municipalities are responsible for collection and management of all municipal solid wastes in the Wilayat.
The wastes are collected by Municipality in dedicated collection trucks and transfer to the waste
dumpsites within the Wilayat. The dumpsites are also managed and maintained by the local municipality.
However, the Oman Environmental Services Holding Company (OESHCO) is formed by a Royal Decree
in August 2009, to take over the waste management responsibilities from the municipalities and ensure
proper management of all solid wastes in the Sultanate. Disposal of non-hazardous industrial solid wastes
is responsibility of respective industries and this is usually be channelized through the licensed contractors
of municipalities.
Presently there is no scientific or engineered way of disposal of the hazardous solid wastes and is
currently being stored within the generating facilities. However, for the SIPA, a centralized hazardous
waste storage yard has been constructed in Liwa and is currently being utilized by the industries.
Furthermore, OESHCO is in the process of developing plans for safe and scientific methods of treatment
and disposal. Based on available information, the main hazardous waste management facility will come in
Adam Wilayat with transfer stations located throughout the country at appropriate locations.
Wastewater Management
Method of transportation of wastewater in the study area is mainly through tankers and the collected waste
is transported to the Sewage Treatment Plants (STP). The treatment of wastewater in the STPs is based on
the conventional method of aeration and trucks to the various waste dumpsites for disposal carry the
sludge from the STPs away. Currently there are no common effluent treatment plants in the Sultanate that
receives industrial wastewater; however, Majis Industrial Services Company SAOG (MISC) has taken up
the responsibility to collect treated industrial wastewater, which is meeting the standards recommended in
RD 115/2001, from the individual industries within SIPA. MISC is currently evaluating various options of
applications of the treated industrial wastewater to conserve the water and use it most appropriately. Other
industries outside these industrial areas, the most prominent being the Aluminum Smelter and the
independent water and power plants in Barka, have installed their own dedicated treatment plants within
the facilities.
Air Emissions
Dust Emission fromTrucks traveling at the site (Unpaved Roads)
For emission estimation, truck emissions/day froma total of: 100 km/day
The PM/dust emissions will be calculated based on unpaved road using equation (1a) contained in USEPA
AP-42 emission factor document entitled "Unpaved Roads - Miscellaneous Sources" contained in Chapter 13.2.2
The following equation applies to vehicles traveling on unpaved surfaces at non-publicly accessible roads.
Therefore, for 100 kmper day traveled by trucks at the project site, the dust suspension may be
estimated as follows:
PM2.5 47.6 lbs per day
21.6 kg per day, uncontroled
6.5 kg per days, after water spraying of the roads
Air Emissions
Mobile Sources
From Appendix H: Highway Mobile Source Emission Factor Tables from USEPA AP-42 Volume -II for heavy duty
diesel powered vehicles, the following equation may be used:
BER (g/mile) = ZML (zero mile level, g/mile) + {(DR-g/ml/10kmiles) X M(cumulative mileage/10k miles)}
For a total of 100 kmper day, the following emissions may be estimated per day
HC = 130 g/day
CO = 643 g/day
NOx = 403 g/day
Category Definition
Certain Will occur under normal operating conditions.
Very likely Very likely to occur under normal operational conditions.
Likely Likely to occur at some time under normal operating conditions.
Unlikely to but may occur at some time under normal operating
Unlikely
conditions.
Very unlikely to occur under normal operating conditions but may occur in
Very unlikely
exceptional circumstances.
Severity Definition
Persistent severe environmental damage or severe nuisance extending over
Massive a large area;
Constant, high exceedance of statutory or prescribed limits (representing a
threat to ecosystem in both the long and short term);
In terms of commercial or recreational use or nature conservancy, a major
economic loss for the company.
Severe environmental damage;
Extended exceedance of statutory or prescribed limits;
Major
The company is required to take extensive measures to restore the
contaminated environment to its original state.
Release of quantifiable discharges of known toxicity;
Moderate Instances exceedance of statutory or prescribed limit;
Causing localized nuisance both on and of site;
Staining;
Minor No permanent effects to the environment;
Single exceedance of statutory or prescribed criterion;
Single complaint.
Slight Local environmental damage
Within the fence and within systems
Negligible financial consequences
Some beneficial improvement to human health.
Modest Some benefits to individual livelihoods (e.g. additional employment
Benefit opportunities).
Limited improvements to community facilities/utilities (e.g. no discernible
improvement).
Some impact on the wider economy (e.g. limited local procurement).
Significant Major beneficial improvement to human health.
Benefit Large scale benefits to individual livelihoods (e.g. large scale employment).
Major improvements to community facilities/utilities.
Notable impact on the wider economy (e.g. extensive use of local supplies).
The resultant impact (consequence) is defined as the multiplication of severity and duration or
likelihood. Accordingly, from the assessment matrix, the resultant impacts are classified as low,
medium, and high. These terms are explained as follows:
Low impacts are considered to be acceptable or within ALARP levels. Further control measures are
not required to mitigate these impacts.
Medium impacts are those requiring control measures; management plans need to be implemented so
as to mitigate the impacts to ALARP levels.
High Impacts are those requiring additional studies for such impacts, alternative activities with lower
impacts or alternative locations with lower environmental sensitivities or compensatory measures
need to be considered during the detailed design stage of the project.
Construction
Receptors
Community Infrastructure
Public and Worker Safety
Archaeology and Culture
Geology and Soil Quality
Population in Vicinity
Marine Environment
Activity
Operation
Receptors
Community Infrastructure
Public and Worker Safety
Archaeology and Culture
Geology and Soil Quality
Population in Vicinity
Marine Environment
Ecology and Wildlife
Noise and Vibration
Activity
Natural Resources
Water
Operation and Maintenance Phase
Map 4: Overall Industrial Cluster in Sohar Area and Proposed plot Location
CB&I ORPIC
Document Title: Process Description – NGLT 1100, RDG 1200, SCU 2000 –
2600 and SLC4HY 2800
Page 1 of 41
"THIS DOCUMENT IS THE PROPERTY OF CHICAGO BRIDGE & IRON COMPANY (CB&I). IT MAY CONTAIN INFORMATION
DESCRIBING TECHNOLOGY OWNED BY CB&I AND DEEMED TO BE COMMERCIALLY SENSITIVE. IT IS TO BE USED ONLY IN
CONNECTION WITH WORK PERFORMED BY CB&I. REPRODUCTION IN WHOLE OR IN PART FOR ANY PURPOSE OTHER THAN
WORK PERFORMED BY CB&I IS FORBIDDEN EXCEPT BY EXPRESS WRITTEN PERMISSION OF CB&I. IT IS TO BE SAFEGUARDED
AGAINST BOTH DELIBERATE AND INADVERTENT DISCLOSURE TO ANY THIRD PARTY."
Liwa Plastics Project
Page 2 of 41
Liwa Plastics Project
Table of Contents
Contents Page
1.0 INTRODUCTION..................................................................................................................................5
2.0 DEFINITIONS ......................................................................................................................................6
3.0 SCU DESIGN CASES..........................................................................................................................6
4.0 NATURAL GAS LIQUID (NGL) TREATING AND FRACTIONATION UNIT..........................................7
4.1 NGL Deethanizer ......................................................................................................................7
4.2 Acid Gas Removal ....................................................................................................................8
4.3 Regeneration ............................................................................................................................8
5.0 REFINERY DRY GAS (RDG) TREATING UNIT ...................................................................................9
5.1 Refinery Dry Gas Compression ...............................................................................................9
5.2 RDG Amine/Water Wash Column ..........................................................................................10
5.3 RDG Caustic Treatment and Oxygen Converter ...................................................................10
5.4 Mixed LPG Drying ..................................................................................................................12
5.5 Refining Dry Gas Chilling & RDG Demethanizer...................................................................13
5.6 RDG Deethanizer ....................................................................................................................13
5.7 RDG Depropylenizer...............................................................................................................14
6.0 AMINE REGENERATION UNIT .........................................................................................................14
6.1 Amine Feed.............................................................................................................................15
6.2 Amine Regeneration...............................................................................................................15
6.3 Amine Preparation, Drain and Storage..................................................................................16
6.4 Amine Reclaiming ..................................................................................................................16
6.5 Acid Gas Treatment ...............................................................................................................16
7.0 STEAM CRACKER UNIT...................................................................................................................16
7.1 Furnace Feed System ............................................................................................................17
7.2 Cracking Heaters....................................................................................................................18
7.3 Gasoline Fractionator ............................................................................................................20
7.4 Quench Tower ........................................................................................................................22
7.5 Process Water Stripping and Dilution Steam Generation ....................................................23
7.6 Charge Gas Compression (Stages 1-2) .................................................................................24
7.7 Acid Gas Removal ..................................................................................................................25
7.8 Charge Gas Compression (Stage 3) ......................................................................................25
7.9 Spent Caustic Pretreatment...................................................................................................26
7.10 Charge Gas and Liquid Condensate Drying .........................................................................27
7.11 Regeneration System.............................................................................................................27
7.12 Depropanization and Acetylene Hydrogenation ...................................................................28
7.13 Charge Gas Chilling ...............................................................................................................30
7.14 Demethanization ....................................................................................................................31
7.15 Deethanization........................................................................................................................31
7.16 Ethylene Fractionation...........................................................................................................32
7.17 MAPD Conversion ..................................................................................................................33
7.18 Propylene Fractionation.........................................................................................................33
7.19 Propylene Product System ....................................................................................................34
7.20 Debutanization .......................................................................................................................35
7.21 Propylene Refrigeration System............................................................................................36
Page 3 of 41
Liwa Plastics Project
Page 4 of 41
Liwa Plastics Project
1.0 INTRODUCTION
Oman Oil Refineries and Petrochemicals Industries Company (ORPIC) currently operates an oil refinery,
aromatics plant (AP) and polypropylene (PP) plant at its complex located within the Port of Sohar Oman.
The refinery includes 115,000 barrels per stream day (BPSD) Crude Unit, an 80,000 BPSD Residue Fluid
Catalytic Cracking (RFCC) unit that operates in a maximum olefins mode, an indirect Alkylation Unit, a
TAME Unit and various hydroprocessing and treating units. The AP processes naphtha and produces
820,000 tonnes per year of Paraxylene and 200,000 tonnes per year of Benzene. The PP plant processes
the propylene produced in the RFCC unit and can produce 350,000 tonnes per year of polypropylene.
ORPIC is currently executing a major project to improve the Sohar Refinery, which is referred to as the
Sohar Refinery Improvement Project (SRIP). The project involves the installation of a new Crude Unit,
Vacuum Unit, Hydrocracking Unit, Delayed Coking Unit, Isomerization Unit, Hydrogen Plant and Sulphur
Recovery Facilities. The project is currently in the detailed engineering phase and is expected to be fully
operational by the end of 2016.
In addition to SRIP, ORPIC is planning the installation of a new Petrochemical Complex to be called Liwa
Plastics Project (LPP) adjacent to SRIP that will include a Steam Cracker Unit (SCU) designed to produce
867 kilo tons per annum (KTA) of polymer grade ethylene and 300 KTA of polymer grade propylene,
Refinery Dry Gas Unit, NGL Treating and Fractionation Unit, Selective C4 Hydrogenation Unit, MTBE Unit,
Butene-1 Recovery Unit, Pygas Hydrotreating Unit, High Density Polyethylene (HDPE) Plant, Linear Low
Density Polyethylene Plant (LLDPE), new Polypropylene Plant (PP), and associated utility and offsite
facilities. The new petrochemical plant will be integrated with the Sohar Refinery, Sohar AP and Sohar PP
plant.
ORPIC is also planning the installation of a new NGL Extraction plant located in Fahud, Central Oman. The
NGL (C2+) extracted from the natural gas will be transported to the petrochemical complex by pipeline and
used as feedstock to LPP. The new NGL Extraction plant will have independent utility and offsite facilities.
Additional feedstock to LPP are mixed LPG (produced in the Sohar Refinery and Sohar AP), refinery dry
gas produced in the RFCC unit and new Delayed Coking unit (included in SRIP), light naphtha condensate
from OLNG by marine tanker.
Some of the materials produced in the LPP petrochemical complex, including hydrogen, MTBE, pyrolysis
fuel oil and products from Pygas Hydrotreating unit will be returned to the refinery, existing aromatics plant
and polypropylene plant.
The Liwa Plastics Project is strategically located in the Sohar Industrial Port next to the SRIP.
This provides excellent opportunities to:
Synergize with the Refinery by upgrading the lower value Refinery products (LPG) and byproducts
(Refinery Dry Gas) to the higher value plastics while upgrading the Steam Cracker products
(Hydrogenated Mixed C4 to MTBE) and byproducts (Raw Pyrolysis Gasoline, Pyrolysis Fuel Oil) in the
Refinery to gasoline and provide valuable hydrogen.
Synergize with the Aromatics Plant by recovering aromatics from the Steam Cracker byproduct (Raw
Pyrolysis Gasoline).
Convert the lower value NGLs from OLNG to the higher value plastics.
Convert the lower value NGLs recovered from Natural Gas in Central Oman (Fahud) to the higher
value plastics.
Give a major boost to plastics production in Oman and provide excellent job opportunities to the local
Omani population.
Page 5 of 41
Liwa Plastics Project
This document covers the process description for the Steam Cracker Units (1000-2600 and 2800) of the
new Liwa Plastics Project in Oman.
2.0 DEFINITIONS
The following terms and abbreviations have been used in this document:
Term Definition
ARU Amine Regeneration Unit
DCU Delayed Coker Unit
DGA Diglycol Amine
LLP Steam Low Low Pressure Steam
LPG Liquefied Petroleum Gas
LPP Liwa Plastic Project
NGLT NGL Treatment
ORPIC Oman Refineries and Petrochemical Company
OSBL Outside Battery Limit
PFD Process Flow Diagram
RDG Refinery Dry Gas Treating Unit
RFCC Residue Fluid Catalytic Cracking
SCU Steam Cracker Unit
SHU Selective Hydrogenation Unit
Case 1: Normal feeds and external recycles as defined in Section 7.1 below.
Case 2: Refinery Dry Gas and Refinery LPG not available, the NGL C2+ is increased 10% and
increase LPG to make minimum 75,000 kg/h ethylene and same propylene as case 1.
Page 6 of 41
Liwa Plastics Project
The top of the NGL Deethanizer operates at a pressure of 20.8 bar(g) which partially condenses overhead
vapor by -10°C propylene refrigerant in the NGL Deethanizer Condenser, E-11003. The tower overhead
pressure is set by a pressure controller (PC) in the gross overhead line, which resets the setpoint of the
flow controller on the feed to the tower. The two-phase stream leaving E-11003 enters the NGL
Deethanizer Reflux Drum, V-11002, where an overhead vapor stream, containing ethane and lighter
components, is sent to the NGL Amine/Water Wash Tower, C-11002, for acid gas removal. Prior to
entering C-11002, the stream is sent to the NGL Amine/Water Wash Column Feed Heater, E-11005 where
the stream is heated to 40°C by controlling the amount of 48°C propylene refrigerant sent to E-11005. Net
liquid from V-11002 is pumped by the Deethanizer Reflux Pumps, P-11001A/B, as reflux to the NGL
Deethanizer, C-11001, on flow control. The level in V-11002 is controlled by throttling the amount of
propylene refrigerant sent to the NGL Deethanizer Condenser, E-11003.
Tower reboiler duty is provided by Low Low Pressure Steam (LLS) in the NGL Deethanizer Reboiler, E-
11002. A temperature controller on Tray #10 sets the temperature by resetting the setpoint of the flow
controller on the LLS feeding the reboiler. The NGL Deethanizer bottoms product, which contains C3 and
heavier components, is cooled to 45°C by cooling water in the NGL Deethanizer Bottoms Cooler, E-11006.
The cooled C3+ stream is sent on flow control, reset by level controller in the tower bottoms sump, through
the NGL COS Treaters, V-11001A/B, for removal of COS and some mercaptans. The stream continues
through the NGL COS Treater Filters, S-11001A/B and is then let down to the desired pressure in a
pressure control valve, and enters the C3+ Feed Preheater, E-20002, located in the SCU furnace feed
system. Downstream of E-20002 is the C3+ Feed Vaporizer Drum, V-20012, on which there is a high level
override level controller to reset the setpoint on the NGL Deethanizer bottoms when high level is reached in
the drum.
An on-line analyzer is provided with probes in two locations which detect the top and bottom specification
of the NGL Deethanizer. One probe detects the amount of C3s found in the C2 and lighter overhead vapor
being fed to the amine wash section. The other probe detects the amount of C2s found in the C3+ feeding
the NGL COS Treaters.
One NGL COS Treater is in operation and operates at a pressure of 11.3 bar(g) while the second treater is
being regenerated or on standby. On-line analyzers are provided to detect the amounts of COS and
mercaptans entering and leaving the treaters. The treaters are designed to run for 48 hours before
requiring regeneration. The process of switching from one treater to the next is a “semi-automated” timed
cycle operation. Prior to switching treaters, it is important to fill the NGL Gas Treater Drain Drum, V-11004,
Page 7 of 41
Liwa Plastics Project
with some of the C3+ product effluent from the treater in operation. Once V-11004 is filled, the liquid is
sent to the standby treater. Then, the online treater is placed in parallel with the standby treater and then
taken offline. The newly off-line treater is drained to the NGL Gas Treater Drain Drum, V-11004, after which
it can undergo regeneration.
Regeneration of the NGL COS Treaters is a two stage approach. In the first stage, hot C3+ vapor from the
C3+ Stripping System is used to strip and recover any C3+ liquid trapped in the pores of the adsorbent.
This stripping step is important because there is a large amount of liquid entrained in the adsorbent pores
even after draining; approximately 20-30% by volume. This material would end up in the fuel gas system
which would alter the molecular weight of the feed stock and result in lost feedstock. Furthermore, when
the pressure is dropped to a level so that the regeneration can enter from the fuel gas system, a
considerable drop in temperature will occur from the flashing of the entrained liquid, also called auto-
refrigeration. At the end of this first stripping stage the resulting temperature in the bed will be 95°C. The
second stage of regeneration is carried out by circulating hot methane-rich regeneration gas from the
treater regeneration system at 290-300°C to drive out the impurities adsorbed in the treater bed. After the
bed has reached the required temperature of 270-290°C, the bed is cooled with unheated regeneration
gas. The spent regeneration gas is returned to the fuel gas system.
The NGL Amine/Water Wash Column, C-11002, runs at a pressure of 19.8 bar(g) and temperature of 42°C
in the overhead. The column is comprised of two sections. The top portion contains 3 bubble cap trays
and serves as a water wash section to avoid amine entrainment in the overhead product. Wash water for
the NGL Amine/Water Wash Column, C-11002, comes from the Continuous Blowdown Cooler, E-20014,
located in the SCU. Waste water from the water section (bubble cap trays) is totally drawn off below the
th
14 tray and is sent to Neutralization (OSBL). The bottom portion is comprised of 13 valve trays and two
packed beds (including a pump-around loop for heat removal) and serves as the amine wash section.
Lean amine, 30 wt.% DGA, is fed to the top of the amine wash section above the valve trays on flow
control. As the vapor continues up the tower the acid compounds (H2S and CO2) will absorb into the lean
amine solution. The bottom of the tower will have a higher temperature, due to the heat of absorption. The
overhead of the NGL Amine/Water Wash Column will contain less than 100 mol ppm CO2 and trace levels
of H2S, and is then sent to the Ethane Feed Preheater, E-20001, in the SCU furnace feed system. Any oils
that form in the absorption process can be skimmed off the liquid level in the sump of C-11002 and sent to
NGL Amine Oil Degassing Drum, V-11006. Overhead vapor from V-11016 is sent to Wet Flare, while any
liquid is sent to the Amine Drain system.
Rich amine, leaving the bottom of C-11002 is sent to the OSBL Amine Regeneration Unit (ARU) on flow
control reset by the level controller on C-11002 at a pressure of 8.0 bar(g) and 63°C.
4.3 Regeneration
As discussed in Section 4.1, regeneration of the NGL COS Treaters, V-11001A/B, is carried out using a
two stage approach. The first stage is the C3+ stripping step which improves feedstock recovery, and
stabilizes the return composition of the fuel gas. A treater is first drained, and then warmed with hot C3+
Page 8 of 41
Liwa Plastics Project
compounds to drive out all the remaining liquid trapped in the pores of the adsorbent and between the
adsorbent particles. The hot C3+ compounds are provided by the C3+ Stripping System which is a
recirculating system.
In the recirculating C3+ stripping system, C3+ liquid is stored in the C3+ Stripping Holdup Drum, V-11007
at a pressure of 9.5 bar(g). The liquids leaving the holdup drum are pumped on flow control by the C3+
Stripping Pumps, P-11004A/B, and vaporized/superheated in the C3+ Stripping Vaporizer, E-11011. The
temperature of the superheated C3+ stripping stream is controlled by throttling the amount of Low Low
Pressure Steam (LLS) flowing to E-11011. The super-heated C3+ stripping vapor is directed to the NGL
COS Treaters, V-11001A/B, for stripping and/or to the C3+ Stripping Condenser, E-11012, via a pressure
differential control valve. C3+ stripping vapor from the treaters (which contains recovered material) is also
condensed in E-11012 prior to entering the C3+ Stripping Holdup Drum. The initial charge of C3+ in this
system is from the NGL COS Treater effluent. Any C3+ compounds recovered during this stripping step
will build up over time in this recirculating system; they are pumped on flow control by P-11004A/B to the
NGL Gas Treater Drain Drum, V-11004.
The second stage involves passing hot methane-rich regeneration gas from the Regeneration Gas Electric
Heater, E-11009, through the treaters at a temperature of 290-300°C. A temperature of 270-290°C is
required in the treater bed to drive out adsorbed impurities. In order to reach this regeneration
temperature, regeneration gas from the SCU fuel system is heated to 290-300°C in the Regeneration Gas
Electric Heater, E-11009. This regeneration heater also provides hot regeneration gas at 290-300°C for
the RDG Dryer/Treater, V-12006A/B.
RDG Fuel Gas which is sent to the SCU fuel gas system
C2 stream which contains ethylene and ethane that is suitable for recovery in the Steam Cracker Unit
(SCU) Ethylene Fractionator
C3+ stream that is fed to the SCU Cracking Heaters
Polymer grade propylene product
The refinery dry gas feed enters the RDG Compressor 1st Stage Suction Drum, V-12001, on flow control.
An online analyzer on the main feed detects the composition of the refinery dry gas feed including levels of
st
acid gas (CO2 and H2S). The overhead vapor from this drum enters the 1 Stage of the RDG Feed
Compressor, K-12001. A steam turbine utilizes High Pressure steam (HS) drives K-12001. The
Page 9 of 41
Liwa Plastics Project
st
compressed hydrocarbon continues to the RDG Compressor 1 Stage Aftercooler, E-12001, where it is
cooled to 48°C against cooling water. The suction pressure of the RDG Feed compressor is controlled via
two pressure controllers located on V-12001. Primary pressure control is accomplished by throttling High
Pressure steam (HS) to the RDG Feed Compressor Turbine. Secondary pressure control is accomplished
by controlling the amount of refinery dry gas vented to the Fuel Gas system or Wet Flare.
The effluent of E-12001, continues to the RDG Compressor 2nd Stage Suction Drum, V-12002. The
nd
overhead vapor from this drum enters the 2 Stage of the RDG Feed Compressor, K-12001. The
nd
compressed hydrocarbon continues to the RDG Compressor 2 Stage Aftercooler, E-12002 where it is
nd
cooled to 48°C against cooling water before it enters the RDG Compressor 2 Stage Discharge Drum, V-
12003. The 48°C temperature on the outlet of E-12002 is controlled by bypassing some of the flow feeding
the exchanger. Flow through both stages of the compressor is measured upstream of the cooler, and
nd
controls the minimum flow recycle from RDG 2 Stage Discharge Drum overhead to the inlet of the RDG
st
Compressor 1 Stage Suction Drum.
Provisions have been made to allow for any hydrocarbon liquid or water that knocks out in the suction and
discharge drums to be combined and sent to the Quench Water Settler, V-21002, in the SCU.
Lean amine, 30 wt.% DGA, is fed to the top of the amine wash section above the two packed beds on flow
control. As the vapor continues up the tower the acid compounds (H2S and CO2) will absorb into the lean
amine solution. The bottom of the tower will have a higher temperature, due to the heat of absorption. The
overhead of the NGL Amine/Water Wash Column will contain less than 100 ppm (m) CO2 and trace levels
of H2S.
Any oils that form in the absorption process can be skimmed off the liquid level in the sump of C-12001 and
sent to RDG Amine Oil Degassing Drum, V-12016. Overhead vapor from V-12016 is sent to Wet Flare,
while any liquid is sent to the Amine Drain system.
The RDG Caustic/Water Wash Column, C-12002, operates similarly to the SCU Caustic/Water Wash
Column, C-22001, except the one in the Refinery Dry Gas unit functions as two separate caustic/water
sections. The overhead from the RDG Amine/Water Wash Column, C-12001, is sent to the lower section
of the RDG Caustic/Water Wash Tower, C-12002. The refinery dry gas is washed in the lower packed
section with weak level caustic to remove CO2 and H2S. The treated gas is then washed with water in 3
Page 10 of 41
Liwa Plastics Project
bubble cap trays to prevent caustic carryover. Wash water for the RDG Amine/Water Wash Column, C-
12002, comes from the Continuous Blowdown Cooler, E-20014, located in the SCU. Waste water from the
st
lower water section (bubble cap trays) is totally drawn off below the 1 tray and is sent to Waste Water
Treatment (OSBL). The refinery dry gas vapor is then totally drawn off and sent to the RDG Oxygen
Converter Feed/Effluent Exchanger, E-12004. On-line analyzers are provided to detect the amounts of
CO2 and H2S entering and leaving this section of C-12002.
The refinery dry gas is heated in the RDG Oxygen Converter Feed/Effluent Exchanger, E-12004, and by
High Pressure Steam (HS) in the RDG Oxygen Converter Feed Heater, E-12005. The hot refinery dry gas
(221°C at SOR, 240°C at EOR) is passed through the RDG Oxygen Converter, R-12001A/B. The catalyst
selectivity is moderated by injecting Dimethyl Disulfide (DMDS) upstream of E-12005, which is eventually
removed in the upper portion of the RDG Caustic/Water Wash Column, C-12002.
The catalyst in the oxygen convertor is a Nickel-sulfide catalyst (Sud-Chemie OleMax 101) and is selective
only in a certain range of temperature. Due to aging of the catalyst, the operating conditions require
gradually increasing temperature with time to maintain conversion. However, as the temperature increases,
the selectivity decreases, and DMDS injection is required to maintain optimum performance.
The Oxygen Converter catalyst primarily removes oxygen, acetylene, and NOx by reaction to other
species. Oxygen is converted to water and NOx is converted to ammonia and water. The Oxygen
Converter also hydrogenates acetylene to ethane and ethylene. In addition, for any C3 or C4 acetylenes
are present, the methylacetylene and the propadiene are partially converted to propylene, and about half of
the butadienes are converted primarily to butenes. Volatile metals such as arsine, phosphine, and mercury
are absorbed onto the oxygen converter catalyst and reduced to less than 5 ppb in the effluent. The
scheme provides a spare reactor bed for in situ regeneration of the catalyst. The Oxygen Converter has
the following expected performance:
On-line analyzers are provided to detect the amounts of C2H2, C2H4, CO, O2, and NOX, entering and
leaving the O2 Converter.
A temperature rise is seen across the reactor (14°C at SOR, 20°C at EOR) and the hot oxygen-free
refinery dry gas effluent passes through the RDG Oxygen Converter Feed/Effluent Exchanger, E-12004,
and is then cooled against cooling water to 45°C in the RDG Oxygen Converter Effluent Cooler, E-12006,
before entering the upper caustic/water wash unit of C-12002.
The oxygen free refinery dry gas is washed with strong level caustic in a packed section. This section
ensures near complete removal of CO2 and H2S. The acid free RDG vapor flows to a water wash section
comprised of three bubble cap trays. Wash water for the RDG Amine/Water Wash Column, C-12002,
comes from the Continuous Blowdown Cooler, E-20014, located in the SCU. Waste water from the lower
st
water section (bubble cap trays) is totally drawn off below the 1 tray and is sent to Waste Water Treatment
(OSBL).
Strong caustic solution from the upper section of the RDG Caustic/Water Wash Tower is added to the
lower section caustic circulation to maintain the appropriate concentration of caustic solution. A net flow of
caustic from the bottom of this tower is sent to the SCU Spent Caustic Treatment.
Page 11 of 41
Liwa Plastics Project
Despite low diolefin concentration, polymeric oil (yellow oil) may form to some extent in the RDG
Caustic/Water Wash Tower. Provisions are made for this oil to be decanted from the tower bottom and
sent, along with the spent caustic for treatment in the SCU.
The overhead of the upper section of the RDG Caustic/Water Wash Tower, C-12002, is chilled against 9°C
propylene refrigerant in the RDG Dryer/Treater Feed Chiller, E-12003. The outlet temperature of E-12003
is controlled to 12°C by throttling the amount of propylene refrigerant sent to the exchanger. The chilled
effluent is sent to RDG Dryer/Treater Feed Gas KO Drum, V-12005, where condensed water and/or
hydrocarbon is knocked out sent to Waste Water Treatment. The overhead from V-12005 proceeds to the
RDG Dryer/Treater V-12006A/B.
The refinery dry gas passes through V-12006A/B for drying and removal of trace impurities such as water,
NH3, COS, CO2, CS2, acetonitrile, aldehydes, and amines to less than 1 ppm (w). After treatment, the
treated refinery dry gas is sent through the RDG Dryer/Treater Effluent Filter, S-12001A/B, and then to the
RDG Cold Box Exchanger No. 1, ME-12000-E01.
One RDG Dryer/Treater is in operation and operates at a pressure of 9.5 bar(g) while the second treater is
being regenerated or on standby. On-line analyzers are provided to detect the amounts of H2O, CO2, H2S,
NOx, and NH3 entering and leaving the treaters. A third probe is placed in the bottom portion of the
adsorbent bed to detect breakthrough of impurities. The treaters are designed to run for 48 hours before
requiring regeneration. The process of switching from one treater to the next is a timed cycle operation.
Regeneration of the RDG Dryer/Treater is accomplished by circulating hot methane-rich regeneration gas
from the Regeneration Electric Heater, E-11009, at 290-300°C and heating the bed to 270-290°C in order
to drive out impurities adsorbed in the treater bed. The spent regeneration gas is returned to the fuel gas
system. After the bed has reached the required temperature, the bed is cooled with unheated regeneration
gas.
One LPG Dryer is in operation and operates at a pressure of 12.8 bar(g) while the second dryer is being
regenerated or on standby. The dryers are designed to run for 48 hours before requiring regeneration.
The process of switching from one dryer to the next is a “semi-automatic” timed cycle operation. Since the
Mixed LPG is coming OSBL storage, the feed flow rate is on flow control. When regeneration is required,
the flow rate will be increased and the extra capacity will be used to fill the standby dryer. Likewise, when
regeneration is complete, the LPG Dryer Drain Drum Pumps, P-12008A/B, will pump the liquid out of the
dryer and back into the main process feed. During this step, the main feed flow rate will be decreased by
the amount of feed that is supplemented from the pump.
Regeneration of the LPG Dryer is accomplished by heating the bed with 232°C gas in order to drive out
moisture. The spent regeneration gas is returned to the fuel gas system. After the bed has reached the
required temperature, the bed is cooled with unheated regeneration gas.
Page 12 of 41
Liwa Plastics Project
Provisions are made to re-route the Mixed LPG to the SCU furnace feed system during Case 2 operation
or also as safe startup fluid to the Selective Hydrogenation Unit (SHU) when required.
In the RDG Demethanizer, C-12003, fractionation is based on the absorption principle whereby the
ethylene and heavier components are absorbed by the LPG wash liquid. The tower is comprised of four
packed beds and the fractionation occurs on the basis of the absorption principle whereby the C2’s
contained in the refinery dry gas are absorbed by the C3 plus LPG Wash Liquid.
The top of C-12003 operates at a pressure of 8.2 bar(g) and the gross overhead is partially condensed by
binary refrigerant in the RDG Demethanizer Condenser, ME-12000-E03, which is also part of the RDG cold
box package. The condenser effluent is sent to the RDG Demethanizer Reflux Drum, V-12007, where any
liquid that condenses is pumped by the RDG Demethanizer Reflux Pumps, P-12003A/B, as reflux to C-
12003 on flow control reset by the level controller on V-12007. The overhead from V-12007, called RDG
Fuel Gas, is comprised primarily of methane and lighter compounds and the temperature of this stream is
set to -93.4°C by controlling the amount of binary refrigeration sent to the RDG Demethanizer Condenser,
ME-12000-E03. The RDG Fuel Gas is then progressively heated in the RDG Cold Box Exchanger No. 2,
ME-12000-E02, to -40°C and further heated in the RDG Cold Box Exchanger No. 1, ME-12000-E01 where
the temperature is set to 35°C by controlling the amount of propylene refrigerant sent to ME-12000-E01.
Once it is heated, the RDG Fuel Gas is sent to the SCU fuel gas system. The pressure in the RDG
Demethanizer is accomplished by controlling the amount of this stream being sent to the SCU fuel gas
system.
The RDG Demethanizer Reboiler, E-12007, supplies heat to the tower by subcooling 48°C propylene
refrigerant. The temperature in the RDG Demethanizer is controlled by the amount of propylene refrigerant
sent to E-12007. The LPG wash liquid along with C2 & heavier components from refinery dry gas is
pumped from the bottom of the RDG Demethanizer, C-12003, to the RDG Deethanizer, C-12004, on flow
control reset by the level controller in the RDG Demethanizer bottom sump. An on-line analyzer on this
stream detects the amount of methane that is found in this stream.
The top of the RDG Deethanizer operates at a pressure of 16.4 bar(g) and the gross overhead vapor from
this tower is totally condensed in the RDG Deethanizer Condenser, E-12009 by -27°C propylene
refrigerant. The tower overhead pressure is set by a split-range pressure controller (PC) in the gross
overhead line. Primary pressure control is accomplished by controlling the amount of -27°C propylene
refrigerant sent to E-12009. Secondary pressure control is accomplished by controlling the vent (normally
Page 13 of 41
Liwa Plastics Project
closed) to the Cold Flare from the RDG Deethanizer Reflux Drum, V-12008. The condensed stream
leaving E-12009 enters the V-12008. Total liquid from V-12008 is pumped by the RDG Deethanizer Reflux
Pumps, P-12005A/B, and a portion is sent as reflux to C-12004 on flow control. The remaining overhead
liquid product is sent to the SCU Ethylene Fractionator, C-24002, on flow control reset by the level
controller in V-12008.
Tower reboiler duty is provided by Low Low Pressure Steam (LLS) in the RDG Deethanizer Reboiler, E-
12008. A temperature controller on Tray #33 sets the temperature by resetting the setpoint of the flow
controller on the LLS feeding the reboiler. The RDG Deethanizer bottoms product, which contains C3 and
heavier components, is sent to the RDG Depropylenizer, C-12005, on flow control reset by the level
controller in C-12004 bottom sump.
An on-line analyzer is provided with probes in two locations which detect the top and bottom specification
of the RDG Deethanizer with measurements made for C1, C2, and C3 components. If any methane or
other non-condensable component makes its way to this tower, it will accumulate in the RDG Deethanizer
Reflux Drum, V-12008. If any non-condensables accumulate in V-12008, a hand control (HC) provides the
ability to send this material back to the cold box for reprocessing.
Tower reboiler duty is provided by Quench Water (QW) from the SCU in the RDG Depropylenizer Reboiler,
E-12010A/B. A continuous analyzer controller on Tray #34 controls the propylene content on that tray and
resets the setpoint of the flow controller on the QW feeding the reboiler. The RDG Depropylenizer bottoms
product, which contains C3 and heavier components, is sent on flow control reset by the level controller in
the C-12005 bottom sump to the C3+ Feed Vaporizer Drum, V-20012, located in the SCU furnace feed
system. An on-line analyzer is provided to detect the amount of propylene contained in this stream. There
is a high level override to reset the setpoint on the tower bottoms flow controller when high level is reached
in V-20012. A normally closed line is available to send material back to the RDG cold box on flow control.
This provides product flexibility if the tower bottoms requires reprocessing. Furthermore, this also provides
an option to build up an internal wash liquid for the RDG Demethanizer, C-12003, in the event that there is
no mixed LPG available.
Page 14 of 41
Liwa Plastics Project
reclamation, filtration and circulation of lean amine back to the absorbers. The major consumer of lean
amine from ARU is the NGLT amine absorber (C-11002) which is about 95% of the circulation rate. NGLT
and RDG feeds are rich in CO2 and H2S; however the CO2 content in NGLT feed is bound to increase in
few years after the plant startup (two fold increase expected). Due to an increase in CO2 content of NGLT
feed, ARU is designed for a 45 wt. % solution of DGA (Diglycol Amine) in water to handle the high CO2
feed (Case-II). However, the unit is also capable of operating at a DGA (Diglycol Amine) concentration of
30 wt. % which will be the initial conditions of operations to handle the normal CO2 feed (Case-I). The unit
is designed to finally deliver a lean amine product specification of max. 0.045 mol CO2/mol amine (CO2 is
the major component present and absorbed from both NGLT and RDG feeds and H2S loading in both
cases are negligible). The design capacity of the unit is 422.5 T/h of rich amine.
The diglycol amine absorbs CO2 and H2S from NGLT and RDG feeds based on the following reactions:
Page 15 of 41
Liwa Plastics Project
Lean amine from the bottom of the regenerator is pumped by the Lean Amine Pumps (P-11051 A/B) to
NGL Amine Wash Column (C-11002) and RDG Amine Wash Column (C-12001) after cooling and filtering.
Lean amine is cooled against the amine regenerator feed in the Lean/Rich Amine Exchangers (E-11052
A/B/C/D) and further cooled by Lean Amine Air Cooler (E-11056) with temperature control on the fans and
finally a Lean Amine Cooler (E-11053 A/B) with cooling water on the tube side to 42°C. FeS corrosion
particles and degraded products, hydrocarbons, carbon fines from activated carbon bed and other
contaminants in the lean amine are removed in the Amine Pre-Filter (S-11051), the Amine Carbon Filter
(V-11051) and the Amine Post Filter (S-11052) – all operated in series. 20% slipstream of the lean amine
flow is filtered; the rest is routed via a bypass line to the amine wash columns.
Page 16 of 41
Liwa Plastics Project
A temperature controller sets the temperature of this combined stream to 60°C by controlling the amount of
low low pressure steam (LLS) sent to E-20001. A pressure controller on this combined stream sets the
pressure by controlling the amount of ethane is brought in from the NGL unit. In a high pressure scenario,
a pressure controller on this combined stream will open a normally closed vent to the Wet Flare. A
provision is provided for a fresh propane/LPG stream (normally no flow) from OSBL to be vaporized in the
Propane Feed Vaporizer, E-20020, and to be combined with main ethane feed, upstream of E-20001.
The feed to the C3+ Feed Preheater, E-20002, is a combination of the following streams:
A temperature controller sets the temperature of this combined stream to 58°C by controlling the amount of
quench water (QW) sent to E-20002. The preheated C3+ stream is sent to the C3+ Feed Vaporizer Drum,
V-20012, where it is vaporized by low low pressure steam (LLS) in the C3+ Feed Vaporizer, E-20018A/B/C.
The vaporized C3+ from V-20012 are superheated in the C3+ Feed Superheater, E-20019, where a
temperature controller sets this temperature to 80°C by controlling the amount of LLS sent to E-20019. A
pressure controlled on this superheated stream sets the pressure by controlling the amount of LLS sent to
the C3+ Feed Vaporizer, E-20018A/B/C. In a high pressure scenario, a pressure controller on this
combined stream will open a normally closed vent to the Wet Flare. When the level gets too high in the
C3+ Feed Vaporizer Drum, V-20012, a high level override provides the ability to reset flow controllers on
each of the feeds to the drum.
The feed to the Liquid Feed Surge Drum, V-20011, is a combination of the following streams:
the Liquid Feed Preheater, E-20003. A temperature controller sets the temperature of this stream to 60°C
by controlling the amount of low low pressure steam (LLS) sent to E-20003.
A total of six SRT-VI cracking heaters provide the cracking capacity of the plant; five heaters will be in
operation along with one spare to allow for decoking or maintenance. The heaters are grouped into two
“Ethane” Heaters (F-20001 and F-20002) and four “Flexible” Heaters (F-20003 thru F-20004).
The heaters are designed and piped to crack different feeds, thus providing feedstock flexibility for easy
operation. The table below summarizes the feed flexibility for the two heater types.
Heater Configuration
F-20006
Heater UID F-20001 F-20002 F-20003 F-20004 F-20005
C2 C2
C2/C3 co-cracking C2/C3 co-cracking
Feed Flexibility C3+ C3+
C2/C3+ co-cracking
C5/OLNG /C3+ split cracking
# of Radiant Coils 8 8 6 6 6 6
# of Primary TLEs 8 8 6 6 6 6
# of Secondary TLEs 1 1 0 0 0 0
Two of the cracking heaters, F-20001 and F-20002, are designed to crack ethane normally. For flexibility,
these heaters are also designed to crack C3+ or cocrack ethane and propane (EP). EP can have up to
50%wt propane in the ethane/propane mix. These heaters have 8 radiant coils and 8 Primary Transfer Line
Exchangers (TLE) per heater, E-20004A-H and E-20005A-H. The TLE’s are connected to one common
steam drum for each heater. Secondary Transfer Line Exchanger (STLE), E-20011 and E-20012, are
provided for additional heat recovery for ethane and EP cracked gas from the PTLE. Mixed feed
(hydrocarbon and dilution steam) is preheated in the shell side of the STLE. A bypass is provided for the
mixed feed around the STLE to limit the tube side STLE outlet temperatures to minimize condensation of
Page 18 of 41
Liwa Plastics Project
heavy components in the cracked gas which could foul the STLE. For EP co cracking, the STLE should be
partially bypassed to no less than 230 °C in the STLE outlet. For C3+ cracking, the STLE should be totally
bypassed. For ethane cracking, no bypass is required.
The remaining four cracking heaters, F-20003 thru F-20006, are “flexible” heaters for all feeds. These
heaters have 6 radiant coils and 6 Primary TLEs, E-20006A-F thru E-20009A-F. The TLE’s are connected
to one common steam drum for each heater. These cracking heaters do not have Secondary TLEs.
Cracking heaters F-20004 and F-20006 crack C3+ feed at 0.40 S/O and split crack C5/OLNG at 0.5 S/O.
All four “flexible” heaters are designed for split cracking: four of the coils will crack C3+ feed while the
remaining two coils will crack C5/OLNG.
All heaters are twin radiant cell design with a common convection section, stack, and steam drum. The
flue gas is exhausted to the atmosphere with one stack and ID fan per heater.
The table below shows some of the many feed allocations that can occur during operation.
In the QO Oil case shown above the cracking heaters are processing different feeds than normal operation.
F-20001 switches from processing ethane to C3+ feed, F-20003 is now in operation cracking ethane, and
the F-20006 heater is on High Steam Standby (HSS).
The radiant coil outlet pressure (COP) is designed for 0.562 bar(g) (22.85 psia). The cracking heaters are
designed for 100% fuel gas fired based on fuel gas produced in the SCU at 10% excess air during normal
feed cracking mode.
For each cracking heater, the feed is preheated in the feed preheat coil in the convection section and then
combined with dilution steam. Ethane feed to the Flexible Heaters F-20003 thru 20006 requires bypass of
the Upper Feed Preheat Coils and part of the Lower Feed Preheat Coils due to the lower feed preheat
requirement of ethane compared to the need to vaporize the liquid C5/OLNG feed. The feed is then
heated in the mixed feed preheat coil to the crossover temperature and then distributed equally to the inlet
tubes of each radiant coil by critical flow venturis. The cracked furnace effluent from each coil is cooled in
a Transfer Line Exchanger.
The ethane cracking effluent from the Primary TLE for F-20001 and F-20002 are further cooled in the
Secondary TLE to maximize heat recovery. Preheated ethane feed from the LFP is mixed with dilution
steam before entering the shell side of the secondary TLE where it is preheated by the ethane cracking
effluent. The mixed feed is sent back to the convection section to further preheat to the crossover
temperature in the Mix Preheat section.
Steam is generated in the TLE and superheated in the USSH and LSSH. There is a desuperheater for
temperature control: one at the outlet of the USSH. The desuperheater is required for temperature control
and to prevent the steam going below the saturation point after BFW injection.
DMDS is injected into the dilution steam header at the inlet to each furnace.
Burners for the heaters shall be hearth burners on the floor plus wall burners. Each of the two radiant cells
of a heater has separate firing controls.
Page 19 of 41
Liwa Plastics Project
Jackshaft is provided to adjust the hearth burner air dampers from the DCS and safety interlock systems
for automatic preset shutdown conditions to protect the convection section.
One ID fan will be provided for each cracking heater with Variable Frequency Drive (VFD) for draft control.
Flue gas exhausts from two radiant cells are combined to a common convection section and single stack.
The heater effluent from the TLE is directed to the main transfer line via the Transfer Line Valve (TLV).
When a heater is in decoke mode, the TLV is closed and the decoke valve is open to the decoke piping.
The Transfer Line Valve is part of a 3-valve system which also includes the TLV on the main transfer line
and the small and large Decoke Valves (DV). The Small Decoke Valve is mechanically linked to the TLV to
make sure the heater effluent will not be blocked and cause overpressure. The objectives of the transfer
line valve and decoke valve system are:
The heater’s cracked effluent outlet piping that connects to the main transfer line must be positively
isolated during the decoking operation to prevent leakage of air into the hydrocarbon-carrying main transfer
line during the burn-off phase of the decoking cycle. Likewise, positive isolation is necessary when
maintenance is being performed on the heater (i.e., mechanical cleaning of TLE's), to ensure against a
backflow of hydrocarbon gas into the heater piping or decoke system.
To achieve the objectives described above a 3-valve mechanical link transfer line valve system will be
used.
Regardless of feedstock type, the heater effluent from the cracking heater TLEs is fed to two main transfer
lines. Each main transfer line receives effluent from three heaters (one Ethane Heater and two Flexible
Heaters) and is sent to the Common Quench Fittings, M-21001A/B. Quench oil is used in the quench
fittings to quench the heater effluent before entering the gasoline fractionator, C-21001.
The heaters are designed for steam/air decoking of the radiant coils and TLE. The TLE decoking procedure
is an extension of the radiant decoke. Normally, the decoking procedure is terminated after the radiant coil
is decoked. When TLE decoking is required, the procedure is extended and additional steps are used to
clean the TLE. Decoke effluent is directed to the firebox where the coke particles are combusted.
Page 20 of 41
Liwa Plastics Project
The Gasoline Fractionator is comprised of two sections. The top section contains IMTP packing and 8
valve trays serve to separate out the gasoline and lighter ends from the heavier hydrocarbons in the heater
effluent. The bottom section contains grid packing and serves as the heat removal zone for the Quench Oil
Loop.
The total bottoms stream of the Gasoline Fractionator, at 170°C is filtered in the Quench Oil Strainers, S-
21001A/B/C/D, and pumped by the Quench Oil Circulation Pumps, P-21001A/B/C/D, through Quench Oil
Coke Removal Package, ME-21000. In this package, the quench oil quality is improved for use in the
process water and dilution steam system as well as the quench fittings. The improved quench oil is split
into two streams. A small purge stream (3% of total quench oil flow) from ME-21000 is sent back to the
Gasoline Fractionator bottoms. The net bottoms product is sent on flow control to the Pyrolysis Fuel Oil
Stripper, C-21002 via the PFO Stripper Feed Filters, S-21002A/B. The remaining quench oil is passed
through the following equipment for heat removal:
The Gasoline Fractionator is refluxed with gasoline condensed in the Quench Tower sent on flow control.
Provision is made to inject Flux Oil from storage into the C-21001 sump, if it is required for purpose of
inventory/makeup and, if required, viscosity adjustment.
A side stream product of Pyrolysis Gas Oil (PGO) is withdrawn from the fractionator and sent to the
Gasoline Fractionator Side Draw Drum, V-21001 on flow control reset by the level controller in V-21001.
PGO from V-21001 is pumped by the Gasoline Fractionator Sidedraw Pumps, P-21002A/B where a part of
the PGO is used as purge oil for instrument flushing prior to returning to the Gasoline Fractionator. The
remainder of the PGO is sent to the Pyrolysis Fuel Oil Stripper, C-21002, bottom section on flow control
reset by the level controller in the bottoms sump of C-21002. Dilution steam is sent to the bottoms of C-
21002 on flow control and serves to control the Pyrolysis Fuel Oil product flash point. The Gasoline
Fractionator net bottoms, PFO, is sent to the upper portion of the Pyrolysis Fuel Oil Stripper, C-21002,
where it is stabilized using Medium Pressure Steam (MS) sent on flow control to achieve a fuel oil product
of acceptable flash point greater than 82°C. The overhead of C-21002 containing vaporized light material
is sent to the bottoms of the Gasoline Fractionator. The bottoms of C-21002, PFO product is pumped by
the Pyrolysis Fuel Oil Pumps, P-21003A/B through the PFO Stripper Bottoms Filters, S-21003A/B, and
then to the PFO Product Cooler, E-21004A/B where it is cooled by Quench Water prior to ending up in
OSBL storage. The temperature of the PFO product is cooled to 90°C by controlling the amount of Quench
Water sent to E-21004A/B.
Page 21 of 41
Liwa Plastics Project
The circulating quench water is pumped by the Quench Water Circulation Pumps, P-21004A/B/C, and
cooled in the following exchangers (unless noted otherwise):
st
1 Level: High Temperature Quench Water
The overhead vapor from the Quench Tower is sent to the charge gas compression section. In a high
pressure scenario, the pressure of this stream is controlled by regulating the amount of vapor sent to Wet
Flare. In a low pressure scenario, the pressure of this stream is controlled by regulating the amount of fuel
gas mixed with this overhead vapor stream.
Page 22 of 41
Liwa Plastics Project
The condensed gasoline and dilution steam (as process water) is separated from the recirculating quench
water in the Quench Tower bottoms and sent to Quench Water Settler, V-21002. Here, the gasoline is
separated from process water. The condensed hydrocarbon is pumped by the Gasoline Fractionator Reflux
Pumps, P-21006A/B and returned as reflux to the Gasoline Fractionator, or used as wash gasoline for
spent caustic treatment. Any excess gasoline is mixed with the bottoms stream from the Debutanizer, and
sent to OSBL as Raw Pyrolysis Gasoline.
The process water from the Quench Water Settler, V-21002, is pumped by the Process Water Stripper
Feed Pump, P-21005A/B, through the Process Water Coalescer Package, ME-21006, where suspended
solids and emulsified oil are removed from process water. The process water is then sent to the Process
Water Stripping section.
The Process Water Stripper is comprised of 12 valve trays and operates at a pressure of 0.40 bar(g) and
temperature of 108°C in the top. The Process Water Stripper Reboiler, E-21002A/B, generates the
stripping steam necessary to remove acid gases and volatile hydrocarbons from the process water. Live
dilution steam injection is provided to the bottom of the process water stripper to supplement steam
generation in the reboiler, if required. The heating medium of E-21002A/B is the recirculating hot quench
oil from the Gasoline Fractionator, C-21001. The overhead vapor from C-21004 is sent back to the Quench
Tower, C-21003, and flow control is accomplished by throttling the amount of Quench Oil bypassing the
Process Water Stripper Reboiler, E-21002A/B. The bottoms of C-21004 is stripped process water and is
pumped by the Process Water Stripper Bottoms Pumps, P-21007A/B, to the Dilution Steam Drum, V-
21003, on flow control reset by the level in the bottom sump of V-21003. Prior to entering V-21003, a
portion of the process water stripper bottoms stream, used as wash water, is sent to the Spent Gasoline/
Wash Water Mixer, M-22003. The rest of the C-21004 bottoms stream is preheated by hot quench oil in
the Quench Oil/Process Water Exchanger, E-21003A/B. Makeup boiler feed water, if required, is added to
the process water before it enters the dilution steam drum. Make up is normally not expected.
The Dilution Steam Drum, V-21003, contains three valve trays in addition to a demister in order to minimize
the possibility of entrainment of residual caustic into the dilution steam. The process water is vaporized at
177°C by Medium Pressure Steam (MS) in the Dilution Steam Drum MS Steam Reboiler, E-21009A/B/C/D.
The dilution steam is superheated against MS in the Dilution Steam Superheater, E-21010, and primary
pressure control is accomplished by controlling the amount of MS sent to E-21010. If necessary,
secondary pressure control involves the injection of live MS into the header to maintain pressure.
Provisions for amine injection to the dilution steam drum feed and process water stripper feed are provided
for pH control.
The steam generated in V-21003 is sent to the cracking heaters as dilution steam and purge steam for
instruments and valves. Dilution steam is also sent to the PFO Stripper, C-21002.
To prevent a build-up of non-volatiles, a blowdown stream from the dilution steam drum is cooled in the
Process Water Stripper Feed Heater, E-21008, and further cooled to 50°C by cooling water in the Dilution
Steam Blowdown Cooler, E-21011. The cooled blowdown is sent to the OSBL waste treatment facility on
flow control reset by the interface level controller in V-21002. An on-line analyzer is provided to measure
the pH this cooled blowdown.
Page 23 of 41
Liwa Plastics Project
The basic control scheme of the Charge Gas Compressor (Stages 1-2) takes the following actions:
st
A pressure controller on the 1 Stage Suction Drum, V-22001, overhead controls the suction pressure
by throttling (SHS) sent to the turbine.
In cases when the pressure gets too high in V-22001, pressure is controlled by venting hydrocarbons
to Wet Flare.
nd
Flow through the first three stages is measured at the 2 stage discharge, upstream of the cooler, and
nd
controls the minimum flow recycle from the Charge Gas Compressor 2 Stage Discharge Drum
st
overhead to the inlet of the Charge Gas Compressor 1 Stage Suction Drum.
Page 24 of 41
Liwa Plastics Project
Any significant breakthrough of H2S or CO2 can jeopardize downstream operations or final product
specifications. 20% Caustic is fed from OSBL to the suction line of P-22004A/B to make up any caustic
that leaves the bottoms (spent caustic) of C-22001.
The basic control scheme of the Charge Gas Compressor (Stage 3) takes the following actions:
A temperature controller on the 3rd Stage Suction Drum, V-22004, overhead sets the temperature to
15°C by throttling the amount of 9°C propylene refrigerant to E-22005.
In cases when the pressure gets too high in V-22004, pressure is controlled by venting hydrocarbons
to Wet Flare.
Page 25 of 41
Liwa Plastics Project
rd
In cases when the pressure gets too high on the 3 stage discharge, pressure is controlled by venting
hydrocarbons to Wet Flare.
rd
Flow through the third stage is measured at the 3 stage discharge, upstream of the cooler, and
rd
controls the minimum flow recycle from the Charge Gas Compressor 3 Stage Discharge Drum
nd
overhead to the inlet of the Charge Gas Compressor 2 Stage Suction Drum.
Spent caustic leaves the bottom of the SCU and RDG Caustic/Water Wash Towers, along with a cooled
wash gasoline stream is sent to the Spent Caustic Wash Gasoline Mixer, M-22002, and then processed in
the Spent Caustic Coalescer, V-22008. Wash gasoline is pumped from the Quench Water Settler on flow
ratio control, maintaining a consistent ratio to the spent caustic flow. Prior to entering V-22008, it is cooled
by cooling water in the Spent Caustic Wash Gasoline Cooler, E-22008. The gasoline wash recovers
hydrocarbon from the spent caustic stream. In the Spent Caustic Coalescer the combined stream is first
degassed, then passed through a packed coalescing pad and into the settling compartment where the
gasoline/caustic separation takes place. The spent caustic is routed to the OSBL WAO unit on flow control
reset by the level controller on V-22008, where it undergoes further treatment. The Wet Air Oxidation unit
converts the sodium sulfides to sodium sulfates and thiosulfates.
The spent gasoline from V-22008, requires further water washing to reduce the quantity of entrained
caustic which can lead to a pH problem. The gasoline is sent on flow control reset by the level controller
on V-22008 to the Spent Gasoline/Wash Water Mixer, M-22003, where it is contacted with wash water prior
to entering the Spent Gasoline Coalescer, V-22009. Wash water is pumped from the Process Water
Stripper bottoms on flow ratio control, maintaining a consistent ratio to the wash gasoline flow from V-
22008. In the Spent Gasoline Coalescer the combined stream is passed through a packed coalescing pad
and into the settling compartment where the gasoline/water separation takes place. The spent wash water
is sent on flow control reset by the level controller on V-22009 to the OSBL WAO. The spent gasoline is
returned to the Quench Tower.
The pressure in the Spent Caustic Coalescer, V-22008, is controlled by split range pressure controllers
located in the overhead vent to the Wet Flare. In a high pressure scenario, the overhead stream is vented
to the Wet Flare. In a low pressure scenario, Nitrogen is brought into the overhead line. The pressure is
set to a sufficient level in the Spent Caustic Coalescer to send spent caustic to the OSBL WAO unit and
Spent Gasoline to the Spent Gasoline Coalescer Drum without the use of pumps.
Similarly, the pressure in the Spent Gasoline Coalescer, V-22009, is controlled by split range pressure
controllers located in the overhead vent to the Wet Flare. In a high pressure scenario, the overhead
stream is vented to the Wet Flare. In a low pressure scenario, Nitrogen is brought into the overhead line.
The pressure is set to a sufficient level in the Spent Gasoline Coalescer to send spent wash water to the
OSBL WAO unit and Spent Gasoline to the Quench Tower without the use of pumps.
Page 26 of 41
Liwa Plastics Project
One Charge Gas Dryer is in operation and operates at a pressure of 24.4 bar(g) while the second dryer is
being regenerated or on standby. Each dryer contains two desiccant bed sections. A moisture analyzer is
provided below the first (main) bed to indicate the arrival of the wet gas “front”. The second bed (guard)
prevents break-through moisture from leaving the dryer. Any indication of the wet gas “front” reaching the
analyzer probes indicates exhaustion and the dryers should be switched immediately. The dryers are
designed to run for 48 hours before requiring regeneration. The process of switching from one dryer to the
next is a timed cycle operation. Regeneration is carried out by circulating hot methane-rich regeneration
gas from the regeneration system at 232°C to drive out moisture adsorbed in the dryer bed. After the bed
has reached the required temperature, the bed is cooled with unheated regeneration gas. The spent
regeneration gas is returned to the fuel gas system.
Liquid condensate is pumped from V-22004 and V-22005 to the Liquid Condensate Coalescer Package,
ME-22002, where the separated hydrocarbon proceeds to the Liquid Condensate Dryers, V-22007A/B, for
moisture removal. Any free water in the feed stream is removed from the bottom boot of ME-22002-V01 on
interface level control and sent to the Quench Tower, C-21003. After drying, the liquid condensate flows
through the Liquid Condensate Dryer Outlet Filter, S-22001A/B, and then sent directly to the HP
Depropanizer, C-22002.
One Liquid Condensate Dryers is in operation and operates at a pressure of 26.2 bar(g) while the second
dryer is being regenerated or on standby. Each dryer contains one dessicant bed. A moisture analyzer is
provided towards the end of the bed to indicate arrival of the wed gas “front”. Any indication of the wet gas
“front” reaching the analyzer probe indicates exhaustion and the dryer should be switched immediately.
The dryers are designed to run for 72 hours before requiring regeneration. The process of switiching from
one dryer to the next is timed cycle operation. The regeneration procedure is similar to that of the Charge
Gas Dryers mentioned above. An on-line analyzer on the effluent from the Liquid Condensate Dryers
measures any water that may break through. A separate on-line analyzer provides a composition of the
charge gas, as well as detecting any acid gases (CO2 and H2S).
Fuel gas from the RDG as well as methane rich offgas from the SCU fuel gas system is combined and
used as regeneration gas in the complex. It is split into two cooling and heating regeneration headers.
The cooling regeneration gas is at a temperature of 40°C. The heating regeneration gas is preheated by
the Regeneration Feed/Effluent Exchanger, E-22009, and then against High Pressure Steam (HS) in the
Regen Gas Heater, E-22011. The temperature of the heating regeneration gas is controlled to 240°C by
throttling the amount of HS sent to E-22011. Some of this heating regeneration gas is sent to the
Regeneration Gas Electric Heater, E-11009, in the NGL unit. A mixture of heating and cooling
regeneration gas is sent to the dryers and treaters on flow control.
Page 27 of 41
Liwa Plastics Project
The regeneration procedure consists of several steps including gradual heating by regeneration gas,
holding at this temperature until all water is driven from the molecular sieve, and finally cooling the beds
before returning to service. Flow control on the combined regeneration gas is established by controlling
the heating regeneration gas sent to the dryer or treater. Temperature control on the combined
regeneration gas is established by resetting the set point on the flow controller of the cooling regeneration
gas.
The spent regeneration gas from the users is cooled in the Regeneration Feed/Effluent Exchanger, E-
22009, and cooled to 45°C in the Regeneration Gas Cooler, E-22010, by cooling water. The cooled
regeneration gas continues to the Regeneration Gas K.O. Drum, V-22011, for removal of water prior to re-
entering the fuel gas system. Any condensed water from the regeneration gas K.O. drum is returned to the
Quench Water Tower, C-21003, on level control.
The reactors in the complex require different types of gases during their regeneration cycles. A Reactor
Reduction Gas Heater, E-22031, heats a Nitrogen (N2) stream along with Hydrogen (H2) when required.
The temperature is controlled by throttling the amount of Medium Pressure Steam (MS) sent to E-22031.
There are also provisions for Plant Air, Super High Pressure Steam (SHS), and Low Low Pressure Steam
(LLS) to be sent to reactors during regeneration oxidation steps.
The charge gas from the Charge Gas Dryers and the condensed hydrocarbon liquid from the Liquid
Condensate Dryer are fed to tray #15 and #19 respectively of the High Pressure (HP) Depropanizer, C-
22002. The gross overhead from the High Pressure Depropanizer, C-22002, at 23.5 bar(g) is heated by
Acetylene Converter reactor effluent in the Acetylene Converter Feed/Effluent Exchanger No. 1 and No. 2,
E-22012A/B and E-22013A/B. The temperature of the reactor feed after the second feed/effluent
exchanger is set to 53°C by controlling the amount that bypasses E-22013A/B. An on-line analyzer detects
the amount of C4’s in this stream, which indicates tower separation performance. A separate analyzer
detects any carbon monoxide found in the stream, which is a temporary poison to the Acetylene Converter
catalyst that reduces activity.
The reactor feed is heated to 66°C at SOR (116°C at EOR) in the Acetylene Converter Heater, E-22014, by
throttling the amount of Medium Pressure Steam (MS) sent to E-22014. The front end Acetylene Converter
system selectively hydrogenates acetylene to ethylene and ethane. Some methyl-acetylene/ propadiene
(MAPD) are hydrogenated to propylene and propane. An on-line analyzer on this stream measures the
amount of acetylene, ethane, and MAPD in the reactor feed.
The Acetylene Converter, R-22001A/B/C, contains 3 beds operating in series with intercoolers after each
staged cooled by cooling water. Temperature controllers downstream of each intercooler set the
temperature of the cooled effluent feeding the next bed, by controlling the amount bypassing each
intercooler. Reactor regeneration is performed ex-situ. The reactor vessels are configured to be put in any
order to allow single vessel catalyst replacement if required. The reactor effluent, 74°C at SOR (125°C at
EOR) is cooled by in the Acetylene Converter Aftercooler, E-22017, by cooling water. An on-line analyzer
on this stream measures the amount of acetylene, ethane, and MAPD in the reactor effluent. The reactor
effluent then is further cooled in the Acetylene Converter Feed/Effluent Exchanger No. 2, E-22013A/B, after
Page 28 of 41
Liwa Plastics Project
which it is sent to the molecular sieve Acetylene Converter Dryer, V-22014A/B, for moisture removal. The
dryer effluent flows through the Acetylene Converter Dryer Outlet Filter, S-22004A/B, and is further cooled
in Acetylene Converter Feed/Effluent Exchanger No. 1 and then sent to the HP Depropanizer Condenser,
E-22018. The hydrocarbons are partially condensed at -21°C by -27°C propylene refrigerant and then
enters the HP Depropanizer Reflux Drum, V-22012. The level controller on V-22012 controls the amount
of propylene refrigerant sent to E-22018. The liquid from V-22012 is pumped by the HP Depropanizer
Reflux Pumps, P-22010A/B, on flow control as reflux to C-22002.
The condensed liquid from the reflux drum provides some of the reflux to the HP Depropanizer. The net
overhead from the HP Depropanizer, which contains the C3 and lighter components of the charge gas, is
then fed to the chilling train. The pressure of the reflux drum is controlled by a pressure controller that
regulates the amount of net overhead vapor is sent to the Demethanizer Feed Chiller, E-23001. A second
pressure controller will vent material to the Cold Flare in high pressure scenarios.
Tower reboiler duty is provided by Desuperheated Low Low Pressure Steam (DS LLS) in the HP
Depropanizer Reboiler, E-22020A/B. Only one of the reboilers is in operation; a spare is provided since
fouling is an issue in this system and periodic cleaning is required. A temperature controller on the
downcomer of Tray #10 maintains a bottoms temperature to 82°C by resetting the setpoint of the flow
controller on the DS LLS feeding the reboiler. The HP Depropanizer bottoms is cooled by cooling water in
the HP Depropanizer Bottoms Cooler, E-22021, and then fed to the LP Depropanizer, C-22003 flow control
reset by the level controller on C-22002 bottoms sump. An on-line analyzer provides a measurement of
C2’s in the bottoms stream which is an indication of tower separation performance. Polymerization
inhibitor from the Polymerization Inhibitor Injection System, ME-22000, is injected into the HP Depropanizer
feed and Reboiler inlet streams.
The bottoms product of the HP Depropanizer enters on tray #33 of the LP Depropanizer which operates at
a top pressure of 6.2 bar(g). The gross overhead of the LP Depropanizer is fully condensed by -27°C
refrigerant in the LP Depropanizer Condenser, E-22002. The tower overhead pressure is set by a split-
range pressure controller (PC) in the gross overhead line. Primary pressure control is accomplished by
controlling the amount of -27°C propylene refrigerant sent to E-22022. Secondary pressure control is
accomplished by controlling the vent (normally closed) to the Cold Flare from the LP Depropanizer Reflux
Drum, V-22015. The condensed stream leaving E-22022 enters V-22015. Total liquid from V-22015 is
pumped by the LP Depropanizer Reflux Pumps, P-22011A/B, and a portion is sent as reflux to the C-22003
on flow control. The remaining overhead liquid product is sent to the HP Depropanizer, C-22002, on flow
control reset by the level controller in V-22015.
Tower reboiler duty is provided by Desuperheated Low Low Pressure Steam (DS LLS) in the LP
Depropanizer Reboiler, E-22023A/B. Only one of the reboilers is in operation; a spare is provided since
fouling is an issue in this system and periodic cleaning is required. A temperature controller in the
downcomer of Tray #14 maintains a bottoms temperature of 75°C resetting the setpoint of the flow
controller on the DS LLS feeding the reboiler. The LP Depropanizer bottoms product, which contains C4
and heavier components, is pumped by the LP Derpopanizer Bottoms Pumps, P-22012A/B, to the
Debutanizer, C-24005, on flow control reset by the level controller in C-22003 bottom sump. On-line
analyzers detect the amount of C4’s in the overhead product stream as well as the C3’s in bottoms product
stream, which indicate tower separation performance. Polymerization inhibitor from the Polymerization
Inhibitor Injection System, ME-22000, is injected into the LP Depropanizer feed and Reboiler inlet streams.
A normally closed vent stream from V-22015, controlled by hand controller (HC), is provided to rout
st
material back to the Charge Gas Compressor 1 Stage Suction Drum, V-22001, for reprocessing.
Page 29 of 41
Liwa Plastics Project
The overhead vapor from the Demethanizer Feed Separator No. 1 is further chilled against offgases and
binary refrigerant in the Offgas Exchanger No. 2, ME-23000-E02. The temperature of the charge gas is set
to -110°C by controlling the amount of binary refrigerant sent to ME-23000-02 and the stream is flashed in
the Demethanizer Feed Separator No. 2, V-23002. The condensate from the Demethanizer Feed
Separator No. 2, V-23002, is sent to the Demethanizer as the “Middle Feed” on flow control reset by the
level controller in V-23002.
The overhead vapor from the Demethanizer Feed Separator No. 2 is further chilled against offgases and
binary refrigerant in the Offgas Exchanger No. 1, ME-23000-01, and is mixed with methane wash liquid in
the Demethanizer Feed/Methane Wash Mixer, M-23001, and is flashed in the Demethanizer Feed
Separator No. 3, V-23003. The condensate from the Demethanizer Feed Separator No. 3, V-23003, is
sent to the Demethanizer as the “Top Feed” on flow control reset by the level controller in V-23003.
The overhead vapor from the Demethanizer Feed Separator No. 3, called hydrogen rich offgas, is reheated
by charge gas in the cold box system and compressed in the Hydrogen Compressor, K-23001, before
being sent to the Hydrogen Pressure Swing Adsorption (PSA) Unit, ME-23001, for hydrogen purification.
The pressure of V-23003 is controlled by two pressure controllers. Primary pressure control is
accomplished by resetting the speed controller on K-23001. In a high pressure scenario, the speed
controller for K-23001 may reach its limit and secondary pressure control is accomplished by sending the
hydrogen rich offgas to the fuel gas system.
The Hydrogen Compressor is comprised of two stages and the discharge from each stage is cooled to
45°C by cooling water in the Hydrogen Compressor Intercooler and Aftercooler, E-23003 and E-23004
respectively. The pressure of the stream is increased to 32.9 bar(g) which is sufficient for the purified
hydrogen (>99.9 mol.%) from the PSA Unit to be sent to the following locations:
Offgas from the PSA Unit is combined with returned regeneration gas and is sent directly to the Fuel Gas
system. A portion of this fuel gas is sent to the Fuel Gas Knock-Out Drum, V-23005, where any liquids are
removed on level control and sent back to the Quench Tower, C-21003. The pressure of V-23005 is
controlled to 4.5 bar(g) by two pressure controllers in the overhead line. In a high pressure scenario, fuel
gas is vented to the Wet Flare. In a low pressure scenario, supplemental fuel gas is brought into V-23005
from OSBL. The overhead of V-23005 undergoes further processing in the Fuel Gas Filter/Coalescer, S-
Page 30 of 41
Liwa Plastics Project
23001A/B, where condensate is removed and sent back to the Quench Tower. The processed fuel gas is
consumed by the Cracking Heaters, F-20001-6, any excess is sent to OSBL. On-line analyzers detect the
composition of this fuel gas stream, to control the firing rate in the cracking heater burners.
7.14 Demethanization
The Demethanizer, C-23001, tower is comprised of four packed bed sections and its primary purpose is to
separate methane and lighter components from the remaining charge gas. The tower operates at a top
pressure of 7.1 bar(g), just high enough to permit overhead methane product to get into the fuel gas
system. By minimizing the operating pressure, the separation efficiency is increased which reduces both
reflux requirements and energy consumption.
There are three primary condensed liquid feeds (top/middle/bottom) to the Demethanizer, C-23001, which
come from feed separator drums in the chill train. Demethanizer gross overhead vapor at -130°C is
partially condensed with binary refrigerant in the Demethanizer Condenser, ME-23000-E07, and sent to the
Demethanizer Reflux Drum, V-23004. The overhead of V-23004 is sent back to the cold box where it is
heated before being sent to the regeneration system; any fuel gas not used for regeneration proceeds to
the PSA unit for hydrogen recovery. A control valve controls the flow of this stream through the control box
which sets the pressure in the Demethanizer tower. The liquid from V-23004 is pumped by the
Demethanizer Reflux Pumps, P-23001A/B. A portion is sent on flow control as reflux to the top bed of the
Demethanizer, while the remaining liquid is used as methane wash liquid in the Demethanizer Feed
Separator No. 3 in the charge gas chilling train to reduce ethylene loss. The level in V-23004 is controlled
by throttling the amount of binary refrigerant sent to the Demethanizer Condenser, ME-23000-E07.
Tower reboiler duty is provided by heat interchange with hot charge gas from the HP Depropanizer Reflux
Drum, V-22012, in the Demethanizer Reboiler, E-23002. A temperature controller sets the temeperature
profile in the tower by bypassing a portion of the charge gas around E-23002. The bottoms product is
pumped by the Demethanizer Bottoms Pumps, P-23002A/B, and split into two streams before being heated
in the cold box and eventually entering the Deethanizer, C-24001. One stream is sent directly as liquid
from the cold box to the Deethanizer as the “Upper Feed”. The other stream is vaporized in the cold box
and sent to the Deethanizer as the “Lower Feed”. A level controller resets the flow controller on the “Lower
Feed” upstream of the cold box. The “Upper Feed” flow controller is set on ratio control relative to the
“Lower Feed”. An on-line analyzer in the tower bottoms detects for methane, an indication of tower
separation performance.
Provisions are made to reprocess vents from ethylene fractionation or the binary refrigeration system.
7.15 Deethanization
The Demethanizer bottoms product, which is split into two streams as described in the Demethanizer
section, feeds the Deethanizer, C-24001. The Deethanizer is comprised of 70 valve trays and its primary
purpose is to create a C2 stream sent to the Ethylene Fractionator and a C3 stream sent to the Propylene
Fractionators.
The top of the Deethanizer operates at a pressure of 18.4 bar(g) and gross overhead vapor is partially
condensed against -27°C propylene refrigerant in the Deethanizer Condenser, E-24001. The two phase
stream leaving E-24001 enters the Deethanizer Reflux Drum, V-24001 where an overhead vapor stream,
containing ethane and ethylene, is sent to the Ethylene Fractionator, C-24002 on flow control. The tower
overhead pressure is set by a pressure controller in the gross overhead line resetting the flow controller on
the C2s sent to the Ethylene Fractionator. In a high pressure scenario, a second pressure controller will
open a normally closed vent on V-24001 to the Cold Flare. Total liquid from V-24001 is pumped by the
Page 31 of 41
Liwa Plastics Project
Deethanizer Reflux Pumps, P-24001A/B, and sent as reflux to the C-24001 on flow control. The level in V-
24001 is controlled by throttling the amount of propylene refrigerant sent to the Deethanizer Condenser, E-
24001.
Tower reboiler duty is provided by Quench Water (QW) in the Deethanizer Reboiler, E-24002. A
temperature controller on Tray #18 sets the temperature by resetting the setpoint of the flow controller on
the QW feeding the reboiler. The Deethanizer LLS Steam Reboiler, E-24016, is provided for use as a
startup/spare reboiler. The Deethanizer bottoms product, which contains C3 and heavier components, is
pumped by the Deethanizer Bottoms Pumps, P-24002A/B, to the MAPD Trim Reactor Feed Cooler, E-
24008, on flow control reset by the level controller in C-24001 bottom sump.
On-line analyzers are provided in the net overhead vapor product and bottoms product to measure their
compositions, and tower separation performance.
Net overhead vapor product from the Deethanizer Reflux Drum, V-24001, fed to Tray #41
Treated C2 stream from the RDG Deethanizer Reflux Pumps, P-12005A/B, fed to Tray #28
The top of the Ethylene Fractionator operates at a pressure of 16.3 bar(g) and gross overhead vapor is
totally condensed against -40°C propylene refrigerant in the Ethylene Fractionator Condenser, E-24003
before it enters the Ethylene Fractionator Reflux Drum, V-24002. The tower overhead pressure is set by a
pressure controller in the gross overhead line which controls the amount of propylene refrigerant sent to E-
24003. In a high pressure scenario, a second pressure controller will open a normally closed vent on V-
24002 to the Cold Flare. If any non-condensables accumulate in V-24002, a hand control (HC) provides
the ability to send this material back to the Demethanizer, C-23001, for reprocessing. The liquid from V-
24002, ethylene product, is pumped by the Ethylene Fractionator Reflux Pumps, P-24003A/B, and sent as
reflux to C-24002 on flow control. A portion of this ethylene product is sent on flow ratio control to the
OSBL storage spheres, maintaining a constant ratio to the reflux flow. This prevents exporting offspec
Ethylene Product. The level controller in V-24002 resets the reflux flow and, therefore, the product draw-off
rate.
Onspec HP Ethylene from OSBL storage is pumped to the Offgas Exchanger No. 6, ME-23000-E06, in the
cold box to heat the stream, before it is vaporized in the kettle side of the Ethylene Product Vaporizer, E-
23005, by 9°C propylene refrigerant. The vaporized ethylene from E-23005 undergoes more heating in
ME-23000-E06, and is sent as HP Ethylene Product Vapor to OSBL at 45°C and 37 bar(g). The pressure
of this stream is set by controlling the amount of liquid ethylene feeding E-23005. A level controller in E-
23005, sends a high level override to control the feed if the level gets too high.
A continuous ethylene rundown stream of 5,000 kg/hr is withdrawn on from the Ethylene Fractionator
Reflux Drum, V-24002, and is chilled by binary refrigerant in the Ethylene Rundown Chiller, ME-24000. A
temperature controller on the outlet of ME-24000 sets the temperature of the ethylene rundown to -101°C.
The ethylene rundown (in liquid phase) is sent to OSBL LP Storage on flow control. A level controller in
OSBL LP Storage, sends a high level override to control the flow if the level gets too high. Higher levels of
rundown can be achieved during SCU turn down.
Tower reboiler duty is provided by two reboilers which permits the maximum cold recuperation from this
tower. In the kettle type Ethylene Fractionator Side Reboiler, E-24006, a liquid stream withdrawn from Tray
Page 32 of 41
Liwa Plastics Project
#21 on flow control is vaporized by -10°C propylene refrigerant. A level controller in E-24006, sends a high
level override to control the sidedraw if the level gets too high. In the Ethylene Fractionator Reboiler, E-
24007, a portion of the bottom sump is vaporized by 9°C propylene frefrigerant. An analyzer controller
detects the ethylene content in the downcomer of Tray #17 and resets the flow controller on the propylene
refrigerant sent to E-24007.
The Ethylene Fractionator bottoms product, ethane recycle, is sent to the cold box on flow control reset by
the level controller on the tower bottom sump. In the cold box, the ethane recycle is heated and vaporized
in the Offgas Exchangers No. 5 and 6, ME-23000-E05/E06 before is recycled back to the feed heater
system.
On-line analyzers are provided on the overhead and bottoms product to ensure product specifications are
met.
The MAPD Converter, R-24001A/B, operates at a pressure of 23.7 bar(g) and is a trickle flow (downflow)
single trim reactor system which reduces the MAPD content in the effluent stream to less than 300 ppm.
The amount of hydrogen injected is just slightly above the amount required to saturate the MAPD so there
is not any need for a separator on the outlet. There is a distributor inside of the reactor to ensure that the
hydrogen is properly mixed. As the liquid reacts with H2 in the reactor a noticeable temperature rise of
15°C will occur, which leads to vaporization. A vapor product is removed from the bottom of R-24001A/B
on back pressure control and is sent to the Propylene Fractionator No. 1, C-24003. Maintaining back
pressure ensures the liquid in the R-24001A/B bottom sump has enough pressure to be sent to the C-
24003 on level control. A portion of the bottom liquid product from R-24001A/B is recycled back to the feed
by the MAPD Recycle Pumps, P-24004A/B which helps control temperature rise, and henceforth,
controlling the vaporization that occurs in the reactor.
On-line analyzers detect the MAPD, propylene, and propane on the feed and product sides of the MAPD
Converter. If too much hydrogen is added, the reactor may become less selective, so it is important to
closely monitor this during operation.
Page 33 of 41
Liwa Plastics Project
The top of Propylene Fractionator No. 1, operates at a pressure of 20.2 bar(g) and gross overhead vapor is
totally condensed against cooling water in the Propylene Fractionator Condenser, E-24009A/B/C/D, before
it enters the Propylene Fractionator Reflux Drum, V-24003. The tower overhead pressure is set by a “hot
vapor bypass”, where a portion of the gross overhead bypasses the condenser and is fed directly to the
reflux drum. Depending on the amount of material that bypasses the condenser, the operating pressure of
the reflux drum will change. By changing the pressure difference between the condenser and the reflux
drum, the liquid level in the condenser will expose or submerge more condenser tubes. A second pressure
controller in the gross overhead line which controls the amount of cooling water sent to the condenser. In a
high pressure scenario, a hand control can open a vent on V-24003 to the Cold Flare. A continuous vent
from V-24003 is cooled in the Propylene Fractionator Vent Condenser, E-24010, by cooling water where
any liquid that condenses is sent back to V-24003. Any non-condensables are sent on flow control to the
nd
Charge Gas Compressor 2 Stage Discharge Drum, V-22003. In a low pressure scenario, the pressure
controller on the gross overhead vapor line will cut back on the amount of vented to V-22003.
The liquid from V-24003, is pumped by the Propylene Fractionator No. 1 Reflux Pumps, P-24005A/B, and
sent as reflux to the top of C-24003 on flow control reset by the level controller on V-24003. A
pasteurization section is provided at the top of Propylene Fractionator No.1 to strip residual hydrogen
added in the MAPD Converter from the propylene. The propylene product (99.5% purity) is withdrawn as a
side draw from C-24003 Tray #115, and is pumped by the Propylene Product Pumps, P-24007A/B, and
sent to the Propylene Treater Feed Cooler, E-24017. A flow ratio controller controls this product side-draw,
maintaining a constant ratio to the reflux flow. This prevents the draw-off of off-spec Propylene Product.
Tower reboiler duty for C-24003 is provided by quench water sent to the Propylene Fractionator No. 1
Reboiler, E-24011A/B. The bottoms product of C-24003 is pumped by the Propylene Fractionator No. 2
Reflux Pump, P-24006A/B, on flow control reset by the level controller in the tower bottom sump as reflux
to the top of Propylene Fractionator No. 2, C-24004.
The top of Propylene Fractionator No.2, C-24004, operates at a pressure of 21.3 bar(g) and the overhead
vapor is sent to the bottom of Propylene Fractionator No. 1, C-24003. Tower reboiler duty for the C-24004
is provided by Very Low Pressure Steam (VLS) sent to the Propylene Fractionator No. 2 Reboiler, E-
24012A/B. An on-line analyzer detects the propylene content in the downcomer of Tray #35 and resets the
flow controller on the VLS feeding the reboiler. The tower bottoms product, primarily propane, is sent on
flow control reset by the level controller in the bottom sump to the C3+ Feed Preheater, E-20002, and then
the C3+ Feed Vaporizer Drum, V-20012, in the furnace feed system. A high level override from the level
controller on V-20012, can control the bottoms product rate if level gets too high.
On-line analyzers are provided on the overhead and bottoms product to ensure product specifications are
met.
Page 34 of 41
Liwa Plastics Project
HP storage to product conditions at 49°C and 29 bar(g). A provision is made for offspec propylene product
to be reprocessed in the Deethanizer, C-24001.
One PG Propylene Treater is in operation and operates at a pressure of 25.0 bar(g) while the second
treater is being regenerated or on standby. On-line analyzers are provided to detect the amounts of COS
entering and leaving the treaters. The treaters are designed to run for 48 hours before requiring
regeneration. The process of switching from one treater to the next is a timed cycle operation.
Regeneration of the PG Propylene Treaters is carried out by circulating hot methane-rich regeneration gas
from the Treater Regeneration Gas Electric Heater, E-24018, at 290-300°C to drive out the impurities
adsorbed in the treater bed. After the bed has reached the required temperature of 270-290°C, the bed is
cooled with unheated regeneration gas. The spent regeneration gas is returned to the fuel gas system.
7.20 Debutanization
The LP Depropanizer bottoms stream containing C4 and heavier material enters the Debutanizer, C-
24005, on Tray #17. Polymerization Inhibitor from the Polymerization Inhibitor Package, ME-22000, is
injected into the main feed to the Debutanizer to limit fouling in the tower. The Debutanizer is comprised of
43 valve trays and the primary purpose of this tower is to separate a mixed C4 product sent to the
Selective Hydrogenation Unit (SHU) from a C5+ raw pyrolysis gasoline product sent to the Pyrolysis
Gasoline Hydrogenation (PGH) unit OSBL.
The top of the Debutanizer operates at a pressure of 5.3 bar(g) and the gross overhead vapor from this
tower is totally condensed in the Debutanizer Condenser, E-24013, by cooling water before it enters the
Debutanizer Reflux Drum, V-24004. The tower overhead pressure is set by a “hot vapor bypass”, where a
portion of the gross overhead bypasses the condenser and is fed directly to the reflux drum. Depending on
the amount of material that bypasses the condenser, the operating pressure of the reflux drum will change.
By changing the pressure difference between the condenser and the reflux drum, the liquid level in the
condenser will expose or submerge more condenser tubes. In a high pressure scenario, a second
pressure controller in the gross overhead vapor line can open a vent on V-24004 to the Wet Flare. If any
non-condensables accumulate in V-24004, a hand control (HC) provides the ability to send this material
back to the Quench Tower, C-21003, for reprocessing. Total liquid from V-24004 is pumped by the
Debutanizer Reflux Pumps, P-24008A/B, and a portion is sent as reflux to the C-24005 on flow control.
st
The remaining overhead liquid product is sent to the SHU 1 Stage Feed Drum, V-28011, on flow control
reset by the level controller in V-24004, at 48°C and 7.0 bar(g). A provision is made to send this mixed C4
product to storage if the downstream SHU is down; the ability to inject TBC into this stream (to limit
polymerization) is provided from the TBC Inhibitor Injection System, ME-24002.
Tower reboiler duty is provided by Low Low Pressure Steam (LLS) in the Debutanizer Reboiler, E-
24014A/B. A temperature controller on Tray #3 sets the temperature by resetting the setpoint of the flow
controller on the LLS feeding the reboiler. The bottoms temperature of 130°C should be closely monitored
and controlled to limit fouling. The Debutanizer bottoms product, which is raw pyrolysis gasoline, is sent to
the OSBL PGH unit, on flow control reset by the level controller in C-24005 bottom sump. Prior to exiting
the SCU, the raw pyrolysis gasoline is combined with gasoline from the Quench Water Settler, V-21002,
and cooled in the Pyrolysis Gasoline Cooler, E-24015, by cooling water and leaves battery limits at 45°C
and 4.2 bar(g). A provision is made to send this product to storage if the downstream PGH unit is down.
Gasoline Polymerization Inhibitor from the Gasoline Polymerization Inhibitor Package, ME-21001, is
injected into the raw pyrolysis gasoline product. Also before sending the raw pyrolysis gasoline to the PGH
unit it will always pass through the Raw Pyrolysis Gasoline Coalescer Package ME-24003 to ensure that
there is no free water carry over towards the downstream PGH Unit.
Page 35 of 41
Liwa Plastics Project
An on-line analyzer is provided to detect the top specification of the Debutanizer with measurements made
for C3 and C5 components. A second on-line analyzer detects C4 components that end up in the raw
pyrolysis gasoline product.
The compressor discharge vapor is desuperheated and condensed by cooling water. The liquid propylene
refrigerant is subcooled against cold streams in the RDG, NGL, and SCU areas before being used at each
level. During normal operation, propylene vapor extracted from the compressor 2nd stage discharge is
condensed against the ethylene fractionator side reboiler.
Major propylene refrigeration users in the SCU are the ethylene fractionator condenser, the binary
refrigerant condenser and the HP and LP depropanizer condensers. Other users are the charge gas area
and demethanizer feed chilling.
The propylene refrigeration system also provides cooling to the RDG and NGL units.
The binary refrigerant (BR) compressor discharge vapors are cooled first against cooling water partially
condensed against three levels of propylene refrigerant and finally condensed against itself in the cold box.
The condensed BR is sub-cooled against demethanizer bottoms and further sub-cooled against highest
level BR. A portion of the sub-cooled BR stream is then let down to a lower pressure and fully vaporized by
the process users on each level. The remaining BR stream flows to the next lowest level where it is again
further sub-cooled and partially let down. Since the system has a constant composition, it is not subject to
the fluctuations in refrigeration temperature that can be the case with other mixed refrigeration systems.
Makeup ethylene liquid is provided from HP ethylene storage while liquid methane is provided from the
demethanizer reflux drum. In addition, ethylene vapor is provided from the LP ethylene product header
while makeup methane vapor is provided from the demethanizer reflux drum.
The binary refrigeration system also provides cooling to the RDG unit.
Page 36 of 41
Liwa Plastics Project
BD Concentration (wt)
Inlet Outlet
st
1 Stage SHU 29% 1.5 %
nd
2 Stage SHU 1.5% 300 ppm
3rd Stage SHU 300 ppm 10 ppm
st
8.1 SHU 1 Stage Reactor
st
A mixed C4 product from the Debutanizer, C-24005, is fed into the SHU 1 Stage Feed Drum, V-28011,
st
prior to being fed to the 1 Stage SHU Reactor. The total fresh C4 stream is then pumped by the SHU First
Stage Feed Pumps, P-28011A/B, to the SHU 1st Stage Reactor, R-28011A/B, where it is mixed with the
hydrogenated recycle before entry. The flow rate of the fresh C4 stream is controlled by the liquid level
controller on V-28011 which resets a flow controller. The recycle stream is fed on flow control. The recycle
stream reduces the butadiene concentration to 4 wt.% and thereby limits the temperature rise across the
reactor. The recycle stream temperature provides for temperature control of the SHU reactor inlet. The
conversion of butadiene achieved in the reactor is determined by catalyst activity, reactor temperature and
st
equilibrium. Hydrogen from the PSA unit is fed to the 1 Stage SHU reactor on ratio flow control to the
fresh C4 feed stream. The reactor has a distributor to ensure even distribution across the catalyst bed.
There are three types of chemical reactions which occur in the SHU; selective hydrogenation of butadiene
and acetylenes into n-butenes, hydro-isomerization of n-butenes between butene-1 and 2-butene, and
olefin saturation. Olefin saturation, however, is minimized due to the high reactivity of butadiene in relation
to the olefins.
Selective hydrogenation is an exothermic process and therefore causes a temperature rise across the
reactor. The heat of reaction is absorbed by the C4 stream as it passes downward through the catalyst bed.
st
The reaction product is then flashed in the SHU 1 Stage Separator Drum, V-28012. In the Separator
Drum, hydrogen, other light gases, and any C4’s vaporized by the heat of reaction are separated. The
st
flashed vapor is sent to the shell side of the SHU 1 Stage Vent Condenser, E-28011, which utilizes
cooling water to condense C4’s which flow by gravity back to V-28012. The off-gas from the cooler is sent
nd
on pressure control to the Charge Gas Compressor 2 Stage Suction Drum, V-22002. The pressure
st
controller on the off-gas is the control point for the 1 Stage SHU Reactor system pressure. If the
hydrogen does not contain sufficient inerts or is reacting to completion, a small amount can be directed to
the Separator Drum to assist in pressure control.
st
The liquid leaving the Separator Drum is pumped by the SHU 1 Stage Recycle/Product Pumps,
nd st
P-28012A/B, to either the 2 Stage SHU or as recycle to the SHU 1st Stage Reactor. The SHU 1 stage
st
effluent is cooled with cooling water in the SHU 1 Stage Recycle/Product Cooler, E-28013. The
st
temperature of the SHU 1 Stage effluent for either location is maintained by separate bypass temperature
st st
controllers. The SHU 1 stage effluent is recycled back to the feed on flow control. The SHU 1 stage
nd
effluent feeding the SHU 2 Stage is fed on flow control reset by level on the Separator Drum.
A gradual loss of catalyst activity will occur as the active sites on the catalyst become blocked by coke.
Regeneration of the catalyst is required when catalyst activity has dropped to the point when the reactor
st
outlet temperature exceeds the 1 Stage Reactor EOR conditions, when high reactor pressure drop
occurs, or with significant loss of selectivity. Regeneration requires the catalyst bed to be taken offline,
drained and purged of hydrocarbons, and heated with hot nitrogen followed by superheated steam. Air is
fed on flow control in the superheated steam to decoke the catalyst bed. A final nitrogen purge, which
contains a controlled amount of hydrogen, activates the catalyst bed by reduction. Regeneration of the
SHU catalyst is typically required after one year of operation.
Page 37 of 41
Liwa Plastics Project
st
The C4 recycle-to-fresh feed ratio in the SHU 1 Stage System is kept constant from SOR to EOR at 10 to
1 on a weight basis.
During startup, a safe fluid (low olefin content) is circulated to bring the system up to the required operating
st st
temperature. The SHU 1 Stage Startup Heater, E-28012, located between the SHU 1 Stage Separator
st
Drum and the SHU 1 Stage Recycle/Product Cooler provides the required heat. The temperature of the
safe fluid is set by a temperature controller, which controls the amount of Saturated LLS sent to E-28012.
Once normal production rates are established, this heater is bypassed.
nd
8.2 SHU 2 Stage Reactor
nd st
The SHU 2 Stage Reactor, R-28021A/B, has a configuration very similar to that of the SHU 1 Stage
nd
Reactor, R-28011A/B. The major difference between the two is that the 2 Stage Reactor’s feed has a
much lower concentration of butadiene and therefore the exothermic temperature rise across the catalyst
nd
bed is smaller. The 2 Stage SHU Reactor reduces the concentration of butadiene in the feed from
approximately 1.5 wt% to below 300 ppmw.
nd st
The SHU 2 Stage Reactor feed is the SHU 1 Stage Reactor effluent mixed with hydrogen from the PSA
nd
unit and SHU 2 stage recycle. Hydrogen is added to the mixed feed stream using a flow ratio controller.
st
This flow ratio controller receives a signal from a flow indicator on the SHU 1 stage effluent stream. The
nd st
SHU 2 Stage effluent recycle stream is added on flow control to the SHU 1 Stage Effluent before the
hydrogen addition. The recycle stream is used to dilute the butadiene concentration at the reactor inlet to
about 0.5 wt.% and thereby limit the exothermic temperature rise. To provide the desired operating
nd
temperature for the reaction, the SHU 2 Stage Feed Heater, E-28021, can heat the reactor feed using
Saturated Low Low pressure steam (Sat LLS) if required. A temperature controller on the 2nd stage feed
resets the flow controller on Saturated LLS fed to E-28021. Control of the inlet temperature and hydrogen
ratio controls the butadiene conversion.
The exothermic heat of reaction heats the C4 stream as it passes downward through the catalyst bed. Like
st
the 1 Stage Reactor, there is a reactor distributor present to ensure even distribution across the catalyst
nd
bed. The reaction product is flashed in the SHU 2 Stage Separator Drum, V-28022. The vapor from the
Separator Drum, which contains some unreacted hydrogen, inerts, and any C4’s vaporized by the heat of
nd
reaction, is sent to the SHU 2 Stage Vent Condenser, E-28022, which uses cooling water in the tube
side. The off-gas from the cooler is sent on pressure control the Charge Gas Compressor 2nd Stage
Suction Drum, V-22002. The pressure controller on the off-gas is the control point for the SHU 2nd Stage
Reactor system pressure. If the hydrogen does not contain sufficient inerts or is reacting to completion, a
small amount can be directed to the Separator Drum to assist in pressure control.
nd
The liquid from the separator drum is then pumped by the SHU 2 Stage Recycle/Product Pumps P-
rd nd
28022A/B, either as product to 3 Stage SHU or as recycle back to the SHU 2 Stage Reactor, R-
28021A/B. Each effluent stream’s temperature is independently controlled using temperature bypass
nd
control around the SHU 2 Stage Recycle/Product Cooler, E-28023, which operates on cooling water in
the tube side. The SHU 2 stage effluent is recycled back to the feed on flow control. The SHU 2nd stage
nd
rd
effluent feeding the SHU 3 Stage is sent on flow control reset by level on the Separator Drum.
st
Just as in the SHU 1 Stage Reactor, a gradual loss of catalyst activity will occur as the active sites on the
nd
catalyst in the 2 Stage Reactor become blocked by coke. Regeneration of the catalyst is required when
nd
catalyst activity has dropped to the point when the reactor outlet temperature exceeds the 2 Stage
Reactor EOR conditions, when high reactor pressure drop occurs, or with significant loss of selectivity.
Regeneration requires the catalyst bed to be taken off line, drained, purged of hydrocarbons, heated with
hot nitrogen, and then with superheated steam. Air is fed on flow control into the steam to decoke the
Page 38 of 41
Liwa Plastics Project
catalyst bed. A final nitrogen purge, which contains a controlled amount of hydrogen, activates the catalyst
bed by reduction. Regeneration of the SHU catalyst is typically required after one year of operation.
nd
The C4 recycle-to-fresh feed ratio in the SHU 2 Stage System is kept constant from SOR to EOR at 2 to
1 on a weight basis.
During startup, a safe fluid (low olefin content) is circulated to bring the system up to the required operating
temperature as is done in the SHU 1st Stage. Unlike the SHU 1st Stage, there is no startup heater. The
nd
heat input (if required) is provided by the SHU 2 Stage Feed Heater, E-28021.
rd
8.3 SHU 3 Stage Reactor
rd
The SHU 3 Stage Reactor, R-28031, has a configuration that differs from the previous two stages of
hydrogenation. The major difference is that there is no recycle of reactor effluent to mix with the feed. The
rd
3 Stage SHU Reactor reduces the concentration of butadiene in the feed from approximately 300 ppmw
to below 10 ppmw.
rd nd
The SHU 3 Stage Reactor feed is the SHU 2 Stage Reactor effluent mixed with hydrogen from the PSA
unit. Hydrogen is added to the mixed feed stream using a flow ratio controller. This flow ratio controller
nd
receives a signal from a flow indicator on the SHU 2 stage effluent stream. To provide the desired
rd
operating temperature for the reaction, the SHU 3 Stage Feed Heater, E-28031, can heat the reactor feed
rd
using Saturated Low Low pressure steam (Sat LLS) if required. A temperature controller on the 3 stage
feed resets the flow controller on Saturated LLS fed to E-28031. Control of the inlet temperature and
hydrogen ratio controls the butadiene conversion.
The exothermic heat of reaction heats the C4 stream as it passes downward through the catalyst bed. Like
the first two SHU stages, there is a reactor distributor present to ensure even distribution across the
rd
catalyst bed. The reaction product is cooled by cooling water in the SHU 3 Stage Effluent Cooler, E-
rd
28032A/B. Pressure control is accomplished in the system by controlling the amount of SHU 3 Stage
product leaves the system.
Just as the first two SHU stages, a gradual loss of catalyst activity will occur as the active sites on the
rd rd
catalyst in the 3 Stage Reactor become blocked by coke. Since no spare reactor is provided for the 3
Stage SHU, the ability to bypass this reactor is provided if regeneration is required. Regeneration of the
catalyst is required when catalyst activity has dropped to the point when the reactor outlet temperature
rd
exceeds the 3 Stage Reactor EOR conditions, when high reactor pressure drop occurs, or with significant
loss of selectivity. Regeneration requires the catalyst bed to be taken off line, drained, purged of
hydrocarbons, heated with hot nitrogen, and then with superheated steam. Air is fed on flow control into
the steam to decoke the catalyst bed. A final nitrogen purge, which contains a controlled amount of
hydrogen, activates the catalyst bed by reduction. Regeneration of the SHU catalyst is typically required
after one year of operation.
During startup, a safe fluid (low olefin content) is brought in to soak the catalyst.
hydrocarbon from OSBL Hydrocarbon Drain Drum (V-83015). Hydrocarbon Drain Pumps (P-10001A and
P-10002A) pump the collected hydrocarbon to Quench Tower (C-21003). The drums are floating on the
flare header and equipped with LLP Steam heating coil to maintain the temperature inside the vessel and
prevent hydrocarbon getting viscous. The drums are swept with fuel gas to prevent concentration of toxic
gas. Hydrocarbon which is drained to the drums may contain benzene more than 5%.
Page 40 of 41
Liwa Plastics Project
Page 41 of 41
Petrochemical Plant Sohar Environmental Impact Assessment Report
Orpic and CB&I HMR #3817
Six (6) SRT VI cracking heaters are installed. Five heaters are normally in
operation and one heater is spare for decoke or maintenance. There are two
Ethane Heaters and four Flexible Heaters. Each heater consists of two radiant
cells, a common convection section, a steam drum, an induced draft (ID) fan, a
SHP steam vent silencer, two desuperheaters, a main transfer line valve, one
large decoke valve, and one small decoke valve. There are 8 radiant coils and 8
primary transfer line exchangers (TLE) for each Ethane Heater. There is one
secondary TLE per heater following the primary TLEs. There are 6 radiant coils
and 6 primary TLE’s for each Flexible Heater. There is no secondary TLE in the
Flexible Heater.
Each heater has two radiant cells with a common convection section in the
middle. There is one ID Fan and stack on top of the convection section. There
is one Steam Drum per heater.
Refer to Section 2 for information and description on the heater design, and the
BEP for the Basis of Design.
The Flexible Heaters are designed to crack all feeds, thus providing full
feedstock flexibility for easy operation. All heaters are twin radiant cell design
with common convection section, stack, and stream drum. The Ethane Heaters
are designed to optimize the cracking of ethane feed. Secondary TLE is
provided for the Ethane Heaters to maximize energy recovery. Flexibility is
provided for the Ethane Heaters to cocrack ethane and propane feed by partially
bypassing the secondary TLE. Additional flexibility is provided for the Ethane
ORPIC SOM – SECTION 3.DOC Page 1 of 60
Lummus Petrochemicals
The convection section of the Ethane Heaters F-20001 and F-20002 contains
the following coil services (in order from top to bottom):
Upper Feed Preheat (UFP) coil,
Boiler Feed Water Preheat (BFWP) coil,
Lower Feed Preheat (LFP) coil,
Upper SHP Steam Superheat (USSH) coil,
For the Flexible Heaters, the upper feed preheat (UFP) coil is used to preheat
and vaporize the liquid C5/OLNG feed and preheat the C3+ feeds Light gas
feeds such as ethane to the Flexible Heaters requirebypassing of the Upper
Feed Preheat Coils and part of the Lower Feed Preheat Coils due to low feed
preheat duty requirement of the ethane compared to the duty needed to vaporize
the liquid C5/OLNG feed. Refer to the Heater Datasheets for the specific usage
of the UFP coil for various feeds.
For each Flexible Cracking Heater, the hydrocarbon feed on flow control to the 6
individual coil passes is first heated in the Upper and Lower Feed Preheat
coils(except for the light gas feed like ethane bypassing the UFP as mentioned
previously) of the heater convection section. Dilution Steam is mixed with the
preheated feed from the Lower Feed Preheat Coil. The mixed hydrocarbon and
dilution steam feed is returned to the Upper Mix Preheat (UMP) Coil of the
convection section. The total mixture of hydrocarbon and steam is heated to the
crossover temperature in the Mixed Preheat Coils before entering the Radiant
ORPIC SOM – SECTION 3.DOC Page 3 of 60
Lummus Petrochemicals
Coils via external crossover piping. The crossover piping from each convection
section coil feeds a single radiant coil inlet manifold at the top of the radiant
section. From the cross over manifold critical flow venturis are provided to
distribute the flow equally to the inlet tubes of the radiant coil. DMDS is injected
into the dilution steam header at the inlet to each heater before mixing with the
preheated hydrocarbon feed as required.
The Ethane Cracking Heaters have a total of 8 radiant coils per heater, four in
each cell and has one Secondary TLE per heater. The effluents from all primary
TLEs are combined and sent to the secondary exchanger.
Excess heat in the flue gas after heating the hydrocarbon and dilution steamg is
recovered in the convection section by preheating the boiler feed water in the
BFWP coil and also by superheating the SHP steam in the USSH and LSSH
coils. There is a Desuperheater for temperature control: one at the outlet of the
USSH before reentering the LSSH. The Desuperheater is required for
temperature control of the SHP steam, which otherwise may exceed the SHP
steam outlet temperature specification and to prevent the steam going below the
saturation point after BFW injection.
Each heater discharges flue gas into an individual stack. A motor-driven induced
draft fan is located in each stack. Draft in the heater is adjusted via a pressure
controller that manipulates the variable frequency drive (VFD) to control the
speed of the fan.
There are 8 radiant coils, 8 primary TLE’s and one secondary TLE in one Ethane
Heater and 6 radiant coils and six primary TLE’s in one Flexible Heater.
There are two radiant cells per heater. Each Ethane Heater radiant cell has 4
radiant coils. Each Flexible Heater radiant cell has 3 radiant coils.
Each radiant coil is composed of four two-pass 8-1 units. This 8-1 coil
arrangement is the same for both Ethane and Flexible Heaters. This results in a
radiant coil with a total of 32 tubes in the inlet pass and 4 tubes in the outlet pass.
The flow to one 32-4 radiant coil is controlled by one (HC) feed control valve and
one dilution steam control valve. The four outlet radiant tubes are combined and
fed to the Primary Transfer Line Exchanger (TLE). There is one TLE per radiant
coil.
The flow from one radiant coil inlet manifold (cross over) is equally distributed to
the multiple inlet tubes of the first pass of the radiant coils using critical flow
venturis.
The first pass inlet tubes are connected to the second pass outlet tubes via
contoured manifold. The manifold is placed in a trough in the radiant box. With
temperature (thermal expansion) and creep the coil freely moves. Free
movement of the coil is important to minimize bending and bowing of the coils.
This is discussed elsewhere.
3.1.3 Burners
The heaters are hearth fired supplemented with wall burners. The proportion of
the total firing for the wall/hearth burners is 25%/75%, respectively. The hearth
and wall burners are arranged symmetrically on both sides of the radiant coils.
All burners are capable of firing methane offgas (plant fuel gas) for normal
operation, natural gas as backup/startup fuel gas, as well as high ethane and
hydrogen as specified in the project design data.
It is expected that the same fuel gas composition will be sent simultaneously to
all heaters at all times, because the fuel gas is fed from a common fuel gas drum.
Coil outlet temperature (COT) is controlled via duty control cascaded to the
hearth fuel gas flow which will vary automatically to maintain the required total
fired duty for the feedrate loading and COT setpoints. The wall burners are base
loaded, therefore the hearth firing varies only the remainder of the required fired
duty.
Individual firing control is provided for each of the two radiant cells of a heater.
The COT control for the coils controls the firing of the corresponding radiant cell.
Large deviations between the firing rates between the two radiant cells should be
minimized.
Multiple small diameter tubes are utilized in the first pass of the radiant coils of
each heater. Each first pass tube has a critical flow venturi at the inlet. The
venturis insure equal flow distribution to the inlet pass tubes fed by each
crossover pipe and each radiant inlet manifold.
The first pass pressure drop (excluding the venturi) is designed to be relatively
low for good selectivity to olefins. However, this makes the flow distribution very
sensitive to differences in flow resistance among the inlet tubes. As a result,
coke may be deposited unevenly among the tubes during the run cycle and
result in pressure drop differences and flow maldistribution which, in turn, can
cause further premature coking and reduced run length. Therefore, the two-pass
coil design uses a critical flow venturi at the inlet of each first pass tube to
counteract this effect and thus maintain even flow distribution at all times during
the run cycle.
The venturi is designed so that the throat velocity remains sonic (choked) from
Start-of-Run (SOR) to End-of-Run (EOR) for all anticipated operating conditions.
ORPIC SOM – SECTION 3.DOC Page 7 of 60
Lummus Petrochemicals
Thus, the flow to each tube is accurately and uniformly controlled by the choked
throat. This design concept results in the pressure upstream of the venturi
remaining essentially constant from SOR to EOR for any given operating
condition. These are specially designed venturis machined with high precision
tools. For the 8 coil Ethane Heaters, the venturi throat diameter is 14.0 mm with
a tolerance of +0.0 / -0.1 mm. For the 6 coil Flexible Heaters, the venture throat
diameter is 15.2 mm with a tolerance of +0.0 / -0.1 mm.
For each 8-1 radiant coil grouping, there is a single pressure differential indicator
(PDI) to monitor the venturi pressure drop across one of the eight venturis.
Coupled with the pressure measured upstream of the radiant inlet manifold
(“crossover pressure”), it is possible to calculate and trend the PDI to upstream
PI ratio as an effective method to monitor whether or not the venturis are choked.
The gage pressure data from the PI should be converted to absolute unit in the
PDI to PI ratio. Unchoking of a venturi (PDI/PI abs. < 0.1) in any of the
groupings is one of the criteria for terminating the heater run cycle. Only one
PDI per grouping is necessary, since the inlet pass tubes experience similar coke
buildup under normal operation. Thus the PDI measurement across a single
venturi in each 8-1 grouping is, in theory, identical to other venturis connected to
the same bottom manifold.
The S/HC ratio should be increased if necessary to keep the venturi choked.
The purpose of the Primary Transfer Line Exchanger (PTLE) is to cool the heater
effluent as rapidly as possible, which minimizes undesirable polymerization and
other tar forming reactions, and to recover energy by generating steam at super
high pressure level.
Effluent from one 32-4 radiant coil outlet is sent to one primary transfer line
exchanger. Each SRT VI Ethane Cracking Heater has eight (8) TLE’s, one for
each radiant coil. Each Flexible Cracking heater has six (6) TLE,s, one for each
ORPIC SOM – SECTION 3.DOC Page 8 of 60
Lummus Petrochemicals
radiant coil. Temperature indicators and high temperature alarms are provided at
the outlet of each PTLE to monitor exchanger performance and to guard against
overheating that might cause damage to the PTLE and downstream transfer line.
The Primary TLE's are vertical exchangers of a special design. The hot cracked
gas enters the tube side via an internally lined inlet cone at the bottom of the
exchanger and flows upward. Super high pressure boiler feed water enters the
shell side via a distribution system at the bottom. The steam/water mixture flows
upward, co-current with the process gas. The steam generation circuit in the
riser and downcomer piping between the steam drum and Primary TLE’s is
designed to circulate water for partial vaporization (about 10% of the circulated
flow) by thermosyphon action, using static head from the steam drum located
above the TLE's as the driving force.
Each Ethane Heater has one Secondary TLE. The Secondary TLE is a vertical
heat exchanger that cools the cracked gas effluent (from the Primary TLE’s) on
the tube side and heats the mixed feed on the shell side. The effluents from the
eight Primary TLE’s of one heater are combined and sent to a Secondary TLE.
A bypass is provided for the mixed feed (shell side) around the STLE to limit the
tube side STLE outlet temperatures to minimize the condensation of heavy
components in the cracked gas which could foul the STLE. For EP co cracking,
the STLE should be partially bypassed to no less than 230 °C in the STLE outlet.
ORPIC SOM – SECTION 3.DOC Page 9 of 60
Lummus Petrochemicals
For C3+ cracking, the STLE should be totally bypassed. For ethane cracking,
no bypass is required. The tarry material present in C9+ components condense
causing this problem. Therefore with higher fuel oil yield, bypassing the
secondary TLE outlet temperature also increases. The above values are only
suggested values for the design feed at the design conditions. When the fouling
is more severe than normal, increase the bypass flow rate.
The flow from the TLE section of each heater can follow two flow paths:
During normal cracking operation, the combined cracked gas effluent
from the TLE’s is sent through the Main Transfer Line Valve (TLV) and
then to the downstream recovery section via the main transfer line.
During steam/air decoking, the combined effluent from the TLE’s is
routed through the decoke valves (motor-operated Large Decoke
Valve and non-MOV Small Decoke Valve) into the decoke effluent
piping to the firebox.
During High Steam Standby, the effluent from the TLE’s can take
either flow path described above.
The motor operated Main TLV and the decoke valves (Large and Small DV) are
interlocked to prevent the accidental release of cracked gas heater effluent to the
atmosphere via the decoking line, or alternatively, the introduction of decoking
steam and air to the downstream recovery section. The Small Decoke Valve
(SDV) is operated via a mechanical link with the Main TLV. Using the SDV
permits its maintaining upstream pressure during switching to be sufficiently high
to prevent reverse flow from the main transfer line into the decoke piping system,
yet avoid overpressure of the main transfer line.
The mechanical linkage between Main TLV and SDV is designed by the valve
vendor such that closing the Main TLV will create adequate backpressure to
ORPIC SOM – SECTION 3.DOC Page 10 of 60
Lummus Petrochemicals
prevent backflow of cracked gases from the main transfer line into the decoke
line. The switching must be done at High Steam Standby (HSS) flow rate. The
SDV, in fact, is sized to have choked flow based on the HSS flowrate. Therefore,
even if the Main TLV and SDV are simultaneously fully open, backflow of
hydrocarbon effluent from the main transfer line into the decoking system cannot
occur against the normal backpressure expected in the transfer line (downstream
of the Main TLV).
The Large Decoke Valve (LDV), in conjunction with the SDV, isolates the heater
from the decoke piping system during cracking operation, and provides the basis
for the main decoke line size to minimize erosion of this piping. The LDV is
interlocked and cannot be opened (in preparation for decoking after feed-out)
unless the Main TLV is fully closed, and conversely, the Main TLV cannot be
opened (in preparation for feed-in after decoking) unless the LDV is fully closed.
Operators should become completely familiar with the 3-valve interlock operation
and sequential movement of these valves before starting the heater. Refer to
the interlock summary table in the BEP.
Periodic steam purging through the two drain connections shown on the P&ID
during the High Steam Standby, Decoke or Shutdown modes of operation is
recommended to minimize the accumulation of material upstream of the both the
Main TLV and the LDV.
There are also continuous steam purges through the Main TLV, LDV and SDV.
Refer to Section 4 for detailed discussions on these steam purges.
The cracked effluents from all heaters are collected and sent to gasoline
fractionator by a common transferline. Quench Fittings are installed in the
common transferline where the combined stream is cooled to the desired
temperature with quench oil.
The new plant shall have two main transfer lines to collect and direct the cracked
gas effluent from the outlet of the TLE’s for the six (6) Cracking Heaters (F-
20001 thru F-20006) to the Gasoline Fractionator. Each one of the two transfer
lines collects the cracked gas from three (3) Heaters and directs the flow to one
of two Quench Fittings M-21001A/B. Quench oil is sprayed into the gas causing
the cooling. The quench oil flow rate is controlled based on outlet temperature.
Too low outlet temperature will require high flow rate of quench oil. Too small
flow rate may produce high mixed temperature. At high temperatures, quench oil
itself can generate coke or tarry matter. Therefore optimum quenching is
recommended (+/- 5 °C of design outlet temperature).
3.2.1 Introduction
The heaters operate under the following allocations for the design operating
case (Case 1) to achieve the required plant capacity:
Refer to the Heater Performance Data Sheets in PDP for a more complete
summary of the detailed parameters.
.
The main operating variables and controls for the cracking heater are:
Heat Input (Fuel Fired) Fuel flow (adjusted for Wobbe index)
The total feed rate to the cracking heaters is set by the operator based on plant
production requirements, with feed allocation not to exceed the design rate of
any heater.
Operating the heater at higher than design ethylene production rates can result
in short run lengths and/or exceeding design temperatures in the convection
section. In extreme cases, it can damage the heater.
Dilution steam is added to the hydrocarbon feed to control the partial pressure of
the reacting hydrocarbons. A lower hydrocarbon partial pressure results in a
higher yield of desirable products such as ethylene. Higher dilution steam rates
also reduce the radiant coil coking rate and the TLE fouling rate. Reducing
dilution steam will have the opposite effect. For each feed type there is a
minimum steam-to-oil ratio. Below this value is not recommended.
Operation at higher or lower than design S/HC is possible with the consequences
as noted above as well as impacts on equipment loading and energy
consumption.
The dilution steam rate also impacts the operation of the critical flow venturis on
the heaters. The limitations on venturi operation and heater turndown should be
considered before adjusting S/HC to lower than design values. The S/HC should
be increased as needed to keep the venturi choked (PDI/PI absolute ratio larger
than 0.1).
Experience has shown that the optimum amount of dilution steam is dependent
upon the feedstock properties and cracking severity. The design quantity of
dilution steam selected for the heaters is shown below as weight ratios of the
feedstock rate.
Experience has shown that the injection of small amounts of sulfur into
feedstocks that are essentially sulfur-free will reduce the concentration of CO
and CO2 in the cracked effluent. Sulfur addition has also been shown to reduce
coking in some cases and carburization of the radiant coils.
The nickel and nickel oxides on the surface of the radiant coil promote a carbon
reaction with steam to produce CO and CO2. The catalytic action is greatest at
start of run with a clean tube. Generally dimethyl disulfide (DMDS) or dimethyl
sulfide(DMS) is used as sulfiding agent for gaseous feeds. All sulfur molecules r
crack to H2S in the pyrolysis coil. Sulfur reacts with coil metal and metal oxides
to form a protective coating. It inhibits the catalytic action of the nickel.
Even hydrocarbon feeds that contain sulfur may require addition sulfur (DMDS or
DMS) to passivate the metal. Amount of sulfur addition varies with feedstock, but
each feed must have a minimum amount. The lowest effective dose can be
found by experimentation. Start with a high sulfur injection rate at feed-in and
decrease the rate until the CO does not change significantly any more.
Experience dictates that this minimum amount is between 50 and 100 ppmw of
Figure 3.2.5
Relationship between CO production and sulfur concentration
The normal injection rate is 50 -100 ppm by weight of sulfur for feedstocks that
are very low in sulfur (C3,C4, light naphtha, condensate liquids) or are essentially
sulfur-free (C2, C3 or C2/C3 mixed gases). For feeds that already contain sulfur,
the injected amount of sulfur should supplement the feed sulfur content such that
about 50-100 ppm is always maintained.
Avoid injected sulfur rates of 200 ppmw and higher as these levels can lead to
sulfur attack and damage to the radiant coils.
The normal concentration of CO and CO2 in the heater effluent is about 0.07
and 0.02 wt%, respectively. Higher effluent levels of CO and CO2 indicate that
the sulfur concentration is insufficient and DMDS rate should be increased. A
calibrated analyzer should be used to verify the small amounts of CO and CO2.
ORPIC SOM – SECTION 3.DOC Page 17 of 60
Lummus Petrochemicals
Some clients practice pre-sulfiding, which is the injection of 200 ppm sulfur
during HSS operation for up to 4 hours prior to feed-in. In these special cases,
pre-sulfiding can help suppress CO formation and possibly extend run length.
For this project front end acetylene converters are used. Therefore, CO to the
converters has to be limited. Hence, presulfiding must be done before oil-in.
The sulfur compound injected into the feed is typically dimethyl-disulfide (DMDS)
of which 68 wt% sulfur. Refer to Section 4 for more discussions on the DMDS
Injection System.
DMDS to the heater should be shut when there is no feed to heater unless
heater is being presulfided. Shutting the supply of DMDS to the decoking heater
should include shutting the manual valve(s) to make sure DMDS is not in contact
with the decoke air or dilution steam. The sulfur when mixed with decoke
air/dilution steam could be a corrosion problem for the radiant coils and
downstream decoke piping. Sulfur should not be discharged to the decoke
system to avoid acid gas emissions.
3.2.6 Conversion/Severity
In general, higher coil outlet temperature means higher conversion (or severity).
Conversion and severity are measured in various ways. Conversion or severity
measures how severely a feedstock is cracked.
The heaters are designed for a conversion of 63% ethane when cracking ethane
feed. For the C3+ Mix, the heaters are designed for 92.8% n-butane conversion.
Operating at higher conversion is possible but this will decrease the run length.
Operation at lower conversion will increase the recycle flows. In commercial units
even for pure components conversion is difficult to measure. Therefore, often
severity as defined by the ratio of two effluent components is used. The famous
one is propylene to ethylene ratio.
As severity is decreased (higher P/E), the ethylene yield will decrease and the
propylene yield will increase until the point of maximum propylene yield is
reached (typically near a P/E of 0.65-0.70 for OLNG). After this point both
ORPIC SOM – SECTION 3.DOC Page 19 of 60
Lummus Petrochemicals
propylene and ethylene will both decrease. Operation at a severity below the
maximum propylene yield is typically not cost-effective for plant economics.
Conversion and severity are calculated using information from the heater effluent
analyzer. A typical analyzer (GC) will report only C3 and lighter components in
mole percent. The reported values are then converted to weight percent or P/E
weight ratio.
Severity and conversion are controlled by changing the heater COT which has
the most significant impact. Increasing COT will increase conversion/severity,
and vice-versa.
In general COTs shown in the datasheets are 10 to 20oC hotter than the actual
value for the given severity. Therefore, always start at 20 to 25oC below the
target COT. After analyzing the effluents and confirming the severity only, the
COT can be increased. Also during this soft start-up, the heater has to be
physically inspected for any mechanical problems like bowing and burner
performance. At low temperatures malfunction of the equipment can be
corrected easily and the damage to the heater is minimum.
3.2.7 Selectivity
Changes in RT and HCPP affect all types of cracking feeds but the effect on
yield for heavier feedstocks, such as OLNG, is much greater than the lighter
feeds such as ethane and propane.
The order of magnitude of RT is largely a function of the radiant coil design but is
relatively affected by:
Feed rate – as feed rate increases the RT decreases
S/HC – as S/HC increases the RT decreases
COP – as COP decreases the RT decreases
In practice, these changes are relatively small and have only a small impact on
selectivity once the coil type is finalized.
The S/HC can be varied to change selectivity. Increasing the S/HC increases
selectivity and the production of desirable products but also consumes more
energy and increases the loading on the heaters, gasoline fractionator, and
quench tower. Decreasing S/HC has the reverse impact and it increases the
coking rate.
Decreasing COP results in a lower HCPP and improved yields. However, the
charge gas compressor (CGC) suction pressure must be reduced in order to
decrease COP, resulting in increased energy consumption and a higher loading
on the compressor. COP can therefore also be optimized based on economic
factors and in consideration of equipment constraints.
COP can be affected significantly by fouling of the radiant coils and TLEs. The
Lummus radiant coils and TLEs are designed to minimize pressure drop
increase over the cracking cycle, thus maintaining close to SOR yields
throughout the run cycle. However, upsets and coke spalling events can result in
increased COP. For example, coke that spalls from the radiant coil can partially
block TLE tubes and increase the COP.
Only 40 to 45% of the heat released by the fuel in a cracking heater is absorbed
in the radiant section. This value is defined as the radiant efficiency. The
remaining heat in the flue gas is recovered in the convection section or lost to the
surroundings (as heat loss).
The overall thermal efficiency is a measure of the percent of fired duty (heat
input), which is recovered as useful heat. Usable heat is the sum of the heat
required to preheat the feed, BFW, SHP steam (superheat), dilution steam, plus
the heat absorbed by the radiant coils, which provide the heat of reaction for the
cracking products. By difference, the unrecovered or unused heat is the sum of
ORPIC SOM – SECTION 3.DOC Page 23 of 60
Lummus Petrochemicals
the heat lost to atmosphere by the flue gas through the heater stack plus the
heat lost to the atmosphere through the casing and convection module (heat
leak).
The convection section is designed to maximize heat recovery. The simplest way
to monitor heater efficiency is by measuring the stack temperature.
Approximately an increase in stack temperature of 18°C indicates a loss of about
1 percentage point in efficiency. Note that increases in stack temperature can
result from other causes.
Heat loss through the casing walls is minimized by maintaining the insulation in
the radiant and convection sections.
Increasing the excess air results in additional flue gas flow and an increased load
on the convection section. As a result, the stack temperature and heat loss will
increase. Small increases in excess air will not result in significant changes in
efficiency in a modern high efficiency heater. Aggressive control of excess air
(low excess air) therefore does not typically yield large benefits. Operating below
10% excess air is discouraged as this can result in poor flame quality for some
burners and the heater damage from localized afterburning.
Increasing the heater feed rate will result in a decrease in efficiency, but the
impact will be small for up to about a 10% change in rate.
Increased feed inlet or BFW inlet temperature will reduce efficiency by reducing
the available temperature driving force for heat transfer (‘LMTD” or log-mean
temperature differential). The impact is minor compared to other factors cited.
ORPIC SOM – SECTION 3.DOC Page 24 of 60
Lummus Petrochemicals
The largest impact on heater efficiency results from fouling. Fouling on the
inside of the convection tubes is generally not significant, unless the feed has
high boiling components. Fouling on the outside of the tubes results from debris
depositing between the fins on the tubes. The material that deposits is believed
to be largely from the atmosphere and brought in with combustion air via the
burners. Refractory dust, dust from decoking and oxidized material from the
radiant coil can also contribute to outside fouling.
There are several methods of cleaning the outside surface of the convection
tubes. All methods work better if the fouling is not allowed to stay in place for a
long time. After several years the material gets baked onto the fins and is much
more difficult or impossible to remove. Lummus should be consulted about the
best method for cleaning the convection section.
Convection section efficiency can also be affected by damage to the tube fins
caused by overheating. Damage can occur if the heater is operated:
At higher than design feed rates and or severities
With very high or low excess air
Fouled or poorly adjusted burners
Some overheating (short duration) can also occur during crash shutdowns.
Consistent overheating of the convection section will oxidize tube fins and
reduce efficiency. Overheating can also damage tube supports and bow tubes
greatly reducing their life span.
For the design feeds typical maximum cross over temperatures are 660C for
C5/OLNG, 680°C for C3+ and 750oC for ethane. These maximum XOT’s are
recommended to prevent coking in the convection tubes. The mechanical
design temperature limit for the crossover piping is 760C. Exercise caution while
decoking since high cross over temperatures are noticed during decoking.
Excess air has the most significant impact. Increasing the excess air will result in
a higher XOT, since more flue gas will be generated as a result of increased
firing in the radiant section.
Increasing the feed rate will also generate more firing, but since more feed is
preheated in the convection section, the result is that XOT is relatively insensitive
to feed rate.
Changes in fuel gas composition that result in a lower fuel heating value will
increase the XOT. For example, a change in the normal fuel gas composition
from 55% to 35% hydrogen (balance methane) results in a predicted XOT
increase of about 4-6°C.
The heater design philosophy precludes the need for XOT to be explicitly
controlled; rather it is set by designing for optimum heating surface utilizing the
ORPIC SOM – SECTION 3.DOC Page 26 of 60
Lummus Petrochemicals
Air can leak into the convection section wherever there are penetrations as such
where BFW enters the preheat coil, where the crossovers exit the convection
section, etc. The cold air that leaks into the heater will reduce the temperature of
the flue gases and increase the mass of flue gas to be processed in the
convection section. Air leakage therefore reduces heater efficiency and
overloads the ID fan. Care should be taken to maintain the seals at all potential
leak points. Comparing the oxygen concentration at the bridge wall (arch) to that
at the stack exit can provide a quantitative measure of leakage in the convection
section. Ideally the stack oxygen concentration should be no more than 0.5%
greater than the bridge wall concentration (make sure that both measurements
are on the same basis, i.e., wet or dry). It is recommended to control the heater
based on excess oxygen measured around bridge wall since the leakage is
minimum. Additional air ingressed in the convection section is not seen at the
burners. This will avoid low excess ( below stoichiometric) oxygen at the burners.
Heat transfer in the PTLE is a function of the amount of fouling that occurs
during the run cycle. Maximum heat transfer occurs at start-of-run (SOR) when
the radiant and TLE tubes have just been cleaned.
ORPIC SOM – SECTION 3.DOC Page 27 of 60
Lummus Petrochemicals
The expected SOR temperature at the PTLE outlet is about 360 - 370C for the
Ethane Heaters cracking ethane normally. When the Ethane Heater is cracking
C3+ (non-normal operation), the PTLE outlet is about 390 - 400C. The
expected SOR temperature at the PTLE outlet is about 350 - 360C for the
Flexible Heaters.
As the run progresses, fouling in the tubes occurs and reduces the heat transfer
and also increases pressure drop. It is very unlikely that the maximum primary
TLE outlet temperature is reached during normal operation. This temperature
will depend on the feedstock and cracking conditions.
The maximum PTLE outlet temperature limit for the Ethane Heaters is 454C
and for Flexible Heaters is 525C. This mechanical design limit must not be
exceeded because it is the basis for material selection of the PTLE and
downstream transfer line. Temperature indicators are provided at the outlet of
the PTLE’s with high temperature alarms. If the mechanical design temperature
is reached, the run should be terminated, and the heater and PTLE should be
decoked.
The heater PTLEs should be cleaned using the TLE online air-polishing step
after the radiant coil decoke is completed. If the air-polishing procedure fails to
return the SOR PTLE temperature to within 10°C of design, the PTLE should be
mechanically cleaned.
As the run cycle progresses, fouling inside the PTLE tubes occurs due to the
condensation high molecular weight components and this reduces the heat
transfer. The fouling for C3+ feed cracking may not be as severe as the
C5/OLNG case. Ethane and propane crackings also result in deposits of coke
on the hot PTLE inlet tubesheet, but much less inside the tubes. If not removed
by decoking or mechanical cleaning, these deposits on the tubesheet can result
in partially or fully blocked TLE tubes, resulting in decreased heat transfer and
increased pressure drop in the exchanger. The rate of fouling can vary
ORPIC SOM – SECTION 3.DOC Page 28 of 60
Lummus Petrochemicals
depending on the composition of the gas feed and heater operating conditions
over the cycle.
The PTLE vendor’s requirements for water quality should be strictly adhered to.
When decoking the heater, circulation on the steam/water side of the PTLE will
be maintained because the steam drum is operated at design pressure level.
During decoking, steam will continue to be generated at the SHP level and be
superheated in the convection coils, but to a lesser quantity than normal cracking
operation.
recommend regular (up to once per shift) blowdown to clear the deposition of
solids( water side) on inlet tubesheet. Usually the duration of PTLE blowdown is
very short, lasting less than 15 seconds.
Quench Fitting
For the Quench Fittings, quench oil from the bottom of the gasoline fractionator
is used to quench the cracked effluent before being routed to the gasoline
fractionator. This quench fitting uses a special arrangement of multiple full-cone
spray nozzles that cool the effluent uniformly within a short distance without
fouling the nozzle and without fouling the downstream transfer line.
Refer to Section 4.4.1 for details of the Quench Fitting, including design,
operation, turndown, temperature control and high temperature interlock
associated with this fitting.
3.2.10 Burners
The operator should refer to burner test flux profiles measured by the vendor.
These tests simulate the particular combination of hearth and wall burner
designs selected for the heaters.
The hearth burner tip design, burner position (orientation) and cleanliness have a
major impact on the heat flux profile in the radiant section.
The hearth burners consist of two stages of fuel release. The fuel is released
from primary tips and secondary tips, which are necessary to achieve low NOx
emissions. NOx formation is inhibited by producing a “cooler” flame, which for
staged burners is a result of entraining flue gas from the firebox and delaying
combustion of a certain amount of the fuel released. This “secondary“ fuel is
burned at a slightly higher elevation just above the corresponding primary burner
tips of the same burner, which cools the flame. As a consequence, a low NOX
staged burner profile will exhibit lower flux near the bottom of the heater
compared to higher elevations. For the burner design selected, hearth burner
flames result in lower heat flux near the bottom and top of the firebox and higher
flux in the middle.
Low NOx staged burners are sensitive to plugging and air supply and therefore
require particular attention and monitoring by the operator.
The small openings at the tip mean a greater tendency for fouling due to pipe
scale in the fuel gas piping or contamination of the fuel gas by heavier polymer
forming components. Fouled burners will be evident by visual inspection through
the heater peep doors and will cause poor flux profile and uneven and
incomplete combustion. Malfunctioning burners must be cleaned as soon as
possible. The burner tip is kept cool as long as a good flow of air and fuel is
maintained. A completely plugged floor burner tip will be badly damaged or
destroyed by the heat release from neighboring burners in a very short time.
ORPIC SOM – SECTION 3.DOC Page 31 of 60
Lummus Petrochemicals
Each hearth burner is equipped with a combination of primary and staged burner
tips. Selected staged burner tips are piped up to the secondary fuel header to
allow fuel to these burner tips to be shut during partial trips, high steam standby
and decoking operation. Typically at least one (actual number to be confirmed
with burner vendor) staged burner tip per burner is piped with the fuel supplied to
the primary burner tips, because the primary burner tip capacity is not large
enough to handle the firing duty required during partial trip, high steam standby
and decoking heater operation. Each hearth burner is provided with a manual
shutoff valve for the primary tips (plus one secondary tip, to be confirmed by
burner vendor), the secondary tips, and the pilot gas.
The wall burners help improve the heat flux of the upper portion of the firebox.
The wall burners are used in combination with the hearth burners to optimize the
radiant heat flux profile from floor to arch and thus insure good operation.
Burner Maintenance
Individual burners can be removed one at a time, cleaned and replaced without
shutting down the heater. A cleaned burner should be reinserted and secured to
the correct position and alignment. Always burner vendor instructions have to be
followed. Refer to Section 6 for burner lighting procedures.
Partial Trip
The heater design provides for a partial heater trip mode to low firing on High
Steam Standby. The partial trip capability minimizes the frequency of heater
shutdown incidents, thus preventing thermal shock to many critical heater
components (tubes, refractory, and supports). Hearth burner firing is reduced to
about 25-40% of design by tripping the staged fuel tips connected to the
secondary fuel gas header (refer to Section 3.2.3.4).
3.2.11 Draft
The cracking heaters are designed to operate at a slight negative draft of as little
as 2.5 mm of draft (minus 2.5 mm of water gauge pressure measured at the arch
location at the top of the radiant section just before the transition to the
convection section). Higher draft will increase air leakage and reduce heater
efficiency but this will not be significant in a well-sealed heater. Too low a draft
setting, however, can create positive pressure in the radiant section which is a
hazardous condition. Outward leakage of hot flue gas can damage the heater
casing, and can cause injury to personnel particularly when peep doors are
opened.
A pressure controller measures the firebox pressure at the arch (at the radiant-
to-convection section transition) and adjusts the induced draft fan speed to
maintain the draft setpoint.
The hearth burners are the raw gas type, meaning that combustion air is pulled
into the burner corresponding to the draft and air damper setting.
The wall burners self inspirate the primary air with the fuel gas. They are
designed so that air flow self-adjusts to changes in fuel flow and draft. The
primary air doors for all of the wall burners should be initially adjusted individually
ORPIC SOM – SECTION 3.DOC Page 33 of 60
Lummus Petrochemicals
with the secondary air doors closed. If insufficient air is available with the
primary air door(s) full open, the secondary air door(s) can be opened. The
adjustment of the air is done by observing the flame while adjusting the air doors
to give non-luminous flame with the minimum air to the burner at normal firing
conditions
Excess air is that amount of combustion air above the theoretical stoichiometric
quantity to ensure complete combustion of a given fuel. Excess air is typically
10% minimum for gas firing.
While it is often desirable to operate at the lowest excess air possible, excess air
significantly below 10% can lead to an unsafe condition. For lower than 10%
excess air operating target, more operator attention is required to keep
satisfactory individual burner performance. It is extremely important that all
burners receive adequate combustion air. If air to any single burner falls below
that required for complete combustion, the unburned fuel will find the necessary
oxygen for combustion at random points in the heater, possibly far from the
burner. This after-burning is a major cause of poor heat flux profiles, local hot
spots and high TMT’s. Though each burner is manufactured to tight tolerance, in
the heater setting identical performance can’t be expected. Therefore, to avoid
substoichiometric combustion in any burner, Lummus recommends 10%
minimum excess at the arch level.
The excess air is monitored by use of a flue gas oxygen analyzer. With a proper
draft control established at the arch, the flue gas should contain about 1.7 vol%
oxygen (wet basis) or 2.1 vol% oxygen (dry basis) corresponding to 10% excess
air when firing the (most) design fuel gas. When the analyzer is not located at
the arch level, suitable correction has to be applied for equivalent arch value.
Often more than one excess oxygen values are analyzed. The average value will
be used for control. The deviations from the average can be used to judge
burner performance in those corresponding locations.
Each hearth burner is provided with an air damper. Hearth burner air dampers
on each side of the heater are linked to a common jackshaft mechanism. Each
radiant cell of a heater has two jackshafts; one on each side running the length
of the radiant cell. Rotation of the jackshaft via a pneumatically-controlled
actuator by a manual HC (one for each jackshaft) from the operator console
simultaneously sets the opening of all connected hearth air dampers. Typically
the two jackshafts on both sides of a heater are set identically. The position of
the jackshaft is calibrated to the individual damper positions during heater
commissioning to compensate for damper-to-damper linkage differences, and to
verify the proper settings for a given heater capacity. The jackshaft system is
primarily used to automatically close the dampers upon partial trip to High Steam
Standby conditions, thus minimizing the combustion air and preventing
overheating of the convection section. The jackshaft system is also used to
manually reduce air flow to a preset position during decoking and High Steam
Standby, or to increase air flow for a high firing (rated capacity) condition. It is
not recommended, however, to automatically control excess air to the burners
using the jackshaft.
It is not possible to vary the position of an individual damper different from the
jackshaft setting. Each damper cannot be disconnected from the jackshaft.
Decoking refers to the process of removing the coke buildup via combustion by a
mixture of steam and air as it flows through the tubes (radiant coil and TLE).
The quality of the feedstock is also important. Feedstocks of all types sometimes
contain impurities that can impact coking rates. Coking rates can be increased
by impurities such as:
Chlorides
Fluorides
Hydrofluoric and other acids
Iron oxides
Potassium
Metals (e.g., vanadium)
Sodium
High boiling compounds (coke precursors)
All of these and potentially other compounds can accelerate coking substantially
if present in sufficient quantity. Sodium has been found to be the most significant
coking accelerator.
Cracking Conditions
Coking rate can be varied by changing cracking conditions. Higher coking rate is
caused by:
ORPIC SOM – SECTION 3.DOC Page 36 of 60
Lummus Petrochemicals
Increase in severity/conversion
Increase in coil outlet pressure
Decrease in S/HC ratio
Increase in feed rate
Burner Performance
Burner performance is critical to minimize coking rate and maximizing run length.
Burners must be installed correctly, maintained properly, and operated
consistently and, most times, uniformly. They must be cleaned properly so that
all tips are working properly.
Depending on the fuel type used and impurities contained in the fuel, burners
can foul over time. Fouling results in plugged fuel ports and distorted flame
patterns. The distortion of the flame pattern can result in poor flux profiles and
hot spots on the radiant tubes. Hot spots will accelerate coking and potentially
damage tubes.
Stability of operation
Changes in operating conditions should be minimized. Changes in feed rate,
severity, and other conditions tend to accelerate coking resulting in shorter run
lengths. The difference in run length between heaters operated at constant feed
rate compared to those where feed rates are changed every few days is often
dramatic. Rapid changes have significantly worse impacts on run length.
contract. This phenomenon is known as spalling. Spalled coke can partially block
the radiant tubes or TLE tubes, causing an increase in pressure drop. A rapid
increase in pressure drop is, in fact, an excellent indication that spalling has
occurred. Spalling is more significant in ethane cracking, especially at high
conversion, because the coke is harder. OLNG coke is softer and tends to break
up and pass through the radiant coil and TLE. For this and other reasons cited
above, rapid changes in operation during a run should be avoided.
3.2.14 Decoking
Periodically, the heater must be taken out of service to remove coke from the
radiant tubes and polymerization/condensation products from the TLE’s.
Decoking is performed after the heater is lined out in the High Steam Standby
mode of operation by withdrawing the hydrocarbon feed and isolating the heater
from the downstream plant transfer line. Decoking air, along with the decoking
steam, is fed into the heater to a controlled outlet temperature (approximately
850-870°C) to "burn off" the coke.
The decoking effluent is sent through the TLE's and to the firebox. Any coke
particles in the effluent will be burned in the firebox.
The recommended flow rates of steam and air for decoking of each heater type
are described in the decoking procedure in Section 8.
The heater run length should be terminated and the heater decoked if any of the
following conditions occur:
The average of the maximum radiant tube metal temperature (TMT) for
the outlet tubes exceeds 1115 °C, corrected for reflectivity using the chart
provided in this supervisory operating manual or using a pyrometer
designed to measured emissivity and make corrections to the measured
TMT.
The outlet temperature of any heater TLE exceeds 454°C for Ethane
Heaters and 525°C for the Flexible Heaters.
When the venturi pressure drop decreases to less than 10% of the venturi
upstream pressure (in absolute units).
When a heater is shutdown or tripped under emergencies after 5 days of
operation (cracking).
a. A rapid pressure drop increase occurs across the TLE that does
not return to normal with TLE polishing. This is usually due to coke
spalling which blocks some tubes;
b. When a TLE outlet temperature does not return to within 10 to
20°C of the theoretical clean SOR outlet temperature after heater
decoking;
c. When a TLE cannot be successfully cleaned by the decoking
procedure, i.e., the TLE pressure drop at feed-in is more than 0.03
to 0.04 bar above its theoretical SOR pressure drop.
Basics
The cracking of feed to yield ethylene and byproducts results from the
summation of numerous endothermic reactions. Hundreds of free radical and
molecular reactions occur even when cracking relatively simple gas feeds.
A free radical reaction involves one or more neutral species that has an unpaired
electron. An example free radical reaction is:
H C2 H 4 C2 H 5
where hydrogen radical combines with ethylene molecule to form ethyl radical.
ORPIC SOM – SECTION 3.DOC Page 41 of 60
Lummus Petrochemicals
C2 H 6 C2 H 4 H 2
C3 H 8 C3 H 6 H 2
In the radiant coil thousands of reactions take place. The overall reaction is
endothermic (consuming heat). For illustration purpose only some simplified
reactions are shown.
Conversion
Some typical reactions involved in ethane cracking are given below ( as an
example):
C 2 H 6 2 CH 3
CH 3 C 2 H 6 CH 4 C 2 H 5
H C 2 H 6 H 2 C 2 H 5
r1 k1 C2 H 6 k1 4.0 x1016 exp
87,500
RT
16,500
r2 k 2 C2 H 6 CH 3 k 2 3.8 x1011 exp
RT
9,700
r3 k3 C2 H 6 H k3 1.0 x1011 exp
RT
Where
The table below shows the rates for these three reactions at three different
temperatures:
As the temperature increases, the reaction rates increase indicating that ethane
conversion increases with temperature. In addition, the reaction rate for k1
ORPIC SOM – SECTION 3.DOC Page 43 of 60
Lummus Petrochemicals
Selectivity
Lower selectivity results in higher yields of less desirable products such as:
Methane
Fuel Oil
Aromatics
The changes in yield noted above result from the competition between primary
and secondary reactions. Primary reactions form ethylene and other desirable
products. Secondary reactions destroy these products and form fuels and
aromatics. The reactions below are typical primary and secondary reactions that
occur in ethane cracking:
(1) C2 H 5 C2 H 4 H
(2) C2 H 4 CH 3 C3 H 7
r1 k1 C2 H 5
r2 k C H CH
2 2 4
3
Considering just these two reactions, the following equation gives the net
formation of ethylene:
dFC 2 H 4
dv
r1 r2 k1 C2 H 5 k2 C2 H 4 CH 3
In the gas phase in a cracking heater, the concentration of a component is given
by:
Fx
Concentration pt
Ft RT
Where :
F moles of component x
Ft total moles FHC FDS
FHC moles of hydrocarbon
FDS moles of dilution steam
R Gas constant
T Temperature
Pt Total pressure
Therefore for a differential reactor volume (dv):
It can be seen from this equation that ethylene production will decrease as
pressure increases. Therefore increases in coil outlet pressure (COP) as the
result of increased TLE fouling and or charge gas compressor suction pressure
increases will reduce selectivity.
Any decrease in dilution steam ratio will favor increases in secondary reactions
and result in poorer selectivity.
Increases in coil pressure drop as the coil cokes will also decrease selectivity.
Coils designed with larger tubes and lower pressure drop are therefore favored.
The rate constants of the two equations analyzed above are given by:
40,000
k1 3.2 x1013 exp
RT
7,900
k 2 2.0 x108 exp
RT
Using these equations, we can calculate the rates of the two reactions at various
temperatures.
The above reactions are used to simply illustrate the effect of pressure,
temperature (and/ or residence time) on conversion (a measure of severity) and
selectivity for ethane cracking. The same concept applies to all feeds, but the
mechanism is more complex than that discussed here.
It is important to make sure the different heater control loops are properly tuned
and to note the differences of tuning requirements between the different
operating modes such as normal run operation and High Steam Standby/Decoke
conditions.
The total throughput controller manipulates the associated individual feed flow
controller’s setpoints to regulate the total feed flow to the heater. In normal
operation, the total feed throughput controller works in conjunction with the
individual coil temperature balancing differential COT controllers to manipulate
the setpoints of the corresponding coil individual feed controllers. This scheme
allows for total feed throughput control as well as individual coil flow trimming so
that all coils operate with the same COT.
The (HC) feed streams to each heater have separate gas and liquid flow control
and measurements. The individual liquid and gas feed flow measurements are
density compensated based on the measured density of the feed. The feed total
throughput is calculated by summing together the setpoints of the individual feed
controller. The feed selector switch and associated control logic are used to
select the feed and associated flow control to each heater. During split cracking
mode for the Flexible Heaters, Coil 3 feed flow is directly controlled by Coil 3
COT. Coils 1 and 2 will have OLNG feed in Cell “A”. Coil 3 in Cell A and all 3
coils (4, 5 & 6) of Cell “B” will be on C3+ feed. Since the firing in Cell “A” is
dictated by OLNG, C3+ flow rate will be adjusted in Coil 3 to keep the same COT
as coils 4 to 6. During other operation modes, the Coil 3 flow is controlled by the
Cell “A” throughput controller. Therefore the average flow rate in Coil 4 to 6 in
Cell B may be different from Coil 3 flow rate for C3+ feed. COT for the OLNG
feed should be established initially and periodically based on offline sampling
analysis from the TLE effluent of the two coils to meet the required cracking
severity (P/E ratio). The operating COT should be slightly lower (~5 C) than the
true COT measured by effluent sampling to allow for potential fluctuation of the
feedstock quality to prevent overcrack.
Dilution steam is mixed with the preheated feed using ratio control. Each coil is
provided with a ratio block that sets the setpoint of the dilution steam flow
controller equal to a ratio to the setpoint of each operating individual coil feed
flow controller. A manual loader (HIC) and high signal selector is furnished to
prevent the ratio controller from reducing the dilution flow setpoint to less than a
preset minimum during heater standby operation and heater trips. Automatic
logic is present in the DCS to determine operating feed (gas or liquid) based on
the position of the heater feed selector switch position.
The COT controller manipulates the heater hearth burner firing rate to regulate
the heater average coil outlet temperature. The process variable for the COT
controller is the average of "good" individual COT measurements ("bad"
thermocouple measurements are ignored).
For the 4 radiant coil groups per coil, there are 4 outlets. Each pair of outlets
from the 4 radiant coil groups is combined with wye fittings into 2 outlets and 2
COT measurements. The 2 COT measurements are averaged representing the
averaged COT for each coil. Each of the COT measurement is provided with
duplex thermocouples with upscale burnout alarms. A hand switch is furnished
in the DCS that allows the operator to select which of the two temperature
measurements from the duplex thermocouple will be utilized in the COT control
strategy. Although the system is configured to continue to operate if the COT
reading of one or more coils is bad, it is recommended to immediately determine
the cause of the failed reading(s), or replace the thermocouple(s). The individual
coil’s COT is used in the coil balancing strategy before being averaged together
with other coil temperatures in a radiant cell to calculate the overall average coil
outlet temperature for the corresponding radiant cell. The two radiant cells of a
heater have separate COT balancing control for each cell.
The COT/firing controller tuning constant which is needed for stable control will
be different during decoking and HSS compared to normal cracking operation,
due to differences in the heat absorbed of hydrocarbon cracking vs. HSS/decoke
operations. Controller tuning constants may need to be changed when switching
to different heater operating modes.
The burners are designed to burn design process gas or startup/backup fuels
using ambient air for combustion. Process upsets or the sudden switch to/from
backup fuel can result in large swings in fuel gas composition. Fuel gas heating
value compensation is furnished with heater firing controls to minimize COT and
combustion excess air fluctuations during fuel composition swings. Rather than
ORPIC SOM – SECTION 3.DOC Page 50 of 60
Lummus Petrochemicals
regulating heater firing based on fuel gas flow rate, the controls are designed to
regulate heater firing based on measured heat energy released from the burners.
The objective of the heater firing controls is to maintain the desired average COT
corresponding to the desired process performance (i.e., conversion or severity).
Each heater has two radiant cells with independent firing control for the
corresponding cell. Therefore, the description below for a “heater” is also
applicable for firing to one radiant cell.
All heaters are equipped with gas fired hearth and wall burners.
The hearth burner firing rate is varied to control the COT for each radiant cell.
The flow of fuel to the hearth burners is controlled by the heat rate controller QC
which receives set points from the average coil outlet temperature controller (TIC)
of each radiant cell. The wall burner firing rates are base-loaded, thus there is an
additional feedback signal to the heat rate controller which compensates for the
partial heat input to the wall burners. Combined with compensation for fuel gas
composition via a continuous calorimeter measurement, the result is that a
constant firing rate (heat energy release from the burners) to the heater radiant
cell is maintained.
The actual total heat energy release to the heaters is calculated by multiplying
the fuel gas heating value by the fuel gas flow which has been corrected for
temperature and pressure fluctuations. The fuel gas heating value is measured
by the Wobbe meter, located in the main gas header upstream of all the heaters.
The Wobbe index may be entered manually via the controller (HS) should the
Wobbe meter be out of service. If the Wobbe index is input by the operator, the
associated auto/manual station must be placed in manual mode.
Pressure controllers have been furnished for hearth burner firing controls for use
during heater start-up and decoke, when the fuel flow rates are less than the
minimum turn down limitations of fuel flow meter. Additionally, these pressure
ORPIC SOM – SECTION 3.DOC Page 51 of 60
Lummus Petrochemicals
Specifically, the burner fuel gas control valve is controlled by the resulting signal
from its respective QC via a high signal selector (QY) which selects the higher of
the two signals from the QC and the burner PC. This insures that the minimum
stable fuel gas pressure to the burners is always maintained.
The heaters should always be operated with the Wobbe meter as an active part
of the control system. During times when it is necessary for the operator to take
direct control of the heater firing, this should be done by breaking the TIC to QIC
cascade and putting a set point into the QIC. Should the fuel composition
change, the control system will attempt to maintain the heat input specified by
the operator.
The operator should be fully trained in the principles and specifics of this firing
control system. The operator should be aware of the circumstances that may
lead up to and result in a shift to backup fuel, as well as the consequence of
shifting to back up fuel and the actions that may be required. For large molecular
weight changes, the operator may be required to assist the control system even
if the Wobbe Meter is in service.
Cautionary Note
At times, the operator may feel it would be easier to maintain fuel flow to the
heaters on direct fuel gas pressure control, and bypass the heat input (Wobbe
index) compensation control.
Extreme care must be exercised when operating heater controls without the
heating value compensation factor in service. A sudden increase in the fuel
heating value, and/or molecular weight, as could be experienced during a
process upset could cause heater overfiring and/or substoichiometric combustion
resulting in damage to the heater. For the same reason, the hearth burners
should never be operated under pressure (PC) control; they should always be
operated on heat rate (QC) control.
The secondary fuel header for each heater is furnished with a control valve that
may be manually shut (HC) by the operator during very low firing operation (High
Steam Standby and decoking) to allow all hearth burners to remain
commissioned on primary tips only, without risk of tripping due to low burner
pressure. During a partial trip, this secondary fuel header valve is automatically
shut.
There is an interlock to shut the secondary fuel when the arch temperature is
below 700 °C. The wall burners will be shut when there is insufficient hearth wall
burner fuel pressure.
Under such circumstances the tolerance can be higher than 1oC in that cracking
cycle. Burner malfunction and severe coking in one coil are probable causes for
large deviations. The operator should try correct these problems as soon as
possible.
A draft pressure controller, located at the heater arch, controls heater draft by
adjusting the ID fan speed.
Combustion air to the burners is regulated differently for the hearth and wall
burners. The combination of draft control and manipulation of these airflow
openings provide the means for manually controlling excess air.
For the hearth burners, the air dampers are connected together and manipulated
by pneumatically actuated jackshafts (refer to Section 3.2.2.12). The mechanical
linkage at each damper is calibrated at heater commissioning to permit virtually
identical air flow to all burners connected to the same jackshaft. Individual
damper control is not possible because the linkage cannot be disconnected from
the jackshaft once installed, and there would be no means of holding the
disconnected damper in a fixed position.
Each wall burner is provided with a rotating shaft that changes the airflow
opening when dialed to a specific position (called primary air). The wall burner
flame must be observed from the peep door above to insure the flame pattern is
acceptable. Typically a low to middle setting of the airflow opening will provide
sufficient excess combustion air, with all the burners set at approximately the
same opening. When more than one row of wall burners is installed, these
opening will vary from row to row. Adjacent wall burners in the same row have
the same level of opening. Since they are self- inspirating the wall burners are
not sensitive to draft (primary air). Wall burners are also provided with secondary
ORPIC SOM – SECTION 3.DOC Page 54 of 60
Lummus Petrochemicals
air door. These doors will be used when primary air is alone insufficient for good
combustion. Secondary air is sensitive to draft. When the burners are selected,
usually secondary doors will be closed for design conditions. Recommendations
from the burner vendor have to be followed for the recommended settings. They
affect the heat flux pattern and the NOx. During decoking most wall burners will
be shut off except the selected few. The lighted wall burner pattern is usually
obtained with experience gained in decoking.
BFW flow to the Super High Pressure (SHP) Steam Drum is controlled by a
three- element control strategy. The setpoint of the BFW flow controller is
manipulated based on summing the measured temperature and pressure
compensated flow of steam production and the (density compensated) output of
the drum level controller.
The strategy is designed to immediately adjust the setpoint of the BFW controller
proportionally to any variation in measured steam production. Once the strategy
is properly tuned, a one unit change in measured steam flow should cause the
BFW setpoint to be adjusted to cause approximately (minus desuperheater BFW
fraction) an equal change in BFW flow rate. The level controller should then be
required to make minor adjustments to the BFW valve's position to insure that
the steam level is maintained at a set value.
The heater is equipped with a BFW preheat coil. The BFW control valve is
furnished with a minimum stop to insure there is flow in the preheat coil at all
times.
the event the drum level exceeds the controller's setpoint. The high level
controller may be required during upset conditions and during startup when BFW
demand is less than the minimum stop position of the BFW control valve.
Refer to the primary TLE vendor operating manual for heat up rate and other
related information.
Super high pressure steam generated by the primary TLE's is superheated in the
convection section of each heater. Each heater has one desuperheater installed
between the Upper SSH and Lower SSH coils to control the steam superheater
outlet temperature. The flow of phosphate-free BFW to the desuperheater is
adjusted to control the superheater outlet temperature.
A high temperature interlock will shutdown the heater in the event the steam
superheater outlet temperature approaches the piping design temperature to
avoid damage to the convection section coil and downstream piping.
The heaters can operate down to about 70% of design hydrocarbon rate. This is
considered minimum turndown (TD) for feedrate at design cracking severity or
conversion. Dilution steam to the heater may be increased to maintain choked
venturi conditions and to keep coking rates low. Burner firing is reduced
uniformly with all burners operating.
The heater can operate on High Steam Standby (dilution steam only) and
decoking (steam plus air mixture), which are considered minimum turndown
conditions for firing. The burner fuel pressure should be closely monitored to
stay above the minimum fuel pressure trip setting for extreme turndown
conditions.
The heater flowrate may be reduced for long-term operation to the minimum
turndown S/HC conditions shown in Table 3.4.1, based on the limitation of
maintaining choked flow through the critical flow venturis in the radiant section
inlet pass tubes. These minimum S/HC are estimates and should be increased
as needed to keep the venturi choked. The venturi pressure ratio (PDI/PI)
should be closely monitored. Refer to previous section on critical flow venturis for
additional information on the venturis. The limitation for choked flow through the
venturis assumes that the coil outlet pressure (COP) upstream of the transfer
line exchanger at SOR conditions does not exceed 0.54 BarG. For a higher
operating SOR COP, the turndown requirements for dilution steam may change
if experience indicates that run length tends to be limited by unchoking venturis
instead of radiant TMT.
Hydrocarbon (HC) rates shown are per heater (Based on DESIGN CASE)
At SOR conditions (clean coil, clean TLE)
FLEXIBLE HEATERS (6 COILS/HEATER)
Notes:
(a) Minimum S/HC required to maintain choked flow through venturi.
(b) SC = split crack operation.
Proper heater operation means the ability to control conversion, maintain high
heater efficiency, meet environmental emissions standards, extend heater run
length, avoid upsets and prolong the mechanical life of the heater components.
A theoretically balanced and uniform heat flux condition would be one where the
total amount of radiant heat absorbed is equally divided to each coil and equally
along the circumference and length of each tube.
As low temperature difference as possible between the top and bottom of the
outlet tube should be maintained. A poor heat flux distribution will be observed
with uneven TMT profiles vertically on the tube(s).
CB&I ORPIC
Document Title: Material and Heat Balance - NGTL 1100, RDG 1200, SCU
2000-2600 and SLC4HY 2800
Page 1 of 3
"THIS DOCUMENT IS THE PROPERTY OF CHICAGO BRIDGE & IRON COMPANY (CB&I). IT MAY CONTAIN INFORMATION
DESCRIBING TECHNOLOGY OWNED BY CB&I AND DEEMED TO BE COMMERCIALLY SENSITIVE. IT IS TO BE USED ONLY IN
CONNECTION WITH WORK PERFORMED BY CB&I. REPRODUCTION IN WHOLE OR IN PART FOR ANY PURPOSE OTHER THAN
WORK PERFORMED BY CB&I IS FORBIDDEN EXCEPT BY EXPRESS WRITTEN PERMISSION OF CB&I. IT IS TO BE SAFEGUARDED
AGAINST BOTH DELIBERATE AND INADVERTENT DISCLOSURE TO ANY THIRD PARTY."
Liwa Plastics Project
Page 2 of 3
Liwa Plastics Project
SUMMARY
Refer Licensor’s Heat and Material Balance (PDP Revision1) Section 3 for NGLT 1100, RDG 1200, SCU 2000-
2600 and SLC4HY 2800’s Heat and Material Balance for LIWA Plastics Project. Refer to Material and Heat
Balance – ARU-1100 (doc. no S-S110-5223-101) for Amine Regeneration Unit.
Cases are defined as below.
Case 2: Refinery Dry Gas and Refinery LPG not available, the NGL C2+ is increased 10% and increase LPG to
make minimum 75,000kg/h ethylene and same propylene as Case 1.
Detailed Material Balances are provided for the following design cases:
Case 2: Refinery Dry Gas and Refinery LPG not available, the NGL C2+ is increased 10% and increase LPG to
make minimum 75,000kg/h ethylene and same propylene as Case 1.
SHU End of Run: 1st Stage SHU, 2nd Stage SHU, 3rd Stage SHU
QO and H1:
QO case provided is Case 1 operation with the TLEs operating at average run temperatures and 1 secondary TLE
bypassed. H1 case provided is Case 1 operation with 1 heater on HHS.
It is anticipated that the CO2 content in NGL feed will increase over time. To compensate, the DGA concentration in
the lean amine sent to the NGL and RDG Amine/Water Wash Columns can be increased from 30% to 45 wt%.
Page 3 of 3
Liwa Plastics Project
CB&I ORPIC
"THIS DOCUMENT IS THE PROPERTY OF CHICAGO BRIDGE & IRON COMPANY (CBI). IT MAY CONTAIN PROPRIETARY
INFORMATION (CBI BACKGROUND & FOREGROUND INFORMATION) OWNED BY CBI AND DEEMED TO BE COMMERCIALLY
SENSITIVE. IT IS TO BE USED ONLY IN CONNECTION WITH WORK PERFORMED BY CBI. REPRODUCTION IN WHOLE OR IN
PART FOR ANY PURPOSE OTHER THAN WORK PERFORMED BY CBI IS FORBIDDEN EXCEPT BY EXPRESS WRITTEN
PERMISSION OF CBI. IT IS TO BE SAFEGUARDED AGAINST BOTH DELIBERATE AND INADVERTENT DISCLOSURE TO ANY
THIRD PARTY."
Page 1 of 4
Liwa Plastics Project
Heat and Material Balance
ARU
Notes:
1) Material Balance Case I: 30 wt% DGA
- 8.6 wt.% CO2, 40 ppmwt H2S in NGL feed + 1.95 wt.% CO2, 1100 ppmwt H2S in RDG feed
5) Stream flow rate and composition to be confirmed and finalised based on Reclaimer Package (ME-11053) Vendor information by
EPC contractor.
Holds:
Stream Number 1162 1163 1171 1172 1173 1174 1175 1176 1177 1178 1179 1180 1181 1182 1183 1184 1185 1151 1187 20651188 1189 1190 1191
Note 4 Note 5 Note 5 Note 3
Stream Name R.Amine Vent Gas R.Amine R.Amine R.Amine Ov Vapor Ov Vapor Acid Gas Acid Gas Reflux Bottom Vap Ret L.Amine L.Amine L.Amine L.Amine L.Amine L.Amine LLS H2O Mkup CO2 L.Amine L.Amine Waste
From C-11002 V-11054 V-11054 E-11052 FCV C-11051 E-11054 V-11052 PCV V-11052 C-11051 E-11051 C-11051 E-11052 E-11056 E-11053 E-11053 Filters DS-11051 E-20014 ME-11052 E-11053 ME-11053 ME-11053
To V-11054 C-21003 E-11052 FCV C-11051 E-11054 V-11052 PCV ME-11052 C-11051 E-11051 C-11051 E-11052 E-11056 E-11053 Filters Filters C-11002 E-11051 V-11052 To ATM ME-11053 P-11051 WWT-Ref
Phase Mixed Vapor Liquid Mixed Mixed Vapor Mixed Vapor Vapor Liquid Liquid Vapor Liquid Liquid Liquid Liquid Liquid Liquid Vapor Liquid Vapor Liquid Liquid Liquid
Component (wt%)
Water 66.63 1.88 66.65 66.65 66.65 20.39 20.39 3.25 3.25 99.84 71.83 94.18 69.44 69.44 69.44 69.44 69.44 69.44 100.00 100.00 0.00 69.44 69.44 69.44
Carbon Dioxide 4.46 0.56 4.46 4.46 4.46 78.85 78.85 95.83 95.83 0.16 1.01 5.23 0.56 0.56 0.56 0.56 0.56 0.56 0.00 0.00 100.00 0.56 0.56 0.56
Hydrogen Sulfide 0.02 0.01 0.02 0.02 0.02 0.32 0.32 0.38 0.38 0.00 0.01 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Methane 0.00 1.58 0.00 0.00 0.00 0.01 0.01 0.01 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Ethylene 0.00 0.99 0.00 0.00 0.00 0.01 0.01 0.01 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Ethane 0.06 91.49 0.02 0.02 0.02 0.41 0.41 0.50 0.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Propane 0.00 2.90 0.00 0.00 0.00 0.01 0.01 0.01 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
DGA 28.84 0.00 28.85 28.85 28.85 0.00 0.00 0.00 0.00 0.00 27.16 0.55 30.00 30.00 30.00 30.00 30.00 30.00 0.00 0.00 0.00 30.00 30.00 30.00
Total Units
Mass Flow kg/h 304447 116 304331 304331 304331 15126 15126 12440 12440 3496 323967 31291 292676 292676 292676 292676 29268 292676 32566 810 11921 14634 14634
Molar Flow kg mol/h 12411 3.9 12407 12407 12407 446 446 297 297 194 13828 1675 12153 12153 12153 12153 1215 12153 1809 45 607.2 607.2
Molecular Weight kg/kg mol 24.5 29.5 24.5 24.5 24.5 33.9 33.9 41.9 41.9 18.0 23.4 18.7 24.1 24.1 24.1 24.1 24.1 24.1 18.0 18.0 24.1 24.1
Temperature °C 63 63 63 99 99 98 58 57 57 57 131 132 132 97 59 42 42 42 148 45 42 42
Pressure bar (g) 8 6 6 5.25 1.7 1.5 1.4 1.3 1.2 1.5 1.7 1.7 1.7 29.45 28.75 28.05 28.05 25 3.5 1.5 28.05 3.5
Liquid Weight Fraction % 99.97 0 100 99.99 99.95 0 17.71 0 0 100 100 0 100 100 100 100 100.0 100 0 100 100 100
Specific Enthalpy kcal/kg -2887.6 -698.3 -2888.4 -2856.0 -2856.0 -2322.4 -2432.8 -2148.2 -2148.2 -3754.8 -2913.2 -3090.9 -2837.9 -2870.5 -2905.3 -2920.4 -2920.4 -2920.4 -3153.7 -3769.3 -2920.4 -2920.4
Critical Temperature °C 367.2 38.9 367.3 367.3 367.3 163.1 163.1 57.3 57.3 374.0 373.9 366.6 374.9 374.9 374.9 374.9 374.9 374.9 374.2 374.2 374.9 374.9
Critical Pressure bar (g) 165.3 49.9 165.3 165.3 165.3 116.2 116.2 80.4 80.4 220.0 172.2 214.3 167.7 167.7 167.7 167.7 167.7 167.7 220.167 220.167 167.7 167.7
Stream Enthalpy MMkcal/h -879.11 -0.08 -879.03 -869.16 -869.16 -35.13 -36.80 -26.72 -26.72 -13.13 -943.78 -96.72 -830.58 -840.12 -850.30 -854.72 -85.47 -854.72 -102.70 -3.05 -42.74 -42.74
Vapor
Mass Flow kg/h 96 116 37 140 15126 12447 12440 12440 31291 32566 11921
Actual Volumetric Flow m3/h 9.7 15.1 6.1 53.5 5428.7 3361.3 3490.9 3649.0 20420.6 13647.0
Molecular Weight kg/kg mol 29.5 29.5 29.7 29.5 33.9 41.9 41.9 41.9 18.7 18.0
Density kg/m3 9.99 7.67 6.15 2.61 2.79 3.70 3.56 3.41 1.53 2.39
Viscosity cP 0.011 0.011 0.013 0.014 0.017 0.016 0.016 0.016 0.014 0.014
Liquid
Mass Flow kg/h 304351 304331 304294 304192 2679.18 3496.43 323967 292676 292676 292676 292676 29267.6 292676 810 14634 14634
Volumetric Flow m3/h 297.3 297.3 305.3 305.2 2.7 3.6 340.1 307.8 297.4 289.1 286.3 28.6 286.4 0.8 14.3 14.3
Molecular Weight kg/kg mol 24.5 24.5 24.5 24.5 18.0 18.0 23.4 24.1 24.1 24.1 24.1 24.1 24.1 18.0 24.1 24.1
Density kg/m3 1023.82 1023.81 996.66 996.67 984.01 984.57 952.46 950.87 984.21 1012.28 1022.17 1022.17 1022.08 989.49 1022.17 1022.17
Viscosity cP 0.97 0.97 0.53 0.54 0.49 0.50 0.34 0.36 0.56 1.07 1.56 1.56 1.56 0.61 1.56 1.56
Surface Tension mN/m 60.77 60.77 54.69 54.71 66.28 66.51 50.24 49.87 56.31 62.79 65.53 65.53 65.52 68.86 65.53 65.53
Thermal Conducitivity kcal/(h.m.°C) 0.382 0.382 0.386 0.387 0.554 0.553 0.418 0.406 0.408 0.402 0.397 0.397 0.397 0.543 0.397 0.397
Stream Number 1162 1163 1171 1172 1173 1174 1175 1176 1177 1178 1179 1180 1181 1182 1183 1184 1185 1151 1187 20651188 1189 1190 1191
Note 4 Note 5 Note 5 Note 3
Stream Name R.Amine Vent Gas R.Amine R.Amine R.Amine Ov Vapor Ov Vapor Acid Gas Acid Gas Reflux Bottom Vap Ret L.Amine L.Amine L.Amine L.Amine L.Amine L.Amine LLS H2O Mkup CO2 L.Amine L.Amine Waste
From C-11002 V-11054 V-11054 E-11052 FCV C-11051 E-11054 V-11052 PCV V-11052 C-11051 E-11051 C-11051 E-11052 E-11056 E-11053 E-11053 Filters DS-11051 E-20014 ME-11052 E-11053 ME-11053 ME-11053
To V-11054 C-21003 E-11052 FCV C-11051 E-11054 V-11052 PCV ME-11052 C-11051 E-11051 C-11051 E-11052 E-11056 E-11053 Filters Filters C-11002 E-11051 V-11052 To ATM ME-11053 P-11051 WWT-Ref
Phase Mixed Vapor Liquid Mixed Mixed Vapor Mixed Vapor Vapor Liquid Liquid Vapor Liquid Liquid Liquid Liquid Liquid Liquid Vapor Liquid Vapor Liquid Liquid Liquid
Component (wt%)
Water 50.79 3.68 50.81 50.81 50.81 18.83 18.83 3.26 3.26 99.84 58.87 93.49 54.24 54.24 54.24 54.24 54.24 54.24 100.00 100.00 0.00 54.24 54.24 54.24
Carbon Dioxide 6.91 3.90 6.91 6.91 6.91 80.69 80.69 96.17 96.17 0.16 1.30 5.40 0.75 0.75 0.75 0.75 0.75 0.75 0.00 0.00 100.00 0.75 0.75 0.75
Hydrogen Sulfide 0.01 0.02 0.01 0.01 0.01 0.18 0.18 0.22 0.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Methane 0.00 1.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Ethylene 0.00 0.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Ethane 0.06 87.18 0.02 0.02 0.02 0.28 0.28 0.33 0.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Propane 0.00 3.34 0.00 0.00 0.00 0.01 0.01 0.02 0.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
DGA 42.22 0.00 42.24 42.24 42.24 0.00 0.00 0.00 0.00 0.00 39.83 1.10 45.01 45.01 45.01 45.01 45.01 45.01 0.00 0.00 0.00 45.01 45.01 45.01
Total Units
Mass Flow kg/h 384000 181 383819 383819 383819 29524 29524 24763 24763 5966 408398 48170 360227 360227 360227 360227 36023 360227 49856 1205 23814 18011 18011
Molar Flow kg mol/h 12981 6.1 12975 12975 12975 854 854 590 590 331 15014 2564 12450 12450 12450 12450 1245 12450 2767 67 623.2 623.2
Molecular Weight kg/kg mol 29.6 29.7 29.6 29.6 29.6 34.6 34.6 41.9 41.9 18.0 27.2 18.8 28.9 28.9 28.9 28.9 28.9 28.9 18.0 18.0 28.9 28.9
Temperature °C 80 80 80 99 99 97 58 57 57 57 132 135 135 116 59 42 42 42 148 45 42 42
Pressure bar (g) 8 6 6 5.25 1.7 1.5 1.4 1.3 1.2 1.5 1.7 1.7 1.7 29.45 28.75 28.05 28.05 25 3.5 1.5 28.05 3.5
Liquid Weight Fraction % 99.96 0 100 99.99 99.94 0 16.10 0 0 100 100 0 100 100 100 100 100 100 0 100 100 100
Specific Enthalpy kcal/kg -2469.0 -789.9 -2469.8 -2453.9 -2453.9 -2311.4 -2412.0 -2154.6 -2154.6 -3754.7 -2556.4 -3075.9 -2416.9 -2432.7 -2481.5 -2495.5 -2495.5 -2495.5 -3153.7 -3769.3 -2495.5 -2495.5
Critical Temperature °C 361.1 51.6 361.2 361.2 361.2 155.1 155.1 57.3 57.3 374.0 374.1 366.4 375.7 375.7 375.7 375.7 375.7 375.7 374.2 374.2 375.7 375.7
Critical Pressure bar (g) 138.8 52.7 138.8 138.8 138.8 113.3 113.3 80.5 80.5 220.0 149.8 213.2 141.5 141.5 141.5 141.5 141.5 141.5 220.2 220.2 141.5 141.5
Stream Enthalpy MMkcal/h -948.10 -0.14 -947.96 -941.87 -941.87 -68.24 -71.21 -53.35 -53.35 -22.40 -1044.04 -148.17 -870.64 -876.34 -893.91 -898.96 -89.90 -898.96 -157.23 -4.54 44.95 44.95
Vapor
Mass Flow kg/h 151 181 42 230 29524 24771 24763 24763 48170 49856 23814
Actual Volumetric Flow m3/h 15.8 29.7 6.6 83.7 10356 6680 6943 7258 31426 20893
Molecular Weight kg/kg mol 29.8 29.7 30.6 31.1 34.6 41.9 41.9 41.9 18.8 18
Density kg/m3 9.51 7.31 6.32 2.75 2.85 3.71 3.57 3.41 1.53 2.39
Viscosity cP 0.011 0.012 0.013 0.015 0.017 0.017 0.016 0.016 0.014 0.014
Liquid
Mass Flow kg/h 383849 383819 383777 383589 4752 5966 408398 360227 360227 360227 360227 36023 360227 1205 18011 18011
Volumetric Flow m3/h 367.8 367.8 373.2 373.0 4.8 6.1 425.9 376.8 369.0 351.3 347.5 34.8 347.5 1.2 17.4 17.4
Molecular Weight kg/kg mol 29.6 29.6 29.6 29.6 18.0 18.0 27.2 28.9 28.9 28.9 28.9 28.9 28.9 18.0 28.9 28.9
Density kg/m3 1043.64 1043.64 1028.27 1028.29 984.02 984.52 958.82 955.92 976.19 1025.38 1036.60 1036.60 1036.49 989.49 1036.60 1036.60
Viscosity cP 1.21 1.21 0.86 0.87 0.49 0.50 0.45 0.50 0.64 1.81 2.79 2.79 2.79 0.61 2.79 2.79
Surface Tension mN/m 54.69 54.69 51.71 51.74 66.28 66.49 48.51 47.77 51.11 60.36 62.81 62.81 62.80 68.86 62.81 62.81
Thermal Conducitivity kcal/(h.m.°C) 0.363 0.312 0.312 0.312 0.553 0.553 0.352 0.331 0.335 0.337 0.336 0.336 0.336 0.542 0.336 0.336
CB&I ORPIC
"THIS DOCUMENT IS THE PROPERTY OF CHICAGO BRIDGE & IRON COMPANY (CBI). IT MAY CONTAIN PROPRIETARY INFORMATION
(CBI BACKGROUND & FOREGROUND INFORMATION) OWNED BY CBI AND DEEMED TO BE COMMERCIALLY SENSITIVE. IT IS TO BE
USED ONLY IN CONNECTION WITH WORK PERFORMED BY CBI. REPRODUCTION IN WHOLE OR IN PART FOR ANY PURPOSE OTHER
THAN WORK PERFORMED BY CBI IS FORBIDDEN EXCEPT BY EXPRESS WRITTEN PERMISSION OF CBI. IT IS TO BE SAFEGUARDED
AGAINST BOTH DELIBERATE AND INADVERTENT DISCLOSURE TO ANY THIRD PARTY."
Lummus Technology
Liwa Plastics Project
Heat and Material Balance
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 1
Stream 6001 6003 6004 6005
0 0 0
Stream Description MIXED WATER WASH WASTE WATER TOTAL WASTE
HYDROGENATED COLUMN TO WATER TO
C4S FROM OSBL BOTTOMS WASTE WATER WASTE WATER
PLANT OSBL PLANT OSBL
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.00 100.00 100.00 100.00
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.01 0.00 0.00 0.00
Propylene 0.01 0.00 0.00 0.00
Propane 0.08 0.00 0.00 0.00
Propadiene 0.03 0.00 0.00 0.00
Isobutane 13.92 0.00 0.00 0.00
Isobutene 30.58 0.00 0.00 0.00
1-Butene 23.41 0.00 0.00 0.00
Butadiene 0.00 0.00 0.00 0.00
n-Butane 14.34 0.00 0.00 0.00
2-Butene 17.25 0.00 0.00 0.00
C5's 0.37 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.00 0.00 0.00 0.00
TBA 0.00 0.00 0.00 0.00
DME 0.00 0.00 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 22376 6706 6706 6709
Actual Volumetric Flow m³/h 39.7 6.8 6.8 6.8
Actual Density kg/m³ 564 992 990 990
Standard Specific Gravity 0.60 1.00 1.00 1.00
Dynamic Viscosity cP 0.15 0.65 0.65 0.65
Kinematic Viscosity cSt 0.26 0.65 0.65 0.65
Specific Enthalpy kcal/kg 22.5 40.3 40.3 40.3
Surface Tension mN/m 10.1 69.5 69.5 69.5
Specific Heat Capacity kcal/(kg°C) 0.58 1.00 1.00 1.00
Thermal Conductivity kcal/(h·m·°C) 0.086 0.542 0.542 0.542
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 1
Stream 6006 6007 6008 6009
0 0 0 0
Stream Description WATER WASH FEED TO C4 FEED C4 FEED
COLUMN C4 FEED PUMP PUMP
OVERHEAD SURGE DRUM SUCTION DISCHARGE
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.03 0.03 0.03 0.03
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.01 0.01 0.01 0.01
Propylene 0.01 0.01 0.01 0.01
Propane 0.08 0.08 0.08 0.08
Propadiene 0.03 0.03 0.03 0.03
Isobutane 13.92 13.92 13.92 13.92
Isobutene 30.57 30.57 30.57 30.57
1-Butene 23.40 23.40 23.40 23.40
Butadiene 0.00 0.00 0.00 0.00
n-Butane 14.34 14.34 14.34 14.34
2-Butene 17.25 17.25 17.25 17.25
C5's 0.37 0.37 0.37 0.37
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.00 0.00 0.00 0.00
TBA 0.00 0.00 0.00 0.00
DME 0.00 0.00 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 22383 22383 22383 22383
Actual Volumetric Flow m³/h 39.7 39.7 39.7 39.8
Actual Density kg/m³ 564 564 564 562
Standard Specific Gravity 0.60 0.60 0.60 0.60
Dynamic Viscosity cP 0.15 0.15 0.15 0.15
Kinematic Viscosity cSt 0.26 0.26 0.26 0.26
Specific Enthalpy kcal/kg 22.4 22.4 22.4 23.2
Surface Tension mN/m 10.1 10.1 10.1 10.0
Specific Heat Capacity kcal/(kg°C) 0.58 0.58 0.58 0.58
Thermal Conductivity kcal/(h·m·°C) 0.086 0.086 0.086 0.085
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 1
Stream 6010 6011 6012 6013
0 0 0 0
Stream Description C4 FEED MIXED DEMINERALIZED DEMINERALIZED
PUMP C4s & MeOH WATER FROM WATER FEED
DISCHARGE OSBL TO WATER TO WATER
DOWNSTRM FV WASH COLUMN WASH COLUMN
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.03 0.04 100.00 100.00
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.01 0.01 0.00 0.00
Propylene 0.01 0.01 0.00 0.00
Propane 0.08 0.07 0.00 0.00
Propadiene 0.03 0.02 0.00 0.00
Isobutane 13.92 11.68 0.00 0.00
Isobutene 30.57 25.65 0.00 0.00
1-Butene 23.40 19.64 0.00 0.00
Butadiene 0.00 0.00 0.00 0.00
n-Butane 14.34 12.03 0.00 0.00
2-Butene 17.25 14.47 0.00 0.00
C5's 0.37 0.31 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.00 16.07 0.00 0.00
TBA 0.00 0.00 0.00 0.00
DME 0.00 0.00 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 22383 26673 6713 6713
Actual Volumetric Flow m³/h 39.8 45.5 6.8 6.8
Actual Density kg/m³ 562 586 990 990
Standard Specific Gravity 0.60 0.62 1.00 1.00
Dynamic Viscosity cP 0.15 0.20 0.65 0.65
Kinematic Viscosity cSt 0.26 0.34 0.66 0.66
Specific Enthalpy kcal/kg 23.2 24.4 40.0 40.0
Surface Tension mN/m 10.0 12.6 69.6 69.6
Specific Heat Capacity kcal/(kg°C) 0.58 0.59 1.00 1.00
Thermal Conductivity kcal/(h·m·°C) 0.085 0.090 0.541 0.541
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 1
Stream 6014 6015 6016 6017
0 0 0 0
Stream Description REACTOR PRIMARY PRIMARY SECONDARY
FEED REACTOR REACTOR REACTOR
PREHEATER FEED EFFLUENT FEED
OUTLET COOLER
INLET
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.04 0.04 0.04 0.04
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.01 0.01 0.01 0.01
Propylene 0.01 0.01 0.01 0.01
Propane 0.07 0.07 0.07 0.07
Propadiene 0.02 0.02 0.02 0.02
Isobutane 11.68 11.68 11.68 11.68
Isobutene 25.65 15.68 5.71 5.71
1-Butene 19.64 19.62 19.59 19.59
Butadiene 0.00 0.00 0.00 0.00
n-Butane 12.03 12.03 12.03 12.03
2-Butene 14.47 14.47 14.47 14.47
C5's 0.31 0.31 0.31 0.31
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.06 0.12 0.12
Methanol 16.07 10.38 4.68 4.68
TBA 0.00 0.05 0.10 0.10
DME 0.00 0.03 0.06 0.06
MTBE 0.00 15.52 31.04 31.04
MSBE 0.00 0.04 0.07 0.07
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 26673 53345 53345 26673
Actual Volumetric Flow m³/h 45.5 89.1 93.5 46.7
Actual Density kg/m³ 586 599 571 571
Standard Specific Gravity 0.62 0.63 0.64 0.64
Dynamic Viscosity cP 0.20 0.19 0.15 0.15
Kinematic Viscosity cSt 0.34 0.32 0.26 0.26
Specific Enthalpy kcal/kg 24.4 23.2 39.6 39.6
Surface Tension mN/m 12.6 12.7 9.5 9.5
Specific Heat Capacity kcal/(kg°C) 0.59 0.58 0.61 0.61
Thermal Conductivity kcal/(h·m·°C) 0.090 0.092 0.084 0.084
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 1
Stream 6018 6019 6020 6021
0 0 0 0
Stream Description SECONDARY SECONDARY SECONDARY INLET TO
REACTOR REACTOR REACTOR PRIMARY
FEED FEED EFFLUENT REACTOR
COOLER EFFLUENT
OUTLET COOLER
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.04 0.04 0.04 0.04
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.01 0.01 0.01 0.01
Propylene 0.01 0.01 0.01 0.01
Propane 0.07 0.07 0.07 0.07
Propadiene 0.02 0.02 0.02 0.02
Isobutane 11.68 11.68 11.68 11.68
Isobutene 5.71 5.71 2.57 5.71
1-Butene 19.59 19.59 19.57 19.59
Butadiene 0.00 0.00 0.00 0.00
n-Butane 12.03 12.03 12.03 12.03
2-Butene 14.47 14.47 14.47 14.47
C5's 0.31 0.31 0.31 0.31
C6's 0.00 0.00 0.00 0.00
DIB 0.12 0.12 0.12 0.12
Methanol 4.68 4.68 2.88 4.68
TBA 0.10 0.10 0.10 0.10
DME 0.06 0.06 0.06 0.06
MTBE 31.04 31.04 35.97 31.04
MSBE 0.07 0.07 0.10 0.07
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 26673 26673 26673 26673
Actual Volumetric Flow m³/h 43.5 43.5 44.2 46.7
Actual Density kg/m³ 613 613 604 571
Standard Specific Gravity 0.64 0.64 0.65 0.64
Dynamic Viscosity cP 0.19 0.19 0.17 0.15
Kinematic Viscosity cSt 0.31 0.31 0.29 0.26
Specific Enthalpy kcal/kg 21.6 21.6 26.8 39.6
Surface Tension mN/m 12.8 12.8 11.8 9.5
Specific Heat Capacity kcal/(kg°C) 0.57 0.57 0.57 0.61
Thermal Conductivity kcal/(h·m·°C) 0.093 0.093 0.090 0.084
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 1
Stream 6022 6023 6024 6025
0 0 0 0
Stream Description PRIMARY PRIMARY PRIMARY CD REACTION
REACTOR REACTOR REACTOR COLUMN
RECYCLE RECYCLE RECYCLE FEED
PUMP PUMP
SUCTION DISCHARGE
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.04 0.04 0.04 0.04
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.01 0.01 0.01 0.01
Propylene 0.01 0.01 0.01 0.01
Propane 0.07 0.07 0.07 0.07
Propadiene 0.02 0.02 0.02 0.02
Isobutane 11.68 11.68 11.68 11.68
Isobutene 5.71 5.71 5.71 2.57
1-Butene 19.59 19.59 19.59 19.57
Butadiene 0.00 0.00 0.00 0.00
n-Butane 12.03 12.03 12.03 12.03
2-Butene 14.47 14.47 14.47 14.47
C5's 0.31 0.31 0.31 0.31
C6's 0.00 0.00 0.00 0.00
DIB 0.12 0.12 0.12 0.12
Methanol 4.68 4.68 4.68 2.88
TBA 0.10 0.10 0.10 0.10
DME 0.06 0.06 0.06 0.06
MTBE 31.04 31.04 31.04 35.97
MSBE 0.07 0.07 0.07 0.10
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 26673 26673 26673 26673
Actual Volumetric Flow m³/h 43.5 43.6 43.6 46.3
Actual Density kg/m³ 613 612 612 576
Standard Specific Gravity 0.64 0.64 0.64 0.65
Dynamic Viscosity cP 0.19 0.19 0.19 0.15
Kinematic Viscosity cSt 0.31 0.31 0.31 0.26
Specific Enthalpy kcal/kg 21.6 21.9 21.9 38.9
Surface Tension mN/m 12.8 12.8 12.8 9.5
Specific Heat Capacity kcal/(kg°C) 0.57 0.57 0.57 0.61
Thermal Conductivity kcal/(h·m·°C) 0.093 0.093 0.093 0.085
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 1
Stream 6026 6027 6028 6029
0 0 0 0
Stream Description CD REACTION MTBE MTBE MTBE
COLUMN PRODUCT PRODUCT PRODUCT
BOTTOMS COOLER COOLER TO OSBL
INLET OUTLET
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.00 0.00 0.00 0.00
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.00 0.00 0.00 0.00
Propylene 0.00 0.00 0.00 0.00
Propane 0.00 0.00 0.00 0.00
Propadiene 0.00 0.00 0.00 0.00
Isobutane 0.00 0.00 0.00 0.00
Isobutene 0.00 0.00 0.00 0.00
1-Butene 0.00 0.00 0.00 0.00
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.02 0.02 0.02 0.02
2-Butene 0.07 0.07 0.07 0.07
C5's 0.76 0.76 0.76 0.76
C6's 0.00 0.00 0.00 0.00
DIB 0.29 0.29 0.29 0.29
Methanol 0.10 0.10 0.10 0.10
TBA 0.26 0.26 0.26 0.26
DME 0.00 0.00 0.00 0.00
MTBE 98.05 98.05 98.05 98.05
MSBE 0.43 0.43 0.43 0.43
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 10867 10867 10867 10867
Actual Volumetric Flow m³/h 18.2 16.3 15.3 15.3
Actual Density kg/m³ 598 666 713 713
Standard Specific Gravity 0.74 0.74 0.74 0.74
Dynamic Viscosity cP 0.13 0.19 0.27 0.27
Kinematic Viscosity cSt 0.22 0.29 0.38 0.38
Specific Enthalpy kcal/kg 74.4 44.8 22.7 22.7
Surface Tension mN/m 7.1 12.3 16.9 16.9
Specific Heat Capacity kcal/(kg°C) 0.62 0.57 0.53 0.53
Thermal Conductivity kcal/(h·m·°C) 0.101 0.101 0.104 0.104
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 1
Stream 6030 6031 6032 6033
0 0 0 0
Stream Description CD REACTION CD REACTION FEED TO CD REACTION
COLUMN COLUMN CD REACTION COLUMN
OVERHEAD CONDENSER COLUMN REFLUX PUMP
OUTLET OVERHEAD SUCTION
DRUM
0 0 0 0
Stream Phase VAPOR LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.09 0.09 0.09 0.09
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.01 0.01 0.01 0.01
Propylene 0.01 0.01 0.01 0.01
Propane 0.11 0.11 0.11 0.11
Propadiene 0.04 0.04 0.04 0.04
Isobutane 19.35 19.35 19.35 19.35
Isobutene 0.04 0.04 0.04 0.04
1-Butene 32.41 32.41 32.41 32.41
Butadiene 0.00 0.00 0.00 0.00
n-Butane 19.92 19.92 19.92 19.92
2-Butene 23.87 23.87 23.87 23.87
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 3.99 3.99 3.99 3.99
TBA 0.00 0.00 0.00 0.00
DME 0.16 0.16 0.16 0.16
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h 37028
Actual Volumetric Flow m³/h 2167
Molecular Weight 55.0
Actual Density kg/m³ 17.1
Viscosity cP 0.009
Specific Enthalpy kcal/kg 119.49
Specific Heat Capacity kcal/(kg°C) 0.45
Thermal Conductivity kcal/(h·m·°C) 0.016
Liquid
Mass Flow Rate kg/h 37028 37028 37028
Actual Volumetric Flow m³/h 66.7 66.7 66.7
Actual Density kg/m³ 555 555 555
Standard Specific Gravity 0.00 0.60 0.60 0.60
Dynamic Viscosity cP 0.14 0.14 0.14
Kinematic Viscosity cSt 0.26 0.26 0.26
Specific Enthalpy kcal/kg 28.3 28.3 28.3
Surface Tension mN/m 10.0 10.0 10.0
Specific Heat Capacity kcal/(kg°C) 0.60 0.60 0.60
Thermal Conductivity kcal/(h·m·°C) 0.084 0.084 0.084
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 1
Stream 6034 6035 6036 6037
0 0 0 0
Stream Description CD REACTION CD REACTION CD REACTION MEOH EXT.
COLUMN COLUMN COLUMN COLUMN
REFLUX PUMP REFLUX REFLUX AT FEED
DISCHARGE COLUMN FEED COOLER
INLET
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.09 0.09 0.09 0.09
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.01 0.01 0.01 0.01
Propylene 0.01 0.01 0.01 0.01
Propane 0.11 0.11 0.11 0.11
Propadiene 0.04 0.04 0.04 0.04
Isobutane 19.35 19.35 19.35 19.35
Isobutene 0.04 0.04 0.04 0.04
1-Butene 32.41 32.41 32.41 32.41
Butadiene 0.00 0.00 0.00 0.00
n-Butane 19.92 19.92 19.92 19.92
2-Butene 23.87 23.87 23.87 23.87
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 3.99 3.99 3.99 3.99
TBA 0.00 0.00 0.00 0.00
DME 0.16 0.16 0.16 0.16
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 37028 20929 20929 16099
Actual Volumetric Flow m³/h 66.8 37.8 37.8 29.1
Actual Density kg/m³ 554 554 554 554
Standard Specific Gravity 0.60 0.60 0.60 0.60
Dynamic Viscosity cP 0.14 0.14 0.14 0.14
Kinematic Viscosity cSt 0.26 0.26 0.26 0.26
Specific Enthalpy kcal/kg 28.8 28.8 28.8 28.8
Surface Tension mN/m 9.9 9.9 9.9 9.9
Specific Heat Capacity kcal/(kg°C) 0.60 0.60 0.60 0.60
Thermal Conductivity kcal/(h·m·°C) 0.084 0.084 0.084 0.084
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 1
Stream 6038 6039 6040 6041
0 0 0 0
Stream Description C4 DISTILLATE METHANOL METHANOL METHANOL
TO METHANOL EXTRACTION REC. COL. RECOVERY
EXTRACTION COLUMN FEED/BTMS COLUMN
COLUMN BOTTOMS EXCHANGER FEED
INLET
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.09 80.00 80.00 80.00
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.01 0.00 0.00 0.00
Propylene 0.01 0.00 0.00 0.00
Propane 0.11 0.00 0.00 0.00
Propadiene 0.04 0.00 0.00 0.00
Isobutane 19.35 0.00 0.00 0.00
Isobutene 0.04 0.00 0.00 0.00
1-Butene 32.41 0.00 0.00 0.00
Butadiene 0.00 0.00 0.00 0.00
n-Butane 19.92 0.00 0.00 0.00
2-Butene 23.87 0.00 0.00 0.00
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 3.99 20.00 20.00 20.00
TBA 0.00 0.00 0.00 0.00
DME 0.16 0.00 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 16099 3213 3213 3213
Actual Volumetric Flow m³/h 28.3 3.4 3.4 3.5
Actual Density kg/m³ 569 938 938 915
Standard Specific Gravity 0.60 0.95 0.95 0.95
Dynamic Viscosity cP 0.16 0.62 0.62 0.37
Kinematic Viscosity cSt 0.27 0.66 0.66 0.40
Specific Enthalpy kcal/kg 22.4 36.8 36.8 69.4
Surface Tension mN/m 11.1 63.6 63.6 58.2
Specific Heat Capacity kcal/(kg°C) 0.59 0.92 0.92 0.94
Thermal Conductivity kcal/(h·m·°C) 0.088 0.320 0.320 0.315
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 1
Stream 6042 6043 6044 6045
0 0 0
Stream Description METHANOL C4s TO METHANOL METHANOL
EXTRACTION B-1 RECOVERY RECOVERY
COLUMN HEAVIES COLUMN COLUMN
OVERHEAD COLUMN BOTTOMS BOTTOMS PUMP
DISCHARGE
0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0
Component (wt%) 0 0 0
Water 0.03 0.03 100.00 100.00
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.01 0.01 0.00 0.00
Propylene 0.01 0.01 0.00 0.00
Propane 0.11 0.11 0.00 0.00
Propadiene 0.04 0.04 0.00 0.00
Isobutane 20.17 20.17 0.00 0.00
Isobutene 0.04 0.04 0.00 0.00
1-Butene 33.78 33.78 0.00 0.00
Butadiene 0.00 0.00 0.00 0.00
n-Butane 20.76 20.76 0.00 0.00
2-Butene 24.87 24.87 0.00 0.00
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.00 0.00 0.00 0.00
TBA 0.00 0.00 0.00 0.00
DME 0.17 0.17 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 15447 15447 2562 2562
Actual Volumetric Flow m³/h 27.5 27.4 2.7 2.7
Actual Density kg/m³ 562 563 939 939
Standard Specific Gravity 0.59 0.59 1.00 1.00
Dynamic Viscosity cP 0.14 0.14 0.22 0.22
Kinematic Viscosity cSt 0.25 0.25 0.23 0.23
Specific Enthalpy kcal/kg 22.3 22.3 126.6 126.7
Surface Tension mN/m 10.3 10.5 54.0 54.0
Specific Heat Capacity kcal/(kg°C) 0.58 0.58 1.02 1.02
Thermal Conductivity kcal/(h·m·°C) 0.086 0.086 0.592 0.591
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 1
Stream 6046 6047 6048 6049
0 0 0 0
Stream Description RECYCLE RECYCLE RECYCLE METHANOL
WATER WATER WATER TO RECOVERY
COOLER COOLER METHANOL COLUMN
INLET OUTLET EXTRACTION OVERHEAD
COLUMN
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID VAPOR
0 0 0 0
Component (wt%) 0 0 0 0
Water 100.00 100.00 100.00 0.05
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.00 0.00 0.00 0.00
Propylene 0.00 0.00 0.00 0.00
Propane 0.00 0.00 0.00 0.00
Propadiene 0.00 0.00 0.00 0.00
Isobutane 0.00 0.00 0.00 0.00
Isobutene 0.00 0.00 0.00 0.00
1-Butene 0.00 0.00 0.00 0.00
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.00 0.00 0.00 0.00
2-Butene 0.00 0.00 0.00 0.00
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.00 0.00 0.00 99.95
TBA 0.00 0.00 0.00 0.00
DME 0.00 0.00 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h 1929
Actual Volumetric Flow m³/h 1000
Molecular Weight 32.0
Actual Density kg/m³ 1.9
Viscosity cP 0.012
Specific Enthalpy kcal/kg 312.51
Specific Heat Capacity kcal/(kg°C) 0.37
Thermal Conductivity kcal/(h·m·°C) 0.018
Liquid
Mass Flow Rate kg/h 2562 2562 2562
Actual Volumetric Flow m³/h 2.6 2.6 2.6
Actual Density kg/m³ 967 990 990
Standard Specific Gravity 1.00 1.00 1.00 0.00
Dynamic Viscosity cP 0.33 0.65 0.65
Kinematic Viscosity cSt 0.34 0.66 0.66
Specific Enthalpy kcal/kg 85.8 40.0 40.0
Surface Tension mN/m 62.0 69.6 69.6
Specific Heat Capacity kcal/(kg°C) 1.00 1.00 1.00
Thermal Conductivity kcal/(h·m·°C) 0.577 0.541 0.541
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 1
Stream 6050 6051 6052 6053
0 0 0 0
Stream Description METHANOL METHANOL METHANOL METHANOL
RECOVERY RECOVERY RECOVERY RECOVERY
COLUMN COLUMN COLUMN COLUMN
CONDENSER OVHD DRUM REFLUX PUMP REFLUX PUMP
OUTLET INLET SUCTION DISCHARGE
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.05 0.05 0.08 0.08
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.00 0.00 0.00 0.00
Propylene 0.00 0.00 0.00 0.00
Propane 0.00 0.00 0.00 0.00
Propadiene 0.00 0.00 0.00 0.00
Isobutane 0.00 0.00 0.00 0.00
Isobutene 0.00 0.00 0.00 0.00
1-Butene 0.00 0.00 0.00 0.00
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.00 0.00 0.00 0.00
2-Butene 0.00 0.00 0.00 0.00
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 99.95 99.95 99.92 99.92
TBA 0.00 0.00 0.00 0.00
DME 0.00 0.00 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 1929 1929 5868 5868
Actual Volumetric Flow m³/h 2.6 2.6 7.7 7.7
Actual Density kg/m³ 749 749 766 765
Standard Specific Gravity 0.80 0.80 0.80 0.80
Dynamic Viscosity cP 0.34 0.34 0.41 0.40
Kinematic Viscosity cSt 0.46 0.46 0.53 0.52
Specific Enthalpy kcal/kg 40.6 40.6 29.4 30.3
Surface Tension mN/m 18.8 18.8 20.3 20.2
Specific Heat Capacity kcal/(kg°C) 0.68 0.68 0.64 0.65
Thermal Conductivity kcal/(h·m·°C) 0.162 0.162 0.166 0.166
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 1
Stream 6054 6055 6056 6057
0 0 0 0
Stream Description METHANOL METHANOL METHANOL RECYCLE
RECOVERY RECOVERY TO MTBE METHANOL
COLUMN COLUMN REACTION TO C4s
REFLUX REFLUX AT SECTION STREAM
COLUMN FEED
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.08 0.08 0.08 0.08
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.00 0.00 0.00 0.00
Propylene 0.00 0.00 0.00 0.00
Propane 0.00 0.00 0.00 0.00
Propadiene 0.00 0.00 0.00 0.00
Isobutane 0.00 0.00 0.00 0.00
Isobutene 0.00 0.00 0.00 0.00
1-Butene 0.00 0.00 0.00 0.00
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.00 0.00 0.00 0.00
2-Butene 0.00 0.00 0.00 0.00
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 99.92 99.92 99.92 99.92
TBA 0.00 0.00 0.00 0.00
DME 0.00 0.00 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 1286 1286 4582 4290
Actual Volumetric Flow m³/h 1.7 1.7 6.0 5.6
Actual Density kg/m³ 765 765 765 765
Standard Specific Gravity 0.80 0.80 0.80 0.80
Dynamic Viscosity cP 0.40 0.40 0.40 0.40
Kinematic Viscosity cSt 0.52 0.52 0.52 0.52
Specific Enthalpy kcal/kg 30.3 30.3 30.3 30.3
Surface Tension mN/m 20.2 20.2 20.2 20.2
Specific Heat Capacity kcal/(kg°C) 0.65 0.65 0.65 0.65
Thermal Conductivity kcal/(h·m·°C) 0.166 0.166 0.166 0.166
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 1
Stream 6058 6059 6060 6061
0 0 0
Stream Description RECYCLE METHANOL METHANOL METHANOL
METHANOL INJECTION TO INJECTION TO INJECTION TO
TO C4s CD REACTION CD REACTION CD REACTION
STREAM COLUMN COLUMN COLUMN
0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.08 0.08 0.08 0.08
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.00 0.00 0.00 0.00
Propylene 0.00 0.00 0.00 0.00
Propane 0.00 0.00 0.00 0.00
Propadiene 0.00 0.00 0.00 0.00
Isobutane 0.00 0.00 0.00 0.00
Isobutene 0.00 0.00 0.00 0.00
1-Butene 0.00 0.00 0.00 0.00
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.00 0.00 0.00 0.00
2-Butene 0.00 0.00 0.00 0.00
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 99.92 99.92 99.92 99.92
TBA 0.00 0.00 0.00 0.00
DME 0.00 0.00 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 4290 294 15 279
Actual Volumetric Flow m³/h 5.6 0.4 0.0 0.4
Actual Density kg/m³ 765 765 765 765
Standard Specific Gravity 0.80 0.80 0.80 0.80
Dynamic Viscosity cP 0.40 0.40 0.40 0.40
Kinematic Viscosity cSt 0.52 0.52 0.52 0.52
Specific Enthalpy kcal/kg 30.3 30.3 30.3 30.3
Surface Tension mN/m 20.2 20.2 20.2 20.2
Specific Heat Capacity kcal/(kg°C) 0.65 0.65 0.65 0.65
Thermal Conductivity kcal/(h·m·°C) 0.166 0.166 0.166 0.166
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 1
Stream 6062 6063 6064 6065
0 0 0
Stream Description FRESH FILTERED FILTERED CD REACTION
METHANOL FRESH FRESH COLUMN
FROM METHANOL METHANOL REBOILER
STORAGE AT INLET
OSBL
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.10 0.10 0.10 0.00
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.00 0.00 0.00 0.00
Propylene 0.00 0.00 0.00 0.00
Propane 0.00 0.00 0.00 0.00
Propadiene 0.00 0.00 0.00 0.00
Isobutane 0.00 0.00 0.00 0.00
Isobutene 0.00 0.00 0.00 0.00
1-Butene 0.00 0.00 0.00 0.00
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.00 0.00 0.00 0.02
2-Butene 0.00 0.00 0.00 0.07
C5's 0.00 0.00 0.00 0.76
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.29
Methanol 99.90 99.90 99.90 0.10
TBA 0.00 0.00 0.00 0.26
DME 0.00 0.00 0.00 0.00
MTBE 0.00 0.00 0.00 98.05
MSBE 0.00 0.00 0.00 0.43
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 3939 3939 3939 191943
Actual Volumetric Flow m³/h 5.1 5.1 5.1 321.2
Actual Density kg/m³ 775 775 775 598
Standard Specific Gravity 0.80 0.80 0.80 0.74
Dynamic Viscosity cP 0.40 0.40 0.40 0.13
Kinematic Viscosity cSt 0.58 0.58 0.58 0.22
Specific Enthalpy kcal/kg 24.0 24.0 24.0 74.4
Surface Tension mN/m 21.1 21.1 21.1 7.1
Specific Heat Capacity kcal/(kg°C) 0.63 0.63 0.63 0.62
Thermal Conductivity kcal/(h·m·°C) 0.166 0.166 0.166 0.101
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 1
Stream 6066 6067 6068 6099
0 0 0
Stream Description CD REACTION METHANOL METHANOL C4 DISTILLATE
COLUMN RECOVERY RECOVERY TO METHANOL
REBOILER COLUMN COLUMN EXTRACTION
OUTLET REBOILER REBOILER COLUMN
INLET OUTLET
0 0 0 0
Stream Phase MIXED LIQUID MIXED LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.00 99.99 99.99 0.09
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.00 0.00 0.00 0.01
Propylene 0.00 0.00 0.00 0.01
Propane 0.00 0.00 0.00 0.11
Propadiene 0.00 0.00 0.00 0.04
Isobutane 0.00 0.00 0.00 19.35
Isobutene 0.00 0.00 0.00 0.04
1-Butene 0.00 0.00 0.00 32.41
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.02 0.00 0.00 19.92
2-Butene 0.07 0.00 0.00 23.87
C5's 0.76 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.29 0.00 0.00 0.00
Methanol 0.10 0.01 0.01 3.99
TBA 0.26 0.00 0.00 0.00
DME 0.00 0.00 0.00 0.16
MTBE 98.05 0.00 0.00 0.00
MSBE 0.43 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h 57401 1278
Actual Volumetric Flow m³/h 2322.0 987.0
Molecular Weight 87.5 18.0
Actual Density kg/m³ 24.7 1.3
Viscosity cP 0.010 0.013
Specific Enthalpy kcal/kg 135.26 649.19
Specific Heat Capacity kcal/(kg°C) 0.50 0.46
Thermal Conductivity kcal/(h·m·°C) 0.021 0.023
Liquid
Mass Flow Rate kg/h 134542 4239 2961 16099
Actual Volumetric Flow m³/h 225.0 4.5 3.2 28.3
Actual Density kg/m³ 598 939 939 569
Standard Specific Gravity 0.75 1.00 1.00 0.60
Dynamic Viscosity cP 0.13 0.22 0.22 0.16
Kinematic Viscosity cSt 0.22 0.23 0.23 0.27
Specific Enthalpy kcal/kg 74.2 126.3 125.6 22.4
Surface Tension mN/m 7.2 54.1 54.2 11.1
Specific Heat Capacity kcal/(kg°C) 0.62 1.02 1.02 0.59
Thermal Conductivity kcal/(h·m·°C) 0.101 0.591 0.591 0.088
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 1
Stream 0
Stream Description
Stream Phase 0
0
Component (wt%) 0
Water 0.00
Hydrogen 0.00
Methane 0.00
Propylene 0.00
Propane 0.00
Propadiene 0.00
Isobutane 0.00
Isobutene 0.00
1-Butene 0.00
Butadiene 0.00
n-Butane 0.00
2-Butene 0.00
C5's 0.00
C6's 0.00
DIB 0.00
Methanol 0.00
TBA 0.00
DME 0.00
MTBE 0.00
MSBE 0.00
0.00
0.00
Mass Flow Rate kg/h 0
Molar Flow Rate kg mol/hr 0.0
Molecular Weight 0.0
Temperature °C 0.0
Stream Pressure bar (g) 0.0
Stream Enthalpy MMkcal/h 0.000
Weight Fraction Liquid 0.00
Critical Temperature °C 0.0
Critical Pressure bar (a) 0.0
0
Vapor 0.0
Mass Flow rate kg/h 0
Actual Volumetric Flow m³/h 0
Molecular Weight 0.00
Actual Density kg/m³ 0.00
Viscosity cP 0.0000
Specific Enthalpy kcal/kg 0.0
Specific Heat Capacity kcal/(kg°C) 0.000
Thermal Conductivity kcal/(h·m·°C) 0.0000
0.000
Liquid 0.0
Mass Flow Rate kg/h 0
Actual Volumetric Flow m³/h 0.0
Actual Density kg/m³ 0.0
Standard Specific Gravity 0.000
Dynamic Viscosity cP 0.000
Kinematic Viscosity cSt
Specific Enthalpy kcal/kg 0.0
Surface Tension mN/m 0.0
Specific Heat Capacity kcal/(kg°C) 0.000
Thermal Conductivity kcal/(h·m·°C) 0.000
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 1
Stream 6101 6102 6103 6104
Stream Description B-1 HEAVIES B-1 HEAVIES B-1 HEAVIES B-1 HEAVIES
COLUMN #1 COLUMN COLUMN #2 COLUMN #2
BOTTOMS TRANSFER FEED OVERHEAD
PUMP DISCH.
Component (wt%)
Water 0.00 0.00 0.00 0.00
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.00 0.00 0.00 0.00
Propylene 0.00 0.00 0.00 0.00
Propane 0.01 0.01 0.01 0.02
Propadiene 0.01 0.01 0.01 0.01
Isobutane 11.73 11.73 11.73 13.46
Isobutene 0.05 0.05 0.05 0.05
1-Butene 57.02 57.02 57.02 57.31
Butadiene 0.00 0.00 0.00 0.00
n-Butane 19.18 19.18 19.18 17.91
2-Butene 11.97 11.97 11.97 11.18
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.00 0.00 0.00 0.00
TBA 0.00 0.00 0.00 0.00
DME 0.02 0.02 0.02 0.04
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h 124137
Actual Volumetric Flow m³/h 6218
Molecular Weight 56.7
Actual Density kg/m³ 20.0
Viscosity cP 0.009
Specific Enthalpy kcal/kg 111.65
Specific Heat Capacity kcal/(kg°C) 0.48
Thermal Conductivity kcal/(h·m·°C) 0.017
Liquid
Mass Flow Rate kg/h 115886 115886 115886
Actual Volumetric Flow m³/h 219.5 219.2 219.5
Actual Density kg/m³ 528 529 528
Standard Specific Gravity 0.59 0.59 0.59 0.00
Dynamic Viscosity cP 0.11 0.11 0.11
Kinematic Viscosity cSt 0.22 0.21 0.22
Specific Enthalpy kcal/kg 36.9 37.2 36.9
Surface Tension mN/m 7.6 7.5 7.5
Specific Heat Capacity kcal/(kg°C) 0.61 0.61 0.61
Thermal Conductivity kcal/(h·m·°C) 0.080 0.079 0.080
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 1
Stream 6105 6106 6107 6108
Component (wt%)
Water 0.06 0.06 0.06
Hydrogen 0.00 0.00 0.00
Methane 0.03 0.03 0.03
Propylene 0.02 0.02 0.02
Propane 0.21 0.21 0.21
Propadiene 0.08 0.08 0.08
Isobutane 37.76 37.76 37.76
Isobutene 0.07 0.07 0.07
1-Butene 61.34 61.34 61.34
Butadiene 0.00 0.00 0.00
n-Butane 0.10 0.10 0.10
2-Butene 0.02 0.02 0.02
C5's 0.00 0.00 0.00
C6's 0.00 0.00 0.00
DIB 0.00 0.00 0.00
Methanol 0.00 0.00 0.00
TBA 0.00 0.00 0.00
DME 0.31 0.31 0.31
MTBE 0.00 0.00 0.00
MSBE 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h 113249
Actual Volumetric Flow m³/h 6121
Molecular Weight 56.6
Actual Density kg/m³ 18.5
Viscosity cP 0.009
Specific Enthalpy kcal/kg 108.40
Specific Heat Capacity kcal/(kg°C) 0.44
Thermal Conductivity kcal/(h·m·°C) 0.016
Liquid
Mass Flow Rate kg/h 113249 113249
Actual Volumetric Flow m³/h 207.8 207.8
Actual Density kg/m³ 545 545
Standard Specific Gravity 0.00 0.59 0.59
Dynamic Viscosity cP 0.13 0.13
Kinematic Viscosity cSt 0.23 0.23
Specific Enthalpy kcal/kg 25.7 25.7
Surface Tension mN/m 9.1 9.1
Specific Heat Capacity kcal/(kg°C) 0.59 0.59
Thermal Conductivity kcal/(h·m·°C) 0.082 0.082
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 1
Stream 6109 6110 6111 6112
Component (wt%)
Water 0.06 0.06 0.06
Hydrogen 0.00 0.00 0.00
Methane 0.03 0.03 0.03
Propylene 0.02 0.02 0.02
Propane 0.21 0.21 0.21
Propadiene 0.08 0.08 0.08
Isobutane 37.76 37.76 37.76
Isobutene 0.07 0.07 0.07
1-Butene 61.34 61.34 61.34
Butadiene 0.00 0.00 0.00
n-Butane 0.10 0.10 0.10
2-Butene 0.02 0.02 0.02
C5's 0.00 0.00 0.00
C6's 0.00 0.00 0.00
DIB 0.00 0.00 0.00
Methanol 0.00 0.00 0.00
TBA 0.00 0.00 0.00
DME 0.31 0.31 0.31
MTBE 0.00 0.00 0.00
MSBE 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 113249 113249 104998
Actual Volumetric Flow m³/h 207.8 207.6 192.5
Actual Density kg/m³ 545 546 546
Standard Specific Gravity 0.59 0.59 0.59
Dynamic Viscosity cP 0.13 0.13 0.13
Kinematic Viscosity cSt 0.23 0.23 0.23
Specific Enthalpy kcal/kg 25.7 26.0 26.0
Surface Tension mN/m 9.1 9.0 9.0
Specific Heat Capacity kcal/(kg°C) 0.59 0.59 0.59
Thermal Conductivity kcal/(h·m·°C) 0.082 0.082 0.082
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 1
Stream 6113 6114 6115 6116
Stream Description B-1 HEAVIES B-1 HEAVIES B-1 HEAVIES B-1 HEAVIES
COLUMN COLUMN COLUMN COLUMN #2
REFLUX AT OVERHEAD TO OVERHEAD TO BOTTOMS
COLUMN FEED B-1 LIGHTS B-1 LIGHTS
COLUMN COLUMN
Component (wt%)
Water 0.06 0.06 0.06 0.00
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.03 0.03 0.03 0.00
Propylene 0.02 0.02 0.02 0.00
Propane 0.21 0.21 0.21 0.00
Propadiene 0.08 0.08 0.08 0.00
Isobutane 37.76 37.76 37.76 0.00
Isobutene 0.07 0.07 0.07 0.00
1-Butene 61.34 61.34 61.34 2.18
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.10 0.10 0.10 44.45
2-Butene 0.02 0.02 0.02 53.37
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.00 0.00 0.00 0.00
TBA 0.00 0.00 0.00 0.00
DME 0.31 0.31 0.31 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 104998 8251 8251 7196
Actual Volumetric Flow m³/h 192.8 15.1 15.1 13.7
Actual Density kg/m³ 545 546 545 526
Standard Specific Gravity 0.59 0.59 0.60
Dynamic Viscosity cP 0.13 0.13 0.13 0.12
Kinematic Viscosity cSt 0.23 0.23 0.23 0.23
Specific Enthalpy kcal/kg 26.0 26.0 26.0 43.6
Surface Tension mN/m 9.0 9.0 9.0 7.4
Specific Heat Capacity kcal/(kg°C) 0.59 0.59 0.59 0.65
Thermal Conductivity kcal/(h·m·°C) 0.082 0.082 0.082 0.078
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 1
Stream 6117 6118 6119 6120
Component (wt%)
Water 0.00 0.00 0.00 0.00
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.00 0.00 0.00 0.00
Propylene 0.00 0.00 0.00 0.00
Propane 0.00 0.00 0.00 0.00
Propadiene 0.00 0.00 0.00 0.00
Isobutane 0.00 0.00 0.00 31.37
Isobutene 0.00 0.00 0.00 0.11
1-Butene 2.18 2.18 2.18 68.46
Butadiene 0.00 0.00 0.00 0.00
n-Butane 44.45 44.45 44.45 0.04
2-Butene 53.37 53.37 53.37 0.01
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.00 0.00 0.00 0.00
TBA 0.00 0.00 0.00 0.00
DME 0.00 0.00 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 7196 7196 7196 126123
Actual Volumetric Flow m³/h 13.7 12.7 12.7 244.7
Actual Density kg/m³ 526 568 568 516
Standard Specific Gravity 0.60 0.60 0.60 0.59
Dynamic Viscosity cP 0.12 0.15 0.15 0.11
Kinematic Viscosity cSt 0.23 0.26 0.26 0.21
Specific Enthalpy kcal/kg 43.7 25.3 25.3 38.8
Surface Tension mN/m 7.4 10.7 10.7 6.7
Specific Heat Capacity kcal/(kg°C) 0.65 0.60 0.60 0.62
Thermal Conductivity kcal/(h·m·°C) 0.078 0.087 0.087 0.076
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 1
Stream 6121 6122 6123 6124
Stream Description B-1 LIGHTS B-1 LIGHTS B-1 LIGHTS B-1 LIGHTS
COLUMN COLUMN #2 COLUMN #2 COLUMN #1
TRANSFER FEED OVERHEAD OVERHEAD
PUMP DISCH.
Component (wt%)
Water 0.00 0.00 0.00 0.04
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.00 0.00 0.00 0.06
Propylene 0.00 0.00 0.00 0.05
Propane 0.00 0.00 0.00 0.51
Propadiene 0.00 0.00 0.00 0.18
Isobutane 31.37 31.37 32.62 90.95
Isobutene 0.11 0.11 0.11 0.03
1-Butene 68.46 68.46 67.22 7.40
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.04 0.04 0.03 0.00
2-Butene 0.01 0.01 0.01 0.00
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.00 0.00 0.00 0.01
TBA 0.00 0.00 0.00 0.00
DME 0.00 0.00 0.00 0.75
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h 121296 108492
Actual Volumetric Flow m³/h 5176 4831
Molecular Weight 56.7 57.5
Actual Density kg/m³ 23.4 22.5
Viscosity cP 0.010 0.009
Specific Enthalpy kcal/kg 110.25 105.91
Specific Heat Capacity kcal/(kg°C) 0.49 0.48
Thermal Conductivity kcal/(h·m·°C) 0.017 0.017
Liquid
Mass Flow Rate kg/h 126123 126123
Actual Volumetric Flow m³/h 244.3 244.7
Actual Density kg/m³ 516 515
Standard Specific Gravity 0.59 0.59 0.00 0.00
Dynamic Viscosity cP 0.11 0.11
Kinematic Viscosity cSt 0.21 0.21
Specific Enthalpy kcal/kg 39.1 38.8
Surface Tension mN/m 6.6 6.6
Specific Heat Capacity kcal/(kg°C) 0.62 0.62
Thermal Conductivity kcal/(h·m·°C) 0.076 0.076
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 1
Stream 6125 6126 6127 6128
Component (wt%)
Water 0.04 0.04 100.00 100.00
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.06 0.06 0.00 0.00
Propylene 0.05 0.05 0.00 0.00
Propane 0.51 0.51 0.00 0.00
Propadiene 0.18 0.18 0.00 0.00
Isobutane 90.95 90.95 0.00 0.00
Isobutene 0.03 0.03 0.00 0.00
1-Butene 7.40 7.40 0.00 0.00
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.00 0.00 0.00 0.00
2-Butene 0.00 0.00 0.00 0.00
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.01 0.01 0.00 0.00
TBA 0.00 0.00 0.00 0.00
DME 0.75 0.75 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 108492 108492 2 2
Actual Volumetric Flow m³/h 206.4 206.4 0.0 0.0
Actual Density kg/m³ 526 526 990 990
Standard Specific Gravity 0.57 0.57 1.00 1.00
Dynamic Viscosity cP 0.14 0.14 0.58 0.58
Kinematic Viscosity cSt 0.26 0.26 0.59 0.59
Specific Enthalpy kcal/kg 26.6 26.6 46.1 46.1
Surface Tension mN/m 7.9 7.9 70.0 70.0
Specific Heat Capacity kcal/(kg°C) 0.62 0.62 1.00 1.00
Thermal Conductivity kcal/(h·m·°C) 0.076 0.076 0.547 0.547
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 1
Stream 6129 6130 6131 6132
Stream Description B-1 LIGHTS B-1 LIGHTS B-1 LIGHTS B-1 LIGHTS
COLUMN COLUMN COLUMN COLUMN
REFLUX PUMP REFLUX PUMP REFLUX REFLUX AT
SUCTION DISCHARGE COLUMN FEED
Component (wt%)
Water 0.04 0.04 0.04 0.04
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.06 0.06 0.06 0.06
Propylene 0.05 0.05 0.05 0.05
Propane 0.51 0.51 0.51 0.51
Propadiene 0.18 0.18 0.18 0.18
Isobutane 90.96 90.96 90.96 90.96
Isobutene 0.03 0.03 0.03 0.03
1-Butene 7.40 7.40 7.40 7.40
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.00 0.00 0.00 0.00
2-Butene 0.00 0.00 0.00 0.00
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.01 0.01 0.01 0.01
TBA 0.00 0.00 0.00 0.00
DME 0.75 0.75 0.75 0.75
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 108489 108489 105069 105069
Actual Volumetric Flow m³/h 206.4 206.0 199.5 200.3
Actual Density kg/m³ 526 527 527 525
Standard Specific Gravity 0.57 0.57 0.57 0.57
Dynamic Viscosity cP 0.14 0.13 0.13 0.13
Kinematic Viscosity cSt 0.26 0.26 0.26 0.26
Specific Enthalpy kcal/kg 26.6 27.1 27.1 27.1
Surface Tension mN/m 7.9 7.8 7.8 7.8
Specific Heat Capacity kcal/(kg°C) 0.62 0.62 0.62 0.62
Thermal Conductivity kcal/(h·m·°C) 0.076 0.076 0.076 0.076
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 1
Stream 6133 6135 6136 6137
Component (wt%)
Water 0.04 0.04 0.00 0.00
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.06 0.06 0.00 0.00
Propylene 0.05 0.05 0.00 0.00
Propane 0.51 0.51 0.00 0.00
Propadiene 0.18 0.18 0.00 0.00
Isobutane 90.96 90.96 0.09 0.09
Isobutene 0.03 0.03 0.10 0.10
1-Butene 7.40 7.40 99.60 99.60
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.00 0.00 0.17 0.17
2-Butene 0.00 0.00 0.03 0.03
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.01 0.01 0.00 0.00
TBA 0.00 0.00 0.00 0.00
DME 0.75 0.75 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 3420 3420 4827 4827
Actual Volumetric Flow m³/h 6.5 6.5 9.3 9.3
Actual Density kg/m³ 527 527 519 519
Standard Specific Gravity 0.57 0.57 0.60 0.60
Dynamic Viscosity cP 0.13 0.14 0.10 0.10
Kinematic Viscosity cSt 0.26 0.26 0.20 0.20
Specific Enthalpy kcal/kg 27.1 27.1 41.1 41.1
Surface Tension mN/m 7.8 7.8 6.6 6.6
Specific Heat Capacity kcal/(kg°C) 0.62 0.62 0.60 0.60
Thermal Conductivity kcal/(h·m·°C) 0.076 0.076 0.079 0.079
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 1
Stream 6138 6139 6140 6141
Component (wt%)
Water 0.00 0.00 0.00 0.00
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.00 0.00 0.00 0.00
Propylene 0.00 0.00 0.00 0.00
Propane 0.00 0.00 0.00 0.00
Propadiene 0.00 0.00 0.00 0.00
Isobutane 0.09 0.09 0.00 0.00
Isobutene 0.10 0.10 0.00 0.00
1-Butene 99.60 99.60 2.26 2.26
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.17 0.17 44.70 44.70
2-Butene 0.03 0.03 53.03 53.03
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.00 0.00 0.00 0.00
TBA 0.00 0.00 0.00 0.00
DME 0.00 0.00 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h 127844
Actual Volumetric Flow m³/h 5969
Molecular Weight 57.0
Actual Density kg/m³ 21.4
Viscosity cP 0.009
Specific Enthalpy kcal/kg 118.33
Specific Heat Capacity kcal/(kg°C) 0.50
Thermal Conductivity kcal/(h·m·°C) 0.018
Liquid
Mass Flow Rate kg/h 4827 4827 426058 298214
Actual Volumetric Flow m³/h 8.6 8.6 809.7 566.6
Actual Density kg/m³ 561 561 526 526
Standard Specific Gravity 0.60 0.60 0.60 0.60
Dynamic Viscosity cP 0.12 0.12 0.12 0.12
Kinematic Viscosity cSt 0.22 0.22 0.23 0.23
Specific Enthalpy kcal/kg 24.6 24.6 43.6 43.6
Surface Tension mN/m 9.9 9.9 7.4 7.4
Specific Heat Capacity kcal/(kg°C) 0.57 0.57 0.65 0.65
Thermal Conductivity kcal/(h·m·°C) 0.088 0.088 0.078 0.078
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 1
Stream 6142 6143
Component (wt%)
Water 0.00 0.00
Hydrogen 0.00 0.00
Methane 0.00 0.00
Propylene 0.00 0.00
Propane 0.00 0.00
Propadiene 0.00 0.00
Isobutane 0.09 0.09
Isobutene 0.11 0.11
1-Butene 99.60 99.60
Butadiene 0.00 0.00
n-Butane 0.17 0.17
2-Butene 0.03 0.03
C5's 0.00 0.00
C6's 0.00 0.00
DIB 0.00 0.00
Methanol 0.00 0.00
TBA 0.00 0.00
DME 0.00 0.00
MTBE 0.00 0.00
MSBE 0.00 0.00
Vapor
Mass Flow rate kg/h 119487
Actual Volumetric Flow m³/h 4853
Molecular Weight 56.1
Actual Density kg/m³ 24.6
Viscosity cP 0.010
Specific Enthalpy kcal/kg 113.67
Specific Heat Capacity kcal/(kg°C) 0.49
Thermal Conductivity kcal/(h·m·°C) 0.017
Liquid
Mass Flow Rate kg/h 398289 278802
Actual Volumetric Flow m³/h 767.8 537.5
Actual Density kg/m³ 519 519
Standard Specific Gravity 0.60 0.60
Dynamic Viscosity cP 0.10 0.10
Kinematic Viscosity cSt 0.20 0.20
Specific Enthalpy kcal/kg 41.1 41.1
Surface Tension mN/m 6.6 6.6
Specific Heat Capacity kcal/(kg°C) 0.60 0.60
Thermal Conductivity kcal/(h·m·°C) 0.079 0.079
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 2
Stream 6001 6003 6004 6005
0 0 0
Stream Description MIXED WATER WASH WASTE WATER TOTAL WASTE
HYDROGENATED COLUMN TO WATER TO
C4S FROM OSBL BOTTOMS WASTE WATER WASTE WATER
PLANT OSBL PLANT OSBL
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.00 100.00 100.00 100
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.01 0.00 0.00 0.00
Propylene 0.01 0.00 0.00 0.00
Propane 0.08 0.00 0.00 0.00
Propadiene 0.03 0.00 0.00 0.00
Isobutane 18.96 0.00 0.00 0.00
Isobutene 29.08 0.00 0.00 0.00
1-Butene 18.67 0.00 0.00 0.00
Butadiene 0.00 0.00 0.00 0.00
n-Butane 18.79 0.00 0.00 0.00
2-Butene 14.00 0.00 0.00 0.00
C5's 0.37 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.00 0.00 0.00 0.00
TBA 0.00 0.00 0.00 0.00
DME 0.00 0.00 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 25719 7708 7708 7712
Actual Volumetric Flow m³/h 45.9 7.8 7.8 7.8
Actual Density kg/m³ 560 992 990 990
Standard Specific Gravity 0.59 1.00 1.00 1.00
Dynamic Viscosity cP 0.15 0.65 0.65 0.65
Kinematic Viscosity cSt 0.26 0.65 0.65 0.65
Specific Enthalpy kcal/kg 22.6 40.3 40.3 40.3
Surface Tension mN/m 9.9 69.5 69.5 69.5
Specific Heat Capacity kcal/(kg°C) 0.58 1.00 1.00 1.00
Thermal Conductivity kcal/(h·m·°C) 0.085 0.542 0.542 0.542
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 2
Stream 6006 6007 6008 6009
0 0 0 0
Stream Description WATER WASH FEED TO C4 FEED C4 FEED
COLUMN C4 FEED PUMP PUMP
OVERHEAD SURGE DRUM SUCTION DISCHARGE
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.03 0.03 0.03 0.03
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.01 0.01 0.01 0.01
Propylene 0.01 0.01 0.01 0.01
Propane 0.08 0.08 0.08 0.08
Propadiene 0.03 0.03 0.03 0.03
Isobutane 18.96 18.96 18.96 18.96
Isobutene 29.08 29.08 29.08 29.08
1-Butene 18.66 18.66 18.66 18.66
Butadiene 0.00 0.00 0.00 0.00
n-Butane 18.79 18.79 18.79 18.79
2-Butene 14.00 14.00 14.00 14.00
C5's 0.37 0.37 0.37 0.37
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.00 0.00 0.00 0.00
TBA 0.00 0.00 0.00 0.00
DME 0.00 0.00 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 25727 25727 25727 25727
Actual Volumetric Flow m³/h 45.8 45.9 45.9 46.0
Actual Density kg/m³ 561 561 561 559
Standard Specific Gravity 0.59 0.59 0.59 0.59
Dynamic Viscosity cP 0.15 0.15 0.15 0.15
Kinematic Viscosity cSt 0.26 0.26 0.26 0.26
Specific Enthalpy kcal/kg 22.5 22.5 22.5 23.3
Surface Tension mN/m 10.0 10.0 10.0 9.8
Specific Heat Capacity kcal/(kg°C) 0.58 0.58 0.58 0.59
Thermal Conductivity kcal/(h·m·°C) 0.085 0.085 0.085 0.084
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 2
Stream 6010 6011 6012 6013
0 0 0 0
Stream Description C4 FEED MIXED DEMINERALIZED DEMINERALIZED
PUMP C4s & MeOH WATER FROM WATER FEED
DISCHARGE OSBL TO WATER TO WATER
DOWNSTRM FV WASH COLUMN WASH COLUMN
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.03 0.04 100.00 100.00
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.01 0.01 0.00 0.00
Propylene 0.01 0.01 0.00 0.00
Propane 0.08 0.07 0.00 0.00
Propadiene 0.03 0.02 0.00 0.00
Isobutane 18.96 16.00 0.00 0.00
Isobutene 29.08 24.53 0.00 0.00
1-Butene 18.66 15.74 0.00 0.00
Butadiene 0.00 0.00 0.00 0.00
n-Butane 18.79 15.85 0.00 0.00
2-Butene 14.00 11.81 0.00 0.00
C5's 0.37 0.31 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.00 15.62 0.00 0.00
TBA 0.00 0.00 0.00 0.00
DME 0.00 0.00 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 25727 30493 7716 7716
Actual Volumetric Flow m³/h 46.0 52.4 7.8 7.8
Actual Density kg/m³ 559 582 990 990
Standard Specific Gravity 0.59 0.62 1.00 1.00
Dynamic Viscosity cP 0.15 0.20 0.65 0.65
Kinematic Viscosity cSt 0.26 0.34 0.66 0.66
Specific Enthalpy kcal/kg 23.3 24.4 40.0 40.0
Surface Tension mN/m 9.8 12.4 69.6 69.6
Specific Heat Capacity kcal/(kg°C) 0.59 0.60 1.00 1.00
Thermal Conductivity kcal/(h·m·°C) 0.084 0.089 0.541 0.541
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 2
Stream 6014 6015 6016 6017
0 0 0 0
Stream Description REACTOR PRIMARY PRIMARY SECONDARY
FEED REACTOR REACTOR REACTOR
PREHEATER FEED EFFLUENT FEED
OUTLET COOLER
INLET
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.04 0.04 0.04 0.04
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.01 0.01 0.01 0.01
Propylene 0.01 0.01 0.01 0.01
Propane 0.07 0.07 0.07 0.07
Propadiene 0.02 0.02 0.02 0.02
Isobutane 16.00 16.00 16.00 16.00
Isobutene 24.53 14.99 5.46 5.46
1-Butene 15.74 15.72 15.71 15.71
Butadiene 0.00 0.00 0.00 0.00
n-Butane 15.85 15.85 15.85 15.85
2-Butene 11.81 11.81 11.81 11.81
C5's 0.31 0.31 0.31 0.31
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.06 0.11 0.11
Methanol 15.62 10.17 4.72 4.72
TBA 0.00 0.05 0.09 0.09
DME 0.00 0.03 0.06 0.06
MTBE 0.00 14.84 29.68 29.68
MSBE 0.00 0.03 0.06 0.06
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 30493 60986 60986 30493
Actual Volumetric Flow m³/h 52.4 102.6 107.4 53.7
Actual Density kg/m³ 582 595 568 568
Standard Specific Gravity 0.62 0.63 0.64 0.64
Dynamic Viscosity cP 0.20 0.19 0.15 0.15
Kinematic Viscosity cSt 0.34 0.32 0.26 0.26
Specific Enthalpy kcal/kg 24.4 23.3 39.0 39.0
Surface Tension mN/m 12.4 12.5 9.5 9.5
Specific Heat Capacity kcal/(kg°C) 0.60 0.58 0.62 0.62
Thermal Conductivity kcal/(h·m·°C) 0.089 0.091 0.083 0.083
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 2
Stream 6018 6019 6020 6021
0 0 0 0
Stream Description SECONDARY SECONDARY SECONDARY INLET TO
REACTOR REACTOR REACTOR PRIMARY
FEED FEED EFFLUENT REACTOR
COOLER EFFLUENT
OUTLET COOLER
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.04 0.04 0.04 0.04
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.01 0.01 0.01 0.01
Propylene 0.01 0.01 0.01 0.01
Propane 0.07 0.07 0.07 0.07
Propadiene 0.02 0.02 0.02 0.02
Isobutane 16.00 16.00 16.00 16.00
Isobutene 5.46 5.46 2.46 5.46
1-Butene 15.71 15.71 15.69 15.71
Butadiene 0.00 0.00 0.00 0.00
n-Butane 15.85 15.85 15.85 15.85
2-Butene 11.81 11.81 11.81 11.81
C5's 0.31 0.31 0.31 0.31
C6's 0.00 0.00 0.00 0.00
DIB 0.11 0.11 0.11 0.11
Methanol 4.72 4.72 3.00 4.72
TBA 0.09 0.09 0.09 0.09
DME 0.06 0.06 0.06 0.06
MTBE 29.68 29.68 34.40 29.68
MSBE 0.06 0.06 0.08 0.06
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 30493 30493 30493 30493
Actual Volumetric Flow m³/h 50.2 50.2 50.9 53.7
Actual Density kg/m³ 608 608 600 568
Standard Specific Gravity 0.64 0.64 0.64 0.64
Dynamic Viscosity cP 0.19 0.19 0.17 0.15
Kinematic Viscosity cSt 0.31 0.31 0.29 0.26
Specific Enthalpy kcal/kg 21.8 21.8 26.7 39.0
Surface Tension mN/m 12.6 12.6 11.6 9.5
Specific Heat Capacity kcal/(kg°C) 0.57 0.57 0.58 0.62
Thermal Conductivity kcal/(h·m·°C) 0.092 0.092 0.089 0.083
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 2
Stream 6022 6023 6024 6025
0 0 0 0
Stream Description PRIMARY PRIMARY PRIMARY CD REACTION
REACTOR REACTOR REACTOR COLUMN
RECYCLE RECYCLE RECYCLE FEED
PUMP PUMP
SUCTION DISCHARGE
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.04 0.04 0.04 0.04
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.01 0.01 0.01 0.01
Propylene 0.01 0.01 0.01 0.01
Propane 0.07 0.07 0.07 0.07
Propadiene 0.02 0.02 0.02 0.02
Isobutane 16.00 16.00 16.00 16.00
Isobutene 5.46 5.46 5.46 2.46
1-Butene 15.71 15.71 15.71 15.69
Butadiene 0.00 0.00 0.00 0.00
n-Butane 15.85 15.85 15.85 15.85
2-Butene 11.81 11.81 11.81 11.81
C5's 0.31 0.31 0.31 0.31
C6's 0.00 0.00 0.00 0.00
DIB 0.11 0.11 0.11 0.11
Methanol 4.72 4.72 4.72 3.00
TBA 0.09 0.09 0.09 0.09
DME 0.06 0.06 0.06 0.06
MTBE 29.68 29.68 29.68 34.40
MSBE 0.06 0.06 0.06 0.08
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 30493 30493 30493 30493
Actual Volumetric Flow m³/h 50.2 50.2 50.2 53.5
Actual Density kg/m³ 608 607 607 570
Standard Specific Gravity 0.64 0.64 0.64 0.64
Dynamic Viscosity cP 0.19 0.19 0.19 0.15
Kinematic Viscosity cSt 0.31 0.31 0.31 0.26
Specific Enthalpy kcal/kg 21.8 22.1 22.1 39.2
Surface Tension mN/m 12.6 12.6 12.6 9.3
Specific Heat Capacity kcal/(kg°C) 0.57 0.57 0.57 0.61
Thermal Conductivity kcal/(h·m·°C) 0.092 0.092 0.092 0.083
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 2
Stream 6026 6027 6028 6029
0 0 0 0
Stream Description CD REACTION MTBE MTBE MTBE
COLUMN PRODUCT PRODUCT PRODUCT
BOTTOMS COOLER COOLER TO OSBL
INLET OUTLET
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.00 0.00 0.00 0.00
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.00 0.00 0.00 0.00
Propylene 0.00 0.00 0.00 0.00
Propane 0.00 0.00 0.00 0.00
Propadiene 0.00 0.00 0.00 0.00
Isobutane 0.00 0.00 0.00 0.00
Isobutene 0.00 0.00 0.00 0.00
1-Butene 0.00 0.00 0.00 0.00
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.03 0.03 0.03 0.03
2-Butene 0.07 0.07 0.07 0.07
C5's 0.80 0.80 0.80 0.80
C6's 0.00 0.00 0.00 0.00
DIB 0.29 0.29 0.29 0.29
Methanol 0.10 0.10 0.10 0.10
TBA 0.26 0.26 0.26 0.26
DME 0.00 0.00 0.00 0.00
MTBE 98.09 98.09 98.09 98.09
MSBE 0.36 0.36 0.36 0.36
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 11877 11877 11877 11877
Actual Volumetric Flow m³/h 19.9 17.7 16.7 16.7
Actual Density kg/m³ 598 671 713 713
Standard Specific Gravity 0.74 0.74 0.74 0.74
Dynamic Viscosity cP 0.13 0.20 0.27 0.27
Kinematic Viscosity cSt 0.22 0.29 0.38 0.38
Specific Enthalpy kcal/kg 74.3 42.4 22.7 22.7
Surface Tension mN/m 7.1 12.8 16.9 16.9
Specific Heat Capacity kcal/(kg°C) 0.62 0.57 0.53 0.53
Thermal Conductivity kcal/(h·m·°C) 0.101 0.101 0.104 0.104
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 2
Stream 6030 6031 6032 6033
0 0 0 0
Stream Description CD REACTION CD REACTION FEED TO CD REACTION
COLUMN COLUMN CD REACTION COLUMN
OVERHEAD CONDENSER COLUMN REFLUX PUMP
OUTLET OVERHEAD SUCTION
DRUM
0 0 0 0
Stream Phase VAPOR LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.09 0.09 0.09 0.09
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.01 0.01 0.01 0.01
Propylene 0.01 0.01 0.01 0.01
Propane 0.11 0.11 0.11 0.11
Propadiene 0.04 0.04 0.04 0.04
Isobutane 25.78 25.78 25.78 25.78
Isobutene 0.04 0.04 0.04 0.04
1-Butene 25.28 25.28 25.28 25.28
Butadiene 0.00 0.00 0.00 0.00
n-Butane 25.54 25.54 25.54 25.54
2-Butene 18.94 18.94 18.94 18.94
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 4.00 4.00 4.00 4.00
TBA 0.00 0.00 0.00 0.00
DME 0.16 0.16 0.16 0.16
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h 43506
Actual Volumetric Flow m³/h 2528
Molecular Weight 55.3
Actual Density kg/m³ 17.2
Viscosity cP 0.009
Specific Enthalpy kcal/kg 118.78
Specific Heat Capacity kcal/(kg°C) 0.45
Thermal Conductivity kcal/(h·m·°C) 0.016
Liquid
Mass Flow Rate kg/h 43506 43506 43506
Actual Volumetric Flow m³/h 78.9 78.9 78.9
Actual Density kg/m³ 552 552 552
Standard Specific Gravity 0.00 0.60 0.60 0.60
Dynamic Viscosity cP 0.14 0.14 0.14
Kinematic Viscosity cSt 0.26 0.26 0.26
Specific Enthalpy kcal/kg 28.3 28.3 28.3
Surface Tension mN/m 9.8 9.8 9.8
Specific Heat Capacity kcal/(kg°C) 0.61 0.61 0.61
Thermal Conductivity kcal/(h·m·°C) 0.084 0.084 0.084
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 2
Stream 6034 6035 6036 6037
0 0 0 0
Stream Description CD REACTION CD REACTION CD REACTION MEOH EXT.
COLUMN COLUMN COLUMN COLUMN
REFLUX PUMP REFLUX REFLUX AT FEED
DISCHARGE COLUMN FEED COOLER
INLET
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.09 0.09 0.09 0.09
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.01 0.01 0.01 0.01
Propylene 0.01 0.01 0.01 0.01
Propane 0.11 0.11 0.11 0.11
Propadiene 0.04 0.04 0.04 0.04
Isobutane 25.78 25.78 25.78 25.78
Isobutene 0.04 0.04 0.04 0.04
1-Butene 25.28 25.28 25.28 25.28
Butadiene 0.00 0.00 0.00 0.00
n-Butane 25.54 25.54 25.54 25.54
2-Butene 18.94 18.94 18.94 18.94
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 4.00 4.00 4.00 4.00
TBA 0.00 0.00 0.00 0.00
DME 0.16 0.16 0.16 0.16
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 43506 24590 24590 18916
Actual Volumetric Flow m³/h 79.0 44.7 44.7 34.4
Actual Density kg/m³ 550 550 550 550
Standard Specific Gravity 0.60 0.60 0.60 0.60
Dynamic Viscosity cP 0.14 0.14 0.14 0.14
Kinematic Viscosity cSt 0.26 0.26 0.26 0.26
Specific Enthalpy kcal/kg 28.8 28.8 28.8 28.8
Surface Tension mN/m 9.7 9.7 9.7 9.7
Specific Heat Capacity kcal/(kg°C) 0.61 0.61 0.61 0.61
Thermal Conductivity kcal/(h·m·°C) 0.083 0.083 0.083 0.083
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 2
Stream 6038 6039 6040 6041
0 0 0 0
Stream Description C4 DISTILLATE METHANOL METHANOL METHANOL
TO METHANOL EXTRACTION REC. COL. RECOVERY
EXTRACTION COLUMN FEED/BTMS COLUMN
COLUMN BOTTOMS EXCHANGER FEED
INLET
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.09 80.00 80.00 80.00
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.01 0.00 0.00 0.00
Propylene 0.01 0.00 0.00 0.00
Propane 0.11 0.00 0.00 0.00
Propadiene 0.04 0.00 0.00 0.00
Isobutane 25.78 0.00 0.00 0.00
Isobutene 0.04 0.00 0.00 0.00
1-Butene 25.28 0.00 0.00 0.00
Butadiene 0.00 0.00 0.00 0.00
n-Butane 25.54 0.00 0.00 0.00
2-Butene 18.94 0.00 0.00 0.00
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 4.00 20.00 20.00 20.00
TBA 0.00 0.00 0.00 0.00
DME 0.16 0.00 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 18916 3784 3784 3784
Actual Volumetric Flow m³/h 33.5 4.0 4.0 4.1
Actual Density kg/m³ 565 938 938 915
Standard Specific Gravity 0.60 0.95 0.95 0.95
Dynamic Viscosity cP 0.16 0.62 0.62 0.37
Kinematic Viscosity cSt 0.28 0.66 0.66 0.40
Specific Enthalpy kcal/kg 22.5 36.8 36.8 69.4
Surface Tension mN/m 10.9 63.6 63.6 58.2
Specific Heat Capacity kcal/(kg°C) 0.59 0.92 0.92 0.94
Thermal Conductivity kcal/(h·m·°C) 0.087 0.320 0.320 0.315
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 2
Stream 6042 6043 6044 6045
0 0 0
Stream Description METHANOL C4s TO METHANOL METHANOL
EXTRACTION B-1 RECOVERY RECOVERY
COLUMN HEAVIES COLUMN COLUMN
OVERHEAD COLUMN BOTTOMS BOTTOMS PUMP
DISCHARGE
0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0
Component (wt%) 0 0 0
Water 0.03 0.03 100.00 100.00
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.01 0.01 0.00 0.00
Propylene 0.01 0.01 0.00 0.00
Propane 0.11 0.11 0.00 0.00
Propadiene 0.04 0.04 0.00 0.00
Isobutane 26.87 26.87 0.00 0.00
Isobutene 0.04 0.04 0.00 0.00
1-Butene 26.35 26.35 0.00 0.00
Butadiene 0.00 0.00 0.00 0.00
n-Butane 26.62 26.62 0.00 0.00
2-Butene 19.75 19.75 0.00 0.00
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.00 0.00 0.00 0.00
TBA 0.00 0.00 0.00 0.00
DME 0.17 0.17 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 18148 18148 3016 3016
Actual Volumetric Flow m³/h 32.5 32.5 3.2 3.2
Actual Density kg/m³ 558 559 939 939
Standard Specific Gravity 0.59 1.00 1.00
Dynamic Viscosity cP 0.14 0.14 0.22 0.22
Kinematic Viscosity cSt 0.25 0.25 0.23 0.23
Specific Enthalpy kcal/kg 22.4 22.4 126.6 126.7
Surface Tension mN/m 10.0 10.2 54.0 54.0
Specific Heat Capacity kcal/(kg°C) 0.59 0.59 1.02 1.02
Thermal Conductivity kcal/(h·m·°C) 0.085 0.085 0.592 0.591
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 2
Stream 6046 6047 6048 6049
0 0 0 0
Stream Description RECYCLE RECYCLE RECYCLE METHANOL
WATER WATER WATER TO RECOVERY
COOLER COOLER METHANOL COLUMN
INLET OUTLET EXTRACTION OVERHEAD
COLUMN
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID VAPOR
0 0 0 0
Component (wt%) 0 0 0 0
Water 100.00 100.00 100.00 0.05
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.00 0.00 0.00 0.00
Propylene 0.00 0.00 0.00 0.00
Propane 0.00 0.00 0.00 0.00
Propadiene 0.00 0.00 0.00 0.00
Isobutane 0.00 0.00 0.00 0.00
Isobutene 0.00 0.00 0.00 0.00
1-Butene 0.00 0.00 0.00 0.00
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.00 0.00 0.00 0.00
2-Butene 0.00 0.00 0.00 0.00
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.00 0.00 0.00 99.95
TBA 0.00 0.00 0.00 0.00
DME 0.00 0.00 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h 2271
Actual Volumetric Flow m³/h 1178
Molecular Weight 32.0
Actual Density kg/m³ 1.9
Viscosity cP 0.012
Specific Enthalpy kcal/kg 312.51
Specific Heat Capacity kcal/(kg°C) 0.37
Thermal Conductivity kcal/(h·m·°C) 0.018
Liquid
Mass Flow Rate kg/h 3016 3016 3016
Actual Volumetric Flow m³/h 3.1 3.0 3.0
Actual Density kg/m³ 967 990 990
Standard Specific Gravity 1.00 1.00 1.00 0.00
Dynamic Viscosity cP 0.33 0.65 0.65
Kinematic Viscosity cSt 0.34 0.66 0.66
Specific Enthalpy kcal/kg 85.8 40.0 40.0
Surface Tension mN/m 62.0 69.6 69.6
Specific Heat Capacity kcal/(kg°C) 1.00 1.00 1.00
Thermal Conductivity kcal/(h·m·°C) 0.577 0.541 0.541
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 2
Stream 6050 6051 6052 6053
0 0 0 0
Stream Description METHANOL METHANOL METHANOL METHANOL
RECOVERY RECOVERY RECOVERY RECOVERY
COLUMN COLUMN COLUMN COLUMN
CONDENSER OVHD DRUM REFLUX PUMP REFLUX PUMP
OUTLET INLET SUCTION DISCHARGE
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.05 0.05 0.08 0.08
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.00 0.00 0.00 0.00
Propylene 0.00 0.00 0.00 0.00
Propane 0.00 0.00 0.00 0.00
Propadiene 0.00 0.00 0.00 0.00
Isobutane 0.00 0.00 0.00 0.00
Isobutene 0.00 0.00 0.00 0.00
1-Butene 0.00 0.00 0.00 0.00
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.00 0.00 0.00 0.00
2-Butene 0.00 0.00 0.00 0.00
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 99.95 99.95 99.92 99.92
TBA 0.00 0.00 0.00 0.00
DME 0.00 0.00 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 2271 2271 6580 6580
Actual Volumetric Flow m³/h 3.0 3.0 8.6 8.6
Actual Density kg/m³ 750 750 766 765
Standard Specific Gravity 0.80 0.80 0.80 0.80
Dynamic Viscosity cP 0.35 0.35 0.41 0.40
Kinematic Viscosity cSt 0.46 0.46 0.53 0.52
Specific Enthalpy kcal/kg 39.8 39.8 29.4 30.3
Surface Tension mN/m 18.9 18.9 20.3 20.2
Specific Heat Capacity kcal/(kg°C) 0.67 0.67 0.64 0.65
Thermal Conductivity kcal/(h·m·°C) 0.162 0.162 0.166 0.166
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 2
Stream 6054 6055 6056 6057
0 0 0 0
Stream Description METHANOL METHANOL METHANOL RECYCLE
RECOVERY RECOVERY TO MTBE METHANOL
COLUMN COLUMN REACTION TO C4s
REFLUX REFLUX AT SECTION STREAM
COLUMN FEED
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.08 0.08 0.08 0.08
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.00 0.00 0.00 0.00
Propylene 0.00 0.00 0.00 0.00
Propane 0.00 0.00 0.00 0.00
Propadiene 0.00 0.00 0.00 0.00
Isobutane 0.00 0.00 0.00 0.00
Isobutene 0.00 0.00 0.00 0.00
1-Butene 0.00 0.00 0.00 0.00
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.00 0.00 0.00 0.00
2-Butene 0.00 0.00 0.00 0.00
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 99.92 99.92 99.92 99.92
TBA 0.00 0.00 0.00 0.00
DME 0.00 0.00 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 1514 1514 5066 4766
Actual Volumetric Flow m³/h 2.0 2.0 6.6 6.2
Actual Density kg/m³ 765 765 765 765
Standard Specific Gravity 0.80 0.80 0.80 0.80
Dynamic Viscosity cP 0.40 0.40 0.40 0.40
Kinematic Viscosity cSt 0.52 0.52 0.52 0.52
Specific Enthalpy kcal/kg 30.3 30.3 30.3 30.3
Surface Tension mN/m 20.2 20.2 20.2 20.2
Specific Heat Capacity kcal/(kg°C) 0.65 0.65 0.65 0.65
Thermal Conductivity kcal/(h·m·°C) 0.166 0.166 0.166 0.166
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 2
Stream 6058 6059 6060 6061
0 0 0
Stream Description RECYCLE METHANOL METHANOL METHANOL
METHANOL INJECTION TO INJECTION TO INJECTION TO
TO C4s CD REACTION CD REACTION CD REACTION
STREAM COLUMN COLUMN COLUMN
0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.08 0.08 0.08 0.08
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.00 0.00 0.00 0.00
Propylene 0.00 0.00 0.00 0.00
Propane 0.00 0.00 0.00 0.00
Propadiene 0.00 0.00 0.00 0.00
Isobutane 0.00 0.00 0.00 0.00
Isobutene 0.00 0.00 0.00 0.00
1-Butene 0.00 0.00 0.00 0.00
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.00 0.00 0.00 0.00
2-Butene 0.00 0.00 0.00 0.00
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 99.92 99.92 99.92 99.92
TBA 0.00 0.00 0.00 0.00
DME 0.00 0.00 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 4766 300 15 285
Actual Volumetric Flow m³/h 6.2 0.4 0.0 0.4
Actual Density kg/m³ 765 765 765 765
Standard Specific Gravity 0.80 0.80 0.80 0.80
Dynamic Viscosity cP 0.40 0.40 0.40 0.40
Kinematic Viscosity cSt 0.52 0.52 0.52 0.52
Specific Enthalpy kcal/kg 30.3 30.3 30.3 30.3
Surface Tension mN/m 20.2 20.2 20.2 20.2
Specific Heat Capacity kcal/(kg°C) 0.65 0.65 0.65 0.65
Thermal Conductivity kcal/(h·m·°C) 0.166 0.166 0.166 0.166
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 2
Stream 6062 6063 6064 6065
0 0 0
Stream Description FRESH FILTERED FILTERED CD REACTION
METHANOL FRESH FRESH COLUMN
FROM METHANOL METHANOL REBOILER
STORAGE AT INLET
OSBL
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.10 0.10 0.10 0.00
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.00 0.00 0.00 0.00
Propylene 0.00 0.00 0.00 0.00
Propane 0.00 0.00 0.00 0.00
Propadiene 0.00 0.00 0.00 0.00
Isobutane 0.00 0.00 0.00 0.00
Isobutene 0.00 0.00 0.00 0.00
1-Butene 0.00 0.00 0.00 0.00
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.00 0.00 0.00 0.03
2-Butene 0.00 0.00 0.00 0.07
C5's 0.00 0.00 0.00 0.80
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.29
Methanol 99.90 99.90 99.90 0.10
TBA 0.00 0.00 0.00 0.26
DME 0.00 0.00 0.00 0.00
MTBE 0.00 0.00 0.00 98.09
MSBE 0.00 0.00 0.00 0.36
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 4309 4309 4309 222076
Actual Volumetric Flow m³/h 5.6 5.6 5.6 371.6
Actual Density kg/m³ 775 775 775 598
Standard Specific Gravity 0.80 0.80 0.80 0.74
Dynamic Viscosity cP 0.40 0.40 0.40 0.13
Kinematic Viscosity cSt 0.58 0.58 0.58 0.22
Specific Enthalpy kcal/kg 24.0 24.0 24.0 74.3
Surface Tension mN/m 21.1 21.1 21.1 7.1
Specific Heat Capacity kcal/(kg°C) 0.63 0.63 0.63 0.62
Thermal Conductivity kcal/(h·m·°C) 0.166 0.166 0.166 0.101
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 2
Stream 6066 6067 6068 6099
0 0 0
Stream Description CD REACTION METHANOL METHANOL C4 DISTILLATE
COLUMN RECOVERY RECOVERY TO METHANOL
REBOILER COLUMN COLUMN EXTRACTION
OUTLET REBOILER REBOILER COLUMN
INLET OUTLET
0 0 0 0
Stream Phase MIXED LIQUID MIXED LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.00 99.99 99.99 0.09
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.00 0.00 0.00 0.01
Propylene 0.00 0.00 0.00 0.01
Propane 0.00 0.00 0.00 0.11
Propadiene 0.00 0.00 0.00 0.04
Isobutane 0.00 0.00 0.00 25.78
Isobutene 0.00 0.00 0.00 0.04
1-Butene 0.00 0.00 0.00 25.28
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.03 0.00 0.00 25.54
2-Butene 0.07 0.00 0.00 18.94
C5's 0.80 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.29 0.00 0.00 0.00
Methanol 0.10 0.01 0.01 4.00
TBA 0.26 0.00 0.00 0.00
DME 0.00 0.00 0.00 0.16
MTBE 98.09 0.00 0.00 0.00
MSBE 0.36 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h 66406 1505
Actual Volumetric Flow m³/h 2687.0 1162.0
Molecular Weight 87.5 18.0
Actual Density kg/m³ 24.7 1.3
Viscosity cP 0.010 0.013
Specific Enthalpy kcal/kg 135.26 649.19
Specific Heat Capacity kcal/(kg°C) 0.50 0.46
Thermal Conductivity kcal/(h·m·°C) 0.021 0.023
Liquid
Mass Flow Rate kg/h 155670 4992 3487 18916
Actual Volumetric Flow m³/h 260.3 5.3 3.7 33.5
Actual Density kg/m³ 598 939 939 565
Standard Specific Gravity 0.74 1.00 1.00 0.60
Dynamic Viscosity cP 0.13 0.22 0.22 0.16
Kinematic Viscosity cSt 0.22 0.23 0.23 0.28
Specific Enthalpy kcal/kg 74.2 126.3 125.6 22.5
Surface Tension mN/m 7.2 54.1 54.2 10.9
Specific Heat Capacity kcal/(kg°C) 0.62 1.02 1.02 0.59
Thermal Conductivity kcal/(h·m·°C) 0.101 0.591 0.591 0.087
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 2
Stream 0
Stream Description
Stream Phase 0
0
Component (wt%) 0
Water 0.00
Hydrogen 0.00
Methane 0.00
Propylene 0.00
Propane 0.00
Propadiene 0.00
Isobutane 0.00
Isobutene 0.00
1-Butene 0.00
Butadiene 0.00
n-Butane 0.00
2-Butene 0.00
C5's 0.00
C6's 0.00
DIB 0.00
Methanol 0.00
TBA 0.00
DME 0.00
MTBE 0.00
MSBE 0.00
0.00
0.00
Mass Flow Rate kg/h 0
Molar Flow Rate kg mol/hr 0.0
Molecular Weight 0.0
Temperature °C 0.0
Stream Pressure bar (g) 0.0
Stream Enthalpy MMkcal/h 0.000
Weight Fraction Liquid 0.00
Critical Temperature °C 0.0
Critical Pressure bar (a) 0.0
Vapor 0.0
Mass Flow rate kg/h 0
Actual Volumetric Flow m³/h 0
Molecular Weight 0.00
Actual Density kg/m³ 0.00
Viscosity cP 0.0000
Specific Enthalpy kcal/kg 0.0
Specific Heat Capacity kcal/(kg°C) 0.000
Thermal Conductivity kcal/(h·m·°C) 0.0000
0.000
Liquid 0.0
Mass Flow Rate kg/h 0
Actual Volumetric Flow m³/h 0.0
Actual Density kg/m³ 0.0
Standard Specific Gravity 0.000
Dynamic Viscosity cP 0.000
Kinematic Viscosity cSt
Specific Enthalpy kcal/kg 0.0
Surface Tension mN/m 0.0
Specific Heat Capacity kcal/(kg°C) 0.000
Thermal Conductivity kcal/(h·m·°C) 0.000
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 2
Stream 6101 6102 6103 6104
Stream Description B-1 HEAVIES B-1 HEAVIES B-1 HEAVIES B-1 HEAVIES
COLUMN #1 COLUMN COLUMN #2 COLUMN #2
BOTTOMS TRANSFER FEED OVERHEAD
PUMP DISCH.
Component (wt%)
Water 0.00 0.00 0.00 0.00
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.00 0.00 0.00 0.00
Propylene 0.00 0.00 0.00 0.00
Propane 0.01 0.01 0.01 0.03
Propadiene 0.01 0.01 0.01 0.01
Isobutane 17.22 17.22 17.22 19.69
Isobutene 0.05 0.05 0.05 0.06
1-Butene 43.30 43.30 43.30 43.67
Butadiene 0.00 0.00 0.00 0.00
n-Butane 25.34 25.34 25.34 23.49
2-Butene 14.04 14.04 14.04 13.01
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.00 0.00 0.00 0.00
TBA 0.00 0.00 0.00 0.00
DME 0.02 0.02 0.02 0.05
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h 130908
Actual Volumetric Flow m³/h 6606
Molecular Weight 56.9
Actual Density kg/m³ 19.8
Viscosity cP 0.009
Specific Enthalpy kcal/kg 111.42
Specific Heat Capacity kcal/(kg°C) 0.49
Thermal Conductivity kcal/(h·m·°C) 0.017
Liquid
Mass Flow Rate kg/h 121306 121306 121306
Actual Volumetric Flow m³/h 230.5 230.2 230.5
Actual Density kg/m³ 526 527 526
Standard Specific Gravity 0.59 0.59 0.59 0.00
Dynamic Viscosity cP 0.12 0.11 0.12
Kinematic Viscosity cSt 0.22 0.22 0.22
Specific Enthalpy kcal/kg 37.0 37.3 37.0
Surface Tension mN/m 7.5 7.5 7.5
Specific Heat Capacity kcal/(kg°C) 0.62 0.62 0.62
Thermal Conductivity kcal/(h·m·°C) 0.079 0.079 0.079
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 2
Stream 6105 6106 6107 6108
Component (wt%)
Water 0.05 0.05 0.05
Hydrogen 0.00 0.00 0.00
Methane 0.02 0.02 0.02
Propylene 0.02 0.02 0.02
Propane 0.21 0.21 0.21
Propadiene 0.08 0.08 0.08
Isobutane 50.79 50.79 50.79
Isobutene 0.08 0.08 0.08
1-Butene 48.31 48.31 48.31
Butadiene 0.00 0.00 0.00
n-Butane 0.09 0.09 0.09
2-Butene 0.03 0.03 0.03
C5's 0.00 0.00 0.00
C6's 0.00 0.00 0.00
DIB 0.00 0.00 0.00
Methanol 0.00 0.00 0.00
TBA 0.00 0.00 0.00
DME 0.32 0.32 0.32
MTBE 0.00 0.00 0.00
MSBE 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h 121284
Actual Volumetric Flow m³/h 6585
Molecular Weight 56.9
Actual Density kg/m³ 18.4
Viscosity cP 0.008
Specific Enthalpy kcal/kg 107.20
Specific Heat Capacity kcal/(kg°C) 0.45
Thermal Conductivity kcal/(h·m·°C) 0.016
Liquid
Mass Flow Rate kg/h 121284 121284
Actual Volumetric Flow m³/h 224.5 224.5
Actual Density kg/m³ 540 540
Standard Specific Gravity 0.00 0.58 0.58
Dynamic Viscosity cP 0.13 0.13
Kinematic Viscosity cSt 0.24 0.24
Specific Enthalpy kcal/kg 26.0 26.0
Surface Tension mN/m 8.8 8.8
Specific Heat Capacity kcal/(kg°C) 0.60 0.60
Thermal Conductivity kcal/(h·m·°C) 0.081 0.081
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 2
Stream 6109 6110 6111 6112
Component (wt%)
Water 0.05 0.05 0.05
Hydrogen 0.00 0.00 0.00
Methane 0.02 0.02 0.02
Propylene 0.02 0.02 0.02
Propane 0.21 0.21 0.21
Propadiene 0.08 0.08 0.08
Isobutane 50.79 50.79 50.79
Isobutene 0.08 0.08 0.08
1-Butene 48.31 48.31 48.31
Butadiene 0.00 0.00 0.00
n-Butane 0.09 0.09 0.09
2-Butene 0.03 0.03 0.03
C5's 0.00 0.00 0.00
C6's 0.00 0.00 0.00
DIB 0.00 0.00 0.00
Methanol 0.00 0.00 0.00
TBA 0.00 0.00 0.00
DME 0.32 0.32 0.32
MTBE 0.00 0.00 0.00
MSBE 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 121284 121284 111682
Actual Volumetric Flow m³/h 224.5 224.3 206.6
Actual Density kg/m³ 540 541 541
Standard Specific Gravity 0.58 0.58 0.58
Dynamic Viscosity cP 0.13 0.13 0.13
Kinematic Viscosity cSt 0.24 0.24 0.24
Specific Enthalpy kcal/kg 26.0 26.3 26.3
Surface Tension mN/m 8.8 8.7 8.7
Specific Heat Capacity kcal/(kg°C) 0.60 0.60 0.60
Thermal Conductivity kcal/(h·m·°C) 0.081 0.081 0.081
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 2
Stream 6113 6114 6115 6116
Stream Description B-1 HEAVIES B-1 HEAVIES B-1 HEAVIES B-1 HEAVIES
COLUMN COLUMN COLUMN COLUMN #2
REFLUX AT OVERHEAD TO OVERHEAD TO BOTTOMS
COLUMN FEED B-1 LIGHTS B-1 LIGHTS
COLUMN COLUMN
Component (wt%)
Water 0.05 0.05 0.05 0.00
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.02 0.02 0.02 0.00
Propylene 0.02 0.02 0.02 0.00
Propane 0.21 0.21 0.21 0.00
Propadiene 0.08 0.08 0.08 0.00
Isobutane 50.79 50.79 50.79 0.00
Isobutene 0.08 0.08 0.08 0.00
1-Butene 48.31 48.31 48.31 1.68
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.09 0.09 0.09 56.42
2-Butene 0.03 0.03 0.03 41.89
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.00 0.00 0.00 0.00
TBA 0.00 0.00 0.00 0.00
DME 0.32 0.32 0.32 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 111682 9601 9601 8546
Actual Volumetric Flow m³/h 207.0 17.8 17.8 16.3
Actual Density kg/m³ 540 541 540 523
Standard Specific Gravity 0.58 0.58 0.60
Dynamic Viscosity cP 0.13 0.13 0.13 0.12
Kinematic Viscosity cSt 0.24 0.24 0.24 0.22
Specific Enthalpy kcal/kg 26.3 26.3 26.3 43.5
Surface Tension mN/m 8.7 8.7 8.7 7.3
Specific Heat Capacity kcal/(kg°C) 0.60 0.60 0.60 0.65
Thermal Conductivity kcal/(h·m·°C) 0.081 0.081 0.081 0.078
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 2
Stream 6117 6118 6119 6120
Component (wt%)
Water 0.00 0.00 0.00 0.00
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.00 0.00 0.00 0.00
Propylene 0.00 0.00 0.00 0.00
Propane 0.00 0.00 0.00 0.00
Propadiene 0.00 0.00 0.00 0.00
Isobutane 0.00 0.00 0.00 31.54
Isobutene 0.00 0.00 0.00 0.18
1-Butene 1.68 1.68 1.68 68.24
Butadiene 0.00 0.00 0.00 0.00
n-Butane 56.42 56.42 56.42 0.02
2-Butene 41.89 41.89 41.89 0.01
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.00 0.00 0.00 0.00
TBA 0.00 0.00 0.00 0.00
DME 0.00 0.00 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 8546 8546 8546 239688
Actual Volumetric Flow m³/h 16.3 15.2 15.2 461.0
Actual Density kg/m³ 524 564 564 520
Standard Specific Gravity 0.60 0.60 0.60 0.59
Dynamic Viscosity cP 0.12 0.14 0.14 0.11
Kinematic Viscosity cSt 0.22 0.25 0.25 0.21
Specific Enthalpy kcal/kg 43.5 25.5 25.5 37.0
Surface Tension mN/m 7.3 10.5 10.5 7.0
Specific Heat Capacity kcal/(kg°C) 0.65 0.60 0.60 0.61
Thermal Conductivity kcal/(h·m·°C) 0.078 0.087 0.087 0.077
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 2
Stream 6121 6122 6123 6124
Stream Description B-1 LIGHTS B-1 LIGHTS B-1 LIGHTS B-1 LIGHTS
COLUMN COLUMN #2 COLUMN #2 COLUMN #1
TRANSFER FEED OVERHEAD OVERHEAD
PUMP DISCH.
Component (wt%)
Water 0.00 0.00 0.00 0.04
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.00 0.00 0.00 0.04
Propylene 0.00 0.00 0.00 0.04
Propane 0.00 0.00 0.00 0.39
Propadiene 0.00 0.00 0.00 0.14
Isobutane 31.54 31.54 32.13 94.24
Isobutene 0.18 0.18 0.19 0.04
1-Butene 68.24 68.24 67.65 4.48
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.02 0.02 0.02 0.00
2-Butene 0.01 0.01 0.01 0.00
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.00 0.00 0.00 0.01
TBA 0.00 0.00 0.00 0.00
DME 0.00 0.00 0.00 0.59
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h 235264 217529
Actual Volumetric Flow m³/h 10728 10361
Molecular Weight 56.7 57.7
Actual Density kg/m³ 21.9 21.0
Viscosity cP 0.009 0.008
Specific Enthalpy kcal/kg 109.49 104.79
Specific Heat Capacity kcal/(kg°C) 0.49 0.47
Thermal Conductivity kcal/(h·m·°C) 0.017 0.017
Liquid
Mass Flow Rate kg/h 239688 239688
Actual Volumetric Flow m³/h 460.4 461.1
Actual Density kg/m³ 521 520
Standard Specific Gravity 0.59 0.59 0.00 0.00
Dynamic Viscosity cP 0.11 0.11
Kinematic Viscosity cSt 0.21 0.21
Specific Enthalpy kcal/kg 37.3 37.0
Surface Tension mN/m 6.9 7.0
Specific Heat Capacity kcal/(kg°C) 0.62 0.62
Thermal Conductivity kcal/(h·m·°C) 0.077 0.077
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 2
Stream 6125 6126 6127 6128
Component (wt%)
Water 0.04 0.04 100.00 100.00
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.04 0.04 0.00 0.00
Propylene 0.04 0.04 0.00 0.00
Propane 0.39 0.39 0.00 0.00
Propadiene 0.14 0.14 0.00 0.00
Isobutane 94.24 94.24 0.00 0.00
Isobutene 0.04 0.04 0.00 0.00
1-Butene 4.48 4.48 0.00 0.00
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.00 0.00 0.00 0.00
2-Butene 0.00 0.00 0.00 0.00
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.01 0.01 0.00 0.00
TBA 0.00 0.00 0.00 0.00
DME 0.59 0.59 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 217529 217529 4 4
Actual Volumetric Flow m³/h 414.6 414.6 0.0 0.0
Actual Density kg/m³ 525 525 990 990
Standard Specific Gravity 0.57 0.57 1.00 1.00
Dynamic Viscosity cP 0.14 0.14 0.58 0.58
Kinematic Viscosity cSt 0.26 0.26 0.59 0.59
Specific Enthalpy kcal/kg 26.6 26.6 46.0 46.0
Surface Tension mN/m 7.8 7.8 70.0 70.0
Specific Heat Capacity kcal/(kg°C) 0.62 0.62 1.00 1.00
Thermal Conductivity kcal/(h·m·°C) 0.076 0.076 0.547 0.547
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 2
Stream 6129 6130 6131 6132
Stream Description B-1 LIGHTS B-1 LIGHTS B-1 LIGHTS B-1 LIGHTS
COLUMN COLUMN COLUMN COLUMN
REFLUX PUMP REFLUX PUMP REFLUX REFLUX AT
SUCTION DISCHARGE COLUMN FEED
Component (wt%)
Water 0.04 0.04 0.04 0.04
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.04 0.04 0.04 0.04
Propylene 0.04 0.04 0.04 0.04
Propane 0.39 0.39 0.39 0.39
Propadiene 0.14 0.14 0.14 0.14
Isobutane 94.24 94.24 94.24 94.24
Isobutene 0.04 0.04 0.04 0.04
1-Butene 4.48 4.48 4.48 4.48
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.00 0.00 0.00 0.00
2-Butene 0.00 0.00 0.00 0.00
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.01 0.01 0.01 0.01
TBA 0.00 0.00 0.00 0.00
DME 0.59 0.59 0.59 0.59
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 217525 217525 212351 212351
Actual Volumetric Flow m³/h 414.6 413.6 403.8 405.7
Actual Density kg/m³ 525 526 526 523
Standard Specific Gravity 0.57 0.57 0.57 0.57
Dynamic Viscosity cP 0.14 0.14 0.14 0.14
Kinematic Viscosity cSt 0.26 0.26 0.26 0.26
Specific Enthalpy kcal/kg 26.6 27.2 27.2 27.2
Surface Tension mN/m 7.8 7.7 7.7 7.7
Specific Heat Capacity kcal/(kg°C) 0.62 0.62 0.62 0.62
Thermal Conductivity kcal/(h·m·°C) 0.076 0.076 0.076 0.076
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 2
Stream 6133 6135 6136 6137
Component (wt%)
Water 0.04 0.04 0.00 0.00
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.04 0.04 0.00 0.00
Propylene 0.04 0.04 0.00 0.00
Propane 0.39 0.39 0.00 0.00
Propadiene 0.14 0.14 0.00 0.00
Isobutane 94.24 94.24 0.01 0.01
Isobutene 0.04 0.04 0.12 0.12
1-Butene 4.48 4.48 99.60 99.60
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.00 0.00 0.19 0.19
2-Butene 0.00 0.00 0.07 0.07
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.01 0.01 0.00 0.00
TBA 0.00 0.00 0.00 0.00
DME 0.59 0.59 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 5174 5174 4424 4424
Actual Volumetric Flow m³/h 9.8 9.8 8.5 8.5
Actual Density kg/m³ 526 526 523 523
Standard Specific Gravity 0.57 0.57 0.60 0.60
Dynamic Viscosity cP 0.14 0.14 0.10 0.10
Kinematic Viscosity cSt 0.26 0.26 0.20 0.20
Specific Enthalpy kcal/kg 27.2 27.1 39.5 39.5
Surface Tension mN/m 7.7 7.7 6.9 6.9
Specific Heat Capacity kcal/(kg°C) 0.62 0.62 0.59 0.59
Thermal Conductivity kcal/(h·m·°C) 0.076 0.076 0.080 0.080
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 2
Stream 6138 6139 6140 6141
Component (wt%)
Water 0.00 0.00 0.00 0.00
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.00 0.00 0.00 0.00
Propylene 0.00 0.00 0.00 0.00
Propane 0.00 0.00 0.00 0.00
Propadiene 0.00 0.00 0.00 0.00
Isobutane 0.01 0.01 0.00 0.00
Isobutene 0.12 0.12 0.00 0.00
1-Butene 99.60 99.60 1.75 1.75
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.19 0.19 56.54 56.54
2-Butene 0.07 0.07 41.71 41.71
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.00 0.00 0.00 0.00
TBA 0.00 0.00 0.00 0.00
DME 0.00 0.00 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h 135193
Actual Volumetric Flow m³/h 6346
Molecular Weight 57.2
Actual Density kg/m³ 21.3
Viscosity cP 0.009
Specific Enthalpy kcal/kg 117.81
Specific Heat Capacity kcal/(kg°C) 0.51
Thermal Conductivity kcal/(h·m·°C) 0.018
Liquid
Mass Flow Rate kg/h 4424 4424 450601 315408
Actual Volumetric Flow m³/h 7.9 7.9 861.1 602.7
Actual Density kg/m³ 561 561 523 523
Standard Specific Gravity 0.60 0.60 0.60 0.60
Dynamic Viscosity cP 0.12 0.12 0.12 0.12
Kinematic Viscosity cSt 0.22 0.22 0.22 0.22
Specific Enthalpy kcal/kg 24.6 24.6 43.4 43.5
Surface Tension mN/m 9.9 9.9 7.3 7.3
Specific Heat Capacity kcal/(kg°C) 0.57 0.57 0.65 0.65
Thermal Conductivity kcal/(h·m·°C) 0.088 0.088 0.078 0.078
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 2
Stream 6142 6143
Component (wt%)
Water 0.00 0.00
Hydrogen 0.00 0.00
Methane 0.00 0.00
Propylene 0.00 0.00
Propane 0.00 0.00
Propadiene 0.00 0.00
Isobutane 0.02 0.02
Isobutene 0.12 0.12
1-Butene 99.61 99.61
Butadiene 0.00 0.00
n-Butane 0.18 0.18
2-Butene 0.07 0.07
C5's 0.00 0.00
C6's 0.00 0.00
DIB 0.00 0.00
Methanol 0.00 0.00
TBA 0.00 0.00
DME 0.00 0.00
MTBE 0.00 0.00
MSBE 0.00 0.00
Vapor
Mass Flow rate kg/h 232001
Actual Volumetric Flow m³/h 10023
Molecular Weight 56.1
Actual Density kg/m³ 23.1
Viscosity cP 0.010
Specific Enthalpy kcal/kg 112.96
Specific Heat Capacity kcal/(kg°C) 0.48
Thermal Conductivity kcal/(h·m·°C) 0.017
Liquid
Mass Flow Rate kg/h 773340 541339
Actual Volumetric Flow m³/h 1478.6 1035.1
Actual Density kg/m³ 523 523
Standard Specific Gravity 0.60 0.60
Dynamic Viscosity cP 0.10 0.10
Kinematic Viscosity cSt 0.20 0.20
Specific Enthalpy kcal/kg 39.4 39.5
Surface Tension mN/m 6.9 6.9
Specific Heat Capacity kcal/(kg°C) 0.59 0.59
Thermal Conductivity kcal/(h·m·°C) 0.080 0.080
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 3
Stream 6001 6003 6004 6005
0 0 0
Stream Description MIXED WATER WASH WASTE WATER TOTAL WASTE
HYDROGENATED COLUMN TO WATER TO
C4S FROM OSBL BOTTOMS WASTE WATER WASTE WATER
PLANT OSBL PLANT OSBL
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.00 100.00 100.00 100.00
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.01 0.00 0.00 0.00
Propylene 0.01 0.00 0.00 0.00
Propane 0.08 0.00 0.00 0.00
Propadiene 0.03 0.00 0.00 0.00
Isobutane 19.08 0.00 0.00 0.00
Isobutene 29.15 0.00 0.00 0.00
1-Butene 18.48 0.00 0.00 0.00
Butadiene 0.00 0.00 0.00 0.00
n-Butane 18.93 0.00 0.00 0.00
2-Butene 13.86 0.00 0.00 0.00
C5's 0.37 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.00 0.00 0.00 0.00
TBA 0.00 0.00 0.00 0.00
DME 0.00 0.00 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 26103 7823 7823 7827
Actual Volumetric Flow m³/h 46.6 7.9 7.9 7.9
Actual Density kg/m³ 560 992 990 990
Standard Specific Gravity 0.59 1.00 1.00 1.00
Dynamic Viscosity cP 0.15 0.65 0.65 0.65
Kinematic Viscosity cSt 0.26 0.65 0.65 0.65
Specific Enthalpy kcal/kg 22.6 40.3 40.3 40.3
Surface Tension mN/m 9.9 69.5 69.5 69.5
Specific Heat Capacity kcal/(kg°C) 0.58 1.00 1.00 1.00
Thermal Conductivity kcal/(h·m·°C) 0.085 0.542 0.542 0.542
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 3
Stream 6006 6007 6008 6009
0 0 0 0
Stream Description WATER WASH FEED TO C4 FEED C4 FEED
COLUMN C4 FEED PUMP PUMP
OVERHEAD SURGE DRUM SUCTION DISCHARGE
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.03 0.03 0.03 0.03
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.01 0.01 0.01 0.01
Propylene 0.01 0.01 0.01 0.01
Propane 0.08 0.08 0.08 0.08
Propadiene 0.03 0.03 0.03 0.03
Isobutane 19.08 19.08 19.08 19.08
Isobutene 29.14 29.14 29.14 29.14
1-Butene 18.48 18.48 18.48 18.48
Butadiene 0.00 0.00 0.00 0.00
n-Butane 18.93 18.93 18.93 18.93
2-Butene 13.86 13.86 13.86 13.86
C5's 0.37 0.37 0.37 0.37
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.00 0.00 0.00 0.00
TBA 0.00 0.00 0.00 0.00
DME 0.00 0.00 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 26111 26111 26111 26111
Actual Volumetric Flow m³/h 46.5 46.6 46.6 46.7
Actual Density kg/m³ 561 561 561 559
Standard Specific Gravity 0.59 0.59 0.59 0.59
Dynamic Viscosity cP 0.15 0.15 0.15 0.15
Kinematic Viscosity cSt 0.26 0.26 0.26 0.26
Specific Enthalpy kcal/kg 22.5 22.5 22.5 23.3
Surface Tension mN/m 10.0 10.0 10.0 9.8
Specific Heat Capacity kcal/(kg°C) 0.58 0.58 0.58 0.59
Thermal Conductivity kcal/(h·m·°C) 0.085 0.085 0.085 0.084
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 3
Stream 6010 6011 6012 6013
0 0 0 0
Stream Description C4 FEED MIXED DEMINERALIZED DEMINERALIZED
PUMP C4s & MeOH WATER FROM WATER FEED
DISCHARGE OSBL TO WATER TO WATER
DOWNSTRM FV WASH COLUMN WASH COLUMN
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.03 0.04 100.00 100.00
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.01 0.01 0.00 0.00
Propylene 0.01 0.01 0.00 0.00
Propane 0.08 0.07 0.00 0.00
Propadiene 0.03 0.02 0.00 0.00
Isobutane 19.08 16.09 0.00 0.00
Isobutene 29.14 24.58 0.00 0.00
1-Butene 18.48 15.58 0.00 0.00
Butadiene 0.00 0.00 0.00 0.00
n-Butane 18.93 15.97 0.00 0.00
2-Butene 13.86 11.69 0.00 0.00
C5's 0.37 0.31 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.00 15.64 0.00 0.00
TBA 0.00 0.00 0.00 0.00
DME 0.00 0.00 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 26111 30955 7831 7831
Actual Volumetric Flow m³/h 46.7 53.2 7.9 7.9
Actual Density kg/m³ 559 582 990 990
Standard Specific Gravity 0.59 0.62 1.00 1.00
Dynamic Viscosity cP 0.15 0.20 0.65 0.65
Kinematic Viscosity cSt 0.26 0.34 0.66 0.66
Specific Enthalpy kcal/kg 23.3 24.4 40.0 40.0
Surface Tension mN/m 9.8 12.4 69.6 69.6
Specific Heat Capacity kcal/(kg°C) 0.59 0.60 1.00 1.00
Thermal Conductivity kcal/(h·m·°C) 0.084 0.089 0.541 0.541
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 3
Stream 6014 6015 6016 6017
0 0 0 0
Stream Description REACTOR PRIMARY PRIMARY SECONDARY
FEED REACTOR REACTOR REACTOR
PREHEATER FEED EFFLUENT FEED
OUTLET COOLER
INLET
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.04 0.04 0.04 0.04
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.01 0.01 0.01 0.01
Propylene 0.01 0.01 0.01 0.01
Propane 0.07 0.07 0.07 0.07
Propadiene 0.02 0.02 0.02 0.02
Isobutane 16.09 16.09 16.09 16.09
Isobutene 24.58 15.03 5.47 5.47
1-Butene 15.58 15.57 15.55 15.55
Butadiene 0.00 0.00 0.00 0.00
n-Butane 15.97 15.97 15.97 15.97
2-Butene 11.69 11.69 11.69 11.69
C5's 0.31 0.31 0.31 0.31
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.06 0.11 0.11
Methanol 15.64 10.18 4.72 4.72
TBA 0.00 0.05 0.09 0.09
DME 0.00 0.03 0.06 0.06
MTBE 0.00 14.87 29.74 29.74
MSBE 0.00 0.03 0.06 0.06
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 30955 61911 61911 30955
Actual Volumetric Flow m³/h 53.2 104.1 109.0 54.5
Actual Density kg/m³ 582 595 568 568
Standard Specific Gravity 0.62 0.63 0.64 0.64
Dynamic Viscosity cP 0.20 0.19 0.15 0.15
Kinematic Viscosity cSt 0.34 0.32 0.26 0.26
Specific Enthalpy kcal/kg 24.4 23.3 39.0 39.0
Surface Tension mN/m 12.4 12.5 9.5 9.5
Specific Heat Capacity kcal/(kg°C) 0.60 0.58 0.62 0.62
Thermal Conductivity kcal/(h·m·°C) 0.089 0.091 0.083 0.083
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 3
Stream 6018 6019 6020 6021
0 0 0 0
Stream Description SECONDARY SECONDARY SECONDARY INLET TO
REACTOR REACTOR REACTOR PRIMARY
FEED FEED EFFLUENT REACTOR
COOLER EFFLUENT
OUTLET COOLER
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.04 0.04 0.04 0.04
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.01 0.01 0.01 0.01
Propylene 0.01 0.01 0.01 0.01
Propane 0.07 0.07 0.07 0.07
Propadiene 0.02 0.02 0.02 0.02
Isobutane 16.09 16.09 16.09 16.09
Isobutene 5.47 5.47 2.46 5.47
1-Butene 15.55 15.55 15.53 15.55
Butadiene 0.00 0.00 0.00 0.00
n-Butane 15.97 15.97 15.97 15.97
2-Butene 11.69 11.69 11.69 11.69
C5's 0.31 0.31 0.31 0.31
C6's 0.00 0.00 0.00 0.00
DIB 0.11 0.11 0.11 0.11
Methanol 4.72 4.72 2.99 4.72
TBA 0.09 0.09 0.09 0.09
DME 0.06 0.06 0.06 0.06
MTBE 29.74 29.74 34.47 29.74
MSBE 0.06 0.06 0.08 0.06
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 30955 30955 30955 30955
Actual Volumetric Flow m³/h 50.9 50.9 51.6 54.5
Actual Density kg/m³ 608 608 600 568
Standard Specific Gravity 0.64 0.64 0.64 0.64
Dynamic Viscosity cP 0.19 0.19 0.17 0.15
Kinematic Viscosity cSt 0.31 0.31 0.29 0.26
Specific Enthalpy kcal/kg 21.8 21.8 26.7 39.0
Surface Tension mN/m 12.6 12.6 11.6 9.5
Specific Heat Capacity kcal/(kg°C) 0.57 0.57 0.58 0.62
Thermal Conductivity kcal/(h·m·°C) 0.092 0.092 0.089 0.083
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 3
Stream 6022 6023 6024 6025
0 0 0 0
Stream Description PRIMARY PRIMARY PRIMARY CD REACTION
REACTOR REACTOR REACTOR COLUMN
RECYCLE RECYCLE RECYCLE FEED
PUMP PUMP
SUCTION DISCHARGE
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.04 0.04 0.04 0.04
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.01 0.01 0.01 0.01
Propylene 0.01 0.01 0.01 0.01
Propane 0.07 0.07 0.07 0.07
Propadiene 0.02 0.02 0.02 0.02
Isobutane 16.09 16.09 16.09 16.09
Isobutene 5.47 5.47 5.47 2.46
1-Butene 15.55 15.55 15.55 15.53
Butadiene 0.00 0.00 0.00 0.00
n-Butane 15.97 15.97 15.97 15.97
2-Butene 11.69 11.69 11.69 11.69
C5's 0.31 0.31 0.31 0.31
C6's 0.00 0.00 0.00 0.00
DIB 0.11 0.11 0.11 0.11
Methanol 4.72 4.72 4.72 2.99
TBA 0.09 0.09 0.09 0.09
DME 0.06 0.06 0.06 0.06
MTBE 29.74 29.74 29.74 34.47
MSBE 0.06 0.06 0.06 0.08
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 30955 30955 30955 30955
Actual Volumetric Flow m³/h 50.9 51.0 51.0 54.3
Actual Density kg/m³ 608 607 607 570
Standard Specific Gravity 0.64 0.64 0.64 0.64
Dynamic Viscosity cP 0.19 0.19 0.19 0.15
Kinematic Viscosity cSt 0.31 0.31 0.31 0.26
Specific Enthalpy kcal/kg 21.8 22.1 22.1 39.2
Surface Tension mN/m 12.6 12.6 12.6 9.3
Specific Heat Capacity kcal/(kg°C) 0.57 0.57 0.57 0.61
Thermal Conductivity kcal/(h·m·°C) 0.092 0.092 0.092 0.083
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 3
Stream 6026 6027 6028 6029
0 0 0 0
Stream Description CD REACTION MTBE MTBE MTBE
COLUMN PRODUCT PRODUCT PRODUCT
BOTTOMS COOLER COOLER TO OSBL
INLET OUTLET
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.00 0.00 0.00 0.00
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.00 0.00 0.00 0.00
Propylene 0.00 0.00 0.00 0.00
Propane 0.00 0.00 0.00 0.00
Propadiene 0.00 0.00 0.00 0.00
Isobutane 0.00 0.00 0.00 0.00
Isobutene 0.00 0.00 0.00 0.00
1-Butene 0.00 0.00 0.00 0.00
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.03 0.03 0.03 0.03
2-Butene 0.07 0.07 0.07 0.07
C5's 0.80 0.80 0.80 0.80
C6's 0.00 0.00 0.00 0.00
DIB 0.29 0.29 0.29 0.29
Methanol 0.10 0.10 0.10 0.10
TBA 0.26 0.26 0.26 0.26
DME 0.00 0.00 0.00 0.00
MTBE 98.09 98.09 98.09 98.09
MSBE 0.36 0.36 0.36 0.36
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 12082 12082 12082 12082
Actual Volumetric Flow m³/h 20.2 18.0 17.0 17.0
Actual Density kg/m³ 598 670 713 713
Standard Specific Gravity 0.74 0.74 0.74 0.74
Dynamic Viscosity cP 0.13 0.20 0.27 0.27
Kinematic Viscosity cSt 0.22 0.29 0.38 0.38
Specific Enthalpy kcal/kg 74.3 42.5 22.7 22.7
Surface Tension mN/m 7.1 12.8 16.9 16.9
Specific Heat Capacity kcal/(kg°C) 0.62 0.57 0.53 0.53
Thermal Conductivity kcal/(h·m·°C) 0.101 0.101 0.104 0.104
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 3
Stream 6030 6031 6032 6033
0 0 0 0
Stream Description CD REACTION CD REACTION FEED TO CD REACTION
COLUMN COLUMN CD REACTION COLUMN
OVERHEAD CONDENSER COLUMN REFLUX PUMP
OUTLET OVERHEAD SUCTION
DRUM
0 0 0 0
Stream Phase VAPOR LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.09 0.09 0.09 0.09
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.01 0.01 0.01 0.01
Propylene 0.01 0.01 0.01 0.01
Propane 0.11 0.11 0.11 0.11
Propadiene 0.04 0.04 0.04 0.04
Isobutane 25.97 25.97 25.97 25.97
Isobutene 0.04 0.04 0.04 0.04
1-Butene 25.05 25.05 25.05 25.05
Butadiene 0.00 0.00 0.00 0.00
n-Butane 25.75 25.75 25.75 25.75
2-Butene 18.78 18.78 18.78 18.78
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 4.00 4.00 4.00 4.00
TBA 0.00 0.00 0.00 0.00
DME 0.16 0.16 0.16 0.16
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h 44111
Actual Volumetric Flow m³/h 2563
Molecular Weight 55.3
Actual Density kg/m³ 17.2
Viscosity cP 0.009
Specific Enthalpy kcal/kg 118.76
Specific Heat Capacity kcal/(kg°C) 0.45
Thermal Conductivity kcal/(h·m·°C) 0.016
Liquid
Mass Flow Rate kg/h 44111 44111 44111
Actual Volumetric Flow m³/h 80.0 80.0 80.0
Actual Density kg/m³ 552 552 552
Standard Specific Gravity 0.00 0.60 0.60 0.60
Dynamic Viscosity cP 0.14 0.14 0.14
Kinematic Viscosity cSt 0.26 0.26 0.26
Specific Enthalpy kcal/kg 28.3 28.3 28.3
Surface Tension mN/m 9.8 9.8 9.8
Specific Heat Capacity kcal/(kg°C) 0.61 0.61 0.61
Thermal Conductivity kcal/(h·m·°C) 0.083 0.083 0.083
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 3
Stream 6034 6035 6036 6037
0 0 0 0
Stream Description CD REACTION CD REACTION CD REACTION MEOH EXT.
COLUMN COLUMN COLUMN COLUMN
REFLUX PUMP REFLUX REFLUX AT FEED
DISCHARGE COLUMN FEED COOLER
INLET
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.09 0.09 0.09 0.09
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.01 0.01 0.01 0.01
Propylene 0.01 0.01 0.01 0.01
Propane 0.11 0.11 0.11 0.11
Propadiene 0.04 0.04 0.04 0.04
Isobutane 25.97 25.97 25.97 25.97
Isobutene 0.04 0.04 0.04 0.04
1-Butene 25.05 25.05 25.05 25.05
Butadiene 0.00 0.00 0.00 0.00
n-Butane 25.75 25.75 25.75 25.75
2-Butene 18.78 18.78 18.78 18.78
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 4.00 4.00 4.00 4.00
TBA 0.00 0.00 0.00 0.00
DME 0.16 0.16 0.16 0.16
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 44111 24933 24933 19179
Actual Volumetric Flow m³/h 80.1 45.3 45.3 34.8
Actual Density kg/m³ 550 550 550 550
Standard Specific Gravity 0.60 0.60 0.60 0.60
Dynamic Viscosity cP 0.14 0.14 0.14 0.14
Kinematic Viscosity cSt 0.26 0.26 0.26 0.26
Specific Enthalpy kcal/kg 28.8 28.8 28.8 28.8
Surface Tension mN/m 9.7 9.7 9.7 9.7
Specific Heat Capacity kcal/(kg°C) 0.61 0.61 0.61 0.61
Thermal Conductivity kcal/(h·m·°C) 0.083 0.083 0.083 0.083
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 3
Stream 6038 6039 6040 6041
0 0 0 0
Stream Description C4 DISTILLATE METHANOL METHANOL METHANOL
TO METHANOL EXTRACTION REC. COL. RECOVERY
EXTRACTION COLUMN FEED/BTMS COLUMN
COLUMN BOTTOMS EXCHANGER FEED
INLET
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.09 80.00 80.00 80.00
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.01 0.00 0.00 0.00
Propylene 0.01 0.00 0.00 0.00
Propane 0.11 0.00 0.00 0.00
Propadiene 0.04 0.00 0.00 0.00
Isobutane 25.97 0.00 0.00 0.00
Isobutene 0.04 0.00 0.00 0.00
1-Butene 25.05 0.00 0.00 0.00
Butadiene 0.00 0.00 0.00 0.00
n-Butane 25.75 0.00 0.00 0.00
2-Butene 18.78 0.00 0.00 0.00
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 4.00 20.00 20.00 20.00
TBA 0.00 0.00 0.00 0.00
DME 0.16 0.00 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 19179 3834 3834 3834
Actual Volumetric Flow m³/h 34.0 4.1 4.1 4.2
Actual Density kg/m³ 564 938 938 915
Standard Specific Gravity 0.60 0.95 0.95 0.95
Dynamic Viscosity cP 0.16 0.62 0.62 0.37
Kinematic Viscosity cSt 0.28 0.66 0.66 0.40
Specific Enthalpy kcal/kg 22.5 36.8 36.8 69.4
Surface Tension mN/m 10.9 63.6 63.6 58.2
Specific Heat Capacity kcal/(kg°C) 0.59 0.92 0.92 0.94
Thermal Conductivity kcal/(h·m·°C) 0.087 0.320 0.320 0.315
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 3
Stream 6042 6043 6044 6045
0 0 0
Stream Description METHANOL C4s TO METHANOL METHANOL
EXTRACTION B-1 RECOVERY RECOVERY
COLUMN HEAVIES COLUMN COLUMN
OVERHEAD COLUMN BOTTOMS BOTTOMS PUMP
DISCHARGE
0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0
Component (wt%) 0 0 0
Water 0.03 0.03 100.00 100.00
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.01 0.01 0.00 0.00
Propylene 0.01 0.01 0.00 0.00
Propane 0.11 0.11 0.00 0.00
Propadiene 0.04 0.04 0.00 0.00
Isobutane 27.07 27.07 0.00 0.00
Isobutene 0.04 0.04 0.00 0.00
1-Butene 26.11 26.11 0.00 0.00
Butadiene 0.00 0.00 0.00 0.00
n-Butane 26.84 26.84 0.00 0.00
2-Butene 19.57 19.57 0.00 0.00
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.00 0.00 0.00 0.00
TBA 0.00 0.00 0.00 0.00
DME 0.17 0.17 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 18401 18401 3056 3056
Actual Volumetric Flow m³/h 33.0 32.9 3.3 3.3
Actual Density kg/m³ 558 559 939 939
Standard Specific Gravity 0.59 0.59 1.00 1.00
Dynamic Viscosity cP 0.14 0.14 0.22 0.22
Kinematic Viscosity cSt 0.25 0.25 0.23 0.23
Specific Enthalpy kcal/kg 22.4 22.4 126.6 126.7
Surface Tension mN/m 10.0 10.2 54.0 54.0
Specific Heat Capacity kcal/(kg°C) 0.59 0.59 1.02 1.02
Thermal Conductivity kcal/(h·m·°C) 0.085 0.085 0.592 0.591
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 3
Stream 6046 6047 6048 6049
0 0 0 0
Stream Description RECYCLE RECYCLE RECYCLE METHANOL
WATER WATER WATER TO RECOVERY
COOLER COOLER METHANOL COLUMN
INLET OUTLET EXTRACTION OVERHEAD
COLUMN
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID VAPOR
0 0 0 0
Component (wt%) 0 0 0 0
Water 100.00 100.00 100.00 0.05
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.00 0.00 0.00 0.00
Propylene 0.00 0.00 0.00 0.00
Propane 0.00 0.00 0.00 0.00
Propadiene 0.00 0.00 0.00 0.00
Isobutane 0.00 0.00 0.00 0.00
Isobutene 0.00 0.00 0.00 0.00
1-Butene 0.00 0.00 0.00 0.00
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.00 0.00 0.00 0.00
2-Butene 0.00 0.00 0.00 0.00
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.00 0.00 0.00 99.95
TBA 0.00 0.00 0.00 0.00
DME 0.00 0.00 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h 2301
Actual Volumetric Flow m³/h 1193
Molecular Weight 32.0
Actual Density kg/m³ 1.9
Viscosity cP 0.012
Specific Enthalpy kcal/kg 312.51
Specific Heat Capacity kcal/(kg°C) 0.37
Thermal Conductivity kcal/(h·m·°C) 0.018
Liquid
Mass Flow Rate kg/h 3056 3056 3056
Actual Volumetric Flow m³/h 3.2 3.1 3.1
Actual Density kg/m³ 967 990 990
Standard Specific Gravity 1.00 1.00 1.00 0.00
Dynamic Viscosity cP 0.33 0.65 0.65
Kinematic Viscosity cSt 0.34 0.66 0.66
Specific Enthalpy kcal/kg 85.8 40.0 40.0
Surface Tension mN/m 62.0 69.6 69.6
Specific Heat Capacity kcal/(kg°C) 1.00 1.00 1.00
Thermal Conductivity kcal/(h·m·°C) 0.577 0.541 0.541
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 3
Stream 6050 6051 6052 6053
0 0 0 0
Stream Description METHANOL METHANOL METHANOL METHANOL
RECOVERY RECOVERY RECOVERY RECOVERY
COLUMN COLUMN COLUMN COLUMN
CONDENSER OVHD DRUM REFLUX PUMP REFLUX PUMP
OUTLET INLET SUCTION DISCHARGE
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.05 0.05 0.08 0.08
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.00 0.00 0.00 0.00
Propylene 0.00 0.00 0.00 0.00
Propane 0.00 0.00 0.00 0.00
Propadiene 0.00 0.00 0.00 0.00
Isobutane 0.00 0.00 0.00 0.00
Isobutene 0.00 0.00 0.00 0.00
1-Butene 0.00 0.00 0.00 0.00
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.00 0.00 0.00 0.00
2-Butene 0.00 0.00 0.00 0.00
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 99.95 99.95 99.92 99.92
TBA 0.00 0.00 0.00 0.00
DME 0.00 0.00 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 2301 2301 6684 6684
Actual Volumetric Flow m³/h 3.1 3.1 8.7 8.7
Actual Density kg/m³ 750 750 766 765
Standard Specific Gravity 0.80 0.80 0.80 0.80
Dynamic Viscosity cP 0.35 0.35 0.41 0.40
Kinematic Viscosity cSt 0.46 0.46 0.53 0.52
Specific Enthalpy kcal/kg 39.9 39.9 29.4 30.3
Surface Tension mN/m 18.9 18.9 20.3 20.2
Specific Heat Capacity kcal/(kg°C) 0.67 0.67 0.64 0.65
Thermal Conductivity kcal/(h·m·°C) 0.162 0.162 0.166 0.166
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 3
Stream 6054 6055 6056 6057
0 0 0 0
Stream Description METHANOL METHANOL METHANOL RECYCLE
RECOVERY RECOVERY TO MTBE METHANOL
COLUMN COLUMN REACTION TO C4s
REFLUX REFLUX AT SECTION STREAM
COLUMN FEED
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.08 0.08 0.08 0.08
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.00 0.00 0.00 0.00
Propylene 0.00 0.00 0.00 0.00
Propane 0.00 0.00 0.00 0.00
Propadiene 0.00 0.00 0.00 0.00
Isobutane 0.00 0.00 0.00 0.00
Isobutene 0.00 0.00 0.00 0.00
1-Butene 0.00 0.00 0.00 0.00
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.00 0.00 0.00 0.00
2-Butene 0.00 0.00 0.00 0.00
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 99.92 99.92 99.92 99.92
TBA 0.00 0.00 0.00 0.00
DME 0.00 0.00 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 1534 1534 5150 4845
Actual Volumetric Flow m³/h 2.0 2.0 6.7 6.3
Actual Density kg/m³ 765 765 765 765
Standard Specific Gravity 0.80 0.80 0.80 0.80
Dynamic Viscosity cP 0.40 0.40 0.40 0.40
Kinematic Viscosity cSt 0.52 0.52 0.52 0.52
Specific Enthalpy kcal/kg 30.3 30.3 30.3 30.3
Surface Tension mN/m 20.2 20.2 20.2 20.2
Specific Heat Capacity kcal/(kg°C) 0.65 0.65 0.65 0.65
Thermal Conductivity kcal/(h·m·°C) 0.166 0.166 0.166 0.166
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 3
Stream 6058 6059 6060 6061
0 0 0
Stream Description RECYCLE METHANOL METHANOL METHANOL
METHANOL INJECTION TO INJECTION TO INJECTION TO
TO C4s CD REACTION CD REACTION CD REACTION
STREAM COLUMN COLUMN COLUMN
0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.08 0.08 0.08 0.08
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.00 0.00 0.00 0.00
Propylene 0.00 0.00 0.00 0.00
Propane 0.00 0.00 0.00 0.00
Propadiene 0.00 0.00 0.00 0.00
Isobutane 0.00 0.00 0.00 0.00
Isobutene 0.00 0.00 0.00 0.00
1-Butene 0.00 0.00 0.00 0.00
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.00 0.00 0.00 0.00
2-Butene 0.00 0.00 0.00 0.00
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 99.92 99.92 99.92 99.92
TBA 0.00 0.00 0.00 0.00
DME 0.00 0.00 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 4845 306 15 290
Actual Volumetric Flow m³/h 6.3 0.4 0.0 0.4
Actual Density kg/m³ 765 765 765 765
Standard Specific Gravity 0.80 0.80 0.80 0.80
Dynamic Viscosity cP 0.40 0.40 0.40 0.40
Kinematic Viscosity cSt 0.52 0.52 0.52 0.52
Specific Enthalpy kcal/kg 30.3 30.3 30.3 30.3
Surface Tension mN/m 20.2 20.2 20.2 20.2
Specific Heat Capacity kcal/(kg°C) 0.65 0.65 0.65 0.65
Thermal Conductivity kcal/(h·m·°C) 0.166 0.166 0.166 0.166
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 3
Stream 6062 6063 6064 6065
0 0 0
Stream Description FRESH FILTERED FILTERED CD REACTION
METHANOL FRESH FRESH COLUMN
FROM METHANOL METHANOL REBOILER
STORAGE AT INLET
OSBL
0 0 0 0
Stream Phase LIQUID LIQUID LIQUID LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.10 0.10 0.10 0.00
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.00 0.00 0.00 0.00
Propylene 0.00 0.00 0.00 0.00
Propane 0.00 0.00 0.00 0.00
Propadiene 0.00 0.00 0.00 0.00
Isobutane 0.00 0.00 0.00 0.00
Isobutene 0.00 0.00 0.00 0.00
1-Butene 0.00 0.00 0.00 0.00
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.00 0.00 0.00 0.03
2-Butene 0.00 0.00 0.00 0.07
C5's 0.00 0.00 0.00 0.80
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.29
Methanol 99.90 99.90 99.90 0.10
TBA 0.00 0.00 0.00 0.26
DME 0.00 0.00 0.00 0.00
MTBE 0.00 0.00 0.00 98.09
MSBE 0.00 0.00 0.00 0.36
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 4383 4383 4383 225143
Actual Volumetric Flow m³/h 5.7 5.7 5.7 376.7
Actual Density kg/m³ 775 775 775 598
Standard Specific Gravity 0.80 0.80 0.80 0.74
Dynamic Viscosity cP 0.40 0.40 0.40 0.13
Kinematic Viscosity cSt 0.58 0.58 0.58 0.22
Specific Enthalpy kcal/kg 24.0 24.0 24.0 74.3
Surface Tension mN/m 21.1 21.1 21.1 7.1
Specific Heat Capacity kcal/(kg°C) 0.63 0.63 0.63 0.62
Thermal Conductivity kcal/(h·m·°C) 0.166 0.166 0.166 0.101
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 3
Stream 6066 6067 6068 6099
0 0 0
Stream Description CD REACTION METHANOL METHANOL C4 DISTILLATE
COLUMN RECOVERY RECOVERY TO METHANOL
REBOILER COLUMN COLUMN EXTRACTION
OUTLET REBOILER REBOILER COLUMN
INLET OUTLET
0 0 0 0
Stream Phase MIXED LIQUID MIXED LIQUID
0 0 0 0
Component (wt%) 0 0 0 0
Water 0.00 99.99 99.99 0.09
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.00 0.00 0.00 0.01
Propylene 0.00 0.00 0.00 0.01
Propane 0.00 0.00 0.00 0.11
Propadiene 0.00 0.00 0.00 0.04
Isobutane 0.00 0.00 0.00 25.97
Isobutene 0.00 0.00 0.00 0.04
1-Butene 0.00 0.00 0.00 25.05
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.03 0.00 0.00 25.75
2-Butene 0.07 0.00 0.00 18.78
C5's 0.80 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.29 0.00 0.00 0.00
Methanol 0.10 0.01 0.01 4.00
TBA 0.26 0.00 0.00 0.00
DME 0.00 0.00 0.00 0.16
MTBE 98.09 0.00 0.00 0.00
MSBE 0.36 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h 67324 1525
Actual Volumetric Flow m³/h 2724.0 1177.0
Molecular Weight 87.5 18.0
Actual Density kg/m³ 24.7 1.3
Viscosity cP 0.010 0.013
Specific Enthalpy kcal/kg 135.26 649.19
Specific Heat Capacity kcal/(kg°C) 0.50 0.46
Thermal Conductivity kcal/(h·m·°C) 0.021 0.023
Liquid
Mass Flow Rate kg/h 157819 5057 3532 19179
Actual Volumetric Flow m³/h 263.9 5.4 3.8 34.0
Actual Density kg/m³ 598 939 939 564
Standard Specific Gravity 0.74 1.00 1.00 0.60
Dynamic Viscosity cP 0.13 0.22 0.22 0.16
Kinematic Viscosity cSt 0.22 0.23 0.23 0.28
Specific Enthalpy kcal/kg 74.2 126.3 125.6 22.5
Surface Tension mN/m 7.2 54.1 54.2 10.9
Specific Heat Capacity kcal/(kg°C) 0.62 1.02 1.02 0.59
Thermal Conductivity kcal/(h·m·°C) 0.101 0.591 0.591 0.087
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 3
Stream 0
Stream Description
Stream Phase 0
0
Component (wt%) 0
Water 0.00
Hydrogen 0.00
Methane 0.00
Propylene 0.00
Propane 0.00
Propadiene 0.00
Isobutane 0.00
Isobutene 0.00
1-Butene 0.00
Butadiene 0.00
n-Butane 0.00
2-Butene 0.00
C5's 0.00
C6's 0.00
DIB 0.00
Methanol 0.00
TBA 0.00
DME 0.00
MTBE 0.00
MSBE 0.00
0.00
0.00
Mass Flow Rate kg/h 0
Molar Flow Rate kg mol/hr 0.0
Molecular Weight 0.0
Temperature °C 0.0
Stream Pressure bar (g) 0.0
Stream Enthalpy MMkcal/h 0.000
Weight Fraction Liquid 0.00
Critical Temperature °C 0.0
Critical Pressure bar (a) 0.0
0
Vapor 0.0
Mass Flow rate kg/h 0
Actual Volumetric Flow m³/h 0
Molecular Weight 0.00
Actual Density kg/m³ 0.00
Viscosity cP 0.0000
Specific Enthalpy kcal/kg 0.0
Specific Heat Capacity kcal/(kg°C) 0.000
Thermal Conductivity kcal/(h·m·°C) 0.0000
0.000
Liquid 0.0
Mass Flow Rate kg/h 0
Actual Volumetric Flow m³/h 0.0
Actual Density kg/m³ 0.0
Standard Specific Gravity 0.000
Dynamic Viscosity cP 0.000
Kinematic Viscosity cSt
Specific Enthalpy kcal/kg 0.0
Surface Tension mN/m 0.0
Specific Heat Capacity kcal/(kg°C) 0.000
Thermal Conductivity kcal/(h·m·°C) 0.000
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 3
Stream 6101 6102 6103 6104
Stream Description B-1 HEAVIES B-1 HEAVIES B-1 HEAVIES B-1 HEAVIES
COLUMN #1 COLUMN COLUMN #2 COLUMN #2
BOTTOMS TRANSFER FEED OVERHEAD
PUMP DISCH.
Component (wt%)
Water 0.00 0.00 0.00 0.00
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.00 0.00 0.00 0.00
Propylene 0.00 0.00 0.00 0.00
Propane 0.01 0.01 0.01 0.03
Propadiene 0.01 0.01 0.01 0.01
Isobutane 17.36 17.36 17.36 19.83
Isobutene 0.05 0.05 0.05 0.05
1-Butene 43.08 43.08 43.08 43.43
Butadiene 0.00 0.00 0.00 0.00
n-Butane 25.40 25.40 25.40 23.56
2-Butene 14.06 14.06 14.06 13.04
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.00 0.00 0.00 0.00
TBA 0.00 0.00 0.00 0.00
DME 0.02 0.02 0.02 0.05
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h 133600
Actual Volumetric Flow m³/h 6659
Molecular Weight 56.9
Actual Density kg/m³ 20.1
Viscosity cP 0.009
Specific Enthalpy kcal/kg 111.57
Specific Heat Capacity kcal/(kg°C) 0.49
Thermal Conductivity kcal/(h·m·°C) 0.017
Liquid
Mass Flow Rate kg/h 123871 123871 123871
Actual Volumetric Flow m³/h 235.7 235.5 235.8
Actual Density kg/m³ 525 526 525
Standard Specific Gravity 0.59 0.59 0.59 0.00
Dynamic Viscosity cP 0.11 0.11 0.11
Kinematic Viscosity cSt 0.22 0.22 0.22
Specific Enthalpy kcal/kg 37.3 37.6 37.4
Surface Tension mN/m 7.5 7.4 7.5
Specific Heat Capacity kcal/(kg°C) 0.62 0.62 0.62
Thermal Conductivity kcal/(h·m·°C) 0.079 0.078 0.079
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 3
Stream 6105 6106 6107 6108
Component (wt%)
Water 0.05 0.05 0.05
Hydrogen 0.00 0.00 0.00
Methane 0.02 0.02 0.02
Propylene 0.02 0.02 0.02
Propane 0.21 0.21 0.21
Propadiene 0.07 0.07 0.07
Isobutane 51.20 51.20 51.20
Isobutene 0.08 0.08 0.08
1-Butene 47.91 47.91 47.91
Butadiene 0.00 0.00 0.00
n-Butane 0.09 0.09 0.09
2-Butene 0.03 0.03 0.03
C5's 0.00 0.00 0.00
C6's 0.00 0.00 0.00
DIB 0.00 0.00 0.00
Methanol 0.00 0.00 0.00
TBA 0.00 0.00 0.00
DME 0.32 0.32 0.32
MTBE 0.00 0.00 0.00
MSBE 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h 123297
Actual Volumetric Flow m³/h 6604
Molecular Weight 56.9
Actual Density kg/m³ 18.7
Viscosity cP 0.009
Specific Enthalpy kcal/kg 107.33
Specific Heat Capacity kcal/(kg°C) 0.45
Thermal Conductivity kcal/(h·m·°C) 0.016
Liquid
Mass Flow Rate kg/h 123297 123297
Actual Volumetric Flow m³/h 228.3 228.3
Actual Density kg/m³ 540 540
Standard Specific Gravity 0.00 0.58 0.58
Dynamic Viscosity cP 0.13 0.13
Kinematic Viscosity cSt 0.24 0.24
Specific Enthalpy kcal/kg 26.0 26.0
Surface Tension mN/m 8.8 8.8
Specific Heat Capacity kcal/(kg°C) 0.60 0.60
Thermal Conductivity kcal/(h·m·°C) 0.081 0.081
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 3
Stream 6109 6110 6111 6112
Component (wt%)
Water 0.05 0.05 0.05
Hydrogen 0.00 0.00 0.00
Methane 0.02 0.02 0.02
Propylene 0.02 0.02 0.02
Propane 0.21 0.21 0.21
Propadiene 0.07 0.07 0.07
Isobutane 51.20 51.20 51.20
Isobutene 0.08 0.08 0.08
1-Butene 47.91 47.91 47.91
Butadiene 0.00 0.00 0.00
n-Butane 0.09 0.09 0.09
2-Butene 0.03 0.03 0.03
C5's 0.00 0.00 0.00
C6's 0.00 0.00 0.00
DIB 0.00 0.00 0.00
Methanol 0.00 0.00 0.00
TBA 0.00 0.00 0.00
DME 0.32 0.32 0.32
MTBE 0.00 0.00 0.00
MSBE 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 123297 123297 113569
Actual Volumetric Flow m³/h 228.3 228.1 210.1
Actual Density kg/m³ 540 541 541
Standard Specific Gravity 0.58 0.58 0.58
Dynamic Viscosity cP 0.13 0.13 0.13
Kinematic Viscosity cSt 0.24 0.24 0.24
Specific Enthalpy kcal/kg 26.0 26.3 26.3
Surface Tension mN/m 8.8 8.7 8.7
Specific Heat Capacity kcal/(kg°C) 0.60 0.60 0.60
Thermal Conductivity kcal/(h·m·°C) 0.081 0.081 0.081
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 3
Stream 6113 6114 6115 6116
Stream Description B-1 HEAVIES B-1 HEAVIES B-1 HEAVIES B-1 HEAVIES
COLUMN COLUMN COLUMN COLUMN #2
REFLUX AT OVERHEAD TO OVERHEAD TO BOTTOMS
COLUMN FEED B-1 LIGHTS B-1 LIGHTS
COLUMN COLUMN
Component (wt%)
Water 0.05 0.05 0.05 0.00
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.02 0.02 0.02 0.00
Propylene 0.02 0.02 0.02 0.00
Propane 0.21 0.21 0.21 0.00
Propadiene 0.07 0.07 0.07 0.00
Isobutane 51.20 51.20 51.20 0.00
Isobutene 0.08 0.08 0.08 0.00
1-Butene 47.91 47.91 47.91 1.66
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.09 0.09 0.09 56.85
2-Butene 0.03 0.03 0.03 41.48
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.00 0.00 0.00 0.00
TBA 0.00 0.00 0.00 0.00
DME 0.32 0.32 0.32 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 113569 9728 9728 8672
Actual Volumetric Flow m³/h 210.5 18.0 18.0 16.6
Actual Density kg/m³ 540 541 540 522
Standard Specific Gravity 0.58 0.58 0.60
Dynamic Viscosity cP 0.13 0.13 0.13 0.12
Kinematic Viscosity cSt 0.24 0.24 0.24 0.22
Specific Enthalpy kcal/kg 26.3 26.3 26.3 43.8
Surface Tension mN/m 8.7 8.7 8.7 7.2
Specific Heat Capacity kcal/(kg°C) 0.60 0.60 0.60 0.65
Thermal Conductivity kcal/(h·m·°C) 0.081 0.081 0.081 0.077
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 3
Stream 6117 6118 6119 6120
Component (wt%)
Water 0.00 0.00 0.00 0.00
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.00 0.00 0.00 0.00
Propylene 0.00 0.00 0.00 0.00
Propane 0.00 0.00 0.00 0.00
Propadiene 0.00 0.00 0.00 0.00
Isobutane 0.00 0.00 0.00 31.72
Isobutene 0.00 0.00 0.00 0.19
1-Butene 1.66 1.66 1.66 68.06
Butadiene 0.00 0.00 0.00 0.00
n-Butane 56.85 56.85 56.85 0.02
2-Butene 41.48 41.48 41.48 0.01
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.00 0.00 0.00 0.00
TBA 0.00 0.00 0.00 0.00
DME 0.00 0.00 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 8672 8672 8672 256782
Actual Volumetric Flow m³/h 16.6 15.4 15.4 495.4
Actual Density kg/m³ 523 563 563 518
Standard Specific Gravity 0.60 0.60 0.60 0.59
Dynamic Viscosity cP 0.12 0.14 0.14 0.11
Kinematic Viscosity cSt 0.22 0.25 0.25 0.21
Specific Enthalpy kcal/kg 43.9 25.5 25.5 37.6
Surface Tension mN/m 7.2 10.5 10.5 6.9
Specific Heat Capacity kcal/(kg°C) 0.65 0.60 0.60 0.62
Thermal Conductivity kcal/(h·m·°C) 0.077 0.087 0.087 0.077
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 3
Stream 6121 6122 6123 6124
Stream Description B-1 LIGHTS B-1 LIGHTS B-1 LIGHTS B-1 LIGHTS
COLUMN COLUMN #2 COLUMN #2 COLUMN #1
TRANSFER FEED OVERHEAD OVERHEAD
PUMP DISCH.
Component (wt%)
Water 0.00 0.00 0.00 0.04
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.00 0.00 0.00 0.04
Propylene 0.00 0.00 0.00 0.04
Propane 0.00 0.00 0.00 0.38
Propadiene 0.00 0.00 0.00 0.14
Isobutane 31.72 31.72 32.28 94.32
Isobutene 0.19 0.19 0.19 0.04
1-Butene 68.06 68.06 67.50 4.42
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.02 0.02 0.02 0.00
2-Butene 0.01 0.01 0.01 0.00
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.00 0.00 0.00 0.01
TBA 0.00 0.00 0.00 0.00
DME 0.00 0.00 0.00 0.58
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h 252336 232155
Actual Volumetric Flow m³/h 11251 10791
Molecular Weight 56.7 57.7
Actual Density kg/m³ 22.4 21.5
Viscosity cP 0.009 0.008
Specific Enthalpy kcal/kg 109.75 105.09
Specific Heat Capacity kcal/(kg°C) 0.49 0.47
Thermal Conductivity kcal/(h·m·°C) 0.017 0.017
Liquid
Mass Flow Rate kg/h 256782 256782
Actual Volumetric Flow m³/h 494.7 495.5
Actual Density kg/m³ 519 518
Standard Specific Gravity 0.59 0.59 0.00 0.00
Dynamic Viscosity cP 0.11 0.11
Kinematic Viscosity cSt 0.21 0.21
Specific Enthalpy kcal/kg 37.9 37.6
Surface Tension mN/m 6.8 6.8
Specific Heat Capacity kcal/(kg°C) 0.62 0.62
Thermal Conductivity kcal/(h·m·°C) 0.077 0.077
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 3
Stream 6125 6126 6127 6128
Component (wt%)
Water 0.04 0.04 100.00 100.00
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.04 0.04 0.00 0.00
Propylene 0.04 0.04 0.00 0.00
Propane 0.38 0.38 0.00 0.00
Propadiene 0.14 0.14 0.00 0.00
Isobutane 94.32 94.32 0.00 0.00
Isobutene 0.04 0.04 0.00 0.00
1-Butene 4.42 4.42 0.00 0.00
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.00 0.00 0.00 0.00
2-Butene 0.00 0.00 0.00 0.00
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.01 0.01 0.00 0.00
TBA 0.00 0.00 0.00 0.00
DME 0.58 0.58 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 232155 232155 4 4
Actual Volumetric Flow m³/h 443.0 443.0 0.0 0.0
Actual Density kg/m³ 524 524 990 990
Standard Specific Gravity 0.57 0.57 1.00 1.00
Dynamic Viscosity cP 0.14 0.14 0.58 0.58
Kinematic Viscosity cSt 0.26 0.26 0.58 0.58
Specific Enthalpy kcal/kg 26.9 26.9 46.5 46.5
Surface Tension mN/m 7.8 7.8 70.0 70.0
Specific Heat Capacity kcal/(kg°C) 0.62 0.62 1.00 1.00
Thermal Conductivity kcal/(h·m·°C) 0.076 0.076 0.548 0.548
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 3
Stream 6129 6130 6131 6132
Stream Description B-1 LIGHTS B-1 LIGHTS B-1 LIGHTS B-1 LIGHTS
COLUMN COLUMN COLUMN COLUMN
REFLUX PUMP REFLUX PUMP REFLUX REFLUX AT
SUCTION DISCHARGE COLUMN FEED
Component (wt%)
Water 0.04 0.04 0.04 0.04
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.04 0.04 0.04 0.04
Propylene 0.04 0.04 0.04 0.04
Propane 0.38 0.38 0.38 0.38
Propadiene 0.14 0.14 0.14 0.14
Isobutane 94.32 94.32 94.32 94.32
Isobutene 0.04 0.04 0.04 0.04
1-Butene 4.42 4.42 4.42 4.42
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.00 0.00 0.00 0.00
2-Butene 0.00 0.00 0.00 0.00
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.01 0.01 0.01 0.01
TBA 0.00 0.00 0.00 0.00
DME 0.58 0.58 0.58 0.58
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 232151 232151 226872 226872
Actual Volumetric Flow m³/h 443.0 442.5 432.4 433.3
Actual Density kg/m³ 524 525 525 524
Standard Specific Gravity 0.57 0.57 0.57 0.57
Dynamic Viscosity cP 0.14 0.14 0.14 0.14
Kinematic Viscosity cSt 0.26 0.26 0.26 0.26
Specific Enthalpy kcal/kg 26.9 27.2 27.2 27.2
Surface Tension mN/m 7.8 7.7 7.7 7.7
Specific Heat Capacity kcal/(kg°C) 0.62 0.62 0.62 0.62
Thermal Conductivity kcal/(h·m·°C) 0.076 0.076 0.076 0.076
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 3
Stream 6133 6135 6136 6137
Component (wt%)
Water 0.04 0.04 0.00 0.00
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.04 0.04 0.00 0.00
Propylene 0.04 0.04 0.00 0.00
Propane 0.38 0.38 0.00 0.00
Propadiene 0.14 0.14 0.00 0.00
Isobutane 94.32 94.32 0.01 0.01
Isobutene 0.04 0.04 0.12 0.12
1-Butene 4.42 4.42 99.60 99.60
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.00 0.00 0.19 0.19
2-Butene 0.00 0.00 0.07 0.07
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.01 0.01 0.00 0.00
TBA 0.00 0.00 0.00 0.00
DME 0.58 0.58 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h
Actual Volumetric Flow m³/h
Molecular Weight
Actual Density kg/m³
Viscosity cP
Specific Enthalpy kcal/kg
Specific Heat Capacity kcal/(kg°C)
Thermal Conductivity kcal/(h·m·°C)
Liquid
Mass Flow Rate kg/h 5280 5280 4446 4446
Actual Volumetric Flow m³/h 10.1 10.1 8.5 8.5
Actual Density kg/m³ 525 525 522 522
Standard Specific Gravity 0.57 0.57 0.60 0.60
Dynamic Viscosity cP 0.14 0.14 0.10 0.10
Kinematic Viscosity cSt 0.26 0.26 0.20 0.20
Specific Enthalpy kcal/kg 27.2 27.2 40.0 40.0
Surface Tension mN/m 7.7 7.8 6.8 6.8
Specific Heat Capacity kcal/(kg°C) 0.62 0.62 0.60 0.60
Thermal Conductivity kcal/(h·m·°C) 0.076 0.076 0.080 0.080
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 3
Stream 6138 6139 6140 6141
Component (wt%)
Water 0.00 0.00 0.00 0.00
Hydrogen 0.00 0.00 0.00 0.00
Methane 0.00 0.00 0.00 0.00
Propylene 0.00 0.00 0.00 0.00
Propane 0.00 0.00 0.00 0.00
Propadiene 0.00 0.00 0.00 0.00
Isobutane 0.01 0.01 0.00 0.00
Isobutene 0.12 0.12 0.00 0.00
1-Butene 99.60 99.60 1.73 1.73
Butadiene 0.00 0.00 0.00 0.00
n-Butane 0.19 0.19 56.96 56.96
2-Butene 0.07 0.07 41.30 41.30
C5's 0.00 0.00 0.00 0.00
C6's 0.00 0.00 0.00 0.00
DIB 0.00 0.00 0.00 0.00
Methanol 0.00 0.00 0.00 0.00
TBA 0.00 0.00 0.00 0.00
DME 0.00 0.00 0.00 0.00
MTBE 0.00 0.00 0.00 0.00
MSBE 0.00 0.00 0.00 0.00
Vapor
Mass Flow rate kg/h 138055
Actual Volumetric Flow m³/h 6405
Molecular Weight 57.2
Actual Density kg/m³ 21.6
Viscosity cP 0.009
Specific Enthalpy kcal/kg 117.95
Specific Heat Capacity kcal/(kg°C) 0.51
Thermal Conductivity kcal/(h·m·°C) 0.018
Liquid
Mass Flow Rate kg/h 4446 4446 460140 322085
Actual Volumetric Flow m³/h 7.9 7.9 880.8 616.5
Actual Density kg/m³ 561 561 522 522
Standard Specific Gravity 0.60 0.60 0.60 0.60
Dynamic Viscosity cP 0.12 0.12 0.12 0.12
Kinematic Viscosity cSt 0.22 0.22 0.22 0.22
Specific Enthalpy kcal/kg 24.6 24.6 43.8 43.8
Surface Tension mN/m 9.9 9.9 7.2 7.2
Specific Heat Capacity kcal/(kg°C) 0.57 0.57 0.65 0.65
Thermal Conductivity kcal/(h·m·°C) 0.088 0.088 0.077 0.077
-----------------------------------------------------------------------------------------------------------------------------
Case: Case 3
Stream 6142 6143
Component (wt%)
Water 0.00 0.00
Hydrogen 0.00 0.00
Methane 0.00 0.00
Propylene 0.00 0.00
Propane 0.00 0.00
Propadiene 0.00 0.00
Isobutane 0.02 0.02
Isobutene 0.12 0.12
1-Butene 99.61 99.61
Butadiene 0.00 0.00
n-Butane 0.18 0.18
2-Butene 0.07 0.07
C5's 0.00 0.00
C6's 0.00 0.00
DIB 0.00 0.00
Methanol 0.00 0.00
TBA 0.00 0.00
DME 0.00 0.00
MTBE 0.00 0.00
MSBE 0.00 0.00
Vapor
Mass Flow rate kg/h 248715
Actual Volumetric Flow m³/h 10523
Molecular Weight 56.1
Actual Density kg/m³ 23.6
Viscosity cP 0.010
Specific Enthalpy kcal/kg 113.20
Specific Heat Capacity kcal/(kg°C) 0.48
Thermal Conductivity kcal/(h·m·°C) 0.017
Liquid
Mass Flow Rate kg/h 829054 580339
Actual Volumetric Flow m³/h 1589.5 1112.7
Actual Density kg/m³ 522 522
Standard Specific Gravity 0.60 0.60
Dynamic Viscosity cP 0.10 0.10
Kinematic Viscosity cSt 0.20 0.20
Specific Enthalpy kcal/kg 40.0 40.0
Surface Tension mN/m 6.8 6.8
Specific Heat Capacity kcal/(kg°C) 0.60 0.60
Thermal Conductivity kcal/(h·m·°C) 0.080 0.080
CB&I ORPIC
"THIS DOCUMENT IS THE PROPERTY OF CHICAGO BRIDGE & IRON COMPANY (CBI). IT MAY CONTAIN PROPRIETARY
INFORMATION (CBI BACKGROUND & FOREGROUND INFORMATION) OWNED BY CBI AND DEEMED TO BE
COMMERCIALLY SENSITIVE. IT IS TO BE USED ONLY IN CONNECTION WITH WORK PERFORMED BY CBI.
REPRODUCTION IN WHOLE OR IN PART FOR ANY PURPOSE OTHER THAN WORK PERFORMED BY CBI IS FORBIDDEN
EXCEPT BY EXPRESS WRITTEN PERMISSION OF CBI. IT IS TO BE SAFEGUARDED AGAINST BOTH DELIBERATE AND
Page 1 of 8
Liwa Plastics Project
Document Title
- This document contains the Material & Heat balance for the Catalyst Treatment Gas System.
- For the Material & Heat balances for the licensed Process unit, please refer to the following Axens documents:
1st Stage Activation
Name H2 N2 PA MS 201 202 203 204 205 206 207 208 209 210 211 212 213 214 215
MEDIUM
HYDROGEN PRESSURE H2 BEFORE N2 BEFORE PA BEFORE MS BEFORE ELECTRIC ELECTRIC 1ST STAGE 2ND STAGE 1ST STAGE 2ND STAGE MIXTURE MIXTURE
NITROGEN PLANT AIR TO KO TO SAFE
MAKE‐UP STEAM CONTROL CONTROL CONTROL CONTROL HEATER HEATER REACTOR REACTOR REACTOR REACTOR COOLER COOLER TO FLARE
FEED FEED DRUM LOCATION
FEED FEED FEED VALVE VALVE VALVE VALVE INLET OUTLET INLET INLET OUTLET OUTLET INLET OUTLET
FEED
Temperature (C) 45 10 45 10 19 410 410 410 410 300 300
Pressure (bara) 31.4 8.0 31.4 7.9 7.3 7.0 7.0 6.0 6.0 5.7 1.5
Weight rate (kg/h) 60 2340 60 2340 2400 2400 2400 2400 2400 2400 2400
Molar rate (kmol/h) 29.8 83.5 29.8 83.5 113.3 113.3 113.3 113.3 113.3 113.3 113.3
Volumetric rate (m3/h) 25.4 244.7 25.4 246.6 376.1 921.4 921.4 1074.7 1074.7 949.0 3601.2
Enthalpy (MMkcal/h) 0.00407 ‐0.0101 0.00407 ‐0.0101 ‐0.00631 0.311 0.311 0.311 0.311 0.220 0.220
Spec. Enthalpy (kcal/kg) 67.8 ‐4.3 67.8 ‐4.3 ‐2.6 129.4 129.4 129.4 129.4 91.6 91.6
Density (kg/m3) 2.366 9.564 2.366 9.489 6.382 2.605 2.605 2.233 2.233 2.529 0.666
Mol. Weight 2.02 28.01 2.02 28.01 21.18 21.18 21.18 21.18 21.18 21.18 21.18
Viscosity (cP) 0.0094 0.0177 0.0094 0.0177 0.0163 0.0313 0.0313 0.0313 0.0313 0.0269 0.0269
Thermal. Cond. (kcal/h.m.C) 0.160 0.022 0.160 0.022 0.038 0.072 0.072 0.072 0.072 0.064 0.064
Specific Heat (kcal/kg.C) 3.398 0.252 3.398 0.252 0.330 0.347 0.347 0.347 0.347 0.341 0.341
Cp/Cv 1.419 1.418 1.419 1.418 1.414 1.373 1.373 1.372 1.372 1.381 1.380
Z‐factor 1.011 0.995 1.011 0.995 0.999 1.002 1.002 1.002 1.002 1.002 1.000
1st Stage Reactivation
Name H2 N2 PA MS 201 202 203 204 205 206 207 208 209 210 211 212 213 214 215
MEDIUM
HYDROGEN H2 BEFORE N2 BEFORE PA BEFORE MS BEFORE ELECTRIC ELECTRIC 1ST STAGE 2ND STAGE 1ST STAGE 2ND STAGE MIXTURE MIXTURE
NITROGEN PLANT AIR PRESSURE TO KO TO SAFE
MAKE‐UP CONTROL CONTROL CONTROL CONTROL HEATER HEATER REACTOR REACTOR REACTOR REACTOR COOLER COOLER TO FLARE
FEED FEED STEAM DRUM LOCATION
FEED VALVE VALVE VALVE VALVE INLET OUTLET INLET INLET OUTLET OUTLET INLET OUTLET
FEED
Temperature (C) 45 10 45 10 19 160 160 160 160 100 100
Pressure (bara) 31.4 8.0 31.4 7.9 7.3 7.0 7.0 6.0 6.0 5.7 1.5
Weight rate (kg/h) 60 2340 60 2340 2400 2400 2400 2400 2400 2400 2400
Molar rate (kmol/h) 29.8 83.5 29.8 83.5 113.3 113.3 113.3 113.3 113.3 113.3 113.3
Volumetric rate (m3/h) 25.4 244.7 25.4 246.6 376.1 584.0 584.0 681.1 681.1 617.3 2341.6
Enthalpy (MMkcal/h) 0.00407 ‐0.0101 0.00407 ‐0.0101 ‐0.00631 0.106 0.106 0.106 0.106 0.0584 0.0584
Spec. Enthalpy (kcal/kg) 67.8 ‐4.3 67.8 ‐4.3 ‐2.6 44.3 44.3 44.3 44.3 24.3 24.3
Density (kg/m3) 2.366 9.564 2.366 9.489 6.382 4.110 4.110 3.524 3.524 3.888 1.025
Mol. Weight 2.02 28.01 2.02 28.01 21.18 21.18 21.18 21.18 21.18 21.18 21.18
Viscosity (cP) 0.0094 0.0177 0.0094 0.0177 0.0163 0.0216 0.0216 0.0216 0.0216 0.0193 0.0193
Thermal. Cond. (kcal/h.m.C) 0.160 0.022 0.160 0.022 0.038 0.052 0.052 0.052 0.052 0.046 0.046
Specific Heat (kcal/kg.C) 3.398 0.252 3.398 0.252 0.330 0.335 0.335 0.335 0.335 0.332 0.331
Cp/Cv 1.419 1.418 1.419 1.418 1.414 1.395 1.395 1.394 1.394 1.401 1.398
Z‐factor 1.011 0.995 1.011 0.995 0.999 1.002 1.002 1.002 1.002 1.001 1.000
3 of 8
Rev. 0 23FEB2015
Liwa Plastics Project Document Title: Material Heat Balance - Unit 6200
Document No.: S-S620-5223-121
1st Stage Hot Hydrogen Stripping
H2 MAKE‐
UP FROM N2 FROM PA FROM MS FROM
Name B.L. B.L. B.L. B.L. 201 202 203 204 205 206 207 208 209 210 211 212 213 214 215
MEDIUM
HYDROGEN H2 BEFORE N2 BEFORE PA BEFORE MS BEFORE ELECTRIC ELECTRIC 1ST STAGE 2ND STAGE 1ST STAGE 2ND STAGE MIXTURE MIXTURE
NITROGEN PLANT AIR PRESSURE TO KO TO SAFE
MAKE‐UP CONTROL CONTROL CONTROL CONTROL HEATER HEATER REACTOR REACTOR REACTOR REACTOR COOLER COOLER TO FLARE
FEED FEED STEAM DRUM LOCATION
FEED VALVE VALVE VALVE VALVE INLET OUTLET INLET INLET OUTLET OUTLET INLET OUTLET
FEED
Temperature (C) 45 10 45 10 19 410 410 410 410 300 300
Pressure (bara) 31.4 8.0 31.4 7.9 7.3 7.0 7.0 6.0 6.0 5.7 1.5
Weight rate (kg/h) 60 2340 60 2340 2400 2400 2400 2400 2400 2400 2400
Molar rate (kmol/h) 29.8 83.5 29.8 83.5 113.3 113.3 113.3 113.3 113.3 113.3 113.3
Volumetric rate (m3/h) 25.4 244.7 25.4 246.6 376.1 921.4 921.4 1074.7 1074.7 949.0 3601.2
Enthalpy (MMkcal/h) 0.00407 ‐0.0101 0.00407 ‐0.0101 ‐0.00631 0.311 0.3107 0.3107 0.3107 0.2199 0.2199
Spec. Enthalpy (kcal/kg) 67.8 ‐4.3 67.8 ‐4.3 ‐2.6 129.4 129.4 129.4 129.4 91.6 91.6
Density (kg/m3) 2.366 9.564 2.366 9.489 6.382 2.605 2.605 2.233 2.233 2.529 0.666
Mol. Weight 2.02 28.01 2.02 28.01 21.18 21.18 21.18 21.18 21.18 21.18 21.18
Viscosity (cP) 0.0094 0.0177 0.0094 0.0177 0.0163 0.0313 0.0313 0.0313 0.0313 0.0269 0.0269
Thermal. Cond. (kcal/h.m.C) 0.160 0.022 0.160 0.022 0.038 0.072 0.072 0.072 0.072 0.064 0.064
Specific Heat (kcal/kg.C) 3.398 0.252 3.398 0.252 0.330 0.347 0.347 0.347 0.347 0.341 0.341
Cp/Cv 1.419 1.418 1.419 1.418 1.414 1.373 1.373 1.372 1.372 1.381 1.380
Z‐factor 1.011 0.995 1.011 0.995 0.999 1.002 1.002 1.002 1.002 1.002 1.000
1st Stage Purge/Heating
Name H2 N2 PA MS 201 202 203 204 205 206 207 208 209 210 211 212 213 214 215
MEDIUM
HYDROGEN H2 BEFORE N2 BEFORE PA BEFORE MS BEFORE ELECTRIC ELECTRIC 1ST STAGE 2ND STAGE 1ST STAGE 2ND STAGE MIXTURE MIXTURE
NITROGEN PLANT AIR PRESSURE TO KO TO SAFE
MAKE‐UP CONTROL CONTROL CONTROL CONTROL HEATER HEATER REACTOR REACTOR REACTOR REACTOR COOLER COOLER TO FLARE
FEED FEED STEAM DRUM LOCATION
FEED VALVE VALVE VALVE VALVE INLET OUTLET INLET INLET OUTLET OUTLET INLET OUTLET
FEED
Temperature (C) 10 10 10 200 200 200 200 150 150
Pressure (bara) 8.0 7.4 7.3 7.0 7.0 6.0 6.0 5.7 1.5
Weight rate (kg/h) 3100 3100 3100 3100 3100 3100 3100 3100 3100
Molar rate (kmol/h) 110.7 110.7 110.7 110.7 110.7 110.7 110.7 110.7 110.7
Volumetric rate (m3/h) 324.1 348.6 355.3 623.5 623.5 727.1 727.1 684.2 2595.0
Enthalpy (MMkcal/h) ‐0.0133 ‐0.0133 ‐0.0136 0.136 0.136 0.136 0.136 0.0967 0.0967
Spec. Enthalpy (kcal/kg) ‐4.3 ‐4.3 ‐4.4 44.0 44.0 44.0 44.0 31.2 31.2
Density (kg/m3) 9.564 8.892 8.727 4.973 4.973 4.264 4.264 4.531 1.195
Mol. Weight 28.01 28.01 28.00 28.00 28.00 28.00 28.00 28.00 28.00
Viscosity (cP) 0.0177 0.0177 0.0177 0.0256 0.0256 0.0256 0.0256 0.0236 0.0235
Thermal. Cond. (kcal/h.m.C) 0.022 0.022 0.022 0.032 0.032 0.032 0.032 0.029 0.029
Specific Heat (kcal/kg.C) 0.252 0.252 0.252 0.258 0.258 0.257 0.257 0.255 0.255
Cp/Cv 1.418 1.417 1.417 1.386 1.386 1.386 1.386 1.391 1.388
Z‐factor 0.995 0.996 0.996 1.002 1.002 1.002 1.002 1.001 1.000
4 of 8
Rev. 0 23FEB2015
Liwa Plastics Project Document Title: Material Heat Balance - Unit 6200
Document No.: S-S620-5223-121
1st Stage Preoxidation
Name H2 N2 PA MS 201 202 203 204 205 206 207 208 209 210 211 212 213 214 215
MEDIUM
HYDROGEN H2 BEFORE N2 BEFORE PA BEFORE MS BEFORE ELECTRIC ELECTRIC 1ST STAGE 2ND STAGE 1ST STAGE 2ND STAGE MIXTURE MIXTURE
NITROGEN PLANT AIR PRESSURE TO KO TO SAFE
MAKE‐UP CONTROL CONTROL CONTROL CONTROL HEATER HEATER REACTOR REACTOR REACTOR REACTOR COOLER COOLER TO FLARE
FEED FEED STEAM DRUM LOCATION
FEED VALVE VALVE VALVE VALVE INLET OUTLET INLET INLET OUTLET OUTLET INLET OUTLET
FEED
Temperature (C) 10 280 10 280 264 264 264 263 263 210 204 204
Pressure (bara) 8.0 19.0 8.0 18.7 7.3 7.0 7.0 6.0 6.0 5.7 1.5 1.5
Weight rate (kg/h) 55 2400 55 2400 2455 2455 2455 2455 2455 2455 2455 2455
Molar rate (kmol/h) 1.9 133.2 1.9 133.2 135.2 135.2 135.2 135.2 135.2 135.2 135.2 135.2
Volumetric rate (m3/h) 5.6 304.6 5.6 308.8 807.2 844.0 844.0 985.6 985.6 930.0 3554.8 3556.7
Enthalpy (MMkcal/h) 0.00 ‐7.44 ‐0.000228 ‐7.44 ‐7.44 ‐7.44 ‐7.44 ‐7.44 ‐7.44 ‐7.50 ‐7.50 ‐7.50
Spec. Enthalpy (kcal/kg) ‐4.1 ‐3101.3 ‐4.1 ‐3101.3 ‐3031.7 ‐3031.3 ‐3031.3 ‐3031.3 ‐3031.3 ‐3056.3 ‐3056.3 ‐3056.3
Density (kg/m3) 9.903 7.879 9.903 7.771 3.042 2.909 2.909 2.491 2.491 2.640 0.691 0.690
Mol. Weight 28.95 18.02 28.95 18.02 18.16 18.16 18.16 18.16 18.16 18.16 18.16 18.16
Viscosity (cP) 0.0182 0.0193 0.0182 0.0193 0.0141 0.0141 0.0141 0.0140 0.0140 0.0125 0.0122 0.0122
Thermal. Cond. (kcal/h.m.C) 0.021 0.038 0.021 0.037 0.035 0.035 0.035 0.035 0.035 0.030 0.029 0.029
Specific Heat (kcal/kg.C) 0.240 0.510 0.240 0.509 0.481 0.480 0.480 0.479 0.479 0.473 0.464 0.464
Cp/Cv 1.428 1.373 1.428 1.372 1.330 1.329 1.329 1.325 1.325 1.338 1.318 1.318
Z‐factor 0.993 0.945 0.993 0.945 0.978 0.979 0.979 0.982 0.982 0.976 0.994 0.994
1st Stage Combustion
Name H2 N2 PA MS 201 202 203 204 205 206 207 208 209 210 211 212 213 214 215
MEDIUM
HYDROGEN H2 BEFORE N2 BEFORE PA BEFORE MS BEFORE ELECTRIC ELECTRIC 1ST STAGE 2ND STAGE 1ST STAGE 2ND STAGE MIXTURE MIXTURE
NITROGEN PLANT AIR PRESSURE TO KO TO SAFE
MAKE‐UP CONTROL CONTROL CONTROL CONTROL HEATER HEATER REACTOR REACTOR REACTOR REACTOR COOLER COOLER TO FLARE
FEED FEED STEAM DRUM LOCATION
FEED VALVE VALVE VALVE VALVE INLET OUTLET INLET INLET OUTLET OUTLET INLET OUTLET
FEED
Temperature (C) 10 280 10 280 235 410 410 409 409 300 296 296
Pressure (bara) 8.0 19.0 8.0 18.7 7.3 7.0 7.0 6.0 6.0 5.7 1.5 1.5
Weight rate (kg/h) 650 2400 650 2400 3050 3050 3050 3050 3050 3050 3050 3050
Molar rate (kmol/h) 22.5 133.2 22.5 133.2 155.7 155.7 155.7 155.7 155.7 155.7 155.7 155.7
Volumetric rate (m3/h) 65.6 304.6 65.6 308.8 882.0 1254.1 1254.1 1463.4 1463.4 1287.5 4902.4 4907.5
Enthalpy (MMkcal/h) ‐0.00269 ‐7.44 ‐0.00269 ‐7.44 ‐7.45 ‐7.21 ‐7.21 ‐7.21 ‐7.21 ‐7.36 ‐7.36 ‐7.36
Spec. Enthalpy (kcal/kg) ‐4.1 ‐3101.3 ‐4.1 ‐3101.3 ‐2441.1 ‐2363.9 ‐2363.9 ‐2363.9 ‐2363.9 ‐2412.4 ‐2412.4 ‐2412.4
Density (kg/m3) 9.903 7.879 9.902 7.771 3.458 2.432 2.432 2.084 2.084 2.369 0.622 0.622
Mol. Weight 28.95 18.02 28.95 18.02 19.59 19.59 19.59 19.59 19.59 19.59 19.59 19.59
Viscosity (cP) 0.0182 0.0193 0.0182 0.0193 0.0147 0.0207 0.0207 0.0206 0.0206 0.0168 0.0166 0.0166
Thermal. Cond. (kcal/h.m.C) 0.021 0.038 0.021 0.037 0.032 0.047 0.047 0.047 0.047 0.038 0.037 0.037
Specific Heat (kcal/kg.C) 0.240 0.510 0.240 0.509 0.433 0.451 0.451 0.450 0.450 0.437 0.432 0.432
Cp/Cv 1.428 1.373 1.428 1.372 1.342 1.305 1.305 1.304 1.304 1.322 1.312 1.312
Z‐factor 0.993 0.945 0.993 0.945 0.979 0.993 0.993 0.994 0.994 0.989 0.997 0.997
5 of 8
Rev. 0 23FEB2015
Liwa Plastics Project Document Title: Material Heat Balance - Unit 6200
Document No.: S-S620-5223-121
1st Stage Polishing
Name H2 N2 PA MS 201 202 203 204 205 206 207 208 209 210 211 212 213 214 215
MEDIUM
HYDROGEN H2 BEFORE N2 BEFORE PA BEFORE MS BEFORE ELECTRIC ELECTRIC 1ST STAGE 2ND STAGE 1ST STAGE 2ND STAGE MIXTURE MIXTURE
NITROGEN PLANT AIR PRESSURE TO KO TO SAFE
MAKE‐UP CONTROL CONTROL CONTROL CONTROL HEATER HEATER REACTOR REACTOR REACTOR REACTOR COOLER COOLER TO FLARE
FEED FEED STEAM DRUM LOCATION
FEED VALVE VALVE VALVE VALVE INLET OUTLET INLET INLET OUTLET OUTLET INLET OUTLET
FEED
Temperature (C) 10 280 10 280 235 480 480 480 480 300 296 296
Pressure (bara) 8.0 19.0 8.0 18.7 7.3 7.0 7.0 6.0 6.0 5.7 1.5 1.5
Weight rate (kg/h) 650 2400 650 2400 3050 3050 3050 3050 3050 3050 3050 3050
Molar rate (kmol/h) 22.5 133.2 22.5 133.2 155.7 155.7 155.7 155.7 155.7 155.7 155.7 155.7
Volumetric rate (m3/h) 65.6 304.6 65.6 308.8 882.0 1385.8 1385.8 1617.0 1617.0 1287.5 4902.4 4907.5
Enthalpy (MMkcal/h) ‐0.00269 ‐7.44 ‐0.00269 ‐7.44 ‐7.45 ‐7.11 ‐7.11 ‐7.11 ‐7.11 ‐7.36 ‐7.36 ‐7.36
Spec. Enthalpy (kcal/kg) ‐4.1 ‐3101.3 ‐4.1 ‐3101.3 ‐2441.1 ‐2332.0 ‐2332.0 ‐2332.0 ‐2332.0 ‐2412.4 ‐2412.4 ‐2412.4
Density (kg/m3) 9.903 7.879 9.902 7.771 3.458 2.201 2.201 1.886 1.886 2.369 0.622 0.622
Mol. Weight 28.95 18.02 28.95 18.02 19.59 19.59 19.59 19.59 19.59 19.59 19.59 19.59
Viscosity (cP) 0.0182 0.0193 0.0182 0.0193 0.0147 0.0232 0.0232 0.0231 0.0231 0.0168 0.0166 0.0166
Thermal. Cond. (kcal/h.m.C) 0.021 0.038 0.021 0.037 0.032 0.053 0.053 0.053 0.053 0.038 0.037 0.037
Specific Heat (kcal/kg.C) 0.240 0.510 0.240 0.509 0.433 0.460 0.460 0.459 0.459 0.437 0.432 0.432
Cp/Cv 1.428 1.373 1.428 1.372 1.342 1.294 1.294 1.293 1.293 1.322 1.312 1.312
Z‐factor 0.993 0.945 0.993 0.945 0.979 0.995 0.995 0.996 0.996 0.989 0.997 0.997
2nd Stage Purge/Heating
Name H2 N2 PA MS 201 202 203 204 205 206 207 208 209 210 211 212 213 214 215
MEDIUM
HYDROGEN H2 BEFORE N2 BEFORE PA BEFORE MS BEFORE ELECTRIC ELECTRIC 1ST STAGE 2ND STAGE 1ST STAGE 2ND STAGE MIXTURE MIXTURE
NITROGEN PLANT AIR PRESSURE TO KO TO SAFE
MAKE‐UP CONTROL CONTROL CONTROL CONTROL HEATER HEATER REACTOR REACTOR REACTOR REACTOR COOLER COOLER TO FLARE
FEED FEED STEAM DRUM LOCATION
FEED VALVE VALVE VALVE VALVE INLET OUTLET INLET INLET OUTLET OUTLET INLET OUTLET
FEED
Temperature (C) 10 10 10 200 200 200 200 150 150
Pressure (bara) 8.0 7.4 7.3 7.0 7.0 6.0 6.0 5.7 1.5
Weight rate (kg/h) 3300 3300 3300 3300 3300 3300 3300 3300 3300
Molar rate (kmol/h) 117.8 117.8 117.9 117.9 117.9 117.9 117.9 117.9 117.9
Volumetric rate (m3/h) 345.0 374.9 378.2 663.7 663.7 773.9 773.9 728.3 2762.4
Enthalpy (MMkcal/h) ‐0.0142 ‐0.0142 ‐0.0145 0.145 0.145 0.145 0.145 0.103 0.103
Spec. Enthalpy (kcal/kg) ‐4.3 ‐4.3 ‐4.4 44.0 44.0 44.0 44.0 31.2 31.2
Density (kg/m3) 9.564 8.801 8.727 4.973 4.973 4.264 4.264 4.531 1.195
Mol. Weight 28.01 28.01 28.00 28.00 28.00 28.00 28.00 28.00 28.00
Viscosity (cP) 0.0177 0.0177 0.0177 0.0256 0.0256 0.0256 0.0256 0.0236 0.0235
Thermal. Cond. (kcal/h.m.C) 0.022 0.022 0.022 0.032 0.032 0.032 0.032 0.029 0.029
Specific Heat (kcal/kg.C) 0.252 0.252 0.252 0.258 0.258 0.257 0.257 0.255 0.255
Cp/Cv 1.418 1.417 1.417 1.386 1.386 1.386 1.386 1.391 1.388
Z‐factor 0.995 0.996 0.996 1.002 1.002 1.002 1.002 1.001 1.000
6 of 8
Rev. 0 23FEB2015
Liwa Plastics Project Document Title: Material Heat Balance - Unit 6200
Document No.: S-S620-5223-121
2nd Stage Steam Stripping
Name H2 N2 PA MS 201 202 203 204 205 206 207 208 209 210 211 212 213 214 215
MEDIUM
HYDROGEN H2 BEFORE N2 BEFORE PA BEFORE MS BEFORE ELECTRIC ELECTRIC 1ST STAGE 2ND STAGE 1ST STAGE 2ND STAGE MIXTURE MIXTURE
NITROGEN PLANT AIR PRESSURE TO KO TO SAFE
MAKE‐UP CONTROL CONTROL CONTROL CONTROL HEATER HEATER REACTOR REACTOR REACTOR REACTOR COOLER COOLER TO FLARE
FEED FEED STEAM DRUM LOCATION
FEED VALVE VALVE VALVE VALVE INLET OUTLET INLET INLET OUTLET OUTLET INLET OUTLET
FEED
Temperature (C) 280 278 267 410 410 409 409 300 296 296
Pressure (bara) 19.0 17.4 7.3 7.0 7.0 6.0 6.0 5.7 1.5 1.5
Weight rate (kg/h) 6050 6050 6050 6050 6050 6050 6050 6050 6050 6050
Molar rate (kmol/h) 335.8 335.8 335.9 335.9 335.9 335.9 335.9 335.9 335.9 335.9
Volumetric rate (m3/h) 767.9 841.3 2008.2 2698.0 2698.0 3148.8 3148.8 2767.4 10549.3 10593.0
Enthalpy (MMkcal/h) ‐18.8 ‐18.8 ‐18.8 ‐18.3 ‐18.3 ‐18.3 ‐18.3 ‐18.7 ‐18.7 ‐18.7
Spec. Enthalpy (kcal/kg) ‐3101.3 ‐3101.3 ‐3101.1 ‐3030.1 ‐3030.1 ‐3030.1 ‐3030.1 ‐3084.1 ‐3084.1 ‐3084.1
Density (kg/m3) 7.879 7.191 3.013 2.243 2.243 1.921 1.921 2.186 0.574 0.571
Mol. Weight 18.02 18.02 18.01 18.01 18.01 18.01 18.01 18.01 18.01 18.01
Viscosity (cP) 0.0193 0.0192 0.0188 0.0248 0.0248 0.0248 0.0248 0.0202 0.0201 0.0201
Thermal. Cond. (kcal/h.m.C) 0.038 0.037 0.035 0.049 0.049 0.049 0.049 0.038 0.037 0.037
Specific Heat (kcal/kg.C) 0.510 0.506 0.487 0.504 0.504 0.503 0.503 0.488 0.481 0.481
Cp/Cv 1.373 1.367 1.329 1.298 1.298 1.296 1.296 1.316 1.304 1.304
Z‐factor 0.945 0.949 0.977 0.990 0.990 0.991 0.991 0.986 0.996 0.996
2nd Stage Combustion
Name H2 N2 PA MS 201 202 203 204 205 206 207 208 209 210 211 212 213 214 215
MEDIUM
HYDROGEN H2 BEFORE N2 BEFORE PA BEFORE MS BEFORE ELECTRIC ELECTRIC 1ST STAGE 2ND STAGE 1ST STAGE 2ND STAGE MIXTURE MIXTURE
NITROGEN PLANT AIR PRESSURE TO KO TO SAFE
MAKE‐UP CONTROL CONTROL CONTROL CONTROL HEATER HEATER REACTOR REACTOR REACTOR REACTOR COOLER COOLER TO FLARE
FEED FEED STEAM DRUM LOCATION
FEED VALVE VALVE VALVE VALVE INLET OUTLET INLET INLET OUTLET OUTLET INLET OUTLET
FEED
Temperature (C) 10 280 10 278 235 410 410 409 409 300 296 296
Pressure (bara) 8.0 19.0 8.0 17.4 7.4 7.0 7.0 6.0 6.0 5.7 1.5 1.5
Weight rate (kg/h) 1650 6050 1650 6050 7700 7700 7700 7700 7700 7700 7700 7700
Molar rate (kmol/h) 57.0 335.8 57.0 335.8 392.9 392.9 392.9 392.9 392.9 392.9 392.9 392.9
Volumetric rate (m3/h) 166.6 767.9 166.7 841.3 2211.8 3164.0 3164.0 3692.1 3692.1 3248.2 12368.1 12440.6
Enthalpy (MMkcal/h) ‐0.00683 ‐18.8 ‐0.00683 ‐18.8 ‐18.8 ‐18.2 ‐18.2 ‐18.2 ‐18.2 ‐18.5 ‐18.5 ‐18.5
Spec. Enthalpy (kcal/kg) ‐4.1 ‐3101.3 ‐4.1 ‐3101.3 ‐2437.6 ‐2360.4 ‐2360.4 ‐2360.4 ‐2360.4 ‐2408.8 ‐2408.8 ‐2408.8
Density (kg/m3) 9.903 7.879 9.898 7.191 3.481 2.434 2.434 2.086 2.086 2.371 0.623 0.619
Mol. Weight 28.95 18.02 28.95 18.02 19.60 19.60 19.60 19.60 19.60 19.60 19.60 19.60
Viscosity (cP) 0.0182 0.0193 0.0182 0.0192 0.0147 0.0207 0.0207 0.0206 0.0206 0.0168 0.0166 0.0166
Thermal. Cond. (kcal/h.m.C) 0.021 0.038 0.021 0.037 0.032 0.047 0.047 0.047 0.047 0.038 0.037 0.037
Specific Heat (kcal/kg.C) 0.240 0.510 0.240 0.506 0.432 0.451 0.451 0.450 0.450 0.437 0.432 0.432
Cp/Cv 1.428 1.373 1.428 1.367 1.342 1.305 1.305 1.304 1.304 1.322 1.312 1.312
Z‐factor 0.993 0.945 0.993 0.949 0.979 0.993 0.993 0.994 0.994 0.989 0.997 0.997
7 of 8
Rev. 0 23FEB2015
Liwa Plastics Project Document Title: Material Heat Balance - Unit 6200
Document No.: S-S620-5223-121
2nd Stage Polishing
Name H2 N2 PA MS 201 202 203 204 205 206 207 208 209 210 211 212 213 214 215
MEDIUM
HYDROGEN H2 BEFORE N2 BEFORE PA BEFORE MS BEFORE ELECTRIC ELECTRIC 1ST STAGE 2ND STAGE 1ST STAGE 2ND STAGE MIXTURE MIXTURE
NITROGEN PLANT AIR PRESSURE TO KO TO SAFE
MAKE‐UP CONTROL CONTROL CONTROL CONTROL HEATER HEATER REACTOR REACTOR REACTOR REACTOR COOLER COOLER TO FLARE
FEED FEED STEAM DRUM LOCATION
FEED VALVE VALVE VALVE VALVE INLET OUTLET INLET INLET OUTLET OUTLET INLET OUTLET
FEED
Temperature (C) 10 280 10 278 180 480 480 480 480 300 298 298
Pressure (bara) 8.0 19.0 8.0 17.4 7.4 7.0 7.0 6.0 6.0 5.7 1.5 1.5
Weight rate (kg/h) 5950 6050 5950 6050 12000 12000 12000 12000 12000 12000 12000 12000
Molar rate (kmol/h) 205.5 335.8 205.5 335.8 541.4 541.4 541.4 541.4 541.4 541.4 541.4 541.4
Volumetric rate (m3/h) 600.9 767.9 604.4 841.3 2711.7 4831.3 4831.3 5636.1 5636.1 4497.6 17100.5 17312.7
Enthalpy (MMkcal/h) ‐0.0246 ‐18.8 ‐0.0246 ‐18.8 ‐18.8 ‐17.4 ‐17.4 ‐17.4 ‐17.4 ‐18.3 ‐18.3 ‐18.3
Spec. Enthalpy (kcal/kg) ‐4.1 ‐3101.3 ‐4.1 ‐3101.3 ‐1565.6 ‐1453.6 ‐1453.6 ‐1453.6 ‐1453.6 ‐1521.5 ‐1521.5 ‐1521.5
Density (kg/m3) 9.903 7.879 9.844 7.191 4.425 2.484 2.484 2.129 2.129 2.668 0.702 0.693
Mol. Weight 28.95 18.02 28.95 18.02 22.16 22.16 22.16 22.16 22.16 22.16 22.16 22.16
Viscosity (cP) 0.0182 0.0193 0.0182 0.0192 0.0159 0.0276 0.0276 0.0276 0.0276 0.0206 0.0205 0.0205
Thermal. Cond. (kcal/h.m.C) 0.021 0.038 0.021 0.037 0.029 0.050 0.050 0.050 0.050 0.037 0.037 0.037
Specific Heat (kcal/kg.C) 0.240 0.510 0.240 0.506 0.362 0.388 0.388 0.387 0.387 0.370 0.367 0.367
Cp/Cv 1.428 1.373 1.428 1.367 1.363 1.309 1.309 1.308 1.308 1.335 1.327 1.327
Z‐factor 0.993 0.945 0.993 0.949 0.982 0.998 0.998 0.998 0.998 0.994 0.998 0.998
8 of 8
Rev. 0 23FEB2015
Petrochemical Plant Sohar Environmental Impact Assessment Report
Orpic and CB&I HMR #3817
CB&I ORPIC
Document Title: Process Description - MTBE & BUT-1 6000 & 6100
Page 1 of 10
"THIS DOCUMENT IS THE PROPERTY OF CHICAGO BRIDGE & IRON COMPANY (CB&I). IT MAY CONTAIN INFORMATION
DESCRIBING TECHNOLOGY OWNED BY CB&I AND DEEMED TO BE COMMERCIALLY SENSITIVE. IT IS TO BE USED ONLY IN
CONNECTION WITH WORK PERFORMED BY CB&I. REPRODUCTION IN WHOLE OR IN PART FOR ANY PURPOSE OTHER THAN
WORK PERFORMED BY CB&I IS FORBIDDEN EXCEPT BY EXPRESS WRITTEN PERMISSION OF CB&I. IT IS TO BE SAFEGUARDED
AGAINST BOTH DELIBERATE AND INADVERTENT DISCLOSURE TO ANY THIRD PARTY."
Liwa Plastics Project
Page 2 of 10
Liwa Plastics Project
Table of Contents
Contents Page
1.0 INTRODUCTION..................................................................................................................................4
2.0 PROCESS DESCRIPTION...................................................................................................................5
2.1 MTBE Unit (6000)......................................................................................................................5
2.2 B-1 Unit (6100) ..........................................................................................................................8
2.3 MTBE Unit Drain Drum Pit Z-60001 (6000 & 6100) ..................................................................9
2.4 MTBE Unit Rain Water Collection Pit Z-60002 (6000 & 6100) .................................................9
2.5 Flare Knock Out Drum V-60006 (6000 & 6100) ......................................................................10
Page 3 of 10
Liwa Plastics Project
1.0 INTRODUCTION
Oman Oil Refineries and Petrochemicals Industries Company (ORPIC) is currently executing a major
project to improve their existing Sohar Refinery located in the Sultanate of Oman, which is referred to as
the Sohar Refinery Improvement Project (SRIP).
In addition to SRIP, ORPIC is planning the installation of a new petrochemical complex in Sohar, adjacent
to SRIP, which will be part of the Liwa Plastics Project (LPP).
The new petrochemical complex will include a Steam Cracker Unit (SCU) designed to produce polymer
grade ethylene and polymer grade propylene, Refinery Dry Gas (RDG) Unit, NGL Treating and
Fractionation Unit, Selective C4’s Hydrogenation Unit, MTBE Unit, Butene-1 Recovery Unit, Pygas
Hydrotreating Unit, High Density Polyethylene (HDPE) Plant, Linear Low Density Polyethylene Plant
(LLDPE), Polypropylene (PP) Plant and associated Utility, Offsite and Storage Facilities.
The petrochemical plant will be integrated with the existing Sohar Refinery, Sohar Aromatics Plant (AP)
and Sohar PP plant.
Page 4 of 10
Liwa Plastics Project
This document describes the Process Flow Scheme of the MTBE and Butene-1 (B-1) Unit as shown on the
Process Flow Diagrams.
The hydrocarbon feed to the unit is supplied from the upstream Selective C4 Hydrogenation unit
(SLC4HY). The Hydrogenated C4 feed is washed with countercurrent stream of deaerated demineralized
water from OSBL to the Water Wash Column, C-60001. This extraction column is composed of 24 sieve
trays with a coalescer pad at its top section. The demineralized water quantity used for washing is typically
˚
30% of the feed rate of the hydrocarbons. The wash water temperature requirement is 40 C or lower. Any
temperature higher than 40˚C adversely impacts the efficiency of acetonitrile removal and increases the
hydrocarbon losses in the effluent water. The washing process removes catalyst poisons such as metal
ions, acetonitrile, some propionitrile and other basic nitrogen compounds. The process wastewater from
the bottom of C-60001 is then sent to a waste water unit at OSBL.
The washed mixed C4 stream is collected in the C4 Feed Surge Drum, V-60001, with a coalescer to
remove any residual free water. From this drum, it is then transported to the MTBE reaction system via C4
Feed Pumps, P-60001A/B. An analyzer is available at the outlet of this pump to determine the composition
of the mixed C4s, especially isobutylene, present in the feed. A calculator block determines the required
methanol flow to be fed to the Primary Reactors R-60001A/B and to the catalytic section of the CD
Reaction Column, C-60002.
The combined C4s feed from the C4 Feed surge Drum, V-60001 is mixed with a fresh and recycled
methanol stream. A Reactor Feed Preheater, E-60001 is provided to reach the required inlet temperature
during the start-up (in case feed C4 feed temperature lower than 40°C). LLP steam supplies the necessary
heat to the feed preheater.
The feed is combined with the recycle stream of the Primary Reactor effluent via the Primary Reactor Feed
Mixer, M-60001, to ensure a homogeneous mixture. The mixture is then fed to Primary Reactors, R-
60001A/B. These reactors are fixed-bed down-flow adiabatic reactors. One Primary Reactor acts as a
spare of the other. Alternatively the spare reactor can be used as Secondary Reactor in case of catalyst
change-out of Secondary Reactor (R-60002), hereby providing the unit with additional flexibility.
The etherification reaction is exothermic. Therefore, there is an increase in temperature across the reactor.
Dilution of the inlet stream limits the temperature rise across the reactor, and prevents vaporization at the
reactor outlet. By doing this, the temperature of the Primary Reactor is controlled and it also serves to
extend the catalyst life and avoids fouling. The cooled recycle effluent provides the necessary dilution
requirement at the inlet.
Page 5 of 10
Liwa Plastics Project
The pressure in this system is maintained by monitoring the pressure upstream of R-60001A/B and
controlling the feed rate to the Secondary Reactor, R-60002. Effluent cooling is provided by Primary
Reactor Effluent Cooler E-60002 and Secondary Reactor Feed Cooler E-60003, respectively.
R-60002 operates in Boiling Point mode. This reactor is a fixed-bed down-flow adiabatic reactor and further
converts the isobutylene to MTBE. There is a limited amount of vaporization that takes place inside this
reactor. A temperature control is provided at the inlet of this reactor to achieve the desired value. For
flexibility purposes, this reactor is identical to the Primary Reactor, and alternative line-up can be
accommodated, i.e. switch of Primary and Secondary Reactor.
The system pressure is controlled by the CD Reaction Column overhead which sets the boiling point of the
reactor contents and hence, the maximum temperature. Since the reacting liquid mixture is at its boiling
point, even the localized “site” temperature cannot exceed the boiling temperature.
Outlet baskets are installed inside each reactor bottom to prevent carryover of catalyst in the reactor
effluent streams.
Effluent from Secondary Reactor R-60002 is heated against the CD Reaction Column C-60002 bottoms
product via the CD Reaction Column Feed/ Bottoms Exchanger, E-60004. It is then fed to the CD Reaction
Column, C-60002, where the rest of the MTBE conversion takes place.
The CD Reaction Column C-60002, has forty-nine (49) valve trays and contains beds packed with Lummus
Technology proprietary catalyst called “CD Modules”. To maximize MTBE conversion in this column,
additional methanol is injected into these packed beds. The amount of methanol carried overhead in the
CD Reaction Column is limited by the azeotropic composition of 4.0-5.0 wt% methanol in non-reactive C4
hydrocarbons. Any excess methanol over this azeotropic limit will exit the CD Reaction Column bottoms
together with the MTBE product as an impurity. The expected overall conversion is greater than 99.9% to
have less than 450 wt.-ppm of Isobutylene in the C4 Raffinate to the B-1 Section.
An online infrared analyzer is provided in the CD Reaction Column C-60002, to monitor the methanol
concentration profile and to adjust the flows of the methanol injections to the packed beds.
The overhead vapor is condensed against cooling water in the CD Reaction Column Condenser, E-60005.
Distillate flows to the CD Reaction Column Overhead Drum, V-60002. A fraction of the distillate from the
drum is pumped via CD Reaction Column Reflux Pumps, P-60003A/B, back to the CD reaction Column as
reflux. Any non-condensables present in the stream are vented to the wet flare.
MP steam supplies the heat required to the CD Reaction Column C-60002 via the CD Reaction Column
Reboiler, E-60006. MP steam passes through the desuperheater DS-60001 where it is saturated by means
of boiler feed water (BFW). The BFW supply is on the temperature control downstream of the
desuperheater DS-60001 on saturated steam line to the reboiler E-60006. The steam supply is on flow
Page 6 of 10
Liwa Plastics Project
control reset by the temperature controller in the column, cascaded with level controller of the condensate
pot V-60021. A condensate pot V-60021 collects the low pressure condensate from E-60006 and the
condensate is transferred via condensate header to the B.L. under flooding level control cascaded with MP
steam supply controller to the desuperheater DS-60001.
MTBE product from the bottom of the CD Reaction Column flows to the CD Reaction Column Feed/
Bottoms Exchanger, E-60004, where heat is removed by preheating the Secondary Reactor effluent
stream.
MTBE product from the CD Reaction Column bottoms is cooled by product cooler E-60007 and sent to
OSBL.
C4 Distillate from the CD Reaction Column C-60002, is cooled via the Methanol Extraction Column Feed
Cooler, E-60012. It is then fed to the bottom of the Methanol Extraction Column, C-60003. Twenty-four (24)
sieve trays inside this column are provided for methanol removal and a coalescer pad on top for coalescing
residual free water that is escaped with methanol through entrainment. Methanol is extracted from the
hydrocarbons by countercurrent contact with water recycled from the Methanol Recovery Column, C-
60004.
The hydrocarbon effluent from the top of C-60003 is fed to the B-1 Unit on pressure control. The water and
methanol mixture leaving the bottom of the Extraction Column C-60003 is on flow control reset by the
interface level at its top section.
The Methanol Recovery Column, C-60004, utilizes fifty-five (55) valve trays to separate water and
methanol. Low Low pressure steam provides heat in the Methanol Recovery Column Reboiler, E-60010.
The steam supply is on flow or level condensate cascade control reset by temperature control of the top
section. Condensate pot V-60022 collects the low low pressure condensate from shell side outlet of the E-
60010. The condensate pot V-60022 is on flooding level control and transfers the condensate via
condensate header under level control cascaded low low pressure steam flow to the reboiler and
temperature controller of tray 32 of Methanol Recovery Column C-60004.
Water exits the bottom of this column for recycle to Methanol Extraction Column, C-60003, via the
Methanol Recovery Column Bottoms Pumps, P-60005A/B. The recycle water is cooled by the Methanol
Recovery Column Feed/Bottoms Exchanger, E-60008 and Recycle Water Cooler, E-60011 before entering
Methanol Extraction Column C-60003.
The Methanol Recovery Column overhead vapor is condensed against air in the Methanol Recovery
Column Condenser, E-60009. The overhead liquid from Methanol Recovery Column C-60004 and the
Fresh Methanol from OSBL are collected in the Methanol Recovery Column Overhead Drum, V-60003.
Fresh methanol from OSBL first passes through Methanol Feed Filters, S-60001A/B. The Methanol
Recovery Column Reflux Pump, P-60004A/B, transfers the methanol mixture to the column as reflux and
the rest to the MTBE Reaction Section.
Page 7 of 10
Liwa Plastics Project
To limit fouling and impurity accumulation, the Methanol Recovery Column C-60004 bottom sump is
purged once every four (4) weeks. Water should be purged by the operator observing the level in the sump
of the Methanol Recovery Column C-60004 until a low level is reached. The purged water, containing less
than 25 ppmw methanol, is sent to the wastewater plant OSBL. The operator should then make-up the
water in the system using demineralized and deaerated water from the complex. This operation is carried
out using manual control by observing the liquid level in the sump of the Methanol Recovery Column C-
60004.
The C4 raffinate from the top of Methanol Extraction Column C-60003 is fed to the B-1 Heavies columns C-
61002, which is used to separate Raffinate from Butene-1 and other lower boiling C4s. Because the B-1
Heavies column would be too tall otherwise, it is split into two smaller columns, B-1 Heavies Column #1 (C-
61001) and B-1 Heavies Column #2 (C-61002), which correspond to the upper and lower section of the
column, respectively. The bottoms from column #1 is pumped to the top of column #2 using the B-1
Heavies Column Transfer Pump, P-61001A/B. The overhead vapor from column #2 is fed below the
bottom tray of column #1.
The Butene-2 product from Heavies column #2 to OSBL, is pumped using the B-1 Heavies Column
Bottoms Pump P-61003A/B and cooled using the Butene-2 Product Cooler.
LLP steam supplies the heat required to the B-1 Heavies Column #2 via the B-1 Heavies Column Reboiler,
E-61002. The steam supply is on flow control.
Condensate pot V-61021 collects the low low pressure condensate from shell side outlet of the B-1
Heavies Column Reboiler E-61002. The condensate pot V-61021 is on flooding level control and transfers
the condensate via condensate header under level control cascaded to low low pressure steam flow to the
reboiler E-61002.
The overhead from the B-1 Heavies Column #1 is cooled in B-1 Heavies Column Condenser, E-61001,
and collected in B-1 Heavies Column Overhead Drum, V-61001. A bypass around the trim condenser is
used to control the B-1 Heavies Column #1 pressure. The vapor that results from the reflux drum is vented
to wet flare. Both reflux and the overhead product to the B-1 Lights section are pumped via the B-1
Heavies Column Reflux Pump, P-61002A/B, to their respective destinations. Any accumulated water in V-
61001 will be sent to waste water plant on interface level control.
The B-1 Lights Column #2 separates the Butene-1 product from the isobutane product. Because the B-1
Lights column would be too tall otherwise, it is split into two smaller columns, B-1 Lights Column #1 (C-
61003) and B-1 Lights Column #2 (C-61004), which correspond to the upper and lower section of the
column, respectively. The bottoms from column #1 is pumped to the top of column #2 using the B-1 Lights
Column Transfer Pump, P-61004A/B. The overhead vapor from column #2 is fed below the bottom tray of
column #1.
The Butene-1 product from Lights column #2 to OSBL, is pumped using the B-1 Lights Column Bottoms
Pump P-61006A/B and cooled using the Butene-1 Product Cooler prior to sending it the B.L.
LLP steam supplies the heat required to the B-1 Lights Column #2 via the B-1 Lights Column Reboiler, E-
61005. The steam supply is on flow control.
Page 8 of 10
Liwa Plastics Project
Condensate pot V-61022 collects the low low pressure condensate from shell side outlet of the B-1 Lights
Column Reboiler E-61005. The condensate pot V-61022 is on flooding level control and transfers the
condensate via condensate header under level control cascaded to low low pressure steam flow to the
reboiler E-61005
The overhead from the B-1 Lights Column #1 is cooled in B-1 Lights Column Condenser, E-61004, and
collected in B-1 Lights Column Overhead Drum, V-61002. A bypass around the trim condenser is used to
control the B-1 Lights Column #1 pressure. The vapor that results from the reflux drum is vented to wet
flare. Both reflux and the Isobutane product to OSBL are pumped via the B-1 Lights Column Reflux Pump,
P-61005A/B, to their respective destinations. Any accumulated water in V-61002 will be sent to waste
water plant on interface level control.
2.3 MTBE Unit Drain Drums Pit Z-60001 (6000 & 6100)
MTBE Unit Drain Drum Pit Z-60001 contains two drain drums i.e. Methanol Drains Drum V-60004 and
MTBE Drains Drum V-60005. Surface water, rain water, spills from the drain drums that are collected in the
pit are transferred to MTBE Unit Rain Water Collection Pit Z-60002 by means of air-driven Drain Drum Pit
Dewatering Pump P-60010 that is installed at grade.
2.4 MTBE Unit Rain Water Collection Pit Z-60002 (6000 & 6100)
MTBE Unit Rain Water Collection Pit Z-60002 collects rainwater as well as oil/hydrocarbon contaminated
water from the MTBE Unit Drain Drums Pit Z-60001, which is transferred from Z-60001 to Z-60002 by
means of Drain Drum Pit Dewatering Pump P-60010. Water in the Z-60002 is collected through a sample
connection for analysis. On the basis of the results of the analysis, the water is pumped out by MTBE Unit
Rain Water Pump P-60008 to the oily water contaminated sewer or to the waste water treatment plant for
further treatment.
Page 9 of 10
Liwa Plastics Project
Page 10 of 10
Petrochemical Plant Sohar Environmental Impact Assessment Report
Orpic and CB&I HMR #3817
CB&I ORPIC
Page 1 of 13
"THIS DOCUMENT IS THE PROPERTY OF CHICAGO BRIDGE & IRON COMPANY (CB&I). IT MAY CONTAIN INFORMATION
DESCRIBING TECHNOLOGY OWNED BY CB&I AND DEEMED TO BE COMMERCIALLY SENSITIVE. IT IS TO BE USED ONLY IN
CONNECTION WITH WORK PERFORMED BY CB&I. REPRODUCTION IN WHOLE OR IN PART FOR ANY PURPOSE OTHER THAN
WORK PERFORMED BY CB&I IS FORBIDDEN EXCEPT BY EXPRESS WRITTEN PERMISSION OF CB&I. IT IS TO BE SAFEGUARDED
AGAINST BOTH DELIBERATE AND INADVERTENT DISCLOSURE TO ANY THIRD PARTY."
UNIT DESCRIPTION
Job Number Unit Type Page
06146 6200 02UD 2/13
Client Oman Oil Refineries and Petroleum Ind. Co. SAOC Date By Check By Rev
CONTENT
ABRREVIATIONS
AOC Accidentally Oil Contaminated
FEED Front-End Engineering and Design
HPS High Pressure Steam
LPP Liwa Plastics Project
MPS Medium Pressure Steam
ORPIC Oman Oil Refineries and Petroleum Industries Company
Pygas Pyrolysis Gasoline
SCU Steam Cracker unit
WWTP Waste Water Treatment Plant
Client Oman Oil Refineries and Petroleum Ind. Co. SAOC Date By Check By Rev
Client Oman Oil Refineries and Petroleum Ind. Co. SAOC Date By Check By Rev
Liquid from the recycle pump is cooled down in 1st Stage Recycle Air Cooler E-62004. Part of it is mixed
with the fresh feed, and the second part is further cooled down in 1st Stage Quench Trim Cooler E-62005
and mixed with 1st Stage Hydrogenation 1st Reactor effluent.
The vapor from Hot separator which contains light hydrocarbons shall be partially condensed in the 1st
Stage Condenser E-62003 and sent to the Cold Separator Drum V-62003. Vapor from V-62003 is sent to
the Second Stage reaction section as make-up hydrogen, under First Stage reaction section pressure
control (pressure control at 1st Stage Hydrogenation Reactors inlet). Liquid from Cold Separator is merged
with liquid from Hot Separator to feed 1st Stage Stabilizer C-62011 under level-flow cascaded control.
1st Stage reactors are also designed to stand in-situ activation and regeneration of the catalyst. Generation
of catalyst treatment gas and management of the catalyst treatment offgases are OSBL and outside Axens
scope of work.
Due to the use of nickel-based catalyst, an additional passivation step shall be performed to prevent high
hydrogenation rates of the feed with potential loss of aromatics and unbearable exotherm in 1st Stage
reactors. This operation will be executed with dedicated facilities (Passivation drum V-62004 and
Passivation pump P-62003) to allow a closed loop circulation of inert naphtha through the 1st Stage First
and Second reactors of the same train (either A or B). The active compound during passivation shall be Di
Methyl Sulfide which will be injected in the closed loop from the DMS injection package A-62001.
Client Oman Oil Refineries and Petroleum Ind. Co. SAOC Date By Check By Rev
Client Oman Oil Refineries and Petroleum Ind. Co. SAOC Date By Check By Rev
The reflux drum is equipped with a boot, which removes potential water. Water (if any) is sent to Waste
Water header.
Rerun Tower is reboiled by the Rerun Tower Reboilers E-62017A/B. To prevent fouling in reboiler, HP
steam shall be desuperheated down to 215°C maximum in DS-62012, prior to being sent to reboiler. In
start-up mode, the steam flow control can be cascaded by the temperature at reboiler outlet.
A spare Rerun Tower Reboiler shall be also installed to allow change-over to maintain continuous
operation.
The Heavy Cut leaving the tower bottom is pumped in the Heavy Cut Pumps P-62013A/B, cooled down in
Heavy Cut Air Cooler E-62016 and sent to the PFO tank, under flow control cascaded by tower level
controller.
Client Oman Oil Refineries and Petroleum Ind. Co. SAOC Date By Check By Rev
Client Oman Oil Refineries and Petroleum Ind. Co. SAOC Date By Check By Rev
The hydrogen consumption in Second Stage will be balanced by injecting pure make-up hydrogen from
PSA. The flow will be automatically adjusted to maintain the pressure in 2nd Stage Separator drum.
2nd Stage reactor is also designed to stand in-situ activation and regeneration of the catalyst. Generation of
catalyst treatment gas for regeneration and management of the catalyst treatment offgases are OSBL and
outside Axens scope of work.
2nd Stage reactor catalyst activation is different from 1st Stage reactors. Catalyst needs to be sulfided prior
to being used. Sulfiding will be performed by circulating hydrogen mixed with H2S inside the reactor in
closed loop through the normal operation lines. H2S will be generated in-situ by injecting Di Methyl Di
Sulfide (DMDS) from DMDS Injection Package A-62031 at 2nd Stage reactor inlet, which will decompose in
H2S at the sulfiding step conditions.
Client Oman Oil Refineries and Petroleum Ind. Co. SAOC Date By Check By Rev
4.2 Depentanizer
The Depentanizer C-62042 has 55 trays and the feed enters the column at tray 26.
The Depentanizer purpose is to recover a C5 cut at overhead (Hydrogenated C5 cut).
The overhead vapor of the tower is totally condensed in the Depentanizer Condenser E-62046 and
collected in Depentanizer Reflux Drum V-62042. The liquid phase is pumped through the Depentanizer
Reflux/Product Pumps P-62042A/B, a part of it is routed back to the column as a reflux under flow control,
while the remaining is sent to storage under flow control cascaded by reflux drum controller, after being
cooled down in the Hydrogenated C5 Trim Cooler E-62047 to meet the refinery battery limit temperature
requirement.
The pressure in reflux drum will be controlled by engassing hot vapor from column overhead under
differential pressure control (PDC). The purpose of the PDV valve on the bypass line is to ensure a
constant differential pressure between the Depentanizer and the reflux drum. If the pressure in the
Depentanizer overhead decreases, then PIC will close the valve on the main line, increasing the pressure
This document contains confidential proprietary information belonging to Axens
Rev.1 23/02/15 It shall not be disclosed to any third parties without Axens’ prior written consent.
PROCESS DESCRIPTION
Job Number Unit Type Page
06146 6200 02UD 10/13
Client Oman Oil Refineries and Petroleum Ind. Co. SAOC Date By Check By Rev
drop in this valve. As the differential pressure between the Depentanizer overhead and the reflux drum is
kept constant by the PDC on the bypass, pressure drop in the air cooler decreases (flow in it decreases).
As the flow decreases and the same amount of vapor is still coming from the Depentanizer overhead, the
pressure tends to increase. When the pressure increases, the pressure control valve starts to open more
and more until equilibrium is reached in the system.
Column is reboiled in the Depentanizer Reboiler E-62048 with MP steam. Steam flowrate is actually
controlled by varying condensate level in reboiler (flooded-type exchanger).
The bottom product leaving the tower feeds the Deheptanizer under flow control cascaded by the level in
the Depentanizer bottom.
4.3 Deheptanizer
The Deheptanizer C-62043 has 43 trays and the feed enters the column at tray 26.
The Deheptanizer purpose is to recover a C6-C7 cut at overhead and a C8-C10 cut in the bottoms.
The overhead vapor of the tower is totally condensed in the Deheptanizer Condenser E-62049 and
collected in Deheptanizer Reflux Drum V-62043. The liquid phase is pumped the Deheptanizer
Reflux/Product Pumps P-62043A/B, a part of it is routed back to the column as a reflux under flow control,
while the remaining is sent to storage under flow control cascaded by reflux drum level controller, after
being cooled down in the C6-C7 Cut Air Cooler E-62050 and C6-C7 Cut Trim Cooler E-62051 to meet the
refinery battery limit temperature requirement.
The pressure in reflux drum will be controlled by engassing hot vapor from column overhead under
differential pressure control (PDC). The purpose of the PDV valve on the bypass line is to ensure a
constant differential pressure between the Deheptanizer and the reflux drum. If the pressure in the
Deheptanizer overhead decreases, then PIC will close the valve on the main line, increasing the pressure
drop in this valve. As the differential pressure between the Deheptanizer overhead and the reflux drum is
kept constant by the PDC on the bypass, pressure drop in the air cooler decreases (flow in it decreases).
As the flow decreases and the same amount of vapor is still coming from the Deheptanizer overhead, the
pressure tends to increase. When the pressure increases, the pressure control valve starts to open more
and more until equilibrium is reached in the system.
Column is reboiled in the Deheptanizer Reboiler E-62052 with HP steam. Steam flowrate is actually
controlled by varying condensate level in reboiler (flooded-type exchanger).
The bottom product leaving the tower is pumped and routed to storage under flow control cascaded by the
level in the Deheptanizer bottom, after being cooled down in 2nd Stage Stabilizer Feed/Deheptanizer Bottom
Exchanger E-62041 and C8-C10 Cut Trim Cooler E-62045.
Client Oman Oil Refineries and Petroleum Ind. Co. SAOC Date By Check By Rev
The reboiler systems of the Pygas unit’s distillation columns are equipped with condensate pots for
easy condensate removal. The design of the five reboiler systems is as follows:
Client Oman Oil Refineries and Petroleum Ind. Co. SAOC Date By Check By Rev
R-62031.
The maximum operating temperature of the hydrogen and nitrogen mixture is 410°C and the
maximum operating temperature of the steam and air mixture is 480°C.
After catalyst treatment the off-gas mixture is cooled in Catalyst Treatment Off-Gas Air Cooler E-
62061. The maximum temperature downstream Catalyst Treatment Gas Cooler E-62061 is 300°C.
The pressure downstream E-62061 is maintained at 5 barg by pressure control valve PV-138.
Steam/Air mixtures are routed to safe location via Catalyst Treatment Gas KO Drum V-62060.
Hydrogen/Nitrogen mixtures are routed to flare.
Full details of catalyst treatment operations are given in the Utility Summary (doc. nr S-S620-5223-
521). The following is a summary of the required catalyst treatment steps:
- Catalyst Activation occurs with hydrogen and nitrogen at minimum 400°C for 15 hours.
- Passivation occurs with Dimethyl Sulfide and naphtha
- Reactivation occurs with nitrogen and hydrogen for 8 hours at 150°C minimum
- Hot hydrogen stripping is done at minimum 400°C for 12 hours.
- Pre-oxidation, combustion and polishing is done with steam & air mixture. During polishing the
temperature is 460°C maximum for 4 hours.
- Regeneration of R-62001 A/B occurs every 18 months and regeneration of R-620031 occurs
every 24 months. The estimated total time that the temperature is at 460°C is expected to be
200 hours during the design life time of 25 years.
Client Oman Oil Refineries and Petroleum Ind. Co. SAOC Date By Check By Rev
Both drain drums are located in Pygas Unit Drain Drums Pit Z-60001. Any collected rainwater is
pumped out by air-driven Dewatering Pump P-62053 and sent to Rainwater Collection Pit Z-60002.
Pygas Unit Rainwater Collection Pit
Rainwater, which is collected from the paved area of the Pygas unit, is collected in Rainwater
Collection Pit Z-62002. If benzene levels are too high, the pit may be emptied by vacuum truck. If
found clean after sampling, surface, water may be discharged to the AOC system on gravity.
CB&I ORPIC
Page 1 of 11
"THIS DOCUMENT IS THE PROPERTY OF CHICAGO BRIDGE & IRON COMPANY (CB&I). IT MAY CONTAIN INFORMATION
DESCRIBING TECHNOLOGY OWNED BY CB&I AND DEEMED TO BE COMMERCIALLY SENSITIVE. IT IS TO BE USED ONLY IN
CONNECTION WITH WORK PERFORMED BY CB&I. REPRODUCTION IN WHOLE OR IN PART FOR ANY PURPOSE OTHER THAN
WORK PERFORMED BY CB&I IS FORBIDDEN EXCEPT BY EXPRESS WRITTEN PERMISSION OF CB&I. IT IS TO BE SAFEGUARDED
AGAINST BOTH DELIBERATE AND INADVERTENT DISCLOSURE TO ANY THIRD PARTY."
Liwa Plastics Project
Page 2 of 11
Liwa Plastics Project
Table of Contents
Contents Page
1.0 INTRODUCTION..................................................................................................................................5
2.0 FLARE SYSTEM .................................................................................................................................5
2.1 Main Wet Flare ME-89001.........................................................................................................5
2.2 Spare Storage Wet Flare ME-89003 .........................................................................................8
2.3 Acid Gas Flare ........................................................................................................................10
2.4 Cryogenic Low Pressure Flare ME-89002 A/B ......................................................................11
Page 3 of 11
Liwa Plastics Project
ABBREVIATION
HP High Pressure
FG Fuel Gas
NG Natural Gas
Page 4 of 11
Liwa Plastics Project
1.0 INTRODUCTION
For operation of the new Olefins Complex located at the Sohar refinery, The Sultanate of Oman, an
elevated flare system has been foreseen to receive reliefs from all the plants.
The new flare system is designed to safely collect and dispose reliefs from the plant. Separate collection
headers are receiving different discharges from the plant. Knock-out drums are foreseen for each process
unit to separate liquid before the gasses are sent to flare. Liquid Hydrocarbon and aqueous phases are
routed to appropriate destination for reprocessing.
The Wet and Cold Flare headers will be combined before to route to main wet flare header/stack. In order
to combine the Wet Flare and Cold Flare into one flare header/stack, the cold flare vapors from the Cold
Flare KO drum (V-83012) is heated to a temperature well above the minimum allowable metal temperature
for Low Temperature Carbon Steel, i.e. above -45°C by means of superheater. After the temperature has
been raised the combine wet and cold reliefs header is routed to Wet Flare K.O. Drum V-89001.
Any liquid accumulated in the V-89001 is routed by the Flare Knock Out Drum Pump P-89001A/B to the
Quench Water Drain Drum V-10003. Only during shutdown of the SCU; the pumped liquid is routed to the
Waste Water Collection Tank T-85001. The pump is automatically started at high level and stopped at low
level. Both pumps are connected to the emergency power grid. The pump capacities are set to drain the
determining load of liquid hydrocarbons and water in two (2) hours.
The vapors flow through the Wet Flare Seal Drum (ME-89001-V-02) to the Wet Flare Stack (ME-89001-
SK-01). Service Water is supplied to Wet Flare Seal Drum to maintain the water seal level. In addition
Service Water flows continuously through an orifice (parallel to the level controller) into the seal drum to
ensure adequate water seal level. The continuous overflow is sent to the Oily Water Sewer (OWS). The
function of the seal drum is to prevent ingress of air into flare header. Ingress of air is not allowed into the
flare header as it can result in an explosive mixture in the header.
Page 5 of 11
Liwa Plastics Project
The inlet to the flare stack and the flare sub-headers are purged with fuel gas to ensure a positive flow from
the flare system to the flare stack. Nitrogen is used as back-up for fuel gas purge.
Vapors from Wet Flare K.O. Drum V-89001 are routed to the Flare Package ME-89001 which mainly
consists of: Wet Flare Seal Drum (ME-89001-V-02), Flare Stack (ME-89001-SK-01), Flare Tip, Flare Fuel
Gas KO Drum (ME-89001-V-01), Flare Ignition System, Molecular Seal and required instrumentation for
control and safe guarding. For details reference is made to Main Wet Flare Package (ME-89001) package
specification.
The stack is equipped with a molecular dry seal as additional protection against air ingress. The relief
gases are ignited by the pilot flames and released to atmosphere. A flame generator is installed to ignite
the pilots. The flare tip pilot temperature switches-on automatically the ignition in case of loss of flame.
Remote ignition from control room is possible in case the automatic re-ignition does not work.
Fuel gas is used as pilot gas and purge gas. Natural gas is used as back-up for fuel gas.
MP steam is routed to the Flare Tip to ensure smokeless flaring at low relief loads and to protect flare
system against flame back. The MP steam flow is controlled by a control valve proportional to the relieved
gas flow rate. To optimize the steam consumption infrared sensors are installed to sense flare
characteristic of the flame and adjust the steam flow rate automatically.
The main equipment connected directly to wet flare header are:
Refinery Dry Gas Treating Unit
st
o RDG Compressor 1 Stage Suction Drum (V-12001)
o RDG Oxygen Converter (R-12001 A/B)
o RDG Amine / Water Wash Column (C-12001)
o RDG Depropylenizer (C-12005)
NGL Treating and Fractionation Unit
o NGL Amine / Water Wash Column (C-11002)
o C3+ Stripping Hold Up Drum (V-11007)
Steam Cracker Unit
o C3+ Feed Vaporizer (E-20018 A/B)
o Quench Tower (C-21003)
st
o Charge Gas Compressor 1 Stage Suction Drum(V-22001)
rd
o Charge Gas Compressor 3 Stage Suction Drum(V-22004)
o Hydrogen Compressor (K-23001)
o Fuel Gas KO Drum (V-23005)
o Acetylene Converters (R-22001 A/B/C)
o MAPD Converters (R-24001 A/B)
o Debutanizer Reflux Drum (V-24004)
o Propylene Fractionators (C-24003-04)
o Propylene Refrigeration Compressor (K-25001)
o Binary Refrigerant Compressor (K-26001)
Selective C4 Hydrogenation Unit
st
o SHU 1 Stage Feed Drum (V-28011)
st
o SHU 1 Stage Separator Drum (V-28012)
nd
o SHU 2 Stage Separator Drum (V-28022)
Page 6 of 11
Liwa Plastics Project
The main equipment connected to wet flare header via cold/dry relief header are:
Refinery Dry Gas Treating Unit
o RDG Demethanizer Reflux Drum (V-12007)
o RDG Deethanizer Reflux Drum (V-12008)
o RDG Depropylenizer Reflux Drum (V-12010)
o NGL Treating and Fractionation Unit
o NGL Deethanizer Reflux Drum (V-11002)
Steam Cracker Unit
o HP Depropanizer Reflux Drum (V-22012)
Page 7 of 11
Liwa Plastics Project
Page 8 of 11
Liwa Plastics Project
The stack is equipped with a molecular dry seal as additional protection against air ingress. The relief
gases are ignited by the pilot flames and released to atmosphere. A flare generator is installed to ignite the
pilots. Fuel gas is used as pilot gas and purge gas. Natural gas is used as back-up for fuel gas. The flare
tip pilot temperature switches-on automatically the ignition in case of loss of flame. Remote ignition from
control room is possible in case the automatic re-ignition does not work.
MP steam is routed to the Flare Tip to ensure smokeless flaring at low relief loads and to protect flare
system against flame back. The MP steam flow is controlled by a control valve proportional to the relieved
gas flow rate. To optimize the steam consumption infrared sensors are installed to sense flare
characteristic of the flame and adjust the steam flow rate automatically.
The main equipment connected to this header is:
Pressurized storage for Mixed C4, Butene-1, Butene-2, Hydrogenated C4, Pressurized storage spheres
for NGL C2+, Ethylene and Propylene including high pressure equipment and piping in Cryogenic
Ethylene and Propylene Storage area.
For graphical representation of the Spare Storage Wet Flare System reference is made to the Utility
Process Flow Diagram D-S890-5223-103.
Page 9 of 11
Liwa Plastics Project
One Sour Water Collection Drum V-89003 is available to drain the liquid from the Acid Gas Flare System.
The contents are routed to the Quench Water Drain Drum (V-10003) by the Sour Water Drain Drum Pump
P-89004.
Sour Water Drain Drum V-89003 is continuously purged with fuel gas and floating on acid gas flare header
pressure.
Page 10 of 11
Liwa Plastics Project
Page 11 of 11
Petrochemical Plant Sohar Environmental Impact Assessment Report
Orpic and CB&I HMR #3817
A A
B B
HOLDS:
C C
D D
E E
F F
G G
H H
J J
K K
REFERENCE DRAWINGS
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
NOTES
A A
B B
C C
D D
E E
F F
G G
H H
J J
K K
REFERENCE DRAWINGS
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Liwa Plastics Project
CB&I ORPIC
Page 1 of 6
"THIS DOCUMENT IS THE PROPERTY OF CHICAGO BRIDGE & IRON COMPANY (CB&I). IT MAY CONTAIN INFORMATION
DESCRIBING TECHNOLOGY OWNED BY CB&I AND DEEMED TO BE COMMERCIALLY SENSITIVE. IT IS TO BE USED ONLY IN
CONNECTION WITH WORK PERFORMED BY CB&I. REPRODUCTION IN WHOLE OR IN PART FOR ANY PURPOSE OTHER THAN
WORK PERFORMED BY CB&I IS FORBIDDEN EXCEPT BY EXPRESS WRITTEN PERMISSION OF CB&I. IT IS TO BE SAFEGUARDED
AGAINST BOTH DELIBERATE AND INADVERTENT DISCLOSURE TO ANY THIRD PARTY."
Liwa Plastics Project
Page 2 of 6
Liwa Plastics Project
Table of Contents
Contents Page
1.0 INTRODUCTION..................................................................................................................................5
2.0 VENT GAS INCINERATOR .................................................................................................................5
3.0 LIQUID AND SOILD WASTE INCINERATOR ......................................................................................6
Page 3 of 6
Liwa Plastics Project
ABBREVIATIONS
Page 4 of 6
Liwa Plastics Project
1.0 INTRODUCTION
Waste incineration unit consists of vent gas incinerator package and combined liquid and solid incinerator
package.
Vent gases with toxic components or smelly fumes are routed to the Vent Gas Incinerator.
One Waste Incinerator is foreseen to receive liquid and solids streams.
The possibility to combine these two incinerators shall be investigated by the vendor during EPC phase.
Reference for this process description is:
Utility Flow Diagram for Vent Gas incineration (Unit 8600) doc. no. D-S860-5223-101.
Utility Flow Diagram for Liquid-Solid Waste incineration (Unit 8600) doc. no. D-S860-5223-102.
This package is an incinerator specially designed for high hydrocarbon conversion efficiency.
Flame Arrestors ME-86001-A01A/B and ME-86001-A02A/B (part of ME-86001) are required to prevent fire
in case of back flow from the incinerators into the vent gas line.
In case the Vent Gas Incinerator ME-86001-F-01 is not available and during the start-up of the blowers, the
vent gases are routed to the atmosphere at safe location via Vent Gas Stack (ME-86001-SK-01).
The flue gas is routed via a stack to the atmosphere. The incinerator is fired by means of fuel gas with
Natural Gas as back-up.
Page 5 of 6
Liwa Plastics Project
Page 6 of 6
Petrochemical Plant Sohar Environmental Impact Assessment Report
Orpic and CB&I HMR #3817
CB&I ORPIC
Page 1 of 6
"THIS DOCUMENT IS THE PROPERTY OF CHICAGO BRIDGE & IRON COMPANY (CB&I). IT MAY CONTAIN INFORMATION
DESCRIBING TECHNOLOGY OWNED BY CB&I AND DEEMED TO BE COMMERCIALLY SENSITIVE. IT IS TO BE USED ONLY IN
CONNECTION WITH WORK PERFORMED BY CB&I. REPRODUCTION IN WHOLE OR IN PART FOR ANY PURPOSE OTHER THAN
WORK PERFORMED BY CB&I IS FORBIDDEN EXCEPT BY EXPRESS WRITTEN PERMISSION OF CB&I. IT IS TO BE SAFEGUARDED
AGAINST BOTH DELIBERATE AND INADVERTENT DISCLOSURE TO ANY THIRD PARTY."
Liwa Plastics Project
Page 2 of 6
Liwa Plastics Project
Table of Contents
Contents Page
Page 3 of 6
Liwa Plastics Project
ABBREVIATIONS
BUT-1 Butene-1 Recovery Unit
LPP Liwa Plastics Project
MTBE Methyl Tertiary Butyl Ether
NGLT NGL Treating & Fractionation Unit
PE Polyethylene Unit
PP Polypropylene Unit
PGHYD Pyrolysis Gasoline Hydrotreater Unit
RDG Refinery Dry Gas Treating Unit
SCU Steam Cracker Unit
SLC4HY Selective C4 Hydrogenation Unit
Page 4 of 6
Liwa Plastics Project
1.0 INTRODUCTION
The objective of Potable and Service Water System is to generate Service Water and Potable Water from
Desalinated Water and distribute to the end users. Service water is to be sent to all process units for LPP
project including PE and PP plant however potable water is only for internal use (PP / PE plant potable
water is to be provided by OTHERS).
For the process description of this system, reference is made to the following Utility Process Flow
Diagrams (UFD’s):
D-S734-5223-101: Potable and Service Water System (Unit 7340)
7000 – 7800
Utilities and Off-sites Service Water
8400 - 9100
Storage 8100 - 8300 Service Water
NGLT 1100 Service Water
RDG 1200 Service Water
SCU 2000 – 2600 Service Water
SLC4HY 2800 Service Water
MTBE 6000 Service Water
BUT-1 6100 Service Water
PGHYD 6200 Service Water
PE/PP - Service Water
Power Plant - Service Water
Page 5 of 6
Liwa Plastics Project
chlorination via Hypochlorite Injection Package (ME-73401). The potable water tank is an atmospheric tank
and sized for a residence time of 3 days based on normal potable water demand.
The potable Water tank (T-73402) represents a break between the desalinated water and the potable
water distribution system.
The chemical solutions are injected into the desalinated water upstream of potable water tank by the
reciprocating pump. The chemical injection rate is controlled by pump stroke to meet WHO potable water
quality specification.
Concentration of residual chlorine in potable water shall be kept at 0.2 – 0.5 mg/l. The concentration of
Chlorine is analyzed at the tank inlet / outlet.
To prevent stagnant point, potable water shall be circulated.
The chemically conditioned potable water is to pass through UV Filter (S-73401) and needs to be chilled by
0
Chilling Package (ME-73406) to 25 C before sending to end users.
7000 – 7800
Utilities and Off-sites Potable Water
8400 - 9100
Storage 8100 - 8300 Potable Water
NGLT 1100 Potable Water
RDG 1200 Potable Water
SCU 2000 – 2600 Potable Water
SLC4HY 2800 Potable Water
MTBE 6000 Potable Water
BUT-1 6100 Potable Water
PGHYD 6200 Potable Water
Page 6 of 6
Petrochemical Plant Sohar Environmental Impact Assessment Report
Orpic and CB&I HMR #3817
CB&I ORPIC
Page 1 of 5
"THIS DOCUMENT IS THE PROPERTY OF CHICAGO BRIDGE & IRON COMPANY (CB&I). IT MAY CONTAIN INFORMATION
DESCRIBING TECHNOLOGY OWNED BY CB&I AND DEEMED TO BE COMMERCIALLY SENSITIVE. IT IS TO BE USED ONLY IN
CONNECTION WITH WORK PERFORMED BY CB&I. REPRODUCTION IN WHOLE OR IN PART FOR ANY PURPOSE OTHER THAN
WORK PERFORMED BY CB&I IS FORBIDDEN EXCEPT BY EXPRESS WRITTEN PERMISSION OF CB&I. IT IS TO BE SAFEGUARDED
AGAINST BOTH DELIBERATE AND INADVERTENT DISCLOSURE TO ANY THIRD PARTY."
Liwa Plastics Project
Page 2 of 5
Liwa Plastics Project
Table of Contents
Contents Page
1.0 INTRODUCTION..................................................................................................................................5
2.0 SEA WATER DESALINATION PACKAGE (MED) ...............................................................................5
3.0 DEMIN WATER PACKAGE (EDI)........................................................................................................5
4.0 DESALINATED WATER DISTRIBUTION ............................................................................................5
Page 3 of 5
Liwa Plastics Project
ABBREVIATIONS
Page 4 of 5
Liwa Plastics Project
1.0 INTRODUCTION
The objective of Sea Water Desalination System is to generate Desalinated Water from sea water by a
proven technique which is called Multi Effect Distillation (MED). Desalinated Water is fed to other water
systems which will produce Demineralized Water, Service Water and Potable Water.
For the process description of this system, reference is made to the following Utility Process Flow
Diagrams (UFD’s):
D-S732-5223-101: Desalination and Demin Water Package (Unit 7320)
Page 5 of 5
Petrochemical Plant Sohar Environmental Impact Assessment Report
Orpic and CB&I HMR #3817
Attachment 10: Process description for Fuel Gas and Natural Gas System
CB&I ORPIC
Page 1 of 6
"THIS DOCUMENT IS THE PROPERTY OF CHICAGO BRIDGE & IRON COMPANY (CB&I). IT MAY CONTAIN INFORMATION
DESCRIBING TECHNOLOGY OWNED BY CB&I AND DEEMED TO BE COMMERCIALLY SENSITIVE. IT IS TO BE USED ONLY IN
CONNECTION WITH WORK PERFORMED BY CB&I. REPRODUCTION IN WHOLE OR IN PART FOR ANY PURPOSE OTHER THAN
WORK PERFORMED BY CB&I IS FORBIDDEN EXCEPT BY EXPRESS WRITTEN PERMISSION OF CB&I. IT IS TO BE SAFEGUARDED
AGAINST BOTH DELIBERATE AND INADVERTENT DISCLOSURE TO ANY THIRD PARTY."
Liwa Plastics Project
Page 2 of 6
Liwa Plastics Project
Table of Contents
Contents Page
1.0 INTRODUCTION..................................................................................................................................5
2.0 FG COLLECTION ................................................................................................................................5
3.0 HP NG INTAKE AND DISTRIBUTION .................................................................................................5
4.0 FG DISTRIBUTION..............................................................................................................................6
Page 3 of 6
Liwa Plastics Project
ABBREVIATION
HP High Pressure
FG Fuel Gas
LP Low pressure
NG Natural Gas
Page 4 of 6
Liwa Plastics Project
1.0 INTRODUCTION
The Fuel Gas (FG) and Natural Gas (NG) system for the LPP project is a common distribution system
inside the LPP Complex including PP and PE units. The fuel gas distribution system receives off-gas from
the Steam Cracker Unit and provides fuel gas for the consumers. Due to the fact that the amount of fuel
gas production from SCU Unit is not sufficient for the operation of the LPP Units there is a need for
additional Natural Gas supplied from the existing NG intake station.
The produced off-gas will be routed to a Fuel Gas K.O. Drum (V-75001) operating at 4.0 bar (g) where fuel
gas is distributed to the consumers.
In case of fuel gas shortage, high pressure Natural Gas at 31 bar (g) is routed to the Cracking Heaters.
The SCU has its own independent fuel gas k.o drum and pressure let down system.
Reference for this process description is Utility Process Flow Diagram for Fuel Gas And Natural Gas
Supply Unit 7500, Doc. No. D-S750-5223-101.
2.0 FG COLLECTION
Off gases produced in the new process units are collected in one common header from the SCU. The
following streams are the main off gas producers:
Regeneration Offgas from Refinery Dry Gas Treating Unit.
Fuel gas from PSA Unit in Steam Cracker Unit.
The off gas stream is divided, one branch serves the Cracking Heaters and the rest is routed to the OSBL
fuel gas system.
The fuel gas stream containing mainly methane, minorities of heavier hydrocarbons and some inerts at
about 4.0 barg is mixed with the Natural Gas stream from Oman Gas Company (OGC). The Static Mixer
(M-75001) assures the continuous mixing of both gases. The fuel gas is further directed to the Fuel Gas
K.O. Drum (V-75001) which provides liquid droplet separation, if present.
Page 5 of 6
Liwa Plastics Project
the pressure reduction valve for the auxiliary steam boilers is located in SCU area. The remaining heated
up HP NG flows through a dedicated pressure control valve to the FG distribution system.
4.0 FG DISTRIBUTION
Pressure of the Fuel Gas System is regulated by the pressure controller located on the outlet of Fuel Gas
Mixing Drum (V-75001), adjusting the intake of NG to the drum. The mixture of FG and NG from V-75001
is distributed to all process and utility consumers in the LPP Complex including PP and PE units. The main
consumers are listed below:
Pilot burners at flare tip.
Purge gas for flare sub-headers.
Auxiliary Steam Boilers, pilot and burners.
Vent Gas Incineration, pilot and burners.
Liquid- Solid Incinerator, pilot and burners.
Blanketing gas for drain vessels.
2nd stage hydrogenation heater in Pygas hydrogenation unit.
PE/PP unit
MTBE/BUT-1 unit
For continuous measurement and monitoring of the FG mixture composition and properties two analyzers
are provided downstream of V-75001 to measure the gas mixture Wobbe Index and FG composition by GC
analyzer.
Page 6 of 6
Petrochemical Plant Sohar Environmental Impact Assessment Report
Orpic and CB&I HMR #3817
CB&I ORPIC
Page 1 of 6
"THIS DOCUMENT IS THE PROPERTY OF CHICAGO BRIDGE & IRON COMPANY (CB&I). IT MAY CONTAIN INFORMATION
DESCRIBING TECHNOLOGY OWNED BY CB&I AND DEEMED TO BE COMMERCIALLY SENSITIVE. IT IS TO BE USED ONLY IN
CONNECTION WITH WORK PERFORMED BY CB&I. REPRODUCTION IN WHOLE OR IN PART FOR ANY PURPOSE OTHER THAN
WORK PERFORMED BY CB&I IS FORBIDDEN EXCEPT BY EXPRESS WRITTEN PERMISSION OF CB&I. IT IS TO BE SAFEGUARDED
AGAINST BOTH DELIBERATE AND INADVERTENT DISCLOSURE TO ANY THIRD PARTY."
Liwa Plastics Project
Page 2 of 6
Liwa Plastics Project
Table of Contents
Contents Page
1.0 INTRODUCTION..................................................................................................................................5
2.0 PROCESS DESCRIPTION...................................................................................................................5
Page 3 of 6
Liwa Plastics Project
ABBREVIATIONS
Page 4 of 6
Liwa Plastics Project
1.0 INTRODUCTION
The Secondary Cooling Water Unit (SCWU) is a closed pump around system. The SCWU supplies cooling
water to all process units of LPP project except PE and PP plant, utilities systems and storage. The system
consists of an expansion drum, circulating pumps, plate and frame coolers, cooling water drain pit(s) and
drain pit pump(s), one storage tank and associated filling pump and chemical dosing package foreseen for
emptying and filling the system.
Reference for this process description is:
Utility Process Flow Diagram for Secondary Cooling Water for Olefins (Unit 7310), document no.
D-S731-5223-101 to D-S731-5223-103.
Page 5 of 6
Liwa Plastics Project
Pressurizing the system as to maintain positive pressure all over the system.
The V-73101 will be located above the highest consumer to maintain the static pressure even in case of
loss of nitrogen.
The cooling water returned from the users is cooled down against sea water in plate and frame heat
exchangers (E-73101). In total, 28 plate and frame heat exchangers are expected, 27 in operation and one
is available for cleaning (HOLD 1).
In case of inspection or maintenance, the Secondary Cooling Water System can be drained into pits from
where it is pumped to the T-73101 (the number of pits and drain pumps will be defined based on the final
plant lay-out by detail engineering contractor). After inspection or maintenance the content can be pumped
back into the system via the Secondary Cooling Water Filling Pump, P-73103. In this way loss of water is
minimized.
In case of tube rupture the vapors are released to the flare via the vent line on the top of the V-73101.
In case of a small tube leakage in an exchanger, the cooling water system can be kept in operation and
hydrocarbons can be drained periodically by means of the skimming connection on the expansion vessel.
In case the leak is more severe or cannot be skimmed off easily, the contents of the closed loop cooling
water system can be routed to the SCW Storage Tank T-73101, and then routed to the Waste Water
Treatment unit. TOC analyzers are installed in return line from each area and in the common return line to
the circulation pumps, to monitor the hydrocarbons content in the system. Recirculating water conductivity
is monitored too.
The SCW Storage Tank T-73101 is provided with a blanketing system to prevent ingress of air, which
affects the water quality.
Page 6 of 6
Petrochemical Plant Sohar Environmental Impact Assessment Report
Orpic and CB&I HMR #3817
CB&I ORPIC
Page 1 of 5
"THIS DOCUMENT IS THE PROPERTY OF CHICAGO BRIDGE & IRON COMPANY (CB&I). IT MAY CONTAIN INFORMATION
DESCRIBING TECHNOLOGY OWNED BY CB&I AND DEEMED TO BE COMMERCIALLY SENSITIVE. IT IS TO BE USED ONLY IN
CONNECTION WITH WORK PERFORMED BY CB&I. REPRODUCTION IN WHOLE OR IN PART FOR ANY PURPOSE OTHER THAN
WORK PERFORMED BY CB&I IS FORBIDDEN EXCEPT BY EXPRESS WRITTEN PERMISSION OF CB&I. IT IS TO BE SAFEGUARDED
AGAINST BOTH DELIBERATE AND INADVERTENT DISCLOSURE TO ANY THIRD PARTY."
Liwa Plastics Project
Page 2 of 5
Liwa Plastics Project
Table of Contents
Contents Page
1.0 INTRODUCTION..................................................................................................................................5
2.0 PROCESS DESCRIPTION...................................................................................................................5
Page 3 of 5
Liwa Plastics Project
ABBREVIATION
Page 4 of 5
Liwa Plastics Project
1.0 INTRODUCTION
For operation of the new LPP of Olefins Complex, located in the Republic of Oman, inert gas (Nitrogen) is
required.
Nitrogen is continuously used for blanketing, purging, start-up, emergency shutdown, catalyst activation,
stripping and regeneration of reactors. Nitrogen is not produced inside the Complex, but it is supplied from
third party to the new Petrochemical Complex.
Page 5 of 5
Petrochemical Plant Sohar Environmental Impact Assessment Report
Orpic and CB&I HMR #3817
CB&I ORPIC
Page 1 of 17
"THIS DOCUMENT IS THE PROPERTY OF CHICAGO BRIDGE & IRON COMPANY (CB&I). IT MAY CONTAIN INFORMATION
DESCRIBING TECHNOLOGY OWNED BY CB&I AND DEEMED TO BE COMMERCIALLY SENSITIVE. IT IS TO BE USED ONLY IN
CONNECTION WITH WORK PERFORMED BY CB&I. REPRODUCTION IN WHOLE OR IN PART FOR ANY PURPOSE OTHER THAN
WORK PERFORMED BY CB&I IS FORBIDDEN EXCEPT BY EXPRESS WRITTEN PERMISSION OF CB&I. IT IS TO BE
SAFEGUARDED AGAINST BOTH DELIBERATE AND INADVERTENT DISCLOSURE TO ANY THIRD PARTY."
Liwa Plastics Project
Page 2 of 17
Liwa Plastics Project
Table of Contents
Contents Page
ABBREVIATIONS ............................................................................................................................................... 4
1.0 INTRODUCTION ....................................................................................................................................... 6
2.0 STEAM SYSTEM INCLUDING AUXILIARY BOILERS ........................................................................... 7
2.1 Auxiliary Boilers .................................................................................................................................. 7
2.2 Super High Pressure Steam ............................................................................................................... 7
2.3 High Pressure Steam .......................................................................................................................... 7
2.4 Medium Pressure Steam..................................................................................................................... 8
2.5 Low Low Pressure Steam ................................................................................................................... 9
2.6 Letdown Stations................................................................................................................................. 9
2.7 Blowdown from Auxiliary Boilers .................................................................................................... 11
3.0 STEAM CONDENSATE SYSTEM.......................................................................................................... 12
3.1 High Pressure Condensate/Medium Pressure Condensate/Low Low Pressure Condensate... 12
3.2 Condensate Collection and Storage................................................................................................ 13
3.3 Condensate Treatment ..................................................................................................................... 13
4.0 BOILER FEED WATER SYSTEM .......................................................................................................... 14
4.1 Deaerator............................................................................................................................................ 14
4.2 BFW Chemical Injection ................................................................................................................... 15
4.3 BFW Pumps ....................................................................................................................................... 16
Page 3 of 17
Liwa Plastics Project
ABBREVIATIONS
Page 4 of 17
Liwa Plastics Project
Page 5 of 17
Liwa Plastics Project
1.0 INTRODUCTION
For the Liwa Plastics Project in Oman this document describes the process of the following units which
are part of utility systems:
Steam System including Auxiliary Boilers (Unit 7400)
Steam Condensate System (Unit 7410)
Boiler Feed Water System (Unit 7420)
For the graphical representation of the Steam System including Auxiliary Boilers (Unit 7400) reference
is made to the Utility Process Flow Diagrams D-S740-5223-101 to D-S740-5223-109.
For the graphical representation of the Steam Condensate System (Unit 7410) reference is made to the
Utility Process Flow Diagrams D-S741-5223-101 to D-S741-5223-108.
For the graphical representation of the Boiler Feed Water System (Unit 7420) reference is made to the
Utility Process Flow Diagrams D-S742-5223-101 to D-S742-5223-103.
Page 6 of 17
Liwa Plastics Project
Page 8 of 17
Liwa Plastics Project
Page 9 of 17
Liwa Plastics Project
Trip of PRC/PRCT causes sudden decrease of the HS header pressure and consequently opening of
Fast Acting SHP/HP Steam Desuperheater (DS-74002). This results in quick pressure recovery of the
HS header by letting down the excess SHS caused by the turbine trip.
During normal operation no steam letdown is required. However, a minimum continuous flow of SHS is
passed through DS-74001 and DS-74002 in order to keep letdown/desuperheater hot and to avoid
thermal shock in case large steam quantities are to be letdown/desuperheated.
Temperature of the HS leaving the desuperheater is controlled by adjusting the flow rate of HP BFW to
the desuperheater.
Page 10 of 17
Liwa Plastics Project
In case the LLS header pressure decreases, first the LLS extraction flow rate from KT-26001 is
increased. If the header pressure continues to decrease, more MS is letdown to LLS via DS-74009 to
recover the pressure. A high selector is provided to override the signal from the LS header for this
purpose.
During normal operation no steam letdown is required. However, a minimum continuous flow of MS is
passed through DS-74005 and DS-74009 in order to keep letdown/desuperheater hot and to avoid
thermal shock in case large steam quantities are to be letdown/desuperheated.
Temperature of the LLS leaving the desuperheater is controlled by adjusting the flow rate of HP BFW
to the desuperheater.
Page 11 of 17
Liwa Plastics Project
Page 12 of 17
Liwa Plastics Project
Clean Condensate Pumps are driven by electric motor which is fed by emergency power. During
normal operation, two pumps are in operation and the third one is standby.
Vacuum Condensate or Cold Condensate (CC) is the steam condensate from surface condensers for
the turbines of the CGC (KT-22001), PRC (KT-25001), BRC (KT-26001), and Secondary CW Pump (P-
73101A/B). It is directly pumped to the ion exchange mixed beds of Condensate Polishing Package
(ME-74001) by the condensate pumps provided at the outlet of each surface condenser.
CC can be contaminated if CW leaks in the surface condensers. Possible leakage of CW into CC is
indicated by detection from the conductivity analyzers installed in CC lines from each of the surface
condensers. In case of high conductivity detection the CC routing is automatically diverted to the
Desalinated Water Tank (T-73401A/B).
Page 13 of 17
Liwa Plastics Project
Due to accumulation of suspended solids and hydrocarbons, it is necessary to regenerate the activated
carbon filters by backwashing. Demineralized water used for backwashing is supplied by Backwash
Water Pump (P-74104A/B) which is located in the demin water unit plot area.
Filtered condensate will be sent to the Condensate Polishing section to meet demin water quality.
Deionization or demineralization of filtered condensate takes place in mixed bed resin ion exchangers.
This is essential to meet the quality requirements of BFW. Four (3+1) mixed beds are provided for this
purpose.
A mixed-bed is a demineralizer unit in which the cation and anion resin beads are mixed together. In
effect, it is equivalent to a number of two-step demineralizers in series. De-ionization or
Demineralization of condensate takes place in mixed beds by exchanging of positive charge ions of
condensate with hydrogen ions (H+) and negative charge ions with hydroxyl ions (OH-).
After all activated sites on resins are deactivated by absorbed anion and cations, mixed bed resins
shall be regenerated by washing with diluted sulfuric acid and caustic. The regeneration effluent will be
sent to Neutralization Basin (Z-74101) for neutralization.
External regeneration of mixed beds is the preferred method of regeneration because of the following
reasons:
To avoid accidental ingress of regenerant chemicals in the water and steam circuit.
To design the operating unit without internals, and with a low bed depth producing a relatively low
pressure drop, whilst the regeneration station is designed with narrower columns and a high bed
depth facilitating resin separation.
In external regeneration exhausted resin is transferred hydraulically from the operating unit to the
regeneration station and a fresh regenerated resin charge is transferred back immediately.
Treated condensate is routed to Demin Water Tank (T-74102A/B) to be used as Demineralized Water
(DMW).
Silica and carbonate content in the raw condensate dictate the quality of the polished condensate. In
order to monitor performance of the polishing section, a silica-analyzer, conductivity-analyzer and a pH-
analyzer are installed downstream of the mixed beds.
To compensate losses of BFW caused by steam stripping, blowdown and etc. an addition of demin
water is required.
Main portion of Demin Water is pumped by Demin Water Pump (P-74103A/B/C) through series of heat
exchangers (E-74106 and E-74107) prior to being sent to the Deaerator Package (ME-74201). The
demin water temperature at the outlet of E-74107 is controlled by adjusting the LLS flow rate to the
exchanger. A small portion of demin water is sent to Power Plant and to Storage area for caustic
dilution prior heating in E-74106 and E-74107.
The Polymer plant demin water demand is provided by DM Water Transfer pump (P-74107 A/B).
A portion of demin water or condensate is utilized for filter backwash and different steps of regeneration
of mixed bed ion exchangers by means of related pumps.
4.1 Deaerator
Deaerator Package (ME-74201) consists of (1+1) x 50% deaerators which each deaerator has two
sections, a Degassing Section and a Storage Section (which provides the liquid hold up).
Deaerating is achieved in the Degassing Section of a deaerator by breaking the water into as many
small droplets as possible, and surrounding these droplets with an atmosphere of steam. This releases
the dissolved gases, which are carried with the excess steam to atmosphere. The deaerated water
then falls to the storage section of the vessel.
Page 14 of 17
Liwa Plastics Project
Demineralized Water (DMW), mainly recovered condensate, is pumped by Demin Water Pump (P-
74103A/B) and heated up in a series of Heat Exchangers (E-74106, and E-74107) prior to entering the
deaerator. DMW is required for producing BFW, making up water losses caused by steam stripping,
blowdown and etc.
Water is heated up to saturation temperature in the deaerator by direct spraying of LLS to the
Degassing Section. The deaerator operates at a positive pressure of 0.4 barg, to produce water at
approximately 110°C.
In order to increase the efficiency of the deaerator and to minimize stripping LLS steam use, the inlet
temperature of DMW to the deaerator (outlet temperature of E-74107) is maintained at 104 °C which is
approximately 6° C colder than the water saturation temperature at deaerator pressure.
The level controller of the deaerator maintains normal liquid level of the vessel by adjusting the flow of
DMW. The deaerator pressure is controlled by regulating flow of LLS supply while maintaining a fixed
purge rate through a restriction orifice.
Downstream of the deaerator, a conductivity analyzer and dissolved oxygen analyzer are used in order
to measure the efficiency of the deaerator and to monitor the BFW quality. Residual oxygen content of
BFW leaving the deaerator shall be less than 20 ppb prior to chemical injection. Residual oxygen of the
treated BFW shall be less than 7 ppb.
In order to meet BFW quality specification, amine solution (neutralizing amine) and oxygen scavenger
are added to BFW. Amine solution is injected to BFW downstream of the deaerator and oxygen
scavenger is injected into the Storage Section of the deaerator.
Downstream of the amine solution injection point, a pH Analyzer is provided to monitor the
performance of the amine solution.
In order to ensure that the desired quality is achieved, regular sampling of BFW is required.
MTBE unit is required deaerated water with specific chemical conditions and temperature. To meet the
MTBE BFW demand, a dedicated BFW Transfer Deaerator Package (ME-74203) is to be installed.
Demin water is to be heated by DM water / LLP Steam Exchanger (E-74108) to 104 °C which is
approximately 6° C colder than the water saturation temperature at BFW Transfer Deaerator Package
(ME-74203) operating pressure.
The deaerated water is sent by BFW Transfer Pump (P-74204 A/B) to MTBE unit after cooling in BFW
Cooler (E-74201) against cooling water. Part of deaerated water is sent directly to MTBE unit without
cooling.
Page 15 of 17
Liwa Plastics Project
The amine solution which is neutralizing amine shall be STEAMATE NA0880 (NALCO), GE or CH
1764D (CHIMEC) or equivalent. This has to be confirmed by chemicals supplier. The injection rate of
neutralizing amine shall be advised by chemicals supplier based on type of chemical selected.
Page 16 of 17
Liwa Plastics Project
Page 17 of 17
Petrochemical Plant Sohar Environmental Impact Assessment Report
Orpic and CB&I HMR #3817
Attachment 14: Process description for Instrument and Plant Air system
CB&I ORPIC
Page 1 of 7
"THIS DOCUMENT IS THE PROPERTY OF CHICAGO BRIDGE & IRON COMPANY (CB&I). IT MAY CONTAIN INFORMATION
DESCRIBING TECHNOLOGY OWNED BY CB&I AND DEEMED TO BE COMMERCIALLY SENSITIVE. IT IS TO BE USED ONLY IN
CONNECTION WITH WORK PERFORMED BY CB&I. REPRODUCTION IN WHOLE OR IN PART FOR ANY PURPOSE OTHER THAN
WORK PERFORMED BY CB&I IS FORBIDDEN EXCEPT BY EXPRESS WRITTEN PERMISSION OF CB&I. IT IS TO BE SAFEGUARDED
AGAINST BOTH DELIBERATE AND INADVERTENT DISCLOSURE TO ANY THIRD PARTY."
Liwa Plastics Project
Page 2 of 7
Liwa Plastics Project
Table of Contents
Contents Page
1.0 INTRODUCTION..................................................................................................................................5
2.0 PROCESS DESCRIPTION...................................................................................................................5
2.1 Instrument and Plant Air Generation.......................................................................................5
2.2 Other intermittent regeneration processes.............................................................................6
2.3 Decoking Air Generation..........................................................................................................7
Page 3 of 7
Liwa Plastics Project
ABBREVIATION
Page 4 of 7
Liwa Plastics Project
1.0 INTRODUCTION
For operation of the new LPP of Petrochemical Complex, located in Sohar refinery, the Sultanate of Oman,
compressed air is required.
Compressed Air is used for three main functions: serving as Instrument Air, serving as Plant Air which can
be also used as a utility stream for maintenance or purging purposes of the Units and as Decoking Air.
Instrument Air is used for pneumatic-operated instrumentation such as control valves, on/off valves, for
purging / cooling of essential instruments such as burner flame scanners and for pilot burner flame front
generation of the flare(s).
Plant air is used for maintenance activities, as purge and as tool air for industrial users. Plant Air is also
used as a peak demand for catalyst regeneration.
Decoking Air is used for steam/air decoking of Cracking Heaters and TLE heat exchangers.
Page 5 of 7
Liwa Plastics Project
the condensate. The water separator is designed so that the air at the outlet of the separator shall not be
more than 5 % over-saturated under any operating conditions. For start-up, a connection for portable air
compressor upstream Air KO Drum (V-76001) has been foreseen.
To reduce the dew point of the compressed air to -30°C at normal operating pressure for dedicated
Instrument air purpose, a heatless desiccant type Air Dryer package ME–76002 will be installed. The
package consists of two set Air Dryers (ME-76002-D01A/B/C/D), each set capable of 100 % air flow. The
desiccant is usually activated alumina or silica gel beds. To prevent rust settlement on the air dryer
desiccants (1 + 1) x 100 % air pre-filter are provided at inlet of the air dryer package.
The Air Dryers are twin vessel adsorption type and provided with depressurization silencer and valves at
the vessels inlets and outlets for automatic switching the vessels from drying to the regeneration stage and
vice versa. Automatic switching is based on air dew point metering/control on dried air header. The
moisture controller is only permitted to change over when the desiccant has adsorbed moisture to its
capacity. During regeneration, the vessel is depressurized slowly to prevent blowing out and/or
fragmentation of the desiccant and is slowly pressurized prior to adsorption.
It is assumed that 20 % of dried air is utilized for air dryer regeneration. After desiccant has been
regenerated the vessel is pressurized slowly before switchover. Slow venting and pressurizing reduce
noise and damage to desiccant bed. Also to prevent desiccant particles from entering the instrument air
supply piping, (1+1) x 100% after-filters are provided at outlet of Air Dryer package. The design capacity of
the Air Dryer Package is set based on dried air to be supplied to instrument air distribution.
The air will be dried in order to avoid condensation in the lines and subsequently corrosion, leading to rust
particles which can clog up instrument air lines and orifices. Filters up and downstream of the dryers
prevent subsequently clogging up of the dryers or desiccant particles in the dried air
Part of dried air is delivered to the Instrument Air Buffer Vessel V-76002 to serve as buffer volume in the
event of compressor failure and also as fluctuation damper for compressors loading and unloading. The
buffer vessel is sized for 20 min of hold-up to provide enough time for operators corrective action. From
there the air is sent via pressure control to instrument air distribution header. The plant air is taken out
upstream of Air Dryers Package (ME-76002) on pressure control. The plant air supply is closed if
Instrument Air pressure in the header becomes too low in order to assure sufficient pressure for instrument
air distribution.
Part of dried instrument air (when is required) is compressed to 40 barg by HP Air Compressor Package
(ME-76004) and stored in high pressure Second Instrument Air Buffer Vessel (V-76003) to serve auxiliary
steam boilers and cracker heaters in case of lack of instrument air. The buffer vessel is sized for 6 hours
hold-up to provide sufficient time for operators for safe shutdown of cracker heaters.
Page 6 of 7
Liwa Plastics Project
The detailed procedures of regeneration of catalyst beds including the required plant air demand is
provided by the relevant Licensors.
All the above processes are on intermittent basis and are not likely to be performed at the same time.
Furnace decoking process requires air quantities to range gradually from virtually zero up to a maximum to
avoid radiant coils overheating due to uncontrolled coke combustion reaction inside the coils. Detailed
procedure of decoking process and required ramp up of air flow together with diluting steam flow will be
provided by the Licensor.
The controllability of the compressor system is of crucial importance. Because the decoking air is required
on intermittent basis, the both compressors will be electric motor-driven and operates based on so called
blow-off and inlet throating.
The compressed air is routed to the Cracking Heater. The pressure in the header is controlled by venting to
the atmosphere, and the decoking air is controlled by flow control valve located at the cracking heaters.
Page 7 of 7
Petrochemical Plant Sohar Environmental Impact Assessment Report
Orpic and CB&I HMR #3817
CB&I ORPIC
Page 1 of 11
"THIS DOCUMENT IS THE PROPERTY OF CHICAGO BRIDGE & IRON COMPANY (CB&I). IT MAY CONTAIN INFORMATION
DESCRIBING TECHNOLOGY OWNED BY CB&I AND DEEMED TO BE COMMERCIALLY SENSITIVE. IT IS TO BE USED ONLY IN
CONNECTION WITH WORK PERFORMED BY CB&I. REPRODUCTION IN WHOLE OR IN PART FOR ANY PURPOSE OTHER THAN
WORK PERFORMED BY CB&I IS FORBIDDEN EXCEPT BY EXPRESS WRITTEN PERMISSION OF CB&I. IT IS TO BE SAFEGUARDED
AGAINST BOTH DELIBERATE AND INADVERTENT DISCLOSURE TO ANY THIRD PARTY."
Liwa Plastics Project
Page 2 of 11
Liwa Plastics Project
Table of Contents
Contents Page
1.0 INTRODUCTION..................................................................................................................................4
2.0 DEFINITIONS ......................................................................................................................................4
3.0 WASTE WATER TREATMENT UNIT...................................................................................................5
3.1 Waste Water Collection and Handling.....................................................................................5
3.2 Last Line of Defense (LLOD)....................................................................................................5
3.3 Benzene / MTBE Contaminated Waste Water Pre-treatment..................................................7
3.4 Waste Water Primary Treatment..............................................................................................8
3.5 Waste Water Secondary Treatment .........................................................................................9
3.6 Waste Water Tertiary Treatment ............................................................................................10
3.7 Chemical Storage, Preparation and Dosing..........................................................................10
Page 3 of 11
Liwa Plastics Project
1.0 INTRODUCTION
Oman Refineries and Petrochemicals Company (ORPIC) is planning the installation of a new
Petrochemical Complex to be called Liwa Plastics Project (LPP) adjacent to Sohar Refinery Improvement
Project (SRIP) that will include a Steam Cracker Unit (SCU) designed to produce 859 kilo tons per annum
(KTA) of polymer grade ethylene and 286 KTA of polymer grade propylene, Refinery Dry Gas Unit, NGL
Treating and Fractionation Unit, Selective C4 Hydrogenation Unit, MTBE Unit, Butene-1 Recovery Unit,
Pygas Hydrotreating Unit, High Density Polyethylene (HDPE) Plant, Linear Low Density Polyethylene Plant
(LLDPE), new Polypropylene Plant (PP), and associated utility and offsite facilities. The new petrochemical
plant will be integrated with the Sohar Refinery, Sohar Aromatics Plant (AP) and Sohar Polypropylene
Plant (PP) plant.
ORPIC is also planning the installation of a new NGL Extraction plant located in Fahud, Central Oman. The
NGL (C2+) extracted from the natural gas will be transported to the petrochemical complex by pipeline and
used as feedstock to LPP. The new NGL Extraction plant will have independent utility and offsite facilities.
Additional feedstock to LPP are mixed LPG (produced in the Sohar Refinery and Sohar AP), refinery dry
gas produced in the RFCC unit and new Delayed Coking unit (included in SRIP), light naphtha condensate
from OLNG by marine tanker.
This document covers the process description for the Waste Water Treatment Unit 8500 of the new Liwa
Plastics Project in Oman. This document needs to be updated based on package equipment vendor
information in the later stage of project.
2.0 DEFINITIONS
The following terms and abbreviations have been used in this document:
Term Definition
AOC Accidentally Oil Contaminated
BOD Biological Oxygen Demand
COD Chemical Oxygen Demand
DGF Dissolved Gas Floatation
FFB First Flush Basin
IAF Induced Air Floatation
LLOD Last Line Of Defense
OC Oil Contaminated
OCB Oil Contaminated Basin
POB Peak Overflow Basin
TOD Total Oxygen Demand
WW Waste Water
WWT Unit Waste Water Treatment Unit
Page 4 of 11
Liwa Plastics Project
Page 6 of 11
Liwa Plastics Project
Domestic Lift Station (ME-85011). Eight (8) number of Domestic Lift Pump Stations will be installed in
specific areas which shall transfer the solid and liquid wastes to OSBL (MISC) for further treatment.
concentrations of hydrocarbons in the feed, the PC will open the valve in the nitrogen line to bring the
pressure up to the desired set point. When there is an overpressure due to an increase in the quantity of
non-condensable in the feed, the PC opens the valve on the vapor outlet to the wet flare. The pressure in
the overhead reflux drum is set at about 1 barg in order to ensure proper disposal of vents to the flare.
The steam stripped effluent collected from the bottom of the column is pumped by means of the Stripped
Waste Water Pump (P-85009 A/B) to the Waste Water Equalization Tank (T-85002) after heat recovery in
Feed/Effluent Heat Exchanger (E-85001 A/B) and cooling down in Stripped WW Trim Cooler (E-85002) to
below 40 °C using cooling water.
In case of high benzene and/or MTBE contamination of the steam stripped effluent, it is manually routed
back to the Benzene / MTBE Contaminated WW Collection Tank (T-85004). This is also done in case of
low-low temperature in the column. In the latter case, sufficient stripping of benzene/MTBE cannot be
ensured.
If the stripped effluent is on-spec according to benzene/MTBE contamination level but off-spec due to high
TOC, the stripped waste water shall be sent to Waste Water Collection Tank (T-85001) and to be treated
by Dissolved Gas Floatation Unit (ME-85005), Otherwise stripped waste water shall be sent to WW
Equalization Tank (T-85002).
Page 8 of 11
Liwa Plastics Project
The Waste Water Equalization Tank (T-85002) receives the waste water streams to be treated in the
Biological Treatment Package (ME-85006). The following streams are routed to the Waste Water
Equalization Tank:
DGF effluent from the waste water primary treatment
TLE Hydrojetting / decoking quench water effluent
Page 9 of 11
Liwa Plastics Project
Oily sludge will be kept separate from bio-sludge. The oily sludge from LLOD basins, Waste water
Collection Tank (T-85001), Skimming from IAF (ME-85009), Sludge from Polymer Plant and WW Dissolved
Gas Floatation (DGF) package (ME-85005) will be sent to Oily Sludge Collection Tank (T-85005) where it
will be pumped to Sludge Dewatering Package (ME-85007). The dewatered oily sludge is collected in a
mobile oily sludge container for incineration. The reject stream will be sent to Waste Water Secondary
Treatment (ME-85006) Package for further processing.
Air Compressor Package (ME-85017) and Critical Equipment in WW Secondary Treatment Package e.g.
Clarifier Scraper, Recirculating Pump etc. to be fed by Emergency Power Supply System.
For removal of remaining suspended solids, the dechlorinated water is routed to the Continuous Sand
Filter. The unit consists of two continuously regenerated sand filters, each designed for 70 % of total
capacity. The continuous backwash stream from the sand filters is recycled to WW Collection Tank (T-
85001). In case of high TOC in Chlorination Tank, the Chlorination Tank has to be drained into the Waste
Water Collection Tank (T-85001) via Backwash Effluent Basin.
The clean effluent from sand filters will flow on gravity into the Filtrate Basin, where the treated effluent
quality is continuously monitored by means of a flow, turbidity, temperature, TOD and pH measurement.
It is expected that sand filter clear water can meet the outfall water quality. However, in case of
hydrocarbon contamination, the effluent can be sent to Activated Carbon Filters for final polishing. The
treated waste water will be sent to the Treated Effluent Tank (T-85003).
Page 10 of 11
Liwa Plastics Project
Caustic Dosing Vessel and Caustic Dosing Pump are surrounded by a dike wall to isolate the package
from surrounding environment in case of any accidental leakages. The drainage is routed to Neutralization
Pit (Z-85005).Nutrient (Urea and Phosphoric Acid) Preparation and Dosing Package (ME-85012)
Urea and phosphoric acid are used as nitrogen and phosphorous supplement for Aeration Tanks and
aerobic Sludge Digester.
Granular urea is dissolved in water with a concentration of about 10 wt% and stored in Urea Solution Tank.
Diluted urea is sent to the users by Urea Solution Dosing Pump.
Chemical Neutralization
All chemical drains, Benzene/MTBE contaminated WW from drainage of P-85007A/B, P-85008A/B and P-
85009A/B are routed by gravity to Neutralization Pit (Z-85005) where either caustic or sulfuric acid will be
added to neutralize the content of basin. A pH measurement is installed for control of neutralization.
To facilitate neutralization process, Neutralization Pit Pump (P-85012 A/B) is utilized to circulate the basin
content. The neutralized chemical will be sent to Cooling Water Outfall channel along with manual
provision for routing it to WW Equalization Tank. Primary destination is Cooling Water Outfall Channel. Due
to high salt content in Neutralized chemical effluent, treated waste water may not meet outfall water spec in
case of routing it to Equalization Tank (T-85002).
The operators are to flush the chemical collection header with water after each drain or spillage.
Page 11 of 11
Liwa Plastics Project
CB&I ORPIC
Page 1 of 11
"THIS DOCUMENT IS THE PROPERTY OF CHICAGO BRIDGE & IRON COMPANY (CB&I). IT MAY CONTAIN INFORMATION
DESCRIBING TECHNOLOGY OWNED BY CB&I AND DEEMED TO BE COMMERCIALLY SENSITIVE. IT IS TO BE USED ONLY IN
CONNECTION WITH WORK PERFORMED BY CB&I. REPRODUCTION IN WHOLE OR IN PART FOR ANY PURPOSE OTHER THAN
WORK PERFORMED BY CB&I IS FORBIDDEN EXCEPT BY EXPRESS WRITTEN PERMISSION OF CB&I. IT IS TO BE SAFEGUARDED
AGAINST BOTH DELIBERATE AND INADVERTENT DISCLOSURE TO ANY THIRD PARTY."
Liwa Plastics Project
Page 2 of 11
Liwa Plastics Project
Table of Contents
Contents Page
1.0 INTRODUCTION..................................................................................................................................4
2.0 DEFINITIONS ......................................................................................................................................4
3.0 WASTE WATER TREATMENT UNIT...................................................................................................5
3.1 Waste Water Collection and Handling.....................................................................................5
3.2 Last Line of Defense (LLOD)....................................................................................................5
3.3 Benzene / MTBE Contaminated Waste Water Pre-treatment..................................................7
3.4 Waste Water Primary Treatment..............................................................................................8
3.5 Waste Water Secondary Treatment .........................................................................................9
3.6 Waste Water Tertiary Treatment ............................................................................................10
3.7 Chemical Storage, Preparation and Dosing..........................................................................10
Page 3 of 11
Liwa Plastics Project
1.0 INTRODUCTION
Oman Refineries and Petrochemicals Company (ORPIC) is planning the installation of a new
Petrochemical Complex to be called Liwa Plastics Project (LPP) adjacent to Sohar Refinery Improvement
Project (SRIP) that will include a Steam Cracker Unit (SCU) designed to produce 859 kilo tons per annum
(KTA) of polymer grade ethylene and 286 KTA of polymer grade propylene, Refinery Dry Gas Unit, NGL
Treating and Fractionation Unit, Selective C4 Hydrogenation Unit, MTBE Unit, Butene-1 Recovery Unit,
Pygas Hydrotreating Unit, High Density Polyethylene (HDPE) Plant, Linear Low Density Polyethylene Plant
(LLDPE), new Polypropylene Plant (PP), and associated utility and offsite facilities. The new petrochemical
plant will be integrated with the Sohar Refinery, Sohar Aromatics Plant (AP) and Sohar Polypropylene
Plant (PP) plant.
ORPIC is also planning the installation of a new NGL Extraction plant located in Fahud, Central Oman. The
NGL (C2+) extracted from the natural gas will be transported to the petrochemical complex by pipeline and
used as feedstock to LPP. The new NGL Extraction plant will have independent utility and offsite facilities.
Additional feedstock to LPP are mixed LPG (produced in the Sohar Refinery and Sohar AP), refinery dry
gas produced in the RFCC unit and new Delayed Coking unit (included in SRIP), light naphtha condensate
from OLNG by marine tanker.
This document covers the process description for the Waste Water Treatment Unit 8500 of the new Liwa
Plastics Project in Oman. This document needs to be updated based on package equipment vendor
information in the later stage of project.
2.0 DEFINITIONS
The following terms and abbreviations have been used in this document:
Term Definition
AOC Accidentally Oil Contaminated
BOD Biological Oxygen Demand
COD Chemical Oxygen Demand
DGF Dissolved Gas Floatation
FFB First Flush Basin
IAF Induced Air Floatation
LLOD Last Line Of Defense
OC Oil Contaminated
OCB Oil Contaminated Basin
POB Peak Overflow Basin
TOD Total Oxygen Demand
WW Waste Water
WWT Unit Waste Water Treatment Unit
Page 4 of 11
Liwa Plastics Project
Page 6 of 11
Liwa Plastics Project
Domestic Lift Station (ME-85011). Eight (8) number of Domestic Lift Pump Stations will be installed in
specific areas which shall transfer the solid and liquid wastes to OSBL (MISC) for further treatment.
concentrations of hydrocarbons in the feed, the PC will open the valve in the nitrogen line to bring the
pressure up to the desired set point. When there is an overpressure due to an increase in the quantity of
non-condensable in the feed, the PC opens the valve on the vapor outlet to the wet flare. The pressure in
the overhead reflux drum is set at about 1 barg in order to ensure proper disposal of vents to the flare.
The steam stripped effluent collected from the bottom of the column is pumped by means of the Stripped
Waste Water Pump (P-85009 A/B) to the Waste Water Equalization Tank (T-85002) after heat recovery in
Feed/Effluent Heat Exchanger (E-85001 A/B) and cooling down in Stripped WW Trim Cooler (E-85002) to
below 40 °C using cooling water.
In case of high benzene and/or MTBE contamination of the steam stripped effluent, it is manually routed
back to the Benzene / MTBE Contaminated WW Collection Tank (T-85004). This is also done in case of
low-low temperature in the column. In the latter case, sufficient stripping of benzene/MTBE cannot be
ensured.
If the stripped effluent is on-spec according to benzene/MTBE contamination level but off-spec due to high
TOC, the stripped waste water shall be sent to Waste Water Collection Tank (T-85001) and to be treated
by Dissolved Gas Floatation Unit (ME-85005), Otherwise stripped waste water shall be sent to WW
Equalization Tank (T-85002).
Page 8 of 11
Liwa Plastics Project
The Waste Water Equalization Tank (T-85002) receives the waste water streams to be treated in the
Biological Treatment Package (ME-85006). The following streams are routed to the Waste Water
Equalization Tank:
DGF effluent from the waste water primary treatment
TLE Hydrojetting / decoking quench water effluent
Page 9 of 11
Liwa Plastics Project
Oily sludge will be kept separate from bio-sludge. The oily sludge from LLOD basins, Waste water
Collection Tank (T-85001), Skimming from IAF (ME-85009), Sludge from Polymer Plant and WW Dissolved
Gas Floatation (DGF) package (ME-85005) will be sent to Oily Sludge Collection Tank (T-85005) where it
will be pumped to Sludge Dewatering Package (ME-85007). The dewatered oily sludge is collected in a
mobile oily sludge container for incineration. The reject stream will be sent to Waste Water Secondary
Treatment (ME-85006) Package for further processing.
Air Compressor Package (ME-85017) and Critical Equipment in WW Secondary Treatment Package e.g.
Clarifier Scraper, Recirculating Pump etc. to be fed by Emergency Power Supply System.
For removal of remaining suspended solids, the dechlorinated water is routed to the Continuous Sand
Filter. The unit consists of two continuously regenerated sand filters, each designed for 70 % of total
capacity. The continuous backwash stream from the sand filters is recycled to WW Collection Tank (T-
85001). In case of high TOC in Chlorination Tank, the Chlorination Tank has to be drained into the Waste
Water Collection Tank (T-85001) via Backwash Effluent Basin.
The clean effluent from sand filters will flow on gravity into the Filtrate Basin, where the treated effluent
quality is continuously monitored by means of a flow, turbidity, temperature, TOD and pH measurement.
It is expected that sand filter clear water can meet the outfall water quality. However, in case of
hydrocarbon contamination, the effluent can be sent to Activated Carbon Filters for final polishing. The
treated waste water will be sent to the Treated Effluent Tank (T-85003).
Page 10 of 11
Liwa Plastics Project
Caustic Dosing Vessel and Caustic Dosing Pump are surrounded by a dike wall to isolate the package
from surrounding environment in case of any accidental leakages. The drainage is routed to Neutralization
Pit (Z-85005).Nutrient (Urea and Phosphoric Acid) Preparation and Dosing Package (ME-85012)
Urea and phosphoric acid are used as nitrogen and phosphorous supplement for Aeration Tanks and
aerobic Sludge Digester.
Granular urea is dissolved in water with a concentration of about 10 wt% and stored in Urea Solution Tank.
Diluted urea is sent to the users by Urea Solution Dosing Pump.
Chemical Neutralization
All chemical drains, Benzene/MTBE contaminated WW from drainage of P-85007A/B, P-85008A/B and P-
85009A/B are routed by gravity to Neutralization Pit (Z-85005) where either caustic or sulfuric acid will be
added to neutralize the content of basin. A pH measurement is installed for control of neutralization.
To facilitate neutralization process, Neutralization Pit Pump (P-85012 A/B) is utilized to circulate the basin
content. The neutralized chemical will be sent to Cooling Water Outfall channel along with manual
provision for routing it to WW Equalization Tank. Primary destination is Cooling Water Outfall Channel. Due
to high salt content in Neutralized chemical effluent, treated waste water may not meet outfall water spec in
case of routing it to Equalization Tank (T-85002).
The operators are to flush the chemical collection header with water after each drain or spillage.
Page 11 of 11
Liwa Plastics Project
CB&I ORPIC
Page 1 of 13
"THIS DOCUMENT IS THE PROPERTY OF CHICAGO BRIDGE & IRON COMPANY (CB&I). IT MAY CONTAIN INFORMATION
DESCRIBING TECHNOLOGY OWNED BY CB&I AND DEEMED TO BE COMMERCIALLY SENSITIVE. IT IS TO BE USED ONLY IN
CONNECTION WITH WORK PERFORMED BY CB&I. REPRODUCTION IN WHOLE OR IN PART FOR ANY PURPOSE OTHER THAN
WORK PERFORMED BY CB&I IS FORBIDDEN EXCEPT BY EXPRESS WRITTEN PERMISSION OF CB&I. IT IS TO BE SAFEGUARDED
AGAINST BOTH DELIBERATE AND INADVERTENT DISCLOSURE TO ANY THIRD PARTY."
Liwa Plastics Project
Page 2 of 13
Liwa Plastics Project
Table of Contents
Contents Page
1.0 INTRODUCTION..................................................................................................................................4
1.1 Purpose ....................................................................................................................................4
1.2 General .....................................................................................................................................4
2.0 REFERENCES.....................................................................................................................................4
3.0 DEFINITIONS ......................................................................................................................................4
4.0 OPERATIONAL CONTROL PHILOSPHY............................................................................................5
4.1 Liquid Waste Handling and Collection ....................................................................................5
4.2 Last Line Of Defense................................................................................................................5
4.3 Benzene / MTBE Contaminated Waste Water Pre-treatment..................................................7
4.4 Waste Water Primary Treatment..............................................................................................9
4.5 Waste Water Secondary Treatment .......................................................................................10
4.6 Waste Water Tertiary Treatment ............................................................................................11
4.7 Chemical Storage, Preparation and Dosing..........................................................................12
Page 3 of 13
Liwa Plastics Project
1.0 INTRODUCTION
1.1 Purpose
The purpose of this document is to present the operation and process control philosophy for the new
Waste Water Treatment Unit 8500, part of the off-sites facilities of the LPP.
1.2 General
Process control is a multi-disciplinary specialism where the process objectives, process constraints,
instrumentation functionality and operational experience should come together to maintain a safe, stable
and optimum operation.
All process control activities are related to the following two functionalities:
Operational control
Instrumented safeguarding
2.0 REFERENCES
The following documents are referenced herein and form part of the technical requirements.
This document shall be read in conjunction with the following documents:
3.0 DEFINITIONS
Term Definition
ASL Atmospheric Safe Location
AOC Accidentally Oil Contaminated
BOD Biological Oxygen Demand
BPCS Basic Process Control System
COD Chemical Oxygen Demand
Page 4 of 13
Liwa Plastics Project
Page 5 of 13
Liwa Plastics Project
The LLOD consists of influent Bar Screening Package ME-85001 and ME-85002, Oil Contaminated Basin
Z-85001, First Flush Basin Z-85002, Peak Overflow Basin Z-85003 and relevant pumps. The inlet
compartments of Z-85001 and Z-85002 are equipped with Oil Skimmer and Sludge Scraper ME-85003 and
ME-85004. The collected sludge will be transferred via LLOD Sludge Pumps P-85003A/B/C/D to Oily
Sludge Collection Tank T-85005 awaiting dewatering process.
Oily Water Sewer
Equipment oily drains, pump base plates, hydrocarbon sampling points and surface water run-off from the
paved area where hydrocarbon leakage expected to be occurred shall be collected by oily water sewer
system and routed by gravity to OCB Z-85001. Collected oily water is transferred to Waste Water
Collection Tank T-85001 via OC Water Pump P-85001A/B for appropriate treatment. Pump P-85001A/B
will be fed by emergency power and protected against clogging by OC Water Screening Package ME-
85001. The inlet compartment of OCB is equipped with a portable floating type oil skimmer to collect
skimmed oil. The skimmed oil is routed to Skimmed Oil Vessel V-85001.
The oily water level in Z-85001 is controlled by ON/OFF control via level transmitter located in Z-85001. In
case of the level in Z-85001 rises to a certain H level, pump P-85001A is automatically started by BPCS.
When the level still rises up to HH level limit, pump P-85001B is started by BPCS. When the level lowers to
a certain L level limit, pump P-85001A is automatically stopped by BPCS. When the level lowers to a
certain LL level limit pump P-85001B is automatically stopped by BPCS.
The quality of surface water run-off from the paved area where benzene / MTBE spillage may occur shall
be checked before routing to the sewer system. In case of high benzene / MTBE contamination, surface
water run-off shall be collected and sent to benzene / MTBE contaminated waste water pre-treatment unit.
Accidently Oil Contaminated Sewer
The AOC sewer system collects equipment drains and surface water run-off which is polluted neither by
benzene / MTBE nor by high concentration of other hydrocarbons and routes the collected effluent to FFB
Z-85002 through AOC Water Screening Package ME-85002, used to remove large objects for protecting
downstream equipment against damage or clogging. The inlet compartment of FFB is equipped with a
portable floating type oil skimmer to collect skimmed oil. The skimmed oil is transferred to Skimmed Oil
Vessel V-85001.
FFB is designed to hold rain water run-off from potentially hydrocarbon polluted area during first 35
minutes of rain fall. After this period FFB is filled and the surface water run-off overflows to POB. It is
expected that the contamination level of surface water run-off collected in POB is diluted to such an extent
that can bypass biological treatment and be treated only by IAF unit ME-85009. If the quality of collected
run-off in POB is far from outfall water specification (high BOD / high COD), the collected run-off shall be
treated along with first flush water collected in FFB in biological treatment unit. In addition, the POB is used
as surge basin in case of cooling water oil contamination. The WW in POB is routed to the Air Floatation
Package ME-85009 by using POB Water Pump P-85014A/B. Pump P-85014A/B is started manually by
operator and is protected by low level switch function located in POB Z-85003 via BPCS. Standby pump P-
85014A/B is available and can be used when required.
However, if the quality of collected water in FFB is off-spec due to high BOD / high COD, the water will be
sent to Waste Water Collection Tank T-85001 by means of FFB Water Pump P-85002A/B for further
treatment in the WWTU. Pump P-85002A/B is started manually by operator and is protected by low level
switch function located in FFB Z-85002 via the BPCS. Standby pump P-85002A/B is available and can be
used when required.
Sludge handling
LLOD Sludge from OCB Z-85001 screening package ME-85001, is routed to Oily Sludge Collection Tank
T-85005 by LLOD Sludge Pump P-85003A/B. The selected duty pump P-85003A/B via BPCS is
automatically started upon H level limit and automatically stopped upon L level limit. A standby pump is
available and can be used when required.
Page 6 of 13
Liwa Plastics Project
LLOD Sludge from FFB Z-85002 screening package ME-85002, is routed to Oily Sludge Collection Tank T-
85005 by LLOD Sludge Pump P-85003C/D. The selected duty pump P-85003C/D via BPCS is
automatically started upon H level limit and automatically stopped upon L level limit. A standby pump is
available and can be used when required.
Clean Water Sewer System
This system is a clean water sewer, collecting surface water run-off from non-contaminated areas where
source of hydrocarbon leakage/spillage does not exist. Due to the collected run-off is inherently clean, it
will be routed by gravity to the Storm Water Channel Pump Pit Z-85006. Overflow from Storm Water
Channel Pump Pit is routed to outfall channel. Collected surface water run-off is routed to Storm Water
Clarifier ME-85010 by using Storm Water Pump P-85015A/B. P-85015A/B is manually started and
protected against running dry by low level trip in the BPCS on the pump pit. The flow to ME-85010 is set by
single flow controller which manipulates the flow control valve downstream the controller. In package ME-
85010 suspended solids and trace of hydrocarbons (if any) will be separated. The clarified storm water will
be sent to MISC along with the provision for sending it to sea water return channel, and the collected
sludge will be transferred to Sludge Dewatering Package ME-85007.
All controls and instrumented safeguarding of the Storm Water Channel and the Storm Water Clarifier ME-
85010 shall be housed within the BPCS and SIS. This will be further developed during EPC phase of the
LPP by Detail Engineering Contractor and vendor.
Domestic Sewer System
This system collects domestic waste water from toilets, urinals, kitchen facilities, sinks, showers and the
like from buildings and shelters. Domestic effluent from kitchen facilities shall be equipped with grease
traps. Domestic effluents are routed by a sloped gravity underground pipe system into the centralized
Domestic Lift Station ME-85011. Eight (8) Domestic Lift Pump stations will be installed in specific areas
which shall transfer the solid and liquid wastes routed to MISC (OSBL) for further treatment.
All controls and instrumented safeguarding of the Domestic Lift Station ME-85011 shall be housed within
the BPCS and SIS. This will be further developed during EPC phase of the LPP by vendor.
Chemical Sewer System
To meet outfall water specification, the spent chemicals shall be neutralized first.
The Chemical Effluent from the collection system is collected by the Neutralization Pit Z-85005, where the
chemical solution is neutralized. The chemical content of the Neutralization Pit is mixed by a Jet Mixer M-
85003. The chemical solution from Z-85005 is pumped through the Jet Mixer M-85003, by Neutralization
Pit Pump P-85012A/B. The pump is manual operated by the operator and a standby pump is available
when required. The pump is protected against running dry, by means of low low level trip, which stops the
pump via BPCS. 20wt% Caustic from Caustic Dosing Package ME-85014 and concentrated sulfuric acid
from Sulfuric Acid Dosing Package ME-85015 can be added in the discharge stream of P-85012A/B, to
neutralize the chemical mixture in the Neutralization Pit Z-85005.
The neutralized spent chemical can be normally transferred to the Cooling Water Outfall Channel when the
temperature is right without further treatment, by using the Neutralization Pit Pump P-85012A/B, along with
manual provision for routing it to the WW Equalization Tank. In normal operation the primary destination is
the Cooling Water Outfall Channel, however due to high salt content in the neutralized chemical effluent
the treated WW may not meet the outfall water specification. When Outfall WW specification is not met the
neutralized spent chemical will be routed to the WW Equalization Tank.
The Benzene / MTBE Contaminated Waste Water Collection Tank T-85004 is used to collect all the waste
water streams before treatment in the Waste Water Steam Stripper C-85001. Since the WW contains
benzene and/or MTBE, the tank is provided with nitrogen blanketing. It is advised to provide the Nitrogen
blanketing pressure control with a ‘dead band’ (gap control), in order to avoid waste of Nitrogen. When the
pressure lowers in the tank to a certain limit Nitrogen will be added, and when the pressure rises to a
certain limit vapors from the tank are vented to the Vent Gas Incinerator Unit via Vent Gas Blower K-
85001A/B.
The tank is equipped with a tangential inlet and oil skimming facilities to remove the separated free oil.
From the tank, waste water is pumped by means of the Benzene / MTBE Contaminated Waste Water
Pump P-85007A/B on flow control to the Waste Water Steam Stripper C-85001. The Contaminated WW
flow to C-85001 is maintained by master level controller located on the WW Collection Tank T-85004,
which adjusts the set point of the slave Contaminated WW flow controller. The flow controller manipulates
the flow control valve in the Contaminated WW line connected to the top of C-85001. If necessary, the pH
of the Contaminated WW is adjusted by means of caustic or sulfuric acid dosing upstream the Steam
Stripper Feed/Effluent Heat Exchanger E-85001A/B. It is advised to provide the pH control with a ‘dead
band’ (gap control), in order to avoid waste of chemicals and unstable pH value. When the pH value lowers
to a certain limit, sulfuric acid will be added via control valve. In case of the pH value rises to a certain limit,
caustic will be added via control valve.
Benzene / MTBE contaminated WW is preheated by the stripper effluent stream in Steam Stripper
Feed/Effluent Heat Exchanger E-85001 A/B and fed to the top of the Waste Water Steam Stripper C-
85001. At the bottom of this column, LLP steam is supplied which strips the hydrocarbons out of the
influent. The amount of LP steam is controlled by a steam control valve located in the LLP steam supply
line, which is manipulated by a flow controller located in the column overhead line. The flow controller
output is adjusted automatically by a Feed Forward signal from the influent flow controller. In case of more
or less influent is transferred to the column, the overhead flow controller is reacting automatically. Vapors
at the top of the column are condensed and collected in the Steam Stripper Overhead Reflux Drum V-
85002. In this vessel, the condensed liquid will separate in a water layer and a thin oil layer, which flows
over the installed weir into the hydrocarbons compartment. The water in the vessel is pumped by means of
the Steam Stripper Reflux Pump P-85008A/B on level control as reflux to the column. A single interface
level controller in V-85002 manipulates the pump stroke length of pump P-85008A/B, in order to maintain a
stable level. A standby pump is available when required. The recovered hydrocarbons are routed to the
Skimmed Oil Vessel V-85001 on intermittent basis, by level on/off control, which manipulates the on/off
valve in the recovered hydrocarbon outlet of V-85002 to the open position automatically when the level
rises to a certain H level limit. The valve is closed automatically when the level is lowered to a certain L
level limit. Vapors are vented to the wet flare system.
Nitrogen will be used in order to maintain sufficient pressure in the overhead system of the column to allow
venting to the flare. Some nitrogen is required in case insufficient hydrocarbons (non-condensable) are
present in the waste water feed stream. It is fed upstream of the Steam Stripper Overhead Condenser E-
85003 to ensure proper condenser operation. In the event of a pressure loss in the system due to low
concentrations of hydrocarbons in the feed, the pressure controller will open the valve in the nitrogen line
to bring the pressure up to the desired set point. When there is an overpressure due to an increase in the
quantity of non-condensable in the feed, the pressure controller opens the valve on the vapor outlet to the
wet flare. It is advised to provide the pressure control with a ‘dead band’ (gap control), in order to avoid
waste of Nitrogen. The pressure in the overhead reflux drum is set at about 1 barg in order to ensure
proper disposal of vents to the flare.
Page 8 of 13
Liwa Plastics Project
The steam stripped effluent collected in the bottom of the column is pumped to the Waste Water
Equalization Tank T-85002 by means of the Stripped Waste Water Pump P-85009A/B under flow control,
after heat recovery in Feed/Effluent Heat Exchanger E-85001A/B. Downstream E-85001A/B the Stripped
WW is further cooled in Stripped WW Trim Cooler E-85002 to below 40°C using cooling water.
Downstream E-85002 the slave flow controller is located, which manipulates the flow control valve
downstream the flow controller in the same line. The slave flow controller set point is automatically
adjusted by master level controller, which is located at the bottom of the WW Steam Stripper C-85001 in
order to maintain a stable level. The Stripped WW Pump P-85009A/B is protected against too low flow by
minimum flow controller located in the pump discharge, which manipulates flow control valve in the pump
minimum flow bypass line routed back to the column bottom. The standby pump is started automatically
upon HH level limit in the stripper bottom and automatically stopped upon LL level limit, detected by BPCS
level transmitter.
In case of high benzene and/or MTBE contamination of the steam stripped effluent, it is manually routed by
BPCS operated 3-way valve back to the Benzene / MTBE Contaminated WW Collection Tank T-85004 for
recycle. This is also done in case of low-low temperature in the column. In the latter case, sufficient
stripping of benzene/MTBE cannot be ensured.
If the stripped effluent is on-spec according to benzene/MTBE contamination level but off-spec due to high
Total Oil Content, the stripped WW shall be manually routed by BPCS operated 3-way valve to Waste
Water Collection Tank T-85001 and to be treated by Dissolved Gas Floatation Unit ME-85005. During
normal operation the stripped WW shall be sent to WW Equalization Tank T-85002.
Page 9 of 13
Liwa Plastics Project
pH
coagulant and flocculant type and dose
nitrogen pressure
recycle rate
WW enters on one end and passes sequentially through coagulation, flocculation and floatation
compartments of the DGF package ME-85005. Poly electrolyte is dosed into the influent upstream of the
DGF unit to enhance the removal of free/emulsified oil and suspended solids. The system forces nitrogen
gas into effluent by means of hydraulic eductors. The nitrogen bubbles will adhere to the oil particles and
form flocs and help these particles to float to the water surface of each flotation compartment. The floating
scum layer is removed by means of a surface skimmer mechanism and sent to the Skimmed Oil Vessel V-
85001. The treated waste water will overflow via the effluent weir into the DGF clear well compartment and
is pumped by means of the DGF Clear well Pump to the Waste Water Equalization Tank T-85002.
All controls and instrumented safeguarding of the DGF package ME-85005 shall be housed within the
BPCS and SIS. This will be further developed during EPC phase of the LPP by vendor.
The Skimmed Oil Vessel V-85001 collects several oil streams from oil skimming facilities. Inside the vessel
a special plate pack is provided to separate the oil and water efficiently. The separated oil is collected via a
weir in the oil compartment of the vessel. This vessel is equipped with an interface level controller in the
oil/water compartment, which manipulates the variable speed drive of the Skimmed Oil Vessel Effluent
Pump P-85011, in order to maintain the interface level in the vessel. Pump P-85011 transfers Skimmed Oil
Vessel Effluent to WW Collection tank T-85001. On/off level control function in the oil compartment of the
vessel starts the Skimmed Oil Pump P-85010 automatically when a certain H level limit is reached, which
transfers skimmed oil to the Liquid Incinerator Package. When the level is lowered to a certain L level limit,
the pump is automatically stopped.
Page 10 of 13
Liwa Plastics Project
After pH adjustment, the mixed stream is routed to the Aeration Tank where the required amount of air is
supplied by Air Compressor Package ME-85017. Control of the required amount of air is done by means of
a dissolved oxygen measurement. Aerated stream will be routed to Clarifier on gravity flow via Degassing
Tank. In the Clarifier, the settled activated sludge is separated from the clean water. Part of the activated
sludge is recycled to the Contact Tank and the excess activated sludge is sent to the Sludge Digester
followed by Sludge Thickener part of package ME-85006. The clarified water is routed to the tertiary
treatment to meet the outfall water specification.
All controls and instrumented safeguarding of the Compressed Air Package ME-85017 and Biotreater
package ME-85006, shall be housed within the BPCS and SIS. This will be further developed during EPC
phase of the LPP by vendor.
Thickened excess bio-sludge from Sludge Thickener is sent to Sludge Dewatering Package ME-85007
where polymer electrolyte solution is added for conditioning of the sludge. Dewatered bio-sludge is
collected in a mobile bio-sludge cake container, which is trucked out for disposal or incineration. The
decanted water from Sludge Dewatering Package ME-85007 is recycled to the Waste Water Collection
Tank T-85001.
Oily sludge will be kept separate from bio-sludge. The oily sludge from LLOD basins, Waste Water
Collection Tank T-85001, skimming from IAF Package ME-85009, sludge from polymer plant and WW
Dissolved Gas Floatation package ME-85005, will be routed to Oily Sludge Collection Tank T-85005 where
it will be pumped by Oily Sludge Pump P-85013A/B to Sludge Dewatering Package ME-85007. The
dewatered oily sludge is collected in a mobile oily sludge container for incineration. The reject stream will
be sent to Sludge Treatment Package ME-85006 for further processing. T-85005 is provided with Nitrogen
blanketing. It is advised to provide the Nitrogen blanketing pressure control with a ‘dead band’ (gap
control), in order to avoid waste of Nitrogen. When the pressure lowers in the tank to a certain limit
Nitrogen will be added, and when the pressure rises to a certain limit vapors from the tank are vented to
the Vent Gas Incinerator Unit via Vent Gas Blower K-85001A/B. The Oily Sludge Pump P-85013A/B is
protected against running dry by a low level trip on the tank via BPCS. A standby pump is available when
required.
All controls and instrumented safeguarding of the Sludge Dewatering Package ME-85007, shall be housed
within the BPCS and SIS. This will be further developed during EPC phase of the LPP by vendor.
For removal of remaining suspended solids, the de-chlorinated water is routed to the Continuous Sand
Filter. The unit consists of two continuously regenerated sand filters, each designed for 70 % of total
capacity. The continuous backwash stream from the sand filters is recycled to WW Collection Tank T-
85001. The clean effluent from sand filters will flow on gravity into the Filtrate Basin, where the treated
effluent quality is continuously monitored by means of a flow, turbidity, temperature, TOD and pH
measurement.
Page 11 of 13
Liwa Plastics Project
It is expected that sand filter effluent (clear water) can meet the outfall water quality. However, in case of
hydrocarbon contamination or high BOD / COD, the effluent can be transferred by manual operation of a 3-
way valve via BPCS to the Activated Carbon Filters for final polishing.
All controls and instrumented safeguarding of the Waste Water Tertiary Treatment package ME-85008,
shall be housed within the BPCS and SIS. This will be further developed during EPC phase of the LPP by
vendor.
Finally the treated WW will be transferred to the Treated Effluent Tank T-85003, from where the treated
WW is transferred to MISC (OSBL) by using Treated Effluent Pump P-85006A/B under flow control. The
slave flow controller in the discharge of the pump manipulates the downstream located flow control valve.
The master level controller on T-85003 adjusts the set point of the slave flow controller automatically, in
order to maintain a stable level in the tank. A standby pump is available when required.
Nutrient (Urea and Phosphoric Acid) Preparation and Dosing Package ME-85012
Urea and phosphoric acid are used as nitrogen and phosphorous supplement for Aeration Tanks and
aerobic Sludge Digester.
Granular urea is dissolved in water with a concentration of about 10 wt% and stored in Urea Solution Tank.
Diluted urea is sent to the users by Urea Solution Dosing Pump.
Concentrated phosphoric acid is supplied in 1 m3 plastic containers. Concentrated phosphoric acid is
diluted with water to a concentration of about 10 wt% in Phosphoric Acid Dosing Vessel and is sent to the
users via Phosphoric Acid Dosing Pumps. The drainage of both tanks is routed to the Neutralization Pit Z-
85005.
All controls and instrumented safeguarding of the Nutrient Preparation and Dosing package ME-85012,
shall be housed within the BPCS and SIS. This will be further developed during EPC phase of the LPP by
vendor.
Page 12 of 13
Liwa Plastics Project
All controls and instrumented safeguarding of the Hypochlorite and SMBS Dosing package ME-85016,
shall be housed within the BPCS and SIS. This will be further developed during EPC phase of the LPP by
vendor.
Page 13 of 13
Liwa Plastics Project
CB&I ORPIC
Page 1 of 75
"THIS DOCUMENT IS THE PROPERTY OF CHICAGO BRIDGE & IRON COMPANY (CB&I). IT MAY CONTAIN INFORMATION
DESCRIBING TECHNOLOGY OWNED BY CB&I AND DEEMED TO BE COMMERCIALLY SENSITIVE. IT IS TO BE USED ONLY IN
CONNECTION WITH WORK PERFORMED BY CB&I. REPRODUCTION IN WHOLE OR IN PART FOR ANY PURPOSE OTHER THAN
WORK PERFORMED BY CB&I IS FORBIDDEN EXCEPT BY EXPRESS WRITTEN PERMISSION OF CB&I. IT IS TO BE SAFEGUARDED
AGAINST BOTH DELIBERATE AND INADVERTENT DISCLOSURE TO ANY THIRD PARTY."
Liwa Plastics Project
Page 2 of 75
Liwa Plastics Project
Page 3 of 75
Liwa Plastics Project
Page 4 of 75
Liwa Plastics Project
Table of Contents
Contents Page
Page 5 of 75
Liwa Plastics Project
1.0 INTRODUCTION
Oman Oil Refineries and Petroleum Industries Company (ORPIC) is planning the installation of a new
Petrochemical Complex to be called Liwa Plastics Project (LPP) adjacent to Sohar Refinery Improvement
Project (SRIP) that will include a Steam Cracker Unit (SCU) designed to produce 859 kilo tons per annum
(KTA) of polymer grade ethylene and 286 KTA of polymer grade propylene, Refinery Dry Gas Unit, NGL
Treating and Fractionation Unit, Selective C4 Hydrogenation Unit, MTBE Unit, Butene-1 Recovery Unit,
Pygas Hydrotreating Unit, High Density Polyethylene (HDPE) Plant, Linear Low Density Polyethylene Plant
(LLDPE), new Polypropylene Plant (PP), and associated utility and offsite facilities. The new petrochemical
plant will be integrated with the Sohar Refinery, Sohar Aromatics Plant (AP) and Sohar Polypropylene
Plant (PP) plant.
ORPIC is also planning the installation of a new NGL Extraction plant located in Fahud, Central Oman. The
NGL (C2+) extracted from the natural gas will be transported to the petrochemical complex by pipeline and
used as feedstock to LPP. The new NGL Extraction plant will have independent utility and offsite facilities.
Additional feedstock to LPP are mixed LPG (produced in the Sohar Refinery and Sohar AP), refinery dry
gas produced in the RFCC unit and new Delayed Coking unit (included in SRIP), light naphtha condensate
from OLNG by marine tanker.
This document contains the Guidelines for Operating Manual of the Off-sites facilities for the following units
of the new Liwa Plastics Project in Oman.
Waste Water Treatment Unit – 8500
Waste Incineration Unit – 8600
Flare Unit – 8900
This manual describes mainly the LLOD section; Benzene/MTBE contaminated waste water steam
stripping section of the WWTU and equipment which are out of package vendor scope of design and
supply for all the three mentioned units. The manual for the entire Utility unit itself will be supplied by the
package vendors. Therefore this manual shall be used together with the vendor’s operating manual(s) as
the basis for the preparation of the detailed operating manuals per unit.
This operating manual is intended as a guide and reference for personnel involved in the operations of the
mentioned units. It provides basic information which should be with the reference documents and vendor
information, sufficient to prepare detailed procedures and instructions for the operations of the unit.
In this operating Manual, reference is made to the following documents:
This document is useful as a guide in operation and does not necessarily represent exact operating
conditions or guarantees.
Page 6 of 75
Liwa Plastics Project
Page 7 of 75
Liwa Plastics Project
2.0 DEFINITIONS
The following terms and abbreviations have been used in this document:
Term Definition
AOC Accidentally Oil Contaminated
BOD Biological Oxygen Demand
COD Chemical Oxygen Demand
DGF Dissolved Gas Floatation
FFB First Flush Basin
IAF Induced Air Floatation
LLOD Last Line Of Defense
OC Oil Contaminated
OCB Oil Contaminated Basin
POB Peak Overflow Basin
TOD Total Oxygen Demand
TOC Total Organic Content
DO Dissolved Oxygen
TLE Transfer Line Exchanger
DCS Distributed Control System
TSS Total Suspended Solids
WW Waste Water
WWT Unit Waste Water Treatment Unit
OSBL Outside Battery Limit
ACF Activated Carbon Filter
DEC Detailed Engineering Contractor
Page 8 of 75
Liwa Plastics Project
Depending on the type of pollution, the waste water stream is routed to the appropriated treatment. As a
general rule, areas that could be contaminated with hydrocarbon shall be kept as small as possible. Also
continuously contaminated streams shall be kept separate from streams that are usually not contaminated
(Accidentally Contaminated) or not contaminated (Clean Drain).
The waste water treatment unit consists mainly of the following sections:
Last Line Of Defence (LLOD)
Benzene / MTBE contaminated waste water pre-treatment
Waste water primary treatment
Waste water secondary (biological) treatment
Waste water tertiary treatment
Clean Surface water run-off treatment
Domestic Effluent Collection and Treatment
Chemical storage, preparation and dosing
Page 9 of 75
Liwa Plastics Project
Page 10 of 75
Liwa Plastics Project
The Liquid and Solid Waste incinerator is fired with fuel gas with Natural Gas as back-up. The following
liquid and solid waste streams will be handled:
Skimmed Oil from Skimmed Oil Pump P-85010 (Skimmed Oil Vessel V-85001 in WWTU)
Waste Liquid from ME-86001-P-01 (Vent Gas KO Drum part of Vent Gas Incinerator Package)
Dewatered Bio Sludge from ME-85007 (from conveyor in WWTU)
Dewatered Oily Sludge from ME-85007 (from conveyor in WWTU)
Liquid waste (in barrel) from polymer plants containing up to 15 – 20% Alkyls
Skimmed oil from Amine Unit hydrocarbon drain pump (P-11054)
Hydrocarbon/water mixtures from drain vessels by tank car
Hydrocarbon/water mixtures or Maintenance Waste Oils from drums
Tar from Quench Water System
Page 11 of 75
Liwa Plastics Project
Flare Stack (ME-89002-SK-01A/B), Flare Tip, Flare Ignition System, and Molecular Seal and Fuel Gas KO
Drum (ME-89002-V-01): One system is in operation and one is in stand-by.
3.2 Product
Page 13 of 75
Liwa Plastics Project
Page 14 of 75
Liwa Plastics Project
Page 15 of 75
Liwa Plastics Project
Page 16 of 75
Liwa Plastics Project
Page 17 of 75
Liwa Plastics Project
Notes –
1. The indicated flow rates represent Waste Water Treatment Design Case. Operating Case flow rates
may differ from these figures.
2. Flow Specified in m3/day.
3. The provided figures are related to surface water run-off collected in Last Line of Defense basins in
case of “good housekeeping”. There is no guarantee on these figures as quality of surface water run-
off inherently depends on Orpic Unit operator’s attention on good housekeeping.
4. In case of higher concentration, the collected water has to be sent to Waste Water Stripper Unit.
5. FFB is designed to hold rain water run-off from potentially hydrocarbon polluted area during first 35
minutes of rain. After this period, FFB is filled and the surface water run-off overflows to POB.
Page 18 of 75
Liwa Plastics Project
Page 19 of 75
Liwa Plastics Project
Page 20 of 75
Liwa Plastics Project
Upon continuous low low level detection (850-LI-032) in the Oil Contaminated Water Basin, both pumps the
standby pump P-85002B will also be stopped automatically via BPCS.
Page 22 of 75
Liwa Plastics Project
Page 23 of 75
Liwa Plastics Project
Page 24 of 75
Liwa Plastics Project
Package (ME-85007) by Oily Sludge Pump P-85013A/B. The tank has been blanketed with nitrogen and
protected against over pressuring by PSV. In addition Oily Sludge Collection Tank (T-85005) has been
equipped with water sealed over flow line to be routed to Bounded Area. Oily Sludge Collection Tank is
provided with Safety Hatch to protect from overpressure during fire case. The relief is routed to
Atmosphere.
Page 25 of 75
Liwa Plastics Project
By getting low-low level detection in the Neutralization Pit (Z-85005) by 850-LI-029, the duty pump (P-
85012A or P-85012B) will be stopped automatically via BPCS.
4.1.2.14 Benzene/MTBE Contaminated Waste Water Collection Tank (T-85004) Normal Operating Variables
The Benzene/MTBE Contaminated Waste Water Collection Tank (T-85004) is used to store the
benzene/MTBE contaminated waste water awaiting steam stripping treatment. To reduce impact of VOC
(Volatile Organic Carbon) on environment, the tank has been blanketed with nitrogen and protected against
over pressuring by PSV. Tank is provided with safety hatch, to protect against the overpressure during the
fire scenario. The vapor release is vented to atmosphere.
Page 26 of 75
Liwa Plastics Project
4.1.2.14.1 Benzene/MTBE Contaminated Waste Water Collection Tank (T-85004) Level Control
The Benzene/MTBE Contaminated Waste Water Collection Tank level will be controlled via liquid level
controller (850-LC-017A) by manipulating flow control valve (850-FV-015) on the feed line to Steam
Stripper Column (C-85001).
To protect Benzene Contaminated WW Pump (P-85007A/B) against running dry, by getting low-low
liquid level (850-LI-018) in Benzene Contaminated Waste Water Collection Tank, both pumps P-
85007A/B will be stopped automatically via BPCS.
4.1.2.14.2 Benzene/MTBE Contaminated Waste Water Collection Tank (T-85004) Pressure Control
To prevent ingress of hazardous hydrocarbons (VOC) to the atmosphere, Benzene/MTBE
Contaminated Waste Water Collection Tank will be kept under nitrogen blanketing.
It is advised to provide the Nitrogen blanketing pressure control with a ‘dead band’ (gap control), in
order to avoid waste of Nitrogen. When the pressure lowers (850-PC-032) in the tank to a certain limit
Nitrogen will be added (Opens Pressure control valve 850-PV-033), and when the pressure rises to a
certain limit vapors from the tank are vented (by means of pressure control valve 850-PV-032) to the
Vent Gas Incinerator Unit via Vent Gas Blower K- 85001A/B.
Page 27 of 75
Liwa Plastics Project
To protect Stripped WW Pump (P-85009A/B) against running dry, by getting low-low liquid level (850-
LI-020) in WW Steam Stripper (C-85001) bottom, both pumps P-85009A/B will be stopped
automatically.
4.1.2.16 Steam Stripper OVHD Reflux Drum (V-85002) Normal Operating Variables
Page 28 of 75
Liwa Plastics Project
Page 29 of 75
Liwa Plastics Project
Page 30 of 75
Liwa Plastics Project
automatically. The MP steam flow is adjusted automatically by the total relief flow from Acid Gas Flare KO
drum V-89008 and Wet Gas Flare KO Drum V-89001 towards the flare stack.
Page 31 of 75
Liwa Plastics Project
Page 32 of 75
Liwa Plastics Project
Page 33 of 75
Liwa Plastics Project
General Note: In each unit, all the utility systems must be in service at normal conditions before
beginning operations on process equipment.
Page 34 of 75
Liwa Plastics Project
The main header is blown first with a high air rate. First the lines from the header to the instrument
air regulators should be disconnected and any other regulator removed from the lines. Each
individual airline should be blown and dried.
The instrument air system shall be tested pneumatically with dry air.
All joints and connections shall be checked for tightness with a soapy water solution. Header and
branch lines shall be blown through with a high flow rate of air. During all these tests, the
instruments that will be supplied with air shall be carefully isolated from the system.
At the end of blowing and drying, all regulators and instruments should be connected again and
the instrument air system is placed in service at the normal operating pressure.
The water dew point of the air should be low enough to avoid condensation (and freezing) of water
at the local atmospheric conditions.
Page 35 of 75
Liwa Plastics Project
5.6.10 Electricity
The electric facilities should be checked and commissioned by the electrical specialists/vendors and other
parties that are involved in these facilities.
Page 36 of 75
Liwa Plastics Project
Page 37 of 75
Liwa Plastics Project
6.1 Introduction
In this section an outline is given for the normal start-up of the WWTU. It shall be reminded that the
package vendors have to be consulted for start-up operation.
Page 38 of 75
Liwa Plastics Project
6.4.1 Status
When the pre-commissioning and commissioning activities have been completed, the status of the units is
as follows:
All equipment and piping has been cleaned, tested and drained.
All equipment is at ambient conditions full of air.
All battery limit valves are closed and can be opened as required.
All instrumentation is commissioned and ready for use.
Seal-oil/water systems are commissioned and ready for use.
All motors are ready for operation.
All relief valves have been shop tested and reinstalled.
All vents, drains and sample points are closed.
The plant has been verified to have been built according to P&IDs.
After inerting, if required, the charging of the headers is done by gradually opening the battery limit valve.
The headers are pressurized and checked for leaks. The headers are blown or flushed through to displace
the air or inert medium. The vents and drains are closed and the header is pressured to plant header
pressure.
6.4.3 Steam-out
Prior to actual start-up, proper steam out has to take place in order to expel air or inerts and clean
equipment and lines. The procedure is general.
First operator has to check that selected equipment is designed for steam out condition
Using the steam out nozzle or utility connection nozzle in equipment, commence steaming out
the unit to displace air and warm up pipe work.
Check that pipe work and vessels are free to expand as designed and are not obstructed.
Drain condensate from all low point drains.
Continue steaming out, until clean white steam plumes are seen at the vents and oxygen
content in the equipment is below 1% vol.
Page 39 of 75
Liwa Plastics Project
Close vents and drains and stop steam flows. Prevent vacuum due to cool down in equipment
which normally operates under atmospheric conditions or overpressure: maintain positive
pressure by introducing nitrogen.
6.5 Start-up
This section describes mainly LLOD and waste water stripper section. For normal start-up procedure
reference is made to package vendor instructions.
6.5.1 LLOD
The start-up procedures described below assumes that appropriate pre-startup preparation of the waste
water collection system has taken place. This includes the following:
All collection pits / sumps / basins / tanks are cleaned
All pumps are installed and tested for good operation
All analyzers are installed and calibrated
The Industrial sewer drainage piping are clean
The Waste Water Collection Tank (T-85001) is properly lined up and blanketed with nitrogen.
The vent gas line from the WW Collection Tank to the Vent Gas Incinerator package is open
and available.
Vent gas Blower K-85001A/B is ready for use, as the vent gas from the tank will be routed to
Vent gas Incinerator package through this Blower.
All controllers are in manual mode.
All utilities should be available at sufficient quantities.
The complete system has to be filled up with clean water.
Before the drainage of water from curbed, diked and bund wall areas, the content has to be
neutralized.
The start-up procedure of the waste water collection system is described below by focusing on the basic
sequence and type of activities that need to be done. Each step needs to be described in more detail in the
Operating Manual to be prepared by Detailed Design Contractor.
Before operation, the complete system has to be partially filled with (clean) water (walls have to
be wet); to prevent that oil is sticking to the wall.
The Oil Contaminated Water Basin (Z-85001) is designed that at high level, pumps will
automatically be switched on by a level switch.
Operator has to take samples from the water in the different compartments of the FFB (Z-
85002), and determine if it has to be treated, and what kind of treatment is required
(Benzene/MTBE containing or non-Benzene / MTBE). Based on the selected treatment, the
correct discharge valves downstream the FFB Water Pump (P-85002A/B) has to be opened and
closed. This procedure has to be executed each time the FFB (Z-85002) and POB (Z-85003)
are filled and has to be emptied.
Page 40 of 75
Liwa Plastics Project
Page 41 of 75
Liwa Plastics Project
Page 42 of 75
Liwa Plastics Project
discharge by proper sewer system and routed by gravity to the below grade Last Line Of Defense (LLOD)
basins.
The LLOD consists of influent Bar Screening Package (ME-85001 and ME-85002), Oil Contaminated Basin
(Z-85001), First Flush Basin (Z-85002), Peak Overflow Basin (Z-85003) and relevant pumps. The POB
together with the FFB are designed to catch the total firewater run-off result of the biggest fire scenario.
The inlet compartments of Z-85001 and Z-85002 are equipped with Oil Skimmer and Sludge Scraper (ME-
85003 and ME-85004). The collected sludge will be sent to Oily Sludge Collection Tank (T-85005) awaiting
dewatering process via LLOD Sludge Pumps (P-85003A/B/C/D).
By taking into account the above considerations, the following effluent collection systems are designed:
Oily Water Sewer (OWS)
Equipment oily drains, pump base plates, hydrocarbon sampling points and surface water run-off from the
paved area where hydrocarbon leakage expected to be occurred shall be collected by oily water sewer
system and routed by gravity to OCB (Z-85001). Then the collected oily water is send to Waste Water
Collection Tank via OC Water Pump (P-85001 A/B) for appropriate treatment. The OC Water Pump (P-
85001 A/B) will be fed by emergency power and protected against clogging by OC Water Screening
Package (ME-85001). The OC Water Pump (P-85001 A/B) is low speed non-emulsified pump. The inlet
compartment of OCB is equipped with portable floating type oil skimmer. The skimmed oil is sent to
Skimmed Oil Vessel (V-85001).
The quality of surface water run-off from the paved area where benzene / MTBE spillage may occur shall
be checked before routing to sewer system. In case of high benzene / MTBE contamination, surface water
run-off shall be collected and sent to benzene / MTBE contaminated waste water pre-treatment unit.
Accidently Oil Contaminated Sewer (AOC)
The AOC sewer system collects equipment drains and surface water run-off which is polluted neither by
benzene / MTBE nor by high concentration of other hydrocarbons and routes the collected effluent to FFB
through AOC Water Screening Package (ME-85002). The purpose of screening is to remove large objects
such as rags, plastics, paper, metals, dead animals, and the like and protect downstream equipment from
damage or clogging. The inlet compartment of FFB is equipped with a portable floating type oil skimmer to
collect skimmed oil if any. The skimmed oil is sent to Skimmed Oil Vessel (V-85001).
FFB is designed to hold rain water run-off from potentially hydrocarbon polluted area during first 35
minutes of rain. After this period, FFB is filled and the surface water run-off overflows to POB. It is
expected that the contamination level of surface water run-off collected in POB is diluted to such an extent
that can bypass biological treatment and be treated only by Induced Air Floatation (IAF) unit (ME-85009). If
the quality of collected run-off in POB is far from outfall water specification (high BOD / high COD), the
collected run-off shall be treated along with first flush water collected in FFB in biological treatment unit. In
addition, the POB is used as surge basin in case of cooling water oil contamination.
During normal plant operation, it is expected that good housekeeping keeps surface water run-off collected
in FFB clean enough (low BOD / low COD) to be treated only by an Induced Air Floatation (IAF) Unit (ME-
85009) for removing any residual oil or suspended solids. Then the treated surface run-off will be sent to
Treated Effluent Tank (T-85003) for the final check and settled sludge will be pumped directly to Sludge
Dewatering Package (ME-85007). However, if the quality of collected water in FFB is off-spec due to high
BOD / high COD, the water will be sent to Waste Water Collection Tank (T-85001) by means of FFB Water
Pump (P-85002 A/B) for further treatment in the WWT unit. If the benzene contamination of the collected
surface water run-off exceeds 10 ppm, then the collected water has to be sent to Benzene / MTBE
Contaminated waste water collection Tank (T-85004) by means of FFB Water Pump (P-85002A/B) for
further Treatment.
Page 43 of 75
Liwa Plastics Project
Page 44 of 75
Liwa Plastics Project
The Benzene / MTBE Contaminated Waste Water Collection Tank (T-85004) is used to collect all the
waste water streams before treatment in the Waste Water Steam Stripper (C-85001). Since the waste
water contains benzene and/or MTBE, the tank is provided with a nitrogen blanket and connected to the
Vent Gas Incinerator Package (ME-86001). The tank is equipped with a tangential inlet and oil skimming
facilities to remove the separated free oil. From the tank, waste water is pumped by means of the Benzene
/ MTBE Contaminated Waste Water Pump (P-85007 A/B) at a controlled flow to the Waste Water Steam
Stripper (C-85001). If necessary, the pH is adjusted by means of caustic or sulfuric acid dosing upstream
the steam stripper.
Benzene / MTBE contaminated waste water is preheated against the stripper effluent stream in Steam
Stripper Feed/Effluent Heat Exchanger (E-85001 A/B) and fed to the top of the Waste Water Steam
Stripper. At the bottom of this column, LP steam is supplied which strips the hydrocarbons out of the
influent. Vapors at the top of the column are condensed and collected in the Steam Stripper Overhead
Reflux Drum (V-85002). In this vessel, the condensed liquid will separate in a water layer and a thin oil
layer, which flows over the installed weir into the hydrocarbons compartment. The water in the vessel is
pumped by means of the Steam Stripper Reflux Pump (P-85008 A/B) on level control as reflux to the
column. The recovered hydrocarbons are routed to the Skimmed Oil Vessel (V-85001). Vapors are vented
to the wet flare system.
Nitrogen will be used in order to maintain sufficient pressure in the overhead system of the column to allow
venting to the flare. Some nitrogen is required in case insufficient hydrocarbons (non-condensable) are
present in the waste water feed stream. It is fed upstream of the Steam Stripper Overhead Condenser (E-
85003) to ensure proper condenser operation. In the event of a pressure loss in the system due to low
concentrations of hydrocarbons in the feed, the PC will open the valve in the nitrogen line to bring the
pressure up to the desired set point. When there is an overpressure due to an increase in the quantity of
non-condensable in the feed, the PC opens the valve on the vapor outlet to the wet flare. The pressure in
the overhead reflux drum is set at about 1 barg in order to ensure proper disposal of vents to the flare.
The steam stripped effluent collected from the bottom of the column is pumped by means of the Stripped
Waste Water Pump (P-85009 A/B) to the Waste Water Collection Tank (T-85001) after heat recovery in
Feed/Effluent Heat Exchanger (E-85001 A/B) and cooling down in Stripped WW Trim Cooler (E-85002) to
below 40 °C using cooling water.
In case of high benzene and/or MTBE contamination of the steam stripped effluent, it is manually routed
back to the Benzene / MTBE Contaminated WW Collection Tank (T-85004). This is also done in case of
low-low temperature in the column. In the latter case, sufficient stripping of benzene/MTBE cannot be
ensured.
If the stripped effluent is on-spec according to benzene/MTBE contamination level but off-spec due to high
TOC, the stripped waste water shall be sent to Waste Water Collection Tank (T-85001) and to be treated
by Dissolved Gas Floatation Unit (ME-85005); otherwise Stripped WW shall be sent to WW Equalization
Tank T-85002.
Waste Water Primary Treatment
The waste water primary treatment will treat oil contaminated waste by means of Dissolved Gas Flotation
(DGF) unit. The following waste water streams are pre-treated:
Oil Contaminated Cooling Water
Crystallizer Distillate Effluent from Spent Caustic Oxidation Unit
Wash water from NGL Amine/Water Wash Column
Hydrocarbon drains from Flare Hydrocarbon Drain Drum
Wash water from Caustic / Water Wash Tower
Surface water run-off from Polymer Plant
Page 45 of 75
Liwa Plastics Project
The waste water primary treatment consists of the following operation units:
Waste Water Collection Tank (T-85001)
DGF Package (ME-85005)
Skimmed Oil Vessel (V-85001)
The Waste Water Collection Tank (T-85001) is used to store the process waste water awaiting the DGF
treatment. The tank is equipped with tangential inlet and skimming facilities to remove any separated free
oil. From the tank, the waste water is pumped by the Waste Water Transfer Pump (P-85004 A/B) under
flow control to Dissolved Gas Floatation (DGF) package (ME-85005). Waste water pH is adjusted by
means of caustic or sulfuric acid dosing upstream DGF unit.
The DGF package should be sized such that to provide sufficient operating flexibility to allow effluent
quality to be maintained in acceptable range by considering the expected variations in the influent
characteristics. The operator should be able to adjust the following major operating variables:
pH
coagulant and flocculant type and dose
nitrogen pressure
recycle rate
Waste water enters on one end and passes sequentially through coagulation, flocculation and floatation
compartments of the DGF unit (ME-85005). Cationic polymer solution is dosed into the influent upstream of
the DGF unit to enhance the removal of free/emulsified oil and suspended solids. The system forces
nitrogen gas into effluent by means of hydraulic eductors. The nitrogen bubbles will adhere to the oil
particles and form flocs and help these particles to float to the water surface of each flotation compartment.
The floating scum layer is removed by means of a surface skimmer mechanism and sent to the Skimmed
Oil Vessel (V-85001). The treated waste water will overflow via the effluent weir into the DGF clear well
compartment and is pumped by means of the DGF Clear well Pump to the Waste Water Equalization Tank
(T-85002).
The Skimmed Oil Vessel (V-85001) collects the following streams:
Skimmed oil from LLOD basins
Skimmed oil from the Waste Water Collection Tank (T-85001)
Skimmed oil from Oily Sludge Storage Tank (T-85005)
Skimmed oil from the Benzene/MTBE Contaminated Waste Water Collection Tank (T-85004)
Skimmed oil from the Steam Stripper Overhead Reflux Drum (V-85002)
DGF skimming (ME-85005)
Skimmed oil from Spent Caustic Oxidation unit storage tanks (T-63001/T-63002)
Inside the vessel, a special plate pack is installed to separate the oil and water efficiently. The separated oil
is collected via a weir in the oil compartment of the vessel. The collected skimmed oil will be sent to Liquid-
Solid Incinerator Package (ME-86002) by Skimmed Oil pump P-85010. Skimmed oil effluent will be
transferred to WW Collection Tank (T-85001) by Skimmed oil Effluent Pump P-85011.
Waste Water Secondary Treatment
The waste water secondary (biological) treatment consists of:
WW Equalization Tank (T-85002)
Biotreater (ME-85006)
Sludge Treatment and Dewatering (ME-85007)
Page 46 of 75
Liwa Plastics Project
The Waste Water Equalization Tank (T-85002) receives the waste water streams to be treated in the
Biological Treatment Package (ME-85006). The following streams are routed to the Waste Water
Equalization Tank:
DGF effluent from the waste water primary treatment
TLE Hydrojetting / decoking quench water effluent
Stripped effluent from Waste Water Steam Stripper
The Waste Water Equalization Tank has a buffering and homogenization function for the feed stream to
the Biotreater, thus minimizing fluctuations in flow rate and composition.
In the Biotreater, BOD and COD is reduced by activated sludge using dissolved oxygen. Biotreater will
receive feed streams from Contact Tank where the equalized WW will be mixed with the recycled activated
sludge and nutrients (urea and H3PO4).
After pH adjustment, the mixed stream is routed to the Aeration Tank where the required amount of air is
supplied by Air Compressor Package. Control of the required amount of air is done by means of a
dissolved oxygen measurement. Aerated stream will be routed to Clarifier on gravity flow via Degassing
Tank. In the Clarifier, the settled activated sludge is separated from the clean water. Part of the activated
sludge is recycled to the Contact Tank and the excess activated sludge is sent to the Sludge Digester
followed by Sludge Thickener. The clarified water is routed to the tertiary treatment to meet the outfall
water specification.
Thickened excess bio-sludge from Sludge Thickener is sent to Sludge Dewatering Package (ME-85007)
where polymer solution is added for conditioning of the sludge. Dewatered bio-sludge is collected in a
mobile bio-sludge cake container, which is trucked out for disposal by incineration. The decanted water
from Sludge Dewatering Package is recycled to the Waste Water Secondary Treatment Package (ME-
85006).
Oily sludge will be kept separate from bio-sludge. The oily sludge from LLOD basins, Waste water
Collection Tank (T-85001), WW Dissolved Gas Floatation (DGF) package (ME-85005), Skimming from IAF
Package ME-85009 and Sludge from Polymer Plant will be sent to Oily Sludge Storage Tank (T-85005)
from where it will be pumped to Sludge Dewatering Package (ME-85007) by Oily Sludge Pump P-
85013A/B. The dewatered oily sludge is collected in a mobile oily sludge container for incineration. The
reject stream from Sludge Dewatering Package (ME-85007) will be sent to Waste Water Secondary
Treatment Package (ME-85006) for further processing.
Waste Water Tertiary Treatment
The waste water tertiary treatment consists of:
Disinfection Unit
Continuous Sand Filter
Activated Carbon Filter
Treated Effluent Tank (T-85003)
In order to meet discharge water specification, Sodium Hypochlorite solution is used for chlorination of
clarified water in Chlorination compartment of Chlorination/Dechlorination Basin followed by Sodium
Metabisulfite solution injection for Dechlorination in Dechlorination compartment.
For removal of remaining suspended solids, the dechlorinated water is routed to the Continuous Sand
Filter. The unit consists of two continuously regenerated sand filters, each designed for 70 % of total
capacity. The continuous backwash stream from the sand filters is recycled to WW Collection Tank (T-
85001). In case of High TOC in Chlorination Tank, the chlorination tank has to be drained into the Waste
Water Collection Tank (T-85001) via Backwash Effluent Basin.
Page 47 of 75
Liwa Plastics Project
The clean effluent from sand filters will flow on gravity into the Filtrate Basin, where the treated effluent
quality is continuously monitored by means of a flow, turbidity, temperature, TOD and pH measurement.
It is expected that sand filter clear water can meet the outfall water quality. However, in case of
hydrocarbon contamination, the effluent can be sent to Activated Carbon Filters for final polishing. The
treated waste water will be sent to the Treated Effluent Tank (T-85003), from where the treated WW is
transferred to MISC (OSBL) by means of Treated Effluent Pump (P-85006A/B).
Chemical Storage, Preparation and Dosing
Nutrient (Urea and Phosphoric Acid) Preparation and Dosing Package (ME-85012)
Urea and phosphoric acid are used as nitrogen and phosphorous supplement for Aeration Tanks and
aerobic Sludge Digester.
Granular urea is dissolved in water with a concentration of about 10 wt% and stored in Urea Solution Tank.
Diluted urea is sent to the users by Urea Solution Dosing Pump.
Page 48 of 75
Liwa Plastics Project
This package is an incinerator specially designed for high hydrocarbon conversion efficiency.
Flame Arrestors ME-86001-A01A/B and ME-86001-A02A/B (part of ME-86001) are required to prevent fire
in case of back flow from the incinerators into the vent gas line.
In case the Vent Gas Incinerator ME-86001-F-01 is not available and during the start-up of the blowers, the
vent gases are routed to the atmosphere at safe location via Vent Gas Stack (ME-86001-SK-01).
The flue gas is routed via a stack to the atmosphere. The incinerator is fired by means of fuel gas with
Natural Gas as back-up.
Page 49 of 75
Liwa Plastics Project
The Wet and Cold Flare headers will be combined before to route to main wet flare header/stack. In order
to combine the Wet Flare and Cold Flare into one flare header/stack, the cold flare vapors from the Cold
Flare KO drum (V-83012) is heated to a temperature well above the minimum allowable metal temperature
Page 50 of 75
Liwa Plastics Project
for Low Temperature Carbon Steel, i.e. above -48°C by means of jacketed pipe. After the temperature has
been raised the combine wet and cold relief’s header is routed to Wet Flare K.O. Drum V-89001.
Any liquid accumulated in the V-89001 is routed by the Flare Knock Out Drum Pump P-89001A/B to the
Quench Water Drain Drum V-10003. Only during shutdown of the SCU; the pumped liquid is routed to the
Waste Water Collection Tank T-85001. The pump is automatically started at high level and stopped at low
level. Both pumps are connected to the emergency power grid. The pump capacities are set to drain the
determining load of liquid hydrocarbons and water in two (2) hours.
The vapors flow through the Wet Flare Seal Drum (ME-89001-V-02) to the Wet Flare Stack (ME-89001-
SK-01). Service Water is supplied to Wet Flare Seal Drum to maintain the water seal level. In addition
Service Water flows continuously through an orifice (parallel to the level controller) into the seal drum to
ensure adequate water seal level. The continuous overflow is sent to the Oily Water Sewer (OWS). The
function of the seal drum is to prevent ingress of air into flare header. Ingress of air is not allowed into the
flare header as it can result in an explosive mixture in the header.
The inlet to the flare stack and the flare sub-headers are purged with fuel gas to ensure a positive flow from
the flare system to the flare stack. Nitrogen is used as back-up for fuel gas purge.
Vapors from Wet Flare K.O. Drum V-89001 are routed to the Flare Package ME-89001 which mainly
consists of: Wet Flare Seal Drum (ME-89001-V-02), Flare Stack (ME-89001-SK-01), Flare Tip, Flare Fuel
Gas KO Drum (ME-89001-V-01), Flare Ignition System, Molecular Seal and required instrumentation for
control and safe guarding. For details reference is made to Main Wet Flare Package (ME-89001) package
specification.
The stack is equipped with a molecular dry seal as additional protection against air ingress. The relief
gases are ignited by the pilot flames and released to atmosphere. A flame generator is installed to ignite
the pilots. The flare tip pilot temperature switches-on automatically the ignition in case of loss of flame.
Remote ignition from control room is possible in case the automatic re-ignition does not work.
Fuel gas is used as pilot gas and purge gas. Natural gas is used as back-up for fuel gas.
MP steam is routed to the Flare Tip to ensure smokeless flaring at low relief loads and to protect flare
system against flame back. The MP steam flow is controlled by a control valve proportional to the relieved
gas flow rate. To optimize the steam consumption infrared sensors are installed to sense flare
characteristic of the flame and adjust the steam flow rate automatically.
The main equipment connected directly to wet flare header are:
Refinery Dry Gas Treating Unit
o RDG Compressor 1st Stage Suction Drum (V-12001)
o RDG Oxygen Converter (R-12001 A/B)
o RDG Amine / Water Wash Column (C-12001)
o RDG Depropylenizer (C-12005)
NGL Treating and Fractionation Unit
o NGL Amine / Water Wash Column (C-11002)
o C3+ Stripping Hold Up Drum (V-11007)
Steam Cracker Unit
o C3+ Feed Vaporizer (E-20018 A/B)
o Quench Tower (C-21003)
st
o Charge Gas Compressor 1 Stage Suction Drum(V-22001)
rd
o Charge Gas Compressor 3 Stage Suction Drum(V-22004)
o Hydrogen Compressor (K-23001)
Page 51 of 75
Liwa Plastics Project
Page 52 of 75
Liwa Plastics Project
Hydrocarbon Drain Pump P-89002. Only during shutdown of the SCU; the pumped liquid is routed to the
Waste Water Collection Tank.
The main equipment connected to wet flare header via cold/dry relief header are:
Refinery Dry Gas Treating Unit
o RDG Demethanizer Reflux Drum (V-12007)
o RDG Deethanizer Reflux Drum (V-12008)
o RDG Depropylenizer Reflux Drum (V-12010)
o NGL Treating and Fractionation Unit
o NGL Deethanizer Reflux Drum (V-11002)
Steam Cracker Unit
o HP Depropanizer Reflux Drum (V-22012)
o LP Depropanizer Reflux Drum (V-22015)
o Demethanizer (C-23001)
o Deethanizer Reflux Drum (V-23004)
o Hydrogen Off gas (ME-23000-E06)
o Methane Off gas (ME-23000-E06)
o Recycle Ethane (ME-23000-E06)
o Ethylene Product (ME-23000-E06)
o Ethylene Fractionator Reflux Drum (V-24002)
o Propylene Fractionator No. 1 and 2 Reflux Drum (V-24003)
o Debutanizer Reflux Drum (V-24004)
st
o Propylene Refrigeration System 1 Stage Suction Drum (V-25001)
nd
o Propylene Refrigeration System 2 Stage Suction Drum (V-25002)
rd
o Propylene Refrigeration System 3 Stage Suction Drum (V-25003)
th
o Propylene Refrigeration System 4 Stage Suction Drum (V-25004)
st
o Binary Refrigeration System1 Stage Suction Drum (V-26001)
o Binary Refrigeration System 2nd Stage Suction Drum (V-26002)
rd
o Binary Refrigeration System 3 Stage Suction Drum (V-26003)
Pressurized storage sphere for NGL C2+.
Pressurized storage spheres for Ethylene and Propylene.
High pressure equipment and piping of Cryogenic Ethylene and Propylene Storage
Page 53 of 75
Liwa Plastics Project
The vapors flow through the Wet Flare Water Seal Drum (ME-89003-V-01) to the Wet Flare Stack ME-
89003-SK-01. Service Water is supplied to Wet Flare Water Seal Drum (ME-89003-V-01) to maintain the
water seal level. In addition Service Water flows continuously through an orifice (parallel to the level
controller) into the seal drum to ensure adequate water seal level. The continuous overflow is sent to the
Oily Water Sewer (OWS). The function of the seal drum is to prevent ingress of air into flare header.
Ingress of air is not allowed into the flare header as it can result in an explosive mixture in the header.
The inlet to the flare stack and the flare sub-headers are purged with fuel gas to ensure a positive flow from
the flare system to the flare stack. Nitrogen is used as back-up for fuel gas purge.
Vapors from Spare Storage Wet Flare K.O. Drum V-89004 are routed to the Flare Package ME-89003
which consists of: Wet Flare Water Seal Drum (ME-89003-V-01), Flare Stack (ME-89003-SK-01), Flare
Tip, Molecular Seal and required instrumentation for control and safe guarding. Ignition system and fuel
gas ko drum will be common with the main wet flare system. For details reference is made to Main Wet
Flare Package (ME-89003) package specification.
The stack is equipped with a molecular dry seal as additional protection against air ingress. The relief
gases are ignited by the pilot flames and released to atmosphere. A flare generator is installed to ignite the
pilots. Fuel gas is used as pilot gas and purge gas. Natural gas is used as back-up for fuel gas. The flare
tip pilot temperature switches-on automatically the ignition in case of loss of flame. Remote ignition from
control room is possible in case the automatic re-ignition does not work.
MP steam is routed to the Flare Tip to ensure smokeless flaring at low relief loads and to protect flare
system against flame back. The MP steam flow is controlled by a control valve proportional to the relieved
gas flow rate. To optimize the steam consumption infrared sensors are installed to sense flare
characteristic of the flame and adjust the steam flow rate automatically.
The main equipment connected to this header is:
Pressurized storage for Mixed C4, Butene-1, Butene-2, Hydrogenated C4, Pressurized storage spheres
for NGL C2+, Ethylene and Propylene including high pressure equipment and piping in Cryogenic
Ethylene and Propylene Storage area.
Page 54 of 75
Liwa Plastics Project
MP steam is routed to the Flare Tip to ensure smokeless flaring at low relief loads and to protect flare
system against flame back. The MP steam flow is controlled by a control valve proportional to the relieved
gas flow rate. To optimize the steam consumption infrared sensors are installed to sense flare
characteristic of the flame and adjust the steam flow rate automatically.
The main equipment connected directly to wet flare header are:
Amine Regenerator Reflux Drum (V-11052)
Amine Regenerator (C-11051)
RDG Mixed Feed from DCU & RFCC (B/L Interconnecting)
Amine Carbon Filter (V-11051)
Amine Regenerator Reboiler A/B (E-11051A/B)
RDG Amine / Water Wash Column (C-12001)
RDG Compressor First Stage Suction Drum (V-12001)
RDG Compressor Second Stage Suction Drum (V-12002)
RDG Compressor Second Stage (K-12001-2)
RDG Compressor Second Stage Discharge Drum (V-12003)
RDG Amine Oil Degassing Drum (V-12016)
One Sour Water Collection Drum V-89003 is available to drain the liquid from the Acid Gas Flare System.
The contents are routed to the Quench Water Drain Drum (V-10003) by the Sour Water Drain Drum Pump
P-89004.
Sour Water Drain Drum V-89003 is continuously purged with fuel gas and floating on acid gas flare header
pressure.
Page 55 of 75
Liwa Plastics Project
Page 56 of 75
Liwa Plastics Project
K-85001A/B 12 (H)
Pressure 850-PC-015 mbar-g 8 8 8 NA
suction line 4(L)
K-85001AB
Pressure Discharge 850-PI-016 mbar-g 116 116 116 128(H) NA
Line
K-85001A/B
Flow Discharge 850-FC-006 kg/h 2856 2635 1580 (L) NA
Line
o
Temperature T-85002 850-TI-001 C 20 20 20 25 (H) NA
P-85005A/B
o
Temperature Discharge 850-TI-002 C 20 20 20 25 (H) NA
Line
18900(H)
Level T-85002 850-LC-010 mm 9850 9850 9850 NA
800(L)
19100 (HH)
Level T-85002 850-LI-011 mm 9200 9200 9200 600 (LL)
600 (LL)
175.45 (H)
Flow P-85005A/B 850-FC-008 m3/h 159.5 145 87 NA
52.6 (L)
8000(H)
Level T-85005 850-LI-012A mm 4400 4400 4400 NA
800(L)
Level T-85005 850-LI-013 mm 4400 4400 4400 600(LL) 600(LL)
12(H)
Pressure T-85005 850-PC-023 mbar-g 8 8 8 NA
4(L)
6000(H)
Level T-85003 850-LC-014A mm 3400 3400 3400 NA
800(L)
Level T-85003 850-LI-015 mm 3400 3400 3400 600(LL) 600(LL)
P-85006A/B
pH Discharge 850-AI-004 - NA 6.5 - 8.5 NA 8.5 (H) NA
Line
Page 57 of 75
Liwa Plastics Project
Pressure C-85001 850-PI-065 bar-g 1.8 1.8 1.8 2.2 (HH) 2.2 (HH)
Page 58 of 75
Liwa Plastics Project
WWT inlet
Sampling position: FFB and OCB
Page 59 of 75
Liwa Plastics Project
Equalized Water
Sampling position: WW Equalization Tank (T-85002) outlet
DGF outlet
Sampling position: Dissolved Gas Floatation outlet
IAF outlet
Sampling position: Induced Air Floatation outlet
Page 60 of 75
Liwa Plastics Project
Mixed Liquid
Sampling position: Bioreactor
Treated Water
Sampling position: Treated Effluent Tank (T-85003)
Waste Incineration
To be provided by package vendor.
Flare Unit
To be provided by package vendor.
Page 61 of 75
Liwa Plastics Project
Page 62 of 75
Liwa Plastics Project
Page 63 of 75
Liwa Plastics Project
The operator has to check the alarms when indicated on the DCS. Refer the instructions as provided by
Package Vendor.
Page 64 of 75
Liwa Plastics Project
8.1 LLOD
In general, there is no action required for short term shutdown. However in case of maintenance or
inspection requirement, the Last Line Of Defense basins have to be isolated from incoming sewer system
by utilizing blind flanges. The counter flanges are located inside the inlet compartment of LLOD basins and
equipped with blind flanges with lifting lugs for proper isolation of LLOD basins from sewer network. The
inspection and maintenance has to be scheduled for dry seasons.
8.2 Other Equipment (out of package vendor scope of design and supply)
Some general normal shutdown procedures are described below:
Drums
For drum, the isolation philosophy is the same as that of column mentioned above. However, in case
that there are blinds on the downstream or upstream equipment nozzles connected to a nozzle via
piping, no blind is required on such a nozzle.
Page 65 of 75
Liwa Plastics Project
Page 66 of 75
Liwa Plastics Project
9.1 General
An Emergency Shutdown (ESD) is not applicable for WWTU. However unplanned shutdown of WWTU
may be required due to fire, mechanical failure, partial or complete failure of one of the utilities.
The nature of the unplanned shutdown can be such that unit operation can be maintained at a reduced rate
or it may necessitate a complete shutdown.
In the following section, information is provided on how to operate in certain emergency cases. Following
cases are covered:
Fire
Power Failure
Instrument Air Failure
Steam failure
Cooling Water Failure
Release of Toxic Gases
Although the procedures cover most types of cases, keep in mind that in some cases the actual procedure
will be dictated by the circumstances. In general, in case of any emergency, action must be taken to make
the unit safe as quickly as possible.
9.2 Fire
Consequence
If a fire occurs in the plant, that section of equipment in which the fire has occurred must be isolated to
confine fire and depressurized to eliminate the source of combustible material. Unless the fire is small and
can be handled quickly the plant will be shutdown. Operation supervisor on duty will advise on shutdown,
based on plant procedures in place.
Actions
Follow operation supervisor’s orders on shutdown and firefighting procedures.
Block in influent and effluent streams.
Isolate section or area where fire is occurring, to remove combustion source.
Depressurize section to flare.
Shutdown remaining portions of plant as time and circumstances permit or require.
Page 68 of 75
Liwa Plastics Project
Actions
Follow operation supervisor’s orders on shutdown.
Block in influent streams.
Isolate section or area where fire is occurring, to remove combustion source.
Depressurize system to flare or safe location
Page 69 of 75
Liwa Plastics Project
10.1 General
It is the responsibility of all personnel to make themselves familiar with the hazardous nature of the
materials handled by the unit, the safety precautions and regulations of the unit and the safety equipment
available within the unit.
The following general safety precautions should be followed at all times:
Unit fire protection equipment shall be available and in working order at all times and at the right
place (e.g. fire hoses). It is the responsibility of the unit supervisor to see that this equipment is
regularly inspected and serviced.
Operators finding extinguishers that have been emptied, damaged or otherwise misused should
report them immediately to the plant Fire Department for replacement.
Eye wash facilities and safety showers should be inspected regularly and maintained to be
functional.
Self-contained breathing apparatus should be readily available and properly stored on the unit. It
is operator's responsibility to be familiar with the operation and use of this equipment. Again the
unit supervisor should see that the equipment is regularly inspected and serviced by the proper
department.
All guards and shields shall be fitted to moving machinery and to equipment that can spray a
hazardous chemical on personnel.
Hard hats, safety shoes and clothing shall be worn at all times. Shoes and clothing shall
be kept clean and free of oils or chemicals, and in a good state of repair.
Operators will wear chemical type gloves and aprons, face shields and/or chemical safety
goggles when handling chemicals in powder or solution form.
Personnel, who is sprayed or splashed by a chemical, will follow the procedure required
for that chemical.
Operations Department will ensure that all lines/equipment have been rendered safe and
thoroughly cleaned before permitting maintenance to work on equipment.
Page 70 of 75
Liwa Plastics Project
Suitable fire extinguisher must be readily available. The area around an extinguisher or hydrant must be
clear so that equipment is readily accessible in case of emergency
10.4.1 General
For personnel protection it is necessary to be aware of the hazardous nature of the materials handled in
the unit. Combustible hydrocarbons and streams containing hazardous substances are found throughout
the unit. It is highly recommended to follow package vendor instructions in the regard.
10.4.2 Hydrocarbons
Light hydrocarbons in Fuel Gas Mixed Drum can be released to air (partly) and the vapor/air mixture can
be ignited by a spark (including from static electricity) or flames.
10.4.3 Nitrogen
Nitrogen is an inert gas used for purging equipment or maintaining a positive pressure inert gas blanket on
a vessel.
Nitrogen is neither poisonous nor flammable, but it is an asphyxiant. Consequently care must be exercised
when working inside equipment that has been N2 purged. Adequate ventilation must be provided and
appropriate breathing devices worn. To breathe an atmosphere high in N2 could result in suffocation.
Before entering vessels that have been purged with N2, a check must be made for proper oxygen content
prior to entry. Rapid vaporization of liquid nitrogen can cause severe burns on contact with the skin.
10.4.4 Ammonia
Ammonia is a colorless gas with an extremely pungent odor. Exposure to ammonia may cause varying
degrees of irritation to the eyes, skin, or mucous membranes.
Ammonia exposure for short term and under 100 wt ppm causes nose and throat irritation. Over 500 wt
ppm exposure for approximately 30 minutes causes upper respiratory irritation, tearing, increased pulse
rate and blood pressure. High level exposures can cause long term respiratory problems and/or death.
Sometimes symptoms do not appear for several hours after the exposure has occurred.
Where ammonia concentrations exist in concentrations above standard, respiratory, eye, and skin
protection should be provided. Full face gas masks with ammonia canister or supplied air respirators, both
Page 71 of 75
Liwa Plastics Project
with full face pieces, afford good protection. In areas where exposure to liquid ammonia exists, goggles or
face shields, as well as protective clothing impervious to ammonia and including gloves, aprons, and boots
should be required.
In heavy concentrations of ammonia gas, workers should be outfitted with complete self-contained
protective suits impervious to ammonia, with supplied air source, and full headpiece and face piece.
10.5.1 General
It is recommended that lines which are used incidentally (e.g. for start-up) are spaded-off after use, flushed
(if necessary) and drained.
For opening lines or equipment for repair or inspection, some suggestions are given below (it is not
intended that they should supersede local plant practice and regulations, they should supplement them).
Maintenance crews should be cautioned when working on equipment or lines containing flammable
material.
Release of hydrocarbon vapor to the air in large amounts should be avoided due to the health and fire
hazards. When it is necessary to release gas to the atmosphere, especially at ground level, it should be
done under a blanket of steam; this will assist on dispersing the gas and displace air from the vicinity of the
release.
Equipment or lines should be steamed out or flushed, before starting repair work. Equipment containing
residue has to be flushed first with hot flushing oil prior to be flushed with cold flushing oil. A direct flush
with cold flushing oil could result in a cooling of residue without proper dilution and the resulting high
viscosity may prevent emptying of the equipment. Residue containing lines do not need a hot flush step
since the residue can easily be replaced by cold flushing oil.
Turning of spectacle blinds shall be performed in strict adherence to the refinery standards and
procedures.
Use of spark proof tools or tools dipped in oil is recommended.
All steam hoses should be provided with an approved ground connection to avoid the possibility of the
steam jet generating static electricity.
Anyone entering a vessel, which may contain an inert or contaminated atmosphere, must follow safety
precautions and rules which apply. The vessels may contain H2S or other toxic material in addition to
hydrocarbons.
Therefore, the following precautions should be included in the standard procedure.
The vessels should be isolated by positive action, such as blinding, to exclude all sources of hydrocarbon,
fuel gas, steam, air, etc.
The refinery safety officer and supervisory personnel will give their permission for vessel entry after they
have made the appropriate tests.
Install an air mover outside the vessel to sweep away any vapors. The man entering the vessel must be
equipped with a fresh air mask in proper working condition. If the condition of vessel is not enough to enter,
use a compressed air self-contained breathing apparatus.
There should be available and ready for immediate use and transfer to the man in the vessel, a separate
air supply which is independent of electrical power.
Page 72 of 75
Liwa Plastics Project
The man entering the vessel should wear a safety harness with properly attached safety line.
If the work involves a large distance above the floor of the vessel, scaffolding or support flooring must be
built to prevent dangerous falls.
There should be a spare fresh air mask complete with its own separate air supply, to allow a second man
to enter the equipment quickly in case of an emergency. This spare equipment must be compact enough to
allow the second man to enter through the manway while entering the equipment.
The API publication “Guide for Inspection of Refinery Equipment” or the NIOSH publication No. 87-113; “A
Guide to Safety in Confined Spaces” can be referred to for additional information on safety procedures for
vessel entry and accident prevention measures.
All lines leading to and from the equipment are to be blinded off as soon as the process vapors
have been eliminated.
The vessels must be ventilated preferably by mechanical means during the whole time
maintenance or inspection crews are inside the vessel.
After maintenance is complete, and before the vessel is returned to service, air must be displaced
with steam or purged with inert gas.
It is recommended that any man working in a vessel, which has an inert or contaminated atmosphere, not
be permitted to move too far away or into any tight areas, such as through a crude column tray manway.
The reason for this precaution is that should the man develop some difficulty while below a tray, for
example, to a point where he could not function properly or lost consciousness, it would be extremely
difficult for the surveillance team outside the vessel to pull the man up through the small tray manway by
use of the safety line.
Any one working in the bottom of the column or vessel should be aware of the hazard of falling objects.
Hard hats should be worn, but these will not provide total protection against heavy objects. The workmen
should be warned to pay attention, to look, and listen. The maintenance supervisor should be careful when
scheduling work, to avoid having people in the bottom of the vessel when there is heavy work going on in
the top of the column or vessels.
A communication system should be provided for the manway watch so that they can quickly call for help in
the event that the personnel inside the vessel encounter difficulty. A radio, telephone, or public address
system is necessary for that purpose.
Before entering a vessel, the refinery’s safety precautions should be observed. These usually include the
following: sampling the vessel for toxic vapors and oxygen concentration, wearing a safety harness, and
having an attendant outside the vessel.
An unattended vessel should never be entered.
Page 73 of 75
Liwa Plastics Project
An explosion meter, to monitor amounts of flammable or explosive gas/air mixtures resulting from
leaks or other releases.
An oxygen analyzer, used mainly to monitor oxygen levels when purging equipment.
A type of chemical gas detector for detecting and identifying chemical gasses. One of the most
commonly used detectors of this type works on a color change of crystals sensitive to the gas to
be analyzed.
Key 1 obtained from the control room is inserted in the locking device of Block valve C.
This block valve is unlocked now.
Block valve C is opened and key 1 is trapped now.
Key 2 is removed and block valve C is locked open now.
Key 2 is inserted in the locking device of block valve B. Block valve B is unlocked now.
Block valve B is closed and key 2 is trapped now.
Key 5 is removed and block valve B is locked closed now.
Page 74 of 75
Liwa Plastics Project
Key 5 is inserted in the locking device of block valve A. Block valve A is unlocked now.
Block valve A is closed and key 5 is now trapped, key 4 is released.
Key 4 is taken to the control room.
Safety valve A can be removed for maintenance.
FLARE
OR BACK TO SYSTEM
OR TO CLOSED
SYSTEM
LO LO
VALVE A VALVE D
Size: ..... Size: .....
Set at: ..... Barg Set at: ..... Barg
PSV PSV
....A ....B
3/4"D 3/4"D
LO(LC) LC (LO)
VALVE B VALVE C
PROCESS LINE
Page 75 of 75
Petrochemical Plant Sohar Environmental Impact Assessment Report
Orpic and CB&I HMR #3817
Attachment 16: Process description and BAT for Spent Caustic Selection Process
CB&I ORPIC
Page 1 of 7
"THIS DOCUMENT IS THE PROPERTY OF CHICAGO BRIDGE & IRON COMPANY (CB&I). IT MAY CONTAIN INFORMATION
DESCRIBING TECHNOLOGY OWNED BY CB&I AND DEEMED TO BE COMMERCIALLY SENSITIVE. IT IS TO BE USED ONLY IN
CONNECTION WITH WORK PERFORMED BY CB&I. REPRODUCTION IN WHOLE OR IN PART FOR ANY PURPOSE OTHER THAN
WORK PERFORMED BY CB&I IS FORBIDDEN EXCEPT BY EXPRESS WRITTEN PERMISSION OF CB&I. IT IS TO BE SAFEGUARDED
AGAINST BOTH DELIBERATE AND INADVERTENT DISCLOSURE TO ANY THIRD PARTY."
Liwa Plastics Project
Page 2 of 7
Liwa Plastics Project
Table of Contents
Contents Page
1.0 INTRODUCTION..................................................................................................................................4
2.0 DEFINITIONS ......................................................................................................................................4
3.0 SPENT CAUSTIC OXIDATION UNIT ...................................................................................................4
3.1 Spent Caustic Storage .............................................................................................................5
3.2 Spent Caustic Oxidation Package ...........................................................................................6
3.3 Crystallizer Package ................................................................................................................7
Page 3 of 7
Liwa Plastics Project
1.0 INTRODUCTION
Oman Oil Refineries and Petroleum Industries Company (ORPIC) is planning the installation of a new
Petrochemical Complex to be called Liwa Plastics Project (LPP) adjacent to Sohar Refinery Improvement
Project (SRIP) that will include a Steam Cracker Unit (SCU) designed to produce 863 kilo tons per annum
(KTA) of polymer grade ethylene and 300 KTA of polymer grade propylene, Refinery Dry Gas Unit, NGL
Treating and Fractionation Unit, Selective C4 Hydrogenation Unit, MTBE Unit, Butene-1 Recovery Unit,
Pygas Hydrotreating Unit, High Density Polyethylene (HDPE) Plant, Linear Low Density Polyethylene Plant
(LLDPE), new Polypropylene Plant (PP), and associated utility and offsite facilities. The new petrochemical
plant will be integrated with the Sohar Refinery, Sohar Aromatics Plant (AP) and Sohar Polypropylene
Plant (PP) plant.
ORPIC is also planning the installation of a new NGL Extraction plant located in Fahud, Central Oman. The
NGL (C2+) extracted from the natural gas will be transported to the petrochemical complex by pipeline and
used as feedstock to LPP. The new NGL Extraction plant will have independent utility and offsite facilities.
Additional feedstock to LPP are mixed LPG (produced in the Sohar Refinery and Sohar AP), refinery dry
gas produced in the RFCC unit and new Delayed Coking unit (included in SRIP), light naphtha condensate
from OLNG by marine tanker.
This document covers the process description for the Spent Caustic Oxidation Unit 6300 of the new Liwa
Plastics Project in Oman.
2.0 DEFINITIONS
The following terms and abbreviations have been used in this document:
Term Definition
ASL Atmospheric Safe Location
LPP Liwa Plastic Project
ORPIC Oman Refineries and Petroleum Industries Company
OSC Oxidized Spent Caustic
PFD Process Flow Diagram
RDG Refinery Dry Gas Treating Unit
SCOP Spent Caustic Oxidation Package
SCU Steam Cracker Unit
UFD Utility Flow Diagram
WWTU Waste Water Treatment Unit
WAO Wet Air Oxidation
Page 4 of 7
Liwa Plastics Project
Page 5 of 7
Liwa Plastics Project
The oxidized Spent Caustic is neutralized with concentrated Sulfuric Acid. The neutralization reactions are
given below:
The Spent Caustic Oxidation Package (ME-63001), abbreviated as SCOP, will be designed to treat the
Spent Caustic stream in a WAO process. The package will be designed for a turndown of 50 % of the
process design flow rate. The oxidized Spent Caustic is neutralized to a pH in the range of 7 to 9 with
concentrated Sulfuric Acid. The net neutralized Spent Caustic is sent to the SCO Effluent Tank T-63002
where after homogenization, it will be sent to the Crystallizer Package (ME-63002) via Spent Caustic
Oxidation Effluent Pump (P-63002A/B).
The unit’s drain system will collect all spent caustic in to the Spent Caustic Area Sump (Z-63001). The
sump is equipped with a submerged pump, Spent Caustic Area Sump Pump (P-63004). The spent caustic
is pumped from the Spent Caustic Area Sump back to the Spent Caustic Feed Storage Tank (T-63001).
The vent gas from storage tanks T-63001/2 and SCOP waste gas are sent to the Vent Gas Incinerator
Unit. This way stripped hydrocarbons from the Spent Caustic feed and any occasional Hydrogen Sulfide
are disposed safely.
All facilities required for neutralization of the oxidized Spent Caustic are included in the Spent Caustic
Oxidation Package and shall be provided by the package vendor.
Operating and design conditions and the WAO process configuration are set by the package vendor based
on the effluent quality requirements. PFDs and the Process Description of the SCOP shall be provided by
vendor as per vendor process configuration.
Page 6 of 7
Liwa Plastics Project
The purpose of installing a Crystallizer Package (ME-63002) is to separate the solids in the fully oxidized
spent Caustic (SCO) effluent by means of an Evaporation System. The Evaporation System consists of a
Steam Driven Forced Circulation Crystallizer System with Centrifuge. The solid crystals are to be sent for
landfill. The distillate stream can be sent to WWTU for further treatment and the purge stream which mainly
contains dissolved non-organic solids needs to be treated by an oxidizing chemical agent and sent as brine
to outfall (Hold 3).
Page 7 of 7
Spent Caustic Treatment and Disposal
Spent caustic needs treatment prior to disposal. The waste stream contains different inorganic and
organic acidic components originated from contact with components such as carbon dioxide,
sulfides, carbonates, benzene and phenolics. Because of their acidity, corrosiveness and toxicity
these components must be removed. Several treatment methods can be used to manage spent
caustic, but their suitability is driven by quantity, composition and disposal limits to be achieved.
The main treatment method selected for the LPP complex is Wet Air Oxidation (WAO), a liquid‐phase
hydrothermal oxidation using dissolved oxygen at elevated temperatures. Oxidation efficiency
increases with temperature, while partial pressure of the oxygen governs the oxidation depth to be
achieved. If needed, a chemical oxidation step can be added in the form of for example hydrogen
peroxide injection to achieve low BOD and COD limits.
Due to its high treatment efficiencies, no‐sludge generation and minimal air pollution, this method is
most widely used. It is one of the European Union and US Environmental Protection Agency’s best
available techniques (BATs).
The alternative for a Wet Air Oxidation treatment would be Spent Caustic Incineration.
This is a gas‐phase oxidation process at much higher temperatures (900‐1000°C), converting
inorganic constituents into molten forms and decomposing organic compounds into most stable
states. It could achieve ultimate oxidation levels. However, the spent caustic stream from the LPP
complex does or hardly provides any calorific value and therefore requires firing of natural gas to
vaporize the spent caustic stream and for sustaining the high‐temperature needs. Eutectic solid
crystals formation in the quench section is crucial. Handling and disposal of this crystalline material is
on an intermittent but frequent basis. Flue gas scrubbing will be required to control NOx and SOx
emission. Still waste water effluent contains high concentrations of dissolved salts (sulphates and
carbonates).
High OPEX (operational cost) due to high maintenance (associated with refractory repairs), high fuel
requirements and high cooling/quenching requirements) make this option environmentally less
attractive compared to the WAO process.
The treated effluent from the WAO process (or from the Incinerator process) can be disposed off
with desalination unit reject (brine) towards the seawater return channel or routed to a
crystallization unit to reduce TDS (mainly material already present in fresh seawater as well) of the
effluent stream. However, this crystalline material will have to be handled as landfill.
1) The FEED package includes a Wet Air Oxidation (WAO) unit for spent caustic treatment with
an additional Spent Caustic Oxidation Effluent Crystallization unit.
a. Final effluent from crystallization unit is free of salts and can be disposed off in normal manner.
b. Solid waste at a rate of 24 t/d salts will have to be disposed.
3) Direct disposal of the WAO effluent (or as applicable Incinerator effluent) with the Desalination
Unit Reject (brine), as already indicated in our earlier correspondence (December 2014), still can be
considered to avoid the installation of a crystallizer unit.
a. Routing 2,150 m3/h of Desalination Unit Reject (brine) with the seawater cooling return (58,000
m3/h) increases the seawater TDS content by 0.29%. Adding WAO effluent (9.7 m3/h) to this mixed
stream adds an additional 0.027% to the TDS by only. This means 12 mg/l out of 43,138 mg/l TDS in
final seawater return is attributable to the WAO effluent.
b. In the seawater return channel, the LPP stream is further diluted with the seawater return from
SRIP. Specifications for the stream from SRIP are not available, but it is assumed that this stream
meets criteria and is comparable with the LPP seawater return. The anticipated contribution of the
WAO effluent on TDS of the combined seawater return stream is even further reduced to 0.016%.
c. Spent Caustic WAO effluent contribution to TDS is mainly in the form of sodium and sulphate
ions. Concentration of these components in seawater outfall is therefore similar of concentrations at
seawater intake.
d. BOD and COD are slightly above natural seawater BOD and COD levels. However, these can
be further reduced chemical injection. Components like benzene have been removed from the effluent
stream already.
From a BREF/BAT point of view, also spent caustic WAO will be the preferred route over spent
caustic Incineration. This also will have to be addressed in the EIA report.
Considering the above, CB&I recommends not to pursue the Incinerator option any further and keep
the configuration as currently provided in the FEED package, i.e. WAO. + crystallization unit. Whether
a crystallization unit will indeed be required will depend on the whether the very small contribution of
the WAO effluent on the total TDS concentration is acceptable or not.
Petrochemical Plant Sohar Environmental Impact Assessment Report
Orpic and CB&I HMR #3817
000
P80010609-6"-T4A1-N (PG PROPYLENE TO T83002A/B FROM TP-S620001)
1 UNIT 1100 UNIT 1300 PLANT
2000.
EXISTING
33
B/L
02A
02B
A1E11STR
NORTH
P)E:
V-1304
500
V- 1101B
V- 1101A
E- 1108A/B
E- 1117A/B
P-61
61M
H-1
E- 1114(L)/E- 1103(U)
P-61
P-61
E- 1118B
E- 1118A
E- 1117C
1950.
E- 1107
E- 1106
DAILY CHEMICAL SHED
E- 1130
E- 1127
B /L
E- 1121A/B
P97010105-12"-T2A1-IC(PG PROPYLENE TO/FROM JETTY TO/FROM T-83004)
E- 1124
92M
V-1303
E- 1129
V- 1301
K-1301A
P-6134A/B/C
C-1121
E- 1105A/B
E- 1104A/B
E- 1102A/B
E- 1101A/B
SI
H ROAD(
NG
R-1301
B /L E:
TP
CONTROL
C-1122
NG
CURB
A-1301
P- 1104A
P- 1106A
P- 1108A
P- 1108B
P- 1104B
P- 1106B
K-1301B
NG METERING
M E- 1101
P- 1111A
P- 1111B
P- 1111C
9000
PARKI
V-1302
LDI
P- 1103A
P- 1102A
P- 1121A
P- 1103B
P- 1102B
P- 1121B
P- 1122A
P- 1124A
P- 1123A
P- 1122B
P- 1124B
P- 1123B
N
P- 1302A
S900
P- 1302B
MAI
ME-1103
6000
A-1302
002
BUI
P97013801-12"-T1A1(PROPANE/LPG VAPOR RETURN FROM K-81004 TO JETTY (BY OGC)
EL 99500
A E-1110 E-1131 E-1125 E-1115 E-1116
92
P97010103-20"-T2A1-IC(PROPANE/LPG FROM JETTY TO V-81008) ME-9101 E-6102
TRUE
P- 1301A
P- 1301B
5000
P97013904-20"-T1A1-IC(PROPANE/LPG FROM P-81009A/B TO JETTY 58.1139734°
P- 1112A
P- 1112B
P- 1251A
P- 1251B
P- 1105A
P- 1110A
PIPE SLEEPER
P- 1105B
P- 1110B
P- 6513A
P- 6512A
P-1303
P- 6513B
P- 6512B
P- 1109A
P- 1109B
P- 1101A
P- 1101B
HOLD
2000
P- 1107A
P- 1107B
M
V-1107 P-1304
V-1305
P- 6514A
A-6501
P- 6514B
S-1251 A-1251 Z-6511
NORTH
7000
90°
500
V-1201 V-1202
PIPE SLEEPER
V-1104
C-1102(U) V-1102 P-6511A
E- 6511
E- 6512
E- 6513
V- 6512
V-1106
TP
1958.
C-1103(L)
TOWER
C-1251 C-1202
61000
E- 1109A/B
C-1101 P-6511B
E- 1126
F-1101
K- 1101A
K- 1101B
V- 6511
S900
B /L E:
A1F001 T-6511 T-1301 T-1302
92
DIKE
M
P97017902-12"-A1A1-N (BUTENE-1 VAPOR RETURN FROM JETTY TO T-83008A/B UNIT 1100 UNIT 1200 UNIT 6500 T-6106
61
M
P-6503A
P-6503B
P97017901-16"-A2A1-N (BUTANE-1 TO/FROM JETTY TO T-830008A/B)
WIND
No.11 ROAD(P) N:983.000
T-6102
Z-6503 N.N.W
EL 100000 PIPE SLEEPER
7M
000
Z-6521
T-6108 7
2280.
T-6532
P-6508A
P-6508B
NO.1 L.S FOR SY Z-6508
P-6521A/B
S)E:
000
P-6533A/B
B B
2148.
V-6901
N ROAD(
PIPE SLEEPER
CORRIDOR FOR FUTURE MECCA
S)E:
W.S.W
K ROAD(
EL 99500
000
B
1448.
N: 2707779.616
NOTES
2
E: 460977.666
90
S)E:
-6
GAS METERING
A
STATION
C ROAD(
No.12 ROAD(S) N:856.000
R
T
C 002-2 002-2 C
E
P
GUARD HOUSE
DMW92010101-6"-N1A1-N (DMW FROM SCU)
2. PLANT DATUM ELEVATION: EL.100.000 = MSL + 4.00 M.
HS70011408-10"-MS13-IH (HP STEAM FROM SCU)
)
5
TP-610001)
LLC70011508-6"-MS11-PP (LLP CONDENSATE TO UTILITIES) HIGH POINT PAVING ELEVATION: EL.101.000 = MSL +5.00 M.
88GH13
9
008)
NG92010204-2"-A1A1-N (LP NATURAL GAS FROM SCU) P-6101B
000
1431.
HY92010108-2"-B2A1-N (HYDROGEN FROM ME-23001)
ROAD(S) E:
P92010201-3"-A2A1 -N (HEXENE-1 TO/FROM STORAGE TO PE/PP)
6M
10
PE SLEEPER
1
RCULATI
P92010105-12"-A4A1-N (ETHYLENE VAPOR TO PPA) T-6101A T-6101B
HOLDS
RCULATI
XED LPG FROM EXI
P80012801-6"-T2A1-N (PROPYLENE FROM P-83013A/B TO PE/PP)
D D
ETHYLENE CI
P92017701-3"-A2A1-N (BUTENE-1 FROM SCU TO HDPE/LLDPE)
PI
PROPYLENE CI
PI
ME-6102
P80019701-3"-A2A1E-N (C6-C7 CUT FROM P-83024A/B TO T-A9103 (TP-S910004))
C(
C(
C(
MIN.EL 98600
MI
P97011606-12"-K2A0CCX-I
P97011608-10"-K2A0CCX-I
P97011609-4"-K2A0CCX-I
P20210109-16"-A1A1E-ST(
P10010104-4"-A1A1-N (FLUX OIL / WASH OIL FROM TP-S910001/2/3) SK-6901
0108-2"-B2A1-N(
P97510402-6"-T2A1-N (
ME-6101
C(
C(
C(
P10010407-3"-A1A1E-N(
-N(
C(
P97017901-16"-A1A1-N(
(
P80017301-4"-A2A1-N(
P97017902-12"-A1A1-N(
C(
P92510107-4"-A1A1-N(
C
P97013904-20"-T1A1-I
V-6902
P97010103-20"-T2A1-I
-I
A1-N (
I
P97013801-12"-T1A1-I
P97013201-12"-T1A1-I
P97010104-4"-T2A1-I
A1(
SK-6911
P97010105-12"-T2A1
P80010609-6"-T4A1
-10"-A1
MA800A-6"-A1
EL.100.000
5M
P-9102B
P-9102A
X-A9921
11
P97010101
T-9101 C)
01
61
HY9201
FT-
T-6101C T-6101D
R
=2 M M
D
2D
(
O (FUTURE)
REFERENCE DRAWINGS
E E
01C
01B
A
P-9101
00
P-91
P-91
D-S975-5225-001 PIPING TRANSPOSITION DRAWING SOHAR AREA - SRIP PLOT
T-A9202
m
No.13 ROAD(S) N:617.000
EL 99150
CRUDE RECEIVING 24"
T-A9105 FACILITIES
000
ROAD(S) E:1431.
(BY ORC)
L
C
EL 99150 N: 544200
F FIRE N:535.000 F
SPOSAL AREA
TRAINING
SPACE ONLY)
EL 99500
WWT SLUDGE
GROUND
T-9110
EL 99350 T-6531
)
002-1
TP-S62012/13/14)
SPOSAL AREA DI
(
UTM COORDINATES N:495.000
C 002-3
P-6504A
P-6504B
SPACE ONLY)
UTM COORDINATES
TANK SLUDGE
N: 2707536.733
)
N: 2707552.017 E: 460586.481 AB
TP-S620015)
)
TP-S910004)
E: 460576.972 MIN.EL 98600
Z-6555
NO.3 L.S FOR SY Z-6504 P-6555A/B
DI
T 2900)
Z-5208-1
(
Z-6523B,P-6523C/D
90.
61M
NG (
L FROM TP-S910001/2/3)
C6-C7 CUT FROM P-83024A/B TO T-A9103 (
U6500
NG)
S)E:
NALK UNI
NTERCONNECTI
NO.2 L.S FOR CWS TREATMENT
L ROAD(
NG)
P-6527
ES)
Z-6528 (REF. TO V-215A-301-A-033)
NTERCONNECTI
TI
P-6528
S/S
LI
NG)
ETHYLENE VAPOR TO PPA)
CE WATER FROM I
NTERCONNECTI
WW FROM PE TO SCU)
No.15 ROAD(P) N:404.000
L / WASH OI
S FUEL OI
SUBSTATION WATER TANK
E
HP BFW FROM I
PE SLEEPER
REUSE
LABORATORY
E: 460556.583 EQUIPMENT
PYROLYSI
FG FROM I
(12)
SHELTER
HYDRO BLAST
FLUX OI
SERVI
(BY OTHERS) No.16 ROAD(S) N:363.000
LPG FROM)
JETTING CLEANING
AREA AREA
P-6524A/B/C/D
PI
000
H(
1-PP (
01-6"-N1A1-N (
H(
04-6"-MS01-N (
CHEMICAL
0"-MS01-N (
I
NG92010204-2"-A1A1-N (
P80019701-3"-A2A1E-N (
-ST (
P920XXYY-6"-HOLD-N (
-N (
208-3"-A1A1-N (
I
448.
P97010102-10"-A1A1-N (
BWF70011508-3"-MS13-I
P80020201-3"-A2A1-N (
NO.4 L.S
P92010202-2"-A2A1-N (
P80018201-4"-HOLD-N (
0104-4"-A1A1-N (
STORAGE
-N (
P80012801-6"-T2A1-N (
P92010201-3"-A2A1-N (
3-I
Z-5208-2
Z-6524A/B
05-12"-A4A1
AB
1508-6"-MS1
0"-MS1
P92010206-2"- -N (
P80015201-4"-A2A1
Z-5209
1
7701-3"-A2A1
P)E:
OPEN YARD
000
SHUTDOWN WAREHOUSE T-6301 T-6302 ME-6302
Z-6522
C ROAD(
1750.
CONTRACTOR AREA
1108-1
1408-1
P-6522A/B
DMW920101
EL 99500
WW920101
PIPE SLEEPER PIPE SLEEPER
P)E:
LLC7001
FG70011
P920101
68" CLEAN SEA WATER RETURN
PW7001
HS7001
P9201
P1001
FIRE EL 99500
F ROAD(
STATION
(8)
61
80"
P-3801
M
V-3801 ME-3801
A/B/C T-3801
WAITING AREA WAITING AREA
GASOLINE 1
WARE HOUSE
FOR CONT.SEE D-S975-5225-004
(6)
WORKSHOP
BUILDING 1 2 3 4
61M
MEDICAL ME-6301
J CENTER
FUTURE
LPG WEIGH SCALE J
EL 99700
(20)
80"
(10) SULFUR GRANULATION &
EL 99500 1st SULFUR STORAGE AREA
NON-RESERVATION
4))
TRUCK WAITING AREA
3/1
No.18 ROAD(S) N:200.000
2/1
TRUCK LOADING
TP-S6201
TRUCK LOADING SATELLITE OFFICE
)
GUARD HOUSE
5)
)
1)
TP-S910004)
TRUCK YARD BUILDING
0001/2/3)
3 AT SOHAR REF.(
PG PROPYLENE TO T83002A/B FROM TP-S620001)
T 2900)
PG ETHYLENE TO/FROM JETTY TO T-83003)
TP-S91
NG (
009A/B TO JETTY
SECURITY OFFICE
NG)
07A TO T-810003A/B (
NALK UNI
88"
88"
448.
8A/B TO T-6231A/B)
002 (
NTERCONNECTI
SOPENTANE FROM JETTY TO STORAGE)
K K
NE TO JETTY)
500
NG)
ST.TANKAGE)
001/21
ES)
2060.
NTERCONNECTI
L TO T-621
LITI
L TO T-21
E:
NG)
ETHYLENE VAPOR TO PPA)
CE WATER FROM I
RCULATI
NTERCONNECTI
WW FROM PE TO SCU)
SOPENTANE VAPOR LI
RCULATI
KEY PLAN
S FUEL OI
HP BFW FROM I
ETHYLENE CI
P/S C
9/K-83009)
BREAKWAT
PROPYLENE CI
ER
OFCC PHASE 1
FG FROM I
PYROLYSI
)
FLUX OI
SERVI
LPG FROM)
DEMI
3/1
ETTY
OFCC PHASE 2
I
MAJSJ
SUBSTATION
C8-C1
-C2A
H
C(
RT
C(
BE
C(
PROPYLENE VAPOR RETURN TO/FROM JETTY TO/FROM V-8301
TP-S62012/1
H(
1-PP (
09-16"-A1A1E-ST (
H(
2B
MI
608-10"-K2A0CCX-I
606-12"-K2A0CCX-I
01-6"-N1A1-N (
-C
0104-6"-MS01-N (
RTH
108-10"-MS01-N (
BE
609-4"-K2A0CCX-I
NG92010204-2"-A1A1-N (
B
HY92010108-2"-B2A1-N (
-
C(
TH