SINOPEC TENTH CONSTRUCTION COMPANY GATHERING CE
KPI REVIEW RECORD FOR 2K20
s.no KPI TARGET KPI ACHIEVED
1 FATALITIES 0 YES
Improved lost time injury frequency <0.006
2 YES
rate Target ;0
3 Total recordable incident rate <0.094 3.38
4 Level 2 Environmental incidents 0 YES
5 severe vehicle accident frequency 0 YES
company and contractor HSE
6 policies communicated to all project 100% YES
personnel
sub contractor senior management
engagement in company HSE
7 >90% YES
meeting and reviews and close out
of mom
HAZ & RM Pefromed as per
8 100% YES
company procedures
legal compliance register
9 established and reviewed >90% YES
periodically
Mobilization and demobilization of
10 project HSE personnel as per the 100% YES
plan/org.charts
HSE induction -All project site
11 personnel received before 100% YES
commencing the work at site
HSE Training carried out to training
matrix. High risk activities to be
recognized and training for
everyone to attend and pass prior to
12 commencement of the activity such 100% YES
as Confined Space, Hazardous
material
handling, working at heights etc.
Effective communication and
consultation aids implemented
(Tool box
talks, Notice boards etc).
13 100% YES
Communication Aides to be
developed/ Delivered
in multilingual languages that the
worker level personnel understand.
Emergency Response plans
14 developed and drills performed to >90% NO
schedule.
All incidents including near misses
15 100% YES
reported and investigated
HSE Audits, inspections performed
to Compliance assurance schedule
16 and >90% YES
action items closed out as per the
agreed time frame.
COMPANY SOC program
17 >90% YES
implemented & tracked weekly
18 Driver Safety Meetings held 4 per month YES
HSE Performance reviewed by 100% once in a
19 YES
Management as per agreed plans month
OMPANY GATHERING CENTRE -32
CORD FOR 2K20
DEFICIENCY REMARKS
Complied and achieved
last updated on q-04 audit and iso 45001
sharjah gap assessment audit for
contractor
As per company procedure for
contractor KOC GE -033
>50 % Not achieved due to the
<40%
construction peak stints
Latest Q-04 audit aggregate score - 4.6/5