MINUTES OF MEETING
RATI MANZIL MATUNGA
Date & Time of Meeting : 08-05-2018 at 12:00 Hours. Venue of Meeting : TREC OFFICE
Meeting No.-MAY-01
Prepared By : RANJAN
Sr. No. Attendees Member Present Designation Project Team
1 √ Mr. Karan Jogani Joint MD RJ Realtors
2 √ Mr. Gulzar Malhotra COO TREC
3 √ Mr. Prem Kumar Bagalkot Planning Manager TREC
4 √ Ms. Akshata Parvatikar Sr. Engineer Planning TREC
5 √ Mr. Manoj K Pandey Project Manager TREC
6 √ Mr. Ranjan Project Engineer RJ Realtors
7 √ Mr. Rajkumar Prajapati Sr. Supervisor RJ Realtors
8 √ Mr. Bali Bhandari Partner M/s. M S Enterprises.
9 √ Mr. Shakeel Ghanchi Partner M/s. M S Enterprises.
Sr. no. Action Required Action By Status Remarks
Department Wise
A HSE
MS Enterprises has been strictly instructed to
Implement the proper safety measures at
1 Safety precautions implementation MS WIP construction. Incase there is no adherence to it
Enterprises
penalty is levied. Safety person to be appointed
by 15-05-2018
Material should be stacked in proper manner
MS
2 Removing of extra material from site. Enterprises WIP and same to be supervised by site team. Scrap
to be removed by 15-05-2018
B QA/QC
The activity is under progress and rectified by
MS
1 RCC Related repairs WIP MS Enterprises. Site team to take the strict
Enterprises action.
D Execution
Girder level slab to be completed by 13-Jun-
1 Progress Review for GIRDER level MS WIP 2018 as per Meeting held at TREC office on
Enterprises
dated 08-05-2018.
MS
2 Submition of BBS upto Girder & Whole Building Enterprises OPEN By today itself as disscused in meeting.
Site logistic plan to be prepared jointly with MS
MS
3 Mansoon preparation Enterprises OPEN Enterprises & Same shall be followed. Expected
Date 20-05-2018 for Mansoon
E Others
1 Micro Schedule upto Girder slab TREC OPEN