Ventilation Duct Installation Plan

The document outlines a duct installation project that will take place from October 1st to October 28th. It includes 10 activities like fabrication of hangers, installation of various duct components, and installation of a grille. Each activity has its own duration and scheduled dates. A second project is also described to install a ventilation system from November 1st to December 1st.

Uploaded by

roland mago
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
345 views5 pages

Ventilation Duct Installation Plan

The document outlines a duct installation project that will take place from October 1st to October 28th. It includes 10 activities like fabrication of hangers, installation of various duct components, and installation of a grille. Each activity has its own duration and scheduled dates. A second project is also described to install a ventilation system from November 1st to December 1st.

Uploaded by

roland mago
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 5

PROJECT START

PROJECT NAME PROJECT DURATION PROJECT END DATE


DATE

DUCT INSTALLATION FOR VENTILLATION 27 10/1/2020 10/28/2020

10/1/2020

10/2/2020

10/3/2020

10/4/2020

10/5/2020

10/6/2020

10/7/2020

10/8/2020
ACTIVITY DESCRIPTION
ACTIVITY
NO ACTIVITY DURATION START DATE END DATE
1 FABRICATION OF HANGER & SUPPORT 5 10/1/2020 10/6/2020
2 INSTALLATION OF SPDR 2 10/7/2020 10/9/2020
3 SEALANT 2 10/10/2020 10/12/2020
4 INSTALLATION OF EADR 2 10/13/2020 10/15/2020
5 INSTALLATION OF TOILET EXHAUST DUCT 1 10/16/2020 10/17/2020
6 INSTALLATION OF BRANCH FOR TED 1 10/18/2020 10/19/2020
7 INSTALLATION DUCT GASKET 1 10/20/2020 10/21/2020
8 INSTALL FIRE DAMPER 1 10/22/2020 10/23/2020
9 VOLUME DAMPER 1 10/24/2020 10/25/2020
10 INSTALL GRILLE 2 10/26/2020 10/28/2020
10/9/2020

10/10/2020

10/11/2020

10/12/2020

10/13/2020

10/14/2020

10/15/2020

10/16/2020

10/17/2020

10/18/2020

10/19/2020

10/20/2020

10/21/2020

10/22/2020

10/23/2020

10/24/2020

10/25/2020

10/26/2020

10/27/2020
PROJECT START
PROJECT NAME PROJECT DURATION PROJECT END DATE
DATE

VENTILLATION SYSTEM B1 30 11/1/2020 12/1/2020

11/10/2020

11/11/2020

11/12/2020

11/13/2020

11/14/2020

11/15/2020

11/16/2020

11/17/2020

11/18/2020

11/19/2020

11/20/2020

10/21/2020

11/22/2020

11/23/2020

11/24/2020

11/25/2020

11/26/2020

11/27/2020

11/28/2020

11/29/2020

11/30/2020
11/1/2020

11/2/2020

11/3/2020

11/4/2020

11/5/2020

11/6/2020

11/7/2020

11/8/2020

11/9/2020

12/1/2020
ACTIVITY DESCRIPTION
ACTIVITY
NO ACTIVITY DURATION START DATE END DATE
1 FABRICATION OF HANGER & SUPPORT 5 11/1/2020 11/6/2020
2 VOLUME DAMPER 2 11/7/2020 11/9/2020
3 INSTALLATION OF EAD 5 11/10/2020 11/15/2020
4 INSTALL FIRE DAMPER 2 11/16/2020 11/18/2020
5 INSTALLATION OF SAG 1 11/19/2020 11/20/2020
6 INSTALLATION OF SAD 1 11/21/2020 11/22/2020
7 INSTALLATION DUCT GASKET 1 11/23/2020 11/24/2020
8 PERIMETER OF DUCT SEALANT 1 11/25/2020 11/26/2020
9 VOLUME DAMPER 1 11/27/2020 11/28/2020
10 INSTALLATION OF EXHAUST AIR GRILLE 2 11/29/2020 12/1/2020

PROJECT START
PROJECT NAME PROJECT DURATION PROJECT END DATE
DATE
VENTILLATION SYSTEM 2ND FLOOR 30 11/1/2020 12/1/2020

11/10/2020

11/11/2020

11/12/2020

11/13/2020

11/14/2020

11/15/2020

11/16/2020

11/17/2020

11/18/2020

11/19/2020

11/20/2020

11/21/2020

11/22/2020

11/23/2020

11/24/2020

11/25/2020

11/26/2020

11/27/2020

11/28/2020

11/29/2020

11/30/2020
11/1/2020

11/2/2020

11/3/2020

11/4/2020

11/5/2020

11/6/2020

11/7/2020

11/8/2020

11/9/2020

12/1/2020
ACTIVITY DESCRIPTION
ACTIVITY
NO ACTIVITY DURATION START DATE END DATE
1 FABRICATION OF HANGER & SUPPORT 4 11/1/2020 11/5/2020
2 INSTALLATION OF JET FAN 3 11/6/2020 11/9/2020
3 INSTALLATION OF EXHAUST AIRDUCT 5 11/10/2020 11/15/2020
4 INSTALL FIRE DAMPER 2 11/16/2020 11/18/2020
5 INSTALLATION OF SAG 1 11/19/2020 11/20/2020
6 INSTALLATION OF FAD 1 11/21/2020 11/22/2020
7 INSTALLATION OF EAD W/ INSECT SCREEN 1 11/23/2020 11/24/2020
8 PERIMETER OF DUCT SEALANT 1 11/25/2020 11/26/2020
9 INSTALLATION OF EXHAUST AIR GRILLE 1 11/27/2020 11/28/2020
10 ROUGHING INS/ THERMOSTAT CONTR0LER 2 11/29/2020 12/1/2020
PROJECT START
PROJECT NAME PROJECT DURATION PROJECT END DATE
DATE

VENTILLATION SYSTEM 2ND FLOOR 29 11/1/2020 11/30/2020

10/1/2020

10/2/2020

10/3/2020

10/4/2020

10/5/2020

10/6/2020

10/7/2020

10/8/2020
ACTIVITY DESCRIPTION
ACTIVITY
NO ACTIVITY DURATION START DATE END DATE
1 FABRICATION OF HANGER & SUPPORT 4 11/1/2020 11/5/2020
2 INSTALLATION OF JET FAN 2 11/6/2020 11/8/2020
3 INSTALLATION OF EXHAUST FAN 5 11/9/2020 11/14/2020
4 INSTALL FIRE DAMPER 2 11/15/2020 11/17/2020
5 INSTALLATION OF SAG 1 11/18/2020 11/19/2020
6 INSTALLATION OF FAD 1 11/20/2020 11/21/2020
7 INSTALLATION OF EAD W/ INSECT SCREEN 1 11/22/2020 11/23/2020
8 PERIMETER OF DUCT SEALANT 1 11/24/2020 11/25/2020
9 INSTALLATION OF EXHAUST AIR GRILLE 1 11/26/2020 11/27/2020
10 ROUGHING INS/ THERMOSTAT CONTR0LER 2 11/28/2020 11/30/2020
10/9/2020

10/10/2020

10/11/2020

10/12/2020

10/13/2020

10/14/2020

10/15/2020

10/16/2020

10/17/2020

10/18/2020

10/19/2020

10/20/2020

10/21/2020

10/22/2020

10/23/2020

10/24/2020

10/25/2020

10/26/2020

10/27/2020

10/28/2020

10/29/2020

10/30/2020

12/1/2020

You might also like