DC Pre-Monsoon Survey.

1. The letter is addressed to M/s Deshmukh and Company regarding pending rectification works that need to be completed before the monsoon season on the Pimpalgaon – Nashik – Gonde Section of NH-3 highway project in Maharashtra. 2. Some of the key pending works mentioned include the application of thermoplastic paint at certain locations, cleaning of drain spouts that were blocked during overlay works, completion of earthen shoulder works, and other pre-monsoon activities listed in previous letters. 3. Considering the fast approaching monsoon season, M/s Deshmukh and Company is instructed to expedite all outstanding balance works within their scope and complete them before the

Uploaded by

Amol Jadhav
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
296 views2 pages

DC Pre-Monsoon Survey.

1. The letter is addressed to M/s Deshmukh and Company regarding pending rectification works that need to be completed before the monsoon season on the Pimpalgaon – Nashik – Gonde Section of NH-3 highway project in Maharashtra. 2. Some of the key pending works mentioned include the application of thermoplastic paint at certain locations, cleaning of drain spouts that were blocked during overlay works, completion of earthen shoulder works, and other pre-monsoon activities listed in previous letters. 3. Considering the fast approaching monsoon season, M/s Deshmukh and Company is instructed to expedite all outstanding balance works within their scope and complete them before the

Uploaded by

Amol Jadhav
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

To,

M/s Deshmukh and Company


Surli Road, At post- Tembhurni,
Tal-Madha, Solapur-413211, Maharashtra (India)

Subject: - NHAI-PIU-NSK- Six Laning of Pimpalgaon – Nashik – Gonde Section of NH-3 from km
421.000 to km 440.000 in the state of Maharashtra – Authority Engineer / Supervision
Consultant Services for PR works & O&M Works on Pimpalgaon – Nashik – Gonde Project
of NH-3 in the state of Maharashtra –
Ref: -1. Our Letter No. TPF/D&C/PR-I/2018-2019/10 dated on 15/06/2019

Dear Sir,
This is in reference to above reference letters wherein you have been directed to rectify the defects
within your scope of work. Looking towards the forthcoming monsoon it is utmost necessary to carry
out the rectification works at the earliest which are summarized as follows:
1. Providing and marking of thermoplastic paint at certain location is still pending from your side.
Considering the fast approaching monsoon season once again you are hereby advice to complete
the balance work at the earliest.
2. During the overlaying works, bituminous material was dumped in the drain spout and as per your
report submitted via mail dated 30/04/2020, you have claimed to complete the drain spout cleaning
work..the AE is of strong opinion that the silt or dust must have penetrated into the pipeline thus
choking it and hence demonstration of free flow of water through the drain spouts is a must.
3. At certain location it was observed that execution of earthen shoulder still pending from your end
looking towards the safety of road user it is utmost necessary to complete the balance work
before the monsoon.
4. In addition to the above, in reference to PD-NHAI letter no 961 dated 25/05/2020 regarding the
debris/left out bituminous material, broken shoulder edges, boulders on shoulder, kerb painting
etc. needs to be expedite for safety of road user.
5. The other pre-monsoon activities as mention at PD-PIU-NHAI letter no 961 dated 25/05/2020
needs to be planned/expedite without any fail
In view of the above & looking towards the time constraint as the monsoon may commence you
are hereby instructed to expedite the balance work within your scope & BOQ items at earliest before
the monsoon.

Thanking You,
Yours Sincerely,
For TPF GETINSA – EUROESTUDIOS S.L. in JV with TPF Engineering Pvt. Ltd.
Pankaj Mohabey
(Team Leader)
C/c: 1. The Project Director, NHAI, PIU Nashik - For Information and record.
2. TPFEPL Head Office - For Information and record.