Gantt Chart

The document provides a Gantt chart schedule for auxiliary works over a 60 working day period from March 16 to May 23. It includes scopes of work for fabrication, concrete pouring and curing, stripping formworks, sanding and painting. The schedule tracks the timing and duration of tasks such as scaffolds installation, rebar work, concrete pouring and curing. It also includes a manpower schedule projecting a team of 16 workers over the duration of the project.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
72 views4 pages

Gantt Chart

The document provides a Gantt chart schedule for auxiliary works over a 60 working day period from March 16 to May 23. It includes scopes of work for fabrication, concrete pouring and curing, stripping formworks, sanding and painting. The schedule tracks the timing and duration of tasks such as scaffolds installation, rebar work, concrete pouring and curing. It also includes a manpower schedule projecting a team of 16 workers over the duration of the project.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 4

CLIENT:

MARCH
PLAN PLAN 16 17 18 19 20
SCOPE OF WORKS
START DURATION
1 2 3 4 5
A. GENERAL REQUIREMENTS
1. Mobilization and Demobilization Day 1 1
2. Delivery of Materials Day2 1
SECOND LEVEL
B. FABRICATION
B.1. Scaffolds, Formworks and Rebars Fab./Inst. Day3 7
A.2. Lightweight Concrete Pouring Day 11 2
A.3. Lightweight Concrete Curing Day 13 28
A.4. Stripping of Scaffolds & Formworks Day 16&24 4
A.5. Sanding of Encasement Day 17&25 8
A.6. Skimcoat/Paint Application Day 19&25 8
B. 11-110 mm diameter PVC in Lightweight Concrete Encasement
B.1. Scaffolds, Formworks and Rebars Fab./Inst. Day 13 7
B.2. Lightweight Concrete Pouring Day 22 2
B.3. Lightweight Concrete Curing Day 24 28
B.4. Stripping of Scaffolds & Formworks Day 27&34 4
B.5. Sanding of Encasement Day 29&36 8
B.6. Skimcoat/Paint Application Day 33 8
C. 2000mm x 1000mm x 1600mm Concrete Pullbox
C.1. Chipping of Slab Day 15 14
C.2. Scaffolds, Formworks and Rebars Fab./Inst. Day 24 7
C.3. Concrete Pouring Day 31 2
C.4. Concrete Curing Day 33 28
C.5. Stripping of Scaffolds & Formworks Day 43 2
C.6. Sanding of Pullbox Day 45 5
OTHERS
A. Rectification/Punchlist Day 45 5
B. Hauling and Clearing Day 51 4

MANPOWER SCHEDULE
P.I.C./Safety Officer 1 1 1 1 1
Foreman 1 1 1 1 1
Carpenter/Mason 3 3 3 3 3
Steelman 2 2 2 2 2
Scaffolds/Formworks Erector 2 2 2 2 2
Labor 7 7 7 7 7
Total 16 16 16 16 16
PREPARED BY: APPROVED BY:
AUXILIARY WORKS
GANTT CHART
LOCATION:

MARCH APRIL
21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
CALENDAR DAYS
6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7
16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16
NOTED BY:
RY WORKS
TT CHART
DURATION:

60 WORKING DAYS

RIL MAY
19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
CALENDAR DAYS
31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54

1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 3 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
2 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
7 4 3 3 3 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
16 10 8 8 8 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
18 19 20 21 22 23

55 56 57 58 59 60