Unit IG2: Risk assessment
Declaration: by submitting this assessment (Parts 1 – 4) for marking I declare that it is entirely my own work. I understand that falsely claiming that the
work is my own is malpractice and can lead to NEBOSH imposing severe penalties (see the NEBOSH Malpractice Policy for further information).
Part 1: Background
 Include in here the organisation’s name* and location* and number of workers. You must then go on to give a description of the main
 activities/products/services carried out. You must also describe the area to be risk assessed eg, whole site, and anything else that you
 consider relevant (approximately 150 to 200 words):
 My selected organization is Al Jaleel Construction Company located in Dubai with total number of workers employed 350
 Al Jaleel Construction Company is working on different projects like power transmission, distribution sector and building construction work and
 currently working on a mega project of construction of Al Mehraj Hotel in Dubai, Al Jaleel construction company is a well stablish mature
 organization of almost 20 year old, it is the big company, its services sach as houses, appartments, schools, roads,factories and bridges
 manufacturing and number of activities are carried out on construction site such as excavation work, finishing, steel, electrical, plumbing work,
 tiles, doors, painting demolition, welding, loading/unloading, moving construction materials, plastering of roof and walls, and drilling work.
 Al Jaleel construction company operates 9:00 AM to 6:00 PM 6 day in a week, Friday off so there are 9 working hours for workers including 1-hour
 rest in a day. So only one shift involved in shift system.
 My assessment will cover Project engineering department site where different civil and MEP works are carried out HR, Financial and marketing
 department has separates risk assessment. The project manager who reports directly to managing director has direct responsibility of health and
 safety.
 You must now give a brief outline on how you completed the risk assessment (approximately 200 words):
 I start looking the ILO Code of Practice (COP) relating to construction works and I found COP Safety and Health in construction,
 https://www.ilo.org good source of information after studying deeply,
 I start working around the workplace and talk with different workers who are working and they gave me information which is very
 authentic and can’t be observable by a simple visual inspection, for example different workers don’t know there are safety jackets are
 available and why these should be worn. Then I looked the accidents and incident records to gather information in the past problems,
 I also checked inspection reports records, safety committee meeting minutes, even i checked the ppolicy and also checked the
 medical record to see if there were any recurring themes for ill health.
Learner number: 00536366                       Learner name:   Mahtab Khan                                                      Page 1 of 11
    For assessing a control measures, ILO C165, R175, safety and health in construction and C155/R164 recommendation 1988.HSE
    construction design and management Regulation 2005. Work at height Regulation 2005.
    I also referred ILO convention C155 and recommendation R164 and ILO COP Safety and Health building & civil engineering works
    https://www.ilo.org/global/topics/safety-and-health-at-work/industries-sectors/WCMS_219022/lang--en/index.htm%20and%20HSE
    %20gaudiness%20documents%20construction%20dust%20https://www.hse.gov.uk/pubns/eh44.pdf .
   * If you’re worried about confidentiality, you can invent a false name and location for your organisation but, all other information provided must be
   factual.
   Part 2: Risk Assessment
   Organisation name: Al Jaleel Construction Company
   Date of assessment:1/03/2020
   Scope of risk assessment: Under Construction Al Mehraj Hotel, Dubai
Hazard       Who might be harmed            What are you already doing? What further controls/actions are            Timescales for
category and and how?                                                   required?                                    further actions Responsible
hazard                                                                                                               to be completed person’s job title
                                                                                                                     (within …)
Vibration      Workers using faulty hand All workers are trained in use of Setup of monitoring system to ensure 2 Week                  Supervisor
               held disks, Cutters,          vibration tools               that vibration tools and equipment’s
Sanding or     Grinders & Hilti Drills could                               are not excessively used without
grinding       lead to arm and hand          Ensure that equipments are    proper maintenance.
activity sach  vibration (HAV)               well maintained to avoid
as grinders,   Tendons, white finger,        excessive vibration           Installing the vibration dumping seats 1 month               Finance manager
hilti drill,   nerve damage, muscles                                                                                                    supervisor
cutters and    weakness, joint damage                                      Implementing Job rotation for workers
hand held disk                                                             who are performing continuous          1 Week                HSE Officer
   Learner number: 00536366                      Learner name:    Mahtab Khan                                                     Page 2 of 11
Hazard       Who might be harmed              What are you already doing? What further controls/actions are             Timescales for
category and and how?                                                     required?                                     further actions Responsible
hazard                                                                                                                  to be completed person’s job title
                                                                                                                        (within …)
                                                                              operations with such tools.
                                                                              Provide vibration reducing PPE such
                                                                              as vibration absorb gloves
                                                                                                                                          Supervisor
                                                                                                                    1 week
Electricity     Workers, Electrician’s                                        Replace the damaged electrical cables 1 week                Line
                                                                              with suitable cables with a outer                           manager/Supervisor
                                                                              covering such as an insulating sheath
Damaged         Skin Burns/ Scalds,           Tools inspection training for   on the cables
electrical      Electrocution resulting in    identification of damaged &
cables found    fatalities, Fire induced by   faulty tools given to all       Provide tools and cables stead            2 week            Store manager
of powered      sparking                      operators and workers.
tools during                                                                  Damaged Tools must be stored and          2 days            Supervisor/Store
Link Box in                                                                   registered separately for rectification                     manager
installation                                                                  as well as to restrict their use.
works
                                                                              Tool fitness card or sticker must be   1 week               Health and safety officer
                                                                              pasted on every tool and should be
                                                                              checked by operator prior to its usage
                                                                              The main switchboard has need to                            Supervisor
                                                                              built with residual current device        1week             Store manager
                                                                              RCDs.
Substance       All Workers involved in the All the chemicals are kept in a Stop the usage of storing chemicals in 1 week                 Supervisor
Abuse at work use of these chemicals          well-ventilated area away from water bottles.
                                              direct sunlight.
Diesel and      Acute or chronic effects on                                    Suitable containers should be provided1 week               Store manager
thinner was     worker’s health due to        Workers  are  informed about the for all the chemicals                                      HSE officer
stored in water accidental ingestion and      usage of these chemicals and
bottles         contact could lead to serious the hazards through tool box     Labelling & Precautions to be pasted 1 week                Store manager
accessed by                                   talk                             on contents of the containers
   Learner number: 00536366                        Learner name:    Mahtab Khan                                                      Page 3 of 11
Hazard       Who might be harmed                What are you already doing? What further controls/actions are             Timescales for
category and and how?                                                       required?                                     further actions Responsible
hazard                                                                                                                    to be completed person’s job title
                                                                                                                          (within …)
persnol use     illnesses such as vomiting’s,
                skin irritation, respiratory                                   Constant supervision should be done 1 month                  Supervisor / HSE
                problem, lung disease                                          regularly                                                    Officer
                nausea, loss of
                consciousness.
Work at height All workers, visitors            Use of certified slinging      Barricading the lifting area to restrict   1 weeks           Line manager
                passing by or involved in       accessories in place.          unnecessary access by visitors,
During lifting  lifting operations due to                                      members of public.
activity rigger improper slinging could         Lifting plan in place to execute
is not          lead to fatal accidents,        lifting operations               Obtaining permits from competent         1 month           Supervisor
possessing      multiple injuries &                                              authorities while working near
competence      damages to the                                                   overhead power lines
certificate.    surrounding area or
                equipment’s.                                                   Arrangement of competence training 3 days                    Health and safety
                                                                               by a third party for certification of the                    officer
                                                                               all the workers such as crane operator,
                                                                               rigger & flagmen.
                                                                               Tool box talks to all the workers prior 1 month              Health and safety
                                                                               to each lifting activity about special                       officer
                                                                               precautions
   Learner number: 00536366                          Learner name:    Mahtab Khan                                                      Page 4 of 11
Hazard       Who might be harmed             What are you already doing? What further controls/actions are           Timescales for
category and and how?                                                    required?                                   further actions Responsible
hazard                                                                                                               to be completed person’s job title
                                                                                                                     (within …)
Work at height Workers working at height     Scaffolding erected by         Provision of safety harness to all the   2 days            Line Manager /
                without safety harnesses     competent persons certified by people working at height.                                  Supervisor
Workers         on scaffolds might be        a third party.
working on      harmed by falling from
scaffolding for height, resulting in         Scaffolding inspected by        Provide frame and brace scaffolding 3weeks                Fiance manager
painting work fractures, head injuries,      scaffolding inspector and place system                                                    Supervisor
                other co-workers, visitors   green tag with his signature.
                                                                             Tool box talks on all precautions prior                   HSE Officer
                                             Proper warning signs in place to each shift for those working at
                                             related to the nature of work. height
                                                                                                                     1 month
Health welfare All employees working       Suitable sheds provided at        Alter working schedule to work in       2 Week            Line Manager /
and work        outdoors could be affected ample locations at all work       cooler time.                                              Director
environment     to Heat Stress, Fatigue    areas under direct sunlight.
                and Sun Stroke leading to                                    Install drinking water stations and     1 month           Supervisor
Mesons          dehydration in the body. Cotton based clothing provided      shelters nearby the activity areas.
plustring and                              to entire workforce for better
welders                                    perspiration and comfort
working in                                 especially during hot season      Mandatory instructions & supervision 1 month              Supervisor / HSE
high                                                                         to entire workforce about the adverse                     Officer
temperature,                                                                 effects & it’s precautions during hot
exposed to                                                                   season.
direct sunlight
and high
levels of
   Learner number: 00536366                       Learner name:   Mahtab Khan                                                     Page 5 of 11
Hazard       Who might be harmed                What are you already doing? What further controls/actions are          Timescales for
category and and how?                                                       required?                                  further actions Responsible
hazard                                                                                                                 to be completed person’s job title
                                                                                                                       (within …)
humidity.
Hazardous        All Workers                    Proper PPE is Provided to all   Assign workers to clean the rest area. 2 days            Supervisor
Substances                                      the workers such as safety
                                                shoes,safety helmet,safety      Isolate or barricade the area with
Sharp edges      Could lead to potential        gloves.                         provision of relevant signage
objects,         sustain puncture injury,                                       Adhere to safe system of work.         1 week            Store Manager
concreet         sever cut and fatal injuries
waste found at                                                                  Continuous monitoring and inspection
various                                                                                                                1 month           Supervisor
locations
worker moving
area and
worker reat
area
Noise          Workers working with        No control measures available        Issuance of hearing protection aids   3 days             Store Manager
               benchtop grinders &                                              such as ear plugs to lessen the noise
Noise emitting cutters working without                                          exposure.
from           any ear protection which
Machineries    could lead to hearing loss.                                      Adequate maintenance of                1 Week            Store Manager / Line
Hilty drill,                                                                    machinery/tools which could reduce
cutter and                                                                      the equipment noise
grinder                                                                                                                                  Store Manager / Line
emitting noise                                                                  Alternative shift procedures to avoid 2 Weeks            Manager
during work                                                                     consistent exposure of same individual
activities
                                                                                Educating workers on hazards &                           Supervisor / HSE
                                                                                precautions to be considered while     1 week            Officer
                                                                                working in a noisy environment
   Learner number: 00536366                          Learner name:   Mahtab Khan                                                    Page 6 of 11
Hazard       Who might be harmed           What are you already doing? What further controls/actions are         Timescales for
category and and how?                                                  required?                                 further actions Responsible
hazard                                                                                                           to be completed person’s job title
                                                                                                                 (within …)
                                                                           through tool box talks
Work          Workers working with       Workers briefed about the       Installation of suitable platform for   1 week            Store manager
equipment     machinery                  hazards associated with         fixing the cutter to stay firm.
and machinery                            improper tools through tool box
              Found unstable platform of talks
              steel cutter which could
Non           result in grave injuries
maintenance while in operation           Workers provided with suitable
of machinery                             protection such as gloves.
Steel cutter
   Learner number: 00536366                     Learner name:    Mahtab Khan                                                  Page 7 of 11
You must pIck the three highest priority/most urgent actions and justify your choice. Your justification must include moral, legal and financial argumen
(500 to 700 words); consideration of likelihood and probable severity of injury, ill-health and/or harm (150 to 250 words); description of how effective each acti
is likely to be in controlling the risk (250 to 350 words).
The action that I prioritise are:
1.       The main switchboard has need to built with residual current device. (hazard category Electricity)
2.       Purchased water cooler and Shelters to place on site so employee work under the high temperature they can drink the cold water and rest in the shel
         (hazard category employee working in high temperature under direct sunlight (Radiation UV))
3.       Provide frame and Brace scaffolding system. (hazard category work at height)
Al Jaleel construction company according to the occupational safety and health administration it has moral responsibility to protect their worker and others who
          connected to their business and provide to healthy and safe place of work. Al jaleel construction company has moral and legal responsibility to provid
          welfare facilities of their employees at the site or the work place where the fulfil their bodily requairments. It is clearly mentioned in ILO 167 about
          provision of basic welfare facilities and easy access to it and mental satisfaction of the employees. It is employer responsibilities to the comply with th
          prescribed safety and health measures at the work place. Accidents at the work place could lead to serious injuries, even death which have a major
          impects workers mently health. Al jaleel construction company expected to provide a work place free of hazards good excess ,agress and morally
          provide safe hardware and substances which would be requaired to be use rotienly or not rotienly.
Financial impacts include to the Al jaleel construction company insurance costs premium will increase, loss of production or reduce output due to loss of staff o
         staff being diverted to investigate the accidents, sikness cover sick pay, Damege (Plants, meterials, premises, Fines panalties) and the cost of
         accidently damage property associated with enforcement action.
Possible enforcement actions that Al Jaleel construction could receive the possible enforcement action with prohibitions that all the particular activities stop. Al
         jaleel constitution company Could receive the notices thats two types possible enforcement action these are prohibition or improvement if prohibitions
         thats means stop all the works of the particular activities and the improvement means things put must be right within certain time period relating these
         activities by the regulation authority. The financial impects on the organization could effect if these activities would stop.
There are also specific requirements that Al Jaleel construction company need to meet under the ILO Convention C155 and
Recommendation (R164). The Convention/Recommendation requires employers to make sure that machines and equipment are safe to use.
Specifically, the ILO’s CoP ‘Safety and health in the use of machinery; (section 8.5) requires that all lifting equipment and accessories should
Learner number: 00536366                      Learner name:    Mahtab Khan                                                      Page 8 of 11
be maintained, inspected and tested at appropriate intervals. Failure to do so could have serious repercussions, including worker \
compensation claims.
The ILO’s Convention C155 and Recommendation (R164) requires employers to make sure that processes are reasonably safe. The ILO
code of practice (CoP) ‘Safety in the use of chemicals at work’ gives specific advice on the appropriate measures that employers must make
to protect workers against the risks identified by an assessment of risk. The ILO’s Code of Practice ‘Recording and notification of
occupational accidents and diseases require employers to report cases of occupational asthma to our country’s health and safety regulator.
The organisation could also find that civil claims from workers made ill by these work activities could be made. Some of these claims may be
made some years after the worker has left Al Jaleel construction company employment. The likely amount of compensation payable for civil
claims can be substantial; in addition to this legal fee (solicitors, courts etc) would also be likely to be very high. I would also point out that
many of these costs would not recoverably from the insurance company.
If something goes wrong, Al Jaleel construction company reputation could take a serious hit which could result in loss of
contracts (especially the insurance work).
 Likelihood and severity:
1.The likelihood of uncertified rigger working on site is quite serious issue, uncertified rigger not knows the technical specification of how to
carrying the load and what is the capacity of crane and load and clings, the severity of the risk occurring could be fairly serious, injury is
likely to head injury, falling load form hight cause serious injury or fatality, possible death, the severity will depend on when and how it’s going
wrong, e.g., fall load due to crane capacity is not applicable, un correct signal form the rigger side and load stuck with any structure, etc.
2.Working under direct sunlight and water cooler is not available on site is very serious issue on site, without water facility there is more
likelihood possibility of occurring accident on site and under the direct sunlight the risk going to higher, consequences are likely to be
unconscious of high temperature, mentally disturb, headache, stress cause some dangerous happened on site, severity of the risk is quite
high because there is also no availability of shelter where work can take rest during break.
3.The likelihood of injuries occurring from working at hight is quite high. The severity of the risk occurring could be fairly serious. Injuries are
likely to range from minor injuries such as bruising, sprains/strains, slightly more serious injuries such as fractures, or very serious injuries
such as head or internal injuries. The severity will depend on what height the worker falls from e.g., from the top of the Scaffold (over an
eight-foot drop) or fall from the access steps.
Learner number: 00536366                       Learner name:    Mahtab Khan                                                       Page 9 of 11
   Controlling the risk:
   1.The residence current device or safety switch protect us from the most frequent cause of electrocution, RCDs is electric safety devices to design to immediat
            switch off the supply of electricity and when electric leaking to earth is detected at harmful levels. I also
   mention the timescale 3days in the report so without the installing the RCDs to work on site can more dangerous for
   others, and it is the company policy that every person should train and competent in his work so there is less possibility of any unwanted
   event.
   2.Exposed to direct sunlight and high levels of humidity is a major subject on site mostly worker working under the direct sunlight and they are
   affected of low water lever in body so must be provide the cold water on site, also provide the shelter for him is very good precaution so
   worker is not under the direct sunlight, allow to time of rest after 1 hour 10 minutes is highly recommended, I also mention the timescale in
   report 1 month so install the cold-water cooler on site in this period.
   3.According to the Health and safety executive working at height is the construction industries top causes of death and majuor injuries in the work place. The
           underlying principal of the work at height regulation is working at height should be avoided where ever possible and also providing the training which
           aware the worker complete hazards about the work at height and how to control the risk of height. I provide the frame and brace scaffolding system to
           the workers and also i have given a timescale of 1 week to provide a frame and brace scaffolding system as discuss and agreed with the project
           manager. It is hoped that this project will be completed well within given timeline.
   Part 4: Review, communicate and check
You must now give a review date for your risk assessment and say why you have chosen this date (10 to 50 words).
I spoke with the line manager and the company Risk assessment is every 6 months which I agreed as for a construction site 6 month is good
   Learner number: 00536366                     Learner name:   Mahtab Khan                                                     Page 10 of 11
enough to review the risk assessment.
You must now indicate how the risk assessment findings will be communicated (including who needs to know the information) (100 to 150 words).
Regarding this risk assessment I arrange a meeting with responsible person of finance department to discuss and agree to go through action in
that risk assessment. Also discuss and provide the summery of my findings and action to the site manager also officially send through email for
further actions. In next tool box talk I aware to the workers about my findings and also, I tells to the worker that action to be taken. This al findings
of the risk assessment and actions to be taken posted on the company entrance that every worker has access to read and knowledge.
You must now indicate how you will follow-up on the risk assessment to check that the actions have been carried out (100 to 150 words).
With a proper schedule meeting with the Supervisor and the Line manager I recorded the deadline of each actions to be taken.
I will check with them regularly about the progress in each action. If no action is taken, I will discuss with the representative about the issues such
as delay in work due to manpower. Any action which is overdue I will speak with the Top management about the concern so that necessary action
is taken as soon as possible.
   Learner number: 00536366                       Learner name:    Mahtab Khan                                                       Page 11 of 11