FE Review - Construction
FE Review - Construction
University of Florida
Topic 1
Project Scheduling
University of Florida
1
Scheduling
Grouping of Activities
Common constraints (ex. Load and non-load bearing walls)
• Labor
• Precedent activity
• Equipment
Continuous tasks (ex. Floor slab and floor covering)
Different attributes (excavation and placement and compaction of fill
materials and utility lines)
Long Lead Items – Chillers
Types of Schedules
Activity on Arrow
Activity on Node
Linear schedules
• Activities that are linear in nature
Bar charts
• Software developed bar charts
• Simple bar chart
o Bar Charts do not show the relationship between activities.
o Which activities must be completed before an activity can start?
o Which activities are critical so that any delay to them will delay the
project?
2
Types of Project Scheduling Methods
Activity On Arrow (AOA) Diagrams
Activity-on-Branch
May have dummy tasks
Finish to start precedence only
Activity on Arrow
Diagrams
3
AOA Precedence Relationships
B
A
A must finish before either B or C can start
C
A
A and B must finish before C can start
C
B
A C
A and B must finish before either C or Dcan
start
B D
A B
Dummy
C D
4
Dummy Activity Example
To be able to bolt a bracket to a panel, the
operations required are :
1 2 3
A A B A B
D
C C D C D
5
Critical Path Example
The project sequence diagram is constructed:
Activity Duration Precedence
A 3 -
B 6 A
C 10 A
B D 11 A
A
C
Project
Start D
E
E
B
A
C F
Project F
D G
Start
6
Critical Path Example
E
B
A
C
F
Project G Project
Start D End
B E
6 8
A C
3 10 F
Project D 5 G Project
Start 11 6 End
7
Critical Path Method (CPM) - Example
B E
6 8
A C
3 10 F
Project D 5 G Project
Start 11 6 End
B E
6 8
A C
3 10 F
Project D 5 G Project
Start 11 6 End
8
Critical Path Method (CPM) - Example
B E
6 8
0 A 3 C 13 24
3 10 F
Project D 5 G Project
Start 11 6 End
18
9
Critical Path Method (CPM) - Example
The CRITICAL PATH is the path along which the earliest
time and latest time are the same for all events, and
the early start time plus activity time for any activity
equals the early start time of the next activity.
9
16 .
B E
6
8
0 A 3
C 13 24
0 3 10 13 24
3 F
Project D G Project
5
Start 11 6 End
18
18
10
Critical Path
11
Arrow on Node
Diagrams
Logic Diagrams
Activity on Node, (AON)
Activities are represented as nodes and arrows represent the relationship
between activities. Complex relationships can be represented.
20 40
Build Wall Found. Build CMU Wall
Dur= 10 Dur= 15
10 60
Start Build ceiling beams
Dur= 0 Dur= 5
30 50
Build Col Found. Build Columns
Dur= 15 Dur= 15
12
AON Diagram Elements
Key Elements
• Early Start Date
• Late Start Date
• Early Finish Date
• Late Finish Date
• Duration
Types of Relationships
Precedence
An activity follows another
Concurrent
Activities can be performed at the same time
Explicit
Activities that have a direct relationship. These are the only ones that
need to be represented.
Simple
Activity B cannot start until activity A finishes (Finish to start, FS)
13
Complex Relationships
Start to Start, SS –
Activity B cannot start until
activity A starts
Finish to Finish, FF –
Activity B cannot finish
until activity A finishes
Lags
Refers to delays or leads added to the relationships.
L=2
L=-2
14
Tasks Times
Early Start, ES
The earliest time and activity can start given all constraints
Early finish, EF
The earliest an activity can finish given all constraints
Late start, LS
The latest time and activity can start without delaying the project
Late finish, LF
The latest time and activity can finish without delaying the project.
Task Floats
Total Float, TF
Critical activities have a total float of zero. Is the amount of time an
activity can be delayed without delaying the project.
TF=LF-Dur-ES
Starting Float, SF
The start of a task can be critical without the whole activity being critical.
The difference between the late start and early start.
SF=LS-ES
Finish Float, FF
The finish of a task can be critical without the whole activity being critical.
Difference between Late finish and early finish.
FF=LF-EF
15
Graphic Representation of PM
ES Act. # EF
Rel #
Activity Description and Duration Lag
LS TF LF
TF= LF –Dur-ES
Example 2 - AON
ES # EF
Des / Dur
20 LS TF LF
50
B 15 40 E 9 60
10
10
A 5 30 2
70
20 C 10 50
G 4
30 70
60
F 6 80
3
40
D 13
16
Example 2 - AON
Forward Pass
Example 2 - AON
Forward Pass ES # EF
5 20 20 LS TF LF
20 50 29
B 15 40 E 9 60
10
0 10 5
A 5 5 30 15 2 31 70 35
20 C 10 50
G 4
30 70
15 60 21
F 6 80
3
8 40 21
D 13
17
Example 2 - AON
Backward Pass
Example 2 - AON
Backward Pass
ES # EF
5 20 20 LS TF LF
20 50 29
B 15 40 E 9 60
10 5 20
20 29
0 10 5
A 5 5 30 15 2 31 70 35
0 5 20 50
C 10 G 4
15 25 70
15 60 21 31 35
30
F 6 80
3
25 31
8 40 21
D 13
18 31
18
Example 2 - AON
Determining the Critical Path
ES # EF
5 20 20 LS TF LF
20 50 29
B 15 40 E 9 60
10 5 0 20
20 0 29
0 10 5
A 5 5 30 15 2 31 70 35
0 0 5 20 50
C 10 G 4
30 15 25 70
15 60 21 31 0 35
F 6 80
3
25 31
8 40 21
D 13
18 31
Example 2 - AON
Calculating Total Float ES # EF
5 20 20 LS TF LF
20 50 29
B 15 40 E 9 60
10 5 0 20
20 0 29
0 10 5
A 5 5 30 15 2 31 70 35
0 0 5 20 50
C 10 G 4
30 15 10 25 70
15 60 21 31 0 35
F 6 80
3
8 40 21
25 10 31 TFC=25-5-10
D 13 TFC=10
18 10 31
19
Example 2 - AON
Calculating Free Float ES # EF
5 20 20 LS TF LF
20 50 29
B 15 40 E 9 60
10 5 0 20
20 0 29
0 10 5
A 5 5 30 15 2 31 70 35
0 0 5 20 50
C 10 G 4
30 15 25 70
15 60 21 31 0 35
F 6 80
3 FFDG=ESG-EFD
25 31
8 40 21
FFDG=31-21
D 13 FFDG=10
18 31
Topic 5
Earned Value Analysis
University of Florida
20
Earned Value Analysis
Definitions – Refer to the Manual
Earned Value Analysis
BCWS – Budgeted cost of work scheduled (planned)
ACWP – Actual cost of work performed (Actual)
BCWP – Budgeted cost of work performed (Earned)
Variances
Cost Variance (CV)
Schedule Variance (SV)
CV = PCWP – ACWP - - (Earned – Actual)
SV = BCWP – BCWS - - (Earned – Planned)
21
Earned Value Analysis
PV – Planned Value or Budgeted Cost of Work Scheduled
22
Earned Value Analysis
EV- Earned Value or Budgeted Cost of Work Performed
23
Earned Value Analysis
Performance Metrics @ “June 03”
Schedule Performance Index
SPI: EV/PV = 49,000/55,000 = 0.891
18
14
On Day X:
PLANNED VALUE (Budgeted cost of the work scheduled, BCWS)
BCWS = 18 + 10 + 16 + 6 = 50
EARNED VALUE (Budgeted cost of the work performed, BCWP)
BCWP = 18 + 8 + 14 + 0 = 40
ACTUAL COST (of the work performed , ACWP)
ACWP = 45 (from your project tracking - not evident in above chart)
24
Earned Value: Example
Time (Date)
Today
Cost (Person-Hours)
Over Budget
Behind
Schedule
Time (Date)
25
Project Size Modifiers
University of Florida
26
Table from Reference book p.176
27
Project Size Modifier Curve / Figure
Multiplier = 1.06
Now apply to area
28
Project Cost Modifier Figure:
Modified cost estimate (based on size) :
∗
18,000 $67.00/ ∗ 1.06 = $1,278,360
29
Extra Topic 1 – Earth Moving
University of Florida
30
Types of Geotechnical Materials
Gravel is rounded or semi-round
particles or rock that will pass a 3 in
and be retained on a 2.0 mm #10 sieve
Sizes larger than 10 in are usually
called boulders
Sand is disintegrated rock whose
particles vary in size from the lower
limit of gravel 2.0 mm down to 0.074
mm (#200 sieve).
Sand can be classified as coarse or fine
sand, depending on the sizes of the
grains
Silt is a material finer than sand, and
thus its particles are smaller than 0.074
mm but larger than 0.005 mm
31
Soils
Bank cubic yards (bcy) In situ-
Loose cubic yards (lcy)
Compacted cubic yards (ccy)
Soils
Bank cubic yards (bcy) In situ-
Loose cubic yards (lcy)
Compacted cubic yards (ccy)
32
Shrink and Swell Factors
– ∗
%
.
% ∗ 100
. –
% – %
x
x
.
33
Application Rate
The water application rate is normally calculated in gallons per square
yard
%
x
x ,
/
x
. /
Application methods
Water Distributor
Ponding
34
Application methods
Sprinkling
The most common method of reducing moisture is to scarify the soil prior
to compaction
35
Reducing Moisture Content
A Motor Grader Using Rippers to Scarify Material
36
Optimum Water Content
The Optimum Water Content for compaction varies from about 12 to 25%
for fine-grained soils and from 7 to 12% for well-graded granular soils
After water is added, it must be thoroughly and uniformly mixed with the
soil
Extra Topic 2
Earthmoving Operations
University of Florida
37
Machine Performance
Cycle time and payload determine a machine’s production rate, and
machine travel speed directly affects cycle time.
The three power questions:
1. Required Power
2. Available Power
3. Usable Power
Resistance
Rolling Resistance (RR)
• The resistance of a level surface to constant-velocity motion
38
Rolling Resistance
Representative rolling resistances for various types of surfaces
Grade Resistance/Assistance
The force-opposing movement of a machine up a frictionless slope is
known as grade resistance.
It acts against the total weight of the machine, whether track type or
wheel type.
39
Frictionless Slope-Force Relationships
Components
sin
cos
• For angles less than 10°, sin (α) ≈ tan (α)
(the small –angle theorem) reduces to:
%
∗
20 / ∗ %
Total Resistance
Total resistance can also be expressed as an effective grade.
/
%
/
40
Rim Pull Equation
Rim Pull
375 ∗ ∗
The efficiency of most tractors and trucks will range from 0.80 to 0.85
(use 0.85 if efficiency is not known).
Drawbar Pull
The towing force a crawler tractor can exert on a load is referred to as
drawbar pull.
If a crawler tractor tows a load up a slope, its drawbar pull will be reduced
by 20 lb for each ton of weight of the tractor for each 1% slope.
41
Performance Charts
Equipment manufacturers publish
performance charts for individual
machine models.
Performance Charts
What is the maximum speed (and gear) for a grader
pulling/pushing a 25000 lb load?
42
Performance Charts
What is the maximum speed (and gear) for a grader
pulling/pushing a 5000 lb load?
Performance Charts
Performance Chart - Scraper
43
Example 1
44
Performance Charts – Step 2
What is the maximum speed (and gear) for a scraper
which has Gross Vehicle Weight (GVW) of 100,000 lb
with 10% total resistance?
Draw a vertical line to
the total resistance
(10% in this case)
45
Performance Charts – Step 4
What is the maximum speed (and gear) for a scraper
which has Gross Vehicle Weight (GVW) of 100,000 lb
with 10% total resistance?
Example 2
46
Performance Charts – Example 2 - Step 1
What is the maximum speed (and gear) for a scraper
which has Gross Vehicle Weight (GVW) of 22,000 lb
with 10% total resistance?
Again, start at the top
GVW = 22K
47
Performance Charts – Example 2 - Step 3
What is the maximum speed (and gear) for a scraper
which has Gross Vehicle Weight (GVW) of 100,000 lb
with 10% total resistance?
48
Extra Topic 3
Earthwork Analysis and Mass Haul
Diagrams
University of Florida
Introduction
49
Excavation – Roadway Construction
Includes:
Cut
Loading and Hauling
Placement in fill site
Compaction
Shaping for finished grade
50
Average End Area Method
V = 2,350 yd3
51
Haul Distance
Distance material is transported
From cut section to fill section
From borrow pit to fill section
From cut section to waste pit
Free Haul Distance (FHD):
Maximum distance material is transported by the
contractor without additional payment
Specified in construction contract
Cost incorporated into the excavation cost
Overhaul:
Any transported distance over the free haul distance
Overhaul - Example
Overhaul compensation is charged in units of sta-CY
or station-yards for the distance past FHD
Overhaul = CY * (haul distance – FHD)
52
Overhaul Problem
Overhaul cost = $2/sta-yards * 400 CY * ( 20 stations-12
stations)
53
Limit of Economic Haul Problem
A contractor is determining the limit of economic haul
for a project. The free haul distance was determined to
be 800 feet. The borrow and waste costs are $22/CY
and $6/CY, respectively. The roadway excavation cost
is $12/CY and the overhaul cost is $2/sta-yard. What is
the LEH?
LEH = 16 stations
Shrinkage Factors
Compacted material takes up less volume than uncompact
material with the same mass
A shrinkage factor (SF) is used to account for this volume
change
A shrinkage factor only applies to fill sections
54
Rock Cuts
Rock cuts are an exception and do not need a
shrinkage factor applied to a fill section
Expands in fill section
Rock that is pulverized and blasted takes up more
volume
Earthwork Quantities
Construction quantities needed for various
construction items/operations
Clearing and Grubbing
Excavation
Overhaul
Borrow
Waste
Tables of quantities (itemized lists) are included in
plan drawings
Contractors use these quantities for bidding
Earthwork quantities incorporate shrinkage factors
55
Cut and Fill
Profile View
56
Mass Haul Diagrams
57
Characteristics of Mass Haul Diagram
58
Characteristics of Mass Haul Diagrams
Balance points – the point at which the prior excavated material can fill an
embankment
Points a, c, and d
Balancing lines - horizontal lines intersecting the mass curve show lengths
over which the cutting and filling are equalized
Line xy quantifies the cut from X to B and the fill from B to Y
The volume being moved is the vertical distance b to z
Maximum haul distance – length of balancing line intercepted by the
mass curve
If the curve lies above the balancing line, the material must be hauled
forward.
If the curve lies below the balancing line, the material must be hauled
backward.
59
Mass Diagram Creation - Revisited
60
Overhaul by Methods of Moments
Steps
1. Create mass diagram
2. Plot cumulative yardage on y-axis
3. Plot stations on X-axis as the baseline
4. Negative (-) cumulative yardage is fill and plotted below
baseline. Positive (+) cumulative yardage is cut and plotted
above baseline.
5. Determine free haul distance on plot
6. Sum moments of overhaul about the stations where the
plotted free haul distance intercepts mass diagram
7. The total overhaul cost = (Sum of overhaul distances) X
(Overhaul yardage) X (Overhaul cost)
61
Overhaul - Method of Moments Example Cont’d
Overhaul
Free haul
A3 distance
A2
Overhaul
A1
62
Overhaul - Method of Moments Example Cont’d
Free haul
Overhaul distance
Overhaul
63
Mass Haul Example
The mass diagram represents the cut of 50,000-yd3
between station 40+00 and the upward balance point
at station 100+00 and a fill of 20,000-yd3 to the
upward transition point at station 130+00. Find the
average haul distance from station 40+00 through the
second transition point:
50,000 cy
25,000 cy 10,000 cy
20,000 cy
64