PROJECT SCHEDULE Ascendas STP Revamping ,Chennai
ID Task Mode Task Name 01 October 11 October 21 October 01 November 11 November 21 November 01 December 11 December 21 December 01 January 11 January 21 January 01 February 11 February 21 February 01 March
WT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S S MTWT F S S MTWT F S SMTWT F S SMTWT F S SM
1
2 OVERALL PROJECT TIMELINE
3 Receipt of PO
4 Proforma Invoice for Mobilization
advance
6 DESIGN & ENGINEERING
7 Basic Engineering
8 Detailed Engineering
9 CIVIL WORKS
10 Area cleaning and marking
11 Civil construction works
12 Sewage inlet pipe line laying with
inspection chambers.
13 PROCUREMENT
14 Mechanical equipment
15 Electrical equipment purchase
16 INSPECTION & DESPATCH
17 ERECTION & COMMISSIONING
18 Mechanical
19 Electrical
20 Precommissioning
21 Commissioning
22
23
24
25
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: PROJECT SCHEDULE AS
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Fri 04-09-20
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Aqua Matrix System Pvt Ltd Page 1