Quality Control & Tests Plan: BAZ-KSA-QAC-034

This document provides a quality control and testing plan for an irrigation and landscaping project. It outlines the following key points: 1. Factory acceptance, provisional site acceptance, final site acceptance, and final project acceptance tests will be conducted to ensure system requirements are met. 2. Tests will check instruments, autonomous weather stations, meteorological information and processing systems, and the integrated network. 3. The contractor is responsible for providing test plans, procedures, and reports for customer review and approval before conducting integration tests.

Uploaded by

Raghad G
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
147 views12 pages

Quality Control & Tests Plan: BAZ-KSA-QAC-034

This document provides a quality control and testing plan for an irrigation and landscaping project. It outlines the following key points: 1. Factory acceptance, provisional site acceptance, final site acceptance, and final project acceptance tests will be conducted to ensure system requirements are met. 2. Tests will check instruments, autonomous weather stations, meteorological information and processing systems, and the integrated network. 3. The contractor is responsible for providing test plans, procedures, and reports for customer review and approval before conducting integration tests.

Uploaded by

Raghad G
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 12

IFU :Status 1.0 :.

Rev Quality Control & Tests Plan


12 of 1 :Page BAZ-KSA-QAC-034 :.Document No

Introduction

Bazaar Alkhaleej Co. already have template documents to cover all aspects of the Quality Control , Procurements of all
Irrigation System and Landscaping Activities.

Efficiency and effectiveness. Both proper selection and correct installation of products with respect to plant water
.requirements and microclimate variables

Elements of a Successful Installation

Quality design, product and installation information •

Quality construction documents •

Quality execution of plans via irrigation construction management •


IFU :Status 1.0 :.Rev Quality Control & Tests Plan
12 of 2 :Page BAZ-KSA-QAC-034 :.Document No

1 TEST PROCEDURES
Shall prove by tests the correct operation and well-functioning of the System according to the specifications, Requirement Specifications, of the
Agreement.

2 TEST REQUIREMENTS
.The following tests have to be performed before the system as a whole can be approved for operational services

1. Factory Acceptance Test (FAT)


All instruments, AWS stations and MIPS shall go through a Factory Acceptance Test (FAT) at the Contractors facilities. The components
and the system as a whole shall be tested in the same configuration that shall be installed in the field on the observation sites. If ‘real’
data input is not available, it shall be provided by a simulation system. Factory Acceptance (FA) shall follow FAT if the all requirements
as defined in the Requirement Specifications document are met.
2. Provisional Site Acceptance Test (PSAT)
After delivery and installation of the AWS stations and the MIPS, the PSAT shall be performed for the AWS including instruments, and
for the MIPS (including display systems) separately. Provisional Site Acceptance (PSA) shall follow PSAT if the requirements as defined
in the Requirement Specifications document are met.
3. Final Site Acceptance Test (FSAT)
After the AWS’ with instruments and the MIPS passed their PSA, a reliability test shall be performed. This test shall in general take more
time (1 week to 3 months in total), in which the system as a whole shall work uninterruptedly without critical failures, to demonstrate its
IFU :Status 1.0 :.Rev Quality Control & Tests Plan
12 of 3 :Page BAZ-KSA-QAC-034 :.Document No

reliability. Final Site Acceptance (FSA) shall follow FSAT if the requirements as defined in the Requirement Specifications document
are met.
4. Final Project Acceptance Test (FPAT) The integration of all instruments, AWS’ and MIPS finally results in the meteorological
observation network. The final project acceptance test includes all deliverables from the project, the instruments, AWS’, the MIPS and
display, but also training, all documentation, spare parts, etc. Final Project Acceptance (FPA) shall follow FPAT if the requirement
specifications as defined in the Requirement Specifications document are met.

3 SYSTEMS TO BE TESTED
All system components shall be subjected to a FAT. FAT-reports per system component shall be submitted for The same procedure shall be
.followed for the PSAT and FSAT

:Integration tests (FAT, PSAT, FSAT, FPAT) shall include

1. Instruments
For all instruments tests shall be conducted to demonstrate that they comply with the requirement specifications.
2. Complete AWS with Instruments
The complete AWS (cabinet, data logger, power supplies, lightning protection, heating, housekeeping measurements, etc.) with
instruments connected, shall be tested as complete systems to demonstrate compliance with the requirement specifications.
3. MIPS
The MIPS functionality shall be tested per requirement specification. Test data may be used to demonstrate the generation of reports.
4. Combining AWS’ and the MIPS
Complete AWS stations with instruments shall be connected to the MIPS. Data communication shall be tested, as well as the complete
chain from instrument measurements to report generation. The connection to and sending of reports to the message switch shall be tested.
IFU :Status 1.0 :.Rev Quality Control & Tests Plan
12 of 4 :Page BAZ-KSA-QAC-034 :.Document No

4 TESTING
To test and verify the conformance of the system the Contractor shall present a Test Plan, Test Description, and Test Reports which are all
.subject to Purchaser review and approval

The Contractor shall conduct all tests in accordance with the approved Test Plan and Test Descriptions. The Contractor shall perform test -1
briefings and debriefings as required, and prepare quick-look summaries of the test results

.At least three weeks prior to any testing requiring Purchaser’s attendance, the Contractor shall notify the Purchaser -2 .

If re-verification is required as a result of any verification defect or deficiency, the Contractor shall perform these re-verifications without -3
.additional costs

4.1 Factory acceptance tests


The Contractor shall provide the Factory Test Procedure in accordance with the Test Plan, Test Procedures and Test Reports for Purchaser
.review and approval

Procedures for final inspection and testing shall ensure that inspections and tests that should have been conducted at earlier stages .1
.have been performed. Successful completion of these tests shall be acknowledged by a certificate of conformity

In presence of the Purchaser, if he requires so, the Contractor shall collect and analyse all system test data to verify that all test objectives .2
.are met and to ensure that deficiencies are noted and solved

.Both a designated Contractor representative and a Purchaser representative shall sign the recorded verification test data sheets .3
IFU :Status 1.0 :.Rev Quality Control & Tests Plan
12 of 5 :Page BAZ-KSA-QAC-034 :.Document No

4.2 On-site acceptance tests


The Contractor shall provide an On-Site Acceptance Test Plan as part of the Test Plan, Test Procedures and Test Reports for Purchaser’s review
.and approval. The Contractor shall conduct the verification tests in accordance with the approved On-Site Acceptance Test Plan

In presence of the Purchaserthe Contractor shall collect and analyse all system test data to verify that all test objectives are met and to -1
.ensure that deficiencies are noted and solved

.Both a designated Contractor representative and an authority representative shall sign the recorded verification test data sheets -2

5 QUALITY CONTROL & TEST PLAN


:This description delineates the overall plan for the system tests. The Contractor shall prepare a Test Plan with content as follows

.Purpose
This section shall state the purpose of the Test Plan and shall identify the phase to which it applies. The purpose shall be stated in terms
of establishing detailed requirements, criteria, general methods, responsibilities, and overall planning to confirm, in accordance with the
specifications, that the system or designated portions of it, fulfils the requirements of the specification. Reasons for excluding any
.portions of the system from this Test Plan shall be stated

.General Requirements
Discuss pertinent background information and functions performed, and include a brief overall description of the system, overall
.responsibility for the execution of the Test Program and overall schedules

.Description of the Test Item


.Indicate the number of test items involved and the features which positively identify the items
IFU :Status 1.0 :.Rev Quality Control & Tests Plan
12 of 6 :Page BAZ-KSA-QAC-034 :.Document No

.Participating Organisations
List each of the participating organisations and their basic responsibilities and tasks. Include a breakdown of the test force functional
.organisation and a time-phased listing of test force personnel requirements by organisations and job title

.Milestones and Schedules


The plan should include an overall flow diagram of the entire Test and deployment program as outlined. This flow shall be sequentially
arranged to include all significant Test milestones and any additional information which clarifies the description of the Test program.
.The schedule includes identification of the milestone, start and finish dates and the associated location

.Test Support Requirements


Include the technical and logistic support required to perform the Test and identify special facilities, support equipment and personnel
required to support the Test. Considerations should be given to such items as electronics, computer programs, facilities, ranges,
simulation, and material. Provide a schedule of critical support requirements showing time, duration, for furnishing the support items.
Provide calibration information, which will define and describe all systems requiring calibration. All responsibilities during Test shall
.be addressed in this section

.Security Requirements
.Provide the security classification of equipment, test, test-results, documents and other material related to the test program

.Specific Test Objectives


Include or reference the list of those objectives, which are necessary to fulfil the applicable requirements contained within the system
.specification and any applicable functional specifications
IFU :Status 1.0 :.Rev Quality Control & Tests Plan
12 of 7 :Page BAZ-KSA-QAC-034 :.Document No

.Test Methods and Descriptions


Outline in general terms the test execution to fulfil each of the objectives identified in the specifications, in order to provide guidance
.for the preparation of more detailed test descriptions

.Data Collection, Reduction and Analysis


Provide an analysis plan which, taking into account the test objectives, indicates the type of data required and its processing. Specify the
form in which the reduced data is to be presented. Outline analysis methods, criteria, and the presentation of final results. Relate results
to specified objectives described in the specifications. Include requirements for data processing equipment (including approximate
computer time required) and any special computer programs required for data collection/analysis. Identify Contractor’s (and sub-
.contractor’s) responsibilities for their respective tasks

.Instrumentation
Indicate the instrumentation required to collect the data indicated in item 10. above and the organisation responsible for acquiring it. A
.block diagram layout of the system showing instrumentation’s points should be included

.Personnel Subsystem Test and Evaluation


.Discuss plans for training operator personnel for active participation in the test program

Control and Reporting Procedures.


Specify requirements and procedures for controlling the Test Plan and for documenting the test procedures and results. Include the following
subsections: control of Test Plan, documentation of test procedures and documentation of system results summary.
Defect classification
In the event a test case within a Test should fail, a report on the defects shall be prepared. To maximise test case results and to minimise
problems attributable to defects, all reports on defects will be classified as follows:
IFU :Status 1.0 :.Rev Quality Control & Tests Plan
12 of 8 :Page BAZ-KSA-QAC-034 :.Document No

 Category A: major defect;


 Category B: average defect;
 Category C: minor defect;
 Category D: test error;
 Category E: dispute concerning an incident.
All categories are described below:
Category A: major defect
Category A defects are defects which adversely affect the system components’ or system’s active operation to such an extent that,
unavoidable, a major part of the system can no longer be used.
Category B: average defect
Category B defects are localised problems, which do not make the system components’ or system’s active operation impossible
(non-serious errors, which do not seriously affect the system). Category B defects shall be no reason to discontinue the test.
Category C: minor defect
Category C defects are related to appearance and do not have serious adverse effects on the system components or system, and its
active operation could continue without eliminating the defects (such as unclear error messages, errors in reports and screen
formats). Category C defects shall be no reason to discontinue the test.
Category D: test error
Category D defects are due to errors in the test method and/or test data, errors occurring while carrying out the test case, or errors
in expected results. In the event of a conflict between Contractor and Purchaser, parties shall discuss about the validity of the test
case, and if the error shall be reclassified into Category E. Category D defects shall be no reason to discontinue the test.
IFU :Status 1.0 :.Rev Quality Control & Tests Plan
12 of 9 :Page BAZ-KSA-QAC-034 :.Document No

Category E: dispute concerning an incident


Category E defects are defects for which Contractor and Purchaserfail to reach an agreement on classification. If the parties fail to
reach an agreement within 5 (five) working days, the issue will be submitted to an independent person to be appointed, after due
consulting, by the parties involved. The decision by the appointed person will be final and binding for both parties.
It is emphasised that any Category B, C, D or E defects occurring during a test shall not result in the discontinuation of that test. In the event of a
Category A defect, both parties will have the right to decide independently whether or not to stop the test. In this case, a new date will be set,
agreed to by both parties, on which the test shall be repeated. With the exception of Category A errors, during re-testing only those test cases that
have not yet been successfully completed will be exercised.
At the end of each testing day, there will be a meeting in which Contractor and Purchaserwill record the findings of that day. This report shall be
.approved by both parties
IFU :Status 1.0 :.Rev Quality Control & Tests Plan
12 of 10 :Page BAZ-KSA-QAC-034 :.Document No

Inspection and Test Plan


Customer: INSPECTION AND TEST PLAN for:
Contract Number: Work area:
Contract/Project Name:
Ref Operation or stage of work Stage/ Records Requirement/ Acceptance Inspection/ test Inspection *what/who
Description Characteristics frequen standard/ specification criteria procedure Employee Service provider Customer
cy

*W = Witness Point; H = Hold Point; H(A) = Inspection/Test by Authority; U(C) = Inspection/Test by Consultant; S = Surveillance or monitoring; X = Self inspection by performer of
work.
IFU :Status 1.0 :.Rev Quality Control & Tests Plan
12 of 11 :Page BAZ-KSA-QAC-034 :.Document No

INSPECTION AND TEST PLAN CHECKLIST for:


(To be completed by the person(s) directly responsible for the work)
Contract Number: Work area: Checklist Number:
Contract/Project Name:
Contractor:
Subcontractor
Work Items/activities to be verified Reference Initialled/OK Comments

I have carried out allnecessary inspections and verify that the above items/activities conform to Name:
the contract specification/documents
Signature:

Date:
IFU :Status 1.0 :.Rev Quality Control & Tests Plan
12 of 12 :Page BAZ-KSA-QAC-034 :.Document No

I have carried out allnecessary inspections and verify that the above items/activities conform to Name:
the contract specification/documents
Signature: