JABAL OMAR DEVELOPMENT
INSPECTION AND TEST PLAN
PROJECT- PHASE IV
ZONE S09, S10 AND S11 (REINFORCED CONCRETE SLAB CONSTRUCTION)
Fixing of reinforcement, supply and installation of formwork, MEP embeds and pouring for CONCRETE
WORK SCOPE
SLAB
MAIN CONSULTANT EHAF
MAIN CONTRACTOR RUWAD CIVIL CONSTRUCTION
PART 1- APPROVALS REQUIRED PRIOR TO COMMENCEMENT OF THE WORKS
Item Frequency of Hold, or Witness Point
Description of Operation/Inspection, Test and Approval Records Generated
No. Inspection & Test Plan Subcont. RCC EHAF
Approved Shop
1 Shop Drawings- Civil & Structural, MEP Once Sub* R R&A
Drawings
Materials Submittals- Concrete Mix, Reinforcement, Mill Certificate, Mix
2 Embedded Pipes, Curing Compound, Concrete Repair Once Design, Data Sheets, Sub R R&A
Materials, PVC Spacers, Couplers Batch Certificates
Propriety Design &
3 Formworks System – Design and Calculation Once Sub R R&A
Drawings
4 Method Statement, Inspection & Test Plan, Check List Once MS, ITP, CL Sub R R&A
Approved Drawings,
5 Survey reference and Bench Marks (drawings) Once Sub** R R&A
Control Point
Permits, Licenses, NOC’s and Authority Approvals (if
6 Once Approval of work Sub** R R&A
required)
Note*- All deviation from the approved drawings/documents to be recorded and discussed with the Main Consultant prior to
proceeding. * Other subcontractor/sub consultant engaged by RCC. ** By RCC
Page 1 of 2
JABAL OMAR DEVELOPMENT
INSPECTION AND TEST PLAN
PROJECT- PHASE IV
ZONE S09, S10 AND S11 (REINFORCED CONCRETE SLAB CONSTRUCTION)
PART 2- INSPECTION AND TEST DURING CONSTRUCTION OF WORKS- CONCRETE SLAB
Item Frequency of Hold, or Witness Point
Description of Operation/Inspection, Test and Approval Records Generated
No. Inspection & Test Plan Subcont. RCC EHAF
Prior to start the
1 Setting out- Alignment, Orientation, openings, level IR, Survey Report H H RC
Rebar & Formwork
Formwork Fixation- Form Release Agent Application,
2 By Area/Layout IR/CL H H S
Edge Setting out, Openings, Dimension, Supports
Steel Reinforcement Installation- Overlap, coupler, bar
3 By Area/Layout IR/CL H H S
sizes, bar marks, bars position/arrangement
4 Embedded MEP items installation By Area/Layout IR/CL H H S
Consultant Inspection and Approval for
5 By Area/Layout IR H H I&A
Reinforcement, MEP and Formworks prior to casting
Concrete Order and Casting- Sampling: Slump/Flow, Delivery notes, Pour
6 By Area/Layout H H RC
Temperature, Compressive Strength Record
Shutter/Formwork Removal- Release and removal of
7 shutter and props are as per required in the By Area/Layout Deshuttering record H H S
specification.
Abbreviations: Sub- SUBMIT, H- HOLD, R&A- REVIEW & APPROVE, RC- RANDOM CHECK, I&A- INSPECT & APPROVE, S- SURVEILANCE,
CL= CHECKLIST, IR- INSPECTION REQUEST
Page 2 of 2