THE ENGINEER:                                                              THE CONTRACTOR:
New King Abdul-Aziz International
                               Airport Development Project
                                        (Phase I) Jeddah, KSA
Contractor: Saudi Binladin Group                   Doc. Ref. No.: 421-422-DCS-MST-E-00722-Rev01
Contract No.: J-10-422-PF-0                        Date Issued:
Contract Title: Aprons, Taxiways, Roads, Tunnels, Bridges, Load Centers and Infrastructure,
                Transportation Center and Supporting Facilities
                                Method Statement
                                                For
                           Low Voltage Transformer
                                       ( Installation )
                                           Submitted By:
                                      Advanced Vision Co.
                                         (Sub-Contractor)
                    Prepared By              Reviewed By            Reviewed By           Approved By
                (Contractor/Sub-Con)       (QA/QC Manager)        (Safety Manager)      (Project Manager)
                                                                                          Eng. Aghyad
  Name :         Engr. Hanna Nassar        Engr. Oussama Abbas   Engr. Motasim Badawi
                                                                                          Dimashqiyeh
  Signature:
  Date:
THE ENGINEER:                New King Abdulaziz International               THE CONTRACTOR:
                               Airport Development Project
                                         (Phase I)
                                            Jeddah, KSA
Contractor: Saudi Binladin Group                    Doc. Ref. No: 421-422-DCS-MST-E-00722-Rev01
Contract No.: J-10-421-PF-0/J-10-422-PF-0           Date Issued:
                         Method Statement for Low Voltage Transformer
                                       List of Contents
    Section               Title                                                         Page
    1.0                   SCOPE OF WORKS                                                 03
    2.0                   PERSONNEL RULES AND RESPONSIBILITIES                           03
    3.0                   CONSTRUCTION PROCEDURES                                        04
    4.0                   CONFORMANCE CRITERIA                                           07
    5.0                   MATERIALS                                                      08
    6.0                   PLANT AND EQUIPMENT                                            09
    7.0                   STORAGE AND HANDLING                                           09
    8.0                   HEALTH AND SAFETY                                              09
    9.0                   ENVIRONMENTAL REQUIREMENTS                                     10
    10.0                  REFERENCES                                                     12
                          Appendix A – Draft Final Drawing
                          Appendix B – Design Report
                          Appendix C -Typical Detail of Low Voltage Transformer
    11.0                  ATTACHMENT                                                     15
                          Appendix A - Sample Test Report
                          SPECIFICATION OF LOW VOLTAGE
    12.0                  TRANSFORMER                                                    15
THE ENGINEER:                    New King Abdulaziz International               THE CONTRACTOR:
                                   Airport Development Project
                                             (Phase I)
                                                Jeddah, KSA
Contractor: Saudi Binladin Group                         Doc. Ref. No: 421-422-DCS-MST-E-00722-Rev01
Contract No.: J-10-421-PF-0/J-10-422-PF-0                Date Issued:
                             Method Statement for Low Voltage Transformer
 1.0        Scope of Work
            The purpose of this Method Statement is to describe the steps to be taken for achieving
            specified requirement for installation of Low Voltage Transformer .
 2.0        Personnel Rules and Responsibilities
       a. the personnel present on site consist of:
          Electrical engineers who monitor all work on site in order to ensure that all standards and
          specs. are being monitored and that the work being executed is of the highest levels of
          professionalism and accuracy.
       b. Quality Control engineer inspects and ensure the construction work is carried out according
          to project’s standards and specifications.
       c. Foremen shall be present on site all the time to give out the correct Instructions for the work
          required according to Electrical Standards and project specifications.
       d. Qualified Technicians lead the way in the required tasks and execute instructions using
          Electrical Code of Standards each in their own field discipline, while accurately considering
          the project’s standards & specs.
       e. Qualified Cable Splicer,trained and certified by material manufacturer,to install,splice and
          terminate at Low Voltage transformer .
       f. The rest of the personnel consist of labours to aid the technicians, store keepers to ensure
          that the material stored is located in a safe environment with proper conditions of storage
          and safety officers who guarantee that all personnel are abiding by the safety rules and
          regulations of site work.
 3.0        Construction Procedures
       a. Physical Inspection of Transformers and accessories shall be carried out for identification and
          damage if any.
       b. Lifting of the transformer shall be done by using lifting hooks provided on transformers.
       c. Trailer / Crane shall be used for loading, unloading and transporting the transformers from
          store to site.
       d. The transformers shall be properly tied with ropes and stoppers on the trailer shall be
          provided to avoid tilting of the transformer in transit due to jerks and vibration.
       e. The transformer foundation level and elevation shall be checked as per civil foundation
          drawing.
       f. Transformer shall be lifted by crane; special care shall be taken to avoid any tilting while
          lifting.
       g. Transformer base and structure are to have lifting hooks or lugs, towing and lashing eyes or
          lugs and provision for roller wheels.
       h. All other accessories shall be mounted on transformer as per manufactures recom-
          mendation.
       i. Final allignment and fixing of transformer shall be done after erection of bus ducts.
       j.   All the bushing shall be cleaned and checked to ensure that there is no crack or leakage.
THE ENGINEER:                    New King Abdulaziz International            THE CONTRACTOR:
                                   Airport Development Project
                                             (Phase I)
                                              Jeddah, KSA
Contractor: Saudi Binladin Group                       Doc. Ref. No: 421-422-DCS-MST-E-00722-Rev01
Contract No.: J-10-421-PF-0/J-10-422-PF-0              Date Issued:
                             Method Statement for Low Voltage Transformer
       k. All the nuts and bolt fitted with the transformer tank shall be checked for tightness.
       l. All the wiring connections shall be checked as per vendor’s drawing.
       m. Installation of all incoming and outgoing cable supports, cable ends and termination fittings
          required for MV, LV and control cables.
       n. Lead length from the gland to the centre phase terminal of cable box shall be minimum 450
          mm and for the other two phases shall be maximum 500 mm
       o. The LV Termination shall comprise 4 pole air insulated cable box with detachable gland
          plate, complete with brass compression glands for receiving and terminating cables.
       p. Tightening of bus joint, connector, and terminal bolts according to manufacturer's published
          torque-tightening values.
       q. Insulation resistance test for the primary and secondary winding and winding to ground .
       r. Examine walls, floors, roofs, and concrete bases for suitable mounting conditions where
           transformers will be installed .
       s. Grounding installation as described in Division 26 Section "Grounding and Bonding" for
          electrical systems. max. ground resistance shall be 5 ohms at location of transformer.
       t. Identification of transformers and installation of warning signs according to Division 26
          Sec."Identification for Electrical Systems."
       u. Connect wiring according to Division 26 Section "Low-Voltage Electrical Power Conductors
          and cables.
       v. Insulation Resistance test of Transformer Primary and Secondary winding to winding and
          winding to ground.
 4.0      Conformance Criteria
          The Personnel on Site ensure that the work done conform to the IEC Standard and
           The required specifications.
           For this task , it consist of the following project Standards/specifications :
           1.   NEMA ST 20, NEMA ST 1, UL 1561,UL 506
           2.   Enclosure: Ventilated, NEMA 250, Type 2 (for indoor use).
           3.   Enclosure: Ventilated, NEMA 250, Type 4X, stainless steel (for outdoor use).
           4.   Transformer Enclosure Finish: Comply with NEMA 250.
           5.   Compliance with NEMA TP 1, Class 1 efficiency levels.
           6.   Low-Sound-Level Requirements: Minimum of 3 dBA less than NEMA ST 20 standard
                Sound levels when factory tested according to IEEE C57.12.91.
 5.0      Materials To Be Used
           1.   Low Voltage Transformer
           2.   MV / LV Cables
           3.   Cable Gland
           4.   Cable Gland Shrouds
           5.   Terminal Lugs
           6.   Electrical Tapes
           7.   Identification Markers
           8.   Warning Signs
THE ENGINEER:                  New King Abdulaziz International               THE CONTRACTOR:
                                 Airport Development Project
                                           (Phase I)
                                             Jeddah, KSA
Contractor: Saudi Binladin Group                      Doc. Ref. No: 421-422-DCS-MST-E-00722-Rev01
Contract No.: J-10-421-PF-0/J-10-422-PF-0             Date Issued:
                           Method Statement for Low Voltage Transformer
 6.0    Plant and Equipment
     The Equipment used in this task consist of the following :
         a.   Crane
         b.   Trailer Truck
         c.   Slings, Ropes, etc.
         d.   Scaffoldings
         e.   Ladder
         f.   Electrical Tool Box
         g.   Mechanical tool box
         h    Grinding Machine
         h    Megger Tester
         i.   Multimeter digital
 7.0    Storage and Handling
         As was mentioned earlier, all materials stored on site are monitored by qualified
         storekeepers that ensure they are in good conditions and safe from environmental
         conditions that might endanger them ( e.g. moisture, heat, dust,friction ) . Materials shall be
         stocked and stored in a safe confined space to prevent from deterioration and damage , the
         delivered material shall be checked to conform to the project specifications. as for the
         handling , workers are instructed to carefully treat all equipment and material with care and
         engineers as well as foremen monitor thematerial handling process for extra assurance.
 8.0 Health and Safety
         Health and Safety International Standards are always implemented on site
         through our experienced health and safety officers and engineers so as to
         prevent danger , hazards that mightlead to serious injuries.Use of approved
         PPE uniforms, tools and equipment by workers at site.
 9.0 Enviromental Requirements
         All construction related works shall be executed to the highest levels of
         quality While at the same time avoiding any operation that might
         endanger the environment .therefore,materials are carefully chosen to be
         as environment friendly as possible. Any hazardous material is carefully
         stored as mentioned Earlier and scrap materials are carefully disposed off.
THE ENGINEER:                New King Abdulaziz International          THE CONTRACTOR:
                               Airport Development Project
                                         (Phase I)
                                            Jeddah, KSA
Contractor: Saudi Binladin Group                   Doc. Ref. No: 421-422-DCS-MST-E-00722-Rev01
Contract No.: J-10-421-PF-0/J-10-422-PF-0          Date Issued:
                         Method Statement for Low Voltage Transformer
 10.0 Reference
        Appendix A – Draft Final Drawing
        Appendix B – Design Report
        Appendix C – Typical Detail for Low Voltage Transformer
 11.0 Attachment
         Appendix A – Sample Test Report
 12.0 SPECIFICATION OF LOW VOLTAGE TRANSFORMER