RMZ2 Campus7 Formwork
RMZ2 Campus7 Formwork
Raft/ Footings 15 70
Waterproofing 15 55
PCC 15 40
Minor Excavation 25 25
Start Date 0 0
217 232 237 233 238 253 317 14-May-15 10.56667 Months
75 80 85 90 95 100
442
212
230
7.666667
232
100
132
4.4
Months
420 436 441 446 450 466 471 476 480 496
330 346 351 356 360 376 381 386 390 406
176
5.866667
501 506
411 416
176
5.866667
SHUTTERING WORKS BLOCK-7
6 SLABS
B-1 SLAB SQM 10,825.36
GROUND FLOOR SLAB SQM 12,458.82
1ST FLOOR SLAB SQM 8,538.26
2ND FLOOR SLAB SQM 5,948.36
3RD FLOOR SLAB SQM 6,419.52
4TH FLOOR SLAB SQM 6,919.65
5TH FLOOR SLAB SQM 7,097.42
6TH FLOOR SLAB SQM 7,212.25
7TH FLOOR SLAB (partly certified) SQM 3,352.95
8TH FLOOR SLAB SQM
9TH FLOOR SLAB SQM
10TH FLOOR SLAB SQM
TERRACE FLOOR SLAB SQM
7 BEAMS
B-1 BEAMS SQM 1,349.85
GROUND FLOOR BEAMS SQM 1,023.07
1ST FLOOR BEAMS SQM 956.50
2ND FLOOR BEAMS SQM 690.28
3RD FLOOR BEAMS SQM 612.46
4TH FLOOR BEAMS SQM 697.47
5TH FLOOR BEAMS (partly certified) SQM 363.47
6TH FLOOR BEAMS (partly certified) SQM 53.44
7TH FLOOR BEAMS (partly certified) SQM 141.29
8TH FLOOR SLAB SQM
9TH FLOOR SLAB SQM
10TH FLOOR SLAB SQM
TERRACE FLOOR SLAB SQM
8 STAIR CASE SQM 2,756.12
123,608.14
Footing/Raft 2,939.16
Columns 13,259.68
Retaining Wall 10,297.93
Shear Walls 16,715.55
Beam 6,061.27
Slab 69,906.45
Staircase 2,756.12
Ramp Slab 1,020.45
Ramp Beam 607.26
Misc Work 44.27
KS BLOCK-7
Ballpark Total
Projection
2,167.88
-
250.00 4,057.25
-
668.09
-
2208.00 15,467.68
-
4976.00 20,274.97
-
-
700.00 11,525.36
700.00 13,158.82
8,538.26
5,948.36
6,419.52
6,919.65
7,097.42
7,212.25
3859.29 7,212.25
7212.25 7,212.25
7212.25 7,212.25
7212.25 7,212.25
5048.57 5,048.57 100,717.20
-
-
-
50.00 1,399.85
50.00 1,073.07
956.50
690.28
612.46
697.47
334.00 697.47
697.47 750.91
697.47 838.76
697.47 697.47
697.47 697.47
697.47 697.47
488.23 488.23
-
-
900.00 3,656.12
-
50.00 414.62
50.00 357.04
57.58
-
100.00 2,503.83
27.6
607.3
100.0 1,120.5
748.5
-
5,390.47
112.60
4,053.48
148.11
1,076.29
-
500.00 2,152.27 1635.6265 500.00 2135.63
16.64
500.00 2,135.63
-
1,178.56
658.67
25.34
494.54
-
-
45,338.18 168,946.32
-
45338.1795871 168,946.32
- 2,939.16
2,208.00 15,467.68
800.00 11,097.93
4,976.00 21,691.55
4,409.57 10,470.84
31,944.61 101,851.07
900.00 3,656.12
100.00 1,120.45
- 607.26
- 44.27
168,946.32
2167.88
0.00
3807.25
0.00
668.09
0.00
0.00
0.00
0.00
0.00
0.00
10825.36
12458.82
8538.26
5948.36
6419.52
6919.65
7097.42
7212.25
3352.95
0.00
0.00
1349.85
1023.07
956.50
690.28
612.46
697.47
363.47
53.44
141.29
2756.12
364.62
2403.83
5390.47
-483.36
1178.56
###
RMZ ECOWORLD - COMMERCIAL DEVELOPMENT
MAIN CIVIL WORKS FOR PLOT C3 - CAMPUS 7
BILL OF QUANTITIES /SCHEDULE OF ITEMS
v For Beams
a) From Basement 2 level to Ground Floor level Sqm 4530
b) From Ground Floor level to Terrace Floor level Sqm 7895
ix Ramps
a) Slab Sqm 1200
b) Beam Sqm 550
xiv OHT
Bottom Slab Sqm 140
Walls Sqm 260
Top Slab Sqm 140
Columns Sqm 60
Beams Sqm 40
xv UG Sump
Bottom Slab Sqm 55
Walls Sqm 4180
Top Slab Sqm 1560
xvi STP
Bottom Slab Sqm 10
Walls Sqm 1835
Top Slab Sqm 102
Beams Sqm
xvii WTP
Bottom Slab Sqm
Walls Sqm 230
Top Slab Sqm
xviii Formwork for Basement drain, drain water collection pits, etc. Sqm 2145
Formwork for DG foundation & pedastals , Security kiosk , Pump, RMU, Transformer Foundations, RCC
xix Sqm 1065
ducts,etc.
xx Extra for double height staging , including required platforms, etc Sqm 132
xxi Extra for Triple height staging , including required platforms,etc. Sqm 75
85 90 20 195.00 95,550.00
80 85 10 175.00 17,500.00
80 90 10 180.00 203,400.00
80 90 10 180.00 18,000.00
85 90 20 195.00 44,850.00
141 27 7 175.00
80 80.00 10,560.00
160 160.00 12,000.00
193 99 28 321
Using MS Sheets
Footings
Total Shuttering Area
Procurement Area
Perimeter
Columns
Rectangular columns
L B Total Nos
Material Required
Aluminium Beam 3.6m 1,040 Nos 1544
Steel Waler 1.2m long Nos 1372
Steel Waler 1.6m long 112 Nos 1778
Steel Waler 2.0m long 432 Nos 2268
Steel Waler 2.4m long 112 Nos 2626
Props 192 Nos 1598
Short prop 192 Nos 1135
COST-COLUMN
System cost 1,081,056 69.89
Ply & Timber 1,394,389 90.15
Misc 378,333 24.46
Total Material cost 2,853,778 184.50
Procurement = 274 Rm
Procurement Area = 986 Sqm
Material Required
Aluminium Beam 3.6m 1370 Nos @
Steel Waler 1.2m 913 Nos @
Props 274 Nos @
Short Prop 274 Nos @
Total cost
Wood
Plywood 3,099 Sqm @
Battens 249.6 Cft @
Cost of wood
Charge to Project 100%
Material Required
Aluminium Beam 3.6m 767 Nos @
Steel Waler 1.2m 520 Nos @
Props 156 Nos @
Short Prop 156 Nos @
Access- for 2nd lift
Cuplock vertical 3.0m 360 Nos @
Cuplock Horizontal 1.25m 360 Nos @
Cuplock Horizontal 1.80m 704 Nos @
Base Jack 360 Nos @
Wood
Plywood 1,457 Sqm @
Battens 85.3 cft @
Cost of wood
Charge to Project 100%
Qty Rate
121,329
428,411
22 (no of repititions)
1605760 Changed with H beam at site
0 checked checked
199136 checked checked
979776 checked checked
294112 checked checked
306,816 checked checked
217,920 Site confirmation required
3,603,520
1081056
600 1,309,738 7.09 checked check for rate with /without taxes
380 84,651 checked check for rate with /without taxes
1,394,389
1,394,389
-
144,160 checked check for rate with /without taxes
36,960 checked check for rate with /without taxes
-
73,472 checked check for rate with /without taxes
254,592
184
200
25
409.00
5,762,349
1,531,292.34
188
200
25
413
7.62 1109.793299
154.1 two sides of wall
77.1 per month
911,742
60 1,154,093
1000 261,000 add 50% for 2nd lvl
145 50,267
56 38,827
1,504,187
311
200
25
536
979.718653 0.2939155959
489.8593265
6.06
45.65
0
ate with /without taxes
ate with /without taxes
13.7
40.5
54.2
wall to be checked
274.002
87558.21
48499.9503
48498.4454
48499.3754
19929.8451
19729.8451
19899.9972
312515.666
312.515666
13405 1541.37958
9.2
2.55555556
12
checked checked
checked checked
checked checked
checked checked
4.8
checked 5.8 10.2222222
checked 11.2222222
checked
checked
checked
checked
checked
checked
checked
checked
Analysis for Basement Slab
TOTAL AREA -
Total 2,500.00
No of Capitals 30
cost of steel
Materials for drop
Steel
2.5 m vertical Nos 528 Rs. 689
1.5 m vertical Nos 528 Rs. 446
1.25 m Horizontal Nos 2,904 Rs. 266
Stirrup Head Nos 528 Rs. 238
Bottom Jack Nos 528 Rs. 217
Secondary 1.8 mtr Nos 1,287 Rs. 1,194
Repropping Nos - Rs. 1,598
Extra height
Material requirement for slab
2.5m vertical Nos 1,268 Rs. 689
1m vertical Nos Rs. 275
1.25 m Horizontal Nos 2,475 Rs. 266
1.8 m Horizontal Nos 2,481 Rs. 349
cost of steel
B Wood
Procurement constant
Ply wood for Slab Bottom & Drop sqm Rs. 600
Battens cft Rs. 380
C Consumables
20
4.05
Rs. 1,039,760 CHECKED CHECKED 0.25
Rs. 1,298,629 CHECKED CHECKED 3.80
Rs. 987,658 CHECKED CHECKED
Rs. 301,784 CHECKED CHECKED 0.232
Rs. 275,156 CHECKED CHECKED 3.57
Rs. 7,584,885 CHECKED CHECKED
Rs. - CHECKED CHECKED
Rs. 3,148,662
Rs. 873,652 CHECKED CHECKED
Rs. - CHECKED CHECKED
Rs. 658,439 CHECKED CHECKED
Rs. 865,753 CHECKED CHECKED
Rs. 2,397,843
17,034,377
CHECKED CHECKED
Rs. -
1,631,732
20.85
PODIUM SLAB
Total Area to be Covered Slab
Total Area to be Covered beam
Total Area to be Covered Capital -
TOTAL AREA -
Total 5,000.00
No of Capitals 100
cost of steel
Materials for drop
Steel
3.0 m vertical Nos 1,760 Rs. 820
1.25 m Horizontal Nos 7,260 Rs. 266
Stirrup Head Nos 1,760 Rs. 238
Bottom Jack Nos 1,760 Rs. 217
Secondary 1.8 mtr Nos 4,290 Rs. 1,194
Repropping Nos - Rs. 1,598
Extra height
Material requirement for slab
0..5m vertical Nos 1,760 Rs. 138
1m vertical Nos 2,537 Rs. 275
1.25 m Horizontal Nos 4,895 Rs. 266
1.8 m Horizontal Nos 2,481 Rs. 349
cost of steel
B Wood
Procurement constant
Ply wood for Slab Bottom & Drop sqm 5842 Rs. 600
Battens cft 114 Rs. 380
C Consumables
20
CHECKED CHECKED
1.8 CHECKED CHECKED
1.25 CHECKED CHECKED
CHECKED CHECKED
CHECKED CHECKED
CHECKED CHECKED
4.05
Rs. 2,080,340 CHECKED CHECKED 0.25
Rs. 2,597,258 CHECKED CHECKED 3.80
Rs. 1,975,050 CHECKED CHECKED
Rs. 603,806 CHECKED CHECKED 0.232
Rs. 550,529 CHECKED CHECKED 3.57
Rs. 15,169,770 CHECKED CHECKED
Rs. 4,864,951 CHECKED CHECKED
Rs. 27,841,704
Rs. 9,297,420
Rs. 242,880 CHECKED CHECKED
Rs. 697,675 CHECKED CHECKED
Rs. 1,302,070 CHECKED CHECKED
Rs. 865,753 CHECKED CHECKED
Rs. 3,108,378
40,247,502
6,037,125
Rs. 3,548,629
3,548,629
3,548,629
3,710,733
119.9025
41.70
TOWER SLAB
Total Area to be Covered Slab 28,840.50
Total Area to be Covered beam
Total Area to be Covered Capital -
Total 1,148.80
No of Capitals 56
cost of steel
Materials for drop (Tower)
Steel
3.0 m vertical Nos 1,344 Rs. 820
1.25 m Horizontal Nos 5,544 Rs. 266
Stirrup Head Nos 1,344 Rs. 238
Bottom Jack Nos 1,344 Rs. 217
Secondary 1.8 mtr Nos 3,276 Rs. 1,194
Repropping Nos - Rs. 1,598
Extra height
Material requirement for slab
0..5m vertical Nos 1,344 Rs. 138
1m vertical Nos 795 Rs. 275
1.25 m Horizontal Nos 2,623 Rs. 266
1.8 m Horizontal Nos 777 Rs. 349
cost of steel
B Wood
Procurement constant
Ply wood for Slab Bottom & Drop sqm 3820 Rs. 600
Battens cft 313 Rs. 380
C Consumables
check
1.8 check
1.25 check
check
check
423.985
Rs. 1,102,080 check
Rs. 1,474,704 check Approx Nos 30
Rs. 319,872 check
Rs. 291,648 check
Rs. 3,911,544 check
Rs. - check
Rs. 7,099,848
Rs. 1,373,077
17,196,104
4,911,677
Rs. 2,410,700
2,410,700
2,410,700
1,666,098
5 5 3.6 3.6
0.25 0.45 0.25 0.45
4.75 4.55 3.35 3.15
DROP
0.225 192.3723
0.225 82.08
14.44
Analysis for Beam
Total 716.00
cost of steel
Extra height
Material requirement for Beam
0..5m vertical Nos Rs. 138
1m vertical Nos Rs. 275
1.25 m Horizontal Nos Rs. 266
1.8 m Horizontal Nos Rs. 349
cost of steel
C Consumables
1,074.00
Rs. 1,035,660
Rs. 503,937 4.05
Rs. 1,319,220 0.9
Rs. 300,594 0.307
Rs. 274,071 1.207
Rs. 4,513,320
Rs. 2,421,929
2.843
Rs. 10,368,731
10,368,731
Rs. -
Rs. -
Rs. -
Rs. -
Rs. -
10,368,731
3,110,619
Rs. 759,493 8.27
Rs. 847,384
Rs. 1,606,877
1,606,877
1,606,877
Rs. 1,304,100
1,304,100 547,722
1,304,100 273,861
13509.9527 6.9
TOTAL BUA
Total slab Shut area
Table form scope assumed
1,530 1,316 -
6 6 4
B TABLE FORM AREA - TOWER
Sl No Description Unit T1 T1A T2A
Table size 1.7x3.6m 1.7X3.6m 1.15x3.6m
Table Nos 250 215
1 Aluminium Secondary 1.15m Nos -
2 Aluminium Secondary 1.70m Nos 3,000 2,580
3 Aluminium Secondary 2.5m Nos
4 Steel Waler 3.6m Nos 500 430 -
5 Steel Waler 2.4m Nos
6 Table Head Nos 1,000 1,290 -
7 CT Prop ( CT410) Nos 1,000 1,290 -
8 CT Prop ( CT410) extra support at patch Nos
9 Tableform Pallet Truck Nos
10 V Hook Nos 6,000 5,160 -
11 12mm thick plywood(densified) Sqm 1,275 1,097 -
12 12mm thick plywood (patch filling) Sqm
595 218
3641.4
Flat Slab Area T1 1.7 3.6 250
2.5 3.6 144
2.5 2.4 19
1.7 2.4 29
Tower Podium
7,120 Sqm -
0 5,616 Sqm 78.9% -
5,616 8,424 Sqm 1.5 Set -
0.67
6,503
1,296 114 118 - 4,374 (145)
9 6 4 3 5,327
T3 T4 T5 T6
2.5x3.6m 2.5x2.4m 1.7x2.4m 1.15x2.4m Total Qty Qty/Sqm Total Qty Rate
Planned
144 19 29
0 - - - 854
232 5,812 1.0 8,718 1,194
1,728 152 1,880 0.3 2,820 1,552
288 1,218 0.2 1,827 4,158
38 58 - 96 0.0 144 2,626
576 76 116 - 3,058 0.5 4,587 550
576 76 116 - 3,058 0.5 4,587 1,598
367 1,598
3 0.0 3 200,983
3,456 304 464 - 15,384 2.7 8,077 50
1,126 96 96 - 3,689 0.7 5,534 750
2,890 750
29 20
System
Plywood
Consumable
360000
1,530.00 27000
1,296.00
114.00 13.33333
118.32
1,315.80
4,374.12
215 14 201
1,504
check
check -
1.5 Set check
4366.478
-1031.04 600.9573
5,472
4967.435
System
Plywood & Timber
Consumables
Other Misc
Total material cost
Labour cost
Tower crane
Cost of Staircase
% charge Chargabel Amt
3.0% 36,818
3.0% 7,937
3.0% 3,168
3.0% 2,298
3.0% 9,046
3.0% 2,500
3.0% 5,484
3.0% 67,046
100% 32,040
100% 40,040
100% 1,728
100% 33,840
100% -
100% 64,040 10.44
100% 210,074
485,574 132.81
132.8
200.0
25.0
357.8
Total area 1,727.71 Sqm
Beam Area 607.26 Sqm 441.00
Slab Area 1,120.45 Sqm
Duration 6 Months
Procurement
Slab 86.988 Sqm 2 173.976
Beam 49 Rmt 2 98
Slab Beam
Material Description Unit Slab Beam
Qty/Sqm Qty/Rmt
4 Cuplock vertical 1.0m Nos 15 16 0.17 0.33
3 Cuplock vertical 1.5m Nos 15 12 0.17 0.24
2 Cuplock vertical 2.0m Nos 15 16 0.17 0.33
1 Cuplock vertical 2.5m Nos 25 24 0.29 0.49
5 Cuplock horizontal 1.25m Nos 134 128 1.54 2.61
6 Cuplock horizontal 1.80m Nos 100 78 1.15 1.59
7 Base Jack Nos 70 68 0.80 1.39
8 Stirrup Head Nos 70 68 0.80 1.39
9 Alum Secondary 1.80 Mtr Nos 162 120 1.86 2.45
Sqm
Rmt
731,973 423.67
SYSTEM COMPONENENT : Unit
Footing
CONSUMABLE COMPONENT :
ISMC 100 Rmt
Tie rod 1.0Mtr Set
Tie rod 1.5Mtr Set
Tie rod 2.0Mtr Set
Tie rod 2.5Mtr Set
Anchor nuts Nos
Spigot pin Nos
Walk way jallies Nos
40 NB MS Pipe Rmt
Swivel couplers Nos
V Hook ( Table Form ) Nos
Water stoper G type Nos
Plywood 12mm Thick densified Sqm
Plywood 12mm Thick semi densified Sqm 484.96
Wooden Runner 3"x2" Cft 361.67
Wooden Runner 3"x4" Cft
Wooden Runner 2"x5" Cft
Retaining
Column Corewall wall Slab from Raft Podium Slab Slab
6,957.39 3,101.18
731 347
544
112
1312 1462 694
1008 4297 2139
200 261
19234.88889
- 0
- 0
- 0
- 0
- 0
DOUBLE HEIGHT SLAB
Plan Area considered for calculation 1,064 Sqm 1679.769
Double Height Area 1,680 Sqm
Duration 3 Months
Beam
Bottom
B D
1 0.20 0.80 0.15 49.00 0.20 0.65 1.00 73.50 49.00 9.80
9.80
49.00 73.50 Sqm
BEAM
0.00
82.03 sqm 595.25 Rmt
1952.41 Rft
81.35 CFT
Slab Total
Sl No BEAM Thick L B D NOS Area Length PLY WOOD
Beam
Bottom
B D
1 0.30 0.60 0.15 226.00 0.30 0.45 1.00 271.20 226.00 67.80
2 0.30 0.80 0.15 278.00 0.30 0.65 1.00 444.80 278.00 83.40
151.20
504.00 716.00 Sqm
Capital Drop Total Slab Edge Total
Perimeter 2439.58 0 0
Height 0.225 0.28 0.15
Perimeter 1520 0 0
Height 0.225 0.28 0.15
3"x2" Runner cft 103.90 103.90 0.04 0.02 0.06
Plywood Sqm 342 342.00 0 0 0.00
BEAM
743.32 CFT
387.84
0.67
0.46
rmedby jaykar sir
rmedby jaykar sir
Procurement Cost Charged to the Project
SL No Description
Steel Wood Misc Total Steel Wood Misc Total
#REF! #REF!