            18.BECHTEL INC / PURNA BINA INDONESIA PT
                          AUGUST 30, I990 TO MAY 12, 1991
LOCATION     : SANGATA, SAMBERA, BONTANG, EAST KALIMANTAN.
JOB          : 1. WEREHOUSE BILDING KALTIM PRIMA COAL
               2. SAMBERA GAS PLANT VICO PROJECT
               3. TRAIN F.BADAK LNG.
CERTFIED    : NPS Ǿ 6” SMAW UP HILL (6G) ASME IX ( MIGAS )
               NPS Ǿ 6” SMAW HORIZONTAL (2G) ASME IX ( MIGAS )
MANAGER     : HAMKA LAREWA / JAPIE. FRITZ TAMPUBOLON / WARIS HN,
               EDWARD / MR. DANCEN / MR. NIEM SYAH. SANGAJI
            19 .BDP ( BALAST DECORINE PETROSEA ) JO.
               JAN 26 ,1990 TO JULY 13,1990
LOCATION    : SANGATA EAST KALIMANTAN
JOB         : KALTIM PRIMA COAL COMPEYOR & PLANT PROJECT
CERTIFIED   ; PLATE T20 MM CS SMAW HORIZONTAL (2G) AWS D.1.1
             PLATE T20 MM CS SMAW VERTICAL UP (3G) AWS D. 1.1
             PLATE T20 MM CS SMAW OVER HEAD (4G) AWS D.1.1
             PLATE T20 MM CS FCAW HORIZONTAL (2G) AWS D.1.1
             PLATE T20 MM CS FCAW VERTICAL UP (3G) AWS D.1.1
             PLATE T20 MM CS FCAW OVER HEAD (4G) AWS D.1.1
SUV/ QC/WE/
MANAGER : MR. BILL ROMORO / MR. RENE COLMEN / MR. H BLOOM
            . 20. BECHTEL INC / PURNA BINA INDONESIA PT
                         MARCH 26, 1987 TO NOV 29, 1989
LOCATION     : BONTANG EAST KALIMANTAN
JOB          : COOLING WATER,TRAIN E. BADAK LNG PROJECT
CERTIFIED    : NPS Ǿ 6” CS SMAW HORIZONTAL (2G) ASME IX (MIGAS)
             NPS Ǿ 6” CS SMAW UP HILL (5G) ASME IX (MIGAS)
SUV/QCWE/
MANAGER      : HAMKA LAREWA / JAPIE. / WARIS HN. / MR. NIEM SYAH.
                       21. CV. RENO SARI
                        JAN ,1984 TO SEPT 1985
 LOCATION : MUARA BADAK EAST KALIMANTAN
JOB       : OIL & GAS PLANT HUFFCO (VICO) PROJECT
CERTIFIED : NPS Ǿ 6” CS SMAW UP HILL (5G) ASME IX (MIGAS)
          NPS Ǿ 6” CS SMAW DOWN HILL (5G) ASME IX ( MIGAS)
MANAGER    : JONIZAR