Summary of Estimated Cost: Item No. and Description I.) Fire Detection and Alarm System II.) Fire Sprinkler System

This document provides an estimate for the completion of a three-storey commercial and residential building located in Baloy, Tablon, Cagayan de Oro, Philippines. It includes a summary of estimated costs totaling PHP 501,624.46 that is broken down into direct costs for a fire detection and alarm system (PHP 131,029.25) and fire sprinkler system (PHP 233,100.00), as well as indirect costs such as overhead, contractor profit, VAT, and total project costs. The scope of work involves supplying all materials, labor, and equipment to complete the projects within a 45 calendar day timeframe.

Uploaded by

NG MOLLANIDA
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
421 views7 pages

Summary of Estimated Cost: Item No. and Description I.) Fire Detection and Alarm System II.) Fire Sprinkler System

This document provides an estimate for the completion of a three-storey commercial and residential building located in Baloy, Tablon, Cagayan de Oro, Philippines. It includes a summary of estimated costs totaling PHP 501,624.46 that is broken down into direct costs for a fire detection and alarm system (PHP 131,029.25) and fire sprinkler system (PHP 233,100.00), as well as indirect costs such as overhead, contractor profit, VAT, and total project costs. The scope of work involves supplying all materials, labor, and equipment to complete the projects within a 45 calendar day timeframe.

Uploaded by

NG MOLLANIDA
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 7

Name of Project : Completion of Three (3) Storey Commercial and Residential Building B

Location of Project : Baloy, Tablon, Cagayan de Oro


SUMMARY OF ESTIMATED COST
Item No. and Description Amount
I.) Fire Detection and Alarm System 131,029.25
II.) Fire Sprinkler System 233,100.00

Total Direct Cost 364,129.25


(OCM) 8.00% 29,130.34
(PROFIT) 15.00% 54,619.39
Vat (12%) 53,745.48
Total Indirect Cost 137,495.21
Total Cost of Project 501,624.46
Scope of Works :
Supply and Install all materials, labor and equipment
Project Duration = 45 Cal. Days

Prepared by: Noted by:

RHEA JOY R. BLASCO GLENN C. AVILA


Engineering Aide General Manager (GBI)

Reviewed and Submitted by: Approved by:

WILTON R. ROZANO GILBERT R. RODRIGUEZ


Name of Project : Completion of Three (3) Storey Commercial and Residential Building B
Location of Project : Baloy, Tablon, Cagayan de Oro
SUMMARY OF ESTIMATED COST
Project In Charge General Manager (KEGI)
Contract Name : Completion of Three (3) Storey Commercial and Residential Building B
Location of Contract : Baloy, Tablon, Cagayan de Oro
DETAILED ESTIMATES
I.) Fire Detection and Alarm System
15.00 set - Smoke Detector @ 1,064.00 = 15,960.00
3.00 set - Heat Detector @ 952.00 = 2,856.00
3.00 set - Manual Call Point @ 1,097.60 = 3,292.80
2.00 set - Alarm Bell @ 1,344.00 = 2,688.00
2.00 set - Back-up Battery @ 1,478.40 = 2,956.80
6.00 set - TF wire #16 @ 5,040.00 = 30,240.00
1.00 lot - Pipe and Fittings @ 15,000.00 = 15,000.00
1.00 lot - Testing and Commissioning @ 5,000.00 = 5,000.00
Total(Materials Cost) = 77,993.60
Total(Labor Cost) = P 50,695.84
Total (Equipment Cost) = P 2,339.81
Total direct cost -Fire Detection and Alarm System = P 131,029.25
II.) Fire Sprinkler System
35.00 lgs - Cable Tray @ 2,250.00 = 78,750.00
1.00 lot - Pipe and Fittings @ 40,000.00 = 40,000.00
1.00 lot - Consumables @ 20,000.00 = 20,000.00
Total(Materials Cost) = 138,750.00
Total(Labor Cost) = P 90,187.50
Total (Equipment Cost) = P 4,162.50
Total direct cost -Fire Sprinkler System = P 233,100.00
SUMMARY OFMATERIALS
QTY. UNIT PARTICULAR
15.0 set 1064 ₱ 15,960.00 Smoke Detector
M 3.0 set 952 ₱ 2,856.00 Heat Detector
A
T 3.0 set 1097.6 ₱ 3,292.80 Manual Call Point
E 2.00 set 1,344.00 ₱ 2,688.00 Alarm Bell
R
I 2.00 set 1,478 ₱ 2,956.80 Back-up Battery
A 6.00 set 5,040 ₱ 30,240.00 TF wire #16
L
S 1.00 lot 12,000 ₱ 12,000.00 Pipe and Fittings
1.00 lot 10,000 ₱ 10,000.00 Consumables
1.00 lot 5,000 ₱ 5,000.00 Testing and Commissioning
TOTAL MATERIAL COST ₱ 84,993.60
ERIALS
PARTICULAR
Detector
etector
Call Point
ell
p Battery
#16
d Fittings
mables
and Commissioning
SUMMARY OFMATERIALS
QTY. UNIT PARTICULAR
M
A 35.0 lgs 1,250 ₱ 43,750.00 Cable Tray
T
6.0 lgs 250 ₱ 1,500.00 Conduit Pipes
E
R 1.00 lot 40,000 ₱ 40,000.00 Pipe and Fittings
I 1.00 lot 20,000 ₱ 20,000.00 Consumables
A
L ₱ - Testing and Commissioning
S ₱ -
TOTAL MATERIAL COST ₱ 105,250.00

PIPES & FITTINGS


(Pipes: Black Iron Pipes Schedu
1", 1-1/2" diameter; Riser, Main
Lines, Cross Mains & Etc.) (Fittin
Flange,
Elbows,
Reducing
Tees,
Equal

Tees,
Tee
welded,
Elbow
Welded,

Concentric
Bell
Reducers,
Etc.)
ERIALS
PARTICULAR
ray 1400 49,000.0
Pipes
d Fittings
mables
and Commissioning

PIPES & FITTINGS


(Pipes: Black Iron Pipes Schedule 40 sizes
1", 1-1/2" diameter; Riser, Main Feeder
Lines, Cross Mains & Etc.) (Fittings: SlipOn

Concentric