1 - Precast Concrete Thesis
1 - Precast Concrete Thesis
A Thesis
presented to
the Faculty of the Graduate School
University of Missouri – Columbia
In Partial Fulfillment
of the Requirements for the Degree
Master of Science
by
GRANT C. LUCKENBILL, E.I.
July 2009
The undersigned, appointed by the Dean of the Graduate School, have examined the
thesis entitled
Master of Science
____________________________________
Dr. Vellore S. Gopalaratnam, P.E.
____________________________________
Dr. Glenn Washer, P.E.
____________________________________
Dr. Sanjeev K. Khanna
________________________________________________________________________
ACKNOWLEDGEMENTS
and Federal Highway Administration for jointly funding the project. Many dedicated
individuals from MoDOT and FHWA have demonstrated strong commitments to the
advancement of new technologies, specifically John Donahue of MoDOT and Sam Tyson
of FHWA. Without their hard work and dedication, pilot projects such as these would
not be undertaken. I would like to acknowledge the many professionals at the MoDOT
District office in Sikeston, MO who were very supportive of this project. Efforts to
accommodate the research team’s many requests from Eric Krapf and Michael Chasteen
were much appreciated. Jim Copeland took time aside to aid the research team with
surveying the pavement. Finally, from MoDOT, I would also like to acknowledge Terry
Fields, senior construction inspector, for his help with the research team.
I would also like to commend the work of the Transtec Group including David
Merritt, design engineer, for providing design expertise and an extensive background in
precast pavements. Additionally I would like to thank the professionals from Concrete
Construction Company who were very accommodating and aided the research team with
and Jimmy Davis from CPI who were very helpful with the research team during
fabrication.
I would like to thank my advisor, Dr. V.S. Gopalaratnam. Dr. Gopal has provided
________________________________________________________________________
Page ii
degree programs. His unwavering dedication has significantly contributed to my growth
as an engineering professional. I will proudly carry the lessons you have taught
I would also like to thank my parents, family, and friends for aiding in my
success. Without their support and guidance, many of these opportunities would not have
________________________________________________________________________
Page iii
TABLE OF CONTENTS
ACKNOWLEDGEMENTS ............................................................................................ II
TABLE OF CONTENTS ............................................................................................... IV
LIST OF TABLES .......................................................................................................... VI
LIST OF FIGURES .......................................................................................................VII
NOMENCLATURE / LIST OF NOTATION .............................................................XII
ABSTRACT .................................................................................................................. XIII
1. INTRODUCTION........................................................................................................1
1.1. GENERAL INFORMATION AND PROJECT SCOPE........................................1
1.1.1. PPCP Project on Interstate 57 and Experimental Investigation ...................1
1.1.2. Research Objectives .....................................................................................2
1.2. OVERVIEW OF PAVEMENT DETAILS AND CONSTRUCTION
PRACTICES ...........................................................................................................3
1.2.1. Fabrication at the Casting Yard ...................................................................4
1.2.2. Construction of Precast Pavement ...............................................................5
1.2.3. Pavement Panel Designs ..............................................................................7
1.3. ORGANIZATION OF THESIS ...........................................................................11
2. BACKGROUND INFORMATION .........................................................................13
2.1. OVERVIEW OF PPCP TECHNOLOGY ............................................................13
2.1.1. Design Considerations for PPCP ...............................................................14
2.2. PPCP PROJECTS IN THE UNITED STATES ...................................................18
2.2.1. Iowa Approach Slab on Highway 60 .........................................................19
2.2.2. Interstate 10 in El Monte, CA ....................................................................20
2.2.3. Outer Road near Interstate 35 in Georgetown, TX ....................................20
2.3. FIELD INSTRUMENTATION OF CONCRETE PROJECTS ...........................22
3. EXPERIMENTAL PROGRAM ...............................................................................25
3.1. FIELD INSTRUMENTATION ............................................................................25
3.1.1. Types of Embedded Instrumentation ........................................................25
3.1.1.1. Strain-Gage Rebar .............................................................................25
3.1.1.2. Vibrating Wire Gage .........................................................................27
3.1.1.3. Vibrating Wire Strandmeters ............................................................28
3.1.1.4. Temperature Gages ...........................................................................29
3.1.2. General Design and Placement Considerations .........................................30
3.1.3. Instrumentation Layouts ............................................................................32
________________________________________________________________________
Page iv
3.1.4. Data Acquisition System............................................................................33
3.1.5. Remote Monitoring ....................................................................................35
3.2. LABORATORY EXPERIMENTS ......................................................................36
3.2.1. Materials Testing .......................................................................................36
3.2.2. Thermal Investigation of Embedded Instrumentation ...............................37
3.3. CHALLENGES FOR REMOTE DATA ACQUISITION ...................................41
3.3.1. Excessive Heat Buildup Affecting Sensitive Hardware ............................42
3.3.2. Moisture Intrusion and Corrosion ..............................................................43
3.3.3. Lightning Protection ..................................................................................44
3.3.4. Snow Removal and Protective Plates ........................................................45
4. SERVICE PERFORMANCE OF PPCP SYSTEM ................................................47
4.1. GENERAL INFORMATION ...............................................................................47
4.2. PAVEMENT THERMAL PERFORMANCE ......................................................48
4.2.1. Temperature Variations .............................................................................48
4.2.2. Daily Thermal Loadings ............................................................................49
4.2.3. Weekly Thermal Behavior .........................................................................57
4.2.4. Seasonal Variations in Panel and Global Pavement Responses ................61
4.3. PAVEMENT RESPONSE DUE TO VEHICULAR LOADING .........................70
4.4. EFFECTIVE POST-TENSIONING STRESS DISTRIBUTIONS ......................73
4.4.1. Post-tensioning Stress Distributions affected by
Poor Transfer at Joints ...............................................................................73
4.4.2. Post-tensioning Stress Losses due to Friction ............................................76
4.5. TRANSVERSE AND LONGITUDINAL CRACKING ......................................77
4.5.1. Expert Task Group Meeting in Sikeston, MO ...........................................80
4.5.2. Visual Crack Surveys .................................................................................82
4.6. JOINT PANEL PERFORMANCE .......................................................................82
5. CONCLUSIONS ........................................................................................................87
5.1. PROJECT OBSERVATIONS ..............................................................................87
5.2. CONSTRUCTION CHALLENGES ....................................................................88
5.3. SERVICE PERFORMANCE ...............................................................................89
5.4. PAVEMENT LONGEVITY ................................................................................90
5.5. RECOMMENDATIONS FOR FUTURE WORK ...............................................90
REFERENCES .................................................................................................................92
APPENDIX A ...................................................................................................................94
APPENDIX B ...................................................................................................................95
________________________________________________________________________
Page v
LIST OF TABLES
TABLE 4.1 – INSTRUMENT LOCATIONS AND EVENT SUMMARY FOR JOINT PANEL A32
________________________________________________________________________
Page vi
LIST OF FIGURES
FIGURE 1.1 – OVERALL PPCP SECTION LAYOUT WITH DRIVING LANES SHOWN (25
FIGURE 1.2 – TYPICAL SECTION OF PPCP PANEL ASSEMBLY AND LAYOUT MODIFIED TO
FIGURE 1.3 – JOINT PANEL ON POLYPROPYLENE OVER ASPHALT, AND AGGREGATE BASE
DIRECTION ...................................................................................................8
FIGURE 1.9 – JOINT PANEL CASTING (LEFT SIDE CURED FOR 1 NIGHT, RIGHT SIDE READY
MATERIAL ..................................................................................................15
________________________________________________________________________
Page vii
FIGURE 3.1 – SCHEMATIC OF THE STRAIN GAGE CONFIGURATION ON THE STRAIN GAGE
FIGURE 3.3 – MODEL 4200 VIBRATING WIRE GAGE FROM GEOKON INCORPORATED ....27
FIGURE 3.12 – (A) TEMPERATURE HISTORY (B) STRAIN HISTORY OF EMBEDDED AND
TEMPERATURE, ΔT ...................................................................................41
________________________________________________________________________
Page viii
FIGURE 3.14 – SIGNAL CABINET PROTECTED DURING THE HEAT OF THE DAY BY A SHADE
ROOF ..........................................................................................................43
FIGURE 4.2 – ONE DAY WINDOW FROM JULY 13, 2006 FOR PANEL A32 (A)
FIGURE 4.3 – ONE DAY WINDOW FROM JULY 13, 2006 SHOWING ALL INSTRUMENTS FOR
FIGURE 4.4 – ONE DAY WINDOW FROM JULY 13, 2006 FOR PANEL B3 (A) TEMPERATURE
FIGURE 4.5 – JOINT PANEL A31 DURING MILD TEMPERATURES (LEFT) AND HOT
TEMPERATURES (RIGHT)...........................................................................56
FIGURE 4.7 – MEDIUM WINDOW INDICATING WEEKLY HEATING AND DRASTIC COLD
________________________________________________________________________
Page ix
FIGURE 4.10 – SIX MONTH WINDOW SHOWING LONGITUDINAL CONCRETE STRAINS AT
FIGURE 4.14 - TRAFFIC STRAIN (REBAR RESPONSE) IN THE PAVEMENT AT CROWN .......71
FIGURE 4.15 – DURATION OF TRAFFIC RESPONSE THAT WAS VERIFIED VISUALLY .........72
OVER ..........................................................................................................73
FIGURE 4.17 – CONCRETE STRAIN FOR A TYPICAL BASE PANEL DURING POST-
TENSIONING OPERATIONS..........................................................................75
________________________________________________________________________
Page x
FIGURE 4.20 - LONGITUDINAL CRACK IN DRIVER SIDE WHEEL LANE ..............................78
FIGURE 4.22 – TYPICAL CRACK LOCATIONS OF A 4-PANEL SET OF THE 3RD TEST
FIGURE 4.23 – FLEXIBLE JOINT COMPOUND SQUEEZING OUT ON A HOT DAY WITH
FIGURE 4.24 – RIGID JOINT COMPOUND CHIPPED AWAY MORE EXTENSIVELY, JOINT
FIGURE A.1 – ONE DAY WINDOW FROM 12/27/2006 FOR PANEL A32 (A) TEMPERATURE
________________________________________________________________________
Page xi
NOMENCLATURE / LIST OF NOTATION
T - TEMPERATURE
t - Time
ε - Strain
N. A. - Neutral Axis
E - Modulus of Elasticity
ν - Poisson’s Ratio
________________________________________________________________________
Page xii
EVALUATION OF THE SERVICE PERFORMANCE OF AN
INNOVATIVE PRECAST PRESTRESSED CONCRETE
PAVEMENT
ABSTRACT
to create a product that exceeds the performance and implementation of current pavement
traffic congestion that causes increased fuel consumption and lost productivity.
hazards pose additional risk to worker safety and construction seasons are limited. This
________________________________________________________________________
Page xiii
(extreme temperatures in summer accompanying deicing salts in winter) in addition to
The focuses of this thesis are to characterize the thermal behavior and evaluate the
cast in concrete, are presented. Analysis of results from the investigation include: (a)
construction challenges that may affect long term durability (b) local and global prestress
distributions within PPCP (c) stress losses during post-tensioning operations (frictional
and stress transfer between panels), (d) daily thermal loadings, (e) weekly and seasonal
traffic loads is presented to contrast daily thermal loadings. Visual crack surveys
(longitudinal and transverse) and joint panel performance over the year long evaluation
________________________________________________________________________
Page xiv
1. Introduction
was chosen for rehabilitation using the PPCP program. The project was completed in
December, 2005 and opened to traffic in mid January, 2006. The goal of the Missouri
environmental conditions.
The Interstate 57 project was the first large scale PPCP project undertaken in
Missouri. Sufficient right of way and funding enabled the installation of asphalt
crossovers which aided the construction of the pavement project by relieving time
constraints on constructors. In turn, this enabled constructors to experiment and work out
the most efficient methods for construction. The site in southern Missouri was also
variations. De-icing salts are commonly used on their roadways. The long-term
durability of the PPCP test section was “put to the test” with the combination of harsh
Page 1
1.1.2. Research Objectives
evaluate the performance of the PPCP subjected to severe weather and traffic conditions
and develop performance data useful for future projects. The team heavily instrumented
several panels to quantify pavement performance and validate design assumptions. Due
to the broad scope of the research goals of the overall pavement project, this thesis is
accompanied by two companion theses by Cody Dailey “Instrumentation and Early Age
System” (2006). These reports, which focus on the instrumentation, materials testing,
throughout this thesis when overlapping topics are discussed. The project report
Prestressed Concrete Pavement, RI03-007,” will also be referenced throughout this paper.
This thesis presents thermal and strain gradient data in conjunction with laboratory
PPCP. This data will be helpful in quantifying the effectiveness of PPCP as a rapid
following:
construction.
________________________________________________________________________
Page 2
o Study of daily and seasonal temperature dependent effects on the concrete
replaced a dilapidated 45 year old section of cast-in-place (CIP) concrete just west of
prestressed panels make up the PPCP system: base panels, joint panels, and anchor
panels. They are pre-tensioned in the transverse direction at the casting yard and post-
tensioned in the longitudinal direction (parallel to traffic). Each panel is 10’-0” x 38’-0”.
The 38 ft dimension is perpendicular to traffic. There is a 4’-0” inside shoulder, two 12’-
0” driving lanes and a 10’-0” outside shoulder. The panels were cast with a constant 2%
anchor panel near the middle with eleven or twelve base panels on each side with a joint
panel at both ends. These joint panels were heavily reinforced since they contained the
the 250 ft section. Figure 1.1 shows the layout of the four sections of pavement (the
highlighted section is heavily instrumented and will be discussed later in detail). Figure
________________________________________________________________________
Page 3
Figure 1.1 – Overall PPCP section layout with driving lanes shown (25 panels per
section; Section 3 is heavily instrumented)
Figure 1.2 – Typical section of PPCP panel assembly and layout modified to reflect
Missouri Project (Merritt, McCullough et al. 2000)
All 101 precast panels were fabricated by Concrete Products Incorporated (CPI)
in Memphis, TN between mid-October and December 2005. They were cast two at a
time, crown up, in self-stressing steel casting beds outdoors. The panels were pre-
tensioned in the transverse direction using 0.5” uncoated, seven-wire low relaxation
strands (270 ksi). The pre-tensioning was incorporated largely to accommodate lifting
performed after placement. After casting, the panels were steam cured overnight. This
was done to minimize shrinkage and ensure proper curing of the panels. The following
________________________________________________________________________
Page 4
morning, they were de-tensioned and de-molded provided the concrete had reached an
initial compressive strength of 3500 psi. Later they were stacked in the storage location
of the casting yard to await transportation to the site near Charleston. This single day
casting/curing/de-molding of the precast panels enabled the fabricator to turn out two
typical base panels per day. The joint panels, which were more complicated in design to
from Wentzville, MO. Typical panel placement rates were between 8 – 25 panels per
day. The base, a very critical component of pavement construction, was made up of a 4”
asphalt treated base over a 4” permeable crushed stone filter layer. A layer of
polypropylene was used as a friction reduction layer and to ease the construction of the
pavement. This friction reduction layer is critical in post-tensioned pavement where sub-
grade friction reduces the efficiency of prestressing. Figure 1.3 shows an instrumented
joint panel on top of the prepared asphalt base with polypropylene sheet clearly visible.
________________________________________________________________________
Page 5
PT Blockout
Joint Panel
Figure 1.3 – Joint panel on polypropylene over asphalt, and aggregate base
(Missouri project) (Note: Instrumentation data cable exiting the end
of the panel)
Panels were taken directly from the trucks via crane and positioned at the end of
the PPCP section. The joints between the panels were sealed with a slow-curing epoxy,
intended to ease placement and seal the joints from water intrusion. Two post-tensioning
strands (0.6 inch seven-wire low relaxation strands) were fed through and stressed lightly
to recover gaps and slack in the pavement system. However, during complications of
feeding post-tensioning strands much of the epoxy placed on the joints was allowed to
harden. This resulted in an uneven surface at the joint which impaired uniform load
hardened epoxy layer is discussed in Chapter 4. Wooden and steel shims were placed
between panels on the southern edge to aid in recovering pavement misalignment. The
usage of rigid shims resulted in uneven distribution of post-tensioning stresses across the
panels. Construction challenges such as these were mitigated during construction of the
________________________________________________________________________
Page 6
PPCP pavement. However, adjustments made during construction affected the pre-
The Transtec Group from Austin, TX designed the PPCP system consisting of
base, anchor, and joint panels. The majority of the panels (92 of 101) were made up of
Standard 60 ksi epoxy coated rebar bordered the edges of each base panel and is
not shown on the schematics. Its role was to provide typical edge reinforcement to curb
cracking and fragmentation of the corners. Each base panel contained eight pre-
tensioning strands as shown in Figure 1.4 and Figure 1.5. The pre-tensioning strands
located in the top half of the panel were draped to follow the slope of the crown and meet
heights of galvanized chairs under the strands at key locations (see Figure 1.6).
Pretensioned Strands
(8 @ 1’-3”)
38’
10’
Inside Outside
Post-Tensioning Ducts
Shoulder Shoulder
(18 @ 2’)
________________________________________________________________________
Page 7
Pre-tensioning Strands
Outside
Shoulder 7” 10 7/8”
10 -0”
Figure 1.5 – Section of base panel looking perpendicular to traffic direction
Anchor panels are similar to base panels with the addition of full depth holes near
the center. These panels are located at the midpoint of each PPCP section and anchor the
joints. Reinforcing dowels were driven into the sub grade through the 4 in diameter
blocked-out anchor sleeves and grouted. The fabrication of the anchor panels were cast
retooling, amount of reinforcement, and functional geometry of the panel, each joint
________________________________________________________________________
Page 8
panel required to be cast in two separate halves. Figure 1.7 shows a plan view of a
typical joint panel. Block-outs toward the center of the panel allow access to the post-
tensioning ducts, which were filled with grout after post-tensioning. Joint panels have 12
pre-tensioned strands instead of 8 (see Figure 1.8). The top strands are draped with the
slope of the crown while the bottom strands are straight. Each half is connected by
smooth dowels that provide shear transfer between sections (not shown in schematic). A
cold-joint between sections was accomplished by using temporary bulkhead that fastened
to the bottom of the bed. The cold-joint was needed to ensure that the joint panel
“opened up” during post-tensioning operations. Figure 1.9 shows two halves of a joint
panel, one side has cured for one night and the other is ready for casting the following
afternoon. Five total joint panels were fabricated for the 1,010 stretch of pavement. The
panels at the ends of the PPCP section were cast without post-tensioning block-outs on
one half. The side of the panels adjoining to cast-in-place concrete pavement was
Traffic Direction
10’
Inside Outside
Post-Tensioning Ducts
Shoulder Shoulder
(18 @ 2’)
Page 9
Prestressing Strands Post-tensioning Blockouts
10 7/8”
7”
10’-0”
Figure 1.8 – Section of joint panel looking perpendicular to traffic
Figure 1.9 – Joint panel casting (left side cured for 1 night, right side ready for
casting on 2nd day)
Brief overviews of the chapters contained in this thesis are presented in the
following paragraphs.
Chapter 1 describes the goals, motivation, and an overview of the design for the
Page 10
Chapter 2 provides a literary review of past concrete pavement projects.
design and placement, and analyses of the thermal behavior of embedded instrumentation
in Chapter 4. Thermal and strain gradients are presented for time windows which
________________________________________________________________________
Page 11
This page intentionally left blank.
________________________________________________________________________
Page 12
2. Background Information
pavement design in a field that has seemingly tried all of the possible permutations for
problematic areas of conventional cast in place pavement. Current design practices and
construction of precast pavement technology have largely been adapted from other
applications of prestressed and precast concrete in bridge design. The allure of PPCP
technology has benefited from decreased shipping costs and more significant political
and monetary benefits from expediting timely pavement projects in high traffic volume
areas. Although other prestressed technologies used frequently in bridge deck and
girders have proved useful in aiding with the design of PPCP, means of construction and
reliability are challenged by clients seeking to employ precast pavement. Pilot PPCP
projects have been sought by several DOT’s for experimentation to acclimate contractors
The pilot project using PPCP in Missouri was performed to address several issues
previous projects have neglected to address. The Missouri Project would evaluate the
to heavy traffic volumes. The previously completed pavement projects have been located
in milder climates where the pavement was not subjected to rapid freezing and thawing
________________________________________________________________________
Page 13
and usage of de-icing salts. The performance of PPCP in a harsh environment will serve
during off peak travel times and place the roadways back into service very rapidly.
Traffic congestion due to the presence of construction activities results in, among many
other variables, increased fuel consumption and lost work time, or user costs and safety
issues related to construction (Merritt 2001). By avoiding peak travel times for
construction areas. PPCP pavement design alternatives combined with improved safety
and timely construction present a clear set of benefits that can be utilized by project
compressive force to minimize amounts and strength of materials, which results in a more
conventional pavement results in a savings of over 770 cubic yards of concrete per lane
mile. Other advantages are inherent with prestressed systems such as the ability to span
voids that develop underneath pavement due to many factors. These voids reduce the
support of conventional pavement and create highly stressed localized areas which may
reduce the life of the pavement under repetitive wheel loading (See Figure 2.1). Simply
________________________________________________________________________
Page 14
increasing the prestressing force will help the panel act like a thicker pavement (Merrrit,
Prestressing
Tendo ns
Precast Slab
Base with
Void Shown
Figure 2.1 – Illustration of pavement section spanning over void in base material
Another inherent benefit from precast pavement is the ability to control the
quality of the finished product. Timeliness is held paramount most often when placing
conventional pavement due to traffic, workers, and high equipment costs and other
constraints. These influences can weigh heavily on builders and can compromise the
effective quality control, lower tolerances in size and shape, and selective production
schedules can be used under controlled conditions since fabricators are not under these
________________________________________________________________________
Page 15
Figure 2.2 – Surface finishing of a typical base panel at the precasting yard
means for controlling the delicate curing process. The panels can be cured in a number
load transfer. Cracks can spall, fault, and allow water to penetrate the base creating voids
under the pavement and facilitate freeze-thaw damage. Crack widths are kept closed by
these cracks would open up wider with each successive freeze/thaw cycle and eventually
expose the reinforcement and base to water and de-icing salts. This quickly results in
replacement. The pre-compression forces in PPCP serve to keep cracks from opening up
wide enough to create the aforementioned problems. The shear friction alone, provided
________________________________________________________________________
Page 16
by the pre-compression in a prestressed pavement, provides optimal load transfer across
Concrete poured on a base course will tend to have a rough underside, because it
takes the shape of the base course, thus increasing the friction of the bottom surface of
the pavement. Additionally, concrete poured onto the base will be restrained by a larger
mechanical means in which small slivers of concrete are allowed to seep in between the
aggregates causing small surface irregularities or “fingers” tying the concrete to the base.
When the concrete shrinks during curing, the restraint against the base causes residual
stresses in the concrete. These additional stresses are not typically included in design
calculations since the geometric constraints are not easily quantified. PPCP has two
advantages over CIP concrete since the majority of shrinkage will have occurred at the
casting yard and precast panels will have a smooth underside limiting mechanical friction
with the base. Fewer shrinkage cracks result in decreased maintenance and repair costs
achieved after installation of PPCP. Polyethylene sheeting has been used to minimize
frictional losses between pavement slabs and the base. Not only do slight elevation
differences between panels create additional friction by slight miss-alignment of the post-
tensioning ducts but can also create an undesirable audible “bump” at panel joints.
often required. Shear keys are cast into the joints of the pavement to ensure proper
________________________________________________________________________
Page 17
The performance of PPCP in this and other pilot projects has proven it to be a
viable substitute for repair and replacement as well as for new construction of pavement
systems. PPCP possesses several design features that make it attractive for
PPCP sections for a ‘standard roadway crossover’ can be stockpiled and used at multiple
unique panel designs and alternative means for pavement system construction methods
showcasing workshop in August of 2006 following the completion of the Missouri Pilot
Project.
The development of PPCP for rapid rehabilitation projects began in the mid
1980’s. Projects utilizing CIP prestressed concrete in Texas and South Dakota have
proven effective. Since the pavement performed well in these states coupled with
advancements in precasting and shipping means facilitated the use of precast slabs. More
recently in Georgetown, Texas a frontage road along Interstate 35 was replaced using
precast prestressed concrete panels. The experience from the Texas project allowed
the advantages of precast panels will serve in urban pavement replacement projects. The
following sections describe the recent PPCP projects undertaken throughout the country.
________________________________________________________________________
Page 18
2.2.1. Iowa Approach Slab on Highway 60
pavement for bridge approach slabs in September 2006. The charge of this project was
for Iowa DOT to refine design and construction details of PPCP bridge approach slabs.
This project was located on Highway 60 near Sheldon, Iowa. The bridge approach slab
tied into a 30 degree skewed, integral abutment for the northbound bridge crossing the
Floyd River. The twin southbound bridge was constructed with conventional cast in
abutment cast to match the skew. They were assembled in “lane-by-lane” construction
on a closed roadway for the new bridge. This project offered a unique bridge approach
slab design for IADOT by tying the approach slab into the abutment and moving the
expansion joint out to the end of the approach slab. Research by IADOT has shown that
removing the expansion joint near the abutment limited water infiltration and erosion of
Due to the success of the pilot project, IADOT has scheduled the replacement of
failed bridge approach slabs at either end of twin bridges under traffic with PPCP. The
end result will be a further understanding and confidence of this pavement system as an
deteriorated or poorly constructed paving notches on high volume roadways and bridges.
________________________________________________________________________
Page 19
2.2.2. I-10 in El Monte, CA
a pilot project using PPCP on Interstate 10 near El Monte, CA. This project involved a
little more complexity compared with the Texas project by requiring varying cross-slopes
cast into the panels, and nighttime construction operation (Tyson and Merritt 2005). The
total length of roadway replaced was 248 ft and consisted of two driving lanes and a 10 ft
shoulder that were part of a widening project on I-10. The panels were cast with a flat
bottom and a variable depth to maintain a desired cross-slope to match the roadway
profile. The pavement was placed on a level 6 inch lean concrete base on top of 8 ½ inch
aggregate base. A total of 31 panels were fabricated for the project. The panels were
installed at a rate of 15 panels per 3 hours (Transtec 2009). The panels were prestressed
transverse to the direction of traffic and post-tensioned in two 124 ft sections longitudinal
to traffic (Tyson and Merritt 2005). The pavement widening project was completed
installed on an outer road near I-35 in a jointly funded Texas DOT and FHWA project.
The frontage road was located just north of Georgetown, TX. Full and partial width
panels were used for this project to test the feasibility of the two panel types. Both types
of panels were post-tensioned longitudinally while the partial width panels had additional
post-tensioning ducts in the transverse direction (See Figure 2.3). A total of 339 panels
were fabricated, of which 123 were full width and 216 were partial width. The full width
________________________________________________________________________
Page 20
panels were wide enough to accommodate two twelve foot lanes an eight foot outside
shoulder and a four foot inside shoulder. The partial width panels were 16 feet and 20
feet in width respectively. When placed, the centerline of the roadway matched with the
joint between the two panels. The Georgetown pilot project presented many challenges
for precast pavement implementation (Merritt 2001). Among the successes were
demonstrating that the match-casting is not necessary due to the rugged formwork used in
fabrication and geometric mechanisms such as the mating connections cast into each
panel that provide for alignment of the post-tensioning ducts in the field. Successful
of contractors to develop new practices where standard details have not been developed.
________________________________________________________________________
Page 21
The pavement in Texas has been in service since March 2002 and no maintenance
related issues have been reported (Transtec 2009). Careful planning and willingness to
explore innovative means of precast implementation by the DOT, precast supplier, and
contractor contributed to the overall success of the project in Georgetown, Texas which
compared with that of traditional pavement techniques creates a demand for the
demonstration of performance. The caveats that affect the design and performance of
various traditional pavement types are well known by designers through experience and
testing which dictate the designer’s evaluation for pavement design. Field measurement
and rigorous evaluation of pilot projects can supply quantifiable information regarding
validation of design. These types of investigations can prove useful for design engineers
________________________________________________________________________
Page 22
• Validate in-service performance of structural design by analyzing strain
strands and concrete strain. This data can be used to monitor pavement
construction methods.
________________________________________________________________________
Page 23
This page intentionally left blank.
________________________________________________________________________
Page 24
3. Experimental Program
acquisition system used for the project. Design, specifications, construction and
calibration of custom instrumentation used for the research project are detailed in-depth
in (Dailey 2006).
prestressed strand strain can be accomplished by embedded strain gages inside of the
concrete matrix and attached directly to prestressing strands during casting. The
following sections describe the instrumentation used to monitor the performance of PPCP
test sections.
Typical #4, Grade 60 rebar was used to fabricate sensitive strain gage
long sections were cut and machined smooth in the center to accommodate a
on the rebar and two were installed along the circumference. A schematic of the circuit
________________________________________________________________________
Page 25
used is illustrated in Figure 3.1. The ends of the strain gage rebars were threaded to
accommodate gripping for calibration. A completed strain gage rebar is shown in Figure
3.2. Strain gage instrumented rebars are capable of measuring very dynamic events such
as stress transfer from strand cutting and traffic loads while in-service. The instruments
are also very robust and have a good track record from previous projects completed at the
S+
S- P+
P- P+
R1 R2
R2
R1
Eo S-
S+
R3 R4
4 V D.C.
R3 R4 Smooth Machined
Surface
P-
Ribs on
Reinforcing Bar
Figure 3.1 – Schematic of the strain gage configuration on the strain gage rebar
(Eatherton 1999)
________________________________________________________________________
Page 26
3.1.1.2. Vibrating Wire Gages
Commercially available vibrating wire embedment type strain gages were used to
complement the dynamic strain gage instrumented rebars (Model 4200, Geokon Inc.).
Vibrating wire gages are reliable for long-term strain measurements due to the nature of
its design which does not depend on electrical resistance like a traditional strain gage.
The gage consists of a wire stretched between two flanges, an electromagnetic plucking
device, and a thermistor used for temperature compensation. The gage operation relies
on the change in resonant frequency of the wire based on its length. When one flange
displaces relative to the other, the wire is elongated resulting in a change in resonant
frequency. This change in resonant frequency can then be related to strain by simple
The vibrating wire gages are very useful for long-term strain measurements;
however, dynamic events cannot be measured due to settling time of the stretched wire.
After embedding the gage in concrete, a zero reading can be taken. At any time the zero
reading can be referenced, and the state of strain of the concrete can be determined based
Figure 3.3 – Model 4200 vibrating wire gage from Geokon Incorporated
________________________________________________________________________
Page 27
3.1.1.3. Vibrating Wire Strandmeters
Incorporated for use in the test panels to monitor prestressing strand strain. The gage
operates on the same principles as the model 4200 discussed above. However, clamps at
gages were encased in a PVC tube filled with grease in order isolate the gage from the
surrounding concrete and only measure strain in the post-tensioning strand. Blockouts
were cast into the test panels to accommodate the installation of strandmeters prior to
The strandmeters primary function was to measure the strain of the post-
tensioning strands during the stressing operations as well as maintain a record of strand
behavior during service. Strand stresses can be correlated with frictional and time-
design.
________________________________________________________________________
Page 28
3.1.1.4. Temperature Gages
concrete temperature measurement. The specified temperature range was -328o to 663o F
(-200° to 900° C). The thermocouples were cut to length, welded using thermocouple
welders, and coated in epoxy at the University of Missouri – Columbia. This type of
temperature measuring device is very advantageous due to its robustness, ease of use, and
accuracy (+/- 0.1o C). Gages were positioned throughout the cross sectional depth, as
shown in Figure 3.5, and at various locations across the panel width and length.
TC
TC
TC
temperature (Model DS1922L.) An array of twelve iButtons was used within one of the
precast panels as a pilot experiment to validate the welded wire thermocouples and to
provide measurement for higher resolution temperature performance through the depth of
the pavement. The iButtons store time and temperature logs in self contained memory
units and requires only a single lead wire to communicate with a computer or other data
________________________________________________________________________
Page 29
logging device. Lead wires were attached and the entire iButton coated in epoxy to
The precast panels used in the project are identified by two different methods.
The identification system used by CPI and Gaines Construction used letters and numbers
to signify the different panel types. An “A” panel was a joint panel, a “B” panel was a
base panel, and a “C” panel was an anchor panel. Since three different types of joint
panels were used, a number after the “A” differentiated the joint panels. Labels “A1” and
“A2” represented the joint panels at the north and south limits of the overall pavement
test section respectively. The symbol “A3” was used for the three intermediate joint
MU research team added a number after the symbols used by the contractors. The panel
numbering increased from south to north. For example the four base panels were labeled
B1, B2, B3 and B4. The southern-most base panel was B1 and the northern-most was
B4. The single instrumented anchor panel was marked C1, and the joint panels were
The gages within the panels were further identified by their type and location.
thermocouples with a T, and strandmeters with an S. The location of the gage was
identified by a number after the type of gage. The seven instrumented panels
incorporated five different devices to measure strain and temperature of the concrete
________________________________________________________________________
Page 30
along with strain in the post-tensioning strands. Figure 3.6 depicts typical
instrumentation in a base or anchor panel and Figure 3.7 shows the instrumentation
locations in joint panel A32. Concrete strain was monitored using the strain gage rebars
and vibrating wire gages mentioned previously. Post-tensioning strand strain history was
thermocouples and iButtons (Maxim) embedded in the concrete along with thermistors
10’-0”
X3
X3
________________________________________________________________________
Page 31
Pretensioned Strands (3@0”-6” T&B) Junction Box
38’-0”
X2 X3 X3
10’-0”
The pilot project encompassed 1,000 feet of roadway rehabilitation and consisted
of four, 250 ft long post-tensioned sections. The primary goal of the research program
was evaluate the performance of the PPCP with regard to temperature, loading, local
strains, and joint displacements. To accomplish this, the research team decided to focus
on a single 250 ft section and instrument panels within this section. Section 3 of the 4
sections along the traffic direction was chosen. It was selected based on its proximity to
an AC power source and to limit possible transition effects from conventional concrete
pavements adjacent to the PPCP. Four base panels, two joint panels, and one anchor
panel were instrumented to characterize the performance of the pavement system under
environmental and vehicle loading. Figure 3.8 shows the location of the instrumented
panels within the chosen section. The panel marked B4 in Figure 3.8 lies outside the
________________________________________________________________________
Page 32
A31 C1 B1 B2 B3 A32 B4
38’-0” Direction of
Traffic
A custom data-acquisition system was assembled and used for the monitoring of
Scientific CR10X data logger, (3)-32 differential AM416 relay multiplexers, 110V AC to
12V DC power supply, two AVW1 vibrating wire interfaces, and an NL100 network link
interface for remote communication. A centralized location at the test site was chosen to
minimize cable lengths and power requirements where the system was housed in an all-
weather signal cabinet typically used to house electronics at traffic signals (Figure 3.9).
________________________________________________________________________
Page 33
Figure 3.9 - Signal cabinet with main data-acquisition equipment installed at the
edge of right of way
Junction boxes were cast into the shoulder of instrumented panels to provide
for thermocouples and voltage regulation circuit for regulating power used by
instrumented rebars (Figure 3.10). Voltage regulation at the pavement was necessary due
to the voltage loss in the long lengths of cabling to connect instrumentation required due
to the large foot print of the project. Multi-pair, stranded wires were run from the
junction boxes of each panel back to the data acquisition system for signal transmission.
________________________________________________________________________
Page 34
Figure 3.10 - Junction box installed in blockout cast in outside shoulder of precast
pavement panels
the research team to gain access to high speed DSL and electricity. An inexpensive spur
line to get closer to the test section was installed by the utility companies for the research
team. Luxuries such as electricity and internet service are not commonly available on
improved the reliability and simplified powering the data-acquisition systems and
circuits accompanying solar panels and back-up generators due to the lack of utilities.
These challenges are best avoided if conditions allow and proper planning is allotted
________________________________________________________________________
Page 35
High-speed DSL enabled the research team to perform real-time data monitoring
from the laboratory. Researchers were able to upload customized programs to perform
specific tests catered to gather timeline and event specific data on selective
diagnostics, high-frequency readings for wheel load response, monitor prestress levels,
instrumentation life and electricity savings by utilizing only the gages or thermocouples
needed for specific long-term experiments and powering down the remaining
instrumentation.
composition and behavior of the concrete and materials used in the PPCP system. This
data was used to understand pavement behavior resulting from temperature and vehicle
loading as well as generate long-term loss models by characterizing shrink, creep, and
relaxation to verify results measured in the field. Additionally, samples were prepared to
measure the chloride ion resistance which was used to predict pavement durability with
respect to salt penetration. Laboratory material testing and results were presented in
(Davis 2006).
Page 36
• Unrestrained Creep & Shrinkage
hardened concrete matrix is useful and necessary to analyze results from service
measurements.
compensating full bridge circuits were used on the instrumented rebars. In order to
understand how the embedded instrumented rebar system responds to thermal and
mechanical loads from restraint, laboratory experiments were performed using both
One instrumented rebar and one vibrating wire gage were cast into a 6 inch x 6 inch x 24
inch (15.24cm x 15.24cm x 60.96 cm) long concrete specimen in order to duplicate the
instrumentation was supported by metal wires so as to eliminate any restraint to their free
oven and subjected to programmed temperature histories. Figure 3.11 shows the
________________________________________________________________________
Page 37
Figure 3.11 – Unrestrained instrumented rebar and vibrating wire gage in
temperature controlled oven
Figure 3.12 shows the responses from the instrumented rebars during the heating
of a 14-day old concrete specimen to the temperature history shown in Figure 3.12a. The
are likely due to temperature dependent non-uniform strain gradients. After several days,
the output returned to zero, wherein the rebar had reached a uniform temperature.
Elevated temperatures were maintained for nearly 12 days to ensure the entire concrete
prism had reached a uniform temperature. The embedded rebar in Figure 3.12 took
predictions of the 52ºC temperature excursion. The theoretical rebar strain was
concrete and steel, which equals -6.2 µstrain/ºC. The embedded rebar strain was
compressive in nature with an increase in temperature, which supports the logic used to
embedded rebar reached higher values than computed from ΔT. This larger magnitude is
attributed to drying shrinkage, which was exaggerated by desiccation due to the high
________________________________________________________________________
Page 38
temperatures in the oven (for a relatively green concrete, 14 days old when experimented
was started). This was confirmed after the heat had been turned off. The resulting
magnitude of residual strain measured by the embedded rebar was equal to the difference
between the theoretical embedded rebar strain and actual embedded rebar stain
(approximately 100 µstrain of drying shrinkage strain). Concrete strain was calculated by
multiplying the scalar (-6 / 6.2), which was calculated from the difference in CTE’s of
concrete and the rebar. It can be seen in Figure 3.12 that after 11 days, the temperature
measured by the thermocouple (wrapped up with the embedded rebar, R17), had reached
room temperature rather quickly yet there was still strain recovery over the following
________________________________________________________________________
Page 39
Figure 3.12 – (a) Temperature history (b) Strain history of embedded and
unrestrained rebar instruments
The concrete strain measurements during service are largely dictated by thermal
excursions from everyday heating and cooling. These analyses have led to the following
idealization and subsequent equation that was used to interpret the service performance
o The concrete (6 µstrain/ºC) has a CTE of roughly half that of the embedded steel
(12.2 µstrain/ºC) instrument.
o The system experiences a +ΔT
o The concrete expands Δ, and the steel wants to expand 2Δ. Yet the steel is
restrained by the concrete to only Δ.
________________________________________________________________________
Page 40
o Hence, the strain in the instrumented rebar is measured as a compressive Δ to a
heating of the system.
D
Steel Rebar
2D
Concrete
D
× (R1 − R0 )
CTEconcrete
∆ε Concrete =
CTEconcrete − CTE rebar
the instrumentation and data acquisition system developed for the precast project. These
challenges sometimes resulted in delays because of the need to undertake several repair
visits after severe weather-related events. In spite of more than adequate planning and
conductors spanning over 9,000 square feet serves as an easy sink for electrical activity
during thunder storms. A summary of the various challenges and appropriate remedies to
mitigate each problem are listed here so as to be helpful for future projects of a similar
nature.
________________________________________________________________________
Page 41
3.3.1. Excessive Heat Build-up affecting Sensitive Hardware
The signal cabinet that housed the power supply, communications and data
acquisition system was located in a field just beyond the shoulder alongside the
instrumented pavement section. This box was exposed to fairly high ambient
temperatures (build-up of temperature in excess of 160°F during peak summer days was
measured). These excessive ambient temperatures and resistive heat build up in the
alleviate this problem. First a roof was built to protect the signal box from direct sun
exposure (Figure 3.14). Secondly, two heavy-duty equipment fans were installed in the
signal cabinet that were on at all times and allowed flow of air through the cabinet.
Third, all the voltage regulators were replaced with military grade regulators that were
specified for higher operating temperatures. And fourth, all the regulators (those in the
signal cabinet as well as the individual panel terminal boxes) were provided with larger
aluminum heat dissipation fins. Collectively all of these four upgrades essentially
eliminated problems associated with excessive heat build-up and associated electronic
instabilities.
________________________________________________________________________
Page 42
Figure 3.14 – Signal cabinet protected during the heat of the day by a shade roof
moisture protection for the electronic components and associated circuitry. While the
hermetically sealed, the holes that allowed instrumentation cables into the box, also
allowed moist air even while the holes were sealed with silicone. The circuit boards were
also mounted with sufficient clearance from the bottom of the terminal boxes using
spacer legs to avoid standing water from interfering with their intended operations. The
circuit boards were additionally sprayed with a non-conducting urethane spray to water-
proof them. The terminal boxes also contained desiccants in cloth bags. With adverse
weather, a significant amount of precipitation and infiltration of moist air, the electronics
in the terminal boxes were exposed to moisture and on rare occasions (in some panels) a
small amount of standing water (inside the terminal boxes). On a few occasions the
moisture shorted the printed circuit boards in these terminal boxes despite all the
________________________________________________________________________
Page 43
terminal boxes during inspection visits, cleaning, caulking and replacement of desiccant
Even while all cables were well shielded and grounded, lightening strikes tripped
the protective circuit breakers, damaged the uninterruptible power supply (UPS), several
voltage regulators and cold junction compensation (CJC) circuitry. While studying the
“as-implemented” circuitry to fix the problem, it came to light that while the circuit was
well protected against a lightning strike on the power pole side of the system, there was
little protection against voltage surges on the instrumentation side of the circuitry. Close-
up of a CJC circuit board damaged by a lightning strike is shown in Figure 3.15. Diodes,
which prevent the reverse flow of electricity, were employed in all of the instrumentation
lines and across all of the voltage regulators to ensure that any electrical surge would be
discharged to the earth ground. After observing that the most viable method to properly
ground the system for lightning affected the magnitudes of the outputs from the
instruments due to a ground loop differential, a spark gap was employed to prevent
adversely affecting the system during normal operating conditions and still provide
________________________________________________________________________
Page 44
Figure 3.15 – Close-up of CJC damaged by lightning
During the first winter (January 2006), snow plows sheared off the bolts securing
the protective covers of the terminal boxes that were slightly above the surface of the
pavement. This allowed water to get in to the terminal boxes. Use of thinner (but yet
sturdy to withstand traffic loads) protective cover plates with counter-sunk recesses
allowed enough clearance so that the bolt heads could be flush with the top surface of the
protective plates. This mechanical upgrade ensured that no repeat of such damage
________________________________________________________________________
Page 45
This page intentionally left blank.
________________________________________________________________________
Page 46
4. Service Performance of PPCP System
A summary of service performance results from the year long monitoring of the
instrumented pavement panels is presented in this chapter. Typical daily, short-term (few
days) and longer term seasonal temperature and strain excursions are presented and
discussed. Vehicular loading events were measured and are presented. An evaluation of
the causes and characterization of prestress losses are presented and discussed. Also
included are observations for visual inspections carried out during the regular field
inspections of the pavement test sections. Since the more consistent data from the
instrumented rebars were available for the majority of the project duration, they are used
primarily for figures and discussions. The vibrating wire data, when available, had been
used to confirm magnitudes of strain excursions measured using the instrumented rebars.
However plots for vibrating wire strain data which are typically noisy and intermittent
It should be noted that strain data presented here includes the combined effects of
thermal loading, vehicular loading, viscous loading due to creep, shrinkage and
relaxation, and loads due to sub grade movement. However, given the time windows of
interest and sample rates of data acquisition, the dominant influence is due to thermal
loading. The effect of vehicular loading is isolated in one plot where a significantly
higher data acquisition rate was intentionally used to highlight this effect.
________________________________________________________________________
Page 47
Strain measurements were recorded using instrumented rebars and vibrating wire
gages. Due to adverse weather events, 5 of 12 vibrating wire gages were damaged during
the storms of spring 2006 and operated intermittently. The remaining vibrating wire
gages have operated consistently throughout the duration of the project. More details on
the challenges faced with the data acquisition system can be found in Section 3.3. It
should be kept in mind that electrical drift can affect long term measurements using
resistance type strain gages. Careful planning and design of the instruments and data
signal output. Daily outputs of strain gages were also subject to voltage fluctuations
recognize that the zero strain reference at the start of each plot doesn’t represent actual
“zero strain” value but is a reference for incremental excursions shown. In other words,
negative strains do not necessarily mean compression but are merely less tension. This is
typical for strain-gage based transducers where “zeroing” long term measurements to
study incremental events is more important than studying actual strain magnitudes.
Thermal loads constitute the single most important influence on pavement strains
observed on a daily basis. However, since the pavement does not have a uniform cross-
section, heating, heat-retention and cooling occur at different rates for different cross-
sections resulting in gradient effects. Proximity within the concrete matrix to both air
________________________________________________________________________
Page 48
and ground work as heat sources and sinks. This enables the thinner sections to heat and
cool more quickly than the thicker section around the crown. Figure 4.1 highlights the
potential for differential heating and cooling using a typical summer day and night. Point
A on the pavement panel is at the outer edge of the thinner section, and during the
daytime it heats quicker than the rest of the panel that is exposed to the air due to the
thicker cross section and proximity to exposed surfaces. Point B is the last portion of the
concrete section to heat up during the day, and during the night is the last section to cool
down (Point C). Similar trends in reverse are anticipated during cooling cycles during
2%
A D
Pavement Pavement
Cross-Section B C Cross-Section
Sub-Grade Sub-Grade
component plus effects of restraint due to sub-grade movements, thermal gradients, and
eccentric prestressing.
________________________________________________________________________
Page 49
The magnitude of recorded concrete temperature and rate of thermal loading is
affected by proximity of the particular section to exposed surfaces and thickness at that
location. Figure 4.2b indicates the daily concrete response at three instrumented rebar
locations (R1, R3 and R4 see inset) that are parallel to the traffic direction. Temperatures
recorded close to the strain measurement locations are reported in Figure 4.2a.
pavement are shown in Table 4.1 (depth of instrument from driving surface). The
magnitudes of the recorded temperatures are reflective of both the thicknesses of the
pavement and proximity to the nearest exposed surface. A32_V3t at R7 is closer to two
surfaces than R1 or R3. This may explain why the temperature excursion at R7 is the
highest. Higher temperature swings produced larger strain excursions, even at localized
panel locations. R7 has a ΔT of 14.4ºC but exhibits a strain differential of 107 µstrain.
If the response were attributed only to the temperature change, R7 would only indicate
86.5 µstrain. The difference between the expected thermal strain and the observed strain
excursion is 20.5 µstrain and is consistent with the strain excursions of R1 and R3 shown
in Figure 4.2. This difference can be attributed to the several additional constraints
described earlier.
________________________________________________________________________
Page 50
Table 4.1 – Instrument Locations and Event Summary for Joint Panel A32 on July 13,
2006
The duration that the strain level is sustained at peak levels during temperature
extremes is correlated well with pavement thickness at the location. In Figure 4.2 , R1
peaks at 5 hours and starts to indicate less tension faster than R3 and R7. R3 and R7
________________________________________________________________________
Page 51
0 4 8 12 16 20 24
50
110
A32_V1t @ R1
A32_T5 @ R3
45 A32_V3t @ R7
103
Average (Ref. for Theo.)
Temperaturel, T (°F)
Temperature, T (°C)
Ambient Temp
40
96
35 89
30 82
25 75
Instrumentation Plan
R8 R5 R2
V4 R6
V2
20 T7-8 68
Inside Shoulder
Outside Shoulder
Traffic
100 T4-6
R1
Direction
R7 V3 R3 V1 T1-3
R4 A32_R1
Vibrating Thermocouple
A32_R3
Instrumented
Rebar Wire Gage A32_R7
Thermal Theo.
ΔR3 = 82
50
Strain, ε (µstrain)
ΔR1 = 83
ΔTH = 65
0
ΔR7 = 106
-50
0 4 8 12 16 20 24
Time, t (Hours)
Figure 4.2 – One day window from July 13, 2006 for Panel A32 (a) temperature
history (b) strain history
The relative strain response from longitudinal and transverse concrete strains was
also studied in relation to the daily thermal history. Figure 4.3a and Figure 4.3b shows
the response from instrumented rebars during a 24-hour window for a typical summer
for the rebars aligned along the traffic direction (longitudinal rebars R1, R3, and R7). R5
________________________________________________________________________
Page 52
which is located transverse to traffic indicates much larger tensile strains on the order of
90 µstrain. The tensile strains of R5 in Figure 4.3b are also sustained at the high
magnitudes of strain for much longer than peak strains sustained by the longitudinal
rebars. The higher tensile strains and durations are also illustrated for the transverse
rebar, R3 in panel B3 (Figure 4.4b). Similar responses for the transverse strain behavior
were recorded for a typical winter day and presented in Appendix A (See Figure A.1),
highlighting the fact that this behavior is not unique to significantly different average
ambient temperatures (30ºC for the summer day shown versus 8ºC for the winter day).
________________________________________________________________________
Page 53
0 4 8 12 16 20 24
50
A32_T1 A32_T2
A32_T3 A32_T4 108
45 A32_T5 A32_T6
A32_T7 A32_T8 103
A32_V1t A32_V3t
Temperaturel, T (°F)
Temperature, T (°C)
A32_V4t Ambient Temp
40 98
93
35
88
30 83
78
25
Instrumentation Plan
R8
73
R6 R5 R2
V4 V2
20 T7-8 68
Inside Shoulder
Outside Shoulder
Traffic
125 T4-6 Direction
R7 R1 V1 T1-3
V3 R3 R4
75
Strain, ε (µstrain)
50
25
0
A32_R1 A32_R3
A32_R4 A32_R5
-25
A32_R7 A32_V1c
A32_V3c Theoretical
-50
0 4 8 12 16 20 24
Time, t (Hours)
Figure 4.3 – One day window from July 13, 2006 showing all instruments for Panel
A32 (a) temperature history (b) strain history
________________________________________________________________________
Page 54
0 4 8 12 16 20 24
50
B3_T1 B3_T2
B3_T3 B3_T4
45 B3_T6 B3_T7 50
B3_T8 B3_V1t
Temperature, T (°C) B3_V2t Ambient Temp.
Temperature, T (°F)
40 30
35 10
30 -10
25 -30
Instrumentation Plan
20 -50
Outside Shoulder
Inside Shoulder
Strandmeter
R5 R2 R1
R4 R3
125 T7-8
V2
V1
Traffic
T1-3
B3_R2 T4-6 Direction
B3_R3
100 B3_R4 Instrumented Vibrating Thermocouple
Rebar Wire
B3_V1c
Theoretical
75
Strain, ε (µstrain)
50
25
-25
-50
0 4 8 12 16 20 24
Time, t (Hours)
Figure 4.4 – One day window from July 13, 2006 for Panel B3 (a) temperature history
(b) strain history
the transverse direction can be attributed to the different levels of restraint provided by
the surrounding concrete with respect to the asphalt stabilized base. In the longitudinal
direction, the pavement is restrained globally by the adjacent post-tensioned panels. The
strain measured in the middle of the panel will be largely dictated by pure thermal
________________________________________________________________________
Page 55
behavior of the concrete sections due to the high level of restraint from the heavy sections
adjacent to the panel. Whereas in the transverse direction, the level of restraint from the
surrounding concrete with respect to the ground is lower and can take on behavior more
indicative of the response from the asphalt concrete base. The CTE of the asphalt
concrete base is higher than that of concrete and likely retains its’ heat longer than the
concrete pavement due to the proximity to the ground and insulation from the pavement.
The difference in magnitudes of the transverse and longitudinal strains can also be
attributed in part to “curling” resultant from differential heating/cooling between the top
and bottom of the concrete pavement. Curling in the transverse direction is likely to be
more than that in the longitudinal direction again due to levels of restraint.
The effect of daily temperature excursions can also be observed by looking at the
performance of a typical joint panel during the day. Figure 4.5 (Left) shows the silicone
based joint compound receding below the pavement surface during lower temperatures.
During the hottest times of the day the joint compound squeezes above the pavement
12 inches
Figure 4.5 – Joint Panel A31 during mild temperatures (Left) and hot temperatures
(Right)
________________________________________________________________________
Page 56
4.2.3. Weekly Thermal Behavior
Temperature and strain variations from a medium sized window were analyzed to
correlate pavement behavior with extended temperature excursions. Figure 4.6 illustrates
the temperature history and associated strain response for a five-day window of a base
panel in late September (2006). As expected, with increasing temperatures, the pavement
exhibits tensile strains. Cooling produces compressive strains. The responses of the
individual rebars are similar to the theoretical values. The temperatures for the
theoretical predictions are averaged values between two thermocouples closest to the
pavement = 8.2 inches) are larger than that of Rebar 4 (thickness of pavement = 11
inches), in part due to Rebar 2 being located in a thinner cross-section of concrete. The
concrete strain behavior mimics what is to be expected for a moderate heating trend for
the entire duration. The day-to-day localized strain behavior is predictable with having
temperature histories.
The rate at which the temperature in the pavement increased or decreased was
Thermocouples 1 and 4 (T1 & T4) had a faster rate of heating and cooling since they
were located approximately 2 inches from the top surface of the pavement. It is for this
reason that they measured the hottest and most cool temperatures from day to day. The
rest of the thermocouples were located at mid-depth or at the bottom 1/3 of the cross-
section. As the location of the temperature measurement gets closer to the crown and
Page 57
shown in Figure 4.6a. The convention used was as follows: T1 closest to the top surface,
T2 in the middle, T3 at the bottom, T4 at top, T5 close to bottom. The exact locations
Appendix B. Concrete strain, as denoted by the individual devices (R2, R4) is largely
35
Temperature, T (°C)
Temperature, T (°F)
90
30
80
25
70
20
15 Instrumentation Plan 60
Outside Shoulder
Inside Shoulder
Strandmeter
R5 R2 R1
10 R4 R3 50
T4-5 V1
V2 Traffic
T1-3 Direction
60 C1_R2
C1_R4
40
Theoretical
Strain, ε (µstrain)
20
-20
-40
-60
-80
0 20 40 60 80 100 120 140
Time, t (Hrs)
Page 58
Analysis of results using time windows of different lengths facilitated study of
seasonal variations and associated performance of the pavement section. Figure 4.7a
shows a moderate heating trend in mid July, including the movement of a cooling front
on Day 11 where the mean temperature drops approximately 5ºC (9ºF). It is readily
apparent in Figure 4.7a that the pavement temperatures are higher than the ambient air
temperature. The temperature in the pavement stays well above the low temperature at
night due to the ground retaining much of its heat. This effect is clearly noted on Day 11
in Figure 4.7 due to the cold front moving and the lowest temperature in the pavement
was still above the hottest air temperature of the previous day. Much larger strains were
measured by the instrumented rebars compared to the theoretical values, which were
validated by comparing with the strain response from the vibrating wire instruments.
This is in part due to the only location that temperature was measured in the panel was
located near the thickest portion, where the change in temperature is the lowest
throughout the day. It was from this temperature measurement the theoretical response
was predicted. Larger temperature variations are prevalent in the thinner sections which
resulted in larger changes in strain over the individual days. This relationship is indicated
in Figure 4.8.
________________________________________________________________________
Page 59
0 4 8 12 16
45
B1_V2t 109
40 Ambient Temp
99
Temperature, T (°F)
Temperature, T (°C)
35
89
30
79
25
20 69
Instrumentation Plan
Outside Shoulder
Inside Shoulder
Strandmeter
15 R5
R4 R3
R2 R1 59
T4-5 V1
V2 Traffic
T1-3 Direction
140
B1_R2 Instrumented Vibrating Thermocouple
120 B1_R3 Rebar Wire
B1_R4
100 B1_R5
B1_V2c
80 Theoretical
Strain, ε (µstrain)
60
40
20
-20
-40
-60
0 4 8 12 16
Time, t (Days)
Figure 4.7 – Medium window indicating weekly heating and drastic cold front with
associated concrete strains (a) temperature history (b) strain history
________________________________________________________________________
Page 60
0 24 48 72 96 120 144
40
120
Temp @ R2
Temp @ R4
35 Ambient Temp. 110
100
Temperature, T (°C)
Temperature, T (°F)
30
90
25
80
20
70
15
60
Instrumentation Plan
Outside Shoulder
Inside Shoulder
Strandmeter
10 R5
R4 R3
R2 R1 50
T7-8 V1
V2 Traffic
T1-3 Direction
T4-6
60
Instrumented Vibrating Thermocouple
Rebar Wire
30
Strain, ε (µstrain)
-30
B3_R2
B3_R4
B3_V1c
Theoretical
-60
0 24 48 72 96 120 144
Time, t (Hrs)
Figure 4.8 – Weekly instrument history for Panel B3 (a) temperature history (b)
strain history
addition to the earlier discussed daily and weekly temperature fluctuations. By filtering
out hourly variations in temperature and strain it was possible to highlight long term and
Page 61
temperature and strain values (average of 24 hourly data points during each day for each
transducer). Figure 4.9 shows a six month window from early October of 2006 to the end
of April, 2007. This window of time represents the longest duration without significant
interruptions in the data acquisition system. Other windows of time show comparable
changes in the data acquisition programs to monitor different sets of instrumentation. The
plots in the following figures highlight typical winter cooling (October through February)
and typical spring heating (February through April) trends and associated strain histories.
There are no data for a small period in late November, when the data acquisition system
was down due to a power outage. The temperature history in Figure 4.9a includes both
mean daily ambient temperature as well as mean daily pavement temperature for Panel
B2. It can be observed that the excursion of mean pavement temperature is smaller than
that observed for the ambient temperature reflecting the time delay in heating and cooling
the concrete pavement and sub-grade mass. As in earlier discussions, it should be noted
that the strain plot provides incremental strain history during the time window of interest
and does not represent actual strain magnitude (which is less important to the discussions
here).
observed as the mean daily temperature drops during winter and similarly a tensile trend
(reduced compression) can be observed when the mean temperatures rise during spring.
The theoretical concrete strain (αΔT) is calculated assuming a CTE of 6 µstrain/ºC (using
________________________________________________________________________
Page 62
10/2/06 11/2/06 12/3/06 1/3/07 2/3/07 3/6/07 4/6/07
40
Mean Daily Ambient Temp
96
B2 Mean Daily Temp
30
76
Temperature, T (°C)
Temperature, T (°F)
20
56
10
36
0
16
-10 Instrumentation Plan
Outside Shoulder
Inside Shoulder
Strandmeter
R5 R2 R1
R4 R3
V1
-20 T4-5
V2 Traffic -4
T1-3 Direction
Instrumented
`
Vibrating Thermocouple
Rebar Wire
100
-50
-100
-150
-200
-250
-300
-350
10/2/06 11/2/06 12/3/06 1/3/07 2/3/07 3/6/07 4/6/07
Time, t (Days)
Figure 4.9 – Six month window showing longitudinal concrete strains in Panel B2 at
different locations (R2 and R5) (a) temperature histories (b) strain
histories
Rebars 2 and 5 (see panel inset in Figure 4.9 for rebar locations) both exhibit
expected trends in strain histories given the thermal loading history. Both of these
instrumented rebars are located where the pavement thickness is comparable (8.5 inches),
and are located at similar heights (4 inches from the bottom). However the magnitudes of
________________________________________________________________________
Page 63
strains at the two locations are significantly different for the same mean daily temperature
drop of approximately 26°C (peak strain differential of approximately 140 µstrain for
Rebar 5 as opposed to 280 µstrain for Rebar R2 from October 2006 to February 2007).
Local sub-grade friction and panel-specific in-plane bending effect due to use of steel
wedges along the outer shoulders (and resultant non-uniform panel to panel contact) are
likely reasons for variations in strain magnitudes between locations R2 and R5.
While simplistic and idealized this prediction captures the essence of trends in
strains from thermal loads. However magnitudes of strains are predicted inadequately. It
should be noted that in addition to thermal loads, the strain histories in plots like that
shown in Figure 4.9 are also influenced, in a location specific manner, by several other
factors including: elastic (modulus) and thermal (CTE) mismatch between pavement and
joint, local thermal variations (differential thermal gradients due to differences in local
in prestressing force due to thermal effects. Relatively negligible influences can also be
attributed to creep and shrinkage of concrete, relaxation of prestressing steel, traffic loads
and strain gradients from bending. Figure 4.10 shows longitudinal strain histories
measured from different instrumented panels using instrumented rebars along the
passenger side wheel path of the right lane (see inset showing measurement location R2).
________________________________________________________________________
Page 64
10/2/06 11/2/06 12/3/06 1/3/07 2/3/07 3/6/07 4/6/07
40.0
Mean Daily Ambient Temp 96
Mean Daily Concrete Temp @ R2 Locations
30.0
76
Temperature, T (°C)
Temperature, T (°F)
20.0
56
10.0
36
0.0
Instrumentation Plan 16
-10.0
Outside Shoulder
Inside Shoulder
Strandmeter
R5 R2 R1
R4 R3
T4-5 V1
-20.0 V2 T1-3
Traffic
Direction
-4
-50
-100
-150
-200
-250
* - Location R1 in A32 is
the same as Location
-300 R2 in the other panels
-350
10/2/06 11/2/06 12/3/06 1/3/07 2/3/07 3/6/07 4/6/07
Time, t (Days)
Figure 4.10 – Six month window showing longitudinal concrete strains at identical
panel location (R2) in different instrumented panels (a) temperature
histories (b) strain histories
all base panels (B2, B3, and B4). It is interesting to observe that strain magnitudes
(from the base panels in the middle of the test section to the joint panel at the end of the
test section). While not conclusive, the consistent and progressive reduction of peak
________________________________________________________________________
Page 65
strain magnitudes (around February 2007) suggests that sub-grade friction may have
some influence on this behavior. It is also important to observe from this figure, that
when temperature returns back to the initial value after approximately 6 months, the
differences in strain magnitudes in the various panels do not vanish, suggesting the effect
that causes peak strains in these panels to be different is not elastic (friction is an inelastic
excursions).
Figure 4.11 shows transverse strains measured from different instrumented panels
using instrumented rebars near the crown (see inset showing measurement location R3).
It should be noted that locations R4 and R5 in joint panel A32 are identical in the
transverse plane to location R3 in the base panel. The transverse strain histories across
the joint in the joint panel (R4 versus R5) are very similar. The magnitudes (150 – 250
µstrain) of peak strain events for transverse direction are comparable to those in the
longitudinal direction (Figure 4.9 and Figure 4.10). Again the magnitudes of
compressive strains during the coldest portion of the year are slightly larger than
force or external frictional characteristic takes place during seasonal variations. The
difference in strain magnitude is largest during the middle of winter (February) and
decreases as the mean temperatures rise during early spring (April) back to levels similar
to those recorded in fall (October). However inconclusive, this strain recovery is more
elastic than recorded in the longitudinal direction suggesting it may be due to changing
prestress levels and eccentric bending effects caused by uneven stress distributions rather
Page 66
10/2/06 11/2/06 12/3/06 1/3/07 2/3/07 3/6/07 4/6/07
40.0
Mean Daily Ambient Temp 96
Mean Daily Concrete Temp @ R3 Locations
30.0
76
Temperature, T (°C)
Temperature, T (°F)
20.0
56
10.0
36
0.0
Instrumentation Plan 16
-10.0
Outside Shoulder
Inside Shoulder
Strandmeter
R5 R2 R1
R4 R3
T4-5 V1
-20.0 V2 T1-3
Traffic
Direction
-4
0 Theoretical
Strain, ε (µstrain)
-50
-100
-150
-200
* - Location R4, R5 in A32
is the same as Location
-250 R3 in Panel B3
-300
10/2/06 11/2/06 12/3/06 1/3/07 2/3/07 3/6/07 4/6/07
Time, t (Days)
Figure 4.11 – Six month window showing transverse concrete strains at identical
panel location (R3) in different instrumented panels (a) temperature
histories (b) strain histories
Even while there was initial speculation that long-term drift in strain readings
from instrumented rebars might significantly affect strain histories, it is clear from Figure
4.12 that this is not the case. Strain history from instrumented rebar at location R1 in the
joint panel A32 is compared with similar history from the vibrating wire gage at the same
________________________________________________________________________
Page 67
location for a two month window during December 2006 – February 2007. The strain
76
Temperature, T (°C)
Temperature, T (°F)
20
56
10
36
0
Instrumentation Plan 16
-10
R8 R5 R2
V4 R6
V2
T7-8
Inside Shoulder
Outside Shoulder
-20 Traffic
-4
T4-6 Direction
R7 R1 V1 T1-3
V3 R3 R4
-50
-100
-150
-200
12/21/06 1/21/07 2/21/07
Time, t (Days)
Figure 4.12 – Two month window showing longitudinal concrete strains at identical
panel location (R1-V1) measured using instrumented rebar R1 and
vibrating wire gage (V1) (a) temperature history (b) strain history
________________________________________________________________________
Page 68
The effect of service temperatures on prestressing force is also of interest from a
performance point of view. Figure 4.13 includes a plot of temperature (ambient and
monitored is located) and associated strandmeter strain history recorded in Panel C1. If
the post-tensioning strand was un-bonded, one would expect strand strain to decrease
section. However, since the post-tensioned strands are grouted, they behave as if they
were bonded, with a decrease in temperature producing tensile strains in the strand
instead (Figure 4.13b, due to prestressing steel which has a higher CTE being restrained
by concrete with a lower CTE – thus producing compression in concrete and tension in
steel for the incremental temperature event). Notice that Figure 4.13b shows actual
strandmeter strain magnitudes (i.e. uses the actual zero strain reference from the start of
the post-tensioning operations, rather than a dummy “zero strain reference” to highlight
effect of the temperature event alone). The loss in prestress force from when the post-
tensioning operations were completed includes losses due to initial elastic shortening,
friction, creep, shrinkage and relaxation. These losses were quantified in Brent Davis’s
companion thesis.
________________________________________________________________________
Page 69
10/2/06 11/2/06 12/3/06
30.0 86
Mean Daily Ambient Temp
Mean Daily Concrete Temp @ Crown Mid-depth
74
Temperature, T (°C) 20.0
Temperature, T (°F)
62
10.0 50
38
0.0
26
Instrumentation Plan
Outside Shoulder
Inside Shoulder
Strandmeter
-10.0 14
R5 R2 R1
R4 R3
T4-5 V1
V2 Traffic
T1-3 Direction
6250
Instrumented Vibrating Thermocouple
Rebar Wire
6150
Strain, ε (µstrain)
6050
5950
5850
Mean Daily Strand Strain from SM_C1
5750
10/2/06 11/2/06 12/3/06
Time, t (Days)
Figure 4.13 – Strandmeter response at center of 250’ test section during typical
winter-time temperature excursion (a) temperature histories (b) strain
histories
A data acquisition program was designed to isolate vehicular traffic strain from
other long-term influences such as temperature, creep, shrinkage and restraint effects.
Data was acquired at significantly higher acquisition rates (12 Hz per channel). This
________________________________________________________________________
Page 70
gives a least count of 0.08 seconds since a large amount of data is acquired in a short
observation of the traffic history was also recorded so that correlations could be made of
strain peaks in the response. An unrelated lane closure (right, outside lane) facilitated
visual monitoring of traffic. Traffic speeds were limited to 55 mph as a result of this lane
closure. The rebar strain response due to traffic loads on the driver-side wheel path of the
inside, left lane is illustrated in Figure 4.14. Since this experiment was performed in the
afternoon, the overall compressive trend (negative slope in the global response) seen in
Traffic Response
Instrumentation Plan
Outside Shoulder
3
Inside Shoulder
T7
R5 R2
See Figure 4.15 R4 R3 R1
V1
2 T4-6
V2 T1-3
Traffic
Direction
Rebar Wire
0
-1
Strain from
-2
-0.75 ºC ΔT
-3 (4.5 µstrain)
-4
-5
Truck traffic loadings
-6 (1 - 3 µstrain)
-7
0 10 20 30
B4_Rebar 5 Time (Minutes)
Passenger vehicles were undetectable with respect to the +/ - 0.35 µstrain level of
noise within the signal of the instrumented rebars. Figure 4.15 displays the concrete
response at the crown of the pavement for a selected duration at which visual vehicle
________________________________________________________________________
Page 71
count was also undertaken. Strains induced by tractor trailers on the pavement, which
make up approximately 1/3 of the vehicles on I-57, can be seen in Figure 4.15.
Traffic Response
1.5
111 seconds 25 Tractor trailers passed
during this duration (25 peaks)
1
0.5
Strain (mstrain)
-0.5
-1
-1.5
B4_Rebar 5
-2
1.5 3 4.5 6 7.5
Time (Minutes)
Figure 4.16 illustrates the individual tractor trailer response on the pavement at
the crown. The tractor trailer that passed the precast panel being recorded had four axles;
one at the front of the tractor, two at the back of the tractor, and one at the rear of the
trailer. The three compressive peaks at 111 seconds suggest a correlation to the
individual axles passing over the instrumented rebar. The two, rear tractor axles were
likely encompassed in the second compressive peak due to their proximity to each other.
The tensile peaks are the result of stress caused by the approaching axles that are not
quite directly over the instrumented rebar. It is useful to note that strain magnitudes from
truck traffic are typically under ± 3 µstrain, compared to strains of ± 6 µstrain for a ±1 ºC
excursion in pavement temperature. It is important to note that these strain readings were
taken near the neutral axis of the prestressed panels. Assuming a linear gradient, surface
________________________________________________________________________
Page 72
strains (extreme fiber) caused by traffic loading are likely less than 25 µstrain which is a
small portion of the total daily strain behavior characterized largely by thermal
expansion/contraction.
Traffic Response
1.5
1
Strain (mstrain)
0.5
0
-0.5
-1
-1.5
B4_Rebar 5
-2
108 110 112 114
Time (Seconds)
Figure 4.16 – Resulting concrete response from a tractor trailer passing over
loadings, confinement and crack control. Post-tensioning also locks the panels together
globally, helping with load transfer and increasing the stiffness of the pavement sections.
This section describes the level of post-tensioning stresses and distribution as indicated
by the embedded instrumented rebars. Figures of strain distributions across the width of
Comparisons throughout the section can be readily made between the various
panels because Rebar 1, 2, 4, and 5 are in the same cross-sectional locations for Panels
________________________________________________________________________
Page 73
C1, B1, B2, and B3. The predictions are shown with expected steps from each pair of
strands that are stressed. These steps are also visible in most of the measured data.
Figure 4.17 illustrates concrete behavior of a typical base panel near the center of
the 250 ft test section during post-tensioning. The theoretical response predicted was
used to compare with the average concrete strain and not the individual rebar responses,
comparing local strain magnitudes at the four locations along the width of the panel, an
idealized sense of where force is transferred can be developed. Lowest strains were
measured at Rebar 2, then slightly higher at Rebar 4, with the largest stress transfer
taking place at the inner and outside shoulders. The poor prestress distribution of this
interior panel is likely resultant of several factors that occurred during fabrication and
construction as follows.
1. Wooden and Steel shims were used during construction along the outside
shoulder (near R1) to correct global alignment problems.
2. The epoxy used to lubricate the edges during the placement and seal off the joint
was allowed to harden prior to post-tensioning.
3. During construction, feeding the post-tensioning strands was difficult because the
PT ducts were thought to have sagged during fabrication. Due to localized
frictional effects, the concrete prestress force near those sections would be
affected.
4. Alignment of the post-tensioning ducts may have been difficult to obtain due to
no transverse “keyway” or other physical system to align the panels.
concrete strain vs. the theoretical strain behavior in Figure 4.17, which was derived from
Page 74
opening in localized concrete regions with lower than desired prestressing may come into
question in the future. Pre-tensioning will aid in the flexural capacity of these regions
and the resistance of surrounding stiffer concrete should minimize any serious
susceptibility to crack openings. More often than not for the instrumented base panels
near the center of the test section, the post-tensioning strain levels near the R2 location
were less than desired, as shown in Figure 4.18. Panel B3 indicates expected prestress
levels since it is the closest to the passive jacking end and does not incur the effects of
cumulative prestress loss along the length due to the aforementioned problems and also
20
0
Strain, ε (µstrain)
-20
-40 B1_R1
B1_R2
B1_R4
B1_R5
-60 B1 Average
Theoretical
R4, S R2
R5 R1
-80
10 9 8 7 6 5 4 1 2 2 3 4 5 6 7 8 9 10
Post-Tensioning Stress Transfer Sequence and Rebar Locations
-100
0 10 20 30 40 50 60 70 80
Time, t (Min)
Figure 4.17 – Concrete strain for a typical base panel during post-tensioning
operations
________________________________________________________________________
Page 75
20
Section 3
10 1
A31 C1 B1 B2 B3 A32 B4
Strain, ε (µstrain) 0 2
3
4
-10 5
6
-20
C1_R2 7
B1_R2
-30 8
B2_R2
B3_R2 9
Theoretical 10
-40
R4, S R2
R5 R1
-50
10 9 8 7 6 5 4 1 2 2 3 4 5 6 7 8 9 10
Post-Tensioning Stress Transfer Sequence and Rebar Locations
-60
0 10 20 30 40 50 60 70 80
Elapsed Time from (Min)
Figure 4.18 – Concrete strain measured at the R2 location (beginning of outside
shoulder)
stresses transferred to the panels are inhibited by sub-grade friction and friction within
the post-tensioning ducts. This is where alignment and possible sagging of the post-
Figure 4.19 illustrates the average concrete strain response of the four
measurements in each panel for the five panels measured in Section 3 during post-
tensioning. There does not exist a nice trend that coincides with frictional losses,
primarily because of localized frictional characteristics with the sub-grade (partial regions
that were filled with sand where the crane had left ruts provide different resistance than
________________________________________________________________________
Page 76
the asphalt base), localized stress distribution inhibitors such as the shims that were
placed between the panels, and the result of only having taken a small sample (four)
measurements in each panel. Most importantly Figure 4.19 reinforces that post-
tensioning forces are possible to obtain with the implemented design save for working
out a few of the minor kinks in the construction and fabrication. Other frictional prestress
10
Section 3
0 A31 C1 B1 B2 B3 A32 B4
-10
Strain, ε (µstrain)
-20
C1 Average
B1 Average
B2 Average
-30 B3 Average
A32 Average
Theoretical
-40
R4, S R2
R5 R1
-50
10 9 8 7 6 5 4 1 2 2 3 4 5 6 7 8 9 10
Post-Tensioning Stress Transfer Sequence and Rebar Locations
-60
0 10 20 30 40 50 60 70 80
Time, t (Min)
Figure 4.19 – Average Post-tensioning concrete strain histories for instrumented
panels
Cracking and visual degradation surveys were performed during inspections in the
latter half of the 18-month service monitoring. Both longitudinal and transverse cracks
have developed in the precast panels. Figure 4.20 and Figure 4.21 show a longitudinal
________________________________________________________________________
Page 77
crack that originated at a corner of a strandmeter block-out. The crack spans several
panels suggesting possible influence from external loading such as traffic loads and sub-
grade movements. The crack has likely propagated since that lane receives the load from
the drivers side wheels of the majority of vehicles and has followed the post-tensioning
duct where a reduced cross-sectional area exists. Figure 4.20 (right) shows the outline of
12 inches
________________________________________________________________________
Page 78
B2 BASE BASE BASE BASE
Blockout
TRAFFIC DIRECTION
Longitudinal cracking have also been documented along the shoulders of the
precast panels. Some transverse cracks are located on an observed schematic in Figure
4.22. Longitudinal cracking along the shoulders may also be exaggerated by shims used
between panels to correct alignment during construction and limited by perimeter rebars
designed for edge reinforcement. Transverse cracking has primarily occurred at the mid-
section of the panels. The scaling noted in Figure 4.22 is located on the inside shoulder
where the pavement was not ground smooth. An official crack survey has been
conducted at several times of the study by MoDOT to locate, measure the length, and
record the width of the cracks. It was found that the majority of the cracks are “hair line”
cracks.
________________________________________________________________________
Page 79
Scaling Inside Shoulder
Grout
Ports
Outside
Shoulder
Figure 4.22 – Typical crack locations of a 4-panel set of the 3rd test section on
May 9, 2007
2006. Departments of Transportation for seven states, the FHWA, many researchers
from universities in the region, and members of the precast and prestressed industries
were represented. Presentations were given by David Nichols (MoDOT), Tommy Beatty
(FHWA), Sam Tyson (FHWA), Eric Krapf (MoDOT), David Merritt (Transtec Group,
Inc.), Vellore Gopalaratnam (UMC), Andrew Maybee (CPI Concrete Products), and John
Donahue (MoDOT). Much discussion was focused on the transfer of PPCP technology
and ways to facilitate practical implementation. The overall purpose of the ETG meeting
was to discuss and receive feedback from all parties involved in the conception, design,
fabrication, and construction of PPCP systems. Several in attendance noted that design
________________________________________________________________________
Page 80
The difficult issues with PPCP are in the actual implementation of the
sophisticated designs. Designs using small post-tensioning ducts are used and may sound
appealing for designers, but the manipulation and placement of large, heavy concrete
panels that are relatively thin becomes complicated when tight tolerances are required.
The higher initial costs associated with PPCP will be offset somewhat by reduced costs
due to more rapid construction and potentially reduced maintenance. In any case, it is
likely that PPCP may be initially reserved for high volume urban areas where lane
closures are both expensive to end users and dangerous for workers and travelers.
Members of the ETG spent time discussing the potential causes of cracking found
in the pavement described in the previous section. Some of the more important causes
for the cracking observed in the pavement system were identified as;
• Thermal shock due to fabrication of the panels during the winter time in
an outdoor bed where panels were steam cured and subsequently exposed
• The effects of epoxy applied between panels that cured well before post-
Since no grout was observed exiting the pavement, much of it could have
________________________________________________________________________
Page 81
gone underneath the panels causing upward pressures and uneven stress
The pavement sections were visually inspected each time the research team
visited the site. A total of 8 visits were undertaken during the 18-month service
electronic circuitry. The overall performance of the pavement system has been very
good. Two aspects that could use more attention in future projects include “as
issues have not, and are not likely to pose performance problems in the future. However,
experience from this project can serve to facilitate design, fabrication and construction
The joint panels were designed to open at the pre-engineered construction joint at
the center of the panel during post-tensioning operations. However due to difficulties in
threading the post-tensioning strands and resulting delays, the contractor decided to place
all panels in all four 250 ft sections prior to post-tensioning. This may have affected
performance at the joint panels as the original plan was to post-tension one 250 ft section
before placing panels for the adjacent section. In addition, the cold joint in the two-step
casting of the joint panels had better bonding than anticipated across the joint. As a result
________________________________________________________________________
Page 82
the joint panel between sections 3 and 4 (the more heavily instrumented joint panel –
A32) did not open up as designed. However, all other joint panels have performed well
during this study. In the contractor’s effort to open the A32 joint using jacks, the
concrete fractured adjacent to the intended joint. A patch mix was used to repair the
loose concrete and later filled as intended with joint compound. The damaged joint
operated fine until the summer of its first year in service. It can be seen in Figure 4.23
that by mid-June with temperatures reaching new highs, the joint compound had started
to chip away due to the restrained joint operation. The following photographs (Figure
4.23 – Figure 4.25) illustrate problems with the joint compound in Panel A32. Initially,
when the joint compound was squeezed out of the joint it was expected that the joint may
deteriorate significantly in time and may exhibit poor performance. However, since the
joint compound chipped away due to normal traffic wear, the recorded concrete strain in
the panel were similar to that of the base panels located in the middle of the 250 ft
section. The joint appeared to be performing well in the most recent inspection in May
2007.
________________________________________________________________________
Page 83
Figure 4.23 – Flexible joint compound squeezing out on a hot day with minor amount
of chipping of rigid compound, Joint Panel A32 (June 27, 2006)
Figure 4.24 – Rigid joint compound chipped away more extensively, Joint Panel A32
(August 16, 2006)
________________________________________________________________________
Page 84
12 inches
Figure 4.25 – Moderate degradation to rigid joint compound, Joint Panel A32 (May 9,
2007)
________________________________________________________________________
Page 85
This page intentionally left blank.
________________________________________________________________________
Page 86
5. Conclusions
Missouri is performing well since being opened to traffic in January, 2006. The
pavement surface and prestressed system are in good condition aside from some visible
cracking. These cracks, which are present in the transverse and longitudinal directions,
are not expected to present problems with regard to the durability or long-term
performance of the pavement system. Possible reasons for the cracking observed under
The pilot project was successful and has provided useful insights into improving
fabrication and construction techniques that will benefit future projects. The structural
design of the panels and their economical implementation will only improve with the
The following sections outline the summary conclusions based on the evaluation
from construction, and visual inspections of the performance of the precast prestressed
pavement system.
________________________________________________________________________
Page 87
5.2. Construction Challenges
The first two challenges are interrelated and stem from the decision by the
contractor to lay all 101 panels before installing and post-tensioning strands in each of the
• Threading of the post-tensioning strands through the ducts for the 250 feet long
• The usage of epoxy between precast panels to facilitate proper alignment of panel
strands. The hardened epoxy bonded the panels together and resulted in the
sections behaving as a monolithic 250 ft. unit prior to stressing instead of 25 10-ft.
• Wooden and steel wedges (shims) were inserted between panels along the outer
placement. The use of these wedges affected the stress distribution during post-
________________________________________________________________________
Page 88
5.3. Service Performance
analysis, it was possible to isolate and measure strains from traffic loads,
all other types of loading (viscous effects such as creep, shrinkage and
ranging from 50-100 µstrain were observed for cool or mild days. Hot
µstrain.
transversely.
surface).
________________________________________________________________________
Page 89
5.4. Pavement Longevity
be without significant problems. The precast prestressed technology that has been
adapted for use as a pavement system has been proof-tested in previous decades of bridge
projects. However it would be naïve to say that among the multitude of pavement
problems that exist, none will arise. It is certain that many of the known significant
challenges, addressed earlier, have been targeted in the design of the prestressed
pavement system which will enable it to perform as well as or better than its traditional
pavement counterparts. The areas that are expected to meet or exceed design
• Ability of the pavement system to span voids that may form in the base
cracks are expected to stay closed. The smaller crack widths compared to
precasting yard.
extent of crack growth. If the extent of cracking is increasing, then potential causes could
be predicted with higher certainty by studying the problematic areas. Although the
________________________________________________________________________
Page 90
cracking currently present does not appear to have been or become detrimental to the
pavement system, it was not a desirable outcome. Further inspection and sampling on a
multi-seasonal level could provide useful data indicating the severity of the cracking and
In-situ chloride permeability tests should also be performed after the pavement
has been subjected to deicing salts to determine the rate of chloride ingress in the field.
These results can then be compared to baseline readings taken on virgin specimens and
compared to field results of other pavement types. This testing may provide useful
________________________________________________________________________
Page 91
REFERENCES
ASTM (2002). Standard Test Method for Flexural Strength of Concrete (Using Simple
Beam with Third-Point Loading, ASTM: 3.
ASTM (2002). Standard Test Method for Fundamental Transverse, Longitudinal, and
Torsional Resonant Frequencies of Concrete Specimens, ASTM: 7.
ASTM (2003). Standard Test Method for Resistance of Concrete to Rapid Freezing and
Thawing, ASTM: 6.
ASTM (2005). Standard Test Method for Compressive Strength of Cylindrical Concrete
Specimens, ASTM: 7.
ASTM (2005). Standard Test Method for Electrical Indication of Concrete's Ability to
Resist Chloride Ion Penetration, ASTM: 6.
Maxim (2007). iButton Instruction Manual Model DS1922L, Maxim IC, Inc.
________________________________________________________________________
Page 92
Merritt, D., F. B. McCullough, et al. (2000). The Feasibility of Using Precast Concrete
Panels to Expedite Highway Pavement Construction. Austin, TX.
________________________________________________________________________
Page 93
APPENDIX A
0 4 8 12 16 20 24
16 60
A32_T1 A32_T2
A32_T3 A32_T4 54
14 A32_T5 A32_T6
A32_T7 A32_T8
A32_V1t A32_V3t 48
12 A32_V4t Ambient Temp
Temperaturel, T (°F)
Temperature, T (°C)
42
10
36
8 30
6 24
18
4
12
2 Instrumentation Plan
R8
R6 R5 R2 6
V4 V2
T7-8
0 0
Inside Shoulder
Outside Shoulder
Traffic
T4-6 Direction
R7 R1 V1 T1-3
V3 R3 R4
60
Instrumented Vibrating Thermocouple
Rebar Wire Gage
45
Strain, ε (µstrain)
30
15
0
A32_R1 A32_R3
A32_R4 A32_R5
A32_V1c A32_V2c
-15 Theoretical
0 4 8 12 16 20 24
Time, t (Hours)
Figure A.1 – One day window from 12/27/2006 for Panel A32 (a) temperature
history (b) strain history
________________________________________________________________________
Page 94
APPENDIX B
The exact locations of instruments (rebars, thermocouples, vibrating wire) used in this
________________________________________________________________________
Page 95
Panel C1 X Y Z Depth X
(in) (in) (in) Section (in)
R1 31 45 3 6.3
R2 142 48 4 8.5
R3 264 52 7 11.0
R4 264 44 4 11.0
R5 384 62 4 8.5
T1 126 70 2 8.2
T2 126 70 4 8.2
T3 126 70 7 8.2
T4 364 52 2 8.9
T5 364 52 7 8.9
Table B.1 – Locations of instruments used in Panel C1
Panel
B1 X Y Z Depth X
(in) (in) (in) Section (in)
R1 29 60 2.5 6.2
R2 137 62 4 8.4
R3 252 55 4 10.8
R4 256 60 4 10.8
R5 378 62 4 8.6
T1 121 54 1 8.1
T2 121 54 3 5.6
T3 121 54 6 5.6
T4 366 68 3 8.9
T5 366 68 7 5.6
V1 137 62 4 8.4
V2 256 60 4 10.8
Table B.2 – Locations of instruments used in Panel B1
________________________________________________________________________
Page 96
Panel
B2 X Y Z Depth X
(in) (in) (in) Section (in)
R1 27 60 4 6.2
R2 142 60 4 8.5
R3 254 56 4 10.8
R4 260 62 4 10.9
R5 392 47 4 8.3
T1 142 67 1 8.5
T2 142 67 3 8.5
T3 142 67 7 8.5
T4 364 52 1 8.9
T5 364 52 6 8.9
V1 142 60 4 8.5
V2 260 62 4 10.9
Table B.3 – Locations of instruments used in Panel B2
Panel
B3 X Y Z Depth X
(in) (in (in) Section (in)
R1 20 46 3 6.0
R2 138 62 4 8.4
R3 251 54 2 10.7
R4 262 59 4 11.0
R5 379 60 4 8.6
T1 145 57 2 8.6
T2 145 57 4 8.6
T3 145 57 6 8.6
T4 289 58 3 10.5
T5 289 58 6 10.5
T6 289 58 8 10.5
T7 361 67 2 9.0
T8 361 67 4 9.0
V1 138 62 4 8.4
V2 262 59 4 11.0
Table B.4 – Locations of instruments used in Panel B3
________________________________________________________________________
Page 97
Panel
B4 X Y Z Depth X
(in) (in) (in) Section (in)
R1 31 61 3 6.3
R2 140 63 4 8.5
R3 255 54 2.5 10.8
R4 264 61 4 11.0
R5 375 62 4 8.7
T1 145 54 1 8.6
T2 145 54 4 8.6
T3 145 54 7 8.6
T4 355 54 2 9.1
T5 355 54 4 9.1
T6 355 54 7 9.1
V1 140 63 4 8.5
V2 264 61 4 11.0
Table B.5 – Locations of instruments used in Panel B4
________________________________________________________________________
Page 98