GANTT CHART
PROGRAM OF WORKS
ID TASK START FINISH DURATION
1 Document Review 03/01/2022 15/01/2022 12
2 Evaluate Cost 16/01/2022 23/01/2022 7
3 Pre-Construction 23/01/2022 09/04/2022 75
4 Gets Bid 25/01/2022 18/02/2022 25
5 Review Contract 19/02/2022 26/02/2022 7
6 Solicits and Evaluate Bids 27/02/2022 05/03/2022 7
7 Contract Agreement 05/03/2022 12/03/2022 7
8 Site Examination 13/03/2022 27/03/2022 14
9 Identify Risks 27/03/2022 02/04/2022 7
10 Approve Construction Draft 03/04/2022 05/04/2022 2
11 Setting Project starting date 05/04/2022 06/04/2022 1
12 Building Permits 07/04/2022 18/04/2022 12
13 Install Construction Storage 19/04/2022 21/04/2022 3
14 Construction 19/04/2022 03/10/2022 195
15 Excavate the land 19/04/2022 01/05/2022 12
16 Do Rough Framing 02/05/2022 15/05/2022 13
17 Layout Footings 16/05/2022 28/05/2022 12
18 Install Reinforcement 29/05/2022 17/06/2022 18
19 Back Filling and Compaction 18/06/2022 26/06/2022 8
20 Set steel 26/06/2022 17/07/2022 21
21 Staging and Framing 18/07/2022 29/07/2022 11
22 Electrical Works 30/07/2022 11/08/2022 12
23 Plumbing Works 30/07/2022 11/08/2022 12
24 Concrete Works 01/08/2022 16/09/2022 45
25 Roofing and Ceiling Installation 17/09/2022 01/10/2022 15
26 Install Doors and Windows 02/10/2022 16/10/2022 14
27 Finish Rough Construction 17/10/2022 21/10/2022 4
28 Paint 21/10/2022 01/12/2022 40
29 Finish Exterior Works 01/12/2022 21/12/2022 20
30 Install Network Facilities 20/12/2022 25/12/2022 5
31 Payment of Construction 26/12/2022 28/12/2022 3
32 Completion 29/12/2022 30/12/2022 1