Steel Structure Fabrication Report: Page 1/1

This 3 page steel structure fabrication report provides details of a project for PTT Polyethylene Company. It includes inspection details for steel pieces produced by Pilin-Project Co for Toyo Thai Corporation's PTTPE LLDPF project. The report documents fitting, welding, bolt holes, gusset plates and other details for pieces marked with precedence numbers. Representatives from the subcontractor and client signed off on the completed work.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1K views8 pages

Steel Structure Fabrication Report: Page 1/1

This 3 page steel structure fabrication report provides details of a project for PTT Polyethylene Company. It includes inspection details for steel pieces produced by Pilin-Project Co for Toyo Thai Corporation's PTTPE LLDPF project. The report documents fitting, welding, bolt holes, gusset plates and other details for pieces marked with precedence numbers. Representatives from the subcontractor and client signed off on the completed work.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 8

Steel Structure Fabrication Report

Page 1/1

Consultant : PTT POLYETHYLENE COMPANY CTD. Job No. : PL-5104

Client : TOYO THAI CORPORATION LTD. Report No. : FIR-001

Project Name : PTTPE LLDPF PROJECT (D- 138) Date :

INSPECTOR NAME : Mr. SURAT MUNKONG

Prece Mark No. QTY SIZE LENGTH FIT-Up WELDING BOLT HOLE GUSSET PL. STRAIGHTEN BASE. Pt DATE NDE. WPS NO. WELDER.

COMPLETED BY Sub Contractor TTCL Client Reprsentative


COMPANY Pilin-Project Co.,LTD.
SIGNATURE
NAME Mr. RAMIN YODSIRI Mr. SURAT MUNKONG
DATE
85
Steel Structure Fabrication Report
Page 2/3

Consultant : PTT POLYETHYLENE COMPANY CTD. Job No. : PL-5104

Client : TOYO THAI CORPORATION LTD. Report No. : FIR-001

Project Name : PTTPE LLDPF PROJECT (D- 138) Date : 7/1/2008

INSPECTOR NAME : Mr. SURAT MUNKONG

Prece Mark No. QTY SIZE LENGTH FIT-Up WELDING BOLT HOLE GUSSET PL. STRAIGHTEN BASE. Pt DATE NDE. WPS NO.

COMPLETED BY Sub Contractor TTCL Client Reprsentative


COMPANY Pilin-Project Co.,LTD.
SIGNATURE
NAME Mr. RAMIN CHAROENPOL Mr. SURAT MUNKONG
DATE
Page 2/3

WELDER.

ative
Steel Structure Fabrication Report
Page 3/3

Consultant : PTT POLYETHYLENE COMPANY CTD. Job No. : PL-5104

Client : TOYO THAI CORPORATION LTD. Report No. : FIR-001

Project Name : PTTPE LLDPF PROJECT (D- 138) Date : 6/30/2008

INSPECTOR NAME : Mr. SURAT MUNKONG

BOLT GUSSET STRAIGHT


Prece Mark No. QTY SIZE LENGTH FIT-Up WELDING BASE. Pt DATE NDE. WPS NO. WELDER.
HOLE PL. EN

COMPLETED BY Sub Contractor TTCL Client Reprsentative


COMPANY Pilin-Project Co.,LTD.
SIGNATURE
NAME Mr. RAMIN CHAROENPOL Mr. SURAT MUNKONG
DATE