Itp For Piping QP

This inspection test plan outlines quality control activities for the fabrication and installation of piping. Key activities include: 1. Engineering and document approval including site surveys, drawings, and technical documents. 2. Material inspection and storage including verifying material test certificates, grades, and heat numbers. Storing materials clearly identified and segregated. 3. Shop fabrication including dimension and specification verification, fit-up checking, welding monitoring and documentation, visual and non-destructive testing of welds. 4. Surface preparation, painting and coating including blasting, paint thickness measurement, and material documentation. 5. Shipping including final review of documents and delivery notes. 6

Uploaded by

Rejoy baby
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
975 views4 pages

Itp For Piping QP

This inspection test plan outlines quality control activities for the fabrication and installation of piping. Key activities include: 1. Engineering and document approval including site surveys, drawings, and technical documents. 2. Material inspection and storage including verifying material test certificates, grades, and heat numbers. Storing materials clearly identified and segregated. 3. Shop fabrication including dimension and specification verification, fit-up checking, welding monitoring and documentation, visual and non-destructive testing of welds. 4. Surface preparation, painting and coating including blasting, paint thickness measurement, and material documentation. 5. Shipping including final review of documents and delivery notes. 6

Uploaded by

Rejoy baby
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 4

DANEM ENGINEERING WORKS WLL.

INSPECTION TEST PLAN

PROJECT : FABRICATION AND INSTALATION OF PIPING for the Project "EPIC OF PRECAST CONCRETE WALL,SHELTERS AND OTHER FACILITIES AT VARIOUS STATIONS IN DUKHAN
FIELDS"
QCP NO: DEW Rev:0 Project/Contract No: GC09113800
Inspection by
Item Quality Control Activity Characterstic to be verified Controling Documents Acceptance Standards Verifying Responsible Person Remarks
Documents/Reports DANEM QP

Site survey and Contractual Documents Relevent Contractual Documents Drawing Calculations Design Engg:
1.0 Engineering Approved Drawings Standards & Relevent Standards &Requirements. Project Manager H H

Preliminary activities
Drawing approval , Approved Drawings & Approved Drawings & Approved letter of
2.0 ITP approval & Technical - signature on Project Manager H H
documents to start of Specifications Specifications documents
fabrication and installation .

Drawing, Test certificates &


Material Certificate , QA/QC ,
3.0 Material Grade &Heat Store record MTC ,Drawing Material inspection Fab:SUPVR H R
report
Number

Clearly identified ,Segregated Store Keeper ,


3.1 Material storage to prevent MTC , Store Record Identification as per MTC - H R
damage&contamination SUPVR

4.0
Shop Fabrication prior to Dimensions, Heat Number Project specification & approved Project specification & Inspection Report QA/QC , H R
cutting of pipe ,Grade, Size&Specs drawings approved drawings Fab:SUPVR

Approved WPS,Check weld Fit Accordance with QA/QC ,


4.1 Fit-Up up as per WPS Approved Drawings approved WPS and Inspection Report Fab:SUPVR H R
project spec

Electrode baking/Holding/Issue QA/QC , Store


5.0 Welding Monitoring Welding control procedure Records MFRS Recommendations Records Keeper H R

ApprovedWPS ,Welders ASME SEC-IX,Project


5.1 Welding WPS /PQR,Welders certificate specification & approved Weld /NDT summary QA/QC H R
certificate drawings report

5.2 Visual Inspection 100% Visual inspection on Approved Drawings & Project specification & Inspection Report QA/QC H R
completed weld Weld map approved drawings

ASME.SEC V,NDT
6.0 NDT Radiogrphy Testing 20 % Weld map/ Records / Asper Scope Procedure &Project Test Reports QA/QC H R
for butt weld of Work and Approved Drawings Specification

1 of 4
DANEM ENGINEERING WORKS WLL. INSPECTION TEST PLAN

PROJECT : FABRICATION AND INSTALATION OF PIPING for the Project "EPIC OF PRECAST CONCRETE WALL,SHELTERS AND OTHER FACILITIES AT VARIOUS STATIONS IN DUKHAN
FIELDS"
QCP NO: DEW Rev:0 Project/Contract No: GC09113800
Inspection by
Item Quality Control Activity Characterstic to be verified Controling Documents Acceptance Standards Verifying Responsible Person Remarks
Documents/Reports DANEM QP

7.0 Blasting&Painting

Inspection of Surface Preparation & Painting As per approved drawings QA/QC


7.1 Surface preparation . surface profile / Blasting Report. H R
(As per Schedule 1Un ) procedure / Project Spec. Project Spec. PAINTING. SUPVR

Paint DFT Surface Preparation /Painting As per approved drawings QA/QC


7.2 Painting ( DFT) (As per Schedule 1Un ) procedure and Project Spec. / Project Spec. painting Report. PAINTING. SUPVR H W/R

9.0 Shipping

9.1 Shipping to Site Final Review Delivery Note Relevant Document Delivery Note FAB.SUPVR. H R
( Document &Reports ) ,

10.1 Site Installation

Accordance with
10.2 Fit-Up Approved WPS,Check weld Fit Approved Drawings approved WPS and Inspection Report QA/QC , H R
up asper WPS project spec Fab:SUPVR

Approved WPS /PQR,Welders WPS /PQR,Welders certificate ASME SEC-IX,Project


10.3 Welding specification & approved Weld /NDT summary QA/QC H R
certificate drawings report

Stage wise Inspection during As per approved drawings


10.4 Stage wise Inspection Installation. As per approved drawings and Project Spec. Inspection Report QA/QC H R

10.5 Alignment Alignment Check of all As per approved drawings As per approved drawings Inspection Report QA/QC H R
Flanges and Project Spec.

2 of 4
DANEM ENGINEERING WORKS WLL. INSPECTION TEST PLAN

PROJECT : FABRICATION AND INSTALATION OF PIPING for the Project "EPIC OF PRECAST CONCRETE WALL,SHELTERS AND OTHER FACILITIES AT VARIOUS STATIONS IN DUKHAN
FIELDS"
QCP NO: DEW Rev:0 Project/Contract No: GC09113800
Inspection by
Item Quality Control Activity Characterstic to be verified Controling Documents Acceptance Standards Verifying Responsible Person Remarks
Documents/Reports DANEM QP

Orientation check of all As per approved drawings


10.6 Orientation Flanges. As per approved drawings and Project Spec. Inspection Report QA/QC H R

10.7 Alignment Alignment Check of all valves As per approved drawings As per approved drawings Inspection Report QA/QC H R
and Project Spec.

As per approved drawings


10.8 Orientation Orientation check of all valves As per approved drawings and Project Spec. Inspection Report QA/QC H R

10.9 Overall dimension Overall dimension check As per approved drawings As per approved drawings Inspection Report QA/QC H R
and Project Spec.

10.11 Visual Inspection 100% Visual inspection on Approved Drawings Weld map As per approved drawings Inspection Report QA/QC H R
completed weld and Project Spec.

Radiogrphy 20 % Weld map Records / Asper Scope ASME.SEC V,NDT


9.10 NDT Procedure &Project RT-Reports QA/QC H R
for butt weld of Work and Approved Drawings Specification

Hydro Test Hydro Test of Piping Weld map /Records / Asper Scope App. Drawing &Project Test Report QA/QC H H
10
of Work and Approved Drawings Specification

Mechanical Completion Activities have to be Weld Map and Records App. Drawing Project QC Documents QA/QC H H
12
completed Specification FAB. SUPVR.

Quality Inspection Test


13 Quality Dossier Contractual Requirements Documents and Reports Plan & QC Dossier QA/QC Engineer H H
Clients Requirements

3 of 4
DANEM ENGINEERING WORKS WLL. INSPECTION TEST PLAN

PROJECT : FABRICATION AND INSTALATION OF PIPING for the Project "EPIC OF PRECAST CONCRETE WALL,SHELTERS AND OTHER FACILITIES AT VARIOUS STATIONS IN DUKHAN
FIELDS"
QCP NO: DEW Rev:0 Project/Contract No: GC09113800
Inspection by
Item Quality Control Activity Characterstic to be verified Controling Documents Acceptance Standards Verifying Responsible Person Remarks
Documents/Reports DANEM QP

Legends: H: Hold point I:Inspection R:Review W:Witness S: Surveillance

4 of 4