CLIENT:
MARCH
PLAN PLAN 16 17 18 19 20
SCOPE OF WORKS
START DURATION
1 2 3 4 5
A. GENERAL REQUIREMENTS
1. Mobilization and Demobilization Day 1 1
2. Delivery of Materials Day2 1
SECOND LEVEL
B. FABRICATION
B.1. Scaffolds, Formworks and Rebars Fab./Inst. Day3 7
A.2. Lightweight Concrete Pouring Day 11 2
A.3. Lightweight Concrete Curing Day 13 28
A.4. Stripping of Scaffolds & Formworks Day 16&24 4
A.5. Sanding of Encasement Day 17&25 8
A.6. Skimcoat/Paint Application Day 19&25 8
B. 11-110 mm diameter PVC in Lightweight Concrete Encasement
B.1. Scaffolds, Formworks and Rebars Fab./Inst. Day 13 7
B.2. Lightweight Concrete Pouring Day 22 2
B.3. Lightweight Concrete Curing Day 24 28
B.4. Stripping of Scaffolds & Formworks Day 27&34 4
B.5. Sanding of Encasement Day 29&36 8
B.6. Skimcoat/Paint Application Day 33 8
C. 2000mm x 1000mm x 1600mm Concrete Pullbox
C.1. Chipping of Slab Day 15 14
C.2. Scaffolds, Formworks and Rebars Fab./Inst. Day 24 7
C.3. Concrete Pouring Day 31 2
C.4. Concrete Curing Day 33 28
C.5. Stripping of Scaffolds & Formworks Day 43 2
C.6. Sanding of Pullbox Day 45 5
OTHERS
A. Rectification/Punchlist Day 45 5
B. Hauling and Clearing Day 51 4
MANPOWER SCHEDULE
P.I.C./Safety Officer 1 1 1 1 1
Foreman 1 1 1 1 1
Carpenter/Mason 3 3 3 3 3
Steelman 2 2 2 2 2
Scaffolds/Formworks Erector 2 2 2 2 2
Labor 7 7 7 7 7
Total 16 16 16 16 16
PREPARED BY: APPROVED BY:
AUXILIARY WORKS
GANTT CHART
LOCATION:
MARCH APRIL
21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
CALENDAR DAYS
6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7
16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16
NOTED BY:
RY WORKS
TT CHART
DURATION:
60 WORKING DAYS
RIL MAY
19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
CALENDAR DAYS
31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 3 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
2 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
7 4 3 3 3 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
16 10 8 8 8 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
18 19 20 21 22 23
55 56 57 58 59 60