THE ENGINEER THE CLIENT THE CONTRACTOR
Date:
KING SALMAN AIRBASE PROJECT DIRAB Rev. 0
Contract No.
KING SALMAN AIRBASE PROJECT DIRAB
INPECTION AND TEST PLAN
(UNDERGROUND PRE-INSULATED CHILLED WATER PIPE
INSTALLATION)
Prepared by: Reviewed by: Concurred by:
QA/QC Engineer Construction Manager QA/QC Manager
1
THE ENGINEER THE CLIENT THE CONTRACTOR
Date:
KING SALMAN AIRBASE PROJECT DIRAB Rev. 0
Contract No.
REVISION SHEET
Date Item
No. Description Form Rev. No. Page
/Line
November
1. 2020
Issued for Submission ITP 00 - -
ACTION CODE
Code Designation Explanation
S Surveillance Random attendance at site.
W Witness An Inspection activity, which can proceed after notifying the DAR Engineer, BSSJV
QC Engineer has the responsibility of detailed Inspection.
An Inspection activity which cannot proceed until inspected and approved by DAR
H Hold point
Engineer. The RFI will be as indicated in the ITP.
R Review Documentation to be reviewed, no signature required. (R may be in addition to any of
the optional codes).
2
THE ENGINEER THE CONTRACTOR
THE CLIENT
Date:
Rev. 0
KING SALMAN AIRBASE PROJECT DIRAB Contract No.
DOCUMENT DISTRIBUTION LIST
S.NO Recipient Position Location
1 MINISTRY OF DEFENCE EMPLOYER
2 DAR AL HANDASAH ENGINEER
3 JV PROJECT DIRECTOR BSSJV MAIN OFFICE
4 JV CONTRACTS MANAGER BSSJV MAIN OFFICE
5 JV TECHNICAL MANAGER BSSJV MAIN OFFICE
6 JV CONSTRUCTION MANAGER BSSJV MAIN OFFICE
7 JV QA/QC MANAGER BSSJV MAIN OFFICE
Page 3 of 5 S19091-COR-BAWI-DOC-G-0003-00
ITP For INTERNAL AND EXTERNAL UNDER GROUND DRAINAGE PIPE
Stakeholders/
Inspection / Test ACTION
Ac. No. Activity Description Reference Documents Frequency of Test Acceptance Criteria Verifying Documents
Required BSS
Sub DAR
JV
1 PRE-COMMENCMENT
1.1 Document Approval
Contract Requirement,
Project Specifications, Prior to start work &
Materials Document Review Consultant Approval R R R
Manufacturer during Execution
Recommendations
Contract Requirement,
Prior to start work &
Drawings Project Specifications, Document Review Consultant Approval R R R
during Execution
Material submittal
Project Specifications,
Material submittal, Shop Prior to start work &
Method statement Drawing transmittals and Document Review Consultant Approval R R R
during Execution
Manufacturer
Recommendations
1.2 Material Approval
Approved Material Visual / Document Each Delivery of Material as per the Delivery note
Pipes, Fittings, & Rubber Rings Material Test Certificate where H H WR
Submittal Review Material Received at site
required warranty Certificate.
Approved Material Visual / Document Each Delivery of Material as per the Delivery note
Bedding, backfilling Submittal Review Material Test Certificate where H H WR
Material Received at site
required warranty Certificate
Approved Material Visual / Document Material as per the Delivery note
Each Delivery of
Anchoring and Thrust support Submittal Review Material Test Certificate where H H WR
Material Received at site
required warranty Certificate
Visual Procedure as Per Manufacturer
Transporting, Handling, Storage Approved Material Randomly during
Recommendation and Project S S S
Materials Submittal Performing the activity
specifications
2 EXECUTION
Approved Shop Drawing,
Excavation of Trenching sand During Execution of Inspection Request and approved
Approved Method Visual Inspection H W S
bedding and compaction work shop Drawing
Statement
4
ITP For INTERNAL AND EXTERNAL UNDER GROUND DRAINAGE PIPE
Stakeholders/
ACTION
Inspection / Test
Ac. No. Activity Description ReferenceShop
Approved Documents
Drawing, Visual Inspection Frequency
During of Test
Execution of Acceptance Criteria Verifying Documents
Layout the Reference Point, Required Inspection Request and as Per
Approved Method work H W S
Invert Level approved Shop Drawing
Statement
Installation of Pipe, Fittings Approved Shop Drawing, Visual Inspection According to Inspection
Inspection Request and as Per
Anchor and Thrust supports as Approved Method Request H H H
approved Shop Drawing
per Sizes Statement
Approved Shop Drawing, Visual Inspection According to Inspection
No leak on Joints, 30 kPa(10-
Gravity Test of Pipe Network Approved Method Request H H H
foot head of water)
Statement
Approved Shop Drawing, Visual Inspection During Execution of
Provide Warning Tape for Pipe Locate Tape 300mm Below
Approved Method work H H W
Network finishing Grade
Statement