A welding machine at a construction site was operating without a proper grounding system, posing an electrical hazard to workers from potential electric shocks. The document recommends ensuring grounding systems are installed properly and functioning, and that Ground Fault Circuit Interrupters are available and working, before performing welding work. A Stop Work Authority was implemented to immediately close the work until the welding machine's grounding system was addressed.

Uploaded by

Muhammad Tohir
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
470 views2 pages

HES Moment 05122019

A welding machine at a construction site was operating without a proper grounding system, posing an electrical hazard to workers from potential electric shocks. The document recommends ensuring grounding systems are installed properly and functioning, and that Ground Fault Circuit Interrupters are available and working, before performing welding work. A Stop Work Authority was implemented to immediately close the work until the welding machine's grounding system was addressed.

Uploaded by

Muhammad Tohir
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

EPCM-SMBR-HES-FRM-CORP-0014 Rev.

SAFETY MOMENT
Topic : Welding machine grounding system
Date : November 10, 2019
Details : Welding Machine at Operation Without Grounding system
Location : PKM # 33.600 Mindal - KB
Contractor : PT. WKS WUR MD
SMBR HES : YUFIRMAN

Descriptions :
Welding machine operated without grounding system
Before After

Hazard: Welding machine operate without grounding system has potential for electrical hazard (Electric
shock to workers)

Action Items / Recommendation:


• Grounding system must be installed properly before welding job performed
• Ensure that Ground Fault Circuit Interrupter (GFCI) available and working properly
• SWA/ SSWA must be applied if GFCI and grounding system not comply
• Pre used inspection must be performed to ensure tools & Equipment in safe condition before operated

SWA Implementation:
Yes, No || SWA Status: Closed Immediately Date:.