L. Gantt Chart: Program of Works

The Gantt chart outlines a program of works for a construction project from March 2022 to December 2022. It lists 31 tasks in chronological order including document review, cost evaluation, pre-construction planning, bidding, site examination, construction activities like excavation and framing, and completion. The chart assigns start and finish dates to each task and calculates their individual durations in days to map out the critical path and full project timeline.

Uploaded by

Lianne Von
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
428 views2 pages

L. Gantt Chart: Program of Works

The Gantt chart outlines a program of works for a construction project from March 2022 to December 2022. It lists 31 tasks in chronological order including document review, cost evaluation, pre-construction planning, bidding, site examination, construction activities like excavation and framing, and completion. The chart assigns start and finish dates to each task and calculates their individual durations in days to map out the critical path and full project timeline.

Uploaded by

Lianne Von
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

L.

GANTT CHART
PROGRAM OF WORKS

ID TASK START FINISH DURATION


1 Document Review 03/01/2022 15/01/2022 12
2 Evaluate Cost 16/01/2022 23/01/2022 7
3 Pre-Construction 23/01/2022 09/04/2022 75
4 Gets Bid 25/01/2022 18/02/2022 25
5 Review Contract 19/02/2022 26/02/2022 7
6 Solicits and Evaluate Bids 27/02/2022 05/03/2022 7
7 Contract Agreement 05/03/2022 12/03/2022 7
8 Site Examination 13/03/2022 27/03/2022 14
9 Identify Risks 27/03/2022 02/04/2022 7
10 Approve Construction Draft 03/04/2022 05/04/2022 2
11 Setting Project starting date 05/04/2022 06/04/2022 1
12 Building Permits 07/04/2022 18/04/2022 12
13 Install Construction Storage 19/04/2022 21/04/2022 3
14 Construction 19/04/2022 03/10/2022 195
15 Excavate the land 19/04/2022 01/05/2022 12
16 Do Rough Framing 02/05/2022 15/05/2022 13
17 Layout Footings 16/05/2022 28/05/2022 12
18 Install Reinforcement 29/05/2022 17/06/2022 18
19 Back Filling and Compaction 18/06/2022 26/06/2022 8
20 Set steel 26/06/2022 17/07/2022 21
21 Staging and Framing 18/07/2022 29/07/2022 11
22 Electrical Works 30/07/2022 11/08/2022 12
23 Plumbing Works 30/07/2022 11/08/2022 12
24 Concrete Works 01/08/2022 16/09/2022 45
25 Roofing and Ceiling Installation 17/09/2022 01/10/2022 15
26 Install Doors and Windows 02/10/2022 16/10/2022 14
27 Finish Rough Construction 17/10/2022 21/10/2022 4
28 Paint 21/10/2022 01/12/2022 40
29 Finish Exterior Works 01/12/2022 21/12/2022 20
30 Install Network Facilities 20/12/2022 25/12/2022 5
31 Payment of Construction 26/12/2022 28/12/2022 3
32 Completion 29/12/2022 30/12/2022 1