Design of RCC Bridge Bagmati River Sankhamul, Kathmandu-Lalitpur
Design of RCC Bridge Bagmati River Sankhamul, Kathmandu-Lalitpur
Institute of Engineering
Himalaya College of Engineering,
Chyasal, Lalitpur
DEPARTMENT OF CIVIL ENGINEERING
Final Project report on
Supervisor
DR. BHARAT MANDAL
Prepared by
AJAY KUMAR MEHTA (071/BCE/02)
ASHMIN PARAJULI (071/BCE/12)
BHAGWAN SHRESTHA (071/BCE/18)
KUSHAL ACHARYA (071/BCE/40)
August, 2018
Tribhuwan University
Institute of Engineering
Himalaya College of Engineering,
Chyasal, Lalitpur
This is to certify that the final year project entitled “DESIGN OF RCC BRIDGE
OVER BAGMATI RIVER, SANKHAMUL, KATHMANDU- LALITPUR” was
submitted to the DEPARTMENT OF CIVIL ENGINEERING in the partial
fulfillment of requirement for the degree of Bachelor in Civil Engineering. The
project was carried under special supervision and within the time frame prescribed by
the syllabus.
…………………..
Dr. Bharat Mandal
Project supervisor
………….…. …………………
Er. Md. Abrar Alam Dr. Rajan Suwal
Project Co-Ordinator External Examiner
…………
Er. Hari Lal Kharel
Head of Department
Department of Civil Engineering
ACKNOWLEDGEMENT
We would like to express deep gratitude to everybody who helped us to complete our
final year project on topic Design of RC Bridge. Without the immense support of you
all, the completion of project in this short frame of time would not have been possible.
To begin with, we would like to thank our college Himalaya College of Engineering
and our project coordinator Er. Md. Abrar Alam sir for giving us this opportunity to
carry out the final year project on this topic. We would like to specially thank our
project supervisor Dr. Bharat Mandal sir for guiding us throughout our work and
helping us to complete our project in time. We would also like to thank our Principal ,
Er. Madan Sharma sir and our Head of Department Er. Hari Lal Kharel sir for their
continuous support throughout the project. Lastly, we would like to thank all our
friends and family for their immense support and help for completion of this project.
CONTENTS
SALIENT FEATURES ................................................................................................... i
1. INTRODUCTION ..................................................................................................... 1
1.1 Background .......................................................................................................... 1
1.2 Objectives ............................................................................................................. 2
1.3 Scope of Work & Limitations .............................................................................. 2
2. METHODOLOGY .................................................................................................... 3
2.1 Acquisition of data ............................................................................................... 3
2.2 Loading IRC loads for the bridge design: ............................................................ 5
2.3 Superstructure....................................................................................................... 6
2.4 Idealization and Analysis of bridge structure ....................................................... 8
2.4.1 Influence Line Diagram ................................................................................. 8
2.4.2 Design of Deck Slab ...................................................................................... 9
2.4.3 Design of T- Girder ..................................................................................... 13
2.5 Selection of bridge and its components.............................................................. 15
2.6 Method of Design of Bridge............................................................................... 15
3. TOPOGRAPHICAL SURVEY ............................................................................... 16
4. HYDROLOGICAL STUDY ................................................................................... 18
4.1 Catchment Area .................................................................................................. 18
4.2 Hydrological Data .............................................................................................. 19
4.3 Selection of Discharge of River ......................................................................... 23
4.4. Linear Waterway: .............................................................................................. 27
4.5 Contracted water way ......................................................................................... 27
4.6 Scour Depth ........................................................................................................ 27
5. GEOTECHNICAL INVESTIGATION ................................................................... 29
BIBLIOGRAPHY ........................................................................................................ 31
CODES/STANDARDS ............................................................................................... 32
Apendix 1: DESIGN OF SUPERSTRUCTURE ......................................................... 33
Analysis and Design of Deck Slab ........................................................................... 34
Analysis and Design of Cantilever Slab ................................................................... 62
Analysis and Design of Longitudinal Girder ........................................................... 65
Analysis and Design of Cross Girder ....................................................................... 77
Apendix 2: DESIGN OF SUBSTRUCTURE .............................................................. 81
Analysis and Design of Bearing ............................................................................... 82
Analysis and Design of Abutment ........................................................................... 90
Analysis and Design of Pier and Pier Foundation ................................................... 99
Apendix 3: ESTIMATION OF QUANTITY ............................................................ 117
SITE PHOTOGRAPH ............................................................................................... 120
Apendix 4: DRAWINGS AND DETAILING ........................................................... 123
Sheet 01: TOPOGRAPHIC MAP OF THE BRIDGE SITE
Sheet 02: LONGITUDINAL SECTION OF THE BRIDGE SITE
Sheet 03: PLAN AND ELEVATION OF BRIDGE
Sheet 04: PLAN AND SECTION OF BRIDGE DECK
Sheet 05:TOP REINFORCEMENT DETAILING OF DECK SLAB
Sheet 06: BOTTOM REINFORCEMENT DETAILING OF DECK SLAB
Sheet 07: DESIGN DETAILING OF DECK SLAB AND CANTILEVER
SLAB
Sheet 08: DESIGN DETAILING OF MAIN AND CROSS GIRDER
Sheet 09: DESIGN DETAIL OF ABUTMENT
Sheet 10: REINFORCEMENT DETAILING OF ABUTMENT STEM
Sheet 11: DESIGN DETAIL OF PIER AND PIER CAP
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
SALIENT FEATURES
Particulars Required information/Values
Location
State State no :- 3
Geographic Location
2) 335218.0334N,
3062927.8161E
Span arrangement 4 * 25 m
Width of:
Page | i
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Design Data
HFL 1239.02 m
LBL 1234.7 m
Scour Depth
Abutment 4.57 m
Pier 7.2 m
Quantity Estimate
Page | ii
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
NOTATIONS
∅ Diameter of Bar
Page | iii
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
1. INTRODUCTION
1.1 Background
Bridge, a civil engineering structure, a structure used since ancient times for crossing any
obstruction beneath it. Who would have imagined that a simple structure used for
crossing obstruction will be used in so many ways with so many materials involved that it
will become such a large field of study at this period of time. Today, bridge is one of the
most prominent civil engineering structures. Different types of bridge are being built
these days due to sophisticated equipment and developed material science.
In context of Nepal, being a mountainous country with a lot of river and rivulets, we need
many bridges just to join one part of the country to another. Therefore, we need to
construct many bridges to ease the extension of road network as well as to carry out other
development works in an efficient way. Therefore, there is a huge potential of bridge
engineering in Nepal.
In this project, we were assigned to design a bridge over Bagmati River connecting the
roads "Baneshwor - Sankhamul - Bangalamukhi - Road" at Sankhamul joining
Kathmandu District with Lalitpur District. As it is a quite busy urban road, two lanes for
design are minimal. We are supposed to design the most economic bridge for this section
based on the various data collected by us. This report is prepared as a part of project work
for the fulfillment of the Project-II as per the syllabus of Bachelor of Civil Engineering
fourth year second part.
In Nepal, mostly RCC T-beam superstructure is preferred as the resources to design and
construct are readily available in Nepal. For our project purpose, we have also designed
RCC T-beam Bridge for learning the bridge engineering skills and practice. The variation
in design procedures for the superstructures, bearings and substructures has helped us to
enhance our understanding of the essentials of Bridge Engineering.
Page | 1
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
1.2 Objectives
The main objectives are to analyze and design the bridge based on Working State method
of design. In addition to that, before start of the work we came with following objectives:
• To obtain the basic ideas of bridge building.
• To be familiar with the different types of bridge and its design principles.
• To know about various type of loading and their forms of application.
• To understand various methods used in the design of the structural components of
bridge and their limitations.
• To be familiar with the design standards and code specifications of bridge
• To be familiar with the standard specification regarding the design of bridge.
The main objective of this project is to design a bridge over Bagmati River by using the
Working State approach of design. Hence, we entitled name of this project as “Design of
RCC T-Bridge over Bagmati River, Sankhamul, Kathmandu- Lalitpur”.
Page | 2
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
2. METHODOLOGY
2.1 Acquisition of data
For the design of our bridge, the preliminary data needed was acquired after carrying out
different surveys.
I. Site selection survey
For the site selection, we kept in mind the following criteria: -
• A straight reach of river.
• Steady river flow without whirls and across currents.
• A narrow channel with firm banks.
• Sustainable high banks above high flood level on each side.
• Rock or other hard in-erodible strata close to the river bed level.
• Proximity to a direct alignment of the road to be connected.
• Absence of sharp curves in the approaches.
• Absence of expensive river training works.
• Avoidance of excessive underwater construction
In selection of site, care should be taken to investigate a number of probable alternative
sites and then decide on the site which is likely to serve the needs of the bridges at the
least cost.
Page | 3
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Scour Depth
Scour of stream bed occurs during the passage of a flood discharge, when the velocity of
stream exceeds the limiting velocity that can be withstand by the particles of the bed
material. The scour depth should be measured with reference to existing structures near
the proposed bridge site, if this is possible. Due allowance should be made in the
observed value for additional scour that may occur due to the designed discharge being
greater than the flood discharge for which the scour was observed, and also due to
increased velocity due to obstruction to flow caused by the construction of bridge.
Page | 4
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
When the above practical method is not possible, the normal depth of scour may be
computed by equation for natural streams in alluvial beds
d =0.473(Q/f).33
Where,
d = normal depth of scour below H.F.L. for regime
conditions in a stable channel in meters.
Q=designed discharge in m3 per second
The minimum depth of foundation is kept at:
• 1.27×d for abutments
• 2×d for piers (IRC 78:2014)
Page | 5
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
This loading is normally considered when the structure is temporary and for bridges in
specified area. Structures with timber spans are to be regarded as temporary structures.
2.3 Superstructure
The basic function of bridge superstructure is to permit the uninterrupted smooth passage
of traffic over it and to transmit the loads and forces to the substructure safely through the
bearings. Although it is difficult to stipulate the aesthetic requirements, it should,
however, be ensured that the type of superstructure adopted is simple, pleasing to the eye,
and blends with the environment.
The superstructure of any bridge must be designed such that it satisfies geometric and
load carrying requirements set forth by its owner. This geometric requirement depends
upon the number and width of traffic lanes and footpaths that have to be carried across.
They also depend on overall alignment and various horizontal and vertical clearances
required above and below the roadway. The superstructure designed has to meet various
structural design requirements such as strength, stiffness and stability.
The horizontal and vertical alignment of a bridge is governed by the geometrics of the
highway, roadway or channel, it is crossing. For girder type bridges, the girders may
either be curved or straight, and may be aligned on chords between supports with the deck
slab built on the curve. The following points require close examination when girders are
aligned on a chord:
• Non-symmetric deck cross section
• Deck finish of the warped surface
• Vertical alignment of the curbs and railings, to preclude visible
discontinuities
• Proper development of super elevation
The various components of superstructure and their limiting dimensions with function as
per IRC 5 is given as follows:
I. Lighting
The lighting of the bridge is generally in accordance with the provisions of the
authority having jurisdiction on that area.
Page | 6
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
II. Drainage
The transverse drainage of the roadway is usually accomplished by providing
suitable crown in the roadway surface, and the longitudinal drainage is
accomplished by camber or gradient.
III. Traffic lane
Roads designed for traffic flow can be single lane, double lane or more. Road
width in meters should be divided by 3.65 and the quotient approximated to the
nearest whole number of design traffic lanes. We have designed our bridge with
two traffic lane.
IV. Road width
Road width is the distance between the roadside faces of the kerbs which depends
on the number and width of traffic lanes and the width of the bounding hard
shoulders. For our project, we have designed road width of 11 m.
V. Footpaths
Footpaths or walkways are generally provided where pedestrian traffic is
anticipated, but not on major arteries or in country sides. Its width is 1.5 m
generally, but may be as narrow as 0.6 m and as wide as 2.5 m depending on the
requirements. For our project, we have designed footpath of 1.75 m wide and 225
mm deep. (DOR)
VI. Road kerb
The road kerb is either surmountable type or insurmountable type. In the absence
of walkways, a road kerb is combined with parapet.
VII. Parapets
Parapets can be of many shapes and of variable sturdiness. They are designed to
prevent a fast moving vehicle of a given mass from shooting off the roadway in
the event of an accidental hit. Their height varies, but it should be at least 700
mm.
VIII. Railing Post
The parapets are usually mounted by metal Railing Post, about 350 mm high.
Their roadside face is double sloped. For our project, we have designed handrail
of size 200×200×1200 mm at end of span and 200×150×1200 mm at middle.
IX. Crash barriers
Page | 7
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Sometimes walkways are protected from the vehicular traffic by crash barriers
which act as insurmountable kerbs and deflect the hitting vehicles back into the
traffic lane.
Page | 8
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
The maximum value of the stress resultants or the deflection at a given section could be
found by taking a number of trial positions of the loads. Such a procedure apart from
being time consuming is also uncertain. The task is very much simplified by using the
concept of influence line.
An influence line is a graph or curve showing the variation of any function such as
reaction, bending moment, shearing force, deflection etc. at a given point of a structure,
as a unit load parallel to a given direction, crosses the structure.
The direction of the moving unit load depends on the nature of loading to be expected in
the structure.
Page | 9
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
importance of the bridge. For slabs supported on two sides, the maximum bending
moment caused by a wheel load may be assumed to be resisted by an effective width
of slab measured parallel to the supporting edges. For a single concentrated load the
effective width of dispersion may be calculated by the equation,
beff = K×x(x-x/L) + bw
Where, beff = Effective width of slab on which load acts
L= effective span
x = Distance of center of gravity from nearer
support
bw = Breadth of concentration of load
K = a constant depending on the ratio (B/L) and is
compiled in IRC 21
II. Slab spanning in two directions
In the case of bridge decks with tee beams and cross girders, the deck slab is
supported on all four sides and is spanning in two directions. The moments in two
directions can be computed by using the design curves developed by M. Pigeaud.
The method developed by Pigeaud is applicable to rectangular slabs
supported freely on all four sides and subjected to a symmetrically
placed concentrated load as shown in the figure below.
The notations used are as follows:
L = long span length
B = short span length
u, v = dimensions of the load spread after allowing for dispersion
through the deck
K = ratio of short to long span = B/L
M1= moment in short span direction
M2= moment in long span direction
m1 and m2 = coefficient of moment along long and short direction
µ = poison’s ratio for concrete generally assumed as 0.15
W = wheel load under consideration.
Page | 10
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
The dispersion of the load may be assumed to be at 45⁰ through the wearing coat
and deck slab according to IRC: 21code specifications. Consequently, the effect
of contact of wheel or track load in the direction of span shall be taken as equal to
the dimension of the tyre contact area over the wearing surface of the slab in the
direction of slab plus twice the overall depth of the slab inclusive of the thickness
of the wearing surface. It is sometimes assumed to be at 45⁰ through the wearing
coat but at steeper angle through the deck slab. The bending moments are
computed as:
M1= (m1+ µm2)×W
M2= (m2+ µm1)×W
Page | 11
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
The values of the moment coefficients m1 and m2, depend upon parameters (u/B), (v/L)
and K.
Page | 12
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Courbon’s method is popular due the simplicity of the computations and is applicable
when the following conditions are satisfied:
• The ratio of span to the width of bridge greater than 2 but less than 4
• The longitudinal girders are interconnected by at least 5 symmetrically spaced
cross girders.
• Depth of transverse beam should be at least 0.75 times the depth of main beam.
Hence, we adopted Courbon’s method for the analysis and design of girders.
In Courbon’s method, it is assumed that the transverse profile of the bridge deck under
loading remains straight & load shared by each girder in central region of bridge deck is
found by the distribution factors.
When the live loads are positioned nearer to the kerb as shown in figure the CG of live
load acts eccentrically with the CG of the girder system. Due to this eccentricity, the
loads shared by each girder is increased or decreased depending upon the position of
girder. This is calculated by Courbon’s theory by reaction factors given by,
Page | 13
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
axis of bridge
CL
w
e
kerb 1.2m
0.85
dx
∑𝑊 ∑𝐼
𝑅𝑥 = [1 + (∑ 𝑑2 × 𝐼) 𝑑𝑥 . 𝑒]
𝑛 𝑥
dx= Distance of the girder under consideration form the central axis of the bridge
The live load bending moments and shear forces are computed for each of the girders.
The maximum design moments and shear forces are obtained by adding the live load and
dead load bending moments. The reinforcement in the main longitudinal girders are
designed for the maximum moments and shears developed in the girders.
Page | 14
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Page | 15
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
3. TOPOGRAPHICAL SURVEY
Topographical survey was carried out to prepare topographical map for
pertinent information that may be required for design, construction and
maintenance.
Centre line of proposed bridge site:
After consultation with the technical personnel and the local villagers and as
directed by the river morphology; an axis joining line joining left bank and right
bank is fixed.
Benchmarks
The reference benchmark was established to start with the survey works. The
suitable and convenient place for starting bench mark was marked as BM1 on
the permanent concrete pillar which is situated near by the bridge site on left
bank of the river.
Page | 16
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Site Topography
The area is mostly densely populated, with very less natural terrain but roads
and structures. The Manohara River meets the Bagmati River at around 250 m
upstream of the bridge site.
The site has mild slope of 1 in 1000. The bridge facilitates the 7.5m wide road
connecting Baneshwor – Sankhamul – Bangalamukhi. There is also a road
running under the bridge, along the river on the Kathmandu side. The road
might suffer rare floods with higher return period.
Page | 17
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
4. HYDROLOGICAL STUDY
4.1 Catchment Area
• The catchment area of the river was determined by area declination method.
• The obtained area of catchment is 379 km2.
• The maximum R.L. of the catchment area is 2739.5m whereas the lowest R.L is
1234m
• Coefficient of run offs = 0.8
Page | 18
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Page | 19
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Year Jan. Feb. Mar. Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Year
1992 2.41 1.77 0.501 0.267 1.74 2.95 22.5 41.2 31.5 10.0 4.98 3.09 10.2
1993 1.66 1.11 0.943 2.21 4.33 13.9 41.6 66.9 29.4 10.9 4.59 2.16 15.0
1994 2.81 2.41 1.28 1.08 3.43 16.1 31.0 69.6 63.2 14.0 6.46 4.44 18.0
1995 2.38 4.23 3.79 2.70 5.00 40.2 57.0 64.1 33.6 16.2 11.7 10.9 21.0
1996 10.9 5.78 2.95 2.03 1.94 26.6 38.9 61.8 34.0 21.5 11.1 7.33 18.7
1997 4.22 2.74 1.65 5.48 3.84 8.17 61.9 68.3 21.4 13.2 10.6 12.9 17.9
1998 5.82 2.77 3.76 3.57 13.2 14.0 71.7 85.6 37.3 22.0 14.4 8.03 23.5
1999 4.87 4.36 2.19 1.02 3.01 31.8 74.5 73.6 41.4 13.8 11.3 7.28 22.4
2000 5.69 4.55 3.58 4.81 9.60 19.4 39.6 87.2 45.5 13.4 9.27 5.59 20.7
2001 5.35 5.18 4.21 3.39 7.54 11.4 37.6 67.4 42.9 17.4 7.00 5.85 17.9
2002 5.65 5.87 5.97 6.66 14.5 13.4 108 80.4 27.2 8.52 5.00 3.18 23.7
2003 3.83 5.22 3.16 2.39 2.71 6.06 57.4 64.1 48.8 17.1 9.73 7.60 19.0
2004 7.94 5.28 3.97 5.02 9.56 11.4 48.1 36.2 28.1 16.7 8.55 6.63 15.6
2005 8.01 5.19 5.05 3.74 4.65 6.75 20.6 42.7 20.1 14.2 7.83 5.17 12.0
2006 3.88 3.22 3.34 5.23 8.86 11.5 27.4 24.0 25.5 9.40 4.08 3.82 10.8
2007 3.21 6.56 4.87 4.34 6.69 15.5 27.2 32.0 55.2 13.1 6.55 4.57 15.0
2008 3.48 2.85 3.31 2.59 3.63 11.2 19.8 35.2 25.2 10.8 5.81 4.37 10.7
2009 2.78 1.50 1.79 2.94 3.64 3.95 66.0 31.4 21.4 12.9 6.02 3.14 13.1
2010 2.90 2.74 2.44 2.48 4.03 16.3 31.8 44.2 41.3 8.63 4.07 4.22 13.8
---------------------------------------------------------------------------------------------------
Average: 4.62 3.86 3.09 3.26 5.89 14.8 46.4 56.6 35.4 13.9 7.84 5.80 16.8
Page | 20
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Latitude(deg/min): 2742
Longitude(deg/min): 8522
Elevation(m): 1337
Rainfall (mm) for KATHMANDU AIRPORT
Year Jan Feb Mar Apr May Jun JUL AUG SEP OCT NOV DEC
1968 30.1 8.5 45.3 25.5 109.6 305.7 379.5 228.2 86.9 160.4 0.0 0.0
1969 8.6 1.4 47.6 27.4 86.9 166.1 299.7 323.9 175.3 40.3 2.0 0.0
1970 29.1 27.6 26.6 34.4 93.6 193.7 494.3 229.7 163.9 58.2 11.2 0.0
1971 3.0 6.3 28.4 180.8 109.7 608.1 204.6 252.6 36.4 81.2 0.2 0.0
1972 1.4 25.5 80.4 23.8 56.6 157.3 480.9 155.3 174.5 86.1 19.6 0.0
1973 23.7 32.4 48.5 25.3 81.1 340.4 456.0 336.5 321.1 119.3 15.5 0.0
1974 16.9 5.8 23.3 30.9 108.0 74.8 339.6 364.2 204.6 45.6 0.0 11.4
1975 30.6 25.4 8.0 36.1 69.1 138.5 436.1 379.0 267.5 34.2 0.0 0.0
1976 30.2 14.5 0.0 68.6 153.4 387.4 335.0 307.3 169.9 24.3 0.0 0.0
1977 11.5 12.1 17.1 103.9 90.1 265.6 322.7 338.3 78.9 29.1 14.4 13.6
1978 4.7 11.1 69.4 41.7 143.3 298.9 323.6 392.5 159.8 108.6 0.2 2.2
1979 5.6 39.3 0.7 42.1 37.3 258.1 447.3 320.3 99.1 35.7 5.6 65.3
1980 1.0 17.7 45.7 10.1 124.4 349.3 296.1 238.5 183.5 69.0 0.0 5.6
1981 14.5 0.0 60.4 100.9 216.2 140.7 304.0 266.9 225.1 0.0 42.0 0.0
1982 14.2 21.9 35.5 48.8 39.7 200.5 238.2 384.3 155.4 9.0 18.3 3.4
1983 18.2 4.0 30.2 78.7 110.1 81.4 499.9 194.2 287.7 129.9 0.0 15.3
1984 13.9 17.4 13.5 60.1 96.0 275.0 250.1 301.9 260.2 18.4 0.1 7.4
1985 9.7 3.2 4.0 24.8 132.5 160.8 418.3 434.4 375.6 167.2 0.0 54.6
1986 0.0 22.5 15.8 93.4 96.9 315.6 380.8 218.6 221.3 79.5 0.0 49.4
1987 3.2 43.3 35.9 34.4 57.6 116.4 498.8 256.3 171.2 159.3 0.0 18.8
1988 0.6 19.1 68.0 42.3 152.9 239.5 397.3 278.7 134.4 17.6 11.7 78.9
1989 47.4 10.7 12.1 4.0 148.7 135.5 328.0 206.0 196.5 42.4 0.0 0.7
1990 0.0 42.2 59.5 116.2 108.3 364.7 345.6 308.5 188.2 78.7 0.0 2.8
1991 20.7 11.4 45.2 106.3 145.3 114.4 190.3 280.9 127.9 0.4 0.2 24.9
Page | 21
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Year Jan Feb Mar Apr May Jun JUL AUG SEP OCT NOV DEC
1992 6.4 17.2 0.2 44.5 69.9 232.7 223.6 219.9 209.1 51.0 15.5 3.1
1993 10.2 15.4 42.0 86.8 184.6 204.4 296.3 293.8 156.2 14.5 1.8 0.0
1994 27.3 19.4 13.9 8.3 141.8 413.6 254.1 445.6 243.2 0.0 12.0 0.0
1995 3.3 28.8 39.8 3.2 60.5 590.5 336.1 404.1 100.6 38.3 61.6 7.0
1996 70.8 15.2 7.1 47.4 57.7 337.8 318.5 485.5 207.3 52.4 0.0 0.0
1997 16.4 5.5 13.9 100.1 90.3 245.4 511.0 370.5 70.9 12.0 4.9 87.4
1998 0.1 28.2 70.6 75.9 282.0 247.7 440.2 376.3 193.6 44.2 12.0 0.0
1999 4.2 4.2 0.0 6.0 106.5 315.6 485.2 393.5 266.9 152.2 0.0 1.2
2000 1.3 5.3 20.9 61.9 209.9 266.5 336.3 384.7 119.4 0.6 0.0 0.2
2001 6.8 15.7 8.4 34.6 179.9 250.4 498.8 460.3 145.5 20.5 0.0 0.0
2002 33.8 29.9 93.0 93.9 158.8 227.4 544.8 499.9 148.0 15.0 26.5 0.0
2003 19.5 68.4 85.9 38.0 37.7 222.3 591.5 347.0 293.4 17.7 0.0 18.6
2004 26.9 0.0 32.3 164.1 168.8 183.0 459.5 219.4 199.1 120.5 36.0 0.0
2005 55.1 17.0 50.1 34.8 40.6 222.9 253.5 309.3 126.5 126.1 0.0 0.0
2006 0.0 0.0 30.9 132.8 145.5 216.2 337.0 248.4 217.5 43.9 1.5 17.5
2007 0.0 72.8 36.3 77.9 90.7 263.0 227.3 223.7 332.5 18.5 3.2 0.0
2008 4.9 0.0 35.9 43.7 99.9 237.7 255.4 240.8 291.3 10.3 0.0 0.0
2009 0.0 0.0 28.4 21.3 132.0 125.0 326.3 382.9 113.4 71.5 1.0 3.6
2010 1.9 23.3 35.7 45.3 148.0 141.7 354.9 486.3 217.1 24.5 0.0 0.0
2011 6.2 54.9 16.4 56.8 167.4 306.0 437.8 265.4 318.0 13.0 12.9 0.0
2012 17.8 41.8 15.6 80.1 42.2 149.2 452.3 289.6 362.2 13.2 0.7 0.0
2013 11.5 45.4 27.3 44.5 278.6 299.1 428.5 451.4 217.3 95.7 0.0 0.0
2014 4.2 26.7 58.7 6.0 153.5 165.8 461.9 294.5 279.4 91.2 0.0 36.7
2015 3.4 35.2 98.7 51.0 155.9 125.6 470.6 452.0 189.4 67.6 0.0 0.0
2016 0.4 25.3 6.3 11.0 92.3 370.2 477.8 126.8 281.7 91.0 0.0 0.0
Page | 22
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Rational Method
𝐶∗𝑖∗𝐴
𝑄𝑝 =
360
A= Area in hectares
i = Rainfall intensity
C= Coefficient of Runoff
𝐾𝑇 𝑎 1
𝑖= 𝑛
; 𝑇 = = 100
(𝑡𝑐 + 𝑏) 𝑃
𝑘 = 5.92, 𝑎 = 0.162, 𝑏 = 0.5, 𝑛 = 1.013
0.77 −0.385
𝑡𝑐 = 0.019478𝐿 𝑆
𝐿 = 21,748 𝑚
𝐻 = 2729.5 − 1234 = 1495.5 𝑚
H= Difference in elevation between remotest point of the basin & outlet in m
= 1495.5 m
1495.5
S= = 0.0688
21748
= 119.37 𝑚𝑖𝑛𝑠
5.92 ∗ 1000.162
𝑖= 1.013
120.968
( + 0.5)
60
= 4.955 𝑚𝑚/ℎ𝑟
Page | 23
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Gumbel Method
DISCHARGE DISCHARGE
̅
𝑋 −𝑋 2 ̅
𝑋 −𝑋 2
(Q) (m3/SEC) (Q) (m3/SEC)
41.2 431.39 108 2118.76
66.9 24.3 64.1 4.54
69.6 58.22 48.1 192.38
64.1 4.54 42.7 371.33
61.8 0.0289 27.4 1195.38
68.3 40.07 55.2 45.83
85.6 558.38 35.2 716.63
74.5 157 66 16.24
87.2 636.55 44.2 315.77
67.4 29.48
∑(𝑋−𝑋̅ )2 6916.52
𝜎𝑥 = √ =√ =19.6
𝑁−1 19−1
For N= 19 years,
Form table:
𝑦̅n= 0.52076
𝑆̅n=1.05148
For T=100 years,
𝑇
yt = −ln(ln(𝑇−1))
100
y100 = −ln(ln(100−1)) = 4.6
𝑦100 −𝑦̅𝑛 4.6−0.52076
∴ 𝐾100 = = =3.87966
𝑆𝑛 1.05148
Page | 24
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
𝑎+6
p = 100 𝐴+𝑎
Fuller's method
𝐴 −0.3
Q max = QT [1 + 2 (2.59) ]
QT = maximum 24 hr flood
= Qav ( 1+0.8log 𝑇) = 120(1+0.8log 100) = 242.76 m3/s
𝐴 −0.3
Q max = QT [1 + 2 (2.59) ]
380 −0.3
=242.76 [1 + 2 (2.59) ]
=351.46 m3/s
WECS method
Q2 = 1.8767 (𝐴3000 + 1)0.8783
Q100 = 14.63 (𝐴3000 + 1)0.7342
= 14.63 ( 380 + 1)0.7342
=1148.57 m3/s
Page | 25
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Flood discharge
S.N. Methods in m3/sec
100 Years
1 Rational Method 371.49
2 WECS Method 1148.57
3 Modified Dickens 1374.85
492.73
4 Slope Area Method
Page | 26
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
In case of Hilly region and alluvial bed river, the waterway calculated by this method
seems to be reasonable in other rivers and streams. We adopted the linear waterway of
about 100 m according to the profile of HFL and practical judgement.
I. IRC 78/2014
d sm=1.34(q2/f)1/3
Q 500
where, q = B =1.3 ∗ 93.4= 6.96 m2/s
Page | 27
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
d=0.473(1.3 * 500/2.49)1/3=3.02 m
W=C×Q0.5=4.75×194.0380.5=58.032 m
D1=D(W/L)0.61 =1.816(58.032/30.4)0.6=2.694m
Page | 28
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
5. GEOTECHNICAL INVESTIGATION
Soil/Bearing Capacity
The average particle size of soil particles was found to be 1 mm through sieve analysis
with the following characteristics.
Page | 29
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
The bearing capacity of soil was adopted to be 350 KN/m2 by observing the general soil
properties and similar works done in the region.
Page | 30
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
BIBLIOGRAPHY
I. Victor, D.J. 2012. Essentials of Bridge Engineering, Oxford and IBH Publishing
Company Pvt. Ltd., New Delhi
II. Design Examples Provided by Asso. Prof. N.C. Sharma, IOE, Pulchowk
III. N.Krishna raju, Design of Bridges, Oxford and IBH Publishing Company Pvt.
Ltd., New Delhi
IV. Swamisaran, Design of substructures
V. Jain, A.K. 2002. Reinforced Concrete Limit State Design, Nem Chand and Bros,
Roorkee, India
VI. Design examples and detail drawings provided by Er. Aanand Kr. Mishra.
Page | 31
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
CODES/STANDARDS
Following codes were followed during the course of our bridge design :-
Codes Uses
SP 16 RCC
Page | 32
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Page | 33
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Page | 34
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
1
=2.14
𝑘
Page | 35
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
300
MAIN GIRDER
WIDTH
CROSS GIRDER
851
2200
3600
5000
Page | 36
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
MAIN GIRDER
WIDTH
ONE TRACK OF IRC
LENGTH CLASS 70R TRACK
VEHICLE
GIRDER
CROSS GIRDER
CROSS
2200
851
4570
5000
FIG: PLACEMENT OF IRC CLASS 70R TRACED VEHICLE FOR MAXIMUM LOADING
Page | 37
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
k = 0.468 ,
𝑢 1.0
= 2.2 = 0.45
𝐵
𝑣 4.7
= 4.7 = 1
𝐿
= 434.725 KN
Moment along shorter span = (m1 + µ m2) × effective load on span
= (7+ 0.15 × 0.7) × 10 – 2 × 434.725
= 30.887KNm
Moment along longer span = (m2 + µ m1) × effective load on span
= (0.7 + 0.15 × 7) × 10 – 2 × 434.725
= 7.607KNm
Page | 38
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
VEHICLE VEHICLE
DIRECTION DIRECTION
2350
270
460
190
300 W1
62.5 KN 62.5 KN
310
37.5 KN
W3 W2
1000
1200 1000
2350
600
310
37.5 KN 62.5 KN 62.5 KN
W6 W4 W5
460
2200
FIG: POSITION OF CLASS AA WHEELED VEHICLE FOR
MAXIMUM MOMENT
Wheel-1
u= 0.3+2×0.08= 0.46
v= 0.15+2×0.08= 0.31
𝑢
=0.21
𝐵
𝑣
=0.07
𝐿
k= 0.047
m1= 21×10-2
m2=18×10-2
Mshort= (21+0.15×18) ×10-2×1.25×62.5=18.51KNm
Mlong= (18+0.15×21) ×10-2×1.25×62.5=16.52KNm
Page | 39
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Wheel-2
DUMMY LOADING
62.5 KN
(62.5×1.25)
Intensity of loading= = 547.86KN/m2
0.46×0.31
k= 0.47
m1= 9.3×10-2
m2=6.3×10-2
Mshort= (9.3+0.15×6.3) ×10-2×2.2×0.31 ×547.86=38.77KNm
Mlong= (6.3+0.15×9.3) ×10-2∗ 2.2 × 0.31 × 547.86=28.75KNm
Considering the area between real and dummy wheel =1.54 m ×0 .31 m
u= 1.54
v= 0.31
𝑢
= 1.54/2.2
𝐵
= 0.7
𝑣
= 0.07
𝐿
k= 0.047
m1= 12×10-2
m2=9 ×10-2
Page | 40
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
DUMMY LOADING
37.5 KN
387 387
1.25×37.5
Intensity of loading= 0.46×0.31 = 328.72KN/m2
Area= 1.66×0.31m
𝑢
=0.75
𝐵
𝑣
= 0.07
𝐿
k= 0.47
m1= 11.5×10-2
m2=9×10-2
Mshort= (11.5+0.15×9) ×10-2×328.72×1.66×0.31=21.74 KNm
Mlong= (9+0.15×11.5) ×10-2×328.72×1.66×0.31=18.14 KNm
Between dummy and wheel
Area= 0.74m×0.31m
𝑢
𝐵
=0.34
Page | 41
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
𝑣
= 0.07
𝐿
k= 0.47
m1= 18×10-2
m2=17×10-2
Mshort= (18+0.15×17) ×10-2×328.72×0.74×0.31=15.97 KNm
Mlong= (17+0.15×18) ×10-2×328.72×0.74×0.31=14.86 KNm
Net moment
Mshort= 0.5×(21.74-15.97) =2.89KNm
Mlong=0.5×(18.14-14.86) = 1.64KNm
Wheel-4
2350
DUMMY LOADING
2350
62.5 KN
2200
Area=0.46m×2.71m
𝑢 0.46
= 2.2 = 0.21
𝐵
𝑣 2.71
= = 0.58
𝐿 4.7
k= 0.47
m1= 12×10-2
m2=2. 1 ×10-2
Mshort= 84.1 KNm
Page | 42
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Mlong= 26.63KNm
Between wheel and dummy load .46 m × 2.09 m
𝑢
=0.21
𝐵
𝑣 2.09
= 0.44
𝐿 4.7
k= 0.047
m1= 13×10-2
m2=3×10-2
Mshort= 70.84 KNm
Mlong= 26.07 KNm
Net moment
Mshort= 0.5×(84.1-70.84) =6.63KNm
Mlong=0.5×(26.63-26.06) = 0.285KNm
Wheel-5
2350
DUMMY LOADING
2350
62.5 KN
Area= 2.2m×2.71m
𝑢
𝐵
=1
Page | 43
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
𝑣
= 0.58
𝐿
k= 0.47
m1= 6.8×10-2
m2=1×10-2
Mshort= 227KNm
Mlong= 65.98 KNm
Between dummy load and wheel
Area =2.2m×2.09m
𝑢
=1
𝐵
k= 0.47
𝑣
= 0.44
𝐿
m1= 7.5×10-2
m2=1.6×10-2
Mshort= 194.97KNm
Mlong= 68.64KNm
Area = 1.54m×2.71m
𝑢
= 0.7
𝐵
𝑣
= 0.58
𝐿
k= 0.047
m1= 8.8×10-2
m2=1.5×10-2
Mshort= 206.35 KNm
Mlong= 64.47KNm
Area = 1.54m×2.09m
𝑢
= 0.7
𝐵
𝑣
= 0.44
𝐿
k= 0.47
Page | 44
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
m1= 9.7×10-2
m2=2.4×10-2
Mshort= 177.39KNm
Mlong= 67.97KNm
Net moment,
Mshort= 0.25 ×(227 – 194.47 -206.35+177.39) = 0.89 KNm
Mlong= .25 × ( 65.98 – 68.64 – 64.47 + 67.97) = 0.21 KNm
Wheel-6
2350
DUMMY LOADING
2350
37.5 KN
2200
Area= 1.66m×2.71m
𝑢
= 0.75
𝐵
𝑣
= 0.58
𝐿
k= 0.47
m1= 8.5×10-2
m2=1.4×10-2
Page | 45
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Mshort= 128.8KNm
Mlong= 39.55KNm
Area= 0.74m×2.71m
𝑢
= 0.34
𝐵
𝑣
= 0.58
𝐿
k= 0.47
m1= 11.5×10-2
m2=1.8×10-2
Mshort= 77.58KNm
Mlong= 23.23KNm
Area= 1.66m×2.09m
𝑢
= 0.75
𝐵
𝑣
= 0.44
𝐿
k= 0.47
m1= 9.4×10-2
m2=2.2×10-2
Mshort= 110.96KNm
Mlong= 41.17KNm
Area= 0.74m×2.09m
𝑢
= 0.34
𝐵
𝑣
= 0. 44
𝐿
k= 0.47
m1= 13.2×10-2
m2=3×10-2
Page | 46
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Mshort= 69.39KNm
Mlong= 25.32KNm
Net moment,
Mshort= 0.25 × (128.8 -77.58-110.96+69.39) = 2.41 KNm
Mlong=0.25×(39.55-23.23-41.17+25.32) =0.12KNm
Moment due to wheel loading,
Mshort= (18.51+1.69+2.89+6.63+0.89+2.14) =32.75 KNm
Mlong= (16.52+0.25+1.64+0.285+0.21+0.12) = 19.025KNm
W3 W1 W2
2200
860
610 1370
60 KN 85 KN 85 KN
BM due to wheel 1
Tyre contact dimension = 0.86 × 0.61
u = 0.86 + 2 × 0.08 = 1.02 m
v = 0.61 + 2× 0.08 = 0.77 m
𝑢 1.02
= = 0.4636
𝐵 2.2
𝑣 0.77
= = 0.164
𝐿 4.7
2.2
K = 4.7 = 0.468
Page | 47
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
for k = 0.5
m1 = 13.5 × 10- 2 , m2 = 9 × 10-2
for k = 0.4
m1 = 16 × 10- 2 , m2 = 9.1 × 10-2
for k = 0.468
m1 = 14.3 × 10- 2 , m2 = 9.068 × 10-2
Impact factor = 25 %
Impact load = 85 × 1.25 = 106.25 KN
Moment along short span = (m1 + µ m2) × w
= (14.3 + 0.15 × 9.068) × 106.25 × 10 - 2
= 16.638 KNm
Moment along short span = (m2 + µ m1) × w
= (9.068+ 0.15 × 14.3) × 106.25 × 10 - 2
= 11.914 KNm
BM due to wheel 2:
4700
DUMMY LOAD
W2
2200
675 675
2130
FIG.BM DUE TO W2
Intensity of
85 2
Loading = 0.86 ∗ 0.61 = 162.028 KN/m
Page | 48
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
For K = 0.4
m1 = 8.9 × 10 – 2 m2 = 1.9 × 10 – 2
for K = 0.5
m1 = 8.8 × 10 – 2 m2 = 0.9 × 10 – 2
for K = 0.468
m1 = 8.832 × 10 – 2 m2 = 1.22 × 10 – 2
Moment along short span = (m1 + µ m2) × w
= ( 8.832 + 0.15 × 1.22 )× 162.028 × 0.86 × 3.35 × 10 – 2
= 42.082 KNm
Moment along short span = (m2 + µ m1) × w = 11.875 KNm
Next, consider the area between the real and dummy load to be ; 2.13 m × 0.86 m
u = 1.02 v = 2.13 + 0.08 ×2 = 2.19
𝑢 1.02 𝑣 2.19
= = 0.464 = = 0.466
𝐵 2.2 𝐿 4.7
K = 0.468
for K = 0.4
m1 = 12 × 10 – 2 m2 = 4 × 10 – 2
for K = 0.5
m1 = 11 × 10 – 2 m2 = 2.6× 10 – 2
for K = 0.468
m1 = 11.32 × 10 – 2 m2 = 3.048 × 10 – 2
Moment along short span = 34.955 KNm
Moment along long span = 14.086 KNm
1
Net BM along short span = 2 ∗ (42.082 − 34.955) = 3.563 KNm
1
Net BM along long span = 2 ∗ (14.086 − 11.879) = 1.1035 KNm
Page | 49
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
BM due to wheel 3
4700
DUMMY LOADING
W3
2200
375 3950 375
60 KN
BM DUE TO WHEEL 3
K = 0.468
For K = 0.4
m1 = 7 × 10 – 2 m2 = 1.3 × 10 – 2
For K = 0.5
m1 = 7.8 × 10 – 2 m2 = 3.2 × 10 – 2
For K = 0.468
m1 = 7.544 × 10 – 2 m2 = 2.592 × 10 – 2
Moment along short span = (m1 + µ m2) × w
= (7.544 + 0.15 × 2.592) × 162.028 × 0.86 × 4.7 × 10 – 2
= 51.953 KNm
Moment along short span = (m2 + µ m1) × w = 24.386 KNm
Next,
Consider the area between the real and dummy load to be; 4.7 m × 0.375 m
u = 1.02 v = 4.7 – 2 × 0.375 = 3.95
𝑢 1.02 𝑣 3.95
= = 0.463 = = 0.84
𝐵 2.2 𝐿 4.7
Page | 50
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
K = 0.463
for K = 0.4
m1 = 8.1× 10 – 2 m2 = 1.7 × 10 – 2
for K = 0.5
m1 = 8.2 × 10 – 2 m2 = 0.8 × 10 – 2
For K = 0.463
m1 = 8.163 × 10 – 2 m2 = 1.133 × 10 – 2
Moment along short span = (m1 + µ m2) × w
= (8.163 + 0.15 × 1.133) ×10 – 2 × 3.95 × 0.86 ×162.028
= 45.86 KNm
Moment along long span = (m2 + µ m1) ×w = 12.975 KNm
1
Net BM along short span = 2 ∗ (51.953 − 45.86) = 3.046 KNm
1
Net BM along long span = 2 ∗ (24.386 − 12.975) = 5.705 KNm
Page | 51
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Mshort=0.8×41.235=32.988KNm
Mlong=0.8×20.15= 16.12KNm
Using M30 concrete and TMT steel,
fck= 30MPa fy=500MPa
𝜎cbc=10MPa 𝜎cbc=240MPa
280/3 280/3
k= 280 =280 =0.28
+𝜎st +240
3 3
𝑘 0.28
j= 1-3 =1- 3
1 1
R= 2 × 𝜎cbc× 𝑘 × 𝑗 = × 10 × 0.9067
2
R= 1.2693
Check for depth:
Bending moment= R×b×d2
32.988×106
D=√1.2693×100 =161.21 <165mm (OK)
Ast, min=240mm2
Provide 12mm∅bars@110mm c/c
𝜋×62
Ast, provided= 110 × 100= 1028.157mm2>Ast, required
In longer direction:
Mlong= 𝜎st×Ast×j× 𝑑 ′
12 10
d’= 168- 2 - 2 =157mm
Page | 52
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
16.12×106
Ast=240×0.9067×158 =471.82mm2
350 KN
80mm Bituminous layer
Page | 53
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Shear Force
= 69.92*(2.2-0.705)/2.2
= 46.51 KN
Shear force with impact
=1.25*46.51
=59.39 KN
Shear force due to dead load
dead load = 25*0.20+22*0.08
=6.76 KN/m2
shear force due to dead load
=6.76 *2.2/2
=7.436 KN
Total S.F = 7.436 +59.39 = 66.826 KN
= 66.826*103/103 *168
=0.398 N/mm2
k =1.2
pt = 100* A/bd
= 100*1028.16/1000*168
= 0.612
For M30 grade concrete τco =0.337N/mm2
τc=k * τc0
=1.2*0.337
=0.404N/mm2
Page | 54
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
A. Wheeled vehicle
Shear due to live load :
I. For 37.5KN
37.5KN
Page | 55
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
II.For 62.5KN
CL
62.5KN
Fig:wheel position for shear force due to IRC Class AA wheel load
2nd wheel only
54.35
Page | 56
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Total design shear force =shear force due to (dead load +live load)
=57.27+7.436
=64.706 KN
Page | 57
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
350KN
700
80
200
280 840
2200
Page | 58
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
a. Wheel vehicle
Shear due to live load:
85KN
710
80
200
280 860
2200
Page | 59
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
57KN 10.36KN
530
80
500
200
280
2200
wheel 1
For continuous slab K=2.6
Effective width of slab = kx(1-x/l)+bw
=2.6*0.53(1-0.53/2.2)+0.25+2*0.08
=1.456m
Load per m width:
=57/1.456
Page | 60
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
=39.15 KN/m
Shear force = 39.15 (2.2-0.53)/2.2
=29.72 KN
Considering impact factor
=1.25*4
=37.15 KN
wheel2
For continuous slab K=2.6
Effective width of slab = kx(1-x/l)+bw
=2.6*2.14(1-2.14/2.2)+0.25+2*0.08
=.561 m
Load per m width:
=10.36/0.561
=18.44 KN/m
Shear force = 18.44(2.2-2.14)/2.2
=0.5 KN
Considering impact factor
=1.25*0.5
=0.63KN
Shear force due to dead load
Dead load = 6.76 KN/m2
Shear force =7.436 KN
Total design shear force = shear force due to (dead load +live load)
= 37.15 + 0.63 + 7.436
= 45.22KN
Check for shear :
Nominal shear stressI(τv) = v/bd
= (45.22*103/103*168)
= 0.27N/mm2
(τc) = 0.404 N/mm2
Since τc is greater than τv .so, the shear stress are with in permissible limit. Hence
deck slab safe against shear failure.
Design summary of deck slab
overall depth of deck slab= 200 mm
Effective depth of deck slab =168 mm
Provide 12mm∅bars@110mm c/c in short direction.
Provide 10mm∅bars @150mm c/c in longer direction.
Page | 61
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Page | 62
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
= 0.7748 KN @ 1.6 m.
Weight of footpath = 22 × 1.75 × 0.225 = 8.6625 KN @ 0.875 m, (22 assuming wearing
coat.)
Self weight of slab W1 = 25 × 0.15 × 1.75 = 6.5625 KN @ 0.875 m.
W2 = 0.5 ×25 ×0.1 × 1.75 = 2.1875 KN @ 0.583 m.
Moment due to dead load
B.M = 0.7748 ×1.6 +8.6625 × 0.875 +6.5625 × 0.875 +2.1875 ×0.583
=15.84 KNm/m.
Bending moment due to live load
Pedestrian load = 5 KN/m2
1.52
Bending moment = 5 × = 5.630 KNm/m.
2
Design of Reinforcement
𝐾
m = σst Ast × d × ( 1 - )
3
𝑚 21.47× 106
Ast = 𝐾 = 0.28
𝜎𝑠𝑡 ( 1− )𝑑 240 × ( 1− ) ×220
3 3
Page | 63
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
0.12
As, Ast min = 250 × 1000 × = 300 mm2
100
𝜏v =0.083 N/mm2
Shear Strength of Concrete:
523.6
Pt = 220×1000 × 100 =0.0238 and M30 concrete.
𝜏c=0.23N/mm2
𝜏c ‘=1.1×0.23 =0.253N/mm2 > 𝜏v
Hence, design is safe.
Design Summary of Cantilever Slab
overall depth of Cantilever Slab = 250mm
Effective depth of deck slab Cantilever Slab =220 mm from near the support
similarly 150mm , 120 at cantilever end.
Provide 10 mm – φ @ 150 mm c/c. in longitudinal direction.
Provide 8mm – φ bar @ 150 mm c/c. in transverse direction
Page | 64
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Page | 65
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Page | 66
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Reaction factors
Using carbon’s theory, the IRC class AA tracked vehicle loads are arranged for maximum
eccentricity as shown in figure. Reaction factor for outer girder is given by:
𝛴𝑊 𝛴𝐼
Rx = [1 + ( × I ) dx × e]
𝑛 𝛴 𝑑𝑥2
Page | 67
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
n=4
2𝑊1 4𝐼∗3.75∗1.1
RA = [1 + (2𝐼∗3.752 )+ (2𝐼 ∗ 1.252 ) ] = 0.764 w1
4
As, w1 = 0.5 w
Therefore, RA = 0.764 × 0.5 w = 0.382 w
similarly,
2𝑊1 4𝐼∗1.25∗1.1
RB = [1 + (2𝐼∗3.752 )+ (2𝐼 ∗ 1.252) ]
4
= 0.58w1
= 0.294 w
2𝑊1 4𝐼∗( − 1.25)∗1.1
RC = [1 + (2𝐼∗3.752 )+ (2𝐼 ∗ 1.252) ]
4
= 0.412w1
= 0.206 w
2𝑊1 4𝐼∗(− 3.75 )∗1.1
RD = [1 + (2𝐼∗3.752 )+ (2𝐼 ∗ 1.252 ) ]
4
= 0.236w1
= 0.118 w
Live load BM in girder due to class AA tracked vehicle:
Effective span of girder = 25m
Impact factor (for class AA loading) = 10%
Live load is placed centrally on the span as shown in figure below.
Page | 68
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
25
TOTAL LOAD
3.6
700KN
12.5 12.5
Wab
l
Unit influence line for
5.35 B.M
5.35
6.25
Fig:Influence line diagram for bending moment for class AA vehicle
2.5
TOTAL LOAD
4.57
700KN
12.5 12.5
Wab
l
Unit influence line for
5.1075 B.M
5.1075
6.25
Fig:Influence line diagram for bending moment for class 70R vehicle
Page | 69
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
as, n = 4, e = 0.7 m
4𝑤 4𝐼
RA = [ 1 + 2 𝐼 ∗ 3.752 + 2𝐼 ∗ 1.252 ∗ 3.75 ∗ 0.7]
4
= 1.336 w
4𝑤 4𝐼
RB = [ 1 + 2 𝐼 ∗ 3.752 + 2𝐼 ∗ 1.252 ∗ 1.25 ∗ 0.7]
4
= 1.112 w
4𝑤 4𝐼
RC = [ 1 − 2 𝐼 ∗ 3.752 + 2𝐼 ∗ 1.252 ∗ 1.25 ∗ 0.7]
4
= 0.888 w L
4𝑤 4𝐼
RD = [ 1 − 2 𝐼 ∗ 3.752 + 2𝐼 ∗ 1.252 ∗ 3.75 ∗ 0.7]
4
= 0.664 w
Reaction factors,
RA = 0.334w
RB = 0.278w
RC = 0.222w RD = 0.166w
Maximum live load BM at mid span i.e. L/2; The below fig shows the ILD
114
114
27
27
68
68
68
4.1
4.05
5.65
6.25
Page | 70
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
68
68
68
68
5075 1100 3200 1200 4300 3000 3000 3000 1125
0.42
1.55
2.67
3.17
3.8
3.86
5.41
5.86
Page | 71
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
114
114
27
27
68
68
68
68
1.95 1.1 3.2 1.2 4.3 3.0 3.0 3.0 4.25
1.0625
1.4625
1.8125
2.2875
2.5625
3.3125
4.3875
4.6875
Page | 72
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
LONGITUDINAL GIRDER
CROSS GIRDER
2.5
5 5
W1=350KN
2.5
B
3.6
W2=350KN
2.5
A
3.6
= 382.53 KN
287 ∗ ( 24.4 – 1.8 )
Maximum reaction in girder A = 24.4
= 265.83 KN
Live load = 5 × 1.5 = 7.5 KN/m
24.42
BM = 7.5 × = 558.15 KNm
8
24.4
F = 7.5 × = 91.5 KN
2
Page | 73
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
k=0.28
d= D-110= 1750-110=1640mm
nc=k×d=0.28×1640mm
nc=459.2mm >Df
𝑛𝑐−𝐷𝑓
𝜎c’= 𝜎cbc× ( )
𝑛𝑐
459.2−200
=10× = 5.64MPa
459.2
𝜎𝑐𝑏𝑐+2×𝜎𝑐′ 𝐷𝑓
𝑦̅ = ×
𝜎𝑐𝑏𝑐+𝜎𝑐 ′ 3
10+2×5.64 200
= ×
10+5.64 3
𝑦̅ = 90.72 𝑚𝑚
𝜎𝑐𝑏𝑐+𝜎𝑐 ′ 𝜎𝑐 ′ 𝑛−𝐷𝑓
Mlimiting=bf×Df× ( ) × (𝑑 − 𝑦̅) + 𝑏𝑤 × (𝑛 − 𝐷𝑓) × × (𝑑 − 𝐷𝑓 − )
2 2 3
Page | 74
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
10+5.64 5.64
= 2500×200× ( ) × (1640 − 90.72) + 300 × (1640 − 200) × ×
2 2
459.2−200
(1640 − 200 − )
3
= 16889.2 mm2
For Girder A
Dead load shear in longitudinal girder, SFD = 46.78×12.2 =570.72 KN
Live load shear in longitudinal girder, SFL = 91.5+265.83 = 357.33 KN
SF total = 570.72 + 357.33 = 928.05 KN
For Girder B
Dead load shear in longitudinal girder, SFD = 38.76×12.2 =472.87 KN
Live load shear in longitudinal girder, SFL = 382.53 KN
SF total = 472.87 + 382.53 = 855.4 KN
Design of shear reinforcement
𝑉 928.08×103
τv = =
𝑏𝑑 300×1640
τC = 0.4973 N/mm2
VC = 0.4973 × 300 ×1640 = 244.66 KN
Vus = 928.05 – 244.66 = 683.39 KN
Provide 2L – 12 mm φ vertical stirrup @ 120 mm C/C
2× 𝛱×62 ×1640×240
Vus = 120
= 741.92 KN
Page | 75
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
80mm THICK
WEARING COAT
@200mm c/c
5 each side
21-32mm Ø
300
tension bars
600
FIG.CROSS SECTION OF
LONGITUDINAL GIRDER
Page | 76
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Page | 77
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
= 11.14 KNm
2.5 21.125
Shear Force = 8.625 × + = 21.34 KN
2 2
Shear Force
IRC class AA Track Vehicle
𝟎.𝟒𝟓
(𝟑𝟓𝟎+𝟑𝟓𝟎× )×𝟏.𝟐𝟓
𝟐𝟓
S.F = 𝟐
= 212.5 KN
Design Bending Moment = 273.44 + 11.14= 284.58 KNm
Design Shear Force = 212.5 +21.34= 234.74 KN
Design of Reinforcement
fy = 500 MPa fck =30 MPa
σst = 240 MPa σcbc = 10 MPa
280
3
K= 280 = 0.28
+240
3
1 𝑥
R= 2 × 𝜎𝑐𝑏𝑐 × 12 (1 − 3)
1 0.28
=2 × 10 × 0.28 × (1 − ) = 1.269
3
Page | 78
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
0.2
𝐴𝑠𝑡,𝑚𝑖𝑛 = × 300 × 1295 = 777 𝑚𝑚2 < 1009.9 𝑚𝑚2
100
𝑉𝑐 = 𝜏𝑐 × 𝑏 × 𝑑
For 𝜏𝑐
𝑓𝑐𝑘 = 30 𝑀𝑃𝑎
100×𝐴𝑠𝑡
= 0.26
𝑏×𝑑
𝜏𝑐 = 0.31 𝑁/𝑚𝑚2
𝑉𝑐 = 0.31 × 300 × 1295 = 120.435 𝐾𝑁
Total Shear, 𝑉𝑡 = 𝑉𝑠 + 𝑉𝑐 = 162.73 + 120.435
= 282.17𝐾𝑁 > 𝑉𝑢 , 𝑂. 𝐾.
Design of side face reinforcement
0.1
𝐴𝑠 = × 300 × 1350 = 486𝑚𝑚2
100
Provide 12 mm – Φ bar
390
Number of bars, n = 𝛱×62 = 3.448 ≈ 4
Page | 79
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Page | 80
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Page | 81
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Page | 82
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
110.8
Horizontal braking load on bearing (𝐹𝑏𝑟 𝐻 ) = = 27.7 KN
4
Page | 83
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
26.79
Wind load in transverse direction of bearing = = 5.95 KN
4
6.7
Wind load in longitudinal direction of bearing = = 1.675 KN
4
5. Seismic load
𝑍 𝐼 𝑆
Seismic load (𝐹𝑠 ℎ ) = (2) 𝑋 (𝑅) 𝑋 ( 𝑔𝑎 ) 𝑋 𝑊
0.36 1.2
αh = 𝑋 𝑋 2.5 = 0.135
2 4
Page | 84
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Page | 85
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Page | 86
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
𝐴1
𝐴𝑙𝑙𝑜𝑤𝑎𝑏𝑙𝑒 𝐵. 𝑆 = 0.25 ∗ 𝑓𝑐𝑘 ∗ √
𝐴2
320 ∗ 500
= 0.230 ∗ √
308 ∗ 488
𝑁
= 7.74
𝑚𝑚2
2) Structural Design
a) Check for Translation
Design strain in bearing (ᵧ𝑑 ) < 0.7
∆𝑏𝑑
= ᵧ𝑏𝑑 = + 𝜏𝑚𝑑
ℎ
∆𝑏𝑑 5 ∗ 10−4 ∗ 24.4 ∗ 103
=
ℎ 2 ∗ 40
= 0.1525
𝐻 27.7 ∗ 103
𝜏𝑚𝑑 = = = 0.1843
𝐴 ∗ 𝐺 308 ∗ 488 ∗ 1
ᵧ𝑑 = 0.1525 + 0.1843 = 0.337 < 0.7 (𝑂. 𝐾)
b) Check for Rotation
Maximum permissible angle of rotation of a single interval layer of elastomer
corresponding to σm value of 10 N/mm2 is given by,
0.5 𝜎𝑚 × ℎ𝑖 0.5×10× 10
αbi. max = = = 0.00193 radians.
𝑏×𝑠2 308× 9.162
where,
ᵧ𝑑 = 0.337
0.2 + 0.1𝜎𝑚 = 0.2 + 0.1 ∗ 6.417
Page | 87
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
𝑁
= 0.8417 𝑚𝑚2 > ᵧ𝑑 (𝑂. 𝐾. )
308 2
= 0.5 ∗ ( ) ∗ 0.00193
10
= 0.915 𝑁/𝑚𝑚2
Total shear stress = 10575 + 0.337 + 0.915
= 2.827 𝑁/𝑚𝑚2 < 5 𝑁/𝑚𝑚2 (O.K.)
Check for Elastomeric Pad Bearing for combination [𝑁 + 𝑇 + 𝑆]
𝑁𝑚𝑖𝑛 = 𝐷𝐿 = 583.335 𝐾𝑁
𝑁𝑚𝑎𝑥 = 661.639 𝐾𝑁
𝐻 = 53.973 𝐾𝑁
Check for bearing stress in concrete
𝑁𝑚𝑎𝑥
Bearing stress in concrete (𝜎𝑚 ) = 𝑙∗𝑏
661.639 ∗ 103
=
488 ∗ 308
= 4.402 𝑁/𝑚𝑚2 < allowable bearing stress ≈ 7.74 𝑁/𝑚𝑚2 (O.K.)
Page | 88
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
500
32
52
10
4 x 3 mm thick
5
0
5
Page | 89
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Page | 90
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
𝜏c=0.25√𝑓𝑐𝑘=0.25√25 =1.25N/mm2
Design of reinforcement:
Longitudinal direction:
Area of steel =1% of BD
=0.01×400×1000=4000mm2
As one side =2000mm2
Adopt 20-mm-∅bar
2000
Number of bar n=𝜋×102=6.36≈7
The traverse direction bars are provided in the term of the stirrups.
Page | 91
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
In addition, two layers of mesh reinforcement; each consisting 8mm∅@75mm c/c in both
direction on at6 20mm and other 100 mm from the top of cap are provided directly under
the bearing.
Check for stability of abutment
Description of item unit Force (KN) Lever arm Moment (KNm)
S.N. Component name wirdth height
of work weight Vertical Horizontal (m) Resisting Overturning
Dead load from
1 232 2.84 658.88
superstructure
Self weight
W1 1*5*1.2*25 1 5 1.2 25 150 2.5 375
W2 1*0.8*4.4*25 1 0.8 4.4 25 88 2.8 246.4
W3 1*1*0.4*25 1 1 0.4 25 10 2.9 29
W4 1*0.3*1.6*25 1 0.3 1.6 25 12 3.25 39
2
W5 0.5*0.4*4.4*25 0.5 0.4 4.4 25 22 2.267 49.874
vertical loab due to live load 1*1*1.2*18 1 1 1.2 18 21.6 4.1 88.56
= 2.13>2 OK
µ ΣV 0.6∗885.55
FOS against sliding = =
ΣH 346.24
= 1.53>1.5 OK
Σm𝑟 − Σm𝑜 2757.51−1292.09
𝑥= = = 1.687 m
ΣV 885.55
Page | 92
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
𝐵 5 𝐵
e = 2 − 𝑥 = 2 − 1.667 = 0.813 < 6 ok
𝛴𝑉 6𝑒
σheel = (1- )
𝐵 𝐵
885.55 6∗0.813
= (1- ) =0.7 KNm
5 5
𝛴𝑉 6𝑒
σtoe = (1+ )
𝐵 𝐵
885.55 6∗0.813
= (1+ ) = 349.98KNm
5 5
Foundation of abutment:
The bending moment is maximum at the face of abutment.
22 2
BM= 212.77× + (349.98-212.77) × 0.5 ×2 × 2 × 3 = 614.05 KNm
2
Depth verification
Fy= 500MPa
𝜎abc=6.67MPa
𝜎st= 240MPa
280/3
k= 280 = 0.28
+240
3
1
R= 2 × 𝜎abc × j × k
R = 0.8466
𝑚 614.05×106
d= √𝑅×𝑏=√0.8466×1000= 851.66mm < 1125 mm (OK)
D= 1200 mm
d= 1200-65-20/2 = 1125 mm
Ast,max=4% of B × D =0.04×1000×1200=4800mm2
Ast, min=0.12%of B×D=0.0012×1000×1200=1440mm2
=2508.37mm2 >Astmin
<Astmax (OK)
Page | 93
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
fck= 20MPa
𝜏c=0.212 N/mm2> 𝜏v (OK)
Design of top bar
1.8 1 1.8
BM = 0.7 × 1.8 × + 2 × (91.94-0.7)*1.8 × – 213.84× 0.9 – 26.6 × 0.9 – 1.8 × 1.2 ×1
2 3
×25 × 0.9
= - 214.59KNm
Top reinforcement is required.
214.59∗10 6
Ast = 0.28 = 876.59 < Ast , min
240∗1125∗(1− )
3
Mu=232.8KNm
Page | 94
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Ast, required=947.72mm2
Provide 20mm∅bar @210mm c/c
Ast, provided=1491.62mm2
= 16.88 KNm
R=0.8466
Depth verification
𝑀𝑢 16.88 ∗106
D=√𝑅∗𝑏=√0.8466∗1000
16.88 ∗106
= 0.28
240∗270∗( 1− )
3
Page | 95
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
𝑣 33.22∗103
τv = 𝑏∗𝑑 = = 0.123 N/mm2 < τc ,max
1000∗270
Page | 96
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
𝑀𝑢 628.565∗106
d = √𝑄∗𝑏=√0.8466∗1000 = 861.66mm < 1125mm OK
𝑀𝑢
Ast = 𝐾
𝑄∗𝑑(1− )
3
628.565∗106
= 0.28
240 ∗1125∗(1− )
3
Page | 97
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Curtailment of reinforcement:
From above 2.4m above the top of footing
Mu=260.55KNm
Ast, min=0.12*10*990= 1188mm2
260.55∗106
Ast, required= 28 = 1308.61mm2
240∗915∗(1− )
3
Page | 98
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Page | 99
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
47
Then PZ= 190.5 × 33 = 271.32 N/m2
G = 2 (up to 150 m height)
47
Vz = 17.8 × 33 = 25.35 m/s
t = 1.8 m. t vz = 1.8 × 25.35 = 45.63 m2 /s > 6 m2 /s
7
CD = 0.8 For 1.8 = 3.8
FwT = 271.32 ×10 – 3 × 0.8 ×2 ×61.72 = 26.79 KN
Page | 100
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Fhyd = c × αh ×w
𝑍 𝐼 𝑆
αh = 2 ∗ 𝑅 ∗ 𝑔𝑎
From IRC – 6
Z= 0.36 for zone V
I = 1.2 important factor of structure
R = 4 response reduction factor
S/g = 2.5 0 < T < 0.67 IRC – 6
0.36 1.2
αh = ∗ ∗ 2.5 = 0.135
2 4
𝐻
C = 0.8 ; = 7.77
𝑅
Fhyd =0.8 × 0.135 × 107.95 = 11.66 KN
Page | 101
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
750
1400 800
1
9000
750 2500
500
1000
1500
S.F.= (1.35 ∗ 1921.96 + 1.75 ∗ 330) + 1.5 ∗ 1388.3 + 50 ∗ 1.15 + 3.886 ∗ 1.4 ∗ 1 ∗
25 + 0.5 ∗ 3.886 ∗ 1.4 ∗ 25
= 2594.646 + 577.5 + 2082.45 + 57.5
= 5312.096 + 136 + 34
= 5482.096 𝐾𝑁
At the face of first beam,
𝑆. 𝐹 = 5312.096 + 3.5 ∗ 1.4 ∗ 1 ∗ 25 + .486 ∗ 1.4 ∗ 0.5 ∗ 3.5 ∗ 25
= 5312.096 + 122.5 + 29.77
= 5464.366 𝐾𝑁
Page | 102
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
7730.96∗106
= √0.1336∗25∗1400
> 𝐴𝑠𝑡,𝑚𝑖𝑛
0.85 ∗ 1400 ∗ 1455
𝐴𝑠𝑡,𝑚𝑖𝑛 = = 3462.9 𝑚𝑚2
500
𝐴𝑠𝑡,𝑚𝑎𝑥 = 0.04 ∗ 1400 ∗ 1000 = 56000 𝑚𝑚2
Provide 23-28 mm-Φ bars
𝐴𝑠𝑡,𝑝𝑟𝑜𝑣𝑖𝑑𝑒𝑑 = 23 ∗ 𝛱 ∗ 142 = 14162.3 𝑚𝑚2 > 𝐴𝑠𝑡,𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑑 (𝑂. 𝐾. )
1400 − 40 ∗ 2
𝑆𝑝𝑎𝑐𝑖𝑛𝑔 = = 60 𝑚𝑚
22
14162.3
𝑝𝑡 = ∗ 100 = 0.7 % ; 𝑓𝑐𝑘 = 25 𝑀𝑃𝑎
1400 ∗ 1447
𝜏𝑚𝑎𝑥 = 3.1 𝑁/𝑚𝑚2
Page | 103
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
𝜏𝑐 = 0.544 𝑁/𝑚𝑚2
𝛽 = 8°
𝑀𝑢
𝑉𝑢 + ∗ 𝑡𝑎𝑛𝛽
𝜏𝑣 = 𝑑
𝑏∗𝑑
7730.96
5482.096 −
= 1.46 ∗ tan(80°)
1.4 ∗ 1460
= 2.32 𝑁/𝑚𝑚2
At the face,
𝑀𝑢 = 7217.82 𝐾𝑁𝑚
𝑀𝑢
𝑉𝑢 + ∗ 𝑡𝑎𝑛𝛽
𝜏𝑣 = 𝑑
𝑏∗𝑑
1217.82
5482.096 − 1.442 ∗ tan(80°)
=
1.4 ∗ 1442
𝑁
= 2.36 < 𝜏𝑐,𝑚𝑎𝑥
𝑚𝑚2
Hence, shear force is maximum at the face of bearing.
𝑉𝑐 = 𝜏𝑐 ∗ 𝑏 ∗ 𝑑
= 0.554 ∗ 1400 ∗ 1442
= 1118.415 𝐾𝑁
𝑉𝑢𝑠 = 𝑉𝑢 − 𝑉𝑐
= 5464.366 − 1118.415
= 4345.951 KN
0.87 ∗ 𝑓𝑦 ∗ 𝐴𝑠𝑣 ∗ 𝑑
𝑉𝑢𝑠 =
𝑠𝑝𝑎𝑐𝑖𝑛𝑔
Provide 6L- 12 mm – Φ vertical stirrup @ 95 mm c/c
4 ∗ 0.87 ∗ 500 ∗ 𝛱 ∗ 62 ∗ 1442
𝑉𝑢𝑠 =
100
= 4480.58 𝐾𝑁
𝑉𝑢′ = 𝑉𝑐 + 𝑉𝑢𝑠
= 4480.583 + 1118.415
Page | 104
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Page | 105
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
cae I
Sesmic combination of loads:
distance eccentrcity Mux Muy
load(KN) Pu(KN) Hx(KN) Hy (KN)
from x (m) y(m) (KN- (KN-m)
DLss 3843.92 1 3843.92 0
DLwc 330 1 330 0
FbrH 100 0.2 8.5 170 20
FbrV 11.11 0.2 2.222 0
Fs L 626.09 1 8.5 5321.8 626.09
Fs VL 22.54 1 22.54 0
L(stem)
Fs(sub) 66.8 1 3.5 233.8 66.8
Fs(sub) L (cap) 61.56 7.838 0
em)FhydL 6.7 1 3.65 24.455 6.7
Wpier 855.696 1 855.696 0
FwcT 21.2 1 4.867 0 103.18 21.2
FwcL 2.8 1 4.867 13.628 2.8
Fbuoy -107.95 0.15 -16.193 0
total (without LL) 5038.19 5763.6 103.18 722.39 21.2
LL' 779 0.2 0.335 155.8 52.193
total (with LL') 5193.99 5815.8 103.18 722.39 21.2
LL'' 1013.3 0.2 0 202.66 0
total (with LL'') 5240.85 5763.6 103.18 722.39 21.2
Page | 106
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
cae II
basic combination of loads:
distance eccentrcity Mux Muy
load(KN) from Pu(KN) Hx(KN) Hy(KN)
(KN-m) (KN-m)
bottom x (m) y(m)
DLss 3843.9 1.35 5189.292 0
DLwc 330 1.75 577.5 0
FbrH 100 1 8.5 850 100
FbrV 11.11 1.15 12.7765 0
FwT 26.79 1.5 8.5 341.57 40.185
Wpier 855.7 1.35 1155.19 0
FwcT 21.2 1 4.867 0 103.18 21.2
FwcL 2.8 1 4.867 13.628 2.8
Fbuoy -107.95 0.15 -16.1925 0
total (without LL) 6918.566 1205.2 103.18 142.985 21.2
LL' 779 1.5 0.335 1168.5 391.45
total (with LL') 8087.066 1596.6 103.18 142.985 21.2
LL'' 1013.3 1.5 0 1519.95 0
total (with LL'') 8438.516 1205.2 103.18 142.985 21.2
cae II
sesmic combination of loads:
distanc eccentrcity Mux Muy
load(KN) e from Pu(KN) Hx(KN) Hy (KN)
(KN-m) (KN-m)
bottom x (m) y(m)
DLss 3843.92 1 3843.92 0
DLwc 330 1 330 0
FbrH 100 0.2 8.5 170 20
FbrV 11.11 0.2 2.222 0
Fs T 626.09 1 8.5 5321.77 626.09
Fs VT 22.54 1 22.54 0
T(stem)
Fs(sub) 66.8 3.5
T(cap)
Fs(sub) 61.56 1 7.838 482.507 61.56
FhydT 6.7 1 3.65 24.455 6.7
Wpier 855.696 1 855.696 0
FwcT 21.2 1 4.867 0 103.1804 21.2
FwcL 2.8 1 4.867 13.6276 2.8
Fbuoy -107.95 0.15 -16.193 0
total (without LL) 5038.19 6012.35 103.1804 717.15 21.2
LL' 779 0.2 0.335 155.8 52.193
total (with LL') 5193.99 6064.55 103.1804 717.15 21.2
LL'' 1013.3 0.2 0 202.66 0
total (with LL'') 5240.85 6012.35 103.1804 717.15 21.2
Page | 107
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
7000 1800
= +
500 30
= 74 𝑚𝑚 > 20 𝑚𝑚
< 0.05 ∗ 1800 = 90 𝑚𝑚 ( 𝑂. 𝐾. )
𝑀𝑢𝑥 = 6012.35 𝐾𝑁𝑚
𝑀𝑢𝑦 = 103.84 𝐾𝑁𝑚
𝑃𝑢 = 5193.98 𝐾𝑁𝑚
𝑀𝑒,𝑚𝑖𝑛 = 𝑃 ∗ 𝑒𝑚𝑖𝑛 = 0.074 ∗ 5193.98 = 384.35 𝐾𝑁𝑚
Design Moment
𝑀𝑢𝑥 = 6012.35 𝐾𝑁𝑚
𝑀𝑢𝑦 = 384.35 𝐾𝑁𝑚
Assume, 𝑑 ′ = 70 𝑚𝑚
𝑝 % = 0.8%
𝑑′
= 0.038 ≈ 0.05
𝐷
From SP-16 code,
Chart 59
𝑑′ 𝑝 0.8
= 0.05 = = 0.04
𝐷 𝑓𝑐𝑘 20
Page | 108
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
𝑃𝑢 5193.98 ∗ 103
= = 0.08
𝑓𝑐𝑘 ∗ 𝐷2 20 ∗ 18002
𝑀𝑢1
= 0.065
𝑓𝑐𝑘 ∗ 𝐷3
𝑀𝑢1 = 0.065 ∗ 20 ∗ 18003
= 7581.6 𝐾𝑁𝑚
𝑃𝑢𝑧 = 0.4 ∗ 𝑓𝑐𝑘 ∗ 𝐴𝑐 + 0.75 ∗ 𝑓𝑦 ∗ 𝐴𝑠𝑐
Page | 109
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Page | 110
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Check
𝑀𝑢𝑥 𝛼 𝑀𝑢𝑦 𝛼
( ) 𝑛 +( ) 𝑛≤1
𝑀𝑢1 𝑀𝑢1
6012.35 1 384.35 1
( ) +( ) ≤1
7581.6 7581.6
0.85 ≤ 1 (𝑂. 𝐾. )
42-25 mm Ø bars
Ø1
80
0
Page | 111
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
𝑃𝑢 8438.52
Direct stress (𝜎𝑑 ) = =
𝐴 7.2∗7.2
𝜎𝑑 = 162.78 𝐾𝑁/𝑚2
𝑃𝑢 ∗𝑒∗6 8438.56∗6∗0.12
Bending Stress (𝜎𝑏 ) = =
𝑙3 7.23
𝐾𝑁
𝜎𝑏 = 19.37
𝑚2
Total Stress 𝜎𝑚𝑎𝑥/𝑚𝑖𝑛 = 𝜎𝑑 ± 𝜎𝑏
𝜎𝑚𝑎𝑥 = 𝜎𝑑 + 𝜎𝑏
= 162.78 + 19.37
= 182.15 𝐾𝑁/𝑚2
𝜎𝑚𝑖𝑛 = 162.78 − 19.37
= 143.4 𝐾𝑁/𝑚2
1) Check for Bending Moment
Bending moment is maximum at the face of the column
2.96362 1 2.9636
𝐵. 𝑀 = {166.2 ∗ + ∗ (182.15 − 166.2) ∗ 2.9636 ∗ 2 ∗ } ∗ 7.2
2 2 3
= 5591.35 𝐾𝑁𝑚
Depth Verification
𝐵. 𝑀 = 0.36 ∗ 𝑓𝑐𝑘 ∗ 𝑏 ∗ 𝑥𝑢 ∗ (𝑑 − 0.42 ∗ 𝑥𝑢,𝑙𝑖𝑚 )
𝑜𝑟, 5591.35 ∗ 106 = 0.36 ∗ 20 ∗ 7200 ∗ 0.46 ∗ (1 − 0.42 ∗ 0.46) ∗ 𝑑 2
𝑜𝑟, 5591.35 ∗ 106 = 2.672 ∗ 𝑏 ∗ 𝑑2
5591.35 ∗ 106
𝑑=√ = 539.1𝑚𝑚 < 1175 𝑚𝑚 (𝑂. 𝐾. )
2.672 ∗ 103 ∗ 7.2
Page | 112
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
𝐷 = 𝑑 + 75 = 1175 + 75 = 1250 𝑚𝑚
1272
7200
1272
7200
4604 2964
143.4
166.2 182.15
Design of Reinforcement
0.12
𝐴𝑠𝑡,𝑚𝑖𝑛 = ∗ 1250 ∗ 72000
100
= 10800 𝑚𝑚2
𝑓𝑦 ∗ 𝐴𝑠𝑡
𝐵. 𝑀. = 0.87 ∗ 𝑓𝑦 ∗ 𝐴𝑠𝑡 ∗ (𝑑 − )
𝑏 ∗ 𝑓𝑐𝑘
500 ∗ 𝐴𝑠𝑡
5591.35 ∗ 106 = 0.87 ∗ 500 ∗ 𝐴𝑠𝑡 ∗ (1175 − )
20 ∗ 7200
Solving, we get
𝐴𝑠𝑡 = 11307.82 𝑚𝑚2 > 𝐴𝑠𝑡,𝑚𝑖𝑛 (𝑂. 𝐾. )
𝑐
𝑃𝑟𝑜𝑣𝑖𝑑𝑒 20 𝑚𝑚 − 𝛷 𝑏𝑎𝑟 @ 175 𝑚𝑚 𝑖𝑛 𝑏𝑜𝑡ℎ 𝑑𝑖𝑟𝑒𝑐𝑡𝑖𝑜𝑛
𝑐
2
𝛱 ∗ 10
𝐴𝑠𝑡,𝑝𝑟𝑜𝑣𝑖𝑑𝑒𝑑 = ∗ 7200
200
= 11309.73𝑚𝑚2 > 𝐴𝑠𝑡,𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑑 (𝑂. 𝐾. )
Page | 113
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
𝑉𝑢 2283.78 𝑁
𝜏𝑣 = = = 0.27
𝑏 ∗ 𝑑 7.2 ∗ 1175 𝑚𝑚2
1272
7200
1272
1175
1789
7200
143.4
172.53
182.15
Page | 114
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
𝜏𝑐 = 0.25 ∗ √𝑓𝑐𝑘
= 0.25 ∗ √20
𝑁
= 1.118
𝑚𝑚2
Ø2975
7200
1800
7200
FIG: Check for Two Way Shear
Page | 115
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
= (0.5 + 1) = 1.5 ≤ 1
𝑘𝑐 = 1
𝑁
𝜏𝑐′ = 𝑘𝑐 ∗ 𝜏𝑐 = 1.118
𝑚𝑚2
7306.99
𝜏𝑣 =
9.346 ∗ 1175
= 0.665 < 𝜏𝑐′ (𝑂. 𝐾. )
Hence, design is safe.
Top reinforcement
Provide 20 mm-Φ bar@ 200 mm c/c
𝛱 ∗ 102
𝐴𝑠𝑡,𝑝𝑟𝑜𝑣𝑖𝑑𝑒𝑑 = ∗ 7200 = 11309.7 𝑚𝑚2 > 𝐴𝑠𝑡,𝑚𝑖𝑛 (𝑂. 𝐾. )
200
Check for Development Length
∅𝜎𝑠
Ld=4𝜏𝑏𝑑
25×0.58×500
= 4×1.2×1.6
=944mm
Page | 116
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Page | 117
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
S.N Description of works No. Length (m) Breadth(m) Height(m) Quantity(m3) Remarks
Super Structure
1 Deck slab 4 25 7.5 0.2 150
2 Cantilever slab 2 25 1.75 0.2 17.5
3 Kerb(Footpath) 8 25 1.75 0.225 78.75
4 Railing post
End 24 0.2 0.2 1.2 1.152 Approach &
Iintermediate 60 0.2 0.15 1.2 2.16 Deck slab
5 Cross Girder 0
End girder 24 2.5 0.4 1.35 32.4
Intermediate 48 2.5 0.3 1.35 48.6
6 Main Girder 0
Web 12 25 0.3 1.75 157.5
Fillet 24 25 0.3 0.15 27
I end (Triangle) 24 25 0.15 0.2 18
I end (Rectangular) 24 25 0.15 0.3 27
Total 560.062 M30 concrete
7 Approach slab 2 3.5 11 0.3 23.1
Sub structure
8 Pier Cap
3 9 1.4 1 37.8
3 1.9 1.4 0.5 3.99
6 3.55 1.4 0.5 7.455 V = (1/2)*l*b*h
9 Abutment cap 2 9 1.1 0.4 7.92
Total 80.265 M25 concrete
11 Abutment
Dirt wall 2 9 0.3 1.5 8.1
Stem wall 2 9 1 4.4 79.2
Fillet (Triangle) 2 9 0.1 0.1 0.09 V = (1/2)*l*b*h
12 Foundation
Abutment 2 9 5 1.2 108
Pier 3 7.2 7.2 1.2 186.624
Total 595.854 M20 concrete
Page | 118
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Page | 119
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
SITE PHOTOGRAPH
Page | 120
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Page | 121
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Page | 122
Design of RCC Bridge over Bagmati River at Sankhamul
Kathmandu- Lalitpur
HCOE/071/BCE
Page | 123