CANAL DESIGN:
DATA:    CANAL LENGTH                                   :                           m
         CANAL BED LEVEL AT START                       :                           m
         CANAL BED LEVEL AT END                         :                           m
         SIDE SLOPE                                            (Z)=   0
         RUGOSITY COFFICIENT                                  (N)=    0.015
         BED SLOPE                                            (S)=    0.0004
         DISCHARGE FOR FEEDER CANAL                           (Q)=    0.085    m3/s
                                                               (Q=    3Cusecs)
                          b                        hz
         FULL SUPPLY DEPTH                                     (h)= 0.400           m
         BED WIDTH                                             (b)= 0.600           m
         CALCULATIONS:
         DISCHARGE                                              Q= 0.085            m3/s
         CROSSECTION AREA                                       A= 0.24             m2
         VETED PERIMETER                                         P= 1.4000          m
         HYDRAULIC RADIUS                                        R= 0.1714          m
         USING MANNING EQUATION                                  V= 0.41            m/s
                                                                Q= 0.09875          m3/s
                                                    Q=      0.085    0.09875        m3/s
         USING FOLLOWING LIMITS
         Q(m3/s)        b(m)         h(m)
           0-.014      0-0.76       0-0.37
         select values for h And b Using above limits
         Traial(1)
         Select values for
                              b= 0.600
                              h= 0.400
                     Critical velosity ratio         = CVR
                     Mean velocity                   =V
                     Critical velosity               = Vc
        Technical guide line page-106              Vc= 0.9994
                                                   Vc= 0.3047         m/s
                                                  CVR= 1.35
        Maximum permissible velocity in Concrete canal
                              Q= Up to 0.71 m3/s
                              V= 0.82m/s
         Our Case             Q= 0.085       m3/s
                              V= 0.41        m/s
         Maximum velocity check is satisfied(V<0.82m/s)
         RESULTS:
         Q(m3/s)        b(m)         h(m)     V(m/s)      CVR          NFB(m)
           0.085       0.600         0.400      0.41      1.35          0.15
                                                               Eng. H.A.Jayantha de silva
                                                                      Di's office
                                                                      Anuradhapura
CANAL DESIGN:
DATA:    CANAL LENGTH                                  :                      m
         CANAL BED LEVEL AT START                      :                      m
         CANAL BED LEVEL AT END                        :                      m
         SIDE SLOPE                                           (Z)=   0
         RUGOSITY COFFICIENT                                 (N)=    0.015
         BED SLOPE                                           (S)=    0.0004
         DISCHARGE FOR FEEDER CANAL                          (Q)=    0.085    m3/s
                                                              (Q=    3Cusecs)
                          b                       hz
         FULL SUPPLY DEPTH                                    (h)= 0.400      m
         BED WIDTH                                            (b)= 0.600      m
         CALCULATIONS:
         DISCHARGE                                              Q= 0.085      m3/s
         CROSSECTION AREA                                       A= 0.24       m2
         VETED PERIMETER                                        P= 1.4000     m
         HYDRAULIC RADIUS                                       R= 0.1714     m
         USING MANNING EQUATION                                 V= 0.41       m/s
                                                               Q= 0.09875     m3/s
                                                    Q=     0.085    0.09875   m3/s
         USING FOLLOWING LIMITS
         Q(m3/s)        b(m)         h(m)
           0-.014      0-0.76       0-0.37
         select values for h And b Using above limits
         Traial(1)
         Select values for
                              b= 0.600
                              h= 0.400
                     Critical velosity ratio         = CVR
                     Mean velocity                   =V
                     Critical velosity               = Vc
        Technical guide line page-106              Vc= 0.9994
                                                   Vc= 0.3047        m/s
                                                  CVR= 1.35
        Maximum permissible velocity in Concrete canal
                              Q= Up to 0.71 m3/s
                              V= 0.82m/s
         Our Case             Q= 0.085       m3/s
                              V= 0.41        m/s
         Maximum velocity check is satisfied(V<0.82m/s)
RESULTS:
Q(m3/s)    b(m)    h(m)    V(m/s)   CVR    NFB(m)
  0.085    0.600   0.400    0.41    1.35    0.15