Project Management Professional (PMP) ® Exam Prep Course 7 - Project Cost Management
Project Management Professional (PMP) ® Exam Prep Course 7 - Project Cost Management
Exam Prep
Course 7 - Project Cost Management
Slide 1
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
Slide 2
                            Cost Management
             All the process involved in planning, estimating,
             budgeting and controlling costs so that the
             project can be completed within the approved
             budget.                                                         Planning Process Group
                                                                                    7. Project Cost
                                                                                     Management
                                                                                         7.1
                                                                                      Plan Cost
                                                                                     Management
                                             7.4                                         7.3
                                           Control                                    Determine
                                            Costs                                      Budget
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
Slide 3
                            Cost Management
              Primarily concerned with cost of resources.
              Also concerned with
                 – Life-cycle costing
                 – Opportunity cost
                 – Sunk costs
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
Slide 4
                           Cost Management
                      7.1 Plan Cost Management
             Defining the rules which are used to manage
              project costs.
             It defines how the team will                                 Planning Process Group
                                                                                       7.1
                                                                                    Plan Cost
                                                                                   Management
                                                                                        7.2
                                                                                     Estimate
                                                                                      Costs
                                                                                       7.3
                                                                                    Determine
                                                                                     Budget
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
Slide 5
                                   Cost Management
                           7.1 Plan Cost Management
                    Inputs               Tools & Techniques                           Outputs
             .1 Project charter            .1 Expert judgment                      .1 Cost management
             .2 Project management         .2 Data analysis                           plan
                plan                       .3 Meetings
             .3 Enterprise
                environmental factors
             .4 Organizational process
                assets
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
Slide 6
                           Cost Management
                             7.2 Estimate Costs
             Developing an approximation of the costs of
              the resources needed to complete each
              schedule activity                                            Planning Process Group
                                                                                  7. Project Cost
                                                                                   Management
                                                                                        7.2
                                                                                     Estimate
                                                                                      Costs
                                                                                       7.3
                                                                                    Determine
                                                                                     Budget
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
Slide 7
                                   Cost Management
                                     7.2 Estimate Costs
                    Inputs               Tools & Techniques                            Outputs
             .1 Project management         .1 Expert judgment                      .1 Cost estimates
                plan                       .2 Analogous estimating                 .2 Basis of estimates
             .2 Project documents          .3 Parametric estimating                .3 Project documents
             .3 Enterprise                 .4 Bottom-up estimating                    updates
                environmental factors      .5 Three-point
             .4 Organizational process        estimating
                assets                     .6 Data analysis
                                           .7 Project management
                                              information system
                                           .8 Decision making
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
Slide 8
                           Cost Management
             Accuracy of estimates increases as the
             project progresses
             Rough Order of Magnitude
                    -25% to +75%
             Budget Estimate or the Budget
                    -5% to +10%
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
Slide 9
                           Cost Management
                          7.3 Determine Budget
              Aggregating the cost estimates of
              individual activities or work packages to
              establish a total Cost Baseline.                             Planning Process Group
                                                                                  7. Project Cost
                                                                                   Management
                                                                                       7.1
                                                                                    Plan Cost
                                                                                   Management
                                                                                        7.2
                                                                                     Estimate
                                                                                      Costs
                                                                                       7.3
                                                                                    Determine
                                                                                     Budget
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
Slide 10
                           Cost Management
                               Accounting Terms
             Variable Costs – Costs that change as the units produced
              changes.
             Fixed Costs – Costs that do not change with changes to
              volume produced.
             Direct Costs – Costs that are directly attributed to
              project work.
             Indirect Costs – Items that benefit more than one
              project and are not attributed to a specific activity.
             Value Analysis or Engineering – Finding less costly ways
              to do the same work. © Copyright and all rights reserved –
                                    Looking Glass Development, LLC.
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
Slide 11
                                   Cost Management
                                 7.3 Determine Budget
                     Inputs              Tools & Techniques                                   Outputs
             .1 Project management        .1 Expert judgment                           .1 Cost baseline
                plan                      .2 Cost aggregation                          .2 Project funding
             .2 Project documents         .3 Data analysis                                requirements
             .3 Business documents        .4 Historical information                    .3 Project documents
             .4 Agreements                   review                                       updates
             .5 Enterprise                .5 Funding limit
                environmental factors        reconciliation
             .6 Organizational process    .6 Financing
                assets
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
Slide 12
                                Cost Management
                                                                           The difference
             Funding Requirements                                         between the
                                                                           maximum
                                                                           funding and the
                                                                           end of the cost
                                                                           baseline is
                                                                           Management
                 Cumulative $
Reserve.
                                                               Cost Baseline
                                                               Actual Costs
                                                               Funding Requirements
Time
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
Slide 13
                           Cost Management
                                Depreciation
             Straight Line Depreciation – Present value
              minus present cost.
                                                Depreciation amt. to deduct
                  cost – residual value       = each year till salvage value
                       useful life              is reached
             Production Method -
                     cost – residual value                       Depreciation amt. to
                                                               = deduct each year till
           estimated units of useful life           (production) salvage value is
                                                                 reached
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
Slide 14
                              Cost Management
                                      Depreciation
            Double Declining Balance (DDB) – Accelerated depreciation method. Begin
            by dividing 100% by the term of the asset and doubling the result. Each
            subsequent year, that same percentage is multiplied by the remaining
            balance to be depreciated. Using a purchase price of $100,000 and a
            residual of $25,000 on a five (5) year schedule:
                   100% / 5 Year Term = 20%
                   Double the 20% rate or 40%
                   Year 1 value = $100,000 - ($100,000 * 40%) = $60,000
                   Year 2 value = $60,000 – ($60,000 * 40%) = $36,000
                   Year 3 value = $36,000 – ($36,000 * 40%) = $21,600
                   Since this is less than the salvage value it is $25,000
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
Slide 15
                            Cost Management
                                   Depreciation
             Sum of the Years Digits (SYD) – Accelerated depreciation method.
             Begin by adding the number of years in the schedule. For example,
             for a five (5) year schedule add 1+2+3+4+5 = 15. Next, take the
             asset value minus the residual value and divide it by this result
             (15). If the salvage value is $25,000 then:
                   Year 1 value = $100,000 – (5/15 * $75,000) = $75,000
                   Year 2 value = $75,000 – (4/15 * $75,000) = $55,000
                   Year 3 value = $55,000 – (3/15 * $75,000) = $40,000
                   Year 4 value = $40,000 – (2/15 * $75,000) = $30,000
                   Year 5 value = $30,000 – (1/15 * $75,000) = $25,000
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
Slide 16
                              Cost Management
                                 7.4 Control Costs
               Influencing the factors that create changes to the
                cost baseline.
               Ensuring requested changes are agreed upon.
               Managing the actual changes when and as they
                occur.
               Assuring that potential cost overruns do not exceed
                the authorized funding periodically and in total for
                the project.                 Monitoring and Controlling Process Group
                                                                                7. Project Cost
                                                                                 Management
                                                                                      7.4
                                                                                    Control
                                                                                     Costs
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
Slide 17
                                  Cost Management
                                        7.4 Control Costs
                    Inputs                Tools & Techniques                             Outputs
             .1 Project management          .1 expert judgment                     .1 Work performance
               plan                         .2 Data analysis                          information
            .2 Project documents            .3 To-complete                         .2 Cost forecasts
            .3 Project funding                 performance index                   .3 Change requests
               requirements                 .4 Project management                  .4 Project management
            .4 Work performance data           information system                     plan updates
            .5 Organizational process                                              .5 Project document
               assets                                                                 updates
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
Slide 18
                        Cost Management
                          Cumulative Cost Curve                                           EAC
VALUE PV BAC
                                                                            SCHEDULE
                               AC                                           VARIANCE
                                                              COST
                                                          VARIANCE
                                          EV
                        SLIPPAGE
                                                                                   TIME
                                   NOW
                                    © Copyright and all rights reserved –
                                     Looking Glass Development, LLC.
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
Slide 19
Cost Management
                           In Alphabetical Order
                 Actual Costs    Earned Value    Planned Value
                           Minus             Minus
                CV =                                                       = SV
               CPI =                                                       = SPI
                          Divided By                         Divided By
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
Slide 20
                            Cost Management
                              Forecasting - ETC
                ETC based on new estimate.
                ETC based on atypical variances.
                  ETC = BAC-EV
                ETC based on typical variances.
                  ETC = (BAC-EV)/CPI
                ETC based on both the CPI & SPI.
                  ETC = (BAC-EV)/(CPI*SPI)
                                                          BAC = Budget at Completion
                                                          BAC-EV = Remaining Work
                                                          VAC = Variance at Completion
                                                          CPI*SPI = Critical Ratio
                                    © Copyright and all rights reserved –
                                     Looking Glass Development, LLC.
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
Slide 21
                           Cost Management
                              Forecasting - EAC
                Using a new estimate
                    – EAC = AC + ETC
                Using remaining budget
                    – EAC = AC + (BAC-EV)
                Using CPI
                    – EAC = AC + ((BAC-EV)/CPI)
                Using both CPI & SPI
                    – EAC = AC + ((BAC-EV)/(CPI*SPI))
                                   © Copyright and all rights reserved –
                                    Looking Glass Development, LLC.
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
Slide 22
                            Cost Management
                               Forecasting - TCPI
                 The calculated projection of cost performance
                  that must be achieved on the remaining work
                  to meet a specified management goal.
                 Using BAC
                    – TCPI = (BAC – EV) / (BAC – AC)
                 Using EAC
                    – TCPI = (BAC - EV) / (EAC - AC)
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
Slide 23
                           Cost Management
                         Earned Schedule Theory
                 Provides formulas for forecasting the project
                  completion date, using the earned schedule,
                  actual time and estimated duration.
                 Schedule at Completion (SAC) — This is the
                  original planned completion duration of the
                  project.
                 Earned Schedule (ES) — The duration from
                  the beginning of the project to the date the
                  planned value is supposed to equal to the
                  BAC.
                 Actual Time (AT) — This is the duration from
                  the beginning of the project to status date.
                                   © Copyright and all rights reserved –
                                    Looking Glass Development, LLC.
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
Slide 24
                          Cost Management
                        Earned Schedule Theory
                Time variance or (TV) — A measure of
                 schedule performance in time units rather
                 than cost units and is defined by the
                 formula:
                                TV = ES – AT
                Time Estimate at Completion (TEAC) — The
                 forecast of time at completion and is
                 similar to EAC. It uses the same basic
                 formulas as EAC but replaces cost with
                 schedule.
                                   © Copyright and all rights reserved –
                                    Looking Glass Development, LLC.
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
Slide 25
                          Cost Management
                        Earned Schedule Theory
                Time Variance at Completion (TVAC) — The
                 estimated amount of time either ahead or
                 behind schedule the project is. It uses the
                 following formula:
                             TVAC = SAC – TEAC
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
Slide 26
                           Cost Management
                    Cost Management – Summary
               Four (4) processes.
               Earned value concepts and calculations.
               Life cycle costing.
               Cost baseline.
               Estimating vs. budgeting.
               Types of estimates and estimating.
               Contingency and management reserve.
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
Review Questions – Part 1:
  1. You are a project manager and have been asked to assess the value of an asset
     on your project at the end of year four using straight line depreciation. Assuming
     the asset costs $100,000 to purchase, has a residual value of $25,000, and is
     depreciated based on a five year schedule what is the assessed value?
        A. $25,000
        B. $40,000
        C. $65,000
        D. $85,000
  2. You are a project manager and have been asked to assess the value of an asset
     on your project at the end of year three using straight line depreciation. Assuming
     the asset costs $225,000 to purchase, has a residual value of $35,000, and is
     depreciated based on a five year schedule what is the assessed value?
        A. $187,000
        B. $149,000
        C. $111,000
        D. $73,000
  3. You are a project manager and have been asked to assess the value of an asset
     on your project at the end of year one using straight line depreciation. Assuming
     the asset costs $75,000 to purchase, has a residual value of $12,500, and is
     depreciated based on a three year schedule what is the assessed value?
        A. $75,000
        B. $12,500
        C. $33,333
        D. $54,167
  4. You are a project manager and have been asked to assess the value of an asset
     on your project at the end of year three (3) using straight line depreciation.
     Assuming the asset costs $50,000 to purchase, has a residual value of $10,000,
     and is depreciated based on a three (3) year schedule what is the assessed
     value?
        A. $10,000
        B. $13,333
        C. $23,333
        D. $36,667
5. You are a project manager and have been asked to assess the value of an asset
   on your project at the end of year three using straight line depreciation. Assuming
   the asset costs $250,000 to purchase, has a residual value of $50,000, and is
   depreciated based on a five year schedule what is the assessed value?
      A. $210,000
      B. $175,000
      C. $130,000
      D. $110,000
6. You are a project manager for a manufacturing company. You are asked to
   determine the depreciated value for a piece of equipment using the UOP method.
   If the piece of equipment initially cost $1,000,000, has a residual value of
   $25,000, has a useful life of 10,000,000 units produced, and has already
   produced 1,000,000 units what is its current value?
        A. $900,000
        B. $902,500
        C. $875,000
        D. $800,000
7. You are a project manager for a manufacturing company. You are asked to
   determine the depreciated value for a piece of equipment using the UOP method.
   If the piece of equipment initially cost $750,000, has a residual value of $40,000,
   has a useful life of 8,000,000 units produced, and has already produced
   2,500,000 units what is its current value?
        A. $375,500
        B. $768,250
        C. $625,500
        D. $528,125
8. You are a project manager for a manufacturing company. You are asked to
   determine the depreciated value for a piece of equipment using the UOP method.
   If the piece of equipment initially cost $500,000, has a residual value of $65,000,
   has a useful life of 7,500,000 units produced, and has already produced 310,000
   units what is its current value?
        A. $365,500
        B. $532,250
        C. $482,020
        D. $525,010
9. You are a project manager for a manufacturing company. You are asked to
   determine the depreciated value for a piece of equipment using the UOP method.
   If the piece of equipment initially cost $250,000, has a residual value of $15,000,
   has a useful life of 5,500,000 units produced, and has already produced
   4,100,000 units what is its current value?
        A. $72,652
        B. $74,818
        C. $76,534
        D. $81,225
10. You are a project manager for a manufacturing company. You are asked to
    determine the depreciated value for a piece of equipment using the UOP method.
    If the piece of equipment initially cost $2,000,000, has a residual value of
    $68,000, has a useful life of 15,000,000 units produced, and has already
    produced 7,200,000 units what is its current value?
         A. $1,072,640
         B. $1,528,860
         C. $925,310
         D. $875,687
11. You are a project manager and have been asked to assess the value of an asset
    on your project at the end of year two using DDB. Assuming the asset costs
    $100,000 to purchase, has a residual value of $25,000, and is depreciated based
    on a five year schedule what is the assessed value?
       A. $60,000
       B. $36,000
       C. $25,000
       D. $21,400
12. You are a project manager and have been asked to assess the value of an asset
    on your project at the end of year three using DDB. Assuming the asset costs
    $250,000 to purchase, has a residual value of $35,000, and is depreciated based
    on a five year schedule what is the assessed value?
       A. $54,000
       B. $64,000
       C. $90,000
       D. $150,000
13. You are a project manager and have been asked to assess the value of an asset
    on your project at the end of year four using DDB. Assuming the asset costs
    $650,000 to purchase, has a residual value of $52,000, and is depreciated based
    on a five year schedule what is the assessed value?
       A. $390,000
       B. $234,512
       C. $140,375
       D. $84,240
14. You are a project manager and have been asked to assess the value of an asset
    on your project at the end of year two using DDB. Assuming the asset costs
    $79,800 to purchase, has a residual value of $12,000, and is depreciated based
    on a three year schedule what is the assessed value?
       A. $26,600
       B. $12,000
       C. $6,500
       D. $18,460
15. You are a project manager and have been asked to assess the value of an asset
    on your project at the end of year two using DDB. Assuming the asset costs
    $150,000 to purchase, has a residual value of $10,000, and is depreciated based
    on a three year schedule what is the assessed value?
       A. $50,000
       B. $36,450
       C. $16,667
       D. $10,000
16. You are a project manager and have been asked to assess the value of an asset
    on your project at the end of year three using SYD. Assuming the asset costs
    $100,000 to purchase, has a residual value of $25,000, and is depreciated based
    on a five year schedule what is the assessed value?
       A. $55,000
       B. $45,000
       C. $40,000
       D. $35,000
17. You are a project manager and have been asked to assess the value of an asset
    on your project at the end of year two using SYD. Assuming the asset costs
    $250,000 to purchase, has a residual value of $29,000, and is depreciated based
    on a three year schedule what is the assessed value?
       A. $65,833
       B. $59,561
       C. $55,610
       D. $49,900
18. You are a project manager and have been asked to assess the value of an asset
    on your project at the end of year three using SYD. Assuming the asset costs
    $350,000 to purchase, has a residual value of $33,000, and is depreciated based
    on a four year schedule what is the assessed value?
       A. $48,750
       B. $55,800
       C. $61,900
       D. $64,700
19. You are a project manager and have been asked to assess the value of an asset
    on your project at the end of year two using SYD. Assuming the asset costs
    $450,000 to purchase, has a residual value of $41,000, and is depreciated based
    on a four year schedule what is the assessed value?
       A. $159,900
       B. $163,700
       C. $165,500
       D. $169,200
20. You are a project manager and have been asked to assess the value of an asset
    on your project at the end of year three using SYD. Assuming the asset costs
    $550,000 to purchase, has a residual value of $62,500, and is depreciated based
    on a four year schedule what is the assessed value?
       A. $111,250
       B. $118,500
       C. $125,200
       D. $130,500
Review Questions – Part 2:
  1. Which of the following variables represents the budgeted cost for the work
     scheduled to be completed up to a given point?
        A. Actual cost
        B. Planned value
        C. Earned value
        D. Estimate at completion
  2. Which of the following variables represents the budgeted amount for the work
     completed on the schedule activity up to a given point?
        A. Planned value
        B. Actual costs
        C. Estimate to completion
        D. Earned value
  4. Which of the following variables represents the amount of additional money that
     needs to be spent to complete the project?
        A. EAC
        B. ETC
        C. CPI
        D. SPI
  5. Which of the following variables represents the total amount of money that is
     estimated to be spent when the project is completed?
         A. ETC
         B. CPI
         C. EAC
         D. SPI
6. Which of the following variables represents the formula: Earned Value minus
   Actual Costs?
      A. CV
      B. CPI
      C. SV
      D. SPI
7. Which of the following variables represents the formula: Earned Value minus
   Planned Value?
      A. SPI
      B. CV
      C. CPI
      D. SV
8. Your boss enters your office and asks for the cost variance on your project that
   has an AC of $290, a PV of $300, and an EV of $270. What value do you provide
   them?
      A. -30
      B. 0.95
      C. 0.92
      D. -20
9. Your boss enters your office and asks for the cost variance on your project that
   has an AC of $400, a PV of $405, and an EV of $391. What value do you provide
   them?
      A. -5
      B. 1.30
      C. 1.08
      D. -9
10. You are preparing your monthly status report for your project. Your project had
    an original budget of $150,000 and an original schedule of 18 months. You
    currently have spent $65,000 and had budgeted to spend $60,000. You have
    produced $55,000 worth of product. Your Vice President is very eager to review
    your report as your project is important to the company's success. What is the
    Cost Variance for the project?
       A. -10,000
       B. -5,000
       C. 0.85
       D. 0.92
11. You are preparing your monthly status report for your project. Your project had
    an original budget of $950,000 and an original schedule of 11 months. Your
    currently have spent $400,000 and had budgeted to spend $405,000. You have
    produced $391,000 worth of product. Your Vice President is very eager to review
    your report as your project is important to the company's success. What is the
    Schedule Variance for the project?
       A. -9,000
       B. 0.98
       C. 14
       D. -14,000
12. You are leading a project that is a low profile project for the organization. The
    project was originally scheduled to take 10 months at a total cost of $70,000.
    Your title is that of a project coordinator, and you often have to struggle to get the
    resources you need. You have already spent $40,000 even though you were only
    scheduled to spend $37,500. If you have already produced $37,500 worth of
    work what is your current SPI?
       A. -2.50
       B. 0
       C. 1.00
       D. It cannot be determined
13. You are the program manager for a large software development company. You
    are currently leading a project that has an original budget of $35,000 and an
    original schedule of seven months. Currently the project has delivered on
    $27,500 of the project. It has also spent $29,000. If the project was forecast to
    spend $30,000 to date, what is the project's SPI?
        A. 0.95
        B. 0.92
        C. 0.87
        D. -1.5
14. What is the Critical Ratio for a project that had an original budget of $25,000, an
    original schedule of ten months, actual costs of $10,000, has produced $9,000
    worth of work, and was scheduled to have spent $10,000?
        A. 0.90
        B. -1
        C. 0.81
        D. It cannot be determined
15. What is the Critical Ratio for a project that had an original budget of $75,000, an
    original schedule of twelve months, actual costs of $45,000, and has produced
    $50,000 worth of work?
        A. 1.11
        B. 1.25
        C. 1.39
        D. It cannot be determined
16. What is the Critical Ratio for a project that had an original budget of $950,000, an
    original schedule of eleven months, actual costs of $400,000, has produced
    $391,000 worth of work, and was scheduled to have spent $405,000?
        A. 0.94
        B. 0.98
        C. 0.97
        D. It cannot be determined
17. You are a project manager working on a project that had an original budget of
    $30,000 and was forecast to take eight months. The project currently has
    delivered on $18,000 worth of the project and has spent $22,500. If the variances
    to date are believed to be atypical and the project had planned to spend $20,000
    what is the estimate at completion?
        A. $34,500
        B. $37,500
        C. $42,670
        D. It cannot be determined
18. You are a project manager working on a project that had an original budget of
    $250,000 and was forecast to take 54 weeks. The project currently has delivered
    on $90,000 worth of the project and has spent $100,000. If the variances to date
    are believed to be atypical and the project had planned to spend $80,000 what is
    the estimate at completion?
       A. $277,780
       B. $260,000
       C. $246,910
       D. It cannot be determined
19. You are a project manager working on a project that had an original budget of
    $300,000 and was forecast to take seventy-two weeks. The project currently has
    delivered on $65,000 worth of the project and has spent $100,000. If the
    variances to date are believed to be atypical and the project had planned to
    spend $75,000 what is the estimate at completion?
        A. $461,540
        B. $532,540
        C. $335,000
        D. $235,000
20. You are a project manager working on a project that had an original budget of
    $300,000 and was forecast to take seventy-two weeks. The project currently has
    delivered on $65,000 worth of the project and has spent $100,000. If the
    variances to date are believed to be typical and the project had planned to spend
    $75,000 what is the estimate at completion?
        A. $335,000
        B. $532,540
        C. $235,000
        D. $461,540
21. You are a project manager working on a project that had an original budget of
    $500,000 and was forecast to take eight months. The project currently has
    delivered on $35,000 worth of the project and has spent $50,000. If the variances
    to date are believed to be typical and the project had planned to spend $40,000
    what is the estimate at completion?
        A. $515,000
        B. $816,330
        C. $465,000
        D. $714,290
22. You are a project manager working on a project that had an original budget of
    $150,000 and was forecast to take eighteen weeks. The project currently has
    delivered on $53,000 worth of the project and has spent $61,000. If the variances
    to date are believed to be typical and the project had planned to spend $57,250
    what is the estimate at completion?
        A. $172,640
        B. $158,000
        C. $186,490
        D. $150,000
23. You are working on a project that had an original budget of $200,000 and was
    originally forecast to take sixty weeks. As the project coordinator, you have been
    somewhat frustrated with your project's performance. To date you have delivered
    on $79,000 of the project's deliverables while you had budgeted $93,000 and
    actually spent $98,000. The project has been progressing consistently and you
    expect the trends the project has shown to continue. Based upon this
    information, what do you expect the project's estimate at completion to be?
        A. $219,000
        B. $248,000
        C. $292,000
        D. $256,000
24. You are currently leading a project that had an original budget of $300,000 and
    an original schedule of twenty-seven weeks. You currently have spent $100,000
    and are currently over budget by $15,000. Your boss comes into your office and
    wants to discuss your project. Specifically, she wants to know how much more
    money it is going to take to complete the project. Assuming you have completed
    $ 78,000 of the deliverables and you expect the performance trends to not
    continue what do you tell her?
       A. $222,000
       B. $285,000
       C. $419,000
       D. $322,000
25. You are preparing your monthly status report for your project. Assuming the
    variances to date are typical, what would the ETC be assuming your project was
    budgeted to cost $125,000 and take twelve months and if you have actually
    spent $42,000, have produced $37,500 worth of product and were scheduled to
    have spent $39,000?
        A. $87,500
        B. $129,500
        C. $140,000
        D. $98,000
26. You are preparing your monthly status report for your project. Assuming the
    variances to date are typical, what would the estimate to complete the project be
    assuming your project was budgeted to cost $90,000 and take thirty-six weeks if
    you have actually spent $50,000, have produced $65,000 worth of product and
    were scheduled to have spent $60,000?
        A. $25,000
        B. $64,000
        C. $69,000
        D. $19,000
27. Which of the following is the calculated projection of cost performance that must
    be achieved on the remaining work to meet a specified management goal?
       A. CPI
       B. TCPI
       C. EAC
       D. ETC
28. You are asked to produce an estimate of the performance rate that must be
    achieved to meet the targeted budget at completion. If the project currently has
    an EV of 18, a PV of 20 and an AC of 22.5. If your original budget was 30 and
    you are using the EAC method, what estimate do you provide?
       A. 0.80
       B. 6.40
       C. 0.81
       D. 0.78
29. You are asked to produce an estimate of the performance rate that must be
    achieved to meet the targeted budget at completion. The project currently has an
    EV of 27.5, a PV of 30 and an AC of 29. If your original budget was 35 and you
    are using the EAC method, what estimate do you provide?
       A. 0.21
       B. 0.91
       C. 0.95
       D. 0.72
30. You are asked to produce an estimate of the performance rate that must be
    achieved to meet the targeted budget at completion. The project currently has an
    EV of 18, a PV of 17.5 and an AC of 20. If your original budget was 55 and you
    are using the EAC method, what estimate do you provide?
       A. 0.90
       B. 1.03
       C. 0.93
       D. 1.50
Review Questions – Part 3:
  1. One way to compute EAC is to take the cumulative actual costs and:
       A. Add the BAC.
       B. Add the cumulative earned value.
       C. Add the BAC - cumulative earned value.
       D. Divide by the CPI.
  2. Your boss comes into your office and asks how much more money it is going to
     take to complete your project. What do you provide her?
        A. The most current EAC.
        B. The project budget plus a variance.
        C. The most current ETC.
        D. The worst case scenario value.
  3. You are six months into a year-long project when your boss comes into your
     office and asks how much money in total your project is going to cost at
     completion. What do you provide him?
         A. The most current ETC.
         B. The most current EAC.
         C. The project budget / CPI.
         D. The project budget plus the latest variance estimate.
  5. Which of the following is primarily concerned with examining the value of the next
     highest alternative?
        A. Sunk costs
        B. Life cycle costs
        C. Opportunity cost
        D. Operational costs
6. At lunch one of your fellow project managers laments about the high sunk costs
   on their project that is impacting key decisions. What are they likely saying?
       A. Money budgeted to be spent is impacting the project.
       B. The unseen costs of the project are impacting decisions.
       C. Their project should be cancelled.
       D. Money already spent on the project is impacting the decisions.
8. Which of the following is not typically part of the cost management plan?
     A. Cost paradigms
     B. Control thresholds
     C. Earned value rules
     D. Reporting formats
9. Considering the effect project decisions have on the cost of using, maintaining,
   and supporting the product of the project is more commonly referred to as what?
      A. Project costing
      B. Ethical cost management
      C. Life cycle costing
      D. Professional cost responsibility
10. Life cycle costing is often combined with what to improve decision making,
    reduce cost and execution time, and to improve the quality of the project?
        A. Earned value management
        B. Opportunity costing
        C. Professional project management
        D. Value engineering
11. In which of the following processes is the project cost management plan
    developed?
        A. The develop project management plan process
        B. The estimate costs process
        C. The determine budget process
        D. The control costs process
12. Which of the following describes the difference between costing and pricing?
      A. Costing includes profit and pricing does not
      B. Pricing includes profit and costing does not
      C. Pricing always includes a factor of cost
      D. Cost is always a multiplier of price
15. A coworker comes into your office and asks about your project that is currently in
    the execution phase. They specifically want to know what the budget for your
    project is. If your team estimated the project at $275,000 what do you tell your
    coworker?
       A. Approximately $302,500
       B. $247,500 to $316,250
       C. $261,250 to $302,500
       D. Approximately $316,250
16. Your manager comes into your office and asks about your project that is currently
    in the initiating phase. They specifically want to know what the budget for your
    project is. If your team estimated the project at $500,000 what do you tell your
    boss?
        A. Approximately $1,000,000
        B. $500,000 to $1,000,000
        C. $750,000 to $250,000
        D. $875,000 to $375,000
17. Your manager comes into your office and asks about your project that is currently
    in the execution phase. They specifically want to know what the budget for your
    project is. If your team estimated the project at $250,000 what do you tell your
    boss?
        A. $225,000 to $275,000
        B. $237,500 to $275,000
        C. $125,000 to $500,000
        D. Approximately $275,000
19. Which of the following is a formally recognized organizational process asset used
    in the Cost Estimating Process?
        A. Cost estimating policies
        B. Commercial databases
        C. Marketplace conditions
        D. Project team knowledge
20. Which of the following cost estimating techniques involves using the actual costs
    from previous, similar projects as its basis?
       A. Bottom-up estimating
       B. Parametric estimating
       C. Analogous estimating
       D. Monte Carlo estimating
21. Which of the following cost estimating techniques involves calculating the costs
    of individual tasks or activities and then summarizing the costs?
        A. Analogous estimating
        B. Bottom-up estimating
        C. Parametric estimating
        D. Monte Carlo estimating
22. Which of the following cost estimating techniques involves calculating the costs
    of individual tasks or activities or work packages by determining the relationship
    between them, historical data and other variables?
        A. Parametric estimating
        B. Bottom-up estimating
        C. Analogous estimating
        D. Monte Carlo estimating
23. Reserve analysis is the process of looking at the estimated costs to deal with
    what?
      A. Unknown unknowns
      B. Certain events
      C. None of the above
      D. Known unknowns
24. If your original estimate was 38 weeks and you provided your sponsor with an
    estimate of 36 to 42 weeks what kind of estimate did you provide?
        A. Rough order of magnitude estimate
        B. Final estimate
        C. Budget estimate
        D. Definitive estimate
25. If you have a burn rate of .92 which of the following is true?
        A. The AC is 110 and the EV is 120
        B. The AC is 120 and the EV is 110
        C. The AC is 120 and the PV is 110
        D. The EV is 110 and the PV is 120
26. If you have a burn rate of 1.21 which of the following is true?
        A. The AC is $84,000 and the EV is $102,000
        B. The AC is $102,000 and the EV is $84,000
        C. The AC is $84,000 and the PV is $102,000
        D. The EV is $102,000 and the PV is $84,000
27. Your manager comes into your office to discuss a project you are leading. In your
    latest status report you indicated a burn rate of 0.86. If you have spent $192,000
    what else do you know to be true?
        A. You had budgeted to spend $165,000
        B. Your SPI is 0.86
        C. You have produced $165,000 of work
        D. Your cost variance is less than your schedule variance
28. You have been assigned a project to deploy new desktop computers throughout
    your organization. Your assignment to the project has occurred after the project
    estimates have been completed and baselines have been established. You are
    concerned that the cost estimates are unrealistic based upon your previous
    experience. Which of the following is the best thing to do?
        A. Determine if the contingency budget will cover the additional costs
        B. Bring your project team together to determine the best solution
        C. Meet with the project sponsor to examine possible solutions
        D. Meet with the people who generated the cost estimate
29. In preparing your monthly status report you determine that your project is behind
    schedule. You believe the variances are typical and using Earned Value Analysis
    you determine the project is 16% behind schedule. Your boss has offered to
    provide access to an additional six resources, but you are concerned about the
    impacts of Brooke's Law and also not providing appropriate reward for the cost of
    the additional resources. Your concerns are best expressed by which of the
    following?
        A. Crashing
        B. Parkinson's law
        C. Pareto principle
        D. Law of diminishing returns
30. You have been asked to take over a project that senior management feels is
    critical to the organization, but has also determined to be failing. Originally, the
    project had a budget of $550,000. The project has only produced 2/3 of the
    required deliverables and has already spent $500,000. The $500,000
    expenditure represents which of the following?
         A. Capital expenditure
         B. Sunk cost
         C. Indirect expenditure
         D. Direct cost
31. In which of the following steps would a project manager allocate overall cost
    estimates to the individual activities, tasks, deliverables or work packages to
    establish a performance measurement baseline?
        A. Estimate costs
        B. Determine budget
        C. Cost baselining
        D. Cost control
32. You are part of a project management office within a large organization. All of the
    organization's resources are currently allocated to projects. A new project has
    just been brought to the PMO by senior management that must be given priority.
    To complete this new project you will have to take resources from the other
    projects which will cause them to be delayed. From which of the following
    projects should you take the resources?
        A. Project A with 17 resources, a NPV of $225,000, and no change
           management plan.
        B. Project B with nine resources, an IRR of 19%, BCR of 1.4, and no project
           cost control plan.
        C. Project C with seven resources, a benefit cost ratio of 1.2, and no project
           charter.
        D. Project D with 11 resources, capital expenses of US $195,000, a burn rate
           of 1.25 and no schedule management plan.
33. Which of the following is not a tool or technique used in the control costs
    process?
       A. Forecasting
       B. Variance analysis
       C. Project management software
       D. Reserve analysis
34. Which of the following is a tool or technique used in the control costs process?
      A. Forecasting
      B. Funding limit reconciliation
      C. Reserve analysis
      D. Parametric analysis
35. Which of the following is not an output of the Control Costs Process?
      A. Work performance measurements
      B. Budget forecasts
      C. Approved changes
      D. Change requests
38. An executive is evaluating project A with BCR of 1.2 and project B with an NPV
    of $380,000. The two projects are mutually exclusive. The cost of choosing one
    of these projects and not obtaining the benefits of the other is called:
        A. Sunk cost
        B. Lost cost
        C. Opportunity cost
        D. Portfolio cost
39. Jim and Sally are two project managers working for a large manufacturing
    organization who are discussing Jim's latest project. Sally comments that it is
    important that Jim consider both the operational and maintenance costs of the
    product being created in his project decisions. To what is Sally referring?
       A. Jim's professional responsibility
       B. Total project costing
       C. Parametric estimating
       D. Life cycle costing
40. You are in the process of establishing the cost performance measurement
    system you will be using for a software development project. Which of the
    following methods would be best?
        A. Ask each resource for a percent of the deliverables that are complete and
           forecast future performance.
        B. Use the physical percent complete of the work product to calculate earned
           value and then forecast future performance.
        C. Use a 0% / 100% rule of reporting deliverable completeness and forecast
           future performance.
        D. Focus on the amount of money budgeted and actually spent in each
           period and then forecast future performance.
41. You are the project manager on a project that has a CPI of 0.92. What do you
    know?
       A. The project is currently 8% behind schedule.
       B. When the project is delivering 92% of the work product.
       C. The project will end up being 92% over budget.
       D. The project is currently 8% over budget.
42. You are the project manager on a project that has a cost performance index of
    0.79. What does this mean?
       A. The project is only producing 79 cents of value for every dollar invested.
       B. The project is 21% behind schedule.
       C. The project is 79% over budget.
       D. The project is likely to cost 79% more than planned.
43. Your project has a CPI of 0.87. What does this mean?
       A. You are behind schedule.
       B. You are 13% under budget.
       C. It is costing you more to produce each deliverable than forecasted.
       D. You are 87% over budget.
44. Your project has a SPI of 0.91 what does this tell you?
       A. You will likely deliver the project 9% behind schedule.
       B. You are currently 9% behind schedule.
       C. Your project has achieved 91% of its objectives.
       D. You are 9% over budget.
45. You are the project manager on a large road project that has a current CV of
    $176,000. What does this mean?
       A. The project is $176,000 over budget.
       B. The project is $176,000 ahead of schedule.
       C. The project is $176,000 behind schedule.
       D. The project is $176,000 under budget.
46. You are leading a project that is using resources in four different locations.
    Management has mandated that you use Earned Value Analysis. If the project is
    a software development project which of the following would not be necessary to
    determine the initial cost baseline?
       A. WBS
       B. Network diagram
       C. Scope change management plan
       D. Risk register
47. You are the project manager for a major road project. You have been asked to
    estimate the cost for your project using the formula of number of miles of road
    multiplied by the number of lanes multiplied by the cost per lane mile of road.
    What kind of estimate is this?
        A. Parametric estimate
        B. Analogous estimate
        C. Rough order of magnitude estimate
        D. Bottom up estimate
48. In which of the project management process groups would you make a ROM
    estimate?
        A. The planning process group
        B. The executing process group
        C. The monitoring and controlling process group
        D. The initiating process group
49. You have been asked to choose between two different projects that your
    organization might undertake. Which of the following would not be grounds for
    comparison?
       A. BCR
       B. Marginal analysis
       C. IRR
       D. NPV
50. Which of the following is a tool for determining when investing any additional
    money will not produce an equivalent return?
      A. Marginal analysis
      B. Benefit cost ratio analysis
      C. Cost benefit ratio analysis
      D. Internal rate of return analysis
51. You have been asked to choose one of three projects. Project A has an NPV of
    $75,000. Project B has an NPV of $81,000. Project C has an NPV of $62,500.
    What is the opportunity cost of selecting Project B?
       A. $81,000
       B. $62,500
       C. $75,000
       D. $6,000
52. You are placed in charge of a software development project. As part of your team
    building you determine that your resources do not have all the necessary skills.
    To improve their skills you decide to send them to an external class to obtain the
    required skills. Which of the following would best categorize this expense?
        A. Indirect cost
        B. External cost
        C. Fixed cost
        D. Direct cost
53. You are meeting with the project sponsor. They voice concern about the setup
    costs of the project escalating. You assure them that this is not an issue. Why?
       A. Because good project management will ensure the costs do not escalate.
       B. Because project setup represents an opportunity cost.
       C. Because project setup represents an overhead cost.
       D. Because project setup represents a fixed cost.
54. You have been asked to determine a less costly way to complete the same work.
    Which of the following tools would you use?
       A. Value analysis
       B. Six sigma analysis
       C. Marginal analysis
       D. Benefit cost analysis
55. When working with earned value management which primary term represents the
    actual output or work product?
       A. Planned value
       B. Earned value
       C. Actual cost
       D. CPI
56. You have been asked to select one of three projects for your organization using
    NPV. Project A has an NPV of $23,000 and will take two years to produce.
    Project B has an NPV of $41,000 and will take three years to produce, and
    Project C has an NPV of $35,000 and will take three years to produce. Which
    project would you select?
       A. Project A
       B. Project B
       C. Project C
       D. It cannot be determined
57. You are leading a project for an external customer. The client representative
    asks that you provide a written cost estimate that is 25% higher than your
    estimate of the project's cost. They justify the request by telling you their
    company budgeting process requires managers to estimate pessimistically to
    ensure enough money is allocated for projects. What is the best way to handle
    this?
        A. Add the 25% as a lump sum contingency to handle project risks.
        B. Add the 25% to the cost estimate by spreading it evenly across all project
           activities.
        C. Create one cost baseline for budget allocation and a second one for the
           actual project management plan.
        D. Ask for information on risks that would cause your estimate to be too low.
60. You have been assigned as the project manager for a medium-sized information
    technology project. Upon receiving your charter, the project sponsor asks if the
    project can be completed within the target budget. Which of the following is the
    best way to handle this?
       A. Build an estimate in the form of a range of possible results.
       B. Ask the team members to help estimate the cost based on the project
           charter.
       C. Based on the information you have, calculate a parametric estimate.
       D. Provide an analogous estimate based on past history.
61. Early in the life of your project, you are having a discussion with the sponsor
    about which estimating techniques should be used. You want a form of expert
    judgment, but the sponsor argues for analogous estimating. It would be best to:
       A. Agree to analogous estimating, as it is a form of expert judgment.
       B. Suggest life cycle costing as a compromise.
       C. Determine why the sponsor wants such an accurate estimate.
       D. Try to convince the sponsor to allow expert judgment because it is
           typically more accurate.
62. You have just completed the initiating processes of a small project and are
    moving into project planning when a project stakeholder asks you for the project's
    budget and cost baseline. What should you tell her?
       A. The project budget can be found in the project charter, which has just
          been completed.
       B. The project budget and baseline will not be finalized and accepted until
          planning processes are completed.
       C. The project management plan will not contain the project's budget and
          baseline; this is a small project.
       D. It is impossible to complete an estimate before the project management
          plan is created.
Answer Key – Part 1:
  1. B
     Answer B. This question requires you to calculate the depreciation using the
     formula below then subtracting that result from the purchase price four times.
     Current Asset Value - ((cost - residual value)/useful life)
  2. C
     Answer C. This question requires you to calculate the depreciation using the
     formula below then subtracting that result from the purchase price three times.
     Current Asset Value - ((cost - residual value)/useful life)
  3. D
     Answer D. Question requires you to calculate the depreciation using the formula
     below then subtracting that result from the purchase price one time. Current
     Asset Value - ((cost - residual value)/useful life)
  4. A
     Answer A. This question requires you to calculate the depreciation using the
     formula below then subtracting that result from the purchase price three times.
     Current Asset Value - ((cost - residual value)/useful life)
  5. C
     Answer C. This question requires you to calculate the depreciation using the
     formula below then subtracting that result from the purchase price three times.
     Current Asset Value - ((cost - residual value)/useful life)
  6. B
     Answer B. The Unit of Production Method, or UOP is defined by first calculating
     the amount of value the asset loses with each unit produced. This is done with
     the formula below. This result is then multiplied by the number of units produced
     giving you the lost value. By subtracting this number from the original purchase
     price you obtain the result. Current Asset Value - (Units Produced * ( (cost -
     residual value)/estimated units of useful life (production)) )
7. D
   Answer D. The Unit of Production Method, or UOP is defined by first calculating
   the amount of value the asset loses with each unit produced. This is done with
   the formula below. This result is then multiplied by the number of units produced
   giving you the lost value. By subtracting this number from the original purchase
   price you obtain the result. Current Asset Value - (Units Produced * ( (cost -
   residual value)/estimated units of useful life (production)) )
8. C
   Answer C. The Unit of Production Method, or UOP is defined by first calculating
   the amount of value the asset loses with each unit produced. This is done with
   the formula below. This result is the multiplied by the number of units produced
   giving you the lost value. By subtracting this number from the original purchase
   price you obtain the result. Current Asset Value - (Units Produced * ( (cost -
   residual value)/estimated units of useful life (production)) )
9. A
   Answer A. The Unit of Production Method, or UOP is defined by first calculating
   the amount of value the asset loses with each unit produced. This is done with
   the formula below. This result is the multiplied by the number of units produced
   giving you the lost value. By subtracting this number from the original purchase
   price you obtain the result. Current Asset Value - (Units Produced * ( (cost -
   residual value)/estimated units of useful life (production)) )
10. A
   Answer A. The Unit of Production Method, or UOP is defined by first calculating
   the amount of value the asset loses with each unit produced. This is done with
   the formula below. This result is the multiplied by the number of units produced
   giving you the lost value. By subtracting this number from the original purchase
   price you obtain the current value. Current Asset Value - (Units Produced * (
   (cost - residual value)/estimated units of useful life (production)) )
11. B
    Answer B. Double Declining Balances or DDB is an accelerated depreciation
    method. Begin by calculating depreciation as if using the straight line method.
    Then determine the total percentage of the asset that is depreciated the first year
    and double it. Each subsequent year, that same percentage is multiplied by the
    remaining balance to be depreciated.
12. A
    Answer A. Double Declining Balances or DDB is an accelerated depreciation
    method. Begin by calculating depreciation as if using the straight line method.
    Then determine the total percentage of the asset that is depreciated the first year
    and double it. Each subsequent year, that same percentage is multiplied by the
    remaining balance to be depreciated.
13. D
    Answer D. Double Declining Balances or DDB is an accelerated depreciation
    method. Begin by calculating depreciation as if using the straight line method.
    Then determine the total percentage of the asset that is depreciated the first year
    and double it. Each subsequent year, that same percentage is multiplied by the
    remaining balance to be depreciated.
14. B
    Answer B. Double Declining Balances or DDB is an accelerated depreciation
    method. Begin by calculating depreciation as if using the straight line method.
    Then determine the total percentage of the asset that is depreciated the first year
    and double it. Each subsequent year, that same percentage is multiplied by the
    remaining balance to be depreciated.
15. C
    Answer C. Double Declining Balances or DDB is an accelerated depreciation
    method. Begin by calculating depreciation as if using the straight line method.
    Then determine the total percentage of the asset that is depreciated the first year
    and double it. Each subsequent year, that same percentage is multiplied by the
    remaining balance to be depreciated.
16. C
    Answer C. SYD or Sum of the Year Digits is an accelerated depreciation method.
    Begin by adding the number of years in the schedule. For example, for a five
    year schedule add 1+2+3+4+5 = 15. Next, take the asset value minus the
    residual value and divide it by this result (15). This creates the amount you will
    use at the end of each year to reduce the value of the asset.
17. A
    Answer A. SYD or Sum of the Year Digits is an accelerated depreciation method.
    Begin by adding the number of years in the schedule. For example, for a five
    year schedule add 1+2+3+4+5 = 15. Next, take the asset value minus the
    residual value and divide it by this result (15). This creates the amount you will
    use at the end of each year to reduce the value of the asset.
18. D
    Answer D. SYD or Sum of the Year Digits is an accelerated depreciation method.
    Begin by adding the number of years in the schedule. For example, for a five
    year schedule add 1+2+3+4+5 = 15. Next, take the asset value minus the
    residual value and divide it by this result (15). This creates the amount you will
    use at the end of each year to reduce the value of the asset.
19. B
    Answer B. SYD or Sum of the Year Digits is an accelerated depreciation method.
    Begin by adding the number of years in the schedule. For example, for a five
    year schedule add 1+2+3+4+5 = 15. Next, take the asset value minus the
    residual value and divide it by this result (15). This creates the amount you will
    use at the end of each year to reduce the value of the asset.
20. A
    Answer A. SYD or Sum of the Year Digits is an accelerated depreciation method.
    Begin by adding the number of years in the schedule. For example, for a five
    year schedule add 1+2+3+4+5 = 15. Next, take the asset value minus the
    residual value and divide it by this result (15). This creates the amount you will
    use at the end of each year to reduce the value of the asset.
Answer Key – Part 2:
  1. B
     Answer B. PMBOK Guide p. 261-267 - The Planned Value is the budgeted cost
     for the work scheduled to be completed on an activity or WBS component up to a
     given point. This is sometimes referred to as the BCWS.
  2. D
     Answer D. PMBOK Guide p. 261-267 - The Earned Value is the budgeted
     amount for the work actually completed on the scheduled activity during a
     specified time period. This is sometimes referred to as the BCWP.
  3. A
     Answer A. PMBOK Guide p. 261-267 - The Actual Costs are the total costs
     incurred in accomplishing work on the schedule activity during a specified time
     period. The actual costs are sometimes referred to as ACWP or actual costs of
     work performed.
  4. B
     Answer B. PMBOK Guide p. 261-267 - The Estimate to Complete provides a
     metric showing how much more money than has already been spent is needed to
     complete the project. This is in addition to the money that has already been
     spent. The ETC is correct.
  5. C
     Answer C. PMBOK Guide p. 261-267 - As a project continues it is important that
     you are constantly revising your estimates of how much money you are going to
     have to spend. This total number is represented by the Estimate At Completion
     or EAC.
  6. A
     Answer A. PMBOK Guide p. 261-267 - The Cost Variance or CV, represents an
     indicator of how far away from the original cost baseline the project actually is. To
     calculate it, take the Earned Value (EV) and subtract the Actual Costs. A project
     is on target if the CV is equal to 0.
7. D
   Answer D. PMBOK Guide p. 261-267 - The Schedule Variance or SV, represents
   an indicator of how far off of the original schedule baseline the project actually is.
   To calculate the SV take the Earned Value and subtract the Planned Value. A
   project is on schedule if the SV is equal to 0.
8. D
   Answer D. PMBOK Guide p. 261-267 - The Cost Variance or CV, represents an
   indicator of how far away from the original cost baseline the project actually is. To
   calculate it take the Earned Value (EV) and subtract the actual costs. A project is
   on target if the CV is equal to 0.
9. D
   Answer D. PMBOK Guide p. 261-267 - The Cost Variance or CV, represents an
   indicator of how far away from the original cost baseline the project actually is. To
   calculate it take the Earned Value (EV) and subtract the actual costs. A project is
   on target if the CV is equal to 0.
10. A
    Answer A. PMBOK Guide p. 261-267 - The Cost Variance or CV, represents an
    indicator of how far away from the original cost baseline the project actually is. To
    calculate it take the Earned Value (EV) and subtract the actual costs. A project is
    on target if the CV is equal to 0.
11. D
    Answer D. PMBOK Guide p. 261-267 - The Schedule Variance or SV, represents
    an indicator of how far away from the original schedule baseline the project
    actually is. To calculate it take the Earned Value (EV) and subtract the Planned
    Value (PV). A project is on target if the SV is equal to 0.
12. C
    Answer C. PMBOK Guide p. 261-267 - The Schedule Performance Index, or SPI,
    is calculated by taking the Earned Value (EV or amount of work produced) and
    dividing it by the Planned Value (PV, budget or planned spending). A project is
    on schedule if the result is 1.
13. B
    Answer B. PMBOK Guide p. 261-267 - The Schedule Performance Index, or SPI,
    is calculated by taking the Earned Value (EV or amount of work produced) and
    dividing it by the Planned Value (PV, budget or planned spending). A project is
    on schedule if the result is 1.
14. C
    Answer C. PMBOK Guide p. 261-267 - The critical ratio is calculated by first
    determining both the Cost Performance Index, or CPI (EV / AC) and the
    Schedule Performance Index or SPI (EV / PV). The Critical Ratio is then equal to
    the CPI * SPI.
15. D
    Answer D. PMBOK Guide p. 261-267 - The critical ratio is calculated by first
    determining both the Cost Performance Index, or CPI (EV / AC) and the
    Schedule Performance Index or SPI (EV / PV). The Critical Ratio is then equal to
    the CPI * SPI. In this case you are missing the planned value so the critical ratio
    cannot be determined.
16. A
    Answer A. PMBOK Guide p. 261-267 - The critical ratio is calculated by first
    determining both the Cost Performance Index, or CPI (EV / AC) and the
    Schedule Performance Index or SPI (EV / PV). The Critical Ratio is then equal to
    the CPI * SPI.
17. A
    Answer A. PMBOK Guide p. 261-267 - The key to this question is the fact that
    the variances are believed to be atypical. With this piece of information, you
    know the formula should be EAC = AC + BAC - EV.
18. B
    Answer B. PMBOK Guide p. 261-267 - The key to this question is the fact that
    the variances are believed to be atypical. With this piece of information, you
    know the formula should be EAC = AC + BAC - EV.
19. C
    Answer C. PMBOK Guide p. 261-267 - The key to this question is the fact that
    the variances are believed to be atypical. With this piece of information, you
    know the formula should be EAC = AC + BAC - EV.
20. D
    Answer D. PMBOK Guide p. 261-267 - The key to this question is the fact that
    the variances are believed to be typical. This means whatever is happening will
    continue to happen at approximately the same rate. With this piece of information
    you should have known to use the following formula: EAC = AC + ((BAC -
    EV)/CPI).
21. D
    Answer D. PMBOK Guide p. 261-267 - The key to this question is the fact that
    the variances are believed to be typical. This means whatever is happening will
    continue to happen at approximately the same rate. With this piece of information
    you should have known to use the following formula: EAC = AC + ((BAC -
    EV)/CPI).
22. A
    Answer A. PMBOK Guide p. 261-267 - The key to this question is the fact that
    the variances are believed to be typical. This means whatever is happening will
    continue to happen at approximately the same rate. With this piece of information
    you should have known to use the following formula: EAC = AC + ((BAC -
    EV)/CPI).
23. B
    Answer B. PMBOK Guide p. 261-267 - The key to this question is the fact that
    the variances are believed to be typical. This means whatever is happening will
    continue to happen at approximately the same rate. With this piece of information
    you should have known to use the following formula: EAC = AC + ((BAC -
    EV)/CPI).
24. A
    Answer A. PMBOK Guide p. 261-267 - To correctly answer this question you
    must first determine exactly what is being asked. In this question you are being
    asked for an estimate to complete the project (ETC). In this case you are told that
    the variances that have been seen to date are not typical. Therefore, your correct
    formula is ETC = BAC - EV.
25. D
    Answer D. PMBOK Guide p. 261-267 - To correctly answer this question you
    must first determine exactly what is being asked. In this question you are being
    asked for an estimate to complete the project (ETC). In this case you are told that
    the variances that have been seen to date are typical. Therefore, your correct
    formula is ETC = (BAC - EV) / CPI.
26. D
    Answer D. PMBOK Guide p. 261-267 - To correctly answer this question you
    must first determine exactly what is being asked. In this question you are being
    asked for an estimate to complete the project (ETC). In this case you are told that
    the variances that have been seen to date are typical. Therefore, your correct
    formula is ETC = (BAC - EV) / CPI.
27. B
    Answer B. PMBOK Guide p. 261-267 - The To-Complete Performance Index is
    the calculated projection of cost performance that must be achieved on the
    remaining work to meet a specified management goal, such as the BAC or the
    EAC.
28. A
    Answer A. PMBOK Guide p. 261-267 - This question requires you to calculate
    the TCPI or the To-Complete Performance Index using the EAC formula. This
    formula is: (BAC - EV) / (EAC - AC). The EAC is calculated using the CPI
    method.
29. C
    Answer C. PMBOK Guide p. 261-267 - This question requires you to calculate
    the TCPI or the To-Complete Performance Index using the EAC formula. This
    formula is: (BAC - EV) / (EAC - AC). The EAC is calculated using the CPI
    method.
30. A
    Answer A. PMBOK Guide p. 261-267 - This question requires you to calculate
    the TCPI or the To-Complete Performance Index using the EAC formula. This
    formula is: (BAC - EV) / (EAC - AC). The EAC is calculated using the CPI
    method.
Answer Key – Part 3:
  1. C
     Answer C. PMBOK Guide p. 264-265. There are several ways to calculate the
     Estimate At Completion or EAC. The most common of these include:
     - Creating an entirely new estimate
     - Cumulative actual costs + (Original Total Budget - Cumulative Earned Value)
     - Cumulative Actual Costs + ((Original Total Budget - Cumulative Earned Value) /
     Cumulative CPI)
     - Cumulative Actual Costs + ((Original Total Budget - Cumulative Earned Value) /
     (Cumulative CPI * SPI))
  2. C
     Answer C. PMBOK Guide p. 264-265. This question is asking how much more
     money is required. This is money in addition to the money already spent. This is
     the definition of the Estimate to Complete or ETC.
  3. B
     Answer B. PMBOK Guide p. 264-265. This question is asking how much money
     will you have spent when the project has been completed. This is the Estimate at
     Completion or EAC.
  4. A
     Answer A. PMBOK Guide p. 264-265. There are three ways to calculate ETC or
     Estimate to Complete. They include:
     - Create an entirely new estimate
     - Assume the variances are atypical (BAC- Cumulative EV)
     - Assume the variances are typical (BAC - cumulative EV) / (CPI* SPI)
     - Using the critical ratio (BAC - cumulative EV) / CPI
  5. C
     Answer C. PMBOK Guide p. 712. Opportunity costs measure the value of the
     next highest alternative. This provides a way of measuring what you chose not to
     do.
  6. D
     Answer D. PMBOK Guide p. 238. Sunk costs represent money that has already
     been spent on the project. Often these costs become so great that projects are
     forcibly continued to save face or for other reasons when they should be
     cancelled.
7. B
   Answer B. Although project costing is a responsibility of the project manager, life
   cycle costing is an ethical responsibility. The project manager has the
   responsibility to ensure the product of the project is within the operating budget of
   the organization.
8. A
   Answer A. Control thresholds, earned value rules and reporting formats are all
   typically part of the cost management plan. "Cost paradigms" is a nonexistent
   term for the purposes of project management.
9. C
   Answer C. Project cost management should consider the effect of project
   decisions on the cost of using, maintaining, and supporting the project's product
   or service, more commonly referred to as life cycle costing.
10. D
    Answer D. Life cycle costing is often combined with value engineering to improve
    decision making, reduce costs and execution time, and to improve the quality of
    the project.
11. A
    Answer A. PMBOK Guide p. 235 - Although it is not formally called out in the cost
    management processes, the PMBOK Guide specifies that the cost management
    plan is initially produced as part of the development of the project management
    plan.
12. B
    Answer B. Price is made up of the cost of the item plus the desired profit. Cost
    simply represents what the item took to produce in monetary terms.
13. B
    Answer B. PMBOK Guide p. 241. Early in a project's life cycle you are not likely
    to have a lot of detailed information. Therefore, you need to provide a wide
    ranging estimate. The Rough Order of Magnitude estimate does just that. It is a
    range of +75% to -25% of the original estimate.
14. D
    Answer D. PMBOK Guide p. 241. The definitive estimate is the final project
    estimate given to all management and resources. It is never a single number and
    always represented by a range. The correct range for a definitive estimate is
    +10% to -5%.
15. C
    Answer C. PMBOK Guide p. 241. Remember, according to PMI, you never give a
    single number. You always provide a range. In this case that fact excludes two of
    the answers. Since you are in the execution phase of the project you are using
    the definitive estimate which is +10% to -5%. That provides a range of 261,250 to
    $302,500.
16. D
    Answer D. PMBOK Guide p. 241. Remember, according to PMI, you never give a
    single number. You always provide a range. In this case that fact excludes two of
    the answers. Since you are in the initiation phase of the project you are using the
    ROM estimate which is +75% to -25% . That provides a range of 375,000 to
    $875,000.
17. B
    Answer B. PMBOK Guide p. 241. Remember, according to PMI, you never give a
    single number. You always provide a range. In this case that fact excludes one of
    the answers. Since you are in the planning phase of the project you are using the
    definitive estimate which is +10% to -5%. That provides a range of $237,500 to
    $275,000.
18. D
    Answer D. PMBOK Guide p. 171 - Enterprise environmental factors are factors or
    conditions that exist within the area that the project resides. When discussing the
    factors for the estimate cost process, PMI specifically calls out two:
    - Market conditions
    - Published commercial information
    - Exchange rates and inflation
19. B
    Answer B. PMBOK Guide p. 171 - Organizational process assets represent
    templates and information that help the project team complete the project. When
    it comes to the cost estimating process these assets formally include:
    - Cost estimating policies
    - Cost estimating templates
    - Historical information
20. C
    Answer C. PMBOK Guide p. 244 - Analogous estimating represents a technique
    used usually early in a project to develop cost and schedule estimates. It makes
    use of comparative analysis and argues that if two projects are similar their costs
    should be similar as well. This method runs a significant accuracy risk because
    often the details of the projects are not that similar.
21. B
    Answer B. PMBOK Guide p. 244. Bottom-up estimating involves completing the
    estimates at the lowest possible level, the task or activity, and then summing the
    work packages as you go higher up the WBS. PMI considers this the most
    accurate and detailed form of estimating.
22. A
    Answer A. PMBOK Guide p. 244. Relationships between historical data and
    other variables to calculate a cost estimate represent parametric estimating.
23. D
    Answer D. PMBOK Guide p. 245 - Reserve analysis is the technique of looking
    for areas where there are known, potential risks, called known unknowns
    because you know they are possible, but you do not know when they are going
    to happen.
24. D
    Answer D. PMBOK Guide p. 241. The definitive estimate is the final estimate
    provided in the project. It is the estimate used for baselines and represents a
    range of +10% to -5%.
25. B
    Answer B. PMBOK Guide p. 263. The "Burn Rate" measures the rate you are
    "burning" or spending your money versus how much work product you are
    obtaining. It is another way to say CPI. It is expressed as a numerical value with
    a target of one. It is defined by the formula of Earned Value / Actual Costs.
26. A
    Answer A. PMBOK Guide p. 263. The "Burn Rate" measures the rate you are
    "burning" or spending your money versus how much work product you are
    obtaining. It is another way to say CPI. It is expressed as a numerical value with
    a target of one. It is defined by the formula of Earned Value / Actual Costs.
27. C
    Answer C. PMBOK Guide p. 263. The "burn rate" measures the rate you are
    "burning" or spending your money versus how much work product you are
    obtaining. It is another way to say CPI. It is expressed as a numerical value with
    a target of one. It is defined by the formula of earned value / actual costs.
28. B
    Answer B. Your best answer is to always work with your project team first to
    determine alternatives. Remember, the PMI standards are all about examining
    alternatives and presenting recommendations. You would not want to meet with
    anyone else until you have met with your team.
29. D
    Answer D. The law of diminishing returns argues that in every scenario there is a
    point where spending money will not get an equal amount of value in return. The
    rest of the question is simply subterfuge and should be ignored.
30. B
    Answer B. Sunk costs represent monies that have already been spent. They
    cannot be recovered. They are important to project managers because many
    organizations make project decisions based upon the money that has already
    been spent. This often leads to good money following bad.
31. B
    Answer B. PMBOK Guide p. 248-256 - Determine budget involves aggregating
    the various estimated costs for all the tasks, activities, deliverables, and/or work
    packages to establish a total cost baseline for the project.
32. C
    Answer C. Each of these projects is in trouble, but only one of them should have
    never been started. That is project C. Project C does not have a project charter
    and should have never been started. Therefore, it should be the first place you
    go for resources. Remember, you never do a project without a charter no matter
    what the numbers say.
33. D
    Answer D. PMBOK Guide p. 257 - The tools and techniques used in the control
    costs process include:
    - Expert judgment
    - Data analysis
    - To-complete performance index (TCPI)
    - Project management information system
34. A
    Answer A. PMBOK Guide p. 167 - The tools and techniques used in the control
    costs process include:
    - Expert judgment
    - Data analysis
    - To-complete performance index (TCPI)
    - Project management information system
35. C
    Answer C. PMBOK Guide p. 167 - The outputs from the cost control process
    include:
    - Work performance measurements
    - Cost forecasts
    - Change requests
    - Project management plan updates
    - Project document updates
36. A
    Answer A. PMBOK Guide p. 244 - Parametric estimating involves using project
    characteristics in a mathematical model to predict total project costs.
37. B
    Answer B. PMBOK Guide p. 243 - Analogous estimating means using the actual
    cost of previous, similar projects as the basis for estimating the cost of the
    current project.
38. C
    Answer C. The opportunity cost for any selection is defined as the value of the
    next highest alternative.
39. D
    Answer D. Life cycle costing is the requirement that the project manager take into
    consideration the cost of operation and the cost of maintenance for the product
    or service being created. It is an ethical responsibility of the project manager.
40. B
    Answer B. PMBOK Guide p. 261-267. In most cases, the best way to report level
    of completeness is to use the actual level of physical completeness as part of the
    earned value calculations. This is the actual amount of work product produced.
    However, the real key to this question is to remember that PMI always wants you
    to use earned value reporting.
41. D
    Answer D. PMBOK Guide p. 261-267. The cost performance index or CPI is
    defined as the Earned Value divided by the Actual Costs. It tells you how close to
    the forecasted budget you actually are. If the CPI is 0.92 that tells you the project
    is 1 - .92 or 0.08 over budget.
42. A
    Answer A. PMBOK Guide p. 261-267. The cost performance index or CPI is
    defined as the Earned Value divided by the Actual Costs. It tells you how close to
    the forecasted budget you actually are. If the CPI is 0.79 that tells you the project
    is 1 - .79 or 0.21 over budget.
43. C
    Answer C. PMBOK Guide p. 261-267. The cost performance index or CPI is
    defined as the Earned Value divided by the Actual Costs. It tells you how close to
    the forecasted budget you actually are. If the CPI is 0.87 that tells you the project
    is 1 - .87 or 0.13 over budget.
44. B
    Answer B. PMBOK Guide p. 261-267. The Schedule Performance Index or SPI is
    defined as the Earned Value divided by the Planned Value. It tells you how close
    to the forecasted schedule you actually are. If the SPI is 0.91 you know that your
    project is currently 1 - 0.91 or 0.09 behind schedule.
45. D
    Answer D. PMBOK Guide p. 261-267. The cost variance, or CV is calculated
    using the formula Earned Value - Actual Cost. A project with a negative value is
    over budget and a project with a positive value is currently under budget.
46. C
    Answer C. PMBOK Guide p. 248 - The cost baseline is an output of the
    determine budget process. In order to determine which it is, you would need the
    WBS to see all the deliverables of the project, a network diagram to see the
    dependencies between deliverables, and the listing of potential risks to establish
    any contingency. However, you would not need your scope change management
    plan to determine the cost baseline.
47. A
    Answer A. PMBOK Guide p. 172 - Parametric estimating is a technique that uses
    a statistical relationship between historical data and other variables to calculate a
    cost estimate. In other words a mathematical model.
48. D
    Answer D. PMBOK Guide p. 168 - A Rough Order of Magnitude estimate, or
    ROM, is done in the initiating phases of the project. This estimate has a range of
    -25% to -75% the widest variance, and is therefore used as the earliest estimate
    in the project, often in a project charter.
49. B
    Answer B. Marginal analysis, which uses the law of diminishing returns is an
    attempt to find the point investing $1 gets you exactly $1 in return and investing
    any more gives you less. In those situations, it usually does not make sense to
    invest more. This is an important measure, but does not help you compare
    projects. The Benefit/Cost Ratio, Internal Rate of Return and Net Present Value
    all can help compare projects.
50. A
    Answer A. Marginal analysis, which uses the law of diminishing returns is an
    attempt to find the point investing $1 gets you exactly $1 in return and investing
    any more gives you less. In those situations, it usually does not make sense to
    invest more.
51. C
    Answer C. Opportunity cost is defined as the value of the next highest, not
    selected alternative. In this case, the correct answer is $75,000.
52. D
    Answer D. In this case the training is directly related to the project and is
    therefore a direct cost of the project.
53. D
    Answer D. The setup of a project does not have a direct tie to the amount or
    number of products produced. It is generally done before any production occurs
    and therefore is a fixed cost.
54. A
    Answer A. This is a simple memorization question. You must remember that
    value analysis is all about determining the least costly way to complete work (e.g.
    obtain the most value).
55. B
    Answer B. PMBOK Guide p. 261-267. There are three key variables to establish
    the earned value calculations:
    - Earned value - the work product
    - Planned value - the budget
    - Actual costs - how much you really spent
56. B
    Answer B. This is a trick question of sorts. The question provides both the term of
    the project and the NPV. This would seem to indicate that you must do
    something with the term. However, the NPV takes into account the project term
    making this information unnecessary. All you have to do is select the largest
    value.
57. D
    Answer D. This is an ethics question. PMI's standards are very clear in this area.
    Although it is a largely western way of thinking about this topic you should only
    present the actual estimate.
58. A
    Answer A. Team development or training is considered a direct cost to the
    project as it represents paying for the skills required to complete the project.
59. C
    Answer C. The primary purpose of value analysis is finding a less costly way to
    do the same work.
60. A
    Answer A. With such limited information, it is best to estimate in a range. The
    range can be narrowed as planning progresses and risks are addressed.
61. A
    Answer A. Determining why the sponsor wants such an accurate estimate
    sounds like a good idea at first; however, analogous estimates are less accurate
    than other forms of estimating, as they are prepared with a limited amount of
    detailed information. You need to realize that analogous estimating is a form of
    expert judgment.
62. B
    Answer B. The overall project budget may be included in the project charter but
    not the detailed costs. Even small projects should have a budget and a schedule.
    It is not impossible to create a project budget before the project management
    plan is created. However, it is not wise to do so, as the budget will not be
    accurate. The project budget and baseline are not finalized and accepted until
    the planning processes are completed.