Leaper Corporation

Leaper Corporation uses an activity-based costing system with three activity cost pools: fabrication, order processing, and other. The company provided costs of wages and salaries ($360,000), depreciation ($140,000), and occupancy ($160,000) that are distributed across the activity cost pools. The activity rate for order processing, which is closest to $1,465 per order, is calculated using the costs allocated to that activity cost pool.

Uploaded by

Hannah Corpuz
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
112 views2 pages

Leaper Corporation

Leaper Corporation uses an activity-based costing system with three activity cost pools: fabrication, order processing, and other. The company provided costs of wages and salaries ($360,000), depreciation ($140,000), and occupancy ($160,000) that are distributed across the activity cost pools. The activity rate for order processing, which is closest to $1,465 per order, is calculated using the costs allocated to that activity cost pool.

Uploaded by

Hannah Corpuz
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

24.

Leaper Corporation uses an activity-based costing system with the following three activity cost
pools:

Activity Cost Pool Total Activity


Fabrication.................................. 40,000 machine-hours
Order processing......................... 200 orders
Other........................................... Not applicable

The Other activity cost pool is used to accumulate costs of idle capacity and organization-
sustaining costs.
The company has provided the following data concerning its costs:

Wages and salaries............... $360,000


Depreciation......................... 140,000
Occupancy...........................  160,000
Total..................................... $660,000

The distribution of resource consumption across activity cost pools is given below:

Activity Cost Pools


Order
Fabrication Processing Other Total
Wages and salaries............... 35% 40% 25% 100%
Depreciation......................... 5% 55% 40% 100%
Occupancy........................... 30% 45% 25% 100%

The activity rate for the Order Processing activity cost pool is closest to:

A) $1,485 per order

B) $1,540 per order

C) $1,465 per order

D) $1,320 per order


Ans:  C LO:  2,3