0% found this document useful (0 votes)
137 views2 pages

Astra Construction: Quality Control Department

1) The document is a quality control checklist from Astra Construction for blinding works, precast manholes, and manhole covers and frames for the Kaden Road Transmission Line and Waterworks project in Riyadh. 2) It includes acceptance criteria for blinding works, precast manholes, and manhole covers and frames to ensure specifications are met on items like excavation, formworks, alignments, and material approvals. 3) The checklist is signed off by quality control engineers from Astra and the main contractor to verify inspections and is then approved by a consultant representative.

Uploaded by

md_rehan_2
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
137 views2 pages

Astra Construction: Quality Control Department

1) The document is a quality control checklist from Astra Construction for blinding works, precast manholes, and manhole covers and frames for the Kaden Road Transmission Line and Waterworks project in Riyadh. 2) It includes acceptance criteria for blinding works, precast manholes, and manhole covers and frames to ensure specifications are met on items like excavation, formworks, alignments, and material approvals. 3) The checklist is signed off by quality control engineers from Astra and the main contractor to verify inspections and is then approved by a consultant representative.

Uploaded by

md_rehan_2
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Program: Riyadh Township – KADEN Road

ASTRA CONSTRUCTION
QUALITY CONTROL
KADEN ROAD TRANSMISSION LINE & WATERWORKS, RIYADH
DEPARTMENT

Check List for Blinding & Pre Cast Manholes, Manholes Covers and Frames

1.0} Information About Item Inspected : Civil Works Date :


1.1} Construction Category : 1.2} Process Location/Component ID No :
Civil
2.0} Inspection checklist : AST-CL-C-003

Pass Fail N/A Remarks


Acceptance Criteria
3.1 Blinding Works

1) Is the work done in accordance with approved Method Statement & ITP

2) Is the work done as per approved drawings

3) Is the Concrete Design Mix Approved


4) Is the Excavation Inspection Approved

5)
Is the Loose Earth removed and Cleaning Done
6) Is adequate compaction done below the Blinding Area

7) Is Alignment and Measurments Checked


8) Is the Formworks Checked

9) Are Blinding Top Levels Marked and Checked

10) Any other Services Crossing Co-ordinates

11) Necessary Tools and Tackles Available

3.2 Precast Manholes

1) Is the Material approved by Engineer, prior to installation through approved MIR

2) Is the Blinding done if required


Is theconcrete poured around the Manhole as per the apporved mix design and
3)
approved shop drawing

4) Are the maholes being Installed at accurate level as per the approved drawing

5) All the opening are provided for pipe at the accurate invert level as required
6) Are the steps provided as required and as per approved drawing
7) Are Concrete Courses installed as Installed
3.3 Manhole Frames and Covers

1) Is the Material approved by Engineer, prior to installation through approved MIR

Are the Cover and Frames Installed accurately as per the approved detail
2)
drawing

3) Is the Clear opening of dia 600 mm provided

4) Are the locks installed


5) Are the lifting key holes provided
6) The text SANITARY is engraved on Cover
7) Are the prising slots provided
Program: Riyadh Township – KADEN Road

ASTRA CONSTRUCTION
QUALITY CONTROL
KADEN ROAD TRANSMISSION LINE & WATERWORKS, RIYADH
DEPARTMENT
Check List for Blinding & Pre Cast Manholes, Manholes Covers and Frames

QA/QC ENGINEER ASTRA Site Engineer ASTRA


Name: _____________________________ Name : ______________________________

Sign: ______________________________ Sign: ________________________________


Date:______________________________ Date:________________________________
MAIN CONTRACTOR Other trade Clearance ( If any)
Name: _____________________________ Name: ________________________________

Sign: ______________________________ Sign: _________________________________


Date:______________________________ Date: _________________________________
Consultant Representative Approval
Status A (Approved) Status B (Approved with Comments)

Status C Revise & Resubmit Status D (Rejected)


Comments

Name: _______________________________ Signature: ____________________ Date: ______________

QC FORM ASTRA CONSTRUCTION

You might also like