Customer : Saudi Electricity Company(EOA) JMC- 14
Contract : Construction of 380kV D/C OHTL interconnected to Dharan South, New Dharan Central and DHO BSP
Portion XI - 380kv D/C OHTL b/w Dhahran Home Ownership BSP - Dhahran South BSP Trans. Yard
Contract No. 4400008460
Contractor : AL SHARIF GROUP & KEC LTD CO
Foundation Works - Portion XI
Contract Work Done
Item No. ITEM DESCRIPTION Qty Total Cum.
UNIT Cont Qty Previous Present Balance
(VO) QTY. Total
3.11.19.9 Demolishing Foundation
3.11.19.9.1 S1N (set) Set 0 2 2.00 0 1.00 1.00 1.00
3.11.19.9.2 TA3N (set) Set 0 3 3 0.0 2 2.0 1.00
3.11.19.9.3 DE (set) Set 0 1 1 0.00 1.000 1.00 -
Construction of Foundations for Latticed Steel
3.11.19.12
Towers (Including Materials)
3.11.19.12.1 TA1N (set) Set 0 3 3 0 2 2 1.00
3.11.19.12.2 TA2N (set) Set 0 1 1 0 0 0 1.00
3.11.19.12.3 TA3N (set) Set 0 4 4 0 3 3 1.00
3.11.19.1 Stub Angles
3.11.19.1.1 TA1N (set) Set 0 3 3 0 2 2 1
3.11.19.1.2 TA2N (set) Set 0 1 1 0 0 0 1.00
3.11.19.1.3 TA3N (set) Set 0 4 4 0 3 3 1.00
Construction of Foundations for Latticed Steel
3.11.20.
Towers (Including Materials)
3.11.20.1 S1N (set) Set 35 0 35 34 1 35 -
3.11.20.3 TA2N (set) Set 2 0 2 1 0 1 1.00
3.11.20.9 TA3N/SP (Set) Set 3 1 4 2 1 3 -
3.11.1 Stub Angles
3.11.1.1 S1N (set) Set 35 0 35 34 1 35 -
3.11.1.3 TA2N (set) Set 2 0 2 1 0 1 1.00
3.11.1.5 Dead end DE (set) Set 7 0 7 6 0 6 1.00
3.11.1.9 TA3N/SP (Set) Set 3 1 4 2 1 3 -
Insulator Assembly including Hardware &
3.11.3
accessiories
3.11.3.1 S1N (set) Set 35 0 35 9 0 9 26
3.11.3.2 TA1N (set) Set 6 0 6 2 0 2 4
3.11.3.3 TA2N (set) Set 2 0 2 1 0 1 1
3.11.3.4 TA3N (set) Set 7 0 7 1 1 2 5
3.11.3.5 Dead end DE (set) Set 7 0 7 1 0 1 6
3.11.3.9 SP-TA3N (set) Set 3 0 3 0 1 1 2
4X1080.6 kcmil ACAR
3.11.4 KM 121 0 121 31.44 3.77 35.20 85.80
conductor per phase
Optical Overhead Ground Wire
3.11.5 (OPGW) including Hardware & KM 40 0 40 0.00 7.40 7.40 32.60
accessories
Underground Non-Metallic
3.11.6 M 2000 0 2000 0.00 0.00 0.00 2,000.00
Fiber Optic Cables
Optical Fiber Management
3.11.7 EA 2 0 2 0.00 0.00 0.00 2
Rack with necessary FSTPRM
3.11.8 Fiber Optic Joint Boxes
3.11.8.1 OPGW-OPGW EA 8 0 8 0 0.000 0 8.00
3.11.8.2 OPGW-U/G NFOC EA 4 0 4 0 0.000 0 4.00
3.11.9 Armor Grip Suspension Units EA 840 0 840 216 0 216 624
Compression Deadend Clamps
3.11.11 and fittings for conductor and LT 1 0 1 0.100 0.160 0.260 0.740
OPGW
Spacer Dampers for Main
3.11.13 EA 3254 0 3254 624 82 706 2,548
Conductors
3.11.14 Vibration Dampers for OPGW EA 356 0 356 0 84 84 272
The Construction done is inline and as per the SEC standards
AL SHARIF GROUP & KEC LTD CO SEC Consultant SEC-EOA
Proj.Engineer/Manager Project Engineer/Manager Project Engineer/Manager
Saudi Electricity Company
Construction of 380kV D/C OHTL interconnected to Dharan South,
New Dharan Central and DHO BSP - CONTRACT NO. 4400008460
Portion XI - 380kv D/C OHTL b/w Dhahran Home Ownership BSP - Dhahran South BSP Trans. Yard
1 st Stage Foundation Completed Locations details
Sl.No. Tower No. Tower Type Date RFI
1 T#10 SP-TA3N 9/4/2019 ASKEC-M707-A-PXI-Civil 325
2 T#11 TA3N 31/3/19 ASKEC-M707-A-PXI-Civil 323
332
3 T#13 DE 13/6/19 ASKEC-M707-A-PXI-Civil
4 T#27 TA3N 2/3/2019 ASKEC-M707-A-PXI-Civil 292, 293,289, 290
5 T#28 (Old) TA3N 26/7/17 ASKEC-M707-A-PXI-Civil 183, 184
6 T#29 (Old) S1N 19/7/17 ASKEC-M707-A-PXI-Civil 165, 166
329
7 T#34 TA1N 11/6/2019 ASKEC-M707-A-PXI-Civil
Total numbers of completed locations:-7 Nos.
2nd Stage Foundation Completed Locations details
Sl.No. Tower No. Tower Type Date RFI
326
1 T#10 SP-TA3N 11/4/2019 ASKEC-M707-A-PXI-Civil
2 T#11 TA3N 29/4/19 ASKEC-M707-A-PXI-Civil 327
3 T#13 DE 16/6/19 ASKEC-M707-A-PXI-Civil 333
4 T#27 TA3N 26/3/19 ASKEC-M707-A-PXI-Civil 324
5 T#28 (Old) TA3N 5/8/2017 ASKEC-M707-A-PXI-Civil 199R1, 200R1
6 T#29 (Old) S1N 22/7/17 ASKEC-M707-A-PXI-Civil 169, 170
7 T#34 TA1N 15/6/19 ASKEC-M707-A-PXI-Civil 334
Total numbers of completed locations:- 7 Nos.
Demolishing Foundation
Sl.No. Tower No. Tower Type Date RFI
1 T#10 TA3N 24/8/2018 ASKEC-M707-A-PXI-Civil 339
2 T#11 DE 24/8/2018 ASKEC-M707-A-PXI-Civil 339
3 T#28 TA3N 24/8/2018 ASKEC-M707-A-PXI-Civil 339
339
4 T#29 S1N 24/8/2018 ASKEC-M707-A-PXI-Civil
Total numbers of completed locations:- 4 Nos.
(All Work has been done as per SEC Standards)
AL-Shariff Group & KEC Ltd SEC Consultant
Name:- Rishikesh V Pawar Name:-
Signature:- Signature:-
Date:- 5/12/2020 Date:-
Page 2 of 6
Saudi Electricity Company
Construction of 380kV D/C OHTL interconnected to Dharan South,
New Dharan Central and DHO BSP - CONTRACT NO. 4400008460
Portion XI - 380kv D/C OHTL b/w Dhahran Home Ownership BSP - Dhahran South BSP Trans. Yard
ACAR Conductor Pulling
Sl.No. Section Phase Span per phase (m) RFI
628.29 ASKEC-M707-PXI-ELE- 32
1 Circuit-1, Top
628.29 ASKEC-M707-PXI-ELE- 32
2 Circuit-1, Middle
628.29 ASKEC-M707-PXI-ELE- 32
3 Circuit-1, Bottom
T#27 to 29
628.29 ASKEC-M707-PXI-ELE- 32
4 Circuit-2, Top
628.29 ASKEC-M707-PXI-ELE- 32
5 Circuit-2, Middle
628.29 ASKEC-M707-PXI-ELE- 32
6 Circuit-2, Bottom
3769.74 m
Total Length of ACAR conductor is 3.768 km
OPGW Pulling
Sl.No. Section Phase Span per phase (m) RFI
3698.97 ASKEC-M707-PXI-ELE- 35
1 Circuit-1
T#12 to 24
3698.97 ASKEC-M707-PXI-ELE- 35
2 Circuit-2
Total Length of OPGW is 7.398 km
AL-Shariff Group & KEC Ltd SEC Consultant
Name:- Rishikesh V Pawar Name:-
Signature:- Signature:-
Date:- 12/5/2020 Date:-
Saudi Electricity Company
Construction of 380kV D/C OHTL interconnected to Dharan South,
New Dharan Central and DHO BSP - CONTRACT NO. 4400008460
Portion XI - 380kv D/C OHTL b/w Dhahran Home Ownership BSP - Dhahran South BSP Trans. Yard
Insulator Assembly and Hoisting Details
Sl.No. Tower No. Tower Type Date RFI
1 27 TA3N 6/2/2020 ASKEC-M707-PXI-ELE- 33
2 28 SP-TA3N 6/2/2020 ASKEC-M707-PXI-ELE- 33
Total numbers of completed locations:- 2 Nos.
Compression Deadend Clamps and fittings for conductor and OPGW
Sl.No. Tower No. Tower Type Date RFI
Conductor Compression Deadend
1 27 TA3N 6/2/2020 ASKEC-M707-PXI-ELE- 33
2 28 SP-TA3N 6/2/2020 ASKEC-M707-PXI-ELE- 33
Sl.No. Tower No. Tower Type Date RFI
OPGW Compression Deadend
1 12 DE 26/11/2019 ASKEC-M707-PXI-ELE- 36
2 13 DE 26/11/2019 ASKEC-M707-PXI-ELE- 36
3 14 TA3N 26/11/2019 ASKEC-M707-PXI-ELE- 36
4 21 TA2N 26/11/2019 ASKEC-M707-PXI-ELE- 36
5 22 TA1N 26/11/2019 ASKEC-M707-PXI-ELE- 36
6 23 TA1N 26/11/2019 ASKEC-M707-PXI-ELE- 36
Total numbers of completed locations:- 0.16 Lot
(All Work has been done as per SEC Standards)
AL-Shariff Group & KEC Ltd SEC Consultant
Name:- Rishikesh V Pawar Name:-
Signature:- Signature:-
Date:- 12/5/2020 Date:-
Page 4 of 6
Saudi Electricity Company
Construction of 380kV D/C OHTL interconnected to Dharan South,
New Dharan Central and DHO BSP - CONTRACT NO. 4400008460
Portion XI - 380kv D/C OHTL b/w Dhahran Home Ownership BSP - Dhahran South BSP Trans. Yard
Installation of Conductor Spacer Dampers
Phase
Sl.No. Span Circuit 1 Circuit 2 Total RFI
Top Middle Bottom Top Middle Bottom
1 T#27 to T#28 372.33 7.00 7.00 7.00 7.00 7.00 7.00 42.00 ASKEC-M707-PXI-ELE- 34
2 T#28 to T#29 255.97 5.00 7.00 7.00 7.00 7.00 7.00 40.00 ASKEC-M707-PXI-ELE- 34
Total No. of spacer dampers installed is 82.00
Installation of Vibration Dampers
Phase
Sl.No. Span Total RFI
Circuit 1 Circuit 2
1 T#12 to T#13 155.14 3.00 3.00 6.00 ASKEC-M707-PXI-ELE- 37
2 T#13 to T#14 263.84 3.00 3.00 6.00 ASKEC-M707-PXI-ELE- 37
3 T#14 to T#15 388.00 4.00 4.00 8.00 ASKEC-M707-PXI-ELE- 37
4 T#15 to T#16 389.00 4.00 4.00 8.00 ASKEC-M707-PXI-ELE- 37
5 T#16 to T#17 374.00 4.00 4.00 8.00 ASKEC-M707-PXI-ELE- 37
6 T#17 to T#18 302.01 4.00 4.00 8.00 ASKEC-M707-PXI-ELE- 37
7 T#18 to T#19 337.00 4.00 4.00 8.00 ASKEC-M707-PXI-ELE- 37
8 T#19 to T#20 353.86 4.00 4.00 8.00 ASKEC-M707-PXI-ELE- 37
9 T#20 to T#21 272.74 3.00 3.00 6.00 ASKEC-M707-PXI-ELE- 37
10 T#21 to T#22 293.86 3.00 3.00 6.00 ASKEC-M707-PXI-ELE- 37
11 T#22 to T#23 288.43 3.00 3.00 6.00 ASKEC-M707-PXI-ELE- 37
Installation of Conductor Spacer Dampers
Phase
Sl.No. Span Total RFI
12 T#23 to T#24 281.11 3.00 3.00 6.00 ASKEC-M707-PXI-ELE- 37
Total No. of spacer dampers installed is 84.00
AL-Shariff Group & KEC Ltd SEC Consultant
Name:- Rishikesh V Pawar Name:-
Signature:- Signature:-
Date:- 12/5/2020 Date:-