Petronas Carigali Sdn. Bhd. Inspection Test Record (Itr) - B Safety Shower / Eyewash S02-B

This document contains inspection test records for various safety systems on an offshore oil and gas project. It includes records for safety showers and eyewashes, survival equipment, firewater systems, fire suppression systems, and a deck integrated firefighting system. The records document completion of inspection and testing checklists, verification that equipment is installed correctly and functions properly, and acceptance of the systems.

Uploaded by

Wael Chouchani
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
416 views6 pages

Petronas Carigali Sdn. Bhd. Inspection Test Record (Itr) - B Safety Shower / Eyewash S02-B

This document contains inspection test records for various safety systems on an offshore oil and gas project. It includes records for safety showers and eyewashes, survival equipment, firewater systems, fire suppression systems, and a deck integrated firefighting system. The records document completion of inspection and testing checklists, verification that equipment is installed correctly and functions properly, and acceptance of the systems.

Uploaded by

Wael Chouchani
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 6

PETRONAS CARIGALI SDN. BHD.

INSPECTION TEST RECORD (ITR) - B


SAFETY SHOWER / EYEWASH S02-B
Project No.
Project Title

INFORMATION
Tag no. System no.
Area Location
Ref. Drawing nos.
INSPECTION / TEST OK N/A P/L No
Ensure A check list and A punch list items completed & no subsequent
1
damage occurred.
2 Check portable eye wash stations are filed with sterilized water.
Check water quality (cleanliness) of the shower/ eyewash station
3
(piped).
4 Test the functioning of each shower station.
5 Test the functioning of eye wash stations.
COMMENT(S) AND ADDITIONAL INFORMATION:

COMPLETED BY VERIFIED BY ACCEPTED


Designation Contractor Representative PMT Inspector Commissioning Engineer
Company PCSB PCSB
Name
Signature
Date

Page 1 of 1
PETRONAS CARIGALI SDN. BHD.

INSPECTION TEST RECORD (ITR) - B


SURVIVAL EQUIPMENT S03-B
Project No.
Project Title

INFORMATION
Tag no. System/Subsyste
m No.

INSPECTION / TEST OK N/A P/L No


Ensure A check list and A punch list items completed & no subsequent
1
damage occurred.
Conduct thorough visual inspection of survival equipment, checking
2 for damage, deterioration and deficiencies since onshore
certification.
Confirm that all loose item supplied with the survival equipment is in
3 accordance with the equipment drawing as detailed in the O & M
Manual
COMMENT(S) AND ADDITIONAL INFORMATION:

COMPLETED BY VERIFIED BY ACCEPTED BY


Designation Contractor Representative PMT Inspector Commissioning Engineer
Company PCSB PCSB
Name
Signature
Date

Page 1 of 1
PETRONAS CARIGALI SDN. BHD.

INSPECTION TEST RECORD (ITR) - B


FIREWATER/ FOAM SYSTEM S10-B
Project No.
Project Title

INFORMATION
Tag no. System no.
Area Location
Ref. Drawing nos
INSPECTION / TEST OK N/A P/L No
Ensure A check list and A punch list items completed & no subsequent
1
damage occurred.
Check location / quantities of firefighting equipment is as per Escape
2 Route, Fire Fighting, Safety and Life Saving Equipment layout
drawings.
FIREWATER PUMP
Ref. Specification/ Datasheet No.:
3 Ensure Mechanical ITR-B for Diesel Engine Fire Pump is completed.
Name plate/tag details correct & in accordance with approved design
4 data sheet. Manufacturers test certificates & SAT documentation
available.
FIREWATER RING MAIN
Ref. Specification/ Datasheet No.:
5 Ensure Piping ITR B for Firewater Ring Main is completed.
6 Check piping/ ring main for signs of damage.
Ensure system flushing is conducted as per flushing procedures.
7 (Ensure gauges liable to be damaged at test pressure and during
flushing operations are removed and stored in instrument store).
8 Check flow at drains and any test connections.
9 Complete Certificate of Flushing after performing flushing operation.
Conduct hydrostatic testing as per approved project specifications and
record details of the hydrostatic test report. Attach copies of:
- Isometric sketch showing as built condition, test limits and
scope
10
- Test equipment calibration certificates
- Certificate of pressure test
- Pressure chart and temperature chart
- Test report
COMMENT(S) AND ADDITIONAL INFORMATION
(List the approved specification and datasheet reference number)

Page 1 of 2
PETRONAS CARIGALI SDN. BHD.

INSPECTION TEST RECORD (ITR) - B


FIREWATER/ FOAM SYSTEM S10-B

COMPLETED BY VERIFIED BY ACCEPTED BY


Designation Contractor Representative PMT Inspector Commissioning Engineer
Company PCSB PCSB
Name
Signature
Date

Page 2 of 2
PETRONAS CARIGALI SDN. BHD.

INSPECTION TEST RECORD (ITR) - B


FIRE SUPPRESSION SYSTEM/ TOTAL FLOODING S11-B
SYSTEM
Project No.
Project Title

INFORMATION
Tag no. System no.
Area Location
Ref. Drawing nos
INSPECTION / TEST OK N/A P/L No

Ensure A check list and A punch list items completed & no subsequent
1
damage occurred.

Check fire suppression/ total flooding system is connected to the fire


2
panel (including status display).

COMMENT(S) AND ADDITIONAL INFORMATION:

COMPLETED BY VERIFIED BY ACCEPTED BY


Designation Contractor Representative PMT Inspector Commissioning Engineer
Company PCSB PCSB
Name
Signature
Date

Page 1 of 1
PETRONAS CARIGALI SDN. BHD.

INSPECTION TEST RECORD (ITR) - B


DECK INTEGRATED FIRE FIGHTING SYSTEM S15-B
Project No.
Project Title

INFORMATION
Tag no. System no.
Area Location
Ref. Drawing nos
INSPECTION / TEST OK N/A P/L No
Ensure A check list and A punch list items completed & no subsequent
1
damage occurred.
Ensure Fire and Gas Device Loop Test (Instrument ITR I16-B) is
2
completed for DIFFS
COMMENT(S) AND ADDITIONAL INFORMATION:

COMPLETED BY VERIFIED BY ACCEPTED BY


Designation Contractor Representative PMT Inspector Commissioning Engineer
Company PCSB PCSB
Name
Signature
Date

Page 1 of 1