BRTC Project - Chichpalli District - Chandrapur
Annexure VI
Testing Statement Upto RA- 21
Unit
Qty as per
Sr. No. Items Specified Frequency
execution
i) (1 set of 3 cubes for each grade)
a) Upto 5 cum.-1 Set.
2 3 b)
4 6 to 15 cum-2 Sets
One
c) 16test forcum-3
to 30 each Sets.
1 Cement Test 47045 Bags consignment of 150
d) 31 to 50 cum-4 MT & part thereof.
Sets.
2 Aggregate 6073.27 Cum One
e) 51 & above-4 Plus & part thereof.
test for 200 cum
3 Sand 3961.32 one additional& sample
At Beginning if there is change in source.
for each additional 50 cum or part thereof.
4 Concrete (Set of at least one sample shall be taken from
M-25 5480.82 Cum each shift of work)
5 Steel Test
5.1 Up to 16 mm Dia 232.478 MT
One test for every 5 metric tones or part there
5.2 Above 16 mm Dia 35.386 MT of for each diameter of bar.
6 Bricks
6.1 230 mm Thk brick wall 679336 Nos (One set of 15 Bricks) For 50,000 Nos and part
6.2 half brick wall 71205 Nos thereof.
7 Flooring Tiles 177.86
6 tiles shall be tested or every test for every
2000 tiles or part thereof
District - Chandrapur
Test
Required Total Test Deficienc Reports
test as Test actual taken at Carried y in Test Submitte Reports Remarks
to be
per d to PWD Submitte
Frequenc d
y PWD
Site office labortory
5 6 7 8 9
17 4 4 13
33 0 7 7 26
1 0 1 1 0
114 0 25 25 89
47 16 16 31
8 4 4 4
15 10 10 5
2 0 2
4 0 4 4 0