Milestone Schedule

This document outlines the project schedule for the Ascendas STP Revamping project in Chennai, India. It details 22 tasks to be completed from October 2020 through February 2021, including design and engineering, civil works like area cleaning and construction, procurement, inspection, erection and commissioning. Key milestones include receipt of purchase order, proforma invoice, basic and detailed engineering, civil construction works, equipment purchase, inspection and dispatch, mechanical and electrical erection and commissioning. The overall project timeline runs from October 2020 through February 2021.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
116 views1 page

Milestone Schedule

This document outlines the project schedule for the Ascendas STP Revamping project in Chennai, India. It details 22 tasks to be completed from October 2020 through February 2021, including design and engineering, civil works like area cleaning and construction, procurement, inspection, erection and commissioning. Key milestones include receipt of purchase order, proforma invoice, basic and detailed engineering, civil construction works, equipment purchase, inspection and dispatch, mechanical and electrical erection and commissioning. The overall project timeline runs from October 2020 through February 2021.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

PROJECT SCHEDULE Ascendas STP Revamping ,Chennai

ID Task Mode Task Name 01 October 11 October 21 October 01 November 11 November 21 November 01 December 11 December 21 December 01 January 11 January 21 January 01 February 11 February 21 February 01 March
WT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S S MTWT F S S MTWT F S SMTWT F S SMTWT F S SM
1

2 OVERALL PROJECT TIMELINE

3 Receipt of PO

4 Proforma Invoice for Mobilization


advance

6 DESIGN & ENGINEERING

7 Basic Engineering

8 Detailed Engineering

9 CIVIL WORKS

10 Area cleaning and marking

11 Civil construction works

12 Sewage inlet pipe line laying with


inspection chambers.

13 PROCUREMENT

14 Mechanical equipment

15 Electrical equipment purchase

16 INSPECTION & DESPATCH

17 ERECTION & COMMISSIONING

18 Mechanical

19 Electrical

20 Precommissioning

21 Commissioning

22

23

24

25

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: PROJECT SCHEDULE AS
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Fri 04-09-20
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Aqua Matrix System Pvt Ltd Page 1