EXERCISE ON PERT-CPM
1. The activities and time estimate for a particular project are as follows:
Immediate time
in days
ACTIVITY Predecessor To Tm Tp Te
A - 7 8 15 9
B A 10 11 12 11
C A,B 5 7 9 7
D B, C 11 14 17 14
E D 5 7 9 7
F E 5 7 11 7
A = (7+4*8+15)/6 = 9 D = (11+4*14+17) = 14
B = (10+4*11+12)/6 = 11 E = (5+4*7+9)/6 = 7
C = (5+4*7+9)/6 = 7 F = (5+4*7+11)/6 = 7.33 or 7
a. Construct the network diagram:
ES EF
B 9 20
11 9 20
LS LF
ES EF ES EF ES EF ES EF
A 0 9 D 27 41 E 41 48 F 48 55
START END
9 0 9 14 27 41 7 41 48 7 48 55
LS LF LS LF LS LF LS LF
ES EF
C 20 27
7 20 27
LS LF
What is the critical path and expected project completion time? ANS.
The critical path is A-B-C-D-E-F and the expected project completion time is 55 days.
b. Determine the expected projected completion time and critical path.
hjb
c. Using te, determine the earliest and latest activity times and slack times. Given ES=0 and
EF=LF.
Activity te LS ES LF EF Slack CP?
0 0 9 9 0
A 9 YES
(9-9) (ES = 0) (LS OF B) (9+0) (0-0)
9 9 20 20 0
B 11 YES
(20-11) (EF of A) (LS OF C) (11+9) (9-9)
20 20 27 27 0
C 7 YES
(27-7) (EF of B) (LS OF D) (7+20 (20-20)
27 27 41 41 0
D 14 YES
(41-14) (EF of C ) (LS OF E) (14+27) (27-27)
41 41 48 48 0
E 7 YES
(48-7) (EF of D) (LS OF F) (7+41) (41-41)
48 48 55 55 0
F 7 YES
(55-7) (EF of E) (EF = LF) (7 +48) (48-48)
d. Using te as the Normal time, compute determine an optimum crashing plan.
Activity Normal time crash time cost/day
A 9 6 12000
B 11 8 4000
C 7 4 7000
D 14 11 2000
E 7 5 7000
F 7 4 3000
ACTIVITY COST/DAY AVAIL.DAY
A 12,000 3
hjb
(9 – 6)
3
B 4,000
(11 – 8)
3
C 7,000
(7 – 4)
3
D 2,000
(14 – 11)
2
E 7,000
(7 – 5)
3
F 3,000
(7 – 4)
Length after crashing in days
Path ‘n=0 1 2 3 4 5
A - B -C -D - E - F 55 54 53 52 51 50
A-B-D-E-F 48 47 46 45 44 43
A - C - D - E -F 44 43 42 41 40 39
Activity Crashed D D D F F
Cost 2000 2000 2000 3000 3000
Deduct one day from the base time (n=0) every day in all three routes since Activity D
and Activity F which is to be crashed is among the activities in all three paths.
A - B -C -D - E – F A - C - D - E -F
9 + 11 + 7 + 14 + 7 + 7 = 55 9 + 7 + 14 + 7 + 7 = 44
A-B-D-E-F
9 + 11 + 14 + 7 + 7 = 48