Blk 39 Lot 1 Northville 2, Bignay, Valenzuela City
Tel. # (02)8 939 0746 / Cel. # 0917 658 7655
CONSTRUCTION PROPOSAL – DEMOLITION AND RENOVATION OF
EXISTING 3-STOREY BUILDING
November 11, 2020
For the Project located at Baler St., San Francisco del Monte, Quezon City
Contractor proposes to furnish all labor, materials and services as listed below for the
above mention Project.
QTY DESCRIBED WORK, MATERIALS AND LABOR AMOUNT
1 Demolition Works ₱410,000.00
Removal of existing Non-Bearing Wall Partitions (Concrete,
1.1
Plywood & Drywall)
1.2 Removal of existing Ceiling
1.3 Removal of stair case (Main Entrance)
1.4 Removal/Hauling of all construction debris from site
2 Masonry Works ₱683,912.00
2.1 Erection of New Partition Wall
Carry out masonry repairs to all internal and exterior wall
2.2 surrounds
2.3 Relocation of staircase
2.4 Slab repair and sealing for relocated staircase
Carry out structural masonry repairs to all internal walls where
2.5
the masonry is cracked and blown
3 Painting Works ₱409,405.00
All walls internal and exterior shall be cleaned and power
3.1
washed if needed, all cracks sealed with a masonry / tape sealer.
All internal walls shall be patched where cracks are evident and
to be primed to with two coats BOYSEN® Permacoat™ Flat
3.2
Latex #701 and two coats of BOYSEN® Permacoat™ Latex as per
approve color
All exterior walls shall be patched where cracks are evident and
to be primed to with two coats BOYSEN® Acrytex™ Primer
3.2
#1705 and two coats of BOYSEN® Acrytex™ Topcoat as per
approve color
4 Electrical Works -
4.1 Reinstallation of all electrical outlets, switches and lights.
5 Carpentry -
5.1 Make repairs to all clear storey windows
5.2 Make repairs to all shutters and door openings
Material Subtotal
Material Tax
Labor Subtotal
₱1,503,317.0
TOTAL 0
This proposal shall be valid for 15 days
Submitted by: DECK HAVEN CONSTRUCTION
Derrick Noynay
November 11, 2020
Contractor Dated