1. This document provides installation instructions for a Ford 289-302 "Action Plus" intake manifold. It outlines the parts required, tools needed, and step-by-step process for removing the old manifold and installing the new one. 2. Key steps include removing vacuum lines, draining the radiator, removing the carburetor and ignition components, cleaning the cylinder head surfaces, and applying sealant before bolting on the new manifold. 3. Once installed, the instructions specify reconnecting linkages, filling fluids, starting the engine, setting timing, and checking for leaks before completing the job.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
174 views2 pages

Ford Engine Manifold Install Guide

1. This document provides installation instructions for a Ford 289-302 "Action Plus" intake manifold. It outlines the parts required, tools needed, and step-by-step process for removing the old manifold and installing the new one. 2. Key steps include removing vacuum lines, draining the radiator, removing the carburetor and ignition components, cleaning the cylinder head surfaces, and applying sealant before bolting on the new manifold. 3. Once installed, the instructions specify reconnecting linkages, filling fluids, starting the engine, setting timing, and checking for leaks before completing the job.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

8011 289-302 FORD “ACTION PLUS”

INTAKE MANIFOLD
INSTALLATION INSTRUCTIONS
This instruction sheet is designed to cover a wide variety of vehicle applications. If your vehicle is not equipped with
the items referred to in these instructions (EGR, transmission kick-down linkage, air conditioning, and power brakes),
proceed to the next step.

Holley Performance Products cannot and will not be responsible for any alleged or actual engine or other damage, or other conditions resulting
from misapplication of the products described herein. However, it is our intent to provide the best possible products for our customer; products
that perform properly and satisfy your expectations. Should you need information or parts assistance, please contact our Technical Service
Department at 1-270-781-9741, Monday through Friday, 7 a.m. to 5 p.m. CST. Please have the part number of the product you purchased on
hand when you call.

IMPORTANT: Although all WEIAND parts pass several inspections, it is imperative that the installer personally inspects the part before
installation. Run a stiff wire through passages while shining a bright light into it. Also, wash the part using a mild soap and water solution.
Check the fit on all boltholes for proper alignment and thread any fittings in first by hand. Failure to perform these simple checks could result in
engine damage and may void your warranty.

APPLICATION: The WEIAND 8011 Action Plus manifold, has been designed to be used on 289 and 302 (Wedge) Ford engines. This 180°
dual-plane manifold is designed as a stock replacement manifold with improved power and torque. The effective RPM range of this manifold is
off idle through approximately 5500 RPM. The carburetor-mounting pad is designed to accept either a stock or aftermarket carburetor.
Combined with Weiand’s dyno-matched cam kits, the Action Plus series provides the ultimate in economical street performance. The “Action
Plus” manifolds have been designed to accept most stock hardware, such as coolant and vacuum lines, coils, and brackets. Little alterations, if
any, will be required.

NOTE: It may be necessary to purchase some of the parts listed below (or their equivalents) in order to properly complete the manifold
installation. Determination of equivalency is the responsibility of the consumer. WEIAND does not assume that responsibility.

PARTS REQUIRED:
A. Intake manifold gasket set, such as Fel-Pro P/N 1250.
B. Thermostat housing gasket.
C. Oil-resistant, silicone based sealant, such as Permatex Silicone “Form-A-Gasket”, Dow Corning Silastic, or equivalent.
D. Spray gasket adhesive, such as Fel-Pro’s “Spray Tack”, P/N 220.
E. Pipe plugs, if needed.
F. Carburetor base gasket (usually supplied with the carburetor).
G. Teflon tape.

NOTE: Never install tapered (pipe) fittings in an aluminum manifold without Teflon tape or thread damage will likely occur.

TOOLS REQUIRED:
A. Socket wrench set – 3/8” drive ratchet and extensions H. Needle nose pliers
B. Open end wrenches – 3/8” to 1” I. Drain bucket
C. Box end/flare wrenches (optional) J. Timing light
D. 10” adjustable wrench (crescent) K. Torque wrench
E. Ignition wrench set L. File
F. Screwdrivers – standard and Phillips, various lengths M. 5/16” x 18NC tap (for cleaning bolt holes)
G. Gasket scraper

MANIFOLD REMOVAL PROCEDURE


1. Disconnect the ground cable from the battery.
2. Identify the vacuum and crankcase ventilation hoses (if any) leading to air cleaner and note routing and connection points. Remove the air
cleaner.
3. Prior to removing any other vacuum lines, identify the routing of the lines. Mark and remove the vacuum lines from the carburetor and/or
intake manifold.
4. Drain the radiator. (It may be necessary to remove the bottom radiator hose if there is no drain plug in the radiator).

WARNING: Hot water and steam may be present if the engine is still warm.
5. Disconnect the throttle linkage, transmission kick-down linkage (auto trans. only), and choke rod from the carburetor, (if applicable).
6. Loosen the gas cap to relieve pressure from the fuel system. Disconnect the fuel line at the carburetor using flare wrenches. Plug the end
of the fuel line to prevent fuel leakage. Remove the carburetor.
7. Tag and disconnect the ignition coil and sensor wires. Remove the ignition coil bracket and the coil.
8. Remove the radiator hose, thermostat housing, and the thermostat.
9. Remove all water and vacuum fittings from the manifold.
10. Remove all remaining brackets (if any) from the manifold.
11. Loosen and remove valve covers to assist in the manifold removal and the new manifold instructions.

IGNITION REMOVAL PROCEDURES


NOTE: In some applications, removal of your distributor is not necessary. If so, move on to step 6 below.

CAUTION: FOLLOW THESE INSTRUCTIONS CAREFULLY, AS SERIOUS DAMAGE CAN OCCUR WHEN THE IGNITION IS NOT RE-
INSTALLED CORRECTLY.

1. Remove the distributor cap.


2. Note the position of the rotor and make a mark on the distributor case in line with the rotor tip.
3. Note the position of the distributor vacuum canister and place some type of reference mark on a convenient surface.
4. Note the position of the points, if open, how much; if closed, note the distance from the point block to the cam lobe.
5. Remove the distributor. DO NOT rotate the engine after removing the distributor.
6. Remove the 12 intake manifold-to-cylinder head bolts.
7. Remove the intake manifold.

INSTALLING YOUR NEW WEIAND MANIFOLD


1. To prevent gasket pieces from falling into ports and valleys when cleaning old gaskets from head surfaces, lay rags into all ports and
valleys. When clean, remove the stuffing carefully. Make sure that all particles that fell on the rags are completely removed. Wipe
surfaces with rags soaked in lacquer thinner or alcohol to remove any oils or grease. This is a must for proper manifold/gasket sealing.
2. Apply a thin coat of spray adhesive to the cylinder head side of the intake gasket surface. Lay the manifold gaskets in place.
3. Ford changed the design of the water outlets in the heads throughout the years. WEIAND manifolds will work on any year heads, provided
that the correct gasket is used. Due to their superior sealing qualities, WEIAND recommends using a high performance style intake
manifold gasket set, such as Fel-Pro’s P/N 1250.
4. Apply a 1/4” wide bead of oil-resistant RTV-silicone sealant to the front and rear block-sealing surfaces, making sure to overlap manifold
gaskets at all four corners. Do not use cork or rubber seals.

NOTE: Thread sealant should be used on all bolt threads.

5. Carefully, lay your WEIAND intake manifold in place. If the manifold must be moved, re-check the gaskets. Install the intake bolts initially
torquing to 10 ft./lbs., then 15 ft./lbs., following the factory GM sequence, and finally torque to 25 ft./lbs.
6. Install the thermostat, gasket, and housing (using silicone sealant on both sides of the gasket). Be sure that the thermostat housing has
been cleaned of any old gasket material.
7. Install the heater and radiator hoses.
8. If you had to remove your distributor, install it at this time. Make sure that your distributor engages the oil pump drive shaft.
9. Check the location of the rotor and distributor body, making sure your reference marks line up. Refer to ignition removal section (steps 2,
3, & 4). Tighten the distributor body just enough that it can still be rotated by hand.
10. Install all water sensors and vacuum fittings into the manifold.

NOTE: Use Teflon tape or pipe dope on all pipe threads.

11. Plug all unused water and vacuum ports in the manifold.
12. Install your four carburetor studs in the manifold. Place the carburetor gasket on the clean carburetor pad. Do not use any type of sealant
on the carburetor gasket.
13. Install the carburetor. Connect all linkage and throttle springs.
14. Connect all vacuum and fuel lines. Refer to your tags or drawings for correct placement.
15. Automatic transmissions only: Adjust kick-down or throttle pressure linkage for proper shift points. Check all linkages, making sure that
there are no obstructions in function.
16. If required, reinstall valve covers and new gaskets.
17. Install the A/C and coil brackets, coil, wires, and all brackets that were removed from the manifold.
18. Close the drain and fill the radiator to the proper level with coolant.
19. Retighten the gas cap and connect the battery cable.
20. Hook up the timing light and start the engine. Set the timing to factory specs. Tighten the distributor.
21. Check for possible fuel, oil, or coolant leaks and for proper choke operation.
22. Install the air cleaner.

CAUTION: Check to be sure that there is adequate clearance for the throttle and choke linkages through their range of travel.

IMPORTANT: Check for adequate hood clearance before closing the hood.

23. Operate the engine for 30 minutes. Allow the engine to cool and retorque the manifold bolts following step 4 above.

YOUR MANIFOLD INSTALLATION IS COMPLETED. NOW IS A GOOD TIME TO CHANGE YOUR OIL AND FILTER.