Z23, Appendix 1
Z23
Z23      Appendix 1
(cont)
         Page 1 of 9   IACS Req. 2006/Rev.6 2016
                                                                                   Z23, Appendix 1
Z23                                Shipyard Review Record
(cont)
                     Name of Shipyard                          Date
         1. Details of any Management Systems
         Obtained approval          Certified by              Expiry Date                Remarks
                                                                                       (scope, etc.)
               ISO-9001
         ISO 14001
         ISO 18001
         Other:
         2. Construction Facilities: (Documents such as a brochure of shipyard can be attached in
         lieu of completing this section.)
         2.1 Building Berth (B) or Dock (D)           *In case of berth, Depth is not applicable.
          B/D             Name        Length     Width      Depth*      Building          Crane
                                        (m)       (m)        (m)        Capacity        (Ton x No.)
                                                                         (Gross
                                                                        Tonnage)
         2.2 Outfitting Quays
                Name             Length       Width         Depth      Berthing           Crane
                                   (m)         (m)           (m)       Capacity         (Ton x No.)
                                                                        (Gross
                                                                       Tonnage)
                                              Page 2 of 9             IACS Req. 2006/Rev.6 2016
                                                                                                  Z23, Appendix 1
         2.3 Main Fabrication and Erection Facilities
Z23
(cont)   (1) Marking and cutting of steel plates (including internal members)
              -   Marking method             (Manual, Photo x ___, EPM x ___, NC x ___ others _______)
              -   NC cutting machine         (Gas x ___, Plasma x ___, Laser x ___)
                      Control procedure of NC (On-line,        other)
              -   Cutting equipment          (Edge planer x ___, Roll-shear x ___)
         (2) Marking and cutting of section bar
              -   Marking method       (Manual, NC)        - Marking of reference curved line     (Manual, NC)
              -   Cutting method       (Manual, NC)        - In case of NC      (Gas x ___, Plasma x ___)
         (3) One-side automatic welding machine (Yes, No)
              -   Type of welding machine         (Flux Backing x ___, Flux and Copper Backing x ___ other _______)
              -   Existence of special surface plate for plate welding (Yes, No)
         (4) Fillet welding machine (Gravity, Automatic) Percentage of automatization except gravity: about ___%
              -   Line Welder                (No, Yes: submerged arc x ___ heads, CO 2 x ___ heads)
              -   Small automatic fillet welding machine        (No, Yes: Name: ____________ x ___)
              -   Welding robot              (No, Yes: Portal x ___, Rectangular x ___, Articulated x ___)
         (5) Painting equipment
              -   Plate shot blasting/primer coating machine (No, Yes: Max. Width ___ m, Length ___ m)
              -   Section bar shot blasting/primer coating machine (No, Yes: Max. Length ___ m)
              -   Special coating factory (No, Yes: ___ m x ___ m x ___ sections)
         (6) Vertical automatic welding machine (No, Yes: EG x ___, SEG x ___, ES x ___)
                  EG: Electrogas     SEG: Simplified Electrogas    ES: Electroslag
         (7) Other main fabrication facilities
                                                        Page 3 of 9                  IACS Req. 2006/Rev.6 2016
                                                                                                     Z23, Appendix 1
         3. Shipyard Control of Qualified Welders
Z23      (1) Normal steel
(cont)
                                                                                                                   maintenance
                                                                 certification    traceability    supervision     of qualification
                                       confirm system in
         Shipyard workers                                         Yes / No         Yes / No         Yes / No            Yes / No
                                       place
                                       confirm system in
         Subcontracted workers                                    Yes / No         Yes / No         Yes / No            Yes / No
                                       place
         4. Feature of Construction Procedure
         (1) Subcontract of hull blocks (weight)
              -   Sub members                (No, Yes: Ratio of subcontracted works ___ %, No., of subcontractors ___)
              -   Blocks                     (No, Yes: Ratio of subcontracted works ___ %, No., of subcontractors ___)
         (2) Method of plate block assembly
              -   Method fitting and welding longitudinals and transverse webs on jointed panels
              -   Method welding longitudinals on jointed panels prior to fitting and welding transverse webs
              -   Method fitting and welding a frame consists of longitudinals and transverse webs on jointed panels
              -   Method jointing panels with pre-assembled longitudinals by welding prior to fitting and welding transverse
                  webs
              -   Other (please specify in (5) below)
         (3) - pre-erection outfitting carried out
             grand block/mega block adopted
             Method of erection at building berth/dock
              -   Max. weight of loading block:         ton
              -   Construction method in building dock/berth/land construction etc. (1 ship,      1.5 ships: Semi-tandem, dual
                  entrance)
              -   Block loading process      (single starting block, multi starting blocks, inserting block: No, Yes)
         (4) Final dock (No, Yes: In-house, Other place of the same company, Use other company)
         (5) Other feature of construction procedure
                                                         Page 4 of 9                 IACS Req. 2006/Rev.6 2016
                                                                                                   Z23, Appendix 1
         5. Quality Control System: (Refer to Quality Manual, if available.)
Z23
(cont)                         Item and description                                 Result                Remarks
         (1) Existence of the organization chart including the departments
         of design, purchasing, manufacturing and quality assurance
              -   Are the function, responsibility and competence of the
                  organization clear?
         (2) Quality control organization
              -   Existence of quality control organization
              -   Number of employees in this organization                   _____ persons
                                                                             including the chief
              -   Existence of procedures or plans related to tests and
                  inspections
         (3) Pre-inspection system of shipyard
              -   Is pre-inspection carried out prior to Class inspection?
              -   Are pre-inspectors assigned? (Check the list.)
              -   Number of pre-inspectors (related to hull only)
              -   Are inspection results marked on the object and/or         _____ persons
                  recorded in the checklist?
         (4) Records of inspections and tests
              -   Are records made and kept properly?
              -   Does the responsible person verify the records?
              -   Can the adoption of necessary corrective actions against
                  non-conformity happened be checked?
         (5) Condition at the time of the surveys in the presence of class
         surveyors
              -   Is the schedule of the surveys changed often?
              -   Are pre-inspection, shipyard inspection and repairs
                  completed beforehand?
              -   Are the sufficient preparations for surveys such as
                  scaffoldings, lighting, cleaning made?
         Note:
         Above-mentioned (3) and (4) include the acceptance inspection of subcontracted items.
                                                        Page 5 of 9            IACS Req. 2006/Rev.6 2016
                                                                                                 Z23, Appendix 1
         6. Measures for Safety and Health
Z23
(cont)                          Item and description                                  Result                Remarks
         (1) Are conditions of scaffolding, nets, safety belt, lighting and
         ventilation good?
         (2) Does sufficient attention paid for radiographic examination
         and operation of cherry picker?
         Note:
         7. Control System of Non-Destructive Examination (NDE)
                            Item and description                                    Result                   Remarks
         (1) Number of NDE supervisors in shipyard (including
         persons responsible for judging results)                               _____ persons
         (2) Dependence on subcontracted NDE work
              -   Number of shipyard employees                                  _____ persons
              -   Number of sub-contractors                                     _____ persons
         (3) NDE sub-contractor company’s name and official               Name ___________
         technical qualifications
                                                                          (approved by) __________
                                                                          Name ___________
                                                                          (approved by) __________
         (4) Grade and number of NDE employees with official
         technical qualifications in shipyard
                  Specialized in radiography                              ____ Grade ____ persons
                  Specialized in ultrasonic                               ____ Grade ____ persons
                  Specialized in surface detection                        ____ Grade ____ persons
         (5) If non-destructive examinations are subcontracted, the
         grade and number of officially qualified persons
                  Specialized in radiography                              ____ Grade ____ persons
                  Specialized in ultrasonic                               ____ Grade ____ persons
                  Specialized in surface detection                        ____ Grade ____ persons
         (6) Non-destructive examination equipment (in house)
              -   Number of radiographic equipment                        ______________
              -   Number of ultrasonic equipment                          ______________
         Note:
         Even if all works are subcontracted, it is recommendable to attach the qualified person(s) who can verify the
         works.
                                                         Page 6 of 9              IACS Req. 2006/Rev.6 2016
                                                                                                        Z23, Appendix 1
         8. Quality Control on Production Line
Z23
(cont)                      Item and description                                       Result                   Remarks
         8.1 Preventative measures for misuse of materials
         (1) Job title of supervisor and person in charge of collating     Title of supervisor:
         ordered steel and received steel, and checking of mill
         sheet                                                             ____________________
                                                                           Title of person in charge:
                                                                           ___________________
         (2) Are means for checking the material grade in hand
         prescribed for high-grade steels
         (3) Are regulations prescribed for checking the material
         grade for high-tensile steel for low-temperature
         applications?
         Are there regulations for inscribing high tensile steel on the
         surface of the high tensile steel and special indication for
         steel for low temperature applications?
         (4) Are procedures for re-using of remaining cut-off mild
         steel?
         (5) Are there procedures for re-using of remaining cut-off
         high-tensile steel?
         (6) In the case of (4) and (5) above, can a collation be
         made with the mill sheet?
         (7) Section of controlling the lists of remaining cut-off steel   Name of section:
                                                                           ____________________
         Note:
              - In case of high tensile steel, are means identifying different grades
              - In the case of (3) and (4) above, are the materials approved by other classes controlled similarly?
         8.2 Shot blasting/Primer coating
         (1) Existence of surface preparation standards
         (2) Existence of coating thickness control standards
              -   Existence of thickness measurement records
         Note:
              - The standard is to include the description related traceability after shot blasting and primer coating.
         8.3 Marking and cutting (Assembly work)
         (1) Existence of standards for accuracy and periodical
         inspection of tape measures, tapes, stencils, etc.
         (2) Existence of standards for accuracy of cut dimensions
         and edge preparation
         (3) Existence of standards for finish of cutting face
         (4) What is the frequency and extent of maintenance and
         inspection carried out for ensuring accuracy of NC cutter
         and/or flame planer?
                                                          Page 7 of 9                IACS Req. 2006/Rev.6 2016
                                                                                               Z23, Appendix 1
                            Item and description                                 Result                    Remarks
Z23      (5) In case of NC, are the disks, tapes etc. maintained in
(cont)   good condition?
         (6) What are the measures adopted and guidance given to
         make the worker fully conversant with cutting work
         standards for maintaining accuracy?
         Note:
             -  In case of (2) and (3) above, check items are to include confirmation of edge preparations free from
                piercing hole.
              - NC for section bars is also to be in accordance with the above.
         8.4 Bending and strain free
         (1) Existence of standards for maximum heating
         temperatures during water cooling and at the time of
         bending and distortion removal of steel by quick heating
         and cooling
         (2) Existence of regulations for plate thickness and
         bending radius for flange processing
         (3) What are the measures adopted and guidance given to
         make the worker fully conversant with maintaining quality
         and accuracy during the bending process?
         Note:
         8.5 Control of welding procedure
         (1) Are all welding procedures applied to the ships
         approved by the Society or other IACS members?
         Note:
         8.6 Treatment of serious non-conformities
         (1) Are repair plans submitted to the Society when serious
         non-conformities happened?
         (2) Were the NDE (RT/UT) plans submitted at appropriate
         timing?
         (3) Was the extent of tests extended considering the
         results of the test?
         Note:
         8.7 Hydrostatic and watertight tests
         (1) Is the test plan submitted to the Society?
         (2) Are vacuum tests applied to?
         (3) Are local air injection tests during sub-assembly works
         applied to?
                                                          Page 8 of 9          IACS Req. 2006/Rev.6 2016
                                                                                     Z23, Appendix 1
                            Item and description                           Result            Remarks
Z23      (4) If (2) or (3) above is applied to, are the test procedures
(cont)   approved by the Society?
         Note:
                                                         Page 9 of 9      IACS Req. 2006/Rev.6 2016
                                                                   Z23, Appendix 2
Z23
Z23                               Appendix 2
(cont)
                 Requirements for Tankers and Bulk Carriers subject to
                      SOLAS Chapter II-1 Part A-1 Regulation 3-10
         Goal-based ship construction standards for bulk carriers and oil tankers
                                   Page 1 of 10         IACS Req. 2006/Rev.6 2016