Transportation Method
Example 1
          A mining company extracts gravel, the basic product it sells, from three mines, L1, L2 and L3. The
          weekly production of each mine is 75, 150 and 75 tones of gravel respectively. The gravel has to
          be transported to five main consumers, K1, K2, K3, K4 and K5 requiring for their needs 100, 60,
          40, 75 and 25 tones of gravel per week respectively. The problem that concerns the company's
          management is the minimization of the required cost for the transportation of the product to the
          consumers. For this purpose a detailed cost analysis was carried out which gave the results of the
          following table
          Cost table of gravel transportation Consumers
                K1             K2        K3            K4        K5
   L1            3             2         3             4         1
   L2            4             1         2             4         2
   L3            1             0         5             3         2
Answer:
                                                   Table 1
                     K1             K2                K3             K4       K5
    L1                     3              2                  3            4        1      75
                     75
    L2                     4                 1               2            4        2     150
                     25             60                40             25
    L3                     1              0                  5            3        2      75
                                                                     50       25
                     100            60                40             75       25
Cost:
              75 x 3 =225           60 x 1 = 60            25 x 4 = 100   25 x 2 = 50
              25 x 4 =100           40 x 2 = 80           50 x 3 = 150    K/min = 765
C.I.I:
L3-K1: 1 - 3 + 4 – 4 = -37          L3-K2: 0 – 1 + 4 – 3 = 0        L3-K3: 5 – 2 + 4 – 3 = 4
L1-K2: 2 – 1 + 4 – 3 = 2            L1-K3: 3 – 2 + 4 – 3 = 2        L1-K4: 4 – 3 + 4 – 4 = 1
L1-K5: 1 – 2 + 3 – 4 + 4 – 3 = -1                                   L2-K5: 2 – 2 + 3 – 4 = -1
                                                Table 2
                        K1           K2             K3              K4            K5
         L1                  3            2                 3             4             1       75
                        50                                                        25
         L2                  4            1                 2             4             2       150
                        35                          40              75
         L3                  1            0                 5             3             2       75
                        15           60
                       100           60             40              75            25
Cost:
L1-K1:50 x 3 = 150           L3-K1:15 x 1 = 15            L2-K3:40 x 2 = 80       L1-K5:25 x 1 = 25
L1-K2:35 x 4 = 140           L3-K2:60 x 0 = 0             L2-K4:75 x 4 =300       K/min= 710
C.I.I:
L1-K2: 2 – 0 + 1 – 3 = 0            L1-K3: 3 – 2 + 4 – 3 = 2              L1-K4: 4 – 4 + 4 – 3 = 1
L2-K2: 1 – 0 + 1 – 4 = 2            L3-K3: 5 – 1 + 4 – 2 = 6              L3-K4: 3 – 1 + 4 – 2 = 4
L2-K5: 2 – 1 + 3 - 4 = 0            L3-K5: 2 – 1 + 3 – 1 = 3
     Decision:
Transport from customer 1 to produce Project 1
Transport from customer 1 to produce Project 2
Transport from customer 3 to produce Project 1
Transport from customer 3 to produce Project 2
Transport from customer 2 to produce Project 3
Transport from customer 2 to produce Project 4
Transport from customer 1 to produce Project 5
Total Kilometer is 710/min
Example 2
A company transports desk top computers from three warehouses to three retail stores. The number of
computers available (supply) in the three warehouses are 40 50 and 30 while the number of computers
required at the three retailers (demand) are 20, 35 and 65 respectively. There is a cost of transporting
from the warehouses to the retail outlets. The cost transport one unit from a given warehouse to a
given retailer is given, How do we transport the computers such that we incur minimum total cost of the
transportation?
                              A                  B                  C               Supply
            1                  9                 6                 10                 40
            2                 10                 8                  9                 50
            3                  5                 4                  7                 30
          Demand              20                 35                65
Answer:                                     Table 1
                              A                 B            C         Supply
            1                        9                   6        10    40
                             20                              20
            2                        10                  8         9    50
                                                35           15
            3                        5                   4         7    30
                                                             30
          Demand             20                 35           65
Cost:
20 x 9 = 180         20 x 10 = 200   30 x 7 = 210
35 x 8 = 280         15 x 9 = 135    Total Cost = 1005
C.I.I.:
A2: 10 – 9 + 10 – 9 = 2     B1: 6 – 8 + 9 – 10 = -3
A3: 5 – 9 + 10 – 7 = -1     B3: 4 – 8 + 9 – 7 = -2
                                               Table 2
                              A                 B            C         Supply
            1                        9                   6        10    40
                             20                 20
            2                        10                  8         9    50
                                                15           35
            3                        5                   4         7    30
                                                             30
          Demand             20                 35           65
Cost:
20 x 9 = 180         15 x 8 = 120     30 x 7 = 210
20 x 6 = 120         35 x 9 = 315     Total Cost = 945
C.I.I:
2A: 10 – 8 + 6 – 9 = -1               3B: 4 – 8 + 9 – 7 = -2
3A: 5 – 7 + 9 – 8 + 6 – 9 = -41C: 10 – 9 + 8 – 6 = 3
                                                 Table 3
                               A                  B                 C          Supply
             1                        9                    6              10    40
                              20                  5                15
             2                       10                    8               9    50
                                                                   50
             3                        5                    4               7    30
                                                 30
           Demand             20                 35                65
Cost:
20 x 9 = 180         30 x 4 = 120     50 x 9 = 450
5 x 6 = 30           15 x 10 = 150                     Total Cost = 930
C.I.I. :
2A: 10 – 9 + 10 - 9 = 2      2B: 8 – 6 + 10 – 9 = 3
3A: 5 – 4 + 6 – 9 = -2       3C: 7 – 10 + 6 – 4 = -1
                                                 Table 4
                              A                   B             C                Supply
            1                         9                 6               10         40
                                                  25            15
            2                        10                8                 9         50
                                                                50
            3                         5                4                 7         30
                              20                  10
        Demand                20                  35            65
Cost:
A3: 20 x 5 = 100    B3:10 x 4 = 40            C2:50 x 9 = 450
B1:25 x 6 = 150     C1:15 x 10 = 150                                 Total Cost = 890
Decision:
Transport from retailers 3 to produce Project A
Transport from retailers 1 to produce Project B
Transport from retailers 3 to produce Project B
Transport from retailers 1 to produce Project C
Transport from retailers 2 to produce Project C
Minimum Cost: 890.00
                                          Assignment Method
   Example 1
Tony Company need to produce 4 iron (J1, J2, J3, and J4) need to be executed by four workers (W1,
W2, W3, and W4), one job per worker. The matrix below shows the cost of assigning a certain worker
to a certain job. The objective is to minimize the total cost of the assignment.
                                  J1            J2             J3           J4
                  W1              82            83             69           92
                  W2              77            37             49           92
                  W3              11            69             5            86
                  W4              8             9              98           23
Answer:
Table 1
                        J1             J2       J3        J4
             W1         13             13       0         23        (-69)
             W2         40             0        12        55        (-37)
             W3          6             64       0         81        (-5)
             W4          0             1        90        15        (-8)
                             J1            J2        J3    J4
Table 2        W1            13            13        0     23
               W2            40             0        12    55
               W3            6             64        0     81
               W4            0              1        90    15
             Smallest uncovers number is 6
Table 3
                                J1       J2    J3   J4
                      W1        7         8    0    2
                      W2        40        0    18   40
                      W3        0        58    0    60
                      W4        0         1    96   0
          Decision:
          worker 1 should perform job 3 = 69
          worker 2 job 2 = 37
          worker 3 job 1 = 11
          worker 4 should perform job 4 = 23
          Total Cost = 140
          Example 2
          An Accounts Officer has 4 suboridnates and 4 tasks. The subordinates differ in efficiency. The
          tasks also differ in their intrinsic difficulty. His estimates of the time each would take to perform
          each task is given in the matrix below. How should the tasks be allocated one to one man, so that
          the total man hours are minimized?
                                       A             B              C              D
                     1                 8             26            17              11
                     2                 13            28             4              26
                     3                 38            19            18              15
                     4                 19            26            24              10
          Answer:
          Table 1
                                 A             B            C             D
                    1            0            18            9             3             (-8)
                    2            9            24            0            22             (-4)
                    3           24             4            3             0            (-15)
                    4            9            16            14            0            (-10)
                                 A             B            C             D
                    1            0            14            9             3
                    2            9            20            0            22
Table 2
                    3           24             0            3             0
                    4            9            12            14            0
                                (-0)          (-4)         (-0)          (-0)
Table 3
                          A            B         C        D
              1            0           14        9        3
              2            9           20        0        22
              3           24           0         3        0
              4            9           12        14       0
Decision:
Subordinates A should perform task 1 = 8
Subordinates C should perform task 2 = 4
Subordinates B should perform task 3 = 19
Subordinates D should perform task 4 = 10
Total hours = 41 hours
                                            PERT Method
Example 1
 Allan Corporation assigned Hino Corporation as project manager of a power plant project and Hino
Corporation listed;
– All the Activities
– Predecessors
– Optimistic, Pessimistic and Most Likely Activity Durations
 Activity               Description            predessors      a    b       m     Expected     variance
                                                                                    time
    0               Start milestone                -            0    0     0           0            0
    A           Select technical staff             0           12   18     15         15            1
    B                 Site Survey                  0            6   12     9           9            1
    C             Select Equipment’s               A            9   15     12         12            1
    D              Prepare Designs                 B            6   18     9          10            4
    E         Bring Utilities to the Site          B           18   36     30         29            9
    F            Interview Applicants              A            9   15     12         12            1
    G         Purchase the Equipment               C           36   42     36         37            1
    H         Construct the Powerplant             D           42   54     48         48            4
    I          Develop an Information              A            6   18     12         12            4
                        System
    J           Install the Equpiment            H,G,E         3    9       6         6             1
    K         Train the Staff to Run the          F,J,I        3    9       6         6             1
                        System
Formula:
                        a+ 4 m+ b
Expected time: t=           6
                    2
           b−a
Variance =  ( )
            6
  Activity       ES             EF            LS            LF            Slack (LS – ES)         Critical Path
    A             0             15             3            18                    3                    NO
    B             0              9             0             9                    0                    YES
    C            15             27            61            73                   46                    NO
    D             9             19             9            19                    0                    YES
    E             9             38            38            67                   31                    NO
    F            15             27            61            73                   46                    NO
    G            27             64            30            67                    3                    NO
    H            19             67            19            67                    0                    YES
     I           15             27            61            73                   46                    NO
     J           67             73            67            73                    0                    YES
    K            73             79            73            79                    0                    YES
Example 2
Maxwell Corporation give to the Casey Corporation the following things need to do
    •   Determine the expected value and the variance of the completion time for each activity.
    •   (b) Use the expected times from (a) to find the critical path.
    •   (c) Assuming that the normal distribution applies, determine the probability that the critical path will
        take between 18 and 26 days to complete.
    •   (d) How much time must be allowed to achieve a 90% probability of timely completion?
    •   (e)By using modified probability of completion method, what is the probability that all paths will take
        before 18 weeks?
  Activity    Activity       Optimistic (a)   Most Likely     Pessimistic   Expected Variance
                                                                              Time
                                                   (m)            (b)
     a             -               5               6              7            6       4/36
     b             -               4               5              18           7      196/36
     c           a                 4               15             20          14       4/36
     d           b,c               3               4              5            4       4/36
     e           a                 5               16             18          14.5    169/36
Formula:
                       a+ 4 m+ b
Expected time: t=          6
                 2
           b−a
Variance =
            6( )                                            FINISH
                         A
                                               C                     D
   START
                         B
                                 6     20.5
                                 9.5 24
                   0   6                                                FINISH
                   0   6           6   20          20 24
START
                                   6   20          20 24
                   0   7
                   13 20
        Activity       ES   EF          LS    LF    Slack    Critical
                                                   (LS-ES)    Path
           A           0     6          0     6      0        YES
           B           0     7          13    20     13        NO
           C           6    20          6     20     0        YES
           D           20   24          20    24     0        YES
           E           6    20.5        9.5   24     3.5       NO