JOB-CARD
DISCIPLINE Piping
PROJECT Bukit Tua JOB CARD NO. MCCS-WP087-JC-P-002
SUB-SYSTEM NO. Various
ACTIVITY Oustanding Support Installation
WORK STARTED ON WORK DURATION
WORK DESCRIPTION (Refer to the next page)
1) Installation of additional Supports
TESTING CLEANING SAFETY SPECIAL
Hydro Test Flushing √ PPE √
RT Blowing JSA Attached √
MT Other Dropped Object Protection √
PT √ Lifting Plan √
UT Others √
√ Visual Inspection
Other
WORK SCOPE ✘ ORIGINAL BASE SCOPE ✘ PUNCH LIST CARRY OVER
VENDOR CALL OUT DATE N/A VENDORS WORK DURATION N/A
MANPOWER
CATEGORY PERSON DUR MANHOUR CATEGORY
SUPERVISOR 1.0 0.2 2.4 SCAFFOLDER
FITTER 1.0 0.2 2.4 Flange Management Crew
0.0 TOTAL
DRAWING / PROCEDURE
NO. DRAWING / PROCEDURE NO. REV DESCRIPTION
1 6 Tackwelded Support (TBA) 0A Tackweld to be completed
2 1 Outstanding support (TBA) 0A Lifted and weld in position
3 1 Seadeck Hosereel Support (TBA) 0A Lifted and weld in position
WORK ORIGINATOR MCCS HUC PTTI HUC
COMMENCE
WORK ORIGINATOR MCCS HUC PTTI HUC
COMPLETED
JOB-CARD
DISCIPLINE Piping
PROJECT Bukit Tua JOB CARD NO. MCCS-WP087-JC-P-002
SUB-SYSTEM NO. 0 Various
ACTIVITY Oustanding Support Installation
WORK STARTED ON 12/30/1899 WORK DURATION
S/N ITEM WORK DESCRIPTION
1 Tackwelded Supports (TBA) Complete Tackweld to fullweld in position
2 Outstanding support (TBA) Lift and fullweld into position
3 Hosereel Support (TBA) Lift and fullweld into position
S/N ITEM MATERIAL DESCRIPTION
S/N ITEM TOOL LIST DESCRIPTION
1
2
SHEET NO. 1 OF 2
REV.NO. B1
PREPARED Andre Austria
WORK PACK NO. MCCS-WP087
LOCATION Below Scdeck/SD
3.0 days
page)
SPECIAL EQUIPMENT PROTECTION
Lifting / Rigging √ Painting
Access Scaffold Insulation
Support Scaffold PFP
Welding Equipment Others
Cutting Equipment
Torque Wrench
Crane
CARRY OVER WORKS
VENDORS NAME N/A
PERSON DUR MANHOUR
2.0 1.0 24.0
1.0 0.2 2.4
0.0
5.0 1.0 31.2
RIPTION REMARK
o be completed
weld in position
weld in position
PTTI HUC PCK2L HUC
PTTI HUC PCK2L HUC
SHEET NO. 2 OF 2
REV.NO. B1
PREPARED Andre Austria
WORK PACK NO. MCCS-WP087
LOCATION Below Scdeck/SD
3.0 days
Q'TY WT(KG) Remarks
6
1
1
Q'TY Packing No.
Q'TY Packing No.
JOB-CARD
DISCIPLINE Piping
PROJECT Bukit Tua JOB CARD NO. MCCS-WP087-JC-P-001
SUB-SYSTEM NO. Flowline
ACTIVITY Additional Support Installation
WORK STARTED ON WORK DURATION
WORK DESCRIPTION (Refer to the next page)
1) Installation of additional Supports
TESTING CLEANING SAFETY SPECIAL
Hydro Test Flushing √ PPE √
RT Blowing JSA Attached √
MT Other Dropped Object Protection √
PT Lifting Plan √
UT Others √
√ Visual Inspection
Other
WORK SCOPE ✘ ORIGINAL BASE SCOPE ✘ PUNCH LIST CARRY OVER
VENDOR CALL OUT DATE N/A VENDORS WORK DURATION N/A
MANPOWER
CATEGORY PERSON DUR MANHOUR CATEGORY
SUPERVISOR 1.0 0.2 2.4 SCAFFOLDER
FITTER 1.0 0.2 2.4 Flange Management Crew
0.0 TOTAL
DRAWING / PROCEDURE
NO. DRAWING / PROCEDURE NO. REV DESCRIPTION
1 /PDBALL-300-P-0405-151430X(ET)-01 0A Flowline
2 /PDBALL-250-P-0409-151430X(ET)-01 0A Flowline
3 /PDBALL-500-P-0449-31430X(ET)-01 0A Flowline
PSA-MD-9000
PSA-MD-9001
MD-06-7602
MZ-06-7743
ORIGINATOR MCCS HUC PTTI HUC
WORK
COMMENCE
ORIGINATOR MCCS HUC PTTI HUC
WORK
COMPLETED
JOB-CARD
DISCIPLINE Piping
PROJECT Bukit Tua JOB CARD NO. MCCS-WP087-JC-P-001
SUB-SYSTEM NO. 0 Flowline
ACTIVITY Additional Support Installation
WORK STARTED ON 12/30/1899 WORK DURATION
S/N ITEM WORK DESCRIPTION
Pipe Support inverted goal post (/PSA-MD-9000
1 Weld to Deck beam below Main deck
w/ stopper)
Pipe Support L-type (/PSA-MD-9001 w/ guide) Weld to Deck beam below Main deck
Pipe Support Hold down Guide installation welded to existing support /PSA-MD-7602(P-0405)
Pipe Support Hold down Guide installation welded to existing support /PSA-MD-7602(P-0409)
Pipe Support Stopper installation welded to existing shoe support /PSA-MZ-7743(P-0449)
S/N ITEM MATERIAL DESCRIPTION
1 PSA-MD-9000
2 PSA-MD-9001
3 Hold down Guide
4 Stopper
S/N ITEM TOOL LIST DESCRIPTION
1
2
SHEET NO. 1 OF 2
REV.NO. B1
PREPARED Andre Austria
WORK PACK NO. MCCS-WP087
LOCATION Below Main deck
1.0 days
PTION (Refer to the next page)
SPECIAL EQUIPMENT PROTECTION
Lifting / Rigging √ Painting
Access Scaffold Insulation
Support Scaffold PFP
Welding Equipment Others
Cutting Equipment
Torque Wrench
Crane
CARRY OVER WORKS
VENDORS NAME N/A
MANPOWER
PERSON DUR MANHOUR
2.0 1.0 24.0
1.0 0.2 2.4
0.0
5.0 1.0 31.2
WING / PROCEDURE
DESCRIPTION REMARK
Flowline
Flowline
Flowline
PTTI HUC PCK2L HUC
PTTI HUC PCK2L HUC
SHEET NO. 2 OF 2
REV.NO. B1
PREPARED Andre Austria
WORK PACK NO. MCCS-WP087
LOCATION Below Main deck
1.0 days
Q'TY WT(KG) Remarks
Q'TY Packing No.
1
1
2
2
Q'TY Packing No.
JOB-CARD
DISCIPLINE Piping
PROJECT Bukit Tua JOB CARD NO. MCCS-WP036-JC-P-003
SUB-SYSTEM NO. 251DH-02 Open Non Hazardous Drains Collection
ACTIVITY Vessel Trim Installation on Caisson
WORK STARTED ON WORK DURATION
WORK DESCRIPTION (Refer to the next page)
1) Installation of vessel trim spool
TESTING CLEANING SAFETY SPECIAL E
Hydro Test Flushing √ PPE
RT Blowing √ JSA Attached √
MT Other Dropped Object Protection
PT Lifting Plan
UT Others
√ Visual Inspection √
Other
WORK SCOPE ✘ ORIGINAL BASE SCOPE PUNCH LIST CARRY OVER
VENDOR CALL OUT DATE N/A VENDORS WORK DURATION N/A
MANPOWER
CATEGORY PERSON DUR MANHOUR CATEGORY
SUPERVISOR 1.0 0.2 2.4 SCAFFOLDER
FITTER 1.0 0.2 2.4 Flange Management Crew
0.0 TOTAL
DRAWING / PROCEDURE
NO. DRAWING / PROCEDURE NO. REV DESCRIPTION
1 PXBALL-50-VT-6520-11430X-01 0 Open Drain Hazardous Drawings
2 BTJT-A-B-1023-0 0A Open Drain Tank and Caisson
ORIGINATOR MCCS HUC PTTI HUC
WORK
COMMENCE
ORIGINATOR MCCS HUC PTTI HUC
WORK
COMPLETED
JOB-CARD
DISCIPLINE Piping
PROJECT Bukit Tua JOB CARD NO. MCCS-WP036-JC-P-003
SUB-SYSTEM NO. 251DH-02 Open Non Hazardous Drains Collection
ACTIVITY Vessel Trim Installation on Caisson
WORK STARTED ON 12/30/1899 WORK DURATION
S/N ITEM WORK DESCRIPTION
Installation of vessel trim spool on open drain
1 pipe spool
caisson
S/N ITEM MATERIAL DESCRIPTION
1 Gasket 6" tanged insert 150# ASME B16.21 Graphite
2 Gasket 4" tanged insert 150# ASME B16.21 Graphite
3 Stud bolts 3/4 x 100 ASTM A-193-B7;nuts ;ASTM A194-2H
4 Stud bolts 5/8 x 100 ASTM A-193-B7;nuts ;ASTM A194-2H
S/N ITEM TOOL LIST DESCRIPTION
1 Flange Management Crew Tools various handtools
2 Pipe Fitter Tools various handtools
SHEET NO. 1 OF 2
REV.NO. B1
PREPARED Andre Austria
WORK PACK NO. MCCS-WP036
LOCATION Sea Deck
1.0 days
PTION (Refer to the next page)
SPECIAL EQUIPMENT PROTECTION
Lifting / Rigging Painting
Access Scaffold Insulation
Support Scaffold PFP
Welding Equipment Others
Cutting Equipment
Torque Wrench
Crane
CARRY OVER WORKS
VENDORS NAME N/A
MANPOWER
PERSON DUR MANHOUR
2.0 1.0 24.0
1.0 0.2 2.4
0.0
5.0 1.0 31.2
WING / PROCEDURE
DESCRIPTION REMARK
Open Drain Hazardous Drawings
Open Drain Tank and Caisson
PTTI HUC PCK2L HUC
PTTI HUC PCK2L HUC
SHEET NO. 2 OF 2
REV.NO. B1
PREPARED Andre Austria
WORK PACK NO. MCCS-WP036
LOCATION Sea Deck
1.0 days
Q'TY WT(KG) Remarks
Revised drawing required
to eliminate vessel trim
1
direct mounting on
caisson nozzle
Q'TY Packing No.
1 BOX 06 / BOX#A
1 BOX 06 / BOX#A
8 BOX #02
8 BOX #02
Q'TY Packing No.
1 lot TBA
1 lot TBA
JOB-CARD
DISCIPLINE Piping
PROJECT Bukit Tua JOB CARD NO. MCCS-WP021-JC-P-001
SUB-SYSTEM NO. Flowline
ACTIVITY Additional Support Installation
WORK STARTED ON WORK DURATION
WORK DESCRIPTION (Refer to the next page)
1) Modification of FW Monitor Supports (6 places)
2) Installation of FW hook-up spool
TESTING CLEANING SAFETY SPECIAL EQ
Hydro Test Flushing √ PPE √
RT Blowing JSA Attached √
MT Other Dropped Object Protection √
PT Lifting Plan
UT Others √
√ Visual Inspection
Other
WORK SCOPE ✘ ORIGINAL BASE SCOPE ✘ PUNCH LIST
VENDOR CALL OUT DATE N/A VENDORS WORK DURATION N/A
MANPOWER
CATEGORY PERSON DUR MANHOUR CATEGORY
SUPERVISOR 1.0 0.2 2.4 SCAFFOLDER
FITTER 1.0 0.2 2.4 Flange Management Crew
0.0 TOTAL
DRAWING / PROCEDURE
NO. DRAWING / PROCEDURE NO. REV DESCRIPTION
1 /PXBALL-150-FW-5313-17161X-01-MOD 0A Connect 2 spools
/PXBALL-150-FW-5310-17161X-01-MOD Increase spool length Connectin to FW mo
/PXBALL-150-FW-5309-17161X-01-MOD Increase spool length Connectin to FW mo
/PXBALL-150-FW-5307-17161X-01-MOD Increase spool length Connectin to FW mo
/PXBALL-150-FW-5306-17161X-01-MOD Increase spool length Connectin to FW mo
/PXBALL-150-FW-5303-17161X-01-MOD Increase spool length Connectin to FW mo
/PXBALL-150-FW-5302-17161X-01-MOD Increase spool length Connectin to FW mo
2 PSA-MD-7562 0A FW Monitor Support
3 PSA-MD-7511 0A FW Monitor Support
4 PSA-MZ-7628 0A FW Monitor Support
5 PSA-MZ-7795 0A FW Monitor Support
6 PSA-CD-8069 0A FW Monitor Support
7 PSA-CD-8027 0A FW Monitor Support
ORIGINATOR MCCS HUC PTTI HUC
WORK
COMMENCE
ORIGINATOR MCCS HUC PTTI HUC
WORK
COMPLETED
JOB-CARD
DISCIPLINE Piping
PROJECT Bukit Tua JOB CARD NO. MCCS-WP021-JC-P-001
SUB-SYSTEM NO. 0 Flowline
ACTIVITY Additional Support Installation
WORK STARTED ON 12/30/1899 WORK DURATION
S/N ITEM WORK DESCRIPTION
Extend elevation by adding additional
1 Pipe Supports (6 places)
Channel
2 conect spool 1 and 2 of FW hook-up spools conect spool 1 and 2 of FW hook-up spools
3 Spool1 connect hook-up spool to the topside piping
Fixe Hook-up spool to the support at Boat
4 Spool2 landing
5 Valve, Hose connection Bolt valves and Hose connections
Increase spool length Connectin to FW monitor (6
Cut and install new pup piece and bolt to FW monitors
places)
S/N ITEM MATERIAL DESCRIPTION
S/N ITEM TOOL LIST DESCRIPTION
1
2
SHEET NO. 1 OF 2
REV.NO. B1
PREPARED Andre Austria
WORK PACK NO. MCCS-WP021
LOCATION All Decks
4.0 days
he next page)
SPECIAL EQUIPMENT PROTECTION
Lifting / Rigging Painting
Access Scaffold Insulation
Support Scaffold PFP
Welding Equipment Others
Cutting Equipment
Torque Wrench
Crane
CARRY OVER WORKS
VENDORS NAME N/A
PERSON DUR MANHOUR
2.0 1.0 24.0
1.0 0.2 2.4 1
0.0
5.0 1.0 31.2
RE
SCRIPTION REMARK
nect 2 spools
gth Connectin to FW monitor
gth Connectin to FW monitor
gth Connectin to FW monitor
gth Connectin to FW monitor
gth Connectin to FW monitor
gth Connectin to FW monitor
Monitor Support
Monitor Support
Monitor Support
Monitor Support
Monitor Support
Monitor Support
PTTI HUC PCK2L HUC
PTTI HUC PCK2L HUC
SHEET NO. 2 OF 2
REV.NO. B1
PREPARED Andre Austria
WORK PACK NO. MCCS-WP021
LOCATION All Decks
4.0 days
Q'TY WT(KG) Remarks
6
2,2
Q'TY Packing No.
Q'TY Packing No.