0% found this document useful (1 vote)
196 views2 pages

Detailed Estimation For Construction of Proposed Building: 27, Navarathinanagar, BPL Complex Karaikudi - 630 001

The document provides a detailed estimation for the construction of a proposed building including items like brickwork, plastering, sand filling, tile work, surki concrete terrace, and miscellaneous expenses. It lists each construction item, the dimensions, volume or area, rate per cubic foot or square foot, total amount, total area of the building, and rate per square foot. The quoted rate for the construction is 90 rupees per square foot.

Uploaded by

ganesh15
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (1 vote)
196 views2 pages

Detailed Estimation For Construction of Proposed Building: 27, Navarathinanagar, BPL Complex Karaikudi - 630 001

The document provides a detailed estimation for the construction of a proposed building including items like brickwork, plastering, sand filling, tile work, surki concrete terrace, and miscellaneous expenses. It lists each construction item, the dimensions, volume or area, rate per cubic foot or square foot, total amount, total area of the building, and rate per square foot. The quoted rate for the construction is 90 rupees per square foot.

Uploaded by

ganesh15
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

27, Navarathinanagar, BPL Complex

Karaikudi – 630 001.

Detailed Estimation for construction of proposed building

Sl. Dimensions Volume Area Rate per Total


Item of work Nos
No L B D Cub. Ft Sq. ft cub.ft sq. ft Amount

1 Brickwork
(i) Laying of brick for plinth
1 300 8 inch 4 inch 67
beam
(i) basement 1 300 5 9 inch 1125
1192 25 29800
2 Plastering work
(i) plastering work in
1 500 5 2500
basement (inside and
2500 8 20000
3 sand filling
(i) Column trench 14 33 inch39 inch 5 625
(ii) basement 1 48 25 4 4800
5425 5 27125
4 Tile work
(i) Floor tiles
(a) Ground floor 1 1300 sq.ft 1300
(b) First floor 1 1300 sq. ft 1300
(c) Roof tiles 1 1200 sq ft 1200
(ii) Wall tiles
(a) Kitchen 2 31 4 250
(b) Bathroom 4 34 7 952
5000 20 100000
5 surki concrete
terrace 1 1200 sq ft 1200 40 48000
6 Miscellaneous expenses
(i) brick work, plastering
15 days duration 500 per day
and sand filling 7500
(ii) tile working 15 days duration 500 per day 7500
(iii) surki concrete 5 days duration 500 per day 2500
(iv) Equipment and
Miscellaneous 6000
machinery rent
TOTAL COST 248425
TOTAL AREA 2700 sq.ft
RATE PER SQ.FT 92
Sl. Dimensions Volume Area Rate per Total
Item of work Nos
No L B D Cub. Ft Sq. ft cub.ft sq. ft Amount

QUOTED RATE 90 / sq.ft