DEPT.
OF ELECTRICAL AND ELECTRONICS ENGINEERING (EEE)
Question Bank (2016-17)
SUBJECT: MANAGEMENT SCIENCE (RT) (III/II) JNTUK-R13
FACULTY: U.Gangadhar Format: 9002/0
UNIT-I
Part-A
1. Management. [3M]
2. Any one of the Functions of Management[3M]
3. Motivation[3M]
4. Leadership [3M]
5. Organization [3M]
6. Explain the significance of organization. [3M]
Part-B
1. Describe the nature and importance of Management.(8M)
2. Explain any one of the Motivation theories. (8M)
3. What is Management? What are the functions of Management? (8M)
4. Discuss the steps in decision making process. (8M)
5. Illustrate types of organization structures. (8M)
6. Principles of Organization(8M)
7. Discuss the main components of Theory of Scientific Management. (8M)
8. Process of Decision Making(8M)
UNIT-II
Part-A
1. EOQ. [3M]
2. Control Charts. [4M]
3. Work Study. [4M]
4. Method Study [3M]
5. Inventory[3M]
6. ABC Analysis[3M]
Part-B
1. “There is various inventory control techniques employed to enhance the productivity levels in an
industry environment.” Explain? (8M)
2. Mention the objectives of work measurement.(8M)
3. Mention the benefits of Statistical Quality Control? (8M)
4. What are the objectives of Inventory Control? (8M)
5. What are the Principles of Management? (8M)
6. What are the Types of Management? (8M)
7. “Method study refers to the systematic recording and critical examination of existing and proposed
ways of doing work.” Write about the basic procedure used in the process of method study.(8M)
8. Explain about the various types of ABC analysis in brief. (8M)
UNIT-III
Part-A
1. What is the importance of Human Resource Management? [4M]
2. Recruitment.(3M)
3. Mention the advantages of Job Evaluation. [4M]
4. Marketing.(4M)
5. Merit Rating (4M)
Part-B
1. Discuss in detail about the various functions of HR manager. [8M]
2. What are the factors affecting the choice of Channel of distribution? [8M]
3. Differentiate personnel and industrial relations from Human Resource Management. [8M]
4. Briefly write about the types of Channels of distribution with suitable examples. [8M]
5. What are stages of product life cycle? What are the marketing strategies, based on product life cycle?
[8M]
6. “Merit rating is the process of evaluating the relative merit of the person on a given job.” Mention
any four methods of Merit rating? [8M]
7. What is meant by marketing management? What are the various functions of marketing? [8M]
8. Explain about various wage payment plans. (8M)
UNIT-IV
Part-A
1. Write short notes on Optimistic time estimate and Pessimistic time estimate? [3M]
2. What are the main advantages of using Network? [3M]
3. Mention the differences between PERT and CPM. [3M]
4. What are the rules that are to be carefully observed while drawing a Network? [3M]
Part-B
1. Write about the differences between PERT and CPM. [8M]
2. What is critical path? What are the steps involved in identifying critical path? [8M]
3. Write briefly about Network Analysis? Mention the rules that should be carefully observed
while drawing a Network. [8M]
4.
Find out:
a) Calculate the values of expected time (te) and S.D variance(t V) each activity
b) Draw the network diagram and mark te on each activity
c) Calculate EST and LFT and mark them on the net work diagram
d) Calculate total slack for each activity
e) Identify the critical path and mark on the net work diagram
f) Probability of completing project in 25 days
5. .
UNIT-V
Part-A
1. Write short notes on Vision and Mission. [4M]
2. Explain about the significance of SWOT analysis. [4M]
3. Write short notes on Generic strategy alternatives? [4M]
4. Strategy [3M]
5. Goal [3M]
Part-B
1. “The corporate plans provide a rational approach to achieve corporate goals.” What are the various
element of corporate planning process? (8M)
2. Explain in detail about International Environment analysis. [8M]
3. “Strategy formulation and implementation is the crux of the strategic management process.” What are
the various stages involved in the process of Strategy formulation and implementation?
4. What are the factors that are to be diagnosed in the External environment for the purpose of Strategy
formulation?
5. Briefly explain about SWOT analysis with suitable examples? [8M]
UNIT-VI
Part-A
1. What are the main objectives of Material Requirement Planning? (3M)
2. What are the major benefits of Just In Time system of production? [4M]
3. BPOs
4. JUST-IN TIME
5. TQM
6. MIS
Part-B
1. Explain the importance of Six Sigma in production. (8M)
2. How is Bench Marking useful? (8M)
3. How does Just-In—Time (JIT) help in reducing costs. (8M)
4. Describe the importance of Total Quality Management. (8M)
5. What do you mean by Capability Maturity Model (CMM)? Briefly mention about various levels of
CMM?(8M)
6. “Enterprise Resource Planning systems (ERPs) integrate all data and process of an organization into
a unified system.” Explain. (8M)