Pkg -1 (Rishikesh to Kodiyala) NH 58 Km 235 to 268
Name of Project: Widening to two lane with paved shoulders
configuration from km 235.00 to 268.00 of NH-58 including 560.00 m
Marine Drive viaduct portion near Byasi(Length: 30.59 km) (Pkg-1)
• Sanctioned cost with Date : 248.22 Cr. and 21.09.2016
• Implementing Agency : PWD
• Mode of executions : EPC
• Awarded cost, : Rs. 157.54 Cr,
• C.B. No. with Date. : 10/CE-NH&B/2017, Dt. 10-07-2017
• appointed date : Dt. 30.12.2017
• Authority Engineer : M/s Ayoleeza Consultant Pvt. Ltd.
• Contractor : M/S Raj Shyama Construction Pvt. Ltd.
• Scheduled date of completion as per : 29.12.2019
contract
• Status of milestones:
M.S. As per C.B As per EOT Status of M.S. EOT Status
1st 27.06.2018 27.06.2018 Achieved Contractor Applied
2nd 29.12.2018 01.03.2019 Achieved Up to Dec 2020
3rd 02.07.2019 28.09.2019 Achieved Under process
4th 29.12.2019 26.03.2020 Not Achieved
• Tentative date of completion : 30.12.2020
• Financial progress (Rs Cr & in %) Rs. 123.40 Cr. (78.33%)
• Physical progress (in %) : 84.03%
• Status of COS:
Sl. Detail of COS Cost of Status
No COS
1 Bridge at Byasi due to Realignment-RVNL(Deposit) 24.57 Cr. Approved
2 Protective Works at Dumping Zones 4.30 Cr. Recommended to Ministry for
Approval
3 Construction of 17 Additional Culverts 1.69 Cr. Recommended to Ministry for
Approval
4 Construction of 6m Span Culvert at 235.564 0.87 Cr. Recommended to Ministry for
Approval
5 Slope Protection at Km 246+020 to Km 246+190 9.05 Cr. Under Review at PWD.
6 Slope Protection at Km252+823 to 253+170 13.73 Cr. Under Review at PWD
Progress Report
Total Quantity To be Quantity
Sl. No. Type of Work Unit Execute as per Executed at site Balance Qty
Agreement as on 13.06.2020
a. Widening and strengthening of existing road
1 Hill cutting Rmt 26186 25960 226
2 Sub Grade Rmt 26186 25960 226
3 GSB Rmt 26186 26100 86
4 WMM Rmt 26186 26070 116
5 Bituminous Work (DBM) Rmt 26626 26030 596
6 Bituminous Work (BC) Rmt 26626 26020 606
b. New 2 lane realignment/Bypass
1 Hill cutting Rmt 1.208 1.208 0
2 Sub Grade Rmt 1.208 1.208 0
3 GSB Rmt 1.208 1.208 0
4 WMM Rmt 1.208 1.208 0
5 Bituminous Work (DBM) Rmt 3968 1300 2668
6 Bituminous Work (BC) Rmt 3968 700 3268
7 Widening & Repair of Culverts Nos 3 3 0
8 New Culverts & Reconstruction Nos 146 142 4
9 Minor Bridges Nos 1 1.00 0
10 Major Bridges( 82.10+560 ) Mtr Foundation LWW 16 nos 16 nos 0
Major Bridges( 82.10+560 ) Mtr Sub-
11 LWW 16 nos 16 nos 0
structure
Major Bridges( 82.10+560 ) Mtr Super-
12 LWW 642.1 LWW 35 LWW 607.1 LWW
structure
c. Other Works
1 Road Side Drain Rmt 42665 30850 11815
Road Signs, Markings, KM Stones, Safety
2 Rmt 30594 9870 20724
Devices
3 Rest Area & view Point Nos 2 0 2
4 Street Light Rmt 13840 0 13840
5 Utility Duct Rmt 37514 34000.00 3514
6 Repair to Bridge/Structure Nos 9 0 9
7 Thrie Beam Crash Barrier Rmt 15860 9980.00 5880
8 Retaining Wall Rmt 6320 6320.00 0
9 Breast Wall Rmt 2420 2420.00 0
10 Junctions(Major & Minor) Nos 3 1 2
11 Safety & Traffic Management LS LS 0 0
12 Avenue Tree Plantation Nos 4774 0 4774
Pkg -2 (Kodiyala to Devprayag) NH 58 Km 268 to 300
Name of Project: Reconstruction with geometric improvement to 2
lane with paved shoulder from km. 268.00 to 300.00 of NH-
58.(Length: 29.915 km) (Pkg-1)
• Sanctioned cost with Date : 200.34 Cr. and 16.09.2016
• Implementing Agency : PWD
• Mode of executions : EPC
• Awarded cost, : Rs. 147.47 Cr,
• C.B. No. with Date. : 07/CE-NH&B/2017, Dt. 26-04-2017
• appointed date : Dt. 30.12.2017
• Authority Engineer : M/s Ayoleeza Consultant Pvt. Ltd.
• Contractor : M/s Centrodorstory (India) Pvt. Ltd
• Scheduled date of completion as : 29.12.2019
per contract
• Status of milestones:
M.S. As per C.B As per EOT Status EOT Status
st
1 27.06.2018 27.06.2018 Achieved Contractor Applied Up to
nd 15 Sep 2020 Under
2 29.12.2018 09.03.2019 Achieved
rd process
3 02.07.2019 11.09.2019 Achieved
4th 29.12.2019 16-06-2020 Not Achieved
• Tentative date of completion : 30.12.2020
• Financial progress (iRs Cr & in %) Rs. 88.52/96.07 Cr. ( 60.02 %)
• Physical progress (in %) : 69.21 %
• Status
o of COS:
Sl. Detail of COS Cost of Status
No COS
1 Protective Works at Dumping Zones 8.10 Recommended to Ministry for
Cr. Approval
2 Minor Bridge at Devprayag 1.87 Under Review at Authority Engineer
Cr.
3 Slope Protection To be submitted by contractor
Progress Report
Total Quantity
Quantity to Executed at
Sl. No. Type Of Work Unit Balance
be execute site as on
as per C.A 14.06.2020
A Widening of Existing 2 Lane Alignment
1 Hill Cutting Km 27.345 25.14 2.21
2 Subgrade Km 27.345 25.070 2.28
3 GSB Km 27.345 21.80 5.55
4 CTB Km 27.345 21.30 6.05
5 SAMI Km 27.345 19.01 8.34
6 BC Km 27.345 6.80 20.55
7 Widening & Repair of Culverts No. 3 0.00 3.00
B New 2 Lane Realignment/Bypass 0.00
1 Hill Cutting Km 2.655 2.655 0.00
2 Subgrade Km 2.655 2.655 0.00
3 GSB Km 2.655 2.655 0.00
4 CTB Km 2.655 2.655 0.00
5 SAMI Km 2.655 1.800 0.86
6 BC Km 2.655 0.575 2.08
New Culverts, Minor Bridge, Underpass,
C
Overpass etc. 0.00
1 New Culvert No. 122 96.00 26.00
2 Minor Bridge No. 1 0.00 1.00
D Other Works 0.00
1 Road side Drain Work Km 31.685 10.10 21.59
Road Signs, Markings,KM Stones, Safety
2 Km 0.00
Devices 29.915 29.92
3 Street Light km 29.915 0.00 29.92
4 Utility Duct Km 31.24 25.70 5.54
5 Repair to Bridge/Structure nos 2 0.00 2.00
6 Thrie Beam Crash Barrier Rmt. 18220 5900.00 12320.00
7 Retaining Wall Rmt. 12000 7785.00 4215.00
8 Breast Wall Rmt. 4030 3795.00 235.00
Half
9 Safety & Traffic Management 3.00
Yearly 4 1.00
10 Junctions(Major & Minor) nos 8 0.00 8.00
11 Avenue Tree Plantation nos 5752 0.00 5752.00
Pkg -3 (Devprayag to Srinagar) NH 58 Km 300 to 338
Name of Project: Reconstruction with geometric improvement of
existing 2 lane/intermediate lane to 2 lane with paved shoulder
configuration from km. 300.00 to 338.00 of NH-58 (Length: 36.90
km) (Pkg-1)
• Sanctioned cost with Date : 257.4 Cr. and 29.08.2016
• Implementing Agency : PWD
• Mode of executions : EPC
• Awarded cost, : Rs. 166.52 Cr,
• C.B. No. with Date. : 09/CE-NH&B/2017, Dt. 27-05-2017
• appointed date : Dt. 30.12.2017
• Authority Engineer : M/s Ayoleeza Consultant Pvt. Ltd.
• Contractor : M/S Raj Shyama Construction Pvt. Ltd.
• Scheduled date of completion as : 29.12.2019
per contract
• Status of milestones:
M.S. As per C.B As per EOT Status EOT Status
1st 29.06.2018 27.06.2018 Achieved Contractor Applied
2nd 29.12.2018 24.02.2019 Achieved Up to 19 July 2020
3rd 02.07.2019 29.09.2019 Achieved Under process
4th 29.12.2019 27.03.2020 Not Achieved
• Tentative date of completion : 30.12.2020
• Financial progress (in Rs Cr & in %) Rs. 129.54 (77.80 %)
• Physical progress (in %) : 86.57 %
• o of COS:
Status
Sl. Detail of COS Cost of Status
No COS
1 Protective Works at Dumping Zones 15.31 Cr. Recommended to Ministry for Approval
2 Extra Widening of Road at Srinagar 3.74 Cr. Under Review at PWD
3 Slope Protection at Km 298+360 to 298+750 and 27.06 Cr. Under Review at Authority Engineer
Km 304+100 to Km 304+370
Progress
Quantity
Total Quantity to
Executed at
Sl. No. Type Of Work Unit be execute as Balance
site as on
per C.A
14.06.2020
A Widening of Existing 2 Lane Alignment
1 Hill cutting km 35.45 34.50 0.95
2 Subgrade Km 35.45 34.48 0.97
3 Cementitious GSB Km 35.45 34.40 1.05
4 WMM Km 35.45 34.20 1.25
5 DBM Km 35.45 34.05 1.40
6 BC Km 35.45 33.50 1.95
Widening & Repair of Culverts No. 22 22.00 0.00
B New 2 Lane Realignment/Bypass
1 Hill cutting km 1.45 1.20 0.25
2 Subgrade Km 1.45 1.20 0.25
3 Cementitious GSB Km 1.45 1.20 0.25
4 WMM Km 1.45 1.20 0.25
5 DBM Km 1.45 1.20 0.25
6 BC Km 1.45 1.20 0.25
New Culverts, Minor Bridge, Underpass,
C
Overpass etc.
1 New Culvert No. 108.00 108.00 0.00
2 Minor Bridge Rmt. 2.00 2.00 0.00
D Major Bridge Rmt. 72.00 50.39 21.61
E Other Works 0.00
1 Road side Drain Work Km 58.58 35.20 23.38
Road Signs, Markings,KM Stones, Safety
2 Km 2.50 34.40
Devices 36.90
3 Rest Area No 1.00 0.00 1.00
4 Street Light km 12.39 3.00 9.39
5 Utility Duct Km 49.29 36.70 12.59
6 Repair to Bridge/Structure nos 8.00 0.00 8.00
7 Thrie Beam Crash Barrier Rmt. 11510.00 7900.00 3610.00
8 Retaining Wall Rmt. 10500.00 10500.00 0.00
9 Breast Wall Rmt. 810.00 680.00 130.00
Half
10 Safety & Traffic Management 4.00 0.00
Yearly 4.00
11 Junctions(Major & Minor) nos 10.00 4.00 6.00
12 Avenue Tree Plantation nos 1342.00 0.00 1342.00
Pkg -4 (Srinagar to Rudrprayag) NH 58 Km 338 to 368
Widening and strengthening/Reconstruction of Existing 2-Lane to 2 Lane
with Paved Shoulder Configuration from existing km. 338+100 (Design km.
333.400) to km. 368+000 (Design km. 360.579) excluding existing km.
349+800 to km. 355+495 (Kaliyasaur Bypass) of NH-58 (2L. Chardham
22.70 km, NH-07, EPC, TPC-136 Cr. date of sanction 03.10.2017). (Total
Length 22.479 Km.) Road length in RudaraprayagDistt. 12.159 Km. (Pkg-
1)
• Sanctioned cost with Date : 136.43&03.10.2017
• Implementing Agency : PWD
• Mode of executions : EPC
• Awarded cost, : Rs 84.00 Cr.
• C.B. No. with Date. : 13/CB-NH&B/2018, Dt. 27.01.2018
• appointed date : 21.08.2018
• Authority Engineer : M/S L- Telford consulting Engineers Pvt Ltd
• Contractor : M/S RCC developers
• Scheduled date of completion as : 20.08.2020
per contract
• Status of milestones:
M.S. As per C.B As per EOT Status EOT Status
1st 16.02.2019 16.02.2019 Achieved NA
2nd 20.08.2019 20.08.2019 Achieved
3rd 21.02.2020 21-02-2020 Achieved
4th 20.08.2020 -
• Tentative date of completion : 20.08.2020
• Financial progress (in Rs Cr & in %) : Rs. 54.13/84s Cr., (64.44%)
• Physical progress (in %) : 66.82%
• o of COS:
Status
Sl. Detail of COS Cost of Status
No COS
1 Dumping Zone 7.79 Cr. Under Review at Authority Engineer
2 Slope Protection at Farashu 15.50 Cr Under Review at Authority Engineer
3 Bridge at Narkota due to Realignment-RVNL 82.00 Cr. Under Review at Authority Engineer
(Deposit )
Progress Report
Scope of
Progress up Balance
Item Description Work as per Unit
to Date work
Sch.-B
A. Widening of Existing 2 Lane Alignment
Hill cutting 22.379 Km 21.189 1.19
(1) Earthwork up to Subgrade
Subgrade 22.379 Km 19.620 2.759
(2) Sub-base Course (GSB) 22.379 Km 18.670 3.709
(3) Non - Bituminous (WMM) 22.379 Km 18.450 3.929
(4) Bituminous Base Course 22.379 Km 11.500 10.879
(5) Wearing Coat 22.379 Km 10.770 11.609
(6) Widening & repair of Culvert 8 Nos 0.000 8
B. Reconstruction / New 2- Lane realignment/ bypass
0.000 0
(Flexible Pavement)
(1) Earthwork up to Subgrade 0.1 Km 0.100 0
(2) Sub-base Course 0.1 Km 0.100 0
(3) Non - Bituminous 0.1 Km 0.100 0
(4) Bituminous Base Course 0.1 Km 0.100 0
(5) Wearing Coat 0.1 Km 0.100 0
C. Re- Construction & New Culverts on existing road,
0.000 0
realignments, Bypasses.
(1)Culverts (Length < 6m) 79 Nos 61.000 18
A. 1 - Widening & repair of Minor Bridges (Length > 6m and
0.000 0
< 60m)
Minor Bridge 2 Nos 0.000 2
A. 2 - New Minor Bridges (Length > 6m and < 60m) 0.000 0
(1) Foundation + Sub- Structure 6 Nos 4.000 2
(2) Super Structure 2 Nos 0.000 2
(i). Road Side Drain KC drain 18.340 11.910 6.43
Km
Covered drain 10.300 2.780 7.52
(ii). Road sign, markings, km stones, Boundary stones, safety
22.479 Km 0.000 22.479
devices, etc.
(iii). Project Facilities 0.000 0
(a). Street Lighting 6.9 Km 0.000 6.9
(b). Utility Duct 27.629 Km 19.850 7.779
(iv). Thrie Beam Crash Barrier 4.536 Km 0.000 4.536
(v). Protection work 0.000 0
(a). Retaining Wall 7900 Rmt 5971.400 1928.6
(b). Breast Wall 780 Rmt 812.000 0
Half
(vi). Safety & Traffic management during construction 4 2.000 2
yearly
(vii). Junction 7 Nos 0.000 7
(viii) Tree Plantation 4100 Rmt 1000.000 3100