CVR - Cost Codes
CVR - Cost Codes
1. INTRODUCTION
This chapter provides an example outline of cost items and their corresponding cost
codes that may be used for construction projects. These cost items are divided into 11
general groups (A-K) known as Level 1 cost items with their respective Level 1 cost
codes. Each cost item is broken into specific items known as Level 2 cost items and has
a Level 2 cost code associated with it. Following each outline of cost items, Level 1 and
2, is their description.
An outline and brief explanation of the Level 1 cost codes in the common cost code of
accounts are as follows:
This cost code includes the purchase price, other acquisition costs, and removal
costs less salvage realized in disposing of any facilities acquired with the land.
Some specific items are as follows.
16-2 DOE G 430.1-1
03-28-97
• the costs of rights, interests, and privileges relating to land, such as leaseholds,
easements, rights-of-way, water and waterpower rights, diversion rights, and
submersion rights;
• the cost and appraised value of timber and pulpwood; cost of reforestation
program for the purpose of dust and soil erosion control, retention of water
tables, etc.; cost of development and improvement of timber stand; and other
forestry management costs; and
• the cost of mineral rights and land containing mineral deposits owned by the
Government.
This cost code includes the cost of general site clearing, grading, drainage, and
facilities common to the project as a whole (such as roads, walks, paved areas,
fences, guard towers, railroads, port facilities, etc.), but excludes individual
buildings, other structures, utilities, special equipment/process systems, and
demolition, tunneling and drilling when they are a significant intermediate or end
product of the project.
C. Buildings (501)
This cost code includes the installed cost of buildings and permanently attached
appurtenances, such as fire protection, lighting, plumbing, heating, ventilation, and
built-in air conditioning systems (excluding window or console air conditioning
units that require no ductwork or cooling towers), and the cost of piping, conduit,
and cable permanently attached to and made a part of the building. The division
between building costs and the costs of utility systems is generally made at a point
nominally 5 feet outside the building wall.
This cost code includes the installed cost of such structures as dams, retention
basins, reservoirs, swimming pools, pits, platforms, underground oil storage
reservoirs, and stacks (when not a part of a building), and installed cost of structures
and frames used to support such items as heat exchangers, vessels, etc., or special
structures, such as towers, utility doors, etc., whether inside or outside a building.
E. Utilities (600)
This cost code includes the installed cost of systems that service the project as a
whole and generally extend between individual buildings or process units.
Examples include communications systems, electric transmission and distribution
systems, alarm systems, gas transmission and distribution systems, irrigation
DOE G 430.1-1 16-3
03-28-97
This cost code includes the installed cost of large items of special equipment and
process systems, such as vessels (e.g., towers, reactors, storage tanks), heat transfer
systems (e.g., heat exchangers, stacks, cooling towers, desuperheaters, etc.),
package units (e.g., waste treatment packages, clarifier packages, sulfurization,
demineralization, etc.), and process piping systems.
This cost code includes the cost of improvements made by DOE to land, buildings,
structures, building services, and utility systems not owned by DOE. Plants,
laboratories, and similar facilities constructed by DOE on land owned by others are
not to be classified in this category.
H. Demolition (810)
This cost code includes the cost of wrecking, dismantling, cutting, drilling, and
removing existing structures, equipment, and materials, as well as any excavation
required to facilitate demolition and the cleaning, stacking, loading, hauling, and
unloading of material for salvage and/or disposal when such activity represents a
major activity in accomplishment of the project. Minor, routine demolition will be
listed under improvements to land.
I. Tunneling (820)
This cost code includes the complete costs of constructing a tunnel consisting of
excavation, drilling, blasting, mucking, shoring, timbering, bolting, mechanical
utilities (air, water, and vent lines), surface construction installation (shaft collars,
portal facings, retaining walls, rock, volts, fences, gates, hatches, doors, muck
dumping facilities, anchors, guys, deadmen, buildings, foundations, docks, etc.),
and associated mobilization and demobilization.
J. Drilling (830)
This cost code includes the complete cost of drilling consisting of purchase or lease
of the drilling rig and associated material mandrels, jet subs, drill collars, drill pipe,
kellys, goosenecks, casing, detergent, mud additives and other chemicals, tool
repair, installing casing (double jointing, lugging, cutting lifting eyes, belling, and
installing guidelines), installing the drilling rig, correcting problems (plugback to
16-4 DOE G 430.1-1
03-28-97
correct well bore deviations), cleaning out and conditioning the hole, coring,
sidewall, sampling, dewatering, fishing, laboratory support, building support
structures, and safety fences.
This level includes items of equipment in which only a minimum of design work is
required, such as “off-the-shelf” items. Examples of standard equipment include
office furniture, laboratory equipment, heavy mobile equipment, etc. Items of
standard equipment that are incorporated into Second Level code systems will be
included with that system and not under standard equipment.
501 Buildings
5011 Excavation and Backfill
5012 Concrete
5013 Masonry
5014 Metals
5015 Wood and Plastic
5016 Finishes
5017 Special Construction
5018 Mechanical
DOE G 430.1-1 16-5
03-28-97
5019 Electrical
600 Utilities
6100 Communications Systems
6150 Electric Transmission and
Distribution Systems
6210 Alarm Systems
6250 Gas Transmission and
Distribution Systems
6300 Irrigation Systems
6400 Sewerage Systems
6450 Steam Generation and
Distribution Systems
6500 Water Supply, Pumping,
Treatment and Distribution
Systems
6600 Oil Piping and Distribution
Systems
6900 Other Utilities
810 Demolition
820 Tunneling
830 Drilling
1. 4010 Land
This includes the purchase price, other acquisition costs, and removal costs
less salvage realized in disposing of any facilities acquired with the land.
Some specific items are as follows.
c. Cost Recoveries: This includes the amounts received from cash sale of
net transfer values of buildings and other structures, acquired with the
purchase or acquisition of the site, on which disposal is made.
This includes the costs of rights, interests, and privileges relating to land, such
as leaseholds, easements, rights-of-way, water and waterpower rights,
diversion rights, and submersion rights.
3. 4030 Minerals
This includes the cost of mineral rights and land containing mineral deposits
owned by the Government.
4. 4040 Timber
This includes the cost and appraised value of timber and pulpwood, cost of
reforestation program for the purpose of dust and soil erosion control,
16-8 DOE G 430.1-1
03-28-97
a. This includes labor and material required for surveying and mapping,
subsurface investigating, clearing, excavating, and backfilling to bring
area to a general grade. This cost code includes digging test trenches
required during construction, demolition, disposing of surplus materials,
maintaining spoil areas, and related work.
b. This excludes specific grading and base materials for roads, walks,
drives, and parking areas; grading for culverts and culvert headwalls;
final grading (see Landscaping); grading for railroads; and marginal and
drainage ditches that are included in other accounts.
1. Clearing, Grading, and Backfill: This includes the cost for clearing,
digging test trenches, and grubbing required during construction;
machine and hand excavation; backfilling and compacting of earth
and stone either by hand or by mechanical and pneumatic
equipment; disposing of surplus materials; maintaining spoil areas;
and related work. This cost code does not include specific grading
or base materials for roads, drainage ditches, etc. (See second level
cost code description.)
2. 4602 Drainage
a. This includes labor and material required for the installation of all storm
sewers and drains for the area between points 5 feet outside the building
lines. This cost code includes all work for storm sewer manholes,
headwalls, precast concrete, concrete slabs, cast-in-place concrete, street
storm water receivers and outfall drainage ditches, and all drainage in the
switchyard.
b. This excludes culverts and marginal ditches along roads, paved areas,
railroads, and cooling ponds or sewage lagoons.
3. Catch Basins and Manholes: This includes the cost required for
forming, hauling, reinforcing, placing, curing, protecting, and
finishing concrete for manholes, catch basins, headwalls, and
drainage ditch slabs. It includes all rip-rap work for storm ditches.
4. Piping: This includes the cost required for installation of cast iron
pipe, corrugated metal pipe, and concrete pipe for the storm sewer
system, from a point 5 feet outside the building line.
16-10 DOE G 430.1-1
03-28-97
3. 4603 Landscaping
This includes labor and material for final grading and landscaping the area.
This cost code includes applying or planting such items as topsoil, fertilizer,
seeds, seedlings, sod, and shrubs.
a. Final Grading: This includes the cost for bringing the area surface to its
final elevation.
4. 4605 Railroads
a. This includes labor and material required for installing railroad trackage
outside of building limits. This cost code includes excavation, backfill,
compacting, fine grading, setting of ties and rails, hauling and spreading
of ballasts, construction-related culverts, bridges, and headwalls, and
installing warning systems and guard gates.
b. It excludes railroad cars, engines, and other railroad equipment that will
operate on the track.
3. Track Laying and Surfacing: This includes the cost for hauling and
placing ties, rails, ballasts, and other track materials, such as angle
bars, frogs, guardrails, track bolts and nuts, rail joints, switches,
spikes, and related work.
DOE G 430.1-1 16-11
03-28-97
5. Warning Systems and Gates: This includes the cost for the complete
installation of railroad warning systems and gates.
a. This includes labor and material required for constructing a port facility.
This cost code includes excavation, backfill, compacting, and
construction involved in building docks, piers, levies, jetties, anchorages,
and other parts of a port facility.
a. This includes labor and material required for the stripping, grading,
backfilling, compacting, and application of base and surface materials for
permanent roads, walks, and paved areas. It includes bridges, culverts,
and culvert headwalls over drainage areas, grading of road and marginal
ditches, construction and painting of curbs and fabricating or installing
guardrails, traffic barriers, and incidental appurtenances and stripping.
16-12 DOE G 430.1-1
03-28-97
b. This excludes any work for railroad track and grade crossings (see
Railroads).
4. Guard Rails, Posts, and Traffic Barriers: This includes the cost for
all work to fabricate and install protective barriers and necessary
stripping.
a. This includes labor and material required for security fences and gates for
the area and all work for erecting guard towers and gatehouses, complete
with interior electrical work.
2. Gatehouses and Guard Towers: This includes the cost for complete
installation of foundations and superstructures. It excludes exterior
electrical work and floodlights (see Utilities).
This includes the installed cost of any improvement to land not included in
codes 4601 through 4800, except demolition, tunneling, and drilling, which
are listed under accounts 810, 820, and 830, respectively. Improvement to
land belonging to others will be included under account 800.
C. 501 Buildings
1. Excavation: This includes the cost for machine and hand excavation
and disposal of surplus material.
2. Backfill: This includes the cost for backfill and compacting of earth,
stone, or other selected materials, either by hand or by mechanical
and pneumatic equipment.
4. Fine Grading: This includes the cost for fine grade work
preparatory to ground floor slab construction, including borrow and
backfill of fine grade selected materials.
2. 5012 Concrete
b. This cost code excludes all work in connection with the construction of
instrument tunnels, foundations for process equipment, and piping
(except the embedded structure support).
1. Forms and Screeds: This includes the cost for hauling, fabricating,
erecting, stripping, cleaning, and disposing of form work and
screeds.
3. Form Ties, Keyways, Inserts, and Joints: This includes the cost for
hauling, fabricating, and inserting of form ties, keyways, inserts, and
premoulded expansion material.
4. Precast Concrete: This includes the cost for hauling, handling, and
placing all precast concrete items.
6. Reinforcing Steel and Mesh: This includes the cost of labor for
handling, hauling, bending, fabricating, placing, tying, and cleaning
of reinforcing steel and mesh.
9. Anchor Bolts and Sleeves: This includes the cost for handling,
fabricating, aligning, and setting of anchor bolts for building
superstructure and sleeves. This cost code excludes grouting and
setting of base plates and miscellaneous structural steel and iron (see
second level cost code description).
3. 5013 Masonry
1. Masonry: This includes the cost for hauling, handling, placing, and
construction of masonry and concrete block unit walls and
partitions, and related scaffolding, bracing, repairing, waterproofing,
and finishing. This cost code excludes painting.
2. Face Tile: This includes the cost for hauling, handling, and
installation of face tile, and related scaffolding, bracing, and
cleaning and washing of face tile after installation.
4. 5014 Metals
b. This cost code excludes anchor bolts for building superstructures and
base plates included with process equipment.
1. Base Plates: This includes the cost for handling, hauling, setting,
and grouting of base plates required to completely install the
structural steel. This account excludes base plates for process gas
piping and those included with process equipment (see second level
cost code description).
2. Steel Handling and Erection: This includes the cost for handling,
hauling, reloading, rehauling, shaking out, erecting, plumbing, and
riveting or welding of structural steel for building superstructure.
4. Railroad Track in Truck Alley: This includes the cost for installing
rail and related items, such as metal ties, tie plates, and bumper
blocks.
6. Embedded Steel and Iron: This includes the cost for fabricating,
handling, hauling, setting, and grouting of anchor bolts and base
plates required for miscellaneous structural steel and iron, including
related caulking.
DOE G 430.1-1 16-17
03-28-97
a. This includes labor and material required for building structural frames
made of wood or plastic construction. The account includes framing and
sheathing, wood decking, fiber underlayerment, timber trusses, pole
construction, trestles, wood treatment, and associated hardware items,
such as nails, screws, bolts, glue, and other fasteners. It includes wood
stairs and railings and any wood used to secure, protect, or in any way
provide safety at the building site, including safety rails, safety fences,
temporary ladders, temporary overhangs, or ceilings. It includes all
plastic used to wrap or protect the materials exposed to the elements at
the building site.
b. This excludes wood or plastic used for earthwork and concrete forms.
1. Framing and Erection: This includes the cost for handling, hauling,
reloading, erecting, and fastening of structural wood for the building
superstructure.
6. 5016 Finishes
a. This includes accounts that generally fall under the broad categories of
thermal and moisture protection, doors and windows, finishes and
specialties. This account covers labor and material required for
construction and revision of built-up roofing, including flashing,
caulking, scuppers, gutters, sheet metal conductors, hatch covers, and
16-18 DOE G 430.1-1
03-28-97
insulation and repair of damaged roofs and roofing items. It also includes
metal, precast or poured roof decks, other-than-reinforced concrete slabs,
and special expansion joints and cap flashings.
1. Roof Construction: This includes the cost for hauling, handling, and
installation of roofing, including revisions, and roof insulation.
3. Roof Decks: This includes the cost for installing metal, precast or
poured decks, other-than-reinforced concrete slabs, and installation
of hatch covers.
d. This includes labor and material required for the installation of building
siding, insulation, flashing, caulking, special expansion joints, and minor
repairs. This cost code excludes siding items for pre-engineered
structures.
1. Siding: This includes the cost for hauling, handling, and installation
of building siding, insulation, and minor repairs.
2. Expansion Joints and Flashing: This includes the cost for hauling,
fabrication, erection, and installation of special expansion joints for
flashing of building siding, including caulking.
1. Interior Walls and Partitions: This includes the cost for hauling,
handling, placing, and constructing interior walls and partitions,
including related scaffolding, bracing, repairing, waterproofing,
fireproofing, and finishing.
3. Special Flooring: This includes the cost for flooring other than
concrete, such as asphalt, rubber, koroseal, quarry tile or wood,
including hauling, handling, placing, and finishing of flooring and
related cove base and shoe moulds.
4. Millwork and Trim: This includes the cost for hauling, handling,
fabricating, and installing all millwork and wood trim. This includes
studs and plates for all wood partitions.
5. Metal Doors: This includes the cost for hauling, handling, erecting,
and other work to install metal and metal clad doors, complete with
frames, hardware, and operating devices.
6. Wood Doors: This includes the cost for hauling, handling, erecting,
and other work to install wood doors, complete with hardware.
8. Caulking: This includes the cost for all caulking required for door
and window installation.
10. Metal: This includes the cost for hauling, handling, and installation
of stud for tile-faced partitions.
f. This includes labor and materials required for all field painting, such as
structural steel, miscellaneous iron, doors, walls, ceilings, equipment and
piping, special codes and identification, hauling and handling of
materials, cleaning prior to painting, application of primer and paint,
necessary scaffolding and cleanup after painting, and the furnishing of all
glass, glazing, and incidental work. Specifically included are the
following.
1. Structural Steel and Iron: This includes the cost for all painting and
related work, or structural steel for building superstructure and
miscellaneous structural steel and iron, such as walkways, stairs,
windows, doors, handrails, thresholds, and similar items.
2. Equipment, Piping, and Supports: This includes the cost for all
painting and related work, of equipment that is not furnished with a
factory finish, pipe hangers and supports, piping, and code coloring
of piping.
3. Code and Identification: This includes the cost for all painting, and
related work of lettering and code identification, and permanent sign
painting.
4. Other Painting: This includes the cost for all other painting, and
related work, such as masonry walls, millwork, plaster walls, plaster
and metal ceilings, and concrete equipment foundations.
a. This includes labor and material costs that are not addressed by other
subaccounts under the 501 account, such as the labor and material
required for installation of bridge and gantry cranes, monorails,
conveyors, and pipe handling trolley assemblies, including related
electrical feed rails, crane rails, internal wiring, erection, and rigging.
Also included are the labor and material required for installation of
miscellaneous building equipment attached to and part of the building,
such as elevators, dumbwaiters, lunchroom equipment, and metal lockers,
etc.
3. Wire: This includes the cost for installing wiring for the equipment.
8. 5018 Mechanical
charged directly. The costs for each size and type of equipment
included in this cost code should be readily identifiable in the cost
code or supporting records.
3. Louvers, Grills, Diffusers, and Registers: This includes the cost for
the complete installation of louvers, grills, diffusers, and registers.
4. Roof Ventilators: This includes the cost for hauling, handling, and
installing roof ventilators.
7. Insulation: This includes the cost for labor and material to install
insulation on environmental control equipment and distribution
systems.
8. Controls: This includes the cost for labor and materials to install all
components of the control system, whether pneumatic or electric.
This cost code includes all control devices, such as thermostats,
relays, valves, valve operator dampers, damper operators, local and
remote indicators, and recorders. It also includes any other devices
used to monitor, record, control, or enunciate conditions and nodes
of the equipment or the supply, return, or exhaust systems.
10. Finishing Filters: This includes the cost for shipping, hauling,
handling, installing, finishing, or polishing filters complete with
frames, filter media, retaining devices, and supports.
DOE G 430.1-1 16-23
03-28-97
11. Piping: This includes the cost for hauling, handling, cutting,
fabricating, placing, and erecting piping for the system together with
related valves, fittings, hangers, expansion joints, and other piping
specialties.
12. Insulation: This includes the cost for handling, hauling, cutting, and
installing insulation for piping.
13. Testing: This includes the cost for preliminary testing of the system,
such as pneumatic or hydraulic pressure testing.
14. Identification: This includes labor and material to label, color code,
tag, or otherwise properly identify the piping system according to
specifications. Painting of pipe and equipment is excluded from this
cost code (see Painting and Glazing).
15. Cleaning: This includes all costs required to clean, condition, and
sterilize the piping system.
17. Excavation and Backfill: This includes all costs of labor and
materials to excavate, shore, pump, or dewater ditches; form,
reinforce, and pour concrete thrust blocks; backfill with any
specified material; compaction of backfill; and repairs to damaged
concrete or asphalt surfaces as required for the installation of a
mechanical system.
9. 5019 Electrical
6. Poles and Fixtures: This includes the cost for hauling, handling, and
complete installation of poles and fixtures. It includes all work
required for the erection of poles, complete with hardware, used
exclusively for the system.
10. Instruments and Panels: This includes the cost for installing all
instruments and panels and the instrumentation connections,
together with related preliminary testing.
11. Switch Panel: This includes the cost for complete installation of
disconnect and switching panels, complete with overload protection
devices, interconnecting busses, etc.
12. Controls: This includes all costs of labor and materials for the
complete installation of all required controls, transfer switches,
protective devices, and similar items.
14. Wire: This includes the cost for installing wire for electric lighting
systems. It also includes wiring for the emergency system to the
lighting panel.
16-26 DOE G 430.1-1
03-28-97
15. Fixtures: This includes the cost for hauling, handling, and complete
installation of all lighting fixtures and related wall switches and
receptacles.
16. Instrument Vacuum Pumps: This includes the cost for installing
instrument vacuum pumps and the instrumentation connections.
18. Tubing: This includes the cost for installing and testing all tubing
for instrumentation.
19. Grounding: This includes the cost for all ground wire, connectors,
grids, etc.
20. Smoke Detectors: This includes the cost for installation of smoke
detection systems, with related wiring, panels, instruments, and
similar items.
21. Alarms: This includes the cost for installation of fire, intrusion, and
radiological alarm systems, with related wiring, panels, instruments,
and similar items.
This code is identical to account 5011 except that it applies to structures other
than buildings.
2. 5502 Concrete
This code is identical to account 5012 except that it applies to structures other
than buildings.
3. 5503 Masonry
DOE G 430.1-1 16-27
03-28-97
This code is identical to account 5013 except that it applies to structures other
than buildings.
4. 5504 Metals
This code is identical to account 5014 except that it applies to structures other
than buildings.
This code is identical to account 5015 except that it applies to structures other
than buildings.
products. It includes primers, backer rods, and bond breaker tape applied
to exterior and interior moving and nonmoving joints to prevent
penetration of moisture, air, and sound. Traffic topping is defined as
surface-applied, waterproof, elastomeric, or composition-type membrane
exposed to weather and suitable for normal or light duty traffic (foot or
automobile), but not intended for heavy industrial use.
1. Materials: This includes the cost for materials used for thermal and
moisture protection.
2. Structural Steel and Iron: This includes the cost for all painting,
insulating, and related work for superstructure and miscellaneous
structural steel and iron items.
3. Code Identification: This includes the cost for all painting and
related work of lettering and code identification and permanent sign
painting.
a. This includes labor and material costs that are not addressed by other
subaccounts under the 550 account, such as labor and materials required
for installation of bridge and gantry cranes, monorails, conveyors, pipe
handling trolley assemblies, including related electrical feed rails, crane
rails, internal wiring, erection, and rigging. Also included are the labor
and materials required for installation of miscellaneous equipment that is
attached to the structure.
DOE G 430.1-1 16-29
03-28-97
8. 5508 Mechanical
This code is identical to account 5018 except that it applies to structures other
than buildings.
9. 5509 Electrical
This code is identical to account 5019 except that it applies to structures other
than buildings.
E. 600 Utilities
This includes the installed cost of all transmission and distribution lines, poles,
towers, grounding systems, substations, transformers, controls, cables,
conduits, services, meters and protective devices, and lighting fixtures, wire,
poles, standards, and related accessories supplying electric service.
This includes the installed cost of equipment necessary for receiving and
transmitting alarms, including control wiring (both cable and open), and other
16-30 DOE G 430.1-1
03-28-97
This includes the installed cost of sewerage treatment and disposal facilities,
including manholes, mains and lateral lines to the point of tie-in with buildings
served, and any septic tanks.
This includes the installed cost of all equipment used for the generation and
distribution of steam to the point of tie-in to buildings where such steam is
utilized primarily for heating and for furnishing power to equipment.
This includes the installed cost of wells, pumping, water treatments, and
distribution facilities to the point of tie-in with buildings served.
This includes the installed cost of pipelines, pipe racks, raceways, valves,
pumps, metering devices, and bulk storage tanks between the oil transporting
vehicle (truck, barge, tanker, or pipeline) and bulk storage tanks of other
piping systems.
This includes the installed cost of utility systems not specifically included
under the 600 account, such as a compressed air system or an anhydrous
hydrogen fluoride gas system.
1. 7010 Vessels
This includes the installed cost of towers, reactors, drums, trays, storage tanks
(not associated with site utilities), cyclones, etc., less the cost of supports or
supporting structures (see 5600).
This includes the installed cost of heat exchangers, heaters, stacks, steam
boilers, furnace cooling towers, ejectors, brazed core exchangers,
desuperheaters and coolers, and refrigeration equipment.
This includes the installed cost of off-the-shelf units that are used in a process
(e.g., gas waste treatment package, clarifier package, desulfurization package,
demineralization, deaerator, incinerator, flare, and odorization package).
This includes the installed cost of process piping to include pipe, pipe racks,
raceways, etc.
6. 7060 Electrical
This includes the installed cost of all process electrical transmission and
distribution equipment not considered a utility system. Costs include wire,
cable, poles, insulators, towers, grounding systems, substations, transformers,
controls, meters, lighting, conduit, piping, distribution fumes, and control
panels.
16-32 DOE G 430.1-1
03-28-97
7. 7065 Instrumentation
This includes the installed cost of reactor support, reactor structure, reactor
internals, reactor control devices, instrumentation and control devices,
monitoring system, leak detection equipment, cooling equipment, makeup
water system, inert gas system, fuel handling tools and equipment, service
platforms, etc.
This includes the cost of improvements made by DOE to land, buildings, structures,
building services, and utility systems not owned by DOE. Plants, laboratories, and
similar facilities constructed by DOE on land owned by others are not to be
classified in this category.
H. 810 Demolition
This includes the cost of wrecking, dismantling, cutting, drilling, and removing
existing structures, equipment, and materials, as well as any excavation required to
facilitate demolition and the cleaning, stacking, loading, hauling, and unloading of
material for salvage and/or disposal when such activity represents a major activity
in accomplishment of the project. Minor, routine demolition will be listed under
improvements to land.
I. 820 Tunneling
J. 830 Drilling
This includes the complete cost of drilling, including purchase or lease of the
drilling rig-associated material mandrels, jet subs, drill collars, drill pipe, kellys,
goosenecks, casing, detergent, mud additives and other chemicals, tool repair,
installing casing (double jointing, lugging, cutting lifting eyes, belling, and
installing guidelines), installing the drilling rig, correcting problems (plugback to
correct well bore deviations), cleaning out and conditioning the hole, coring,
side-wall, sampling, dewatering, fishing, laboratory support, building support
structures, and safety fences.
This includes the cost of heavy, mobile equipment (other than motor vehicles),
such as concrete mixers, power shovels, cranes, compressors, rollers, road
graders, tractors, farm implements, boats, and barges. The cost of trucks is
included in Code 725.
This includes the cost of hospital, clinical, and dental equipment, such as
hospital beds, dentist chairs, instruments, sterilizers, and other scientific
equipment used by dentists and doctors.
This includes the cost of passenger cars, trucks, buses, jeeps, trailers, airplanes,
and fire trucks.
This includes the installed cost of office furniture and equipment, such as
machines, desks, drafting sets, safes, photographic equipment, copy-making
equipment, printing equipment, and other office equipment regardless of
where located. The cost of automatic data processing equipment is included in
Code 770.
This includes the installed cost of railroad rolling stock, such as locomotives
and cars.
This includes the installed cost of man and vehicular portable equipment used
for police, security, and fire protection purposes. The cost of vehicles is in
Code 725, and the cost of installed alarm systems is in Code 621.
This includes the installed cost of shop equipment, such as lathes, drilling
machines, rolling mills, hoists, grinders, forges, pipecutting machines, presses,
saws, shapers, and other equipment usually associated with shops, garages,
and service stations. Similar equipment used in laboratories and other areas
for research purposes should also be identified by this code.
This includes the installed cost of all equipment used in ADP, such as:
This includes the installed cost of furniture and fixtures for hotels, dormitories,
and apartments; laundry equipment; restaurant, cafeteria, and canteen
equipment; and other miscellaneous equipment not includable in other codes.
This includes the cost of topographical and other field surveys, soil tests, load
tests, geological studies, test borings, or other subsurface investigations.
16-36 DOE G 430.1-1
03-28-97
2. Preliminary Work
This includes the cost of preliminary studies, sketches, cost estimates, layout
plans, and reports.
3. Design
4. Consulting Services
6. Expediting or Procurement
7. Inspection
8. Miscellaneous
This includes the cost of items allowable under the contract or amendments
thereto that are not susceptible to classification in any one of the above
accounts. Such items include bonds and insurance, materials, and supplies for
the Architect/Engineer (A/E) contractors’ use; patents; purchase designs and
royalty payments; structures and facilities of a temporary nature used by the
A/E contractor; taxes, fees, and charges levied by public agencies on
personnel; the transportation of personal household goods and effects; losses
DOE G 430.1-1 16-37
03-28-97
not compensated for by insurance; litigation; A/E contractor’s fees; and other
costs specifically certified in writing by the contracting officer according to the
terms of the contract.
1. Administration
This includes salaries, travel, and other expenses for the overall administration
of the project.
2. Superintendence
4. Accounting
This includes salaries, travel, and other expenses for accounting staff,
including accountants, timekeepers, clerks, and their secretaries and
stenographers.
5. Procurement
This includes salaries, travel, and other expenses of personnel responsible for
purchasing and expediting materials, supplies, and equipment except if
chargeable to ED&I.
6. Personnel
16-38 DOE G 430.1-1
03-28-97
This includes salaries, travel, and other expenses of personnel for recruitment,
employment, and employee relations activities.
7. Legal
8. Security
This includes salaries, travel, and other expenses of personnel for security
protection.
C. Other Indirect
1. Payroll Insurance
2. Insurance
This includes the cost of insurance, other than payroll, carried by the
contractor in connection with the construction work and not charged
elsewhere.
This includes the cost of damage settlements not covered by insurance and not
chargeable elsewhere.
4. Payroll Taxes
DOE G 430.1-1 16-39
03-28-97
This includes the cost of contractors’ contributions for social security not
charged elsewhere.
This includes the cost of business and property taxes incurred during the
construction period.
This includes the cost of holiday and vacation pay not charged elsewhere.
This includes the cost of signup and termination pay not charged elsewhere.
8. Retroactive Pay
9. Reporting Time
This includes the cost of time given employees who report for work when no
work is available because of weather or other conditions.
This includes the cost of conducting welding tests at the job site or elsewhere.
This includes the cost of contributions to labor union welfare plans not
charged elsewhere.
This includes the cost of operating a pool of motor vehicles for general,
administrative services. Costs of operating automobiles specifically assigned
to other services are not to be included.
This includes the cost of medical, first aid, and hospital services.
16. Safety
This includes the cost of all safety programs carried on during the course of
the construction contract. Costs of glasses for welding operations, gloves for
linemen, scaffold railing for bricklayers, etc., are trade safety measures and, as
such, are charged to the appropriate cost accounts rather than to this account.
This includes the cost of maintaining and operating general construction plant
facilities not chargeable to other accounts. It includes depreciation on general
Site Improvement, Temporary Land Improvements, General Plant, and
Miscellaneous Equipment.
This includes the cost of small hand tools and of operating the toolroom.
Included are costs of tool boxes, tool shanties, wages of toolroom employees,
and costs of rehandling and sharpening tools. Costs of boots, raincoats, and
other protective clothing issued to workers are included. It does not include
hand tools used in shops. The costs of pneumatic and electric tools larger than
handtools are chargeable to Miscellaneous Equipment.
This includes the cost of supplying drinking water and toilet facilities.
DOE G 430.1-1 16-41 (and 16-42)
03-28-97
22. Heat
This includes the cost of heat that is not chargeable to other accounts.
24. Water
This includes the cost of water that is not chargeable to other accounts.