Detailed Estimate For Girls Friendly Toilet: SL No - Description of Work No L (M) B (M) H (M) Qnty Unit Rate Amount (RS)

The document provides a detailed estimate for the construction of girls friendly and common toilets. It lists 17 items with descriptions of work, quantities, units, rates and amounts for each. The total estimate for the girls friendly toilet is Rs. 97896 and for the common toilet/urinals is Rs. 80000. The estimates include costs for earthwork, masonry, flooring, plastering, fittings and other miscellaneous works.

Uploaded by

Lama Ressu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
225 views4 pages

Detailed Estimate For Girls Friendly Toilet: SL No - Description of Work No L (M) B (M) H (M) Qnty Unit Rate Amount (RS)

The document provides a detailed estimate for the construction of girls friendly and common toilets. It lists 17 items with descriptions of work, quantities, units, rates and amounts for each. The total estimate for the girls friendly toilet is Rs. 97896 and for the common toilet/urinals is Rs. 80000. The estimates include costs for earthwork, masonry, flooring, plastering, fittings and other miscellaneous works.

Uploaded by

Lama Ressu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

Detailed estimate for Girls friendly toilet

Sl
H Amount
No Description of work No L (m) B (m) Qnty Unit Rate
(m) (Rs)
.
1 Earth work excavation in
ordinary soil for foundation 1 10.25 0.60 0.75 m3 126.30
6.15 776.745
2 Dry rubble masonry cm 1:8
for foundation including all
1 10.25 0.45 0.45 m3 1709.60
cost of materials and labour
charges 2.08 3548.489
3 Random rubble in cement
1 10.25 0.45 0.3 m3 3235.79
mortar 1:6 for Basement 1.38 4477.52
4 Earth filling
2 1.1 1.6 0.3 m3
1.06 422.52 446.18
5
Solid brick masonry using
bricks of good quality with
CM 1:6 for super structure
1 10.25 0.15 2.30 3.54

steps 1 2.65 0.45 0.15 0.18

3.72

Deductions

D1 2 0.8 0,15 2.1


0.28
Net total(3.54--.28) x x x 3.26 m3 4460.15 14540.09
6 Flooring with cement
concrete 1:4:8 75mm thick
using 40mm (nominal size)
broken stone and plastered 2 1.10 1.60
over with 12mm thick cement
m2 564.18
mortar 1:3 one coat floated
hard and trowelled smooth 3.52 1985.91
7 Flooring with Ceramic
2 1.1 1.6 3.52 m2 736.72
tiles 2593.254
8 Dadoing in thewith CM 1:3
12mm

with coloured tiles 1 10.8 1.5 16.20 m2 1249.63 20244.01

9 RC C 1:2:4 20mm with


formwork

for slab,,2noscorner slab. 2.65 2.65 0.1 0.70 m3 12291.00 8631.35


10 Reinforcement
62.00 kg 63.40 3930.80
11 Plastering of wall with CM
1:4, 12 mm thick
Outside 2 10.8 2.30 49.68

step 1 2.65 0.90 2.39

52.07 m2 127.00 6612.255


12 Plastering of wall with CM
2 2.65 2.65 m2 163.00
1:3, 9mm thick 14.05 2289.335
13 Whitewashing 2 coats
area same as plastering of
m2 9.60
walls & ceilings 62 595.2
14
Steel doors for urinals 2 LS 3000.00

15 Water supply and Sanitary


fittings
Indian water closet 1 Each 650.00 650.00
European water closet 1 Each 822.00 822.00
Wash basin 1 Each 632.00 632.00
Rectangular mirror 2 Each 306.00 612.00
soap tray 2 Each 163.00 326.00

Other pipe fittings for water


LS
supply and sanitary
6000.00

16 Soak pit construction


( 1.00X1.0X1.5 m)

4000.00
17 Incinerator LS 5000.00
18 Unforseen items if any
including tax 6182.85
97896.00
(Rupees One lakh Only)
Detailed estimate for common toilet / urinals
Sl
H Amount
No Description of work No L (m) B (m) Qnty Unit Rate
(m) (Rs)
.
1 Earth work excavation in
ordinary soil for foundation 1 7.90 0.60 0.75 4.74 m3 126.30 598.662
2 Dry rubble masonry cm 1:8
for foundation including all
1 7.90 0.45 0.45 m3 1709.60
cost of materials and labour
charges 1.60 2734.933
3 Random rubble in cement
1 7.90 0.45 0.3 m3 3235.79
mortar 1:6 for Basement 1.07 3450.97
4 Earth filling 2 1.1 2 0.3 1.32 m3 422.52 557.73
5 Solid brick masonry using
bricks of good quality with
CM 1:6 for super structure 1 7.90 0.15 2.30 2.73

steps 1 2.65 0.45 0.15 0.18


2.90
Deductions
D1 1 0.9 0,15 2.1 0.28
Net total(2.9--0.28) x x x 2.62 m3 4460.15 11685.59

6 Flooring with cement


concrete 1:4:8 75mm thick
2 1.10 2.00
using 40mm (nominal size)
broken stone and plastered 4.40 m2 564.18 2482.39
7 over with 12mm
Flooring thick cement
with Ceramic
2 1.1 2 4.40 m2 736.72
tiles 3241.568
8 Dadoing walls with CM 1:3
12mm
with coloured tiles 1 7.9 1 7.90 m2 1249.63 9872.08
9 RC C 1:2:4 20mm with
formwork
for slab,2 nos corner slab. 3.25 3 0.1 0.98 m3 12291.00 11983.73
10
Reinforcement 78.00 kg 63.40 4945.20
11 Plastering of wall with CM
1:4, 12 mm thick
Outside 2 7.9 2.30 36.34
step 1 2.65 0.90 2.39
38.73 m2 127.00 4918.075
12 Plastering of wall with CM 2 7.9 2.65 41.87 m2 163.00 6824.81
13 Whitewashing 2 coats
area same as plastering of
m2 9.60
walls & ceilings 41.87 401.952
14 Steel doors for
1 nos LS 3000.00
urinals(22gauge sheet)
15 Water supply and Sanitary
fittings ,wash basin,soap tray
etc.
Urinal flat large 2 Each 1023.00 2046.00
Washbasin 1 Each 632.00 632.00
Rectangular mirror 1 Each 306.00 306.00
Soap tray 1 Each 163.00 163.00
Other sanitary and plumbing
LS
fittings 3000.00
16 Soak pit construction
LS
( 1.00X1.0X1.5 m) 3000.00
17 Unforseen items if any
including tax 4155.32
80000.00
(Rupees Eighty thousand Only)