Construction Cost Analysis
Construction Cost Analysis
Total = 399,618.40
Unit Cost = 1,002.55
DESCRIPTION NUMBER DAYS RATE SUB-TOTAL
Total = 20,853.33
Unit Cost = 52.32
DESCRIPTION NUMBER DAYS RATE SUB-TOTAL
Total = 17,315.66
Unit Cost = 43.44
Labor
A.1 Health and Safety Practitioner
a. Safety Practitioner/ Officer (Part Time) 1 12.00 93.62 1,123.44
b. First Aider 1 64.00 67.67 4,330.88
Sub - Total for A.1 - As Submitted 5,454.32
Labor
Health and Safety Practitioner
A.2 a. Safety Practitioner/ Officer (Part Time)
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment
B.1
B.2
Materials
Personal Protective Equipment
F.1
a. Safety Helmet mandays 218.33 0.25 54.58
b. Safety Shoes mandays 218.33 2.77 604.78
c. Safety Gloves mandays 218.33 7.67 1,674.62
Sub - Total for F.1 - As Submitted 2,333.99
Materials
Personal Protective Equipment
a. Safety Helmet
F.2
b. Safety Shoes
c. Safety Gloves
Sub - Total for F.2 - As Evaluated
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 7,788.31
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 0% -
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated
I.1 Contractor's Profit (CP) - As Submitted 10% 778.83
I.2 Contractor's Profit (CP) - As Evaluated
J.1 Value Added Tax (VAT) - As Submitted 5% 428.36
J.2 Value Added Tax (VAT) - As Evaluated
K.1 Total Unit Cost - As Submitted 8,995.49
K.2 Total Unit Cost - As Evaluated
8 pcs. Steel Base Plate - 0.25m x 0.35m x 10mm thick 54.95 kgs. 52.00 2,857.40
21 pcs. Tension Rods, 16mmØ x 6.0m 198.87 kgs. 52.00 10,341.26
3/4"Ø 16" - Anchor Bolts 32.00 pcs. 128.00 4,096.00
3/4"Ø 4" - Bolts & Knots 16.00 pcs. 15.00 240.00
Turnbuckles, 15mmØ 12.00 pcs. 416.00 4,992.00
Metal Primer Paint 8.00 gal 625.00 5,000.00
Welding Rod 10.00 boxes 1,200.00 12,000.00
Paint Thinner 4.00 gal 200.00 800.00
Paint Brush 4.00 pcs. 80.00 320.00
Total = 426,671.86
Unit Cost = 55.58
DESCRIPTION NUMBER DAYS RATE SUB-TOTAL
Total = 58,767.80
Unit Cost = 7.65
DESCRIPTION NUMBER DAYS RATE SUB-TOTAL
Total = 33,444.99
Unit Cost = 4.36
Project Name : Construction of Multi-Purpose Building, Brgy. Nancasalan Net Length : (a) Road -
(b) Bridge -
Project ID : (c) Others -
Project Component ID : Dimension = (16.00m x 18.00m)
Project Location : Mangatarem, Pangasinan Target Start Date : Upon Approval
Project Description : Construction of Covered Court (3 Bays x 6.00 m) with Permits and Clearances; Electrical Works; Painting Works; Construction of Slab 16 x 18 m (0.10m elevation) Total Project Duration : 90 Calendar Days
with Decorative Stone and Sunbreaker at Front (Metal Tube; 50mmx75mm)
Appropriation : ₱ 2,500,000.00 No. of Pre-determined : -
Source of Fund : NEP FY 2020 Unworkable Days
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
PART II OTHER GENERAL REQUIREMENTS 3.96% 75,085.13
PART III
A: EARTHWORK (PLS. SEE FORM POW-2015-01C-00) 3.12% 59,094.28
B: PLAIN AND REINFORCED CONCRETE WORK 28.49% 540,528.01
C: FINISHING AND OTHER CIVIL WORKS 62.07% 1,177,444.63
Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:
ALEJANDRO M. DE VERA, III SHEBA M. ESTRADA FERNANDO F. BUGARIN ERICSON A. PAZ EDITA L. MANUEL
Architect II Assistant Chief/Engineer III OIC-Chief/Engineer III Caretaker District Engineer
Planning and Design Section Planning and Design Section Planning and Design Section Office of the Assistant District Engineer
Name of Project: EXTENSION/CONSTRUCTION OF BANK PROTECTION WORKS, BRGY. ALIWEKWEK
LINGAYEN, PANGASINAN
Item
Description
No.
Err:509 Engineer's Field Office (Rental)
Err:509 Operation Maintenance of Field Office for the Engineers
Err:509 Provision of 4x4 Pick-up Type Service Vehicle for the Engineer on Bare Rental Basis
Err:509 Project Billboard/Signboard
PART II Occupational Safety & Health Program
B.5 Mobilization/Demobilization
0 Geotechnical Exploration
B.7(2)
0
Err:509
Err:509
0
0
PART A
803(1)a
0
Err:509
Err:509
Err:509
Err:509
804(4)
0
0
0
PART B
900(1)c2
0
900(1)c3
0
900(1)c4
0
Err:509
Err:509
902(1)a
0
903(2)
0
0
0
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
PART C
Err:509
Err:509
Err:509 Hand Laid Rock Embankment
Err:509 Gabions (2.00mx1.00mx1.00m)
Err:509 Clearing & Grubbing
Err:509 Structure Excavation(Common Soil)
Err:509 Embankment
Err:509 Gabions(3.00mx1.00mx1.00m)
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
1027(1)
0
Err:509
Err:509
Err:509 Mattress (0.30mx2.00mx6.0m)
Err:509 Filter Cloth
Err:509
Err:509
1032(1)a
0
Err:509
Err:509
1032(1)c
0
1014(1)b2
0
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
TOTAL =
I HEREBY CERTIFY that the account and the work accomplished stated above are correct
and the labor and materials in connection with this project have already paid and payment
thereof requested.
WILPRES ENTERPRISES
Contractor
Recommending Approval:
STATEMENT OF WORK ACCO
As of
N, PANGASINAN
account and the work accomplished stated above are correct I HEREBY CERTIFY that
n connection with this project have already paid and payment undersigned and have be
specially and program of
REBECC
OIC-Chief, C
DIOSDADO C. LOMIBAO
Assistant District Engineer
NT OF WORK ACCOMPLISHED
HEREBY CERTIFY that all the work items were duly verified by the
ersigned and have been accomplished in according with the plans
ially and program of works.
Approved:
RODOLFO C. DION
District Engineer
Total Value of Work Total Value of Work % Accomplished
this Billing to Date
22,546.00 22,546.00 0.12%
15,218.55 15,218.55 0.08%
78,562.50 78,562.50 0.42%
9,487.74 9,487.74 0.05%
54,193.18 54,193.18 0.29%
71,824.98 71,824.98 0.39%
49,882.95 49,882.95 0.27%
- - 0.00%
1,498,392.48 1,498,392.48 8.05%
22,218.00 22,218.00 0.12%
98,913.92 98,913.92 0.53%
335,401.96 335,401.96 1.80%
1,636,888.92 1,636,888.92 8.79%
SYLVIA C. GALLANG
Chief, Quality Assurance Section
OLFO C. DION
rict Engineer
STATEMENT OF WORK ACCOMPLISHED
As of March 20, 2017
Name of Contractor : J.G. GARCIA CONSTRUCTION AND SUPPLY
Name of Project: Construction of Multi-Purpose Building, Brgy. Nancasalan Contract Amount : Err:509
Notice to Proceed : February 20, 2017
Mangatarem, Pangasinan Contract Effectivity : February 24, 2017
Contract Expiry : May 24, 2017
Actual Starting Dates : February 20, 2017
Calendar Days : 90 C.D.
Item Total Cost Unit Approved Quantity Total Value of Total Value of Total Value of
Description Unit Bid Amount % Accomplished
No. Quantity Cost Previous This Billing To Date Work Previously Work this Billing Work to Date
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
B.5 Project Billboard/ Sign Board ea. 2.00 5,440.14 10,880.28 - 2.00 2.00 - 10,880.28 10,880.28 Err:509
B.7(2) Occupational Safety and Health Program L.S. 1.00 29,216.17 29,216.17 - 1.00 1.00 - 29,216.17 29,216.17 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
803(1)a Structure Excavation (Common Soil) m3 81.51 305.31 24,885.81 81.51 - - 24,885.81 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
804(4) Gravelfill m3 34.91 1,195.29 41,721.77 34.91 - - 41,721.77 Err:509
900(1)c2 Structural Concrete for Footing and Slab on Fill (Class A, 28 da m3 38.28 6,231.09 238,507.36 38.28 - - 238,507.36 Err:509
900(1)c3 Structural Concrete for Footing Tie Beam (Class A, 28 days) m3 11.57 6,917.27 80,018.96 11.57 - - 80,018.96 Err:509
900(1)c4 Structural Concrete for Column (Class A, 28 days) m3 5.86 6,917.27 40,507.53 5.86 - - 40,507.53 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
902(1)a Reinforcing Steel, Grade 40 kgs. 4,125.08 68.58 282,911.05 4,125.08 - - 282,911.05 Err:509
903(2) Formworks and Falseworks m2 135.80 497.04 67,498.11 135.80 - - 67,498.11 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
1027(1) Cement Plaster Finish m² 50.40 214.73 10,822.31 50.40 - - 10,822.31 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
1032(1)a Painting Works (Masonry/Concrete) m² 50.40 291.09 14,670.72 50.40 - - 14,670.72 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
1032(1)c Painting Works (Steel) m² 571.93 390.89 223,563.62 571.93 - - 223,563.62 Err:509
1014(1)b2 Prepainted Metal Sheets ( Long Span,Rib-Type,0.427mm thk) m² 462.81 672.55 311,267.11 462.81 - - 311,267.11 Err:509
1013(2)a1 Fabricated Metal Roofing Accessory (Ridge Roll/Hip); (gauge 2 L.M. 20.00 307.83 6,156.52 20.00 - - 6,156.52 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
1047(2)a Structural Steel, Trusses kgs. 4,381.43 103.02 451,377.84 4,381.43 - - 451,377.84 Err:509
1047(2)b Structural Steel Purlins kgs. 3,441.71 96.73 332,925.17 3,441.71 - - 332,925.17 Err:509
1047(6) Metal Structure Accessories (Steel Plates) kgs. 54.95 97.53 5,359.52 54.95 - - 5,359.52 Err:509
1047(3)a Metal Structure Accessories (Bolts) each 48.00 204.96 9,837.90 48.00 - - 9,837.90 Err:509
1047(3)b Metal Structure Accessories (Sagrods) each 10.00 310.49 3,104.94 10.00 - - 3,104.94 Err:509
1047(4) Metal Structure Accessories (Crossbracing) kgs. 198.87 80.50 16,009.25 198.87 - - 16,009.25 Err:509
1047(3)c Metal Structure Accessories (Turnbuckle) e.a. 12.00 289.05 3,468.64 12.00 - - 3,468.64 Err:509
1100(10) Conduit, Boxes, & Fittings (Conduit Works/Conduit Rough-in) L.S. 1.00 13,756.89 13,756.89 1.00 - - 13,756.89 Err:509
1101(33) Wires and Wiring Devices L.S. 1.00 32,132.81 32,132.81 1.00 - - 32,132.81 Err:509
1102(1) Panelboard with Main & Branch Breakers L.S. 1.00 13,038.50 13,038.50 1.00 - - 13,038.50 Err:509
1103(1) Lighting Fixtures and Lamps L.S. - #DIV/0! #DIV/0! - #DIV/0! #DIV/0! #DIV/0! #DIV/0!
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
TOTAL = Err:509 Err:509 Err:509 Err:509 Err:509
Checked by:
GABBY P. TUAZON
Project Engineer I
I HEREBY CERTIFY that the account and the work accomplished I HEREBY CERTIFY that all the work items were duly verified I HEREBY CERTIFY that the materials used in
stated above are correct and the labor and materials in connection by the undersigned and have been accomplished in according project have been tested and have passed
with this project have already paid and payment thereof requested. with the plans specially and program of works. requirements.
Mangatarem, Pangasinan
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST % DIRECT
QTY
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT) COST
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS EVALUATED
PART II OTHER GENERAL REQUIREMENTS
B.3 Permits and Clearances 1.00 L.S. 41,500.00 41,500.00 43,575.00
B.5 Project Billboard/ Sign Board 2.00 ea. 8,289.74 4,144.87 10,880.28
B.7(2) Occupational Safety and Health Program 1.00 L.S. 25,295.39 25,295.39 29,216.17
TOTAL OF PART II 33,585.13
PART III-A EARTHWORK
803(1)a Structure Excavation (Common Soil) 81.51 m³ 18,960.62 232.62 24,885.81
804(1)a Embankment (from Structure Excavation) 54.02 m³ 8,345.65 154.51 10,953.67
804(4) Gravelfill 34.91 m³ 31,788.01 910.70 41,721.77
TOTAL OF PART III-A 59,094.28
PART III-B PLAIN AND REINFORCED CONCRETE WORK
900(1)c2 Structural Concrete for Footing and Slab on Fill (Class A, 28 days) 38.28 m³ 181,719.90 4,747.50 238,507.36
900(1)c3 Structural Concrete for Footing Tie Beam (Class A, 28 days) 11.57 m³ 60,966.83 5,270.30 80,018.96
900(1)c4 Structural Concrete for Column (Class A, 28 days) 5.86 m³ 30,862.88 5,270.30 40,507.53
902(1)a Reinforcing Steel, Grade 40 4,125.08 kgs. 215,551.27 52.25 282,911.05
903(2) Formworks and Falseworks 135.80 m² 51,427.14 378.70 67,498.11
TOTAL OF PART III-B 540,528.01
PART III-C FINISHING AND OTHER CIVIL WORKS
1027(1) Cement Plaster Finish 50.40 m² 8,245.57 163.60 10,822.31
1027(3) Decorative Stone 11.20 m2 19,644.70 1,753.99 25,783.66
1051(6) Railing 1.00 L.S. 52,863.03 52,863.03 69,382.73
1032(1)a Painting Works (Masonry/Concrete) 50.40 m² 11,177.69 221.78 14,670.72
1032(1)c Painting Works (Steel) 571.93 m² 170,334.19 297.82 223,563.62
1014(1)b2 Prepainted Metal Sheets ( Long Span,Rib-Type,0.427mm thk) 462.81 m² 237,155.89 512.42 311,267.11
1013(2)a1 Fabricated Metal Roofing Accessory (Ridge Roll/Hip); (gauge 26) 20.00 L.M. 4,690.68 234.53 6,156.52
1013(2)a2 Fabricated Metal Roofing Accessory (Flashings); (gauge 26) 40.00 L.M. 9,381.37 234.53 12,313.05
1013(2)b1 Fabricated Metal Roofing Accessory (Gutters); (gauge 24) 40.00 L.M. 14,886.58 372.16 19,538.63
1047(2)a Structural Steel, Trusses 4,381.43 kgs. 343,906.93 78.49 451,377.84
1047(2)b Structural Steel Purlins 3,441.71 kgs. 253,657.27 73.70 332,925.17
1047(6) Metal Structure Accessories (Steel Plates) 54.95 kgs. 4,083.45 74.31 5,359.52
1047(3)a Metal Structure Accessories (Bolts) 48.00 each 7,495.55 156.16 9,837.90
1047(3)b Metal Structure Accessories (Sagrods) 10.00 each 2,365.67 236.57 3,104.94
1047(4) Metal Structure Accessories (Crossbracing) 198.87 kgs. 12,197.52 61.33 16,009.25
1047(3)c Metal Structure Accessories (Turnbuckle) 12.00 e.a. 2,642.77 220.23 3,468.64
1001(19) Storm Drainage and Downspout 1.00 L.S. 22,715.79 22,715.79 29,814.47
TOTAL OF PART III-C 1,177,444.63
PART III-D ELECTRICAL WORKS
1100(10) Conduit, Boxes, & Fittings (Conduit Works/Conduit Rough-in) 1.00 L.S. 10,481.44 10,481.44 13,756.89
1101(33) Wires and Wiring Devices 1.00 L.S. 24,482.14 24,482.14 32,132.81
1102(1) Panelboard with Main & Branch Breakers 1.00 L.S. 9,934.10 9,934.10 13,038.50
TOTAL OF PART III-D 44,897.68
GRAND TOTAL 1,855,549.73
Construction of 1 Storey - 2 Classroom School Building at Manaoag National High School
Manaoag, Pangasinan
BACK-UP COMPUTATION
B.3 - Permit and Clearance
Qty = 1.00 L.S.
804(4) - Gravelfill
Qty = 23.34 cu.m.
Blackboard
Qty = 2.00 sets
A1 = 4.88 x 1.20 x 2.00 = 11.71 sq.m.
Ground Floor
C/1-5 = 3.50 x 4.50 x 2.00 x 2.00 x 1.00 = 63.00
= 2.50 x 4.50 x 2.00 x 2.00 x 1.00 = 45.00
A(w-1) = 2.60 x 1.83 x 2.00 x 2.00 x 2.00 = 38.06
69.94
A/1-5 = 3.50 x 4.50 x 2.00 x 2.00 x 1.00 = 63.00
= 2.50 x 4.50 x 2.00 x 2.00 x 1.00 = 45.00
A(w-2) = 1.30 x 1.83 x 2.00 x 2.00 x 2.00 = 19.03
A(d-1) = 0.90 x 2.40 x 2.00 x 2.00 x 2.00 = 17.28
71.69
1/A-C, 3/A-C, = 3.40 x 7.00 x 2.00 x 1.00 = 47.60
5/A-C = 2.40 x 7.00 x 4.00 x 1.00 = 67.20
114.80
A = 0.50 x 7.00 x 1.75 x 2.00 x 2.00 = 24.50
corridor = 21.00 x 1.00 x 1.00 = 21.00
ramp = 30.00 x 0.50 x 1.00 = 15.00
stairs = 5.70 x 0.80 x 1.00 = 4.56
= 5.70 x 0.60 x 1.00 = 3.42
= 5.70 x 0.40 x 1.00 = 2.28
= 5.70 x 0.20 x 1.00 = 1.14
plant box = 5.70 x 1.00 x 1.00 =
= 5.70 x 0.50 x 1.00 =
71.90
Ground Floor
C/1-5 = 3.50 x 4.150 x 2.00 x 2.00 = 58.10 sq.m.
A(w-1) = 2.60 x 1.83 x 2.00 x 2.00 = 19.03 sq.m. (deduct)
39.07 sq.m.
A/1-5 = 3.50 x 4.150 x 2.00 x 2.00 = 58.10 sq.m.
A(w-2) = 1.30 x 1.83 x 2.00 x 2.00 = 9.52 sq.m. (deduct)
A(d-1) = 0.90 x 2.40 x 2.00 x 2.00 = 8.64 sq.m. (deduct)
39.94 sq.m.
1/A-C, 3/A-C, = 3.40 x 6.650 x 3.00 x 1.00 = 67.83 sq.m.
5/A-C
A = 1/2 x 7.00 x 1.75 x 2.00 = 12.25 sq.m.
corridor = 21.00 x 1.00 x 1.00 = 21.00 sq.m.
ramp = 30.00 x 0.50 x 1.00 = 15.00 sq.m.
stairs = 5.70 x 0.80 x 1.00 = 4.56 sq.m.
= 5.70 x 0.60 x 1.00 = 3.42 sq.m.
= 5.70 x 0.40 x 1.00 = 2.28 sq.m.
= 5.70 x 0.20 x 1.00 = 1.14 sq.m.
plant box = 5.70 x 1.00 x 1.00 = 5.70 sq.m.
= 5.70 x 0.50 x 1.00 = 2.85 sq.m.
68.20 sq.m.
1047(8) - Structural Steel (Roof Framing)
Trusses
Qty = 1.00 L.S.
Prepared by:
GABBY P. TUAZON
Engineer II
onal High School
sq.m.
sq.m.
sq.m. (deduct)
sq.m.
sq.m.
sq.m.
sq.m. (deduct)
sq.m. (deduct)
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
(deduct)
(deduct)
(deduct)
REGION I
FORM ABC-2015-02A-00
Mangatarem, Pangasinan
Mangatarem, Pangasinan
Page 31 of 109
Construction of Multi-Purpose Building, Brgy. Nancasalan
Mangatarem, Pangasinan
FORM POW-2015-01B-00
Mangatarem, Pangasinan
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY UNIT 5 % VAT TOTAL COST
MATERIAL LABOR EQUIPMENT UNIT COST TOTAL % VALUE
PART II OTHER GENERAL REQUIREMENTS
AS EVALUATED
B.3 Permits and Clearances
AS SUBMITTED 1.761% 1.00 L.S. 41,500.00 - - 43,575.00 41,500.00 0% - 2,075.00 43,575.00
AS EVALUATED
B.5 Project Billboard/ Sign Board
AS SUBMITTED 0.440% 2.00 ea. 6,660.81 1,480.84 148.08 5,440.14 8,289.74 25% 2,072.43 518.11 10,880.28
AS EVALUATED
B.7(2) Occupational Safety and Health Program
AS SUBMITTED 1.180% 1.00 L.S. 8,443.79 16,851.60 - 29,216.17 25,295.39 10% 2,529.54 1,391.25 29,216.17
AS EVALUATED
TOTAL OF PART II
AS SUBMITTED 3.381% 56,604.60 18,332.44 148.08 75,085.13 4,601.97 3,984.35 83,671.45
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORK
AS EVALUATED
803(1)a Structure Excavation (Common Soil)
AS SUBMITTED 1.005% 81.51 m³ - 1,020.14 17,940.48 305.31 18,960.62 25% 4,740.15 1,185.04 24,885.81
AS EVALUATED
804(1)a Embankment (from Structure Excavation)
AS SUBMITTED 0.443% 54.02 m³ - 1,374.03 6,971.62 202.79 8,345.65 25% 2,086.41 521.60 10,953.67
AS EVALUATED
804(4) Gravelfill
AS SUBMITTED 1.686% 34.91 m³ 21,990.15 7,280.89 2,516.97 1,195.29 31,788.01 25% 7,947.00 1,986.75 41,721.77
AS EVALUATED
SUB TOTAL OF PART III-A
AS SUBMITTED 3.134% 21,990.15 9,675.06 27,429.07 59,094.28 14,773.57 3,693.39 77,561.24
PART B PLAIN AND REINFORCED CONCRETE WORK
AS EVALUATED
900(1)c2 Structural Concrete for Footing and Slab on Fill (Class A, 28 days)
AS SUBMITTED 9.637% 38.28 m³ 119,615.63 39,693.36 22,410.92 6,231.09 181,719.90 25% 45,429.97 11,357.49 238,507.36
AS EVALUATED
900(1)c3 Structural Concrete for Footing Tie Beam (Class A, 28 days)
AS SUBMITTED 3.233% 11.57 m³ 36,150.00 15,861.44 8,955.39 6,917.27 60,966.83 25% 15,241.71 3,810.43 80,018.96
AS EVALUATED
900(1)c4 Structural Concrete for Column (Class A, 28 days)
AS SUBMITTED 1.637% 5.86 m³ 18,300.00 8,029.44 4,533.43 6,917.27 30,862.88 25% 7,715.72 1,928.93 40,507.53
AS EVALUATED
902(1)a Reinforcing Steel, Grade 40
AS SUBMITTED 11.431% 4,125.08 kgs. 178,126.12 26,555.43 10,869.73 68.58 215,551.27 25% 53,887.82 13,471.95 282,911.05
AS EVALUATED
903(2) Formworks and Falseworks
AS SUBMITTED 2.727% 135.80 m² 23,545.17 25,347.24 2,534.72 497.04 51,427.14 25% 12,856.78 3,214.20 67,498.11
AS EVALUATED
SUB TOTAL OF PART III-B
AS SUBMITTED 28.664% 375,736.92 115,486.91 49,304.19 540,528.01 135,132.00 33,783.00 709,443.02
PART C FINISHING AND OTHER CIVIL WORKS
C.2. Finishing Works
AS EVALUATED
1027(1) Cement Plaster Finish
AS SUBMITTED 0.437% 50.40 m² 4,838.40 3,097.42 309.74 214.73 8,245.57 25% 2,061.39 515.35 10,822.31
AS EVALUATED
1027(3) Decorative Stone
AS SUBMITTED 1.042% 11.20 m2 15,265.60 3,981.00 398.10 2,302.11 19,644.70 25% 4,911.17 1,227.79 25,783.66
AS EVALUATED
1051(6) Railing
AS SUBMITTED 2.803% 1.00 L.S. 32,257.68 9,678.98 10,926.37 69,382.73 52,863.03 25% 13,215.76 3,303.94 69,382.73
AS EVALUATED
Sub-Total C.1
AS SUBMITTED 4.282% 52,361.68 16,757.40 11,634.21 80,753.30 20,188.32 5,047.08 105,988.70
C.3. Painting Works
AS EVALUATED
1032(1)a Painting Works (Masonry/Concrete)
AS SUBMITTED 0.593% 50.40 m² 3,754.27 6,748.56 674.86 291.09 11,177.69 25% 2,794.42 698.61 14,670.72
AS EVALUATED
1032(1)c Painting Works (Steel)
AS SUBMITTED 9.033% 571.93 m² 81,882.20 80,410.90 8,041.09 390.89 170,334.19 25% 42,583.55 10,645.89 223,563.62
AS EVALUATED
Sub-Total C.2
AS SUBMITTED 9.626% 85,636.47 87,159.46 8,715.95 181,511.87 45,377.97 11,344.49 238,234.33
Page 33 of 109
Construction of Multi-Purpose Building, Brgy. Nancasalan
Mangatarem, Pangasinan
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY UNIT 5 % VAT TOTAL COST
MATERIAL LABOR EQUIPMENT UNIT COST TOTAL % VALUE
C.4. Roof Framing and Roofing Works
AS EVALUATED
1014(1)b2 Prepainted Metal Sheets ( Long Span,Rib-Type,0.427mm thk)
AS SUBMITTED 12.576% 462.81 m² 188,296.25 44,417.86 4,441.79 672.55 237,155.89 25% 59,288.97 14,822.24 311,267.11
AS EVALUATED
1013(2)a1 Fabricated Metal Roofing Accessory (Ridge Roll/Hip); (gauge 26)
AS SUBMITTED 0.249% 20.00 L.M. 4,220.94 427.04 42.70 307.83 4,690.68 25% 1,172.67 293.17 6,156.52
AS EVALUATED
1013(2)a2 Fabricated Metal Roofing Accessory (Flashings); (gauge 26)
AS SUBMITTED 0.497% 40.00 L.M. 8,441.88 854.08 85.41 307.83 9,381.37 25% 2,345.34 586.34 12,313.05
AS EVALUATED
1013(2)b1 Fabricated Metal Roofing Accessory (Gutters); (gauge 24)
AS SUBMITTED 0.789% 40.00 L.M. 14,090.40 723.80 72.38 488.47 14,886.58 25% 3,721.64 930.41 19,538.63
AS EVALUATED
1047(2)a Structural Steel, Trusses
AS SUBMITTED 18.237% 4,381.43 kgs. 258,111.16 26,271.73 59,524.04 103.02 343,906.93 25% 85,976.73 21,494.18 451,377.84
AS EVALUATED
1047(2)b Structural Steel Purlins
AS SUBMITTED 13.452% 3,441.71 kgs. 205,573.45 16,661.77 31,422.05 96.73 253,657.27 25% 63,414.32 15,853.58 332,925.17
AS EVALUATED
1047(6) Metal Structure Accessories (Steel Plates)
AS SUBMITTED 0.217% 54.95 kgs. 3,090.28 902.88 90.29 97.53 4,083.45 25% 1,020.86 255.22 5,359.52
AS EVALUATED
1047(3)a Metal Structure Accessories (Bolts)
AS SUBMITTED 0.397% 48.00 each 6,368.16 1,024.90 102.49 204.96 7,495.55 25% 1,873.89 468.47 9,837.90
AS EVALUATED
1047(3)b Metal Structure Accessories (Sagrods)
AS SUBMITTED 0.125% 10.00 each 2,130.80 213.52 21.35 310.49 2,365.67 25% 591.42 147.85 3,104.94
AS EVALUATED
1047(4) Metal Structure Accessories (Crossbracing)
AS SUBMITTED 0.647% 198.87 kgs. 8,603.13 3,267.63 326.76 80.50 12,197.52 25% 3,049.38 762.35 16,009.25
AS EVALUATED
1047(3)c Metal Structure Accessories (Turnbuckle)
AS SUBMITTED 0.140% 12.00 e.a. 2,220.00 384.34 38.43 289.05 2,642.77 25% 660.69 165.17 3,468.64
AS EVALUATED
Sub-Total C.3
AS SUBMITTED 47.328% 701,146.45 95,149.53 96,167.69 892,463.67 223,115.92 55,778.98 1,171,358.57
C.5. Plumbing Works
AS EVALUATED
1001(19) Storm Drainage and Downspout
AS SUBMITTED 1.205% 1.00 L.S. 16,478.00 5,670.72 567.07 29,814.47 22,715.79 25% 5,678.95 1,419.74 29,814.47
AS EVALUATED
Sub-Total C.4
AS SUBMITTED 1.205% 16,478.00 5,670.72 567.07 22,715.79 5,678.95 1,419.74 29,814.47
AS EVALUATED
SUB TOTAL OF PART III-C
AS SUBMITTED 62.440% 855,622.60 204,737.11 117,084.92 1,177,444.63 294,361.16 73,590.29 1,545,396.08
PART D ELECTRICAL WORKS
AS EVALUATED
1100(10) Conduit, Boxes, & Fittings (Conduit Works/Conduit Rough-in)
AS SUBMITTED 0.556% 1.00 L.S. 5,784.00 4,270.40 427.04 13,756.89 10,481.44 25% 2,620.36 655.09 13,756.89
AS EVALUATED
1101(33) Wires and Wiring Devices
AS SUBMITTED 1.298% 1.00 L.S. 20,081.00 4,001.04 400.10 32,132.81 24,482.14 25% 6,120.54 1,530.13 32,132.81
AS EVALUATED
1102(1) Panelboard with Main & Branch Breakers
AS SUBMITTED 0.527% 1.00 L.S. 7,000.00 2,667.36 266.74 13,038.50 9,934.10 25% 2,483.52 620.88 13,038.50
AS EVALUATED
SUB TOTAL OF PART III-D
AS SUBMITTED 2.38% 32,865.00 10,938.80 1,093.88 44,897.68 11,224.42 2,806.11 58,928.21
AS EVALUATED
TOTAL OF PART III
AS SUBMITTED 96.619% 1,286,214.66 340,837.88 194,912.06 1,821,964.61 455,491.15 113,872.79 2,391,328.54
AS EVALUATED
GRAND TOTAL
AS SUBMITTED 100.00% 1,342,819.27 359,170.32 195,060.14 1,897,049.73 460,093.12 117,857.14 2,475,000.00
Page 34 of 109
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
PANGASINAN 2ND
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE I
Alvear St., Lingayen, Pangasinan
Mangatarem, Pangasinan
TOTAL MARK-UP
ITEM NO. DESCRIPTION ESTIMATED DIRECT COST 5% VAT TOTAL IND
% VALUE
AS EVALUATED
PART B OTHER GENERAL REQUIREMENTS
AS SUBMITTED 75,085.13 6% 4,601.97 3,984.35 8,5
AS EVALUATED
PART III-A EARTHWORKS
AS SUBMITTED 59,094.28 25% 14,773.57 3,693.39 18,
AS EVALUATED
PART III-B REINFORCED CONCRETE WORKS
AS SUBMITTED 540,528.01 25% 135,132.00 33,783.00 168
AS EVALUATED
PART III-C FINISHING
AS SUBMITTED 1,177,444.63 25% 294,361.16 73,590.29 367
AS EVALUATED
PART III-D ELECTRICAL WORKS
AS SUBMITTED 44,897.68 25% 11,224.42 2,806.11 14,
AS EVALUATED
TOTAL
AS SUBMITTED 1,897,049.73 460,093.12 117,857.14 577
Mangatarem, Pangasinan
8,586.33 83,671.45
18,466.96 77,561.24
168,915.00 709,443.02
367,951.45 1,545,396.08
14,030.53 58,928.21
577,950.27 2,475,000.00
Approval:
Mangatarem, Pangasinan
BILL OF QUANTITIES
Contract Duration : 90 CALENDAR DAYS
Page 39 of 109
BILL OF QUANTITIES
Contract Duration : 90 CALENDAR DAYS
Prepared by:
Page 40 of 109
BACK-UP COMPUTATION
Construction of Multi-Purpose Building, Brgy. Nancasalan
Mangatarem, Pangasinan
804(4) - Gravelfill
Qty = 34.91 m³
1051(6) Railing
Qty = 1.00 L.S.
A1 = 0.12 x 18.00
= 2.15 m²
A2 = 0.19 x 240.00
= 46.08 m²
A3 = 0.19 x 186.00
= 35.71 m²
A4 = 0.15 x 864.00
= 131.33 m²
A5 = 0.28 x 684.00
= 191.52 m²
A6 = 0.43 x 84.00
= 36.12 m²
A7 = 0.18 x 48.00
= 8.40 m²
A5 = 0.19 x 90.00
= 17.28 m²
A6 = 0.19 x 132.00
= 25.34 m²
A7 = 1.50 x 52.00
= 78.00 m²
Total = 571.93 m²
A1 = 20.11 x 20.00
= 402.27 sq.m.
A2 = 30.27 x 2.00
60.54 sq.m.
VTOTAL = 462.81 sq.m.
L= 20.00 L.M.
L= 40.00 L.M.
8 pcs. - Steel Base Plate - 0.25m x 0.35m x 10mm thick = 54.95 kgs.
PREPARED BY:
A.1 Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Materials
a. Fire Clearance and Inspection L.S. 1.00 2,500.00 2,500.00
b. Professional Fee L.S. 1.00 13,000.00 13,000.00
F.1
c. Cooperative Fee L.S. 1.00 15,000.00 15,000.00
d. Building Permit Inspection Fee L.S. 1.00 3,000.00 3,000.00
e. DENR Fees L.S. 1.00 5,000.00 5,000.00
f. Notary, Blue Print, Miscellaneous Fee & etc…L.S. L.S. 1.00 3,000.00 3,000.00
Sub - Total for F.1 - As Submitted 41,500.00
Materials
F.2
Sub - Total for F.2 - As Evaluated
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 41,500.00
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 0% -
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated
I.1 Contractor's Profit (CP) - As Submitted 0% -
I.2 Contractor's Profit (CP) - As Evaluated
J.1 Value Added Tax (VAT) - As Submitted 5% 2,075.00
J.2 Value Added Tax (VAT) - As Evaluated
K.1 Total Unit Cost - As Submitted 43,575.00
K.2 Total Unit Cost - As Evaluated
Labor
A.1 a. Construction Foreman 1 2.00 93.62 187.24
b. Skilled Laborer 1 2.00 67.67 135.34
c. Unskilled Laborer 4 2.00 52.23 417.84
Sub - Total for A.1 - As Submitted 740.42
Labor
a. Construction Foreman
A.2 b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of labor cost) 74.04
Sub - Total for B.1 - As Submitted 74.04
Equipment
B.2 Minor Tools (10% of labor cost)
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 814.46
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 814.46
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Materials
Marine Plywoord, 1/4"x 4'x8' pcs 1.33 350.00 465.50
Coco Lumber 13 -2'' x 3'' x 10'' 1,120.00
F.1 bd ft 56.00 20.00
12-2'' x 2''x 8'' -
Hardware, CWN assorted kgs 0.56 65.00 36.40
Tarpauline 4'x 8' 1,708.51
sq.ft 42.67 40.04
Tarpauline 8'x 8' ( COA Circular 2013) -
Sub - Total for F.1 - As Submitted 3,330.41
Materials
Marine Plywoord, 1/4"x 4'x8'
Coco Lumber 13 -2'' x 3'' x 10''
12-2'' x 2''x 8''
F.2
Hardware, CWN assorted
Tarpauline 4'x 8'
Tarpauline 8'x 8' ( COA Circular 2013)
Sub - Total for F.2 - As Evaluated
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 4,144.87
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% 621.73
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated
I.1 Contractor's Profit (CP) - As Submitted 10% 414.49
I.2 Contractor's Profit (CP) - As Evaluated
J.1 Value Added Tax (VAT) - As Submitted 5% 259.05
J.2 Value Added Tax (VAT) - As Evaluated
K.1 Total Unit Cost - As Submitted 5,440.14
K.2 Total Unit Cost - As Evaluated
Labor
A.1 Health and Safety Practitioner
a. Safety Practitioner/ Officer (Part Time) 1 22.50 748.96 16,851.60
-
Sub - Total for A.1 - As Submitted 16,851.60
Labor
Health and Safety Practitioner
A.2 a. Safety Practitioner/ Officer (Part Time)
Name and Capacity No. of Unit/s No. of Days Daily Rate Amount (PhP)
Equipment
B.1
B.2
Materials
Personal Protective Equipment
a. Safety Helmet mandays 630.76 0.25 157.69
b. Safety Shoes mandays 630.76 2.77 1,747.22
F.1 c. Safety Gloves mandays 630.76 7.67 4,837.96
Signage and Barricades
PPE Signage (4'x8') set 1.00 506.37 506.37
Safety First (4'x4') set 1.00 270.87 270.87
Warning Signs (2'x'3') set 1.00 123.68 123.68
Caution Tape, 1000ft roll 1.00 800.00 800.00
Sub - Total for F.1 - As Submitted 8,443.79
Materials
Personal Protective Equipment
a. Safety Helmet
F.2
b. Safety Shoes
c. Safety Gloves
Sub - Total for F.2 - As Evaluated
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 25,295.39
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 0% -
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated
I.1 Contractor's Profit (CP) - As Submitted 10% 2,529.54
I.2 Contractor's Profit (CP) - As Evaluated
J.1 Value Added Tax (VAT) - As Submitted 5% 1,391.25
J.2 Value Added Tax (VAT) - As Evaluated
K.1 Total Unit Cost - As Submitted 29,216.17
K.2 Total Unit Cost - As Evaluated
A.1 Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment
a. Mobilization/Demobilization 34,079.69
B.1
F.1 Materials
Labor
A.1 a. Construction Foreman 1 51.00 65.55 3,342.80
b. Skilled Laborer 2 51.00 47.62 4,857.62
c. Unskilled Laborer 7 51.00 36.75 13,117.97
Sub - Total for A.1 - As Submitted 21,318.38
Labor
a. Construction Foreman
A.2 b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of labor cost) 2,131.84
Sub - Total for B.1 - As Submitted 2,131.84
Equipment
B.2 Minor Tools (10% of labor cost)
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 23,450.22
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 23,450.22
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Materials
F.1
F.2
Unit of Measurement : m³
Output per hour - As Submitted : 20.00
Output per hour - As Evaluated : 20.00
Labor
A.1 a. Construction Foreman 1 1.00 93.62 93.62
b. Skilled Laborer 0 1.00 67.67 -
c. Unskilled Laborer 3 1.00 52.23 156.69
Sub - Total for A.1 - As Submitted 250.31
Labor
a. Construction Foreman
A.2 b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment
B.1 a. Backhoe (0.80 m^3) 1 1.00 1,537.00 1,537.00
b. Dump Truck (12 yd^3) 2 1.00 1,420.00 2,840.00
Minor Tools (10% of labor cost) 25.03
Sub - Total for B.1 - As Submitted 4,402.03
Equipment
B.2 Minor Tools (10% of labor cost)
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 4,652.34
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 20.00
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 232.62
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Materials
F.1
F.2
Unit of Measurement : m3
Output per hour - As Submitted : 9.84
Output per hour - As Evaluated : 9.84
Labor
A.1 a. Construction Foreman 1 1.00 93.62 93.62
b. Skilled Laborer 0 1.00 67.67 -
c. Unskilled Laborer 3 1.00 52.23 156.69
Sub - Total for A.1 - As Submitted 250.31
Labor
a. Construction Foreman
A.2 b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment
B.1 a. Plate Compactor 1 0.75 123.00 92.25
b. Backhoe (0.80cu.m.) 1 0.75 1,537.00 1,152.75
Minor Tools (10% of labor cost) 25.03
Sub - Total for B.1 - As Submitted 1,270.03
Equipment
a. Plate Compactor
B.2
Minor Tools (10% of labor cost)
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 1,520.34
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 9.84
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 154.51
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Materials
F.1
F.2
Unit of Measurement : m3
Output per hour - As Submitted : 9.84
Output per hour - As Evaluated : 9.84
Labor
A.1 a. Construction Foreman 1 1.00 748.96 748.96
b. Skilled Laborer 0 1.00 67.67 -
c. Unskilled Laborer 3 1.00 52.23 156.69
Sub - Total for A.1 - As Submitted 905.65
Labor
a. Construction Foreman
A.2 b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment
B.1
a. Plate Compactor 1 0.50 62.50 31.25
Minor Tools (10% of labor cost) 90.57
Sub - Total for B.1 - As Submitted 121.82
Equipment
a. Plate Compactor
B.2
Minor Tools (10% of labor cost)
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 1,027.47
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 9.84
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 104.42
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Materials
a. Embankment Materials (w/ 20% Shrinkage Factor) m3 1.20 270.00 324.00
F.1
F.2
Unit of Measurement : m³
Output per hour - As Submitted : 1.20
Output per hour - As Evaluated : 1.20
Labor
A.1 a. Construction Foreman 1 1.00 93.62 93.62
b. Skilled Laborer 0 1.00 67.67 -
c. Unskilled Laborer 3 1.00 52.23 156.69
Sub - Total for A.1 - As Submitted 250.31
Labor
a. Construction Foreman
A.2 b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment
B.1
a. Plate Compactor 1 0.50 123.00 61.50
Minor Tools (10% of labor cost) 25.03
Sub - Total for B.1 - As Submitted 86.53
Equipment
a. Plate Compactor
B.2
Minor Tools (10% of labor cost)
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 336.84
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 1.20
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 280.70
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Materials
a. Gravel Bedding (G1) (w/ 5% Shrinkage Factor) m3 1.05 600.00 630.00
F.1
F.2
Unit of Measurement : m³
Output per hour - As Submitted : 0.365
Output per hour - As Evaluated : 0.365
Labor
A.1 a. Construction Foreman December 31, 1899 1.00 65.55 65.55
b. Skilled Laborer December 31, 1899 1.00 47.62 47.62
c. Unskilled Laborer January 3, 1900 1.00 36.75 146.98
Sub - Total for A.1 - As Submitted 260.15
Labor
a. Construction Foreman
A.2 b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment
B.1
a. One Bagger Mixer December 31, 1899 1.00 156.00 156.00
Minor Tools (10% of labor cost) 26.01
Sub - Total for B.1 - As Submitted 182.01
Equipment
a. One Bagger Mixer
B.2
Minor Tools (10% of labor cost)
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 442.16
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 0.365
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 1,211.41
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Materials
a. Gravel m3 1.00 600.00 600.00
b. Sand m3 0.50 500.00 250.00
F.1
c. Portland Cement bags 10.00 240.00 2,400.00
F.2
Item No. / Description : 900(1)c2 - Structural Concrete for Footing and Slab on Fill (Class A, 28 days)
Unit of Measurement : m³
Output per hour - As Submitted : 0.357
Output per hour - As Evaluated : 0.357
Labor
A.1 a. Construction Foreman 1 1.00 93.62 93.62
b. Skilled Laborer 1 1.00 67.67 67.67
c. Unskilled Laborer 4 1.00 52.23 208.92
Sub - Total for A.1 - As Submitted 370.21
Labor
a. Construction Foreman
A.2 b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment
B.1
a. One Bagger Mixer 1 1.00 172.00 172.00
Minor Tools (10% of labor cost) 37.02
Sub - Total for B.1 - As Submitted 209.02
Equipment
a. One Bagger Mixer
B.2
Minor Tools (10% of labor cost)
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 579.23
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 0.357
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 1,622.50
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Materials
a. Gravel m3 1.00 600.00 600.00
b. Sand m3 0.50 500.00 250.00
F.1
c. Portland Cement bags 9.10 250.00 2,275.00
F.2
Item No. / Description : 900(1)c3 - Structural Concrete for Footing Tie Beam (Class A, 28 days)
Unit of Measurement : m³
Output per hour - As Submitted : 0.270
Output per hour - As Evaluated : 0.270
Labor
A.1 a. Construction Foreman 1 1.00 93.62 93.62
b. Skilled Laborer 1 1.00 67.67 67.67
c. Unskilled Laborer 4 1.00 52.23 208.92
Sub - Total for A.1 - As Submitted 370.21
Labor
a. Construction Foreman
A.2 b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment
B.1
a. One Bagger Mixer 1 1.00 172.00 172.00
Minor Tools (10% of labor cost) 37.02
Sub - Total for B.1 - As Submitted 209.02
Equipment
a. One Bagger Mixer
B.2
Minor Tools (10% of labor cost)
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 579.23
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 0.270
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 2,145.30
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Materials
a. Gravel m3 1.00 600.00 600.00
b. Sand m3 0.50 500.00 250.00
F.1
c. Portland Cement bags 9.10 250.00 2,275.00
F.2
Item No. / Description : 900(1)c4 - Structural Concrete for Column (Class A, 28 days)
Unit of Measurement : m³
Output per hour - As Submitted : 0.270
Output per hour - As Evaluated : 0.270
Labor
A.1 a. Construction Foreman 1 1.00 93.62 93.62
b. Skilled Laborer 1 1.00 67.67 67.67
c. Unskilled Laborer 4 1.00 52.23 208.92
Sub - Total for A.1 - As Submitted 370.21
Labor
a. Construction Foreman
A.2 b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment
B.1
a. One Bagger Mixer 1 1.00 172.00 172.00
Minor Tools (10% of labor cost) 37.02
Sub - Total for B.1 - As Submitted 209.02
Equipment
a. One Bagger Mixer
B.2
Minor Tools (10% of labor cost)
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 579.23
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 0.270
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 2,145.30
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Materials
a. Gravel m3 1.00 600.00 600.00
b. Sand m3 0.50 500.00 250.00
F.1
c. Portland Cement bags 9.10 250.00 2,275.00
F.2
Item No. / Description : 900(1)c6 - Structural Concrete for Beams (Class A, 28 days)
Unit of Measurement : m3
Output per hour - As Submitted : 0.270
Output per hour - As Evaluated : 0.270
Labor
A.1 a. Construction Foreman December 31, 1899 1.00 65.55 65.55
b. Skilled Laborer December 31, 1899 1.00 47.62 47.62
c. Unskilled Laborer January 3, 1900 1.00 36.75 146.98
Sub - Total for A.1 - As Submitted 260.15
Labor
a. Construction Foreman
A.2 b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment
B.1
a. One Bagger Mixer December 31, 1899 1.00 156.00 156.00
Minor Tools (10% of labor cost) 26.01
Sub - Total for B.1 - As Submitted 182.01
Equipment
a. One Bagger Mixer
B.2
Minor Tools (10% of labor cost)
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 442.16
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 0.270
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 1,637.64
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Materials
a. Gravel m3 1.00 600.00 600.00
b. Sand m3 0.50 500.00 250.00
F.1
c. Portland Cement bags 10.00 240.00 2,400.00
F.2
Labor
A.1 a. Construction Foreman 1 1.00 93.62 93.62
b. Skilled Laborer 3 1.00 67.67 203.01
c. Unskilled Laborer 12 1.00 52.23 626.76
Sub - Total for A.1 - As Submitted 923.39
Labor
a. Construction Foreman
A.2 b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment
B.1 a. Bar Cutter 1 0.50 219.75 109.88
b. Bar Bender 1 0.50 351.50 175.75
Minor Tools (10% of labor cost) 92.34
Sub - Total for B.1 - As Submitted 377.96
Equipment
a. Bar Cutter
B.2 b. Bar Bender
Minor Tools (10% of labor cost)
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 1,301.35
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 143.438
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 9.07
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Materials
a. Deformed Reinforcing Steel, Grade 40 kg. 1.00 40.00 40.00
b. #16 Galvanized Iron Wire kg. 0.02 75.00 1.13
F.1
c. Consumables (5% of Materials Cost) 2.06
F.2
Unit of Measurement : m2
Output per hour - As Submitted : 3.240
Output per hour - As Evaluated : 3.240
Labor
Installation
a. Construction Foreman 1 1.00 93.62 93.62
A.1 b. Skilled Laborer 2 1.00 67.67 135.34
c. Unskilled Laborer 4 1.00 52.23 208.92
Stripping -
a. Construction Foreman 1 0.41 93.62 38.38
c. Unskilled Laborer 6 0.41 52.23 128.49
Sub - Total for A.1 - As Submitted 604.75
Labor
Installation
a. Construction Foreman
b. Skilled Laborer
A.2 c. Unskilled Laborer
Stripping
a. Construction Foreman
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of labor cost) 60.48
Sub - Total for B.1 - As Submitted 60.48
Equipment
B.2 Minor Tools (10% of labor cost)
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 665.23
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 3.240
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 205.32
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Materials
a. Ordinary Plywood - 3 uses pcs 0.347 315.00 36.44
F.1
b. Good Lumber - 3 uses Bd. Ft. 7.190 48.00 115.04
c. Assorted Common Wire Nails kg. 0.210 65.00 13.65
d. Consumables (5% of Materials Cost) 8.26
Sub - Total for F.1 - As Submitted 173.38
Materials
a. Ordinary Plywood - 3 uses
b. Good Lumber - 3 uses
F.2
c. Assorted Common Wire Nails
d. Consumables (5% of Materials Cost)
Sub - Total for F.2 - As Evaluated
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 378.70
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% 56.80
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated
I.1 Contractor's Profit (CP) - As Submitted 10% 37.87
I.2 Contractor's Profit (CP) - As Evaluated
J.1 Value Added Tax (VAT) - As Submitted 5% 23.67
J.2 Value Added Tax (VAT) - As Evaluated
K.1 Total Unit Cost - As Submitted 497.04
K.2 Total Unit Cost - As Evaluated
Labor
A.1 a. Construction Foreman December 31, 1899 1.00 65.55 65.55
b. Skilled Laborer December 31, 1899 1.00 47.62 47.62
c. Unskilled Laborer January 1, 1900 1.00 36.75 73.49
Sub - Total for A.1 - As Submitted 186.66
Labor
a. Construction Foreman
A.2 b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment
B.1
Minor Tools (10% of labor cost) 18.67
Materials
a. Soil Poisoning liters 1.000 320.00 320.00
F.1
F.2
Unit of Measurement : m2
Output per hour - As Submitted : 1.000
Output per hour - As Evaluated : 1.000
Labor
A.1 a. Construction Foreman December 31, 1899 1.00 65.55 65.55
b. Skilled Laborer December 31, 1899 1.00 47.62 47.62
c. Unskilled Laborer December 31, 1899 1.00 36.75 36.75
Sub - Total for A.1 - As Submitted 149.91
Labor
a. Construction Foreman
A.2 b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of labor cost) 14.99
Sub - Total for B.1 - As Submitted 14.99
Equipment
B.2
Materials
a. Panel door m2 1.000 2,500.00 2,500.00
F.1
F.2
Item No. / Description : 1010(1) - Frames (Jambs, Sill, Head, Transoms and Mullions)
Labor
A.1 a. Construction Foreman December 31, 1899 2.00 65.55 131.09
b. Skilled Laborer December 31, 1899 2.00 47.62 95.25
c. Unskilled Laborer December 31, 1899 2.00 36.75 73.49
Sub - Total for A.1 - As Submitted 299.83
Labor
a. Construction Foreman
A.2 b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of labor cost) 29.98
Sub - Total for B.1 - As Submitted 29.98
Equipment
B.2
Materials
a. Door Jambs set 1.000 2,000.00 2,000.00
b. Consumables (5% of Materials Cost) 100.00
F.1
F.2
Unit of Measurement : m2
Output per hour - As Submitted : 1.600
Output per hour - As Evaluated : 1.600
Labor
A.1 a. Construction Foreman December 31, 1899 1.00 65.55 65.55
b. Skilled Laborer December 31, 1899 1.00 47.62 47.62
c. Unskilled Laborer January 1, 1900 1.00 36.75 73.49
Sub - Total for A.1 - As Submitted 186.66
Labor
a. Construction Foreman
A.2 b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of labor cost) 18.67
Sub - Total for B.1 - As Submitted 18.67
Equipment
B.2
Materials
a. 12 mm x 12 mm square bar kg. 12.560 52.00 653.12
b. 25 x 4 mm flat bar kg. 2.080 52.00 108.16
F.1
c. Metal Paint gal. 0.100 550.00 55.00
d. Consumables (3% of Materials Cost) 24.49
Unit of Measurement : m2
Output per hour - As Submitted : 1.600
Output per hour - As Evaluated : 1.600
Labor
A.1 a. Construction Foreman December 31, 1899 1.00 65.55 65.55
b. Skilled Laborer December 31, 1899 1.00 47.62 47.62
c. Unskilled Laborer December 31, 1899 1.00 36.75 36.75
Sub - Total for A.1 - As Submitted 149.91
Labor
a. Construction Foreman
A.2 b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of labor cost) 14.99
Sub - Total for B.1 - As Submitted 14.99
Equipment
B.2
Materials
a. Jalousie Window (Glass) m2 1.000 1,700.00 1,700.00
F.1
d. Consumables (3% of Materials Cost) 51.00
Labor
A.1 (Labor cost for these items are to be considered/included in the installation of doors, windows, and other fabricated materials.)
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of labor cost) -
Sub - Total for B.1 - As Submitted -
Equipment
B.2
Materials
a. Lockset (Lever Type) set 1.000 1,200.00 1,200.00
F.1
F.2
Labor
A.1 (Labor cost for these items are to be considered/included in the installation of doors, windows, and other fabricated materials.)
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of labor cost) -
Sub - Total for B.1 - As Submitted -
Equipment
B.2
Materials
a. Hinges set 1.000 65.00 65.00
F.1
F.2
Labor
A.1 a. Construction Foreman December 31, 1899 6.00 65.55 393.27
b. Skilled Laborer December 31, 1899 8.00 47.62 380.99
c. Unskilled Laborer December 31, 1899 8.00 36.75 293.96
Sub - Total for A.1 - As Submitted 1,068.22
Labor
A.2
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of labor cost) 106.82
Sub - Total for B.1 - As Submitted 106.82
Equipment
B.2
Materials
a. Blackboard sets 2.000 3,100.00 6,200.00
F.1
F.2
Item No. / Description : 1046(2)a1 - 100mm CHB Non-Load Bearing(Incldg. Reinforced Steel)
Unit of Measurement : m²
Output per hour - As Submitted : 3.825
Output per hour - As Evaluated : 3.825
Labor
A.1 a. Construction Foreman 1 1.00 93.62 93.62
b. Skilled Laborer 2 1.00 67.67 135.34
c. Unskilled Laborer 3 1.00 52.23 156.69
Sub - Total for A.1 - As Submitted 385.65
Labor
A.2
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment
B.1
a. One-bagger mixer 1 1.00 172.00 172.00
Minor Tools (10% of labor cost) 38.57
Sub - Total for B.1 - As Submitted 210.57
Equipment
B.2
Materials
a. 100 mm thk CHB (Non - Load Bearing) pc. 13.000 10.00 130.00
b. Cement bag 0.525 250.00 131.25
F.1
c. Sand m3 0.040 500.00 20.00
d. Reinforcing Steel
kgs. 3.24 40.00 129.60
e. #16 Tie wire kg. 0.05 75.00 3.75
F.2
Unit of Measurement : m2
Output per hour - As Submitted : 1.120
Output per hour - As Evaluated : 1.120
Labor
A.1 a. Construction Foreman December 31, 1899 1.00 65.55 65.55
b. Skilled Laborer January 1, 1900 1.00 47.62 95.25
c. Unskilled Laborer January 1, 1900 1.00 36.75 73.49
Sub - Total for A.1 - As Submitted 234.28
Labor
A.2
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment
B.1
Tile cutter December 31, 1899 1.00 January 17, 1900 18.75
Minor Tools (10% of labor cost) 23.43
Sub - Total for B.1 - As Submitted 42.18
Equipment
B.2
Materials
a. Granite Floor Tiles, 0.60m x 0.60m (Glazed) sq.m. 1.000 740.00 740.00
F.1
b. Portland Cement bag 1.00 240.00 240.00
c. White Cement, Tile Trim & etc…(L.S.) 165.00
F.2
Item No. / Description : 1021(1)c - Plain Cement Floor Finish with Floor Hardener
Unit of Measurement : m2
Output per hour - As Submitted : 5.950
Output per hour - As Evaluated : 5.950
Labor
A.1 a. Construction Foreman December 31, 1899 1.00 65.55 65.55
b. Skilled Laborer December 31, 1899 1.00 47.62 47.62
c. Unskilled Laborer January 2, 1900 1.00 36.75 110.24
Sub - Total for A.1 - As Submitted 223.40
Labor
A.2
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of labor cost) 22.34
Sub - Total for B.1 - As Submitted 22.34
Equipment
B.2
Materials
a. Cement bag 0.726 240.00 174.24
F.1
b. Sand m3 0.06 500.00 27.50
c. Floor Hardener bag 0.05 250.00 12.50
F.2
Item No. / Description : 1046(2)a2 - 150mm CHB Non-Load Bearing(Incldg. Reinforced Steel)
Unit of Measurement : m2
Output per hour - As Submitted : 3.180
Output per hour - As Evaluated : 3.180
Labor
A.1 a. Construction Foreman December 31, 1899 1.00 65.55 65.55
b. Skilled Laborer January 1, 1900 1.00 47.62 95.25
c. Unskilled Laborer January 2, 1900 1.00 36.75 110.24
Sub - Total for A.1 - As Submitted 271.03
Labor
a. Construction Foreman
A.2 b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment
B.1
a. One-bagger mixer December 31, 1899 1.00 172.00 172.00
Minor Tools (10% of labor cost) 27.10
Sub - Total for B.1 - As Submitted 199.10
Equipment
a. One-bagger mixer
B.2
Materials
a. 150 mm thk CHB (Non - Load Bearing) pc. 12.500 12.00 150.00
b. Cement bag 1.400 240.00 336.00
F.1
c. Sand m3 0.040 500.00 20.00
d. Reinforcing Steel
kgs. 3.24 37.00 119.88
e. #16 Tie wire kg. 0.05 75.00 3.75
Unit of Measurement : m²
Output per hour - As Submitted : 7.125
Output per hour - As Evaluated : 7.125
Labor
A.1 a. Construction Foreman 1 1.00 93.62 93.62
b. Skilled Laborer 2 1.00 67.67 135.34
c. Unskilled Laborer 4 1.00 52.23 208.92
Sub - Total for A.1 - As Submitted 437.88
Labor
A.2
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of labor cost) 43.79
Sub - Total for B.1 - As Submitted 43.79
Equipment
B.2
Materials
a. Cement bag 0.330 250.00 82.50
F.1
b. Sand m3 0.027 500.00 13.50
F.2
Unit of Measurement : m2
Output per hour - As Submitted : 1.950
Output per hour - As Evaluated :
Labor
A.1 a. Construction Foreman 1 1.00 93.62 93.62
b. Skilled Laborer 5 1.00 67.67 338.35
c. Unskilled Laborer 5 1.00 52.23 261.15
Sub - Total for A.1 - As Submitted 693.12
Labor
a. Construction Foreman
A.2 b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of labor cost) 69.31
Sub - Total for B.1 - As Submitted 69.31
Equipment
B.2
Materials
a. Decorative Stone sq.m. 1.050 1200.00 1,260.00
b. Cement bag 0.325 250.00 81.25
F.1
c. Sand cu.m. 0.026 500.00 13.00
d. Tile Grout bag 0.125 70.00 8.75
Labor
A.1 a. Construction Foreman 1 12.38 93.62 1,158.55
b. Skilled Laborer 2 24.75 67.67 3,349.67
c. Unskilled Laborer 4 24.75 52.23 5,170.77
Sub - Total for A.1 - As Submitted 9,678.98
Labor
A.2
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment
B.1 a. Welding Machine 1 24.75 391.00 9,677.25
b. Cutting Outfit 1 6.19 45.45 281.22
Minor Tools (10% of labor cost) 967.90
Sub - Total for B.1 - As Submitted 10,926.37
Equipment
a. Welding Machine
B.2 b. Cutting Outfit
Minor Tools (10% of labor cost)
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 20,605.35
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 1.000
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 20,605.35
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Materials
F.1 Metal Tube - 50mm x 75 mm x 6.0m (0.9mm thick) pcs. 52.00 580.00 30,160.00
Welding Rod pcs. 4.68 120.00 561.60
Consumables (5% of material cost) 1,536.08
Sub - Total for F.1 - As Submitted 32,257.68
Materials
F.2
Unit of Measurement : m2
Output per hour - As Submitted : 5.560
Output per hour - As Evaluated :
Labor
A.1 a. Construction Foreman 1 1.00 93.62 93.62
b. Skilled Laborer 1 1.00 67.67 67.67
c. Unskilled Laborer 2 1.00 52.23 104.46
Sub - Total for A.1 - As Submitted 265.75
Labor
A.2
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of labor cost) 26.58
Sub - Total for B.1 - As Submitted 26.58
Equipment
B.2
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 292.33
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 5.560
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 52.58
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Materials
F.1
a. Reflective Insulation, 10 mm thk m2 1.00 135.00 135.00
b. Consumbles (5% of Materials Cost) 6.75
Sub - Total for F.1 - As Submitted 141.75
Materials
F.2
Sub - Total for F.2 - As Evaluated
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 194.33
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% 29.15
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated
I.1 Contractor's Profit (CP) - As Submitted 10% 19.43
I.2 Contractor's Profit (CP) - As Evaluated
J.1 Value Added Tax (VAT) - As Submitted 5% 12.15
J.2 Value Added Tax (VAT) - As Evaluated
K.1 Total Unit Cost - As Submitted 255.05
K.2 Total Unit Cost - As Evaluated
Unit of Measurement : m
Output per hour - As Submitted : 6.255
Output per hour - As Evaluated : 6.255
Labor
A.1 a. Construction Foreman 1 1.00 93.62 93.62
b. Skilled Laborer 1 1.00 67.67 67.67
c. Unskilled Laborer 2 1.00 52.23 104.46
Sub - Total for A.1 - As Submitted 265.75
Labor
A.2
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment
B.1 a. Welding Machine 1 0.75 391.00 293.25
b. Cutting Outfit 1 0.25 45.45 11.36
Minor Tools (10% of labor cost) 26.58
Sub - Total for B.1 - As Submitted 331.19
Equipment
a. Welding Machine
B.2 b. Cutting Outfit
Minor Tools (10% of labor cost)
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 596.94
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 6.255
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 95.43
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Materials
a. 38 mm Ø G.I. Pipe pc. 0.330 1,050.00 346.50
F.1
b. Welding Rod pcs. 0.02 105.00 1.58
c. Consumables (5% of material cost) 17.40
F.2
Item No. / Description : 1003(1) - 4.5mm Fiber Cement Board on Metal Frame Ceiling
Unit of Measurement : m2
Output per hour - As Submitted : 1.243
Output per hour - As Evaluated : 1.243
Labor
A.1 a. Construction Foreman December 31, 1899 1.00 65.55 65.55
b. Skilled Laborer December 31, 1899 1.00 47.62 47.62
c. Unskilled Laborer January 1, 1900 1.00 36.75 73.49
Sub - Total for A.1 - As Submitted 186.66
Labor
a. Construction Foreman
A.2 b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of labor cost) 18.67
Sub - Total for B.1 - As Submitted 18.67
Equipment
B.2 Minor Tools (10% of labor cost)
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 205.32
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 1.243
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 165.18
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Materials
a. 4.5mm Fiber Cement Board pc. 0.365 450.00 164.25
b. Metal Furring pc. 1.131 130.00 147.03
and specifications
c. Carrying ) 3m length
Channels pc. 0.357 150.00 53.55
F.1
d. Hanger Bars/Rod pc. 1.00 80.00 80.00
e. Channel clip pc. 6.00 20.00 120.00
f. Wall Angle pc. 0.24 100.00 23.80
g. Rivets pc. 14.00 1.50 21.00
h. 1" Metal Screw pc. 4.00 3.00 12.00
Sub - Total for F.1 - As Submitted 621.63
Materials
a. 4.5mm Fiber Cement Board
b. Metal Furring
and specifications ) 3m length
c. Carrying Channels
d. Hanger Bars/Rod
F.2
e. Channel clip
f. Wall Angle
g. Rivets
h. 1" Metal Screw
Sub - Total for F.2 - As Evaluated
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 786.81
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% 118.02
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated
I.1 Contractor's Profit (CP) - As Submitted 10% 78.68
I.2 Contractor's Profit (CP) - As Evaluated
J.1 Value Added Tax (VAT) - As Submitted 5% 49.18
J.2 Value Added Tax (VAT) - As Evaluated
K.1 Total Unit Cost - As Submitted 1,032.69
K.2 Total Unit Cost - As Evaluated
Unit of Measurement : m2
Output per hour - As Submitted : 5.560
Output per hour - As Evaluated : 5.560
Labor
A.1 a. Construction Foreman December 31, 1899 1.00 65.55 65.55
b. Skilled Laborer December 31, 1899 1.00 47.62 47.62
c. Unskilled Laborer January 1, 1900 1.00 36.75 73.49
Sub - Total for A.1 - As Submitted 186.66
Labor
a. Construction Foreman
A.2 b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of labor cost) 18.67
Sub - Total for B.1 - As Submitted 18.67
Equipment
B.2 Minor Tools (10% of labor cost)
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 205.32
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 5.560
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 36.93
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Materials
a. Reflective Insulation, 10 mm thk m2 1.000 135.00 135.00
b. Consumbles (5% of Materials Cost) 6.75
F.1
F.2
Unit of Measurement : m²
Output per hour - As Submitted : 2.100
Output per hour - As Evaluated : 2.100
Labor
A.1 a. Construction Foreman 1 1.00 93.62 93.62
b. Skilled Laborer 2 1.00 67.67 135.34
c. Unskilled Laborer 1 1.00 52.23 52.23
Sub - Total for A.1 - As Submitted 281.19
Labor
a. Construction Foreman
A.2 b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of labor cost) 28.12
Sub - Total for B.1 - As Submitted 28.12
Equipment
B.2 Minor Tools (10% of labor cost)
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 309.31
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 2.100
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 147.29
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Materials
a. Concrete Neutralizer gal. 0.020 227.12 4.54
b. Concrete Sealer/Primer gal. 0.040 300.00 12.00
c. Patching Compound gal. 0.050 320.00 16.00
F.1
d. Semi Gloss Latex (two coats) gal. 0.080 480.00 38.40
e. Consumables (5% of Materials Cost) 3.55
Unit of Measurement : m2
Output per hour - As Submitted : 1.890
Output per hour - As Evaluated : 1.890
Labor
A.1 a. Construction Foreman December 31, 1899 1.00 65.55 65.55
b. Skilled Laborer January 1, 1900 1.00 47.62 95.25
c. Unskilled Laborer December 31, 1899 1.00 36.75 36.75
Sub - Total for A.1 - As Submitted 197.54
Labor
a. Construction Foreman
A.2 b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of labor cost) 19.75
Sub - Total for B.1 - As Submitted 19.75
Equipment
B.2 Minor Tools (10% of labor cost)
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 217.29
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 1.890
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 114.97
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Materials
a. Glazzing Putty gal. 0.050 492.00 24.60
b. Flat Wall Enamel gal. 0.082 480.00 39.36
c. Enamel Quick Dry gal. 0.082 600.00 49.20
F.1
d. Paint Thinner liter 0.040 260.00 10.40
e. Tinting Color (Optional) pint 0.010 135.00 1.35
f. Consumables (5% of Materials Cost) 6.25
Unit of Measurement : m²
Output per hour - As Submitted : 2.000
Output per hour - As Evaluated : 2.000
Labor
A.1 a. Construction Foreman 1 1.00 93.62 93.62
b. Skilled Laborer 2 1.00 67.67 135.34
c. Unskilled Laborer 1 1.00 52.23 52.23
Sub - Total for A.1 - As Submitted 281.19
Labor
a. Construction Foreman
A.2 b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of labor cost) 28.12
Sub - Total for B.1 - As Submitted 28.12
Equipment
B.2 Minor Tools (10% of labor cost)
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 309.31
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 2.000
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 154.65
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Materials
a. Red Oxide Primer gal. 0.040 625.00 25.00
b. Enamel Paint gal. 0.100 600.00 60.00
c. Paint thinner liter 0.250 200.00 50.00
F.1
d. Tinting Color (Optional) pint 0.010 135.00 1.35
e. Consumables (5% of Materials Cost) 6.82
Item No. / Description : 1014(1)b2 - Prepainted Metal Sheets ( Long Span,Rib-Type,0.427mm thk)
Unit of Measurement : m²
Output per hour - As Submitted : 2.769
Output per hour - As Evaluated : 2.769
Labor
A.1 a. Construction Foreman 1 1.00 93.62 93.62
b. Skilled Laborer 1 1.00 67.67 67.67
c. Unskilled Laborer 2 1.00 52.23 104.46
Sub - Total for A.1 - As Submitted 265.75
Labor
a. Construction Foreman
A.2 b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of labor cost) 26.58
Sub - Total for B.1 - As Submitted 26.58
Equipment
B.2 Minor Tools (10% of labor cost)
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 292.33
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 2.769
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 105.57
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Materials
a. Prepainted Metal Sheets ( Long Span, 0.427mm thk) m2 1.000 370.00 370.00
b. Tekscrew/J-bolt with washers pc. 10.000 2.50 25.00
c. Consumables (3% of Materials Cost) 11.85
F.1
F.2
Item No. / Description : 1013(2)a1 - Fabricated Metal Roofing Accessory (Ridge Roll/Hip); (gauge 26)
Labor
A.1 a. Construction Foreman 1 1.00 93.62 93.62
b. Skilled Laborer 1 1.00 67.67 67.67
c. Unskilled Laborer 1 1.00 52.23 52.23
Sub - Total for A.1 - As Submitted 213.52
Labor
a. Construction Foreman
A.2 b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of labor cost) 21.35
Sub - Total for B.1 - As Submitted 21.35
Equipment
B.2 Minor Tools (10% of labor cost)
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 234.87
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 10.000
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 23.49
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Materials
a. Ridge Roll m 1.050 168.00 176.40
b. Blind Rivets pc. 19.000 1.50 28.50
c. Consumables (3% of Materials Cost) 6.15
F.1
F.2
Item No. / Description : 1013(2)a2 - Fabricated Metal Roofing Accessory (Flashings); (gauge 26)
Labor
A.1 a. Construction Foreman 1 1.00 93.62 93.62
b. Skilled Laborer 1 1.00 67.67 67.67
c. Unskilled Laborer 1 1.00 52.23 52.23
Sub - Total for A.1 - As Submitted 213.52
Labor
a. Construction Foreman
A.2 b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of labor cost) 21.35
Sub - Total for B.1 - As Submitted 21.35
Equipment
B.2 Minor Tools (10% of labor cost)
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 234.87
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 10.000
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 23.49
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Materials
a. Pre-Painted Plain Sheet (Flashing), 0.80m. x 2.44m. x 0.40mm. m 1.05 168.00 176.40
b. Blind Rivets pcs. 19.00 1.50 28.50
c. Consumables (3% of Materials Cost) 6.15
F.1
F.2
Item No. / Description : 1013(2)b1 - Fabricated Metal Roofing Accessory (Gutters); (gauge 24)
Labor
A.1 a. Construction Foreman 1 1.00 93.62 93.62
b. Skilled Laborer 1 1.00 67.67 67.67
c. Unskilled Laborer 1 1.00 52.23 52.23
Sub - Total for A.1 - As Submitted 213.52
Labor
a. Construction Foreman
A.2 b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of labor cost) 21.35
Sub - Total for B.1 - As Submitted 21.35
Equipment
B.2 Minor Tools (10% of labor cost)
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 234.87
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 11.800
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 19.90
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Materials
a. Pre-Painted Gutter, 0.457m. x 2.44m. x 0.40mm. m 1.00 168.00 168.00
b.12" x 1" Plain GI Strap pcs. 3.00 50.00 150.00
c. Blind Rivets pcs. 16.00 1.50 24.00
F.1
d. Consumables (3% of Materials Cost) 10.26
F.2
Labor
Fabrication:
a. Construction Foreman 1 1.00 93.62 93.62
A.1 b. Skilled Laborer 2 1.00 67.67 135.34
c. Unskilled Laborer 2 1.00 52.23 104.46
Erection:
a. Skilled Laborer 3 0.49 67.67 99.47
b. Unskilled Laborer 3 0.49 52.23 76.78
Sub - Total for A.1 - As Submitted 509.67
Labor
Fabrication:
a. Construction Foreman
a. Skilled Laborer
b. Unskilled Laborer
A.2
Sub - Total for A.1 - As Submitted
Erection:
a. Skilled Laborer
b. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment
a. Welding Machine 1 0.750 391.00 293.25
B.1
b. Cutting Outfit 1 0.250 45.45 11.36
c. Truck Mounted Crane (20-25 mt) 1 0.49 1,631.00 799.19
Minor Tools (10% of labor cost) 50.97
Sub - Total for B.1 - As Submitted 1,154.77
Equipment
a. Welding Machine
B.2 b. Cutting Outfit
Minor Tools (10% of labor cost)
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 1,664.44
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 85.000
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 19.58
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Materials
a. Structural Steel Truss kg. 1.000 52.00 52.00
F.1 b. Acetylene kg. 0.011 65.00 0.72
c. Oxygen kg. 0.022 45.00 0.99
d. Welding Rod kg. 0.020 120.00 2.40
e. Consumables (5% of Materials Cost) 2.81
Sub - Total for F.1 - As Submitted 58.91
Materials
a. Structural Steel Truss
b. Acetylene
F.2 c. Oxygen
d. Welding Rod
e. Consumables (5% of Materials Cost)
Sub - Total for F.2 - As Evaluated
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 78.49
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% 11.77
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated
I.1 Contractor's Profit (CP) - As Submitted 10% 7.85
I.2 Contractor's Profit (CP) - As Evaluated
J.1 Value Added Tax (VAT) - As Submitted 5% 4.91
J.2 Value Added Tax (VAT) - As Evaluated
K.1 Total Unit Cost - As Submitted 103.02
K.2 Total Unit Cost - As Evaluated
Prepared by: Checked/Reviewed by:
Labor
Fabrication:
A.1
a. Construction Foreman 1 1.00 93.62 93.62
b. Skilled Laborer 2 1.00 67.67 135.34
c. Unskilled Laborer 4 1.00 52.23 208.92
Sub - Total for A.1 - As Submitted 437.88
Labor
Fabrication:
a. Construction Foreman
A.2
b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment
B.1
a. Welding Machine 2 1.000 391.00 782.00
Minor Tools (10% of labor cost) 43.79
Sub - Total for B.1 - As Submitted 825.79
Equipment
a. Welding Machine
B.2
Minor Tools (10% of labor cost)
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 1,263.67
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 90.450
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 13.97
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Materials
a. Structural Steel Purlins kg. 1.050 52.00 54.60
b. Welding Rod kg. 0.020 120.00 2.40
F.1
c. Consumables (5% of Materials Cost) 2.73
Labor
Fabrication:
A.1
a. Construction Foreman 1 1.00 93.62 93.62
b. Skilled Laborer 1 1.00 67.67 67.67
c. Unskilled Laborer 1 1.00 52.23 52.23
Sub - Total for A.1 - As Submitted 213.52
Labor
Fabrication:
a. Construction Foreman
A.2
b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of labor cost) 21.35
Sub - Total for B.1 - As Submitted 21.35
Equipment
B.2 Minor Tools (10% of labor cost)
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 234.87
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 12.995
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 18.07
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Materials
a. Steel Plates kg. 1.050 52.00 54.60
F.1 b. Consumables (3% of Materials Cost) 1.64
F.2
Labor
Fabrication:
A.1
a. Construction Foreman 1 0.10 93.62 9.36
b. Skilled Laborer 1 0.10 67.67 6.77
c. Unskilled Laborer 1 0.10 52.23 5.22
Sub - Total for A.1 - As Submitted 21.35
Labor
Fabrication:
a. Construction Foreman
A.2
b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of labor cost) 2.14
Sub - Total for B.1 - As Submitted 2.14
Equipment
B.2 Minor Tools (10% of labor cost)
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 23.49
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 1.000
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 23.49
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Materials
a. Bolts kgs. 1.000 132.67 132.67
F.1
F.2
Labor
Fabrication:
A.1
a. Construction Foreman 1 0.10 93.62 9.36
b. Skilled Laborer 1 0.10 67.67 6.77
c. Unskilled Laborer 1 0.10 52.23 5.22
Sub - Total for A.1 - As Submitted 21.35
Labor
Fabrication:
a. Construction Foreman
A.2
b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of labor cost) 2.14
Sub - Total for B.1 - As Submitted 2.14
Equipment
B.2 Minor Tools (10% of labor cost)
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 23.49
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 1.000
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 23.49
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Materials
a. Sagrod with nuts and bolts kg. 1.000 213.08 213.08
F.1
F.2
Labor
Fabrication:
A.1
a. Construction Foreman 1 1.00 93.62 93.62
b. Skilled Laborer 1 1.00 67.67 67.67
c. Unskilled Laborer 1 1.00 52.23 52.23
Sub - Total for A.1 - As Submitted 213.52
Labor
Fabrication:
a. Construction Foreman
A.2
b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of labor cost) 21.35
Sub - Total for B.1 - As Submitted 21.35
Equipment
B.2 Minor Tools (10% of labor cost)
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 234.87
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 12.995
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 18.07
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Materials
a. Crossbracing kg. 1.050 40.00 42.00
F.1 b. Consumables (3% of Materials Cost) 1.26
F.2
Labor
Fabrication:
A.1
a. Construction Foreman 1 0.15 93.62 14.04
b. Skilled Laborer 1 0.15 67.67 10.15
c. Unskilled Laborer 1 0.15 52.23 7.83
Sub - Total for A.1 - As Submitted 32.03
Labor
Fabrication:
a. Construction Foreman
A.2
b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of labor cost) 3.20
Sub - Total for B.1 - As Submitted 3.20
Equipment
B.2 Minor Tools (10% of labor cost)
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 35.23
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 1.000
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 35.23
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Materials
a. Standard Turnbuckle kg. 1.000 185.00 185.00
F.1
F.2
Labor
Fabrication:
A.1
a. Construction Foreman 1 17.01 93.62 1,592.26
b. Skilled Laborer 2 17.01 67.67 2,301.83
c. Unskilled Laborer 2 17.01 52.23 1,776.63
Sub - Total for A.1 - As Submitted 5,670.72
Labor
Fabrication:
a. Construction Foreman
A.2
b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of labor cost) 567.07
Sub - Total for B.1 - As Submitted 567.07
Equipment
B.2 Minor Tools (10% of labor cost)
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 6,237.79
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 1.000
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 6,237.79
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Materials
a. PVC Pipe, 75mm Ø x 3m, S-1000 pcs 24.00 434.00 10,416.00
F.1 b. PVC Elbow, 75mm Ø x 45 deg. Bend pcs 24.00 38.00 912.00
c. PVC Solvent, 400cc cans 5.00 190.00 950.00
d. Roof Drain (Dome-Type Strainer) pcs 12.00 350.00 4,200.00
Labor
Fabrication:
A.1
a. Construction Foreman 1 20.00 93.62 1,872.40
b. Skilled Laborer 1 20.00 67.67 1,353.40
c. Unskilled Laborer 1 20.00 52.23 1,044.60
Sub - Total for A.1 - As Submitted 4,270.40
Labor
Fabrication:
a. Construction Foreman
A.2
b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of labor cost) 427.04
Sub - Total for B.1 - As Submitted 427.04
Equipment
B.2 Minor Tools (10% of labor cost)
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 4,697.44
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 1.000
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 4,697.44
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Materials
a. Utility Box # 4" x 2" deep type (PVC type) pcs 7.000 30.00 210.00
b. Junction Box # 4" x 4" deep type (PVC type) w/ cover pcs 14.000 37.00 518.00
c. PVC Pipe # ½"Ø pcs 50.000 69.00 3,450.00
d. PVC Pipe # 3/4"Ø pcs 5.000 92.00 460.00
F.1 e. PVC Clamp # ½"Ø pcs 32.000 3.00 96.00
f. PVC Clamp # 3/4"Ø pcs 5.00 10.00 50.00
g. PVC Adapter # 3/4"Ø pcs 2.00 25.00 50.00
h. PVC Long radius elbow # ½"Ø pcs 14.00 15.00 210.00
i. PVC solvent cement (medium) can 2.00 120.00 240.00
j. Entrance Cap # 3/4"Ø set 1.00 100.00 100.00
k. Secondary Rock 2 point ball insulator w/ machine bolts & nuts (Heavy Duty) set 1.00 400.00 400.00
Sub - Total for F.1 - As Submitted 5,784.00
Materials
a. Utility Box # 4" x 2" deep type (PVC type)
b. Junction Box # 4" x 4" deep type (PVC type) w/ cover
F.2
c. PVC Pipe # ½"Ø
Labor
Fabrication:
A.1
a. Construction Foreman 1 12.00 93.62 1,123.44
b. Skilled Laborer 2 12.00 67.67 1,624.08
c. Unskilled Laborer 2 12.00 52.23 1,253.52
Sub - Total for A.1 - As Submitted 4,001.04
Labor
Fabrication:
a. Construction Foreman
A.2
b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of labor cost) 400.10
Sub - Total for B.1 - As Submitted 400.10
Equipment
B.2 Minor Tools (10% of labor cost)
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 4,401.14
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 1.000
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 4,401.14
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Materials
a. Light Switch, 2 - Gang sets 1.000 126.00 126.00
b. Light Switch, 3 - Gang sets 2.000 170.00 340.00
c. Duplex Convenience Outlet sets 4.000 120.00 480.00
F.1
d. Copper Wire # 3.5mm² THHN rolls 5.000 3,500.00 17,500.00
e. Copper Wire # 8.0mm² THHN m 30.000 50.00 1,500.00
f. Electrical Tape (big) pcs 3.000 45.00 135.00
F.2
Item No. / Description : 1102(1) - Panelboard with Main & Branch Breakers
Labor
A.1 a. Construction Foreman 1 8.00 93.62 748.96
b. Skilled Laborer 2 8.00 67.67 1,082.72
c. Unskilled Laborer 2 8.00 52.23 835.68
Sub - Total for A.1 - As Submitted 2,667.36
Labor
a. Construction Foreman
A.2 b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of labor cost) 266.74
Sub - Total for B.1 - As Submitted 266.74
Equipment
B.2 Minor Tools (10% of labor cost)
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 2,934.10
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 1.000
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 2,934.10
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Materials
Ligthing Panelboard/Molded Case Air Circuit set 1.000 7,000.00 7,000.00
F.1 Breaker w/ Main 1 x 40 AT, 2P, 230 V, 1-Ø
2 x 15 AT, 2P, 230 V, 1-Ø
2 x 20 AT, 2P, 230 V, 1-Ø
+ 1 Spare ( 6 Branches )
Sub - Total for F.1 - As Submitted 7,000.00
Materials
Ligthing Panelboard/Molded Case Air Circuit
Breaker w/ Main 1 x 40 AT, 2P, 230 V, 1-Ø
2 x 15 AT, 2P, 230 V, 1-Ø
F.2
2 x 20 AT, 2P, 230 V, 1-Ø
+ 1 Spare ( 6 Branches )
Labor
Fabrication:
A.1
a. Construction Foreman 1 4.00 93.62 374.48
b. Skilled Laborer 1 4.00 67.67 270.68
c. Unskilled Laborer 1 4.00 52.23 208.92
Sub - Total for A.1 - As Submitted 854.08
Labor
Fabrication:
a. Construction Foreman
A.2
b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of labor cost) 85.41
Sub - Total for B.1 - As Submitted 85.41
Equipment
B.2 Minor Tools (10% of labor cost)
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 939.49
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 1.000
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 939.49
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Materials
F.1 a. Integrated LED Flood light, 50W set 8.000 5,000.00 40,000.00
Labor
Fabrication:
A.1
a. Construction Foreman December 31, 1899 2.00 65.55 131.09
b. Skilled Laborer December 31, 1899 8.00 47.62 380.99
c. Unskilled Laborer December 31, 1899 8.00 36.75 293.96
Sub - Total for A.1 - As Submitted 806.04
Labor
Fabrication:
a. Construction Foreman
A.2
b. Skilled Laborer
c. Unskilled Laborer
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of labor cost) 80.60
Sub - Total for B.1 - As Submitted 80.60
Equipment
B.2 Minor Tools (10% of labor cost)
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 886.64
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 1.000
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 886.64
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Materials
F.1 FACP set 1.000 7,200.00 7,200.00
F.A. manual station set 1.000 1,200.00 1,200.00
F.A. bell, vibrating type set 1.000 1,100.00 1,100.00
Sub - Total for F.1 - As Submitted 9,500.00
Materials
FACP
F.A. manual station
F.2
F.A. bell, vibrating type
Sub - Total for F.1 - As Submitted
Sub - Total for F.2 - As Evaluated
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 10,386.64
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% 1,558.00
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated
I.1 Contractor's Profit (CP) - As Submitted 10% 1,038.66
I.2 Contractor's Profit (CP) - As Evaluated
J.1 Value Added Tax (VAT) - As Submitted 5% 649.17
J.2 Value Added Tax (VAT) - As Evaluated
K.1 Total Unit Cost - As Submitted 13,632.47
K.2 Total Unit Cost - As Evaluated