Construction Material Transport Costs

This document provides a cost breakdown for construction materials and labor for building a pucca drain. It lists transportation and material costs for stone metal, bitumen, and mixed materials to a total of Rs. 511.09 per square meter. It also provides a cost of Rs. 158.31 per cubic meter for excavating hard/dense soil for drain foundations including taxes. The document gives a detailed cost estimate for building a pucca drain from quarrying and transporting materials to excavation.

Uploaded by

Hemam Prasanta
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
183 views1 page

Construction Material Transport Costs

This document provides a cost breakdown for construction materials and labor for building a pucca drain. It lists transportation and material costs for stone metal, bitumen, and mixed materials to a total of Rs. 511.09 per square meter. It also provides a cost of Rs. 158.31 per cubic meter for excavating hard/dense soil for drain foundations including taxes. The document gives a detailed cost estimate for building a pucca drain from quarrying and transporting materials to excavation.

Uploaded by

Hemam Prasanta
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

p/166 1 x Rs.55.70 /sqm = Rs.55.

70 / sqm
Transportation charges (Quarry toMixing yard)
a) Stone metal below 40mm 0.03400 cum/sqm@ Rs.645.17 /cum = Rs.21.94 / sqm
b) Bitumen
i) Carriage charge (Source to W/site)
( 0.5 / 1000 ) MT/sqm x Rs.210.63 = Rs.0.11 / sqm
ii) Carriage charge (Source to mixing yard)
( 316.25 )/ (1000 x100) MT/sqm x Rs.134.61 = Rs.0.43 / sqm
iii) Mixed material from yard to site
= 2.3MT/CUM' 0.0575 x Rs.242.19 = Rs.13.93 / sqm
Rs.452.29 / sqm
Add 12% GST = Rs. 54.28 / sqm
Add 1%Labour Cess = Rs. 4.52 / sqm
Rs. 511.09 / sqm
Pucca drain
Item -5 Earthwork in excavation of foundation trenches or drains including dressing of sides and ramming of bottoms lift upto 1.5metres including getting out the
excavated soil and disposal of surplus excavated soil as directed within a lead of 50 metres. 1.10.2. Hard/Dense Soil.
p/66 = Rs.140.10 / Cum
Add 12% GST = Rs. 16.81 / Cum
Add 1%Labour Cess = Rs. 1.40 / Cum