PMP Certification Practice Exam1
PMP Certification Practice Exam1
(/Default.aspx)
Materials in this exam are based on the text, A Guide to the Project Management Body of Knowledge (PMBOK®
Guide), Sixth edition, Project Management Institute, Inc. 2018
Questions
1. An important trend in the Project Stakeholder Engagement process is ...?
a. Identifying all stakeholders
b. Stakeholder diversity
c. Complexity of stakeholder relationships
d. Communication technology
CORRECT: a – Answers b, c and d are tailoring considerations. PMBOK Guide®, 6th edition, p. 505
6. You are the project manager of ABC project. Mid-way through the project a key component was found defective.
This was not planned for. The team met after the event and managed to make the product work without the
defective component. This is an example of -
a. Risk mitigation
b. Transfer of risk
c. Work-around
d. Accepting the consequences passively.
CORRECT: c. This was an unplanned event that happened. Work around refers to handling of risk that has
occurred but was not planned for.
CORRECT: b. Problem-solving or Confrontation is the best solution for resolving conflicts and leads to long-lasting
conflict resolution.
9. You are the Project Manager of ABC project. The project is being executed in an earthquake-prone area. To take
care of this you buy insurance for earthquakes. This is an example of
https://www.edwel.com/Free-Resources/PMP-Certification-Practice-Exam.aspx?fbclid=IwAR0rK8MIw5YV1cskTe9AklQokwTwYZMUrVsRDZlLTB… 2/18
09/04/2020 PMP Certification Practice Exam
a. Risk mitigation
b. Transfer of risk
c. Risk contingency planning
d. Accepting the consequences passively.
10. Which of these is correct with respect to a product developed or a service performed.
a. Bad quality is acceptable, but bad grade is not.
b. Bad grade is acceptable, but bad quality is not.
c. Neither bad grade nor quality is acceptable.
d. Grade and quality is the same thing.
CORRECT: b. Grade refers to category or rank given to entities having same functional use but different technical
characteristics.
CORRECT: d. Continuous small improvements is part of Kaizen theory. Hence a is incorrect. The Plan-do-Check-
Act doctrine was proposed by Deming.
13. You are the Project Manager for ABC project. You need to find out which issue has maximum impact on the project.
Which tool should you use?
a. Pareto diagram
b. Control chart
c. Trend analysis
d. Fishbone diagram
CORRECT: a. Pareto chart is built on the 80:20 theory. 80% of the defects are caused due to 20% of the issues. A
Project Manager needs to focus on these 20% issues.
https://www.edwel.com/Free-Resources/PMP-Certification-Practice-Exam.aspx?fbclid=IwAR0rK8MIw5YV1cskTe9AklQokwTwYZMUrVsRDZlLTB… 3/18
09/04/2020 PMP Certification Practice Exam
14. When analyzing quality for a project a Project Manager decides to use a tool. This tool provides a creative way to
look at the causes or potential causes of a problem. Which tool is the Project Manager planning to use?
a. Pareto diagram
b. Control chart
c. Statistical sampling
d. Ishikawa diagram
CORRECT: d. Ishikawa or Fish bone diagram is the tool that the Project Manager is planning to use.
15. A Project Manager is using AOA to perform critical path analysis. The network diagram is represented as shown
using below. Which of the following represents the path:
a. ABIR
b. CDHR
c. CDGIR
d. EFGIR
ActivityDuration Dependent on
A 3 none
C 3 none
B 2 A
D 5 C
E 2 none
F 4 E
G 3 D,F
H 1 D,F
I 2 B,G
R 0 H,I
CORRECT: c. CDGIR represents the critical path. It is the longest path through the network with the duration of 13.
16. For the sequence diagram in question 15, what is the float of activity B
a. 2
b. 3
c. 5
d. 6
CORRECT: d. The path ABIR has duration of seven. Hence B can be delayed by six days before the next event can
begin.
17. For the sequence diagram in question 15, what is the float of activity H
a. 2
b. 3
c. 4
d. 6
CORRECT: c. The path CDHR has duration of nine days. Hence H can be delayed by four days before the next
event can begin.
https://www.edwel.com/Free-Resources/PMP-Certification-Practice-Exam.aspx?fbclid=IwAR0rK8MIw5YV1cskTe9AklQokwTwYZMUrVsRDZlLTB… 4/18
09/04/2020 PMP Certification Practice Exam
CORRECT: d. Job security, salary, clean and safe working conditions are examples of hygiene factors. Appreciation
at work is not a hygiene factor, but instead a motivating factor.
19. According to Maslow's hierarchy of needs, which is the lowest level which must be met before other levels can be
met.
a. Esteem
b. Physiological
c. Social
d. Safety
CORRECT: b. Physiological factors appear at the lowest level of Maslow's hierarchy triangle.
CORRECT: a. The other three options are examples of benefit measurement method.
22. You are part of an expert committee deciding which project should be implemented by your company. Your
committee asks tough questions from the project teams and helps decide which project your company should
select. Which project selection technique are you using.
a. Scoring Model
b. Committee Selection
c. Murder Board
d. Defined Benefit
CORRECT: c. Murder board is a process where a committee asks questions from project representatives as part of
the project selection process.
https://www.edwel.com/Free-Resources/PMP-Certification-Practice-Exam.aspx?fbclid=IwAR0rK8MIw5YV1cskTe9AklQokwTwYZMUrVsRDZlLTB… 5/18
09/04/2020 PMP Certification Practice Exam
24. You have just been made the Project Manager of the ABC project. You are trying to read the WBS and are unable to
understand some of the WBS components. Which should be your first step to understand this?
a. Refer to the WBS dictionary
b. Refer to the scope statement
c. Refer to the Project charter
d. Contact the previous Project Manager
CORRECT: a. WBS dictionary is the best option. WBS Dictionary identifies all the components used in the WBS
25. Who among the following is responsible for performing the scope validation
a. Project Manager
b. Senior Management
c. The quality team
d. The customer
CORRECT: d. Scope Validation is the process of the customer accepting the project deliverables.
26. You are planning to use PERT for planning of your project. A task has pessimistic estimate of 24 days, most likely
estimate of 15 days and optimistic estimate of 12 days. What is the mean using the PERT technique?
a. 18 days
b. 25.5 days
c. 15 days
d. 16 days
CORRECT: d. Mean for PERT is defined as (P+4M+O)/6 which comes out to be 16 days.
27. Before committing to a larger portion of the project scope, the buyer of a product or service will frequently implement
a ...?
a. Logistics approach
b. Long lead time
c. Managed supply chain
d. Trial engagement
https://www.edwel.com/Free-Resources/PMP-Certification-Practice-Exam.aspx?fbclid=IwAR0rK8MIw5YV1cskTe9AklQokwTwYZMUrVsRDZlLTB… 6/18
09/04/2020 PMP Certification Practice Exam
CORRECT: c. In oligopoly, the action of one seller has an impact on other sellers, as there are very few sellers.
29. You are using straight line depreciation to compute the value of your computer after three years. If the current cost
is $1000, what will be the value after three years assuming that the computer's life is five years.
a. $0
b. $400
c. $500
d. $600
CORRECT: b. Each year $200 gets removed from the value of computer. After three years the value becomes
$400.
31. You have been asked to make an estimate for a project. The project involves manufacturing 1000 toys. You expect
that as the team manufactures some toys, the time to make them will reduce. Which estimation technique are you
trying to use?
a. Analogous Estimation
b. Regression Analysis
c. Bottom up Estimating
d. Learning Curve
CORRECT: d. Learning curve estimation uses the principal that the cost per unit will decrease as more units of work
are manufactured.
32. John is an excellent engineer. The management assumes that since he is a good technical performer, he will be a
good project manager too. Based upon this, John was promoted to Project Manager. This is an example of
a. Halo Effect
b. Expectancy Theory
c. McGregory Theory of X and Y
d. Herzberg Theory
CORRECT: c. Close Procurements and Close Project or phase are the two closure processes.
CORRECT: d. The Configuration (or Change) Control Board has the authority to approve or deny change requests.
35. You are the Project Manager of the XYZ project. You want to find the planned expenses for next month. Which
document do you need to refer to?
a. Cost Management Plan
b. Cost Baseline
c. Cost Control Plan
d. Cost Variance report
CORRECT: b. Cost baseline includes the project budget for each month.
36. Which of the following is not true about the WBS report?
a. WBS should focus in on the activities that must be performed in the project and should not focus on the
deliverables.
b. The project team must be involved in developing the WBS.
c. As a rule of thumb, each activity of WBS should take less than 80 hours.
d. WBS is usually represented in a hierarchical fashion.
https://www.edwel.com/Free-Resources/PMP-Certification-Practice-Exam.aspx?fbclid=IwAR0rK8MIw5YV1cskTe9AklQokwTwYZMUrVsRDZlLTB… 8/18
09/04/2020 PMP Certification Practice Exam
CORRECT: b. Project Manager is identified as part of the Develop Project Charter process.
39. You are the Project Manager assigned to build a next generation vehicle. You identify a dependency that the wheels
must be designed and developed before the assembly of the vehicle can be performed. This is an example of which
type of dependency?
a. External
b. Discretionary
c. Soft Logic
d. Mandatory
40. You are the Project Manager assigned to build a next generation vehicle. You identify a dependency that before the
vehicle can be sold, it must be approved by the Government regulatory authority. This is an example of which type
of dependency?
a. External
b. Discretionary
c. Soft Logic
d. Mandatory
41. You are required to estimate the time to paint a large wall. You know it takes two hours to paint one square foot of
wall. The wall has an area of 30 square foot. So you estimate that it will take 60 hours to paint the wall. Which
estimation model are you using?
a. Bottom-up
b. Parametric modeling
c. Analogous
d. Expert judgment
CORRECT: a. The order of magnitude is preferred during initiation phase, and it has an accuracy range of -25% to
75%
https://www.edwel.com/Free-Resources/PMP-Certification-Practice-Exam.aspx?fbclid=IwAR0rK8MIw5YV1cskTe9AklQokwTwYZMUrVsRDZlLTB… 9/18
09/04/2020 PMP Certification Practice Exam
43. You are the project manager responsible for building a new web site. The project is running late. To bring the project
on schedule, you decide to add additional resources to the critical path. This is an example of
a. Fast-tracking
b. Resource planning
c. Crashing
d. Schedule Management
CORRECT: c. Crashing involves adding extra resources to reduce the project duration.
44. You are the project manager of ABC project. One of the risks that has been identifies is attrition of team members.
Mid-way through the project you notice that the morale and motivation of the team members is going down. You
think that this is a precursor to people leaving the organization. For this risk, low motivation is an example of
a. work-around
b. trigger
c. risk monitoring
d. risk planning
CORRECT: b. A risk trigger is an indication that the risk is about to occur or has occurred.
45. You are working on the project of painting of your house. You identify a dependency that the painting of roof should
begin only after two days of completion of painting of walls. This is an example of
a. Lag
b. Lead
c. Slack
d. Float
CORRECT: a. This is an example of lag. Lag is the amount of time after the completion of the predecessor activity,
when the successor activity can start.
47. You are the Project Manager for XYZ project. The scope of the project has been completed. You receive a request
for a new module to be developed as part of this project. What should you do next?
a. You should approach the Project sponsor and ask her for a new module to be developed as part of this
project.
b. You should approach the Senior Management and ask them for a new module to be developed as part of this
project.
c. You should send the request to Change Control Board for approval.
https://www.edwel.com/Free-Resources/PMP-Certification-Practice-Exam.aspx?fbclid=IwAR0rK8MIw5YV1cskTe9AklQokwTwYZMUrVsRDZlLT… 10/18
09/04/2020 PMP Certification Practice Exam
d. Since the project scope is completed you should inform the customer that this change cannot be done as
part of the project.
CORRECT: d. As the scope is completed, the project is complete. Additional work should be done as part of a new
project.
49. You are managing the project of planning a party for your company employees. There is a risk that the employees
will not come to the party. You decide to not take any action against this as the likely-hood of this is low. Which risk
response strategy are you following?
a. Acceptance
b. Avoidance
c. Mitigation
d. Transference
51. You are the Project Manager of ABC project. There was a conflict between two key project members. The three of
you meet and decide to use compromise as the conflict resolution technique. Compromise generally leads to
a. Win-win situation
b. Win-Lose situation
c. Lose-Lose situation
d. None of these
52. Bids, tenders and quotes are other names for what?
a. Proposals
b. Make-or-buy decisions
https://www.edwel.com/Free-Resources/PMP-Certification-Practice-Exam.aspx?fbclid=IwAR0rK8MIw5YV1cskTe9AklQokwTwYZMUrVsRDZlLT… 11/18
09/04/2020 PMP Certification Practice Exam
c. Buyer responses
d. Pre-bid conferences
CORRECT: c. Expert judgment is a tool for the Develop Project Charter process.
54. Which of the following best describes the purpose of a war room?
a. A war room is used for meetings between the Project Manager and the customer.
b. A war room is used for important meetings between the Project team and the senior management.
c. A war room is used for collocation
d. Whenever there is a resource conflict between different Project Managers, they meet in a war room.
CORRECT: c. War room is used for collocation to facilitate communication within the team.
55. You are the Project Manager of a project involving building a computer. Your team members follow what you tell
them because you have the authority to provide negative feedback in their performance appraisal. This is an
example of which type of power?
a. Coercive
b. Referent
c. Formal
d. Reward
CORRECT: a. When the team is afraid of the Project Manager, the power yielded is of type Coercive.
CORRECT: b. An S-curve is typically used to represent a cost baseline. The cost is low in the beginning and end,
and high during the middle of the project.
57. You are in the process of Source Selection for a contract for your project. You are planning to use weighing process
for source selection. There are four vendors being considered. There are two deciding factors price (weightage 40),
quality (weightage 60). The scores of four vendors that your team has computed are displayed in the table below.
Which vendor will among these four should be chosen?
a. Vendor 1
https://www.edwel.com/Free-Resources/PMP-Certification-Practice-Exam.aspx?fbclid=IwAR0rK8MIw5YV1cskTe9AklQokwTwYZMUrVsRDZlLT… 12/18
09/04/2020 PMP Certification Practice Exam
b. Vendor 2
c. Vendor 3
d. Vendor 4
Vendor 1Vendor 2Vendor 3Vendor 4
Price 8 10 12 11
Quality 12 10 8 11
INCORRECT: d. We need to compute the following for all the vendors - (0.4*Price + 0.6*Quality). The scores come
out to be vendor 1 - 10.4, vendor 2 - 10, vendor 3 - 9.6, and vendor 4's 11. Since vendor 4 has the highest score, it
should get selected.
58. Which of the following indicate that the project is doing well? Select the best option.
a. A negative Cost Variance
b. An SPI of less than one
c. A negative schedule variance
d. A CPI of greater than one.
CORRECT: d. A CPI of greater than one indicates you are taking less money than planed to do the project.
59. You are performing Earned Value Reporting for your project. The project's CPI is 0.9 and the budget at completion
is One thousand dollars. What is the estimated cost at completion?
a. Nine hundred dollars
b. One thousand one hundred and eleven dollars
c. One thousand dollars
d. One thousand and one hundred dollars
60. You are working on a project to build a bridge. You have reached the planned half way mark. The total planned cost
at this stage is five hundred dollars. The actual physical work that has been completed at this stage is worth $400.
You have already spent one thousand dollars on the project. What is the CPI?
a. 0.8
b. 1.2
c. 0.5
d. 0.4
61. You are working on a project to build a bridge. You have reached the planned half way mark. The total planned cost
at this stage is five hundred dollars. The actual physical work that has been completed at this stage is worth $400.
You have already spent one thousand dollars on the project. What is the Schedule Variance?
a. -100
b. 100
c. -600
d. 600
https://www.edwel.com/Free-Resources/PMP-Certification-Practice-Exam.aspx?fbclid=IwAR0rK8MIw5YV1cskTe9AklQokwTwYZMUrVsRDZlLT… 13/18
09/04/2020 PMP Certification Practice Exam
62. John needs to visit many countries as part of his job. He has learned that he needs to avoid being ethno-centric.
What does ethnocentrism mean?
a. Not being friendly to strangers
b. Unable to get adjusted to the food of a new place
c. Belief that ones culture is superior to others.
d. Initial shock of landing in a new country.
CORRECT: c. Ethnocentrism refers to belief that ones culture is superior to other cultures.
63. You are planning to use screening system for source selection process to select a vendor for supplying food for your
company? Which of these is a good example of screening system?
a. You interview all the vendors and decide based upon the interviews.
b. You negotiate with all the vendors and select the one that provides the best price.
c. You only consider those vendors who have revenue of ten million dollars in the last financial year.
d. You select the vendor who responds first to your advertisement.
CORRECT: c. Screening system are predefined criteria that are used to short-list vendors for source selection
64. Which of the following is not an input to the Conduct Procurements process?
a. Source selection criteria
b. Make-or-buy decisions
c. Organizational process assets
d. WBS
65. You are using control charts to perform quality control. Which of these situations does not indicate that the process
is out of control and an assignable cause needs to be assigned. Assume that the control limits have been set to
three sigma.
a. One of the point is more than the mean + (3*sigma)
b. Two points together are more than mean +(2*sigma), but less than mean + (3*sigma)
c. Seven points together are on one side of the mean.
d. Three points are on one side of the mean
CORRECT: b. The other two are conditions that indicate the process is out of control.
66. You are the Project Manager of a car manufacturing company. As part of Quality Control you decide to check only
5% of the cars generated for environmental check. Which technique are you using?
a. Pareto Diagram
b. Control Charts
c. Statistical Sampling
https://www.edwel.com/Free-Resources/PMP-Certification-Practice-Exam.aspx?fbclid=IwAR0rK8MIw5YV1cskTe9AklQokwTwYZMUrVsRDZlLT… 14/18
09/04/2020 PMP Certification Practice Exam
d. Sample Selection
CORRECT: c. Statistical Sampling is the standard technique that is used to test only a small sample of products
instead of all the products manufactured.
68. Which of the following is not true about the Close Project or Phase process?
a. Contract closeout must be performed after the Administrative Closeout.
b. The risk is the lowest at this stage of the project.
c. The probability of completion is the highest at this stage of the project.
d. Stakeholders have least amount of influence at this stage.
CORRECT: c. Risk Register is the only output of the Risk identification process.
70. In which process of Project Risk Management knowledge area are numeric values assigned to probabilities and
impact of risks
a. Perform Qualitative Risk Analysis
b. Perform Quantitative Risk Analysis
c. Perform Numeric Risk Analysis
d. Plan Risk Response
CORRECT: b. A numeric value is assigned to risks impact and probability during the Quantitative Risk Analysis
process.
71. Your project is well underway, and the project management plan as well as subsidiary plans have been baselined
and work is proceeding apace. A key project stakeholder has just approached you with a problem: a requirement
was missed by the business in the requirements gathering process and they want it inserted into the project plan
without having to go through the formal change request process. They would consider it a huge favor if you did so
and would be willing to reciprocate at some later date. What should you do next?
https://www.edwel.com/Free-Resources/PMP-Certification-Practice-Exam.aspx?fbclid=IwAR0rK8MIw5YV1cskTe9AklQokwTwYZMUrVsRDZlLT… 15/18
09/04/2020 PMP Certification Practice Exam
a. Talk to the stakeholder's manager about the stakeholder's request for a breach in the formal corporate
change management process
b. Since the stakeholder has key resources on the project, it may pay off in the long run to agree to the
stakeholder's request
c. Perform an impact assessment on the requested change and submit to the CCB for approval
d. Agree to the request only if the stakeholder is willing to remove a less important feature of equal effort so as
not to impact the costs or the timeline on the project
CORRECT: C - This is an ethics question dressed up as a stakeholder management question. What happens next
is an impact assessment. Under the mandatory Responsibility section: "We inform ourselves and uphold the
policies, rules, regulations and laws that gover
CORRECT: d. Cleaning the building is a repetitive task that is done everyday. Hence it is not an example of a
project.
74. Describing stakeholders based on their power (ability to impose will), urgency (need for immediate attention), and
legitimacy (their involvement), describes what type of grid or model?
a. Power/Influence grid
b. Salience Model
c. Influence/Impact grid
d. Power model
75. Which of the following best describes Plan Stakeholder Management process?
a. Creation and maintenance of relationships between the project team and stakeholders
b. Preventing negative stakeholders from derailing theproject
c. Striking a balance between stakeholder needs and project needs
d. Focuses on from the creation of the stakeholder management strategy
CORRECT: A - stakeholder management is about the creation and maintenance of relationships between the
project team and stakeholders. Under specific circumstances, answers B and C may be partially or. Answer D is
https://www.edwel.com/Free-Resources/PMP-Certification-Practice-Exam.aspx?fbclid=IwAR0rK8MIw5YV1cskTe9AklQokwTwYZMUrVsRDZlLT… 16/18
09/04/2020 PMP Certification Practice Exam
About
About Us (/About-Us.aspx)
Instructors (/Edwel-Instructors.aspx)
Guarantee Terms (/Guarantee-Terms.aspx)
Contact us (mailto:info@edwel.com)
PMI, PMBOK, PMP®, the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.
Courses
PMP Certification (/PMP-Certification.aspx)
Agile Exam (/Agile-Certification.aspx)
Six Sigma (/Six-Sigma-Training.aspx)
Live PMP Online (/Online/PMP-Boot-Camp-Live-Online.aspx)
Learn More (/Learn-More-Edwel.aspx)
Cities
Atlanta (/Atlanta/PMP-Certification.aspx)
Austin (/Austin/PMP-Certification.aspx)
Baltimore (/Baltimore/PMP-Certification.aspx)
Boston (/Boston/PMP-Certification.aspx)
Chicago (/Chicago/PMP-Certification.aspx)
Dallas (/Dallas/PMP-Certification.aspx)
Denver (/Denver/PMP-Certification.aspx)
Detroit (/Detroit/PMP-Certification.aspx)
Houston (/Houston/PMP-Certification.aspx)
https://www.edwel.com/Free-Resources/PMP-Certification-Practice-Exam.aspx?fbclid=IwAR0rK8MIw5YV1cskTe9AklQokwTwYZMUrVsRDZlLT… 17/18
09/04/2020 PMP Certification Practice Exam
Contact us
EdWel Programs
1115 North Broadway, Suite 105
Denver, CO 80203
USA
1.800.544.1995
info@edwel.com (mailto:info@edwel.com)
https://www.edwel.com/Free-Resources/PMP-Certification-Practice-Exam.aspx?fbclid=IwAR0rK8MIw5YV1cskTe9AklQokwTwYZMUrVsRDZlLT… 18/18