Keelayur Contract Modified

This document is a proposal from Seven Hills Construction Company to a customer for construction of a 2-story building measuring approximately 1350 square feet. The total cost quoted is Rs. 135 per square foot including construction of columns, foundation, beams, roof slab, staircase, low roof, and loft. Additional costs include Rs. 5000 if the customer does not excavate foundation trenches, and 18% GST on the total amount. Expenditure rates for additional work are also provided.

Uploaded by

ganesh15
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
44 views1 page

Keelayur Contract Modified

This document is a proposal from Seven Hills Construction Company to a customer for construction of a 2-story building measuring approximately 1350 square feet. The total cost quoted is Rs. 135 per square foot including construction of columns, foundation, beams, roof slab, staircase, low roof, and loft. Additional costs include Rs. 5000 if the customer does not excavate foundation trenches, and 18% GST on the total amount. Expenditure rates for additional work are also provided.

Uploaded by

ganesh15
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

27, Navarathinanagar, BPL Complex

Karaikudi – 630 001.


9698773339, 9976008582

Dear sir/madam
Greetings!
With respect to discussion made on 28.08.2020 and detailed study of your proposed project
plan, we are revised our contract work and cost. Herewith we attached the details of our work with
dimensions and cost for your kind reference. For any further clarification please contact
9698773339, 9976008582.
Construction of 2 storied (G+1) building measuring about approx. 1350 square feet plinth area
We quote the total cost including centering, bar bending, pouring of concrete, transportation
of equipments, loft and low roof area will be Rs. 135 per square feet. The details of work as
follows

Sl.
Items of work Nos Remarks
No
1 Columns 14 Any dimensions as per project owner design norms
Foundation
2 14 Any dimensions as per project owner design norms
concrete

3 Earth beam - Size – 1 ½ x 9” up to a maximum length of 300 ft

4 Lintel beam Size – 1 x 8” up to a maximum length of 500 ft


5 Roof slab Area 2700 sq.ft of required thickness depends upon owner design norms
6 Staircase Any dimensions depends upon owner design norms
7 Low roof Maximum area of 250sq.ft
Any dimensions as per project owner design norms up to a maximum
8 loft
length of 70ft

Note :
1. Foundation trenches should be made by owner of the project. Otherwise additional amount
of Rs. 5000 will be charged
2. GST of 18% will be added in gross amount.

Expenditure rate for additional work


Sl. Items of work Rate per quantity
No
1 Columns Rs. 40 per ft height
2 Earth beam Rs. 80 per ft length
3 Lintel beam Rs. 50 per ft length
4 Roof slab Rs. 30 per sq. ft
5 Staircase NIL
6 Low roof Rs. 15 per sq.ft
7 Loft Rs. 30 per sq.ft

Thanks with Regards


Seven Hills Construction Company