Approval
Project manager
0        November ‘17   Initially                Dan Pîrvulescu   Florinel Petrilă   Gheorghe Ţăranu
                        NO. DOCUMENT
REV.     DATE                                    DESIGNED         CHECKED            APPROVED
                        DESCRIPTION
Revision Sheet
 CUSTOMER:
MINISTRY OF ELECTRICITY (MOE)
REPUBLIC OF IRAQ
    PROJECT :
IFB no. M21-21-2016
Rehabilitation of Unit 3
Facilities and Common System, Al Mussaib Thermal Power Plant Rehabilitation
CONTRACTOR:
                        BLACK SEA TECHNOCHIM CO SRL
DESIGNED BY             DATE
Dan Pîrvulescu          November ‘17
CHECKED BY              DATE           TITLE:
                                       THE PROCEDURE FOR DISMANTLING OLD MCC PANELS
Florinel Petrilă        November ‘17   AND MOUNTING NEW MCC PANEL
APPROVED BY             DATE
Gheorghe Ţăranu         November ‘17
Contract No.            DOCUMENT NUMBER                                 REV.NO.
IFB no. M-21-2016          XXXXXXXXX                                    0
TABLE OF CONTENTS
1. SCOPE .................................................................................................................. 3
2. DOMAIN ................................................................................................................ 3
3. TERMS, DEFINITIONS AND ABBREVIATIONS................................................. 3
4. REFERENCE DOCUMENTS................................................................................ 3
5. RESPONSIBILITIES ............................................................................................. 3
6. PROCEDURE ....................................................................................................... 4
  6.1         Preparatory operations ............................................................................................... 4
  6.2         Making measurements ................................................................................................ 4
  6.3         Command-control cabinets test ................................................................................. 4
  6.4         Checking Projection Cabinets .................................................................................... 4
7. ACCEPTANCE CRITERIA ................................................................................... 5
8. REPORTS AND REGISTERS .............................................................................. 5
                                                                                                                                2|5
       1. SCOPE
       This procedure establishes checks and verification methods that are performed on cabinets
and electrical panels.
       2. DOMAIN
        This procedure applies to checks and tests of control cabinets and control panels and
protection.
       3. TERMS, DEFINITIONS AND ABBREVIATIONS
       According to MC-PRAM-ELC
       4. REFERENCE DOCUMENTS
      At the latest applicable revision
          Document type                                      Documents
       International         4.1 ISO 9001:2015 – Quality management systems. Requirements.
       Standards             4.2 ISO 14001:2015 – Environment management systems. Requirements with
                             user guide.
                             4.3 OHSAS 18001:2007 - OH&S Management Systems. Requirements.
                             4.4 ISO / TR 10013:2006 - Guidelines for quality management system‘s
                             documentation.
                             4.5 Purchase contract.
      NOTE: The user’s responsibility is to ensure that it is using the valid editions of the
      documents, by reading the reference list of the documents.
       5. RESPONSIBILITIES
                                                Position / Competence
       5.1. PRAM laboratory supervisor
       5.1.1. Shall ensure that electrical checks are carried out by qualified, authorized and trained personnel
       for the specifics of these works.
       5.1.2. Shall ensure the equipping of PRAM teams with the necessary equipment and devices as well
       as with metrological measuring devices.
       5.1.3. Check and approve Electric Checks Records.
       5.2. PRAM team supervisor
       5.2.1. Instructs PRAM members to work under the Specific Safety and Health Regulations applicable to
       the work and the project and operations to be performed.
       5.2.2. Prepare a Work Authorization where necessary, coordinate and supervise a team member for
       the duration of the work.
       5.2.3. Draw Verification Records with Measurement Results
       5.3 PRAM personnel
       5.3.1. It appropriates and complies with the provisions of this procedure.
                                                                                                                   3|5
       5.3.2. Perform measurements in accordance with the Specific Wiring Instructions, applicable Norms
       and Specific Instruction Guidelines.
       5.3.3. He / she understands and complies with the Specific Work Safety and PSI Norms applicable to
       the work.
       5.3.4. Uses metrology devices only.
       6. PROCEDURE
       6.1       Preparatory operations
       6.1.1. Preparation of appliances, devices, cords, sources of power required for Checks at
the established Cabinets / Panels.
       6.1.2. Identify and isolate the work area.
       6.1.3. Dust or dirt cleaning of electrical components as well as cable clamps.
       6.1.4. Determining the order execution of the measurements.
       6.2     Making measurements
       6.2.1. The types of measurements required depend on the type and destination of cabinets
or paintings. When performing the measurements, the requirements of the Equipment Factory
Instructions and then those set out in PE 116/94 shall be met first.
      6.3      Command-control cabinets test
      6.3.1. On the control cabinets / panels the following measurements and checks are made:
             a) Measurement of the insulation resistance of the AC and / or DC supply circuits is
                done with a 500 V megohmmeter (at least) on each phase with respect to the
                mass, as well as between the phases;
             b) The insulation resistance of the secondary circuits is measured with the 1000 V
                megohmmeter and the minimum value at the PIF must be 5 MΩ;
             c) Checking the phasing of the voltage circuits is done with a phasmerer and it is
                observed that the phases are in a correct sequence (R, S, T) in accordance with
                the source from where they leave;
             d) Check the polarity of the DC circuits with a DC tester, checking that they are not
                reversed (+) with (-);
             e) Verification of current flows is done with a Ditz Pliers. by priming or secondary
                current injection and measuring each current circuit in the Panel;
             f) Local and remote command checks are made with operative voltage fed by
                preference from an independent, temporary source;
             g) Check local and remote signaling is done simultaneously with order verification;
             h) Checking the lighting circuits inside the cabinet is done with a voltage tester for
                the socket and lamp;
             i) Checking the heating circuits refers to the operation of the heating resistance of
                the cabinet as well as the thermostat;
             j) Verification of earthing circuits refers to checking the continuity at the ground in all
                the metal parts of the cabinet.
      6.4     Checking Projection Cabinets
      6.4.1. Protective cabinets are subject to the following checks:
             a) Measurement of insulation resistance of supply circuits, ca. and / or c.c. is done
                as in command-control cabinets;
                                                                                                            4|5
             b) Measuring the polarity of the operational current circuits is done as in control-
                command cabinets;
             c) Verification of current flows is done as in command-control cabinets;
             d) Checking the protection circuits is done only by identifying the threads with a
                tester;
             e) Checking the protection relays is only done by an authorized company that has
                the necessary verification equipment; Their verification bulletins are valid for PIF;
             f) Verification of the lighting and heating cabinet, as well as control-cabinets;
             g) Verification of earthing circuits is done as in control-cabinets.
       7. ACCEPTANCE CRITERIA
        7.1. The measured values will be passed to the Testing Bulletins by the Team Set, which
will then be forwarded to the Head of the PRAM Laboratory.
        7.2. The head of the PRAM Laboratory will compare the measured values with the
reference values and establish the conclusion in Verification Report (V.R.) if the cable can be
energized.
       8. REPORTS AND REGISTERS
      8.1.   Verification Checklist command-control / protection panel - FORM-ELC-057.
                                                                                               5|5
                               COMMAND PANEL - CONTROL / PROTECTION                        Page
                                      VERIFICATION REPORT
                                                                                           from
                                           No.                      Date
NOMINAL DATA
    Cabinet                   Serial                    Manufacturing year       Manufacturer        U
     T y pe                  Number                                                                  N
                                                                                (
                                                                                k
                                                                                V
The results were obtained at ambient temperature …………. ℃ and humidity ………….. %. )
        1. MEASUREMENT   OF ELECTRICAL PARAMETERS
                    Insulation Resistance
        Circuits           Insulation Resistance    Enhanced voltage test           Insulation
                                    M𝛀)                 ( kV) (min)            Resistance after V>
  Power Supply
  Secondary Circuit
      2. FUNCTIONAL TESTS
  Cr.             Tests                                   Conclusions              Remarks
  No.
   1     Identification of circuits
   2     Phase power circuits
   3     Polarity current circuits
   4     Circulation current
   5     Local and remote command
   6     Local and remote signaling
   7     Heating panels in the cabinet
   8     Indoor lighting circuits
   9     Grounding circuits
        3. FUNCTIONAL TESTS
  Cr.          Name              Type          Serial      Precisio        No.         Valid until
  No.                                         number       n class Verification Report   date:
   1
   2
   3
CONCLUSIONS: From the point of view of the tests carried out according to the Norm PE 116/94,
            The verified cable does not / correspond and cannot / be energized.
                   EXECUTING WORK                                            VERIFIED
NAME:
SIGNATURE:
DATE:
FORM-ELC-057, revision 1