Project Certificate No.: 1 Sheet 1 of 2
Project Certificate No.: 1 Sheet 1 of 2
101(3a) Removal of Existing Concrete Pavement sq.m. 3,305.50 201.34 665,529.37 0.73% 145.15 204.85 350.00 0.03% 0.05% 0.08% 29,224.50
101(3b) Removal of Existing Asphalt Pavement sq.m. 360.00 104.95 37,782.00 0.04% 73.04 - 73.04 0.01% 0.00% 0.01% 7,665.55
102(2) Surplus Common Excavation cu.m 2,605.34 196.77 512,652.75 0.57% - 0.00% 0.00% 0.00% -
103 Structure Excavation cu.m 7,991.62 286.30 2,288,000.80 2.52% 2851.73 - 2,851.73 0.90% 0.00% 0.90% 816,450.30
104(1) Embankment cu.m 14,731.54 605.71 8,923,041.09 9.84% 10525.17 678.57 11,203.74 7.03% 0.45% 7.48% 6,375,200.72
105(1) Subgrade Preparation (common material) sq.m. 13,061.45 19.94 260,445.31 0.29% 2339.48 - 2,339.48 0.05% 0.00% 0.05% 46,649.23
200 Aggregate Sub-base Coarse cu.m 2,741.59 668.38 1,832,423.92 2.02% 1,624.75 192.37 1,817.12 1.20% 0.14% 1.34% 1,085,950.40
311(1a) PCC Pavement (0.30m thk) sq.m. 4,483.36 1,584.07 7,101,956.07 7.83% 2,161.22 - 2,161.22 3.77% 0.00% 3.77% 3,423,523.76
311(1b) PCC Pavement (0.23m thk) sq.m. 3,564.40 1,194.04 4,256,036.17 4.69% 240.80 276.18 516.98 0.32% 0.36% 0.68% 287,524.83
311(1c) PCC Pavement (0.15m thk) sq.m. 3,858.57 818.71 3,159,049.84 3.48% 455.74 900.26 1,356.00 0.41% 0.81% 1.22% 373,118.89
404 Reinforcing Steel (grade 40) kgs 275,683.65 70.17 19,344,721.72 21.33% 46,851.41 11,013.66 57,865.07 3.62% 0.85% 4.48% 3,287,563.44
405(a) Structural Concrete, Class "A" cu.m 1,986.78 5,569.86 11,066,086.45 12.20% 506.35 377.51 883.86 3.11% 2.32% 5.43% 2,820,298.61
Reinforced Concrete Pipe Culvert (1.22mØ,
500 (1)a RCPC) l.m 100.00 6,826.51 682,651.00 0.75% 10.00 10.00 0.00% 0.08% 0.08% -
600(2)a Mountable Concrete Gutter l.m 1,843.75 639.72 1,179,483.75 1.30% 553.13 553.13 0.00% 0.39% 0.39% -
600(3) Concrete Curb and Gutter, Type A l.m 2,116.07 866.17 1,832,876.35 2.02% 634.82 634.82 0.00% 0.61% 0.61% -
601 Sidewalk (150mm thk) sq.m. 2,320.80 800.65 1,858,148.52 2.05% 696.24 696.24 0.00% 0.61% 0.61% -
605(2b) Regulatory Signs (450x750) each 2.00 12,778.44 25,556.88 0.03% - 0.00% 0.00% 0.00% -
605(2c) Regulatory Signs (600x650) each 7.00 12,159.36 85,115.52 0.09% - 0.00% 0.00% 0.00%
605(2)d Regulatory Signs (600x900) each 1.00 12,595.78 12,595.78 0.01% - 0.00% 0.00% 0.00% -
605(3a) Informatory Signs (400x600) each 1.00 12,595.78 12,595.78 0.01% - 0.00% 0.00% 0.00% -
606(2) Pavement Markings sq.m. 151.44 650.33 98,485.97 0.11% - 0.00% 0.00% 0.00%
609 Sprigging sq.m. 3,179.84 957.30 3,044,060.83 3.36% 10.00 20.00 30.00 0.00% 0.02% 0.02%
611 Trees (Furnishing & Transplanting) each 229.00 10,392.60 2,379,905.40 2.62% 4.00 4.00 8.00 0.00% 0.05% 0.05%
612(1) Reflectorized Thermoplastic Pavement sq.m. 499.06 1,727.44 862,096.20 0.95% - 0.00% 0.00% 0.00%
Markings (White)
Reflectorized Thermoplastic Pavement
612(2) Markings (Yellow) sq.m. 24.84 1,766.30 43,874.89 0.05% - 0.00% 0.00% 0.00%
SPL-1 Unit Pavers sq.m. 7,638.76 1,890.37 14,440,082.74 15.92% 274.65 77.90 352.55 0.00% 0.16% 0.16%
SPL-2 Unit Pavers (Lining) sq.m. 2,040.28 1,890.37 3,856,884.10 4.25% 89.30 - 89.30 0.00% 0.00% 0.00%
SPL-3 Mobilization/Demobilization l.s. 1.00 666,886.90 666,886.90 0.74% 0.50 - 0.50 0.00% 0.00% 0.00%
SPL-4 Provide and Maintain Traffic Control l.s. 1.00 112,740.75 112,740.75 0.12% 0.50 - 0.50 0.00% 0.00% 0.00%
SPL-5 Project Billboard each 2.00 3,098.87 6,197.74 0.01% 2.00 2.00 0.00% 0.01% 0.01%
SPL-6 Construction Safety and Health l.s. 1.00 48,193.50 48,193.50 0.05% 0.50 - 0.50 0.00% 0.00% 0.00%
F. GURREA CONSTRUCTION, INC. LEO P. BIONAT JOSE AL V. FRUTO LEA N. DELFINADO, CES E
Contractor Project Engineer Chief, Planning & Design Division Asst. Regional Director
T OF WORK ACCOMPLISHED
As of March 25, 2014
18,553,170.24
41,244.50 70,469.00
- 7,665.55
- -
- 816,450.30
411,016.63 6,786,217.35
- 46,649.23
128,576.26 1,214,526.66
- 3,423,523.76
329,769.97 617,294.80
737,051.86 1,110,170.76
772,828.52 4,060,391.96
2,102,677.85 4,922,976.46
68,265.10 68,265.10
353,845.13 353,845.13
549,862.91 549,862.91
557,444.56 557,444.56
- -
- -
- -
- -
- -
19,146.00 19,146.00
41,570.40 41,570.40
- -
- -
147,259.82 147,259.82
- -
- -
- -
6,197.74 6,197.74
- -
6,266,757.24 24,819,927.48
Approved by:
EDILBERTO D. TAYAO
Regional Director
STATEMENT OF WORK ACCOMPLISHED
For the Period:
101(3a) Removal of Existing Concrete Pavement sq.m. 3,305.50 201.34 665,529.37 0.73% 1,767.31 1,767.31 0.00% 0.39% 0.39% -
101(3b) Removal of Existing Asphalt Pavement sq.m. 360.00 104.95 37,782.00 0.04% 21.40 21.40 0.00% 0.00% 0.00% -
102(2) Surplus Common Excavation cu.m 2,605.34 196.77 512,652.75 0.57% - 0.00% 0.00% 0.00% -
103 Structure Excavation cu.m 7,991.62 286.30 2,288,000.80 2.52% 1009.49 4,852.31 5,861.80 0.32% 1.53% 1.85% 289,016.99
104(1) Embankment cu.m 14,731.54 605.71 8,923,041.09 9.84% 10403.09 400.65 10,803.74 6.95% 0.27% 7.22% 6,301,255.64
105(1) Subgrade Preparation (common material) sq.m. 13,061.45 19.94 260,445.31 0.29% 178.26 6,873.21 7,051.47 0.00% 0.15% 0.16% 3,554.50
200 Aggregate Sub-base Coarse cu.m 2,741.59 668.38 1,832,423.92 2.02% 1,127.57 1,064.07 2,191.64 0.83% 0.78% 1.62% 753,645.23
311(1a) PCC Pavement (0.30m thk) sq.m. 4,483.36 1,584.07 7,101,956.07 7.83% 849.22 849.22 0.00% 1.48% 1.48% -
311(1b) PCC Pavement (0.23m thk) sq.m. 3,564.40 1,194.04 4,256,036.17 4.69% 792.39 792.39 0.00% 1.04% 1.04% -
311(1c) PCC Pavement (0.15m thk) sq.m. 3,858.57 818.71 3,159,049.84 3.48% 207.60 1,619.10 1,826.70 0.19% 1.46% 1.65% 169,964.20
404 Reinforcing Steel (grade 40) kgs 275,683.65 70.17 19,344,721.72 21.33% 30,228.74 142,662.57 172,891.31 2.34% 11.04% 13.38% 2,121,150.69
405(a) Structural Concrete, Class "A" cu.m 1,986.78 5,569.86 11,066,086.45 12.20% 161.15 701.19 862.34 0.99% 4.31% 5.30% 897,582.94
Reinforced Concrete Pipe Culvert (1.22mØ,
500 (1)a RCPC) l.m 100.00 6,826.51 682,651.00 0.75% - 0.00% 0.00% 0.00% -
600(2)a Mountable Concrete Gutter l.m 1,843.75 639.72 1,179,483.75 1.30% - 0.00% 0.00% 0.00% -
600(3) Concrete Curb and Gutter, Type A l.m 2,116.07 866.17 1,832,876.35 2.02% 1,526.88 1,526.88 0.00% 1.46% 1.46% -
601 Sidewalk (150mm thk) sq.m. 2,320.80 800.65 1,858,148.52 2.05% 1,536.73 1,536.73 0.00% 1.36% 1.36% -
605(2b) Regulatory Signs (450x750) each 2.00 12,778.44 25,556.88 0.03% - 0.00% 0.00% 0.00% -
605(2c) Regulatory Signs (600x650) each 7.00 12,159.36 85,115.52 0.09% - 0.00% 0.00% 0.00% -
605(2)d Regulatory Signs (600x900) each 1.00 12,595.78 12,595.78 0.01% - 0.00% 0.00% 0.00% -
605(3a) Informatory Signs (400x600) each 1.00 12,595.78 12,595.78 0.01% - 0.00% 0.00% 0.00% -
606(2) Pavement Markings sq.m. 151.44 650.33 98,485.97 0.11% - 0.00% 0.00% 0.00% -
609 Sprigging sq.m. 3,179.84 957.30 3,044,060.83 3.36% - 0.00% 0.00% 0.00% -
611 Trees (Furnishing & Transplanting) each 229.00 10,392.60 2,379,905.40 2.62% - 0.00% 0.00% 0.00% -
Reflectorized Thermoplastic Pavement
612(1) Markings (White) sq.m. 499.06 1,727.44 862,096.20 0.95% - 0.00% 0.00% 0.00% -
F. GURREA CONSTRUCTION, INC. LEO P. BIONAT JOSE AL V. FRUTO LEA N. DELFINADO, CES E
Contractor Project Engineer Chief, Planning & Design Division Asst. Regional Director
T OF WORK ACCOMPLISHED
For the Period:
10,925,984.01
355,830.20 355,830.20
2,245.93 2,245.93
- -
1,389,216.35 1,678,233.34
242,677.71 6,543,933.35
137,051.81 140,606.31
711,203.10 1,464,848.34
1,345,223.92 1,345,223.92
946,145.35 946,145.35
1,325,573.36 1,495,537.55
10,010,632.54 12,131,783.22
3,905,530.13 4,803,113.07
- -
- -
1,322,537.65 1,322,537.65
1,230,382.87 1,230,382.87
- -
- -
- -
- -
- -
- -
- -
- -
- -
10,193,895.84 10,193,895.84
1,798,044.33 1,798,044.33
- 333,443.45
- 56,370.38
- -
- -
34,916,191.09 45,842,175.11
Approved by:
EDILBERTO D. TAYAO
Regional Director
STATEMENT OF WORK ACCOMPLISHED
For the Period:
101(3a) Removal of Existing Concrete Pavement sq.m. 3,305.50 201.34 665,529.37 0.73% 145.15 75.00 220.15 0.03% 0.02% 0.05% 29,224.50 15,100.50
101(3b) Removal of Existing Asphalt Pavement sq.m. 360.00 104.95 37,782.00 0.04% 73.04 - 73.04 0.01% 0.00% 0.01% 7,665.55 -
102(2) Surplus Common Excavation cu.m 2,605.34 196.77 512,652.75 0.57% - 0.00% 0.00% 0.00% - -
103 Structure Excavation cu.m 7,991.62 286.30 2,288,000.80 2.52% 2030.5 896.88 2,927.38 0.64% 0.28% 0.92% 581,332.15 256,776.74
104(1) Embankment cu.m 14,731.54 605.71 8,923,041.09 9.84% 122.08 - 122.08 0.08% 0.00% 0.08% 73,945.08 -
105(1) Subgrade Preparation (common material) sq.m. 13,061.45 19.94 260,445.31 0.29% 2356.12 488.40 2,844.52 0.05% 0.01% 0.06% 46,981.03 9,738.70
200 Aggregate Sub-base Coarse cu.m 2,741.59 668.38 1,832,423.92 2.02% 946.43 494.60 1,441.03 0.70% 0.36% 1.06% 632,574.88 330,580.75
311(1a) PCC Pavement (0.30m thk) sq.m. 4,483.36 1,584.07 7,101,956.07 7.83% 2,345.14 487.20 2,832.34 4.10% 0.85% 4.95% 3,714,865.92 771,758.90
311(1b) PCC Pavement (0.23m thk) sq.m. 3,564.40 1,194.04 4,256,036.17 4.69% 240.80 - 240.80 0.32% 0.00% 0.32% 287,524.83 -
311(1c) PCC Pavement (0.15m thk) sq.m. 3,858.57 818.71 3,159,049.84 3.48% 503.07 592.40 1,095.47 0.45% 0.53% 0.99% 411,868.44 485,003.80
404 Reinforcing Steel (grade 40) kgs 275,683.65 70.17 19,344,721.72 21.33% 18,591.15 9,959.55 28,550.70 1.44% 0.77% 2.21% 1,304,541.00 698,861.62
405(a) Structural Concrete, Class "A" cu.m 1,986.78 5,569.86 11,066,086.45 12.20% 226.86 118.78 345.64 1.39% 0.73% 2.12% 1,263,578.44 661,587.97
Reinforced Concrete Pipe Culvert (1.22mØ,
500 (1)a RCPC) l.m 100.00 6,826.51 682,651.00 0.75% - 0.00% 0.00% 0.00% - -
600(2)a Mountable Concrete Gutter l.m 1,843.75 639.72 1,179,483.75 1.30% - 0.00% 0.00% 0.00% - -
600(3) Concrete Curb and Gutter, Type A l.m 2,116.07 866.17 1,832,876.35 2.02% 345.20 - 345.20 0.33% 0.00% 0.33% 299,001.88 -
601 Sidewalk (150mm thk) sq.m. 2,320.80 800.65 1,858,148.52 2.05% - 0.00% 0.00% 0.00% - -
605(2b) Regulatory Signs (450x750) each 2.00 12,778.44 25,556.88 0.03% - 0.00% 0.00% 0.00% - -
605(2c) Regulatory Signs (600x650) each 7.00 12,159.36 85,115.52 0.09% - 0.00% 0.00% 0.00% -
605(2)d Regulatory Signs (600x900) each 1.00 12,595.78 12,595.78 0.01% - 0.00% 0.00% 0.00% - -
605(3a) Informatory Signs (400x600) each 1.00 12,595.78 12,595.78 0.01% - 0.00% 0.00% 0.00% - -
606(2) Pavement Markings sq.m. 151.44 650.33 98,485.97 0.11% - 0.00% 0.00% 0.00% - -
609 Sprigging sq.m. 3,179.84 957.30 3,044,060.83 3.36% 10.00 - 10.00 0.01% 0.00% 0.01% 9,573.00 -
611 Trees (Furnishing & Transplanting) each 229.00 10,392.60 2,379,905.40 2.62% 4.00 - 4.00 0.05% 0.00% 0.05% 41,570.40 -
Reflectorized Thermoplastic Pavement
612(1) Markings (White) sq.m. 499.06 1,727.44 862,096.20 0.95% - 0.00% 0.00% 0.00% - -
612(2) Reflectorized Thermoplastic Pavement sq.m. 24.84 1,766.30 43,874.89 0.05% - 0.00% 0.00% 0.00% - -
Markings (Yellow)
SPL-1 Unit Pavers sq.m. 7,638.76 1,890.37 14,440,082.74 15.92% 274.65 311.58 586.23 0.57% 0.65% 1.22% 519,190.12 589,001.48
SPL-2 Unit Pavers (Lining) sq.m. 2,040.28 1,890.37 3,856,884.10 4.25% 89.30 133.25 222.55 0.19% 0.28% 0.46% 168,810.04 251,891.80
SPL-3 Mobilization/Demobilization l.s. 1.00 666,886.90 666,886.90 0.74% - 0.00% 0.00% 0.00% - -
SPL-4 Provide and Maintain Traffic Control l.s. 1.00 112,740.75 112,740.75 0.12% - 0.00% 0.00% 0.00% - -
SPL-5 Project Billboard each 2.00 3,098.87 6,197.74 0.01% - 0.00% 0.00% 0.00% - -
SPL-6 Construction Safety and Health l.s. 1.00 48,193.50 48,193.50 0.05% - 0.00% 0.00% 0.00% -
Additional Works
Unsuitable Excavation cu.m 0.00% 21.99 21.99 0.00% 0.00% 0.00% - -
Backfilling cu.m 0.00% 347.67 347.67 0.00% 0.00% 0.00% -
F. GURREA CONSTRUCTION, INC. LEO P. BIONAT JOSE AL V. FRUTO LEA N. DELFINADO, CES E EDILBERTO D
Contractor Project Engineer Chief, Planning & Design Division Asst. Regional Director Regional D
WORK ACCOMPLISHED
r the Period:
TO DATE
44,325.00
7,665.55
-
838,108.89
73,945.08
56,719.73
963,155.63
4,486,624.82
287,524.83
896,872.24
2,003,402.62
1,925,166.41
-
299,001.88
-
-
-
-
-
-
9,573.00
41,570.40
1,108,191.61
420,701.84
-
-
-
-
-
-
13,462,549.53
Approved by:
EDILBERTO D. TAYAO
Regional Director
STATEMENT OF WORK ACCOMPLISHED
For the Period:
101(3a) Removal of Existing Concrete Pavement sq.m. 3,305.50 105.18 347,672.49 0.58% 145.15 145.15 0.00% 0.03% 0.03% - 15,266.88
101(3b) Removal of Existing Asphalt Pavement sq.m. 360.00 48.84 17,582.40 0.03% 73.04 73.04 0.00% 0.01% 0.01% - 3,567.27
102(2) Surplus Common Excavation cu.m 2,605.34 130.68 340,465.83 0.57% 0.00% 0.00% 0.00% - -
103 Structure Excavation cu.m 7,991.62 156.67 1,252,047.11 2.09% 2,030.50 2,927.38 0.00% 0.53% 0.53% - 318,118.44
104(1) Embankment cu.m 14,731.54 347.67 5,121,714.51 8.53% 122.08 122.08 0.00% 0.07% 0.07% - 42,443.55
105(1) Subgrade Preparation (common material) sq.m. 13,061.45 14.78 193,048.23 0.32% 2,356.12 2,844.52 0.00% 0.06% 0.06% - 34,823.45
200 Aggregate Sub-base Coarse cu.m 2,741.59 333.61 914,621.84 1.52% 946.43 1,441.03 0.00% 0.53% 0.53% - 315,738.51
311(1a) PCC Pavement (0.30m thk) sq.m. 4,483.36 1,100.03 4,931,830.50 8.22% 2,345.14 2,832.34 0.00% 4.30% 4.30% - 2,579,724.35
311(1b) PCC Pavement (0.23m thk) sq.m. 3,564.40 856.84 3,054,120.50 5.09% 240.80 240.80 0.00% 0.34% 0.34% - 206,327.07
311(1c) PCC Pavement (0.15m thk) sq.m. 3,858.57 577.47 2,228,208.42 3.71% 503.07 1,095.47 0.00% 0.48% 0.48% - 290,507.83
404 Reinforcing Steel (grade 40) kgs 275,683.65 43.56 12,008,779.79 20.01% 18,591.15 28,550.70 0.00% 1.35% 1.35% - 809,830.49
405(a) Structural Concrete, Class "A" cu.m 1,986.78 4,600.00 9,139,188.00 15.23% 226.86 345.64 0.00% 1.74% 1.74% - 1,043,556.00
Reinforced Concrete Pipe Culvert (1.22mØ,
500 (1)a RCPC) l.m 100.00 4,905.56 490,556.00 0.82% 0.00% 0.00% 0.00% - -
600(2)a Mountable Concrete Gutter l.m 1,843.75 369.39 681,062.81 1.13% 0.00% 0.00% 0.00% - -
600(3) Concrete Curb and Gutter, Type A l.m 2,116.07 572.08 1,210,561.33 2.02% 345.20 345.20 0.00% 0.33% 0.33% - 197,482.02
601 Sidewalk (150mm thk) sq.m. 2,320.80 581.81 1,350,264.65 2.25% 0.00% 0.00% 0.00% - -
605(2b) Regulatory Signs (450x750) each 2.00 8,356.47 16,712.94 0.03% 0.00% 0.00% 0.00% - -
605(2c) Regulatory Signs (600x650) each 7.00 9,076.47 63,535.29 0.11% 0.00% 0.00% 0.00% -
605(2)d Regulatory Signs (600x900) each 1.00 11,582.04 11,582.04 0.02% 0.00% 0.00% 0.00% - -
605(3a) Informatory Signs (400x600) each 1.00 12,082.04 12,082.04 0.02% 0.00% 0.00% 0.00% - -
606(2) Pavement Markings sq.m. 151.44 483.02 73,148.55 0.12% 0.00% 0.00% 0.00% - -
609 Sprigging sq.m. 3,179.84 572.08 1,819,122.87 3.03% 10.00 10.00 0.00% 0.01% 0.01% - 5,720.80
611 Trees (Furnishing & Transplanting) each 229.00 4,584.72 1,049,900.88 1.75% 4.00 4.00 0.00% 0.03% 0.03% - 18,338.88
Reflectorized Thermoplastic Pavement
612(1) Markings (White) sq.m. 499.06 743.96 371,280.68 0.62% 0.00% 0.00% 0.00% - -
612(2) Reflectorized Thermoplastic Pavement sq.m. 24.84 1,073.07 26,655.06 0.04% 0.00% 0.00% 0.00% - -
Markings (Yellow)
SPL-1 Unit Pavers sq.m. 7,638.76 1,346.00 10,281,770.96 17.13% 274.65 586.23 0.00% 0.62% 0.62% - 369,678.90
SPL-2 Unit Pavers (Lining) sq.m. 2,040.28 1,346.00 2,746,216.88 4.58% 89.30 222.55 0.00% 0.20% 0.20% - 120,197.80
SPL-3 Mobilization/Demobilization l.s. 1.00 105,500.00 105,500.00 0.18% 0.00% 0.00% 0.00% - -
SPL-4 Provide and Maintain Traffic Control l.s. 1.00 115,700.00 115,700.00 0.19% 0.00% 0.00% 0.00% - -
SPL-5 Project Billboard each 2.00 2,321.25 4,642.50 0.01% 0.00% 0.00% 0.00% - -
SPL-6 Construction Safety and Health l.s. 1.00 36,100.00 36,100.00 0.06% 0.00% 0.00% 0.00% -
Additional Works
Unsuitable Excavation cu.m 0.00% 21.99 0.00% 0.00% 0.00% - -
Backfilling cu.m 0.00% 347.67 0.00% 0.00% 0.00% -
F. GURREA CONSTRUCTION, INC. LEO P. BIONAT JOSE AL V. FRUTO LEA N. DELFINADO, CES E EDILBERTO D
Contractor Project Engineer Chief, Planning & Design Division Asst. Regional Director Regional D
WORK ACCOMPLISHED
r the Period:
TO DATE
15,266.88
3,567.27
-
318,118.44
42,443.55
34,823.45
315,738.51
2,579,724.35
206,327.07
290,507.83
809,830.49
1,043,556.00
-
197,482.02
-
-
-
-
-
-
5,720.80
18,338.88
369,678.90
120,197.80
-
-
-
-
-
-
6,371,322.25
Approved by:
EDILBERTO D. TAYAO
Regional Director
STATEMENT OF WORK ACCOMPLISHED
For the Period:
101(3a) Removal of Existing Concrete Pavement sq.m. 3,305.50 105.18 347,672.49 0.58% 145.15 141.80 286.95 0.03% 0.02% 0.05% 15,266.88 14,914.52
101(3b) Removal of Existing Asphalt Pavement sq.m. 360.00 48.84 17,582.40 0.03% 73.04 73.04 0.01% 0.00% 0.01% 3,567.27 -
102(2) Surplus Common Excavation cu.m 2,605.34 130.68 340,465.83 0.57% 675.87 675.87 0.00% 0.15% 0.15% - 88,322.69
103 Structure Excavation cu.m 7,991.62 156.67 1,252,047.11 2.09% 2030.5 2,030.50 0.53% 0.00% 0.53% 318,118.44 -
104(1) Embankment cu.m 14,731.54 347.67 5,121,714.51 8.53% 122.08 37.54 159.62 0.07% 0.02% 0.09% 42,443.55 13,051.53
105(1) Subgrade Preparation (common material) sq.m. 13,061.45 14.78 193,048.23 0.32% 2356.12 217.41 2,573.53 0.06% 0.01% 0.06% 34,823.45 3,213.32
200 Aggregate Sub-base Coarse cu.m 2,741.59 333.61 914,621.84 1.52% 946.43 946.43 0.53% 0.00% 0.53% 315,738.51 -
311(1a) PCC Pavement (0.30m thk) sq.m. 4,483.36 1,100.03 4,931,830.50 8.22% 2,345.14 516.73 2,861.87 4.30% 0.95% 5.25% 2,579,724.35 568,418.50
311(1b) PCC Pavement (0.23m thk) sq.m. 3,564.40 856.84 3,054,120.50 5.09% 240.80 240.80 0.34% 0.00% 0.34% 206,327.07 -
311(1c) PCC Pavement (0.15m thk) sq.m. 3,858.57 577.47 2,228,208.42 3.71% 503.07 503.07 0.48% 0.00% 0.48% 290,507.83 -
404 Reinforcing Steel (grade 40) kgs 275,683.65 43.56 12,008,779.79 20.01% 18,591.15 11,675.12 30,266.27 1.35% 0.85% 2.20% 809,830.49 508,568.23
405(a) Structural Concrete, Class "A" cu.m 1,986.78 4,600.00 9,139,188.00 15.23% 226.86 77.71 304.57 1.74% 0.60% 2.33% 1,043,556.00 357,466.00
500 (1)a Reinforced Concrete Pipe Culvert (1.22mØ, l.m 100.00 4,905.56 490,556.00 0.82% - 0.00% 0.00% 0.00% - -
RCPC)
600(2)a Mountable Concrete Gutter l.m 1,843.75 369.39 681,062.81 1.13% - 0.00% 0.00% 0.00% - -
600(3) Concrete Curb and Gutter, Type A l.m 2,116.07 572.08 1,210,561.33 2.02% 345.20 345.20 0.33% 0.00% 0.33% 197,482.02 -
601 Sidewalk (150mm thk) sq.m. 2,320.80 581.81 1,350,264.65 2.25% 906.20 906.20 0.00% 0.88% 0.88% - 527,236.22
605(2b) Regulatory Signs (450x750) each 2.00 8,356.47 16,712.94 0.03% - 0.00% 0.00% 0.00% - -
605(2c) Regulatory Signs (600x650) each 7.00 9,076.47 63,535.29 0.11% - 0.00% 0.00% 0.00% -
605(2)d Regulatory Signs (600x900) each 1.00 11,582.04 11,582.04 0.02% - 0.00% 0.00% 0.00% - -
605(3a) Informatory Signs (400x600) each 1.00 12,082.04 12,082.04 0.02% - 0.00% 0.00% 0.00% - -
606(2) Pavement Markings sq.m. 151.44 483.02 73,148.55 0.12% - 0.00% 0.00% 0.00% - -
609 Sprigging sq.m. 3,179.84 572.08 1,819,122.87 3.03% 10.00 10.00 0.01% 0.00% 0.01% 5,720.80 -
611 Trees (Furnishing & Transplanting) each 229.00 4,584.72 1,049,900.88 1.75% 4.00 4.00 0.03% 0.00% 0.03% 18,338.88 -
612(1) Reflectorized Thermoplastic Pavement sq.m. 499.06 743.96 371,280.68 0.62% - 0.00% 0.00% 0.00% - -
Markings (White)
612(2) Reflectorized Thermoplastic Pavement sq.m. 24.84 1,073.07 26,655.06 0.04% - 0.00% 0.00% 0.00% - -
Markings (Yellow)
SPL-1 Unit Pavers sq.m. 7,638.76 1,346.00 10,281,770.96 17.13% 274.65 585.13 859.78 0.62% 1.31% 1.93% 369,678.90 787,584.98
SPL-2 Unit Pavers (Lining) sq.m. 2,040.28 1,346.00 2,746,216.88 4.58% 89.30 302.97 392.27 0.20% 0.68% 0.88% 120,197.80 407,797.62
SPL-3 Mobilization/Demobilization l.s. 1.00 105,500.00 105,500.00 0.18% - 0.00% 0.00% 0.00% - -
SPL-4 Provide and Maintain Traffic Control l.s. 1.00 115,700.00 115,700.00 0.19% - 0.00% 0.00% 0.00% - -
SPL-5 Project Billboard each 2.00 2,321.25 4,642.50 0.01% - 0.00% 0.00% 0.00% - -
SPL-6 Construction Safety and Health l.s. 1.00 36,100.00 36,100.00 0.06% - 0.00% 0.00% 0.00% -
Additional Works -
Dropped Inlet
Concrete Curb
Concrete Lining
Fabrication & Installation of Bollard (G.I.
Pipe)
F. GURREA CONSTRUCTION, INC. LEO P. BIONAT JOSE AL V. FRUTO LEA N. DELFINADO, CES E EDILBERTO D. T
GNO S. AQUINO AVENUE (ILOILO-JARO-DIVERSION ROAD) TO ILOILO CITY-PAVIA ROAD
30,181.40
762.75 80,226.05 475.80 50,044.64
3,567.27
798.4 38,993.86 725.36 35,426.58
88,322.69
2770.36 362,030.64 2,094.49 273,707.95
318,118.44
865.86 135,654.29 (1,164.64) (182,464.15)
55,495.09
729.18 253,514.01 569.56 198,018.93
38,036.77
2573.53 38,036.77 - -
315,738.51
462.3 154,227.90 (484.13) (161,510.61)
3,148,142.86
2861.87 3,148,142.86 - -
206,327.07
- (240.80) (206,327.07)
290,507.83
- (503.07) (290,507.83)
1,318,398.72
30266.27 1,318,398.72 - -
1,401,022.00
304.57 1,401,022.00 - -
-
- - -
-
- - -
197,482.02
399.2 228,374.34 54.00 30,892.32
527,236.22
1839.96 1,070,507.13 933.76 543,270.91
-
- - -
-
- - -
-
- - -
-
- - -
-
- - -
5,720.80
621 355,261.68 611.00 349,540.88
18,338.88
- (4.00) (18,338.88)
-
- - -
-
- - -
1,157,263.88
1185.59 1,595,804.14 325.81 438,540.26
527,995.42
654.37 880,782.02 262.10 352,786.60
-
- - -
-
- - -
-
- - -
-
- - -
- - -
-
- - -
-
- - -
- - -
- - -
- - -
- - -
- - -
- -
9,647,895.87 11,060,976.40 1,413,080.53
Approved by:
EDILBERTO D. TAYAO
STATEMENT OF WORK ACCOMPLISHED
For the Period:
101(3a) Removal of Existing Concrete Pavement sq.m. 3,305.50 105.18 347,672.49 0.58% 145.15 141.80 286.95 0.03% 0.02% 0.05% 15,266.88 14,914.52
101(3b) Removal of Existing Asphalt Pavement sq.m. 360.00 48.84 17,582.40 0.03% 73.04 73.04 0.01% 0.00% 0.01% 3,567.27 -
102(2) Surplus Common Excavation cu.m 2,605.34 130.68 340,465.83 0.57% 675.87 675.87 0.00% 0.15% 0.15% - 88,322.69
103 Structure Excavation cu.m 7,991.62 156.67 1,252,047.11 2.09% 2030.5 (1,164.64) 865.86 0.53% -0.30% 0.23% 318,118.44 (182,464.15)
104(1) Embankment cu.m 14,731.54 347.67 5,121,714.51 8.53% 122.08 37.54 159.62 0.07% 0.02% 0.09% 42,443.55 13,051.53
105(1) Subgrade Preparation (common material) sq.m. 13,061.45 14.78 193,048.23 0.32% 2356.12 217.41 2,573.53 0.06% 0.01% 0.06% 34,823.45 3,213.32
200 Aggregate Sub-base Coarse cu.m 2,741.59 333.61 914,621.84 1.52% 946.43 (484.13) 462.30 0.53% -0.27% 0.26% 315,738.51 (161,510.61)
311(1a) PCC Pavement (0.30m thk) sq.m. 4,483.36 1,100.03 4,931,830.50 8.22% 2,345.14 516.73 2,861.87 4.30% 0.95% 5.25% 2,579,724.35 568,418.50
311(1b) PCC Pavement (0.23m thk) sq.m. 3,564.40 856.84 3,054,120.50 5.09% 240.80 (240.80) - 0.34% -0.34% 0.00% 206,327.07 (206,327.07)
311(1c) PCC Pavement (0.15m thk) sq.m. 3,858.57 577.47 2,228,208.42 3.71% 503.07 (503.07) - 0.48% -0.48% 0.00% 290,507.83 (290,507.83)
404 Reinforcing Steel (grade 40) kgs 275,683.65 43.56 12,008,779.79 20.01% 18,591.15 11,675.12 30,266.27 1.35% 0.85% 2.20% 809,830.49 508,568.23
405(a) Structural Concrete, Class "A" cu.m 1,986.78 4,600.00 9,139,188.00 15.23% 226.86 77.71 304.57 1.74% 0.60% 2.33% 1,043,556.00 357,466.00
500 (1)a Reinforced Concrete Pipe Culvert (1.22mØ, l.m 100.00 4,905.56 490,556.00 0.82% - 0.00% 0.00% 0.00% - -
RCPC)
600(2)a Mountable Concrete Gutter l.m 1,843.75 369.39 681,062.81 1.13% - 0.00% 0.00% 0.00% - -
600(3) Concrete Curb and Gutter, Type A l.m 2,116.07 572.08 1,210,561.33 2.02% 345.20 345.20 0.33% 0.00% 0.33% 197,482.02 -
601 Sidewalk (150mm thk) sq.m. 2,320.80 581.81 1,350,264.65 2.25% 906.20 906.20 0.00% 0.88% 0.88% - 527,236.22
605(2b) Regulatory Signs (450x750) each 2.00 8,356.47 16,712.94 0.03% - 0.00% 0.00% 0.00% - -
605(2c) Regulatory Signs (600x650) each 7.00 9,076.47 63,535.29 0.11% - 0.00% 0.00% 0.00% -
605(2)d Regulatory Signs (600x900) each 1.00 11,582.04 11,582.04 0.02% - 0.00% 0.00% 0.00% - -
605(3a) Informatory Signs (400x600) each 1.00 12,082.04 12,082.04 0.02% - 0.00% 0.00% 0.00% - -
606(2) Pavement Markings sq.m. 151.44 483.02 73,148.55 0.12% - 0.00% 0.00% 0.00% - -
609 Sprigging sq.m. 3,179.84 572.08 1,819,122.87 3.03% 10.00 10.00 0.01% 0.00% 0.01% 5,720.80 -
611 Trees (Furnishing & Transplanting) each 229.00 4,584.72 1,049,900.88 1.75% 4.00 (4.00) - 0.03% -0.03% 0.00% 18,338.88 (18,338.88)
612(1) Reflectorized Thermoplastic Pavement sq.m. 499.06 743.96 371,280.68 0.62% - 0.00% 0.00% 0.00% - -
Markings (White)
612(2) Reflectorized Thermoplastic Pavement sq.m. 24.84 1,073.07 26,655.06 0.04% - 0.00% 0.00% 0.00% - -
Markings (Yellow)
SPL-1 Unit Pavers sq.m. 7,638.76 1,346.00 10,281,770.96 17.13% 274.65 585.13 859.78 0.62% 1.31% 1.93% 369,678.90 787,584.98
SPL-2 Unit Pavers (Lining) sq.m. 2,040.28 1,346.00 2,746,216.88 4.58% 89.30 302.97 392.27 0.20% 0.68% 0.88% 120,197.80 407,797.62
SPL-3 Mobilization/Demobilization l.s. 1.00 105,500.00 105,500.00 0.18% - 0.00% 0.00% 0.00% - -
SPL-4 Provide and Maintain Traffic Control l.s. 1.00 115,700.00 115,700.00 0.19% - 0.00% 0.00% 0.00% - -
SPL-5 Project Billboard each 2.00 2,321.25 4,642.50 0.01% - 0.00% 0.00% 0.00% - -
SPL-6 Construction Safety and Health l.s. 1.00 36,100.00 36,100.00 0.06% - 0.00% 0.00% 0.00% -
Additional Works -
Dropped Inlet
Concrete Curb
Concrete Lining
Fabrication & Installation of Bollard (G.I.
Pipe)
F. GURREA CONSTRUCTION, INC. LEO P. BIONAT JOSE AL V. FRUTO LEA N. DELFINADO, CES E EDILBERTO D. T
NO S. AQUINO AVENUE (ILOILO-JARO-DIVERSION ROAD) TO ILOILO CITY-PAVIA ROAD
30,181.40
762.75 80,226.05 475.80 50,044.64
3,567.27
798.4 38,993.86 725.36 35,426.58
88,322.69
2770.36 362,030.64 2,094.49 273,707.95
135,654.29
865.86 135,654.29 - -
55,495.09
729.18 253,514.01 569.56 198,018.93
38,036.77
2573.53 38,036.77 - -
154,227.90
462.3 154,227.90 - -
3,148,142.86
2861.87 3,148,142.86 - -
-
- - -
-
- - -
1,318,398.72
30266.27 1,318,398.72 - -
1,401,022.00
304.57 1,401,022.00 - -
-
- - -
-
- - -
197,482.02
399.2 228,374.34 54.00 30,892.32
527,236.22
1839.96 1,070,507.13 933.76 543,270.91
-
- - -
-
- - -
-
- - -
-
- - -
-
- - -
5,720.80
621 355,261.68 611.00 349,540.88
-
- - -
-
- - -
-
- - -
1,157,263.88
1185.59 1,595,804.14 325.81 438,540.26
527,995.42
654.37 880,782.02 262.10 352,786.60
-
- - -
-
- - -
-
- - -
-
- - -
- - -
-
- - -
-
- - -
- - -
- - -
- - -
- - -
- - -
- -
8,788,747.33 11,060,976.40 2,272,229.07
Approved by:
EDILBERTO D. TAYAO
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
OFFICE OF THE REGIONAL DIRECTOR
REGION VI - WESTERN VISAYAS
Fort San Pedro, Iloilo City