Proposed Design of 600 MW Coal - Fired Power Plant Located at Brgy. Balanga, Lemery, Batangas
Proposed Design of 600 MW Coal - Fired Power Plant Located at Brgy. Balanga, Lemery, Batangas
MERCADO, BRYAN V.
PANOPIO, VINCE LEMUEL B.
RIVERA, LEMUEL ARNEL A.
ME – 5302
17 JULY 2019
i
EXECUTIVE SUMMARY
The design of the proposed project 600 MW Coal – Fired Power Plant
owned by MRP Power Generation Corporation consists of two steam turbines
which both provide a 300MW capacity. The plant capacity was based on the
increasing power demand of the Philippines particularly in the Luzon grid. The
power plant will be located in Brgy. Balanga, Lemery, Batangas. The location
is in a vacant lot distanced from commercial establishments such as resorts,
but is strategically located along the shore line of Balayan Bay. Balayan Bay
will serve as the water source for plant operations
Among the three design options, the most beneficial one was selected.
Design option 2 was selected as it gave the best efficiency of 31.9% without
sacrificing economic viability.
ii
TABLE OF CONTENTS
Page No.
EXECUTIVE SUMMARY ii
TABLE OF CONTENTS iii
LIST OF TABLES v
LIST OF FIGURES vii
CHAPTER
I INTRODUCTION
Introduction 1
Subject of the Report 2
Capitalization 2
Ownership 2
Organizational Set-up with Technical Organization 3
Location Map 3
Load Projection 7
II REPORT PROPER
Theoretical Consideration 8
Scope of the Design of a 600 MW Coal –Fired 9
Power Plant
Design Options 10
Design Option 1 10
Design Option 2 11
Design Option 3 12
Design Data 13
Summary of Calculations 15
Design Options 15
Design Option 1 15
Design Option 2 18
Design Option 3 22
Fuel and Boiler Efficiency 26
Coal Transport and Storage 28
Chimney 29
iii
Cooling Water Requirement 29
Environmental Parameters 30
Equipment Selection 30
Components of a Coal-Fired Power Plant 34
Process/Schematic/System Diagram 38
Environmental Impact Assessment (EIA) 40
Environmental Impact Mitigation Measures 43
V BIBLIOGRAPHY
Bibliography 70
APPENDICES
A. Computations 72
B. Catalogue 121
C. Project Documentation 129
iv
LIST OF TABLES
Table No. Title Page No.
1 Comparison of Parameters of the Three Locations 4
v
26 Summary of Calculations for SST 5000, SST 4000, and STF 31
D650 based on Design Option 2
27 Equipment Selection 32
28 Summary of Equipment 33
vi
LIST OF FIGURES
Table No. Title Page No.
1 Organizational Chart 3
12 Condenser, GE 36
13 Gigatop Generator. GE 36
15 Deaerator, Eurowater 37
vii
CHAPTER I
INTRODUCTION
In line with the articles reported, it was determined that building a new
power plant in the Luzon grid will be both beneficial and profitable. This study
proposes a 600 MW coal-fired power plant.
1
The subject of the Report
Capitalization
Ownership
2
Organizational Set-up with Technical Organization
This figure shows the flow of power from the skilled worker up to the
professional worker. It shows how every worker relates to each other, who
has a higher position.
Location Map
Table 1
Comparison of Parameters of the Three Locations
Surrounding
Present Present Present
bodies of water
Vast open area Present Present Present
Nearness to the
Near Near Near
grid
ambient air
27.75oC 27oC 29oC
temperature
Forestation and
Disturbances Forestation Many Resorts
Excavation
Elevated by
Topography Flat Flat
100m
Factors that are Seaside and Seaside and the
Seaside and sea
being protected the sea sea
Cost of Land Area PHP1800.00 PHP1500.00 PHP1650.00
Access to
Easy Easy Easy
transportation
The construction of the power plant will not only benefit the corporation
but will also provide career opportunities for the community. The power plant
will help in the economic development and industrialization of Brgy. Balanga,
Lemery.
5
Figure 2 shows the location of the proposed plant site. The proposed
coal-fired power plant is to be constructed in Brgy. Balanga, Lemery,
Batangas with a land area of 0.325 square kilometers.
Figure 3 shows that the proposed power plant will provide energy
primarily for the province of Batangas with the help of the distribution units of
BATELEC I BATELEC II, First Bay Power Corporation (FBPC) and Ibaan
Electric Engineering Corporation (IEEC). BATELEC distributes electricity in
the municipalities of Nasugbu, Lian, Calatagan, Tuy, Balayan, Calaca,
Lemery, Agoncillo, San Nicolas, Sta. Teresita, and San Luis. BATELEC II
distributes electricity to the municipalities of Laurel, Talisay, Tanauan, Malvar,
Balete, Lipa, Cuenca, San Jose, Alitagtag, Mabini, Tingloy, Padre Garcia,
Rosario, Taysan, Lobo, and San Juan. Additional power produced can be
exported to other provinces connected to the Luzon grid such as MERALCO
which supplies the greater Manila area. Reports have shown that the country
is faced with problems regarding energy demand especially the Luzon grid.
6
Load Projection
The following data necessary for the load projection were gathered from the
Department of Energy (DOE) distribution utility profile particularly the
distribution utilities operating in Batangas Province: BATELEC I, BATELEC II,
FBPC, and IEEC. The Manila Electric Company (MERALCO) was also added
to the load projection. The data were gathered to determine the forecast of the
electrical consumption of the target locations.
Table 2
Projected load in MW from 2019-2044
Year BATELEC I BATELEC II FBPC IEEC MERALCO TOTAL
2019 69.93958701 165.59 9.44 4.75 7372.97 7622.7
2020 72.7511584 172.41 9.37 4.90 7608.91 7868.3
2021 75.67575497 179.52 9.30 5.06 7852.39 8121.9
2022 78.71792032 186.91 9.23 5.22 8103.67 8383.7
2023 81.88238072 194.61 9.16 5.39 8362.98 8654
2024 85.17405242 202.63 9.09 5.56 8630.60 8933.1
2025 88.59804933 210.98 9.02 5.74 8906.78 9221.1
2026 92.15969092 219.67 8.95 5.92 9191.80 9518.5
2027 95.86451049 228.72 8.89 6.11 9485.93 9825.5
2028 99.71826381 238.14 8.82 6.31 9789.48 10142
2029 103.726938 247.96 8.75 6.51 10102.75 10470
Source: Department of Energy
The data gathered from DOE showed the projected load from 2015-
2029 for BATELEC I, BATELEC II, IEEC, and MERALCO. At 2019 the total
projected load is equal to 7622.7MW and after 10 years the projected load will
increase to 10470MW. The power demand has an average growth rate of
9.64% starting from 245.65 MW to 327 MW averaging 309.21 MW for 10
years.
Assuming no other power plants will provide the additional demand, the
proposed 600 MW power plant will reach its capacity within the next 2 years
of operation upon the finishing of construction within the next 10 years.
7
CHAPTER II
REPORT PROPER
This chapter is composed of the report proper and design calculations
considered in the proposed 600 MW Coal-Fired Power Plant.
Theoretical Consideration
A steam power plant is used to generate electricity by the use of steam
turbine. The major components of this power plant are boiler, steam turbine,
condenser and water feed pump.
Coal is shipped to the port area where it will be conveyed in the coal
yard for storage prior to being transported to the main power generating units.
The first process of this power plant is where the pulverized coal is fed into
the boiler and it is burnt in the furnace. The flue gasses and ash formed
during combustion will be treated accordingly. The water present in the boiler
drum changes to high pressure steam. From the boiler the high-pressure
steam passed to the super heater where it is again heated up to its dryness.
This super-heated steam strikes the turbine blades with a high speed and the
turbine starts rotating at high speed. A generator is attached to the rotor of the
turbine and as the turbine rotates it also rotates with the speed of the turbine.
The generator converts the mechanical energy of the turbine into electrical
energy. The electrical energy will be amplified by a transformer and will then
be transferred to the switch yard. After striking on the turbine the steam
leaves the turbine and enters into the condenser. The steam gets condensed
with the help of cold water from the cooling tower. The condensed water with
the feed water enters into the economizer. In the economizer the feed water
gets heated up before entering into the boiler. This heating of water increases
the efficiency of the boiler. The exhaust gases from the furnace pass through
the super heater, economizer and air pre-heater. The heat of this exhaust
gases is utilized in the heating of steam in the super heater, feed water in the
economizer and air in the air pre-heater. After burning of the coal into the
furnace, it is transported to ash handling plant and finally to the ash storage.
The electricity produced by the generator are then stored at transformers
before distributing it to the consumers.
8
Scope of the Design of a 600 MW Coal Fired Power Plant
1. Present and evaluate the design and development of the projected 600
MW coal fired power plant taking into account of the following
considerations:
9
Design Calculation
1. Design Options
Design Option 1
10
Design Option 2
11
Design Option 3
12
2. Design Data
The design data includes the ambient conditions in the proposed
location in Brgy. Balanga, Lemery, Batangas and the steam cycle operating
conditions used in the calculation of technical parameters of the design
options.
Table 3
Ambient Condition in Brgy, Balanga, Lemery, Batangas
Ambient Condition
Humidity % 61
Temperature
o
Design Temperature C 27
o
Max. Temperature C 34
o
Min. Temperature C 22
The data from table 3 shows the ambient weather conditions for Brgy.
Balanga, Lemery, Batangas. The atmospheric pressure is 101.4 mbar. The air
has a relative humidity of 61%. The chosen design temperature is 27 oC as
the historic maximum and minimum temperatures are 34 oC and 22 oC
respectively.
13
Table 4
Steam Cycle Operating Conditions
Parameter Design 1 Design 2 Design 3 Value
High Pressure Turbine
Pressure 20 20 20 Mpa
1st Extraction
- 10 10 Mpa
Pressure
Temperature 0
540 540 540 C
(inlet)
Intermediate Pressure Turbine
Pressure / Reheat
7.5 7.5 7.5 MPa
Pressure
Reheat Temp. 0
540 540 540 C
(inlet)
2nd Extraction
7.5 7.5 7.5 MPa
Pressure
3rd Extraction
5 5 3.5 MPa
Pressure
4th Extraction
2 2 1.5 MPa
Pressure
5th Extraction
0.5 0.5 0.5 MPa
Pressure
6th Extraction
0.1 0.1 0.2 MPa
Pressure
7th Extraction
- - 0.05 MPa
Pressure
Condenser
Pressure 0.005 0.005 0.005 Mpa
The table above shows the operating conditions of the three different
design options. The pressure in the heat generating unit is 540 oC, the
maximum pressure in the superheater is 20Mpa, and the condenser pressure
is 0.005 Mpa.
14
3. Summary of Calculations
A. Design Options
Table 5
Operating Conditions for Design Option 1
0
Reheat Temperature (inlet) 540 C
Condenser
Pressure 0.005 0.005
15
Table 6
Mass and Heat Balance for each State Point of Design Option 1
State Pressure
Temp. (oC) Enthalpy (kJ/kg) Masssteam (kg/s)
Point (Mpa)
1 20 540 3366.370 419.910
2 7.5 375.498 3080.280 36.005
3 7.5 540 3502.650 384.223
4 5 469.812 3363.980 348.218
5 2 330.068 3092.920 307.504
6 0.5 163.635 2775.750 278.926
7 0.1 99.6059 2498.250 237.867
8 0.005 32.8743 2119.920 237.867
9 0.005 32.8743 137.749 384.223
10 0.1 32.8768 137.845 307.504
11 0.1 99.6059 417.504 76.719
12 0.5 99.6335 417.921 307.504
13 0.5 151.831 640.085 28.578
14 2 151.999 641.724 307.504
15 2 212.377 908.498 40.715
16 5 212.935 912.028 307.504
17 5 263.941 1154.640 419.910
18 7.5 284.692 1157.856 419.910
19 7.5 290.535 1292.930 36.005
20 20 295.439 1310.326 419.910
Table 6 shows the obtained temperature, enthalpy, and steam flow for
the operating conditions in design option 2. Values were obtained from
SteamTab Companion software from ChemicaLogic Corporation. The actual
enthalpies were obtained using a turbine efficiency of 53% and a pump
efficiency of 85%.
16
Table 7
m ( )= 35.68721014 kg/s
m 36.00473013 kg/s
m 40.71466011 kg/s
m 28.5777881 kg/s
m 41.05895598 kg/s
m ∑ 6.6 kg/s
Table 7 shows the mass balance calculations for design option 1. The
work produced by the turbine is 300MW and the total mass of steam required
to produce the output is 356.6383313 kg/s
Table 8
W 50.02568176 MW
W 72.45438297 MW
W 6 71.91183431 MW
W6 76.51916214 MW
W 53.28022109 MW
W MW
17
Table 8 shows the calculations used to obtain the work of the turbine in
design option 1 from individual state points and also the total output which is
300 MW.
Table 9
WP 1.317484306 MW
WP 1.344211154 MW
Table 9 enlists the calculations used for the work of the condensate
pump and the open feedwater pump. The total pump work is 1.344211154
MW.
Table 10
Operating Conditions for Design Option 2
0
Reheat Temperature (inlet) 540 C
18
Fourth Extraction Pressure 2 MPa
Condenser
Pressure 005 MPa
Table 11
Mass and Heat Balance for each State Point of Design Option 2
19
18 5 263.941 1154.640 402.439
19 7.5 271.543 1192.475 402.439
20 7.5 290.535 1292.930 27.607
21 10 310.997 1299.771 402.439
22 10 310.997 1408.060 32.897
23 20 316.545 1425.491 402.439
Table 11 shows the obtained temperature, enthalpy, and steam flow for
the operating conditions in design option 2. Values were obtained from
SteamTab Companion software from ChemicaLogic Corporation. The actual
enthalpies were obtained using a turbine efficiency of 53% and a pump
efficiency of 85%.
Table 12
Summary of Calculation of Mass Balance of Design Option 2
Symbol Equation Value Unit
m ( )= 27.38094375 kg/s
m 26.34971427 kg/s
m 31.43026046 kg/s
m 34.9187646 kg/s
m 27.60703378 kg/s
( )=
m6 32.89675604 kg/s
m ∑ 419.9103376 kg/s
20
Table 12 shows the mass balance calculations for design option 2. The
work produced by the turbine is 300MW and the total mass of steam required
to produce the output 419.9103376 kg/s
Table 13
44.47152311 MW
34.90292266 MW
25.62835541 MW
55.96860863 MW
70.21184978 MW
66.6873736 MW
73.45226665 MW
Table 13 shows the calculations used to obtain the work of the turbine
in design option 2 from individual state points and also the total output which
is 300 MW.
Table 14
MW
MW
MW
21
Table 14 enlists the calculations used for the work of the condensate
pump and the open feedwater pump. The total pump work is 1.344211154
MW.
Table 15
Operating Conditions for Design Option 2
0
Reheat Temperature (inlet) 540 C
Condenser
Pressure 0.005 Mpa
22
Table 16
Mass and Heat Balance for each State Point of Design Option 3
23
Table 16 shows the obtained temperature, enthalpy, and steam flow for
the operating conditions in design option 3. Values were obtained from
SteamTab Companion software from ChemicaLogic Corporation. The actual
enthalpies were obtained using a turbine efficiency of 53% and a pump
efficiency of 85%.
Table 17
Summary of Calculation of Mass Balance of Design Option 3
Symbol Equation Value Unit
m ( )= 27.65681659 kg/s
m 33.52580983 kg/s
m 20.61445805 kg/s
m 10.27033512 kg/s
m 59.29194521 kg/s
( )=
m6 28.04492697 kg/s
m 36.40490734 kg/s
m ∑ 402.4390128 kg/s
Table 17 shows the mass balance calculations for design option 2. The
work produced by the turbine is 300MW and the total mass of steam required
to produce the output is 402.4390128 kg/s
24
Table 18
W 44.91958968 MW
W 35.25458214 MW
W 40.64394569 MW
W 52.1340169 MW
6
W6 66.5492868 MW
W 43.17374351 MW
W 55.7787587 MW
W 47.01927295 MW
0
W 300 MW
The table above shows the calculations used to obtain the work of the
turbine in design option 3 from individual state points and also the total output
which is 300 MW.
Table 19
WP 13.1933806 MW
WP 13.20499259 MW
25
Table 19 enlists the calculations used for the work of the condensate
pump and the open feedwater pump. The total pump work is 13.20499259
MW.
Table 20
Summary of Design Calculations
Work of
300 MW 300 MW 300 MW
Turbine
Work of
1.344211154 MW 13.20499259 MW 1.543884 MW
Pump
Thermal
0.306636046 0.318805366 0.315962689
Efficiency
The table above shows the computed values needed to determine the
thermal efficiency. The calculations show that design option 2 has the most
desirable thermal efficiency of 31.8805572%.
Table 21
Summary of Calculations for Heat Losses in the Boiler
( )
Dry flue gas loss %
( )
Moisture loss %
( )
Humidity loss %
26
Unburnt loss %
Radiation 1 %
loss
Unaccountable 10 %
loss
Total Boiler ∑ %
Loss
Gross efficiency ∑ %
of boiler
Fuel Computations
Hydrogen = 4.318%
Carbon = 56.556%
Nitrogen = 1.038%
Sulfur = 0.752%
Oxygen = 16.336%
Ash = 21%
27
Table 22
Summary of Fuel Properties
The higher heating value was obtained using Dulongs Formula with the
given fuel contents. The boiler efficiency was computed to determine the
actual heating value for operations. The theoretical air-fuel ratio was
determined. The excess air fuel ratio and the humidity of the air was
considered in determining the actual air fuel ratio.
Table 23
Summary of Calculations for the Fuel Flow Rate
The calculations for the fuel flow rate shows that design option 2 has
the least fuel requirement reducing the fuel costs for operation.
The coal consumption for 1 day is 8136.34 tons and requires coal
transport of 66, 3000 ton capacity barges per month.
In case of unexpected hindrances with the transport of coal, the plant
has a coal storage capacity good for 1 month with a total area of
2x260mx125m.
28
D. Chimney Calculations
Table 24
Summary of Calculations for the Chimney
9.98519387 kgair/kgfuel
470.1559387 kg/s
0.8643457kg/m3
8.98519387 kgair/kgfuel
; 9.6095m2≈ 0m2
( ) 706.9033026Pa
For the chimney computations, the flue gasses were assumed to all
exit the chimney. The exit temperature was assumed 150 oC. Ambient air
conditions were used for the outside air density. The maximum allowable flue
gas velocity is 7.5m/s. The chimney diameter to be built is 10m. For a
chimney height of 220m, the pressure drop was 706.9033026Pa.
The change in enthalpy occurs on statepoint 9 and statepoint 10, while the
initial temperature of the water from Balayan Bay is 30 oC.
29
F. Environmental Parameters
The selection of the best design option are also compared based on
the environmental effects of the gases resulted in the combustion of primary
fuel which is the lignite coal. The environmental parameters being compared
are the carbon oxides emission (COx), nitrogen oxides emission (NOx), sulfur
oxides emission (SOx), and ash disposal. The summary of heat losses in the
boiler are also tabulated as follows.
Table 25
Equation
Symbol Design Option 1 Design Option 2 Design Option 3
Table 25 shows that design option 2 has the least emission due to it
also consuming the least amount of fuel. Design option 2 has a Carbon
emission of 92.3316171 kg/s, nitrogen oxide emission of 1.392379999 kg/s
Sulfur Oxide emission of 0.6780285215 kg/s, and ang ash flow of
11.64478109 kg/s.
Equipment Selection
30
on the turbine SST-5000. SST-4000 and STF-D650 are also viable options for
the power plant and comparisons were made for the three turbines.
Table 26
Summary of Calculations for SST 5000, SST 4000, and STF D650 based
on Design Option 2
Frequency 50 or 60 Hz 50 or 60 Hz 50 or 60 Hz
Technical Parameters
Environmental Parameter
31
able 6 presents the summary of calculations for the steam turbines’
performance with design option 2. It can be seen that SST 500 is the best
choice in terms of efficiency, fuel consumption, and environmental impact.
Table 27
Equipment Selection
Php
SIEMENS Php
9.8599 43% 1 25
SST 4000 197,507,050,260.00 17,214,143,300.00
GE Php Php
9.8599 47.5% 1 25
STF D650 200,126,507,160.00 18,093,264,348.00
Summary of Equipment
The summary of equipment shows how the specification of each
component are chosen based on the selection parameter required in the
calculation of the design options.
32
Table 28
Summary of Equipment
Tag. No. Component Selection Parameter Specification Page No.
Fuel: Sub-Bituminous
Typical Fuels: Bituminous, sub-
Capacity: 962.25 MW bituminous. Lignite A, Oil and gas
Pressure: 200 bar Capacity: up to 1350 MWe
Reheat Temperature: Pressure: up to 330 bar Appendix B,
BT-10X Boiler 540 °C page 124
Temperature: 650/670°C
Reheat Pressure: 65
bar Reheat Pressure: 330 bar
Reheat Temperature: Reheat Temperature: 650/670°C
540 °C
DRT- Mass flow rate: 3240 Total Tank Volume: 11,575 liters Appendix B,
Deaerator
10X kg/h Steam Requirements: 3240 kg/h page 124
Flows: 5220m3/h
Flows: 1450m3/h
Head: 100 m
BFP- Pressure: 50 bar Appendix B,
Boiler Feed Pump Pressure: up to 517 bar
10X Temperature: 263°C page 125
Temperature range: up to 318°C
Efficiency:85%
Efficiency: up to 85%
Flows: 13600m3/h
Flows: 1144m3/h
Head: 1070 m
Condensate Pressure: 0.05 bar Appendix B,
CP-10X Pressure: up to 100 bar
Extraction Pump Temperature: 32°C page 125
Temperature range: up to 230°C
Efficiency:85%
Efficiency:85%
33
Flows: 543m3/h Flows: 9085m3/h
FGP- Appendix B,
Flue Gas Pump Temperature: 150°C Head: 100 m
10X page 126
Temperature range: up to 150°C
Flows: 181700m3/h
Flows: 180000m3/h
CWP- Circulating Water Head: 110 m Appendix B,
Pressure: up to 517 bar
10X Pump Pressure: up to 5bar page 126
Temperature: 30°C
Temperature range: up to 318°C
Frequency: 60 Hz
Power factor: 0.85
Apparent Power: 510 MVA to
Power: 300 MVA Appendix B,
G-10X Generator 1400 MVA
Efficiency: 100% page 126
Efficiency: Up to 99%
Terminal Voltage: 19-25 kV
Output Voltage: 26kV
1. Steam Turbine
The steam turbine serves as the heart of the power plant as it is
responsible in converting the kinetic energy of steam into mechanical
energy from the blades in order to generate electric energy in the
generator. The steam turbine to be used is SST-5000 manufactured by
Siemens Company with an operating capacity of 200MW-500MW, inlet
pressure of up to 260 bar, main and reheat temperature of 600 oC,
frequency of 60 Hz, and efficiency of 53%.
34
Figure 10. SST 5000, SIEMENS
2. Boiler
Two-Pass Boiler by GE CFB Technology will be installed for the
proposed coal fired power plant design. The sub-bituminous coal from
Semirara is a suitable type of fuel for this boiler. The boiler has a
capacity of 1350 MW, a pressure of 330 bar and a temperature ranges
from 650-670oC.
3. Condenser
The condenser equipment to be used is 2017 Steam Power
Systems Product Catalog (GE Single Vacuum Type Condenser) having
an operating pressure of 0.05 bar, circulating seawater temperature of
30oC rising to 33 oC, circulating water flow of 50m3/s, and a tube length
of 16.5 meters.
35
Figure 12. Condenser, GE
4. Generator
A water-cooled generator is used for the coal fired power plant.
A water cooled generator is well suited for large power station
applications where output requirements exceed the cooling capabilities
of air-cooled or conventional hydrogen-cooled options. The apparent
power of the generator is up to 1120 MVA and has a terminal voltage
of up to 26 kV.
36
Figure 14. SPX Heater, Energyen
6. Deaerator
A single deaerator is installed per unit. he deaerator’s purpose
is to remove dissolved gases from the feed water to prevent corrosion.
Steam from the intermediate pressure turbine and feedwater from the
feedwater heater will openly mix increasing the feedwater temperature.
A thermal deaerator from Eurowater is installed in the plant
7. Pump
The pump that will be installed in the coal fired power plant is
from Flowserve. The boiler feed pump can deliver a maximum flowrate
of 1.45m3/s with a head up to 4270m and a temperature limit of 315C.
The circulating water pump has an operational flow rate of 50m 3/s with
a head of 110m. The selected design is a vertical wel-pit pump suitable
for extended operation in condenser cooling water service. The
condensate extraction pump has a maximum flow rate of 3.778m 3/s
37
with a head of up to 1070m designed for continuous plant operations.
The flue gas desulfurization pump flows up to 2.5m3/s with a 100m
head and temperature limit of 150C.
8. Pulveriser
The pulveriser is responsible for coal preparation for increased
combustion efficiency. A pulverized reject hopper is installed together
with the pulverizer. The hopper returns the coal not small enough for
the combustion process. Suitably pulverized coal will be transported to
the feeder for combustion.
9. Chimney
The product of combustion of the boiler is exhausted in the
chimney as a flue gas. A flue-gas type of chimney is to be used for it is
fitted on the design consideration of the power plant. It can be
observed that in a flue-gas type of chimney, condensate is being
spitted. The chimney has a height of 220m and a diameter of 10m.
Process/Schematic/System Diagram
Other systems in the power plant includes flue gas treatment system
for the removal of dust and components of combustion; ash handling system
38
for the proper disposal of bottom ash product from the combustion process;
and water treatment system for the reverse osmosis and demineralization of
water to remove elements and minerals from seawater which causes damage
in the components of power plant and in the piping system.
39
The ash from the combustion of coal is properly handled through ash
handling system. This system cools down the raw ash to a manageable
temperature before transferring it to the slurry tank. The coarse ash from the
boiler is conveyed and treated to reduce its size for better handling. The
collected ash in the bottom is transported in a to store it temporarily.
40
are things that cannot be avoided but can be minimized by means of studies
and compliance with norms.
A. Air
One of the major impacts of constructing a steam energy plant is
the effect on air quality. During operation, the heat in the boiler will release
several pollutants such as sulfur dioxide, nitrogen oxide, and other gasses
into the environment. Other pollutants include intermittent fugitive dust
emissions during the construction period; car exhausts used for
transportation of employees, transportation of construction materials and
basic equipment, and transportation during power plant operation.
41
C. Water
For the cooling system, a steam power plant must operate close to
a large body of water, hence there is a risk of water contamination
affecting the surrounding animal life and the potential for human use.
G. Plant Noise
Socio-economicc Benefits
42
The power plant project enables a part of the production to be retained
without the need to purchase carbon dioxide emission allowances related to
the combustion of fuels.
The required steps will be integrated into the power plant design to
avoid or minimize future environmental operational impacts. The following
mitigation measures will be implemented to mitigate the potential adverse
effects connected with the operation of the proposed power plant:
A. Waste Water
Water supply is one of the demands for the steam power plant's
building and operation. This will be given in the project region from the
creek and/or comparable water sources. As a result, the water used during
building became polluted, contaminating water bodies that can influence
both aquatic and human life.
43
Anti-degradation and Clean-up Policy
Important Considerations
44
5) No effluent shall be discharged into Class AA and SA waters from any
point sources.
Air Quality
Contractors on-site and should monitor the air mitigation steps and include
at least the following:
The removal of dust from the site will be used to avoid dust from
becoming a nuisance during the building stage.
Roads will be compacted and engraved during building if needed
and maintained in good condition;
Access roads from the site entrance will be compacted and water-
sprayed to minimize the dust produced by cars and trucks;
The building stage will start with the building of access roads to
minimize the dust from car movements
Stack and ambient air quality surveillance equipment and testing
equipment shall be supplied to properly determine the nature and
amount of air pollutants emitted as a consequence of the operation
of the power plant.
45
(b) Include enforceable emission constraints and other control
measures, means or methods, as well as compliance schedules and
time tables as may be essential or suitable to comply with the relevant
conditions of this Act;
C. Noise
The following steps will mitigate the noise produced during the
building. In the plant operation stage, the indoor regions will be put with
the cooling scheme and turbines. The steam turbine will be the main noise
source, but it will be provided with its own individual noise enclosure and
noise will have no important tonal or impulsive personality. The enclosure
is going to be housed within a building.
46
CHAPTER III
Table 29
Monthly System Peak Demand as of 2018 (in MW)
Month (MW)
January 9,213
February 9,579
March 9,936
April 10,539
May 10,570
June 10,876
July 9,996
August 9,843
47
September 10,035
October 10,346
November 10,088
December 9,987
Table 30
Power Generation by Grid as of 2018 (in GWh)
Luzon 72, 728
48
Table 31
Power Consumption by Sector as of 2018 (in GWh)
Residential 28, 261
Others 2, 753
Total 99,765
Table 32
Power Generation by Source in GWh, Total Philippines (2018)
Coal 51, 932
Oil-Based 3,173
Diesel 2,505
Gas Turbine 0
49
Geothermal 10, 435
Hydro 9, 384
Biomass 1, 105
Solar 1, 249
Wind 1, 153
Table 33
Installed Generating Capacity in MW (2018)
Coal 8, 844
Oil-Based 4, 292
Geothermal 1, 944
Hydro 3, 701
Biomass 258
Solar 896
Wind 427
50
Table 33 above shows the installed generating capacity in MW as of
2018 by the different sources of power in the Philippines. Natural gas has an
installed generating capacity of 3, 453 MW, coal has 8, 844 MW, renewable
energy has 7, 227 MW. Total installed generating capacity as of 2018
amounts to 23, 815 MW.
Table 34
Dependable Generating Capacity in MW (2018)
Coal 8, 368
Oil-Based 2, 995
Geothermal 1, 770
Hydro 3, 473
Biomass 182
Solar 740
Wind 427
51
Table 35
Peak Demand at Batangas
Name of Cooperative Peak Demand (MW)
BATELEC I 67.34
BATELEC II 156.43
FBPC 9.03
IEEC 4.74
Total 234.54
Table 36
Power Consumption by Sector as of 2018 in Batangas (in MWh)
Residential 492,316
Commercial 273,870
Industrial 242,285
Others 93,117
Total 1,101,588
52
The energy consumed in residential sectors were 492,316 MWh, in
commercial sectors were 273,870 MWh, while in industrial sectors were
242,285 MWh and others were 93,117 MWh. The total electricity sales sums
up to 1,101,588 MWh.
Economic Cost
Table 37
Power Demand Analysis (SIEMENS SST 5000)
53
Table 38
Depreciation (SIEMENS SST 5000)
Service
Life Depreciation
Book Value(Php) Salvage Value (yrs) (BV-SV)/SL
Purchased 4,961,062,839.0
Equipment 193,911,717,260.00 69,885,146,260.00 25 0
Instrumentatio
n and Control 38,782,343,452.00 13,977,029,252.00 25 992,212,567.00
Service
Facilities 19,391,171,726.00 6,988,514,626.00 25 496,106,283.00
Etc 29,086,757,589.00 10,482,771,939.00 25 744,159,425.00
7,193,541,117.0
Total 0
Table 39
Return of Investment (SIEMENS SST 5000)
Net Income After
Period TCI ROI
Year Tax
(Php) (Php) (%)
2019 2 316,888,599,133.8 45,118,262,840.00 14.2378939
2020 3 271,770,336,293.8 45,118,262,840.00 16.6016142
2021 4 226,652,073,453.8 45,118,262,840.00 19.9063975
2022 5 181,533,810,613.8 45,118,262,840.00 24.8539171
2023 6 136,415,547,773.8 45,118,262,840.00 33.0741352
2024 7 91,297,284,933.8 45,118,262,840.00 49.4190630
2025 8 46,179,022,093.8 45,118,262,840.00 97.7029412
Average 36.5422803
54
Table 40
Payback Period (Siemens SST 5000)
Table 41
Sensitivity Analysis (SIEMENS SST 5000)
Change ENPV EIRR
Table 41 shows the sensitivity analysis using the SIEMENS SST 500
catalogue when the power generation is reduced by 10%, the fuel price is
increase by 10%, and when the fuel price drop by 10%.
55
CASE 1. Reduce of Power Generation by 10%
Chart Title
1,400,000,000,000.00
1,200,000,000,000.00
1,000,000,000,000.00
800,000,000,000.00
600,000,000,000.00
400,000,000,000.00
200,000,000,000.00
0.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Series1 Series2
This graph shows the behavior of the cash inflow and cash outflow for
design option 2 using SST 5000. The intersection point is the breakeven point
in which the power plant recovers its initial capital. The breakeven point of the
plant is on the 11.5th year.
56
Chart Title
1,600,000,000,000.00
1,400,000,000,000.00
1,200,000,000,000.00
1,000,000,000,000.00
800,000,000,000.00
600,000,000,000.00
400,000,000,000.00
200,000,000,000.00
0.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Series1 Series2
The third case is a sudden drop of fuel price by 10% in the span of 25
years is given by the graph to find the breakeven point for design option 2
using SST 5000:
Chart Title
1,600,000,000,000.00
1,400,000,000,000.00
1,200,000,000,000.00
1,000,000,000,000.00
800,000,000,000.00
600,000,000,000.00
400,000,000,000.00
200,000,000,000.00
0.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Series1 Series2
57
This graph shows the behavior of the cash inflow and cash outflow for
design option 2 using SST 5000. The breakeven point is the intersection point
in which the power plant recovers its initial capital. The breakeven point of the
plant is on the 10th year.
Table 42
Power Demand Analysis (SIEMENS SST 4000)
Table 43
Depreciation (Siemens SST 4000)
Service
Life Depreciation
Book Value(Php) Salvage Value (yrs) (BV-SV)/SL
Purchased
Equipment 197,507,050,260.00 69,885,146,260.80 25 5,053,046,311.59
Instrumentation
and Control 39,501,410,052.00 13,977,029,252.16 25 1,010,609,262.31
Service
Facilities 19,750,705,026.00 6,988,514,626.08 25 505,304,631.15
Etc 29,626,057,539.00 10,482,771,939.12 25 757,956,946.73
Total 7,326,917,151.81
58
Table 43 above presents the depreciation values of the purchased
equipment, instrumentation and control, service facilities and auxiliary
systems with a service life of 25 years.
Table 44
Return of Investment (Siemens SST 4000)
Net Income After
Period TCI ROI
Year Tax
(Php) (Php) (%)
2019 2 322,748,991,923.8 45,118,262,840.00 13.97936
2020 3 277,630,729,083.8 45,118,262,840.00 16.25117
2021 4 232,512,466,243.8 45,118,262,840.00 19.40466
2022 5 187,394,203,403.8 45,118,262,840.00 24.07665
2023 6 142,275,940,563.8 45,118,262,840.00 31.71180
2024 7 97,157,677,723.8 45,118,262,840.00 46.43818
2025 8 52,039,414,883.8 45,118,262,840.00 86.70017
Average 34.08028
Table 45
Payback Period (Siemens SST 4000)
Net Income TCI Depreciation
after Tax (Php) (Php) (Php)
2019 4,511,826,840.00 322,748,991,923.8 7,326,917,151.81
2020 4,511,826,840.00 277,630,729,083.8 7,326,917,151.81
2021 4,511,826,840.00 232,512,466,243.8 7,326,917,151.81
2022 4,511,826,840.00 1873,94,203,403.8 7,326,917,151.81
2023 4,511,826,840.00 142,275,940,563.8 7,326,917,151.81
2024 4,511,826,840.00 97,157,677,723.8 7,326,917,151.81
2025 4,511,826,840.00 52,039414,,883.8 7,326,917,151.81
Payback Period 6 years
The table presents the depreciation through the 6-year service life of
the proposed coal fired power plant and the payback period by dividing the
59
total annual cost to the profit element. The chosen design option using the
SIEMENS SST 4000 catalogue has a total of 6 years of payback period.
Table 46
Sensitivity Analysis (Siemens SST 4000)
Change ENPV EIRR
Table 46 shows the sensitivity analysis using the Siemens SST 4000
catalogue when the power generation is reduced by 10%, the fuel price is
increase by 10%, and when the fuel price drop by 10%.
Chart Title
1200000000000.00
1000000000000.00
800000000000.00
600000000000.00
400000000000.00
200000000000.00
0.00
1 2 3 4 5 6 7 8 9 10111213141516171819202122232425
Series1 Series2
60
This graph shows the behavior of the cash inflow and cash outflow for
design option 2 using SST 4000. The intersection point is the breakeven point
in which the power plant recovers its initial capital. The breakeven point of the
plant is on the 12th year.
Chart Title
1,400,000,000,000.00
1,200,000,000,000.00
1,000,000,000,000.00
800,000,000,000.00
600,000,000,000.00
400,000,000,000.00
200,000,000,000.00
0.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Series1 Series2
The third case is a sudden drop of fuel price by 10% in the span of 25
years is given by the graph to find the breakeven point for design option 2
using SST 4000:
61
Chart Title
1,400,000,000,000.00
1,200,000,000,000.00
1,000,000,000,000.00
800,000,000,000.00
600,000,000,000.00
400,000,000,000.00
200,000,000,000.00
0.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Series1 Series2
This graph shows the behavior of the cash inflow and cash outflow for
design option 2 using SST 5000. The breakeven point is the intersection point
in which the power plant recovers its initial capital. The breakeven point of the
plant is on the 11th year.
Table 47
Power Demand Analysis (GE STF D650)
62
capacity that has a value of 600 MW, capacity factor of 40%, and the
assumed and computed energy per year, cost per kilowatt, capital cost, life
years, discount rate, capital recovery factor, annual capacity cost, fixed
operation and maintenance cost, total fixed cost, fixed cost per kilowatt,
variable cost per kilowatt and LCOE based on the catalogue selected. The
proposed coal fired power plant design option will be having a 365-day
operation.
Table 48
Depreciation (GE STF D650)
Service
Book Life Depreciation
Value(Php) Salvage Value (yrs) (BV-SV)/SL
Purchased
Equipment 200,126,507,160.00 72,124,936,136.72 25 5,120,062,840.93
Instrumentation
and Control 40,025,301,432.00 14424987227.34 25 1,024,012,568.18
Service
Facilities 20,012,650,716.00 7,212,493,613.67 25 512,006,284.09
Etc 30,018,976,074.00 10,818,740,420.50 25 768,009,426.13
Total 7,424,091,119.34
Table 49
Return of Investment (GE STF D650)
Net Income After
Period TCI ROI
Tax
Year
(Php) (Php) (%)
63
Table 49 shows the return of investment of the proposed plant through
the first 9-year service life with an average of 32.5420166% ROI. On the 7th
year, the power plant will be able to return the investment with a rate of
80.12%.
Table 50
Payback Period (GE STF D650)
Net Income TCI Depreciation
Year
after Tax (Php) (Php) (Php)
2019 4,511,826,840.00 327018706670.8 7,326,917,151.81
2020 4,511,826,840.00 281900443830.8 7,326,917,151.81
2021 4,511,826,840.00 236782180990.8 7,326,917,151.81
2022 4,511,826,840.00 191663918150.8 7,326,917,151.81
2023 4,511,826,840.00 146545655310.8 7,326,917,151.81
2024 4,511,826,840.00 101427392470.8 7,326,917,151.81
2025 4,511,826,840.00 56309129630.8 7,326,917,151.81
Payback
Period 6 years
Table 51
Sensitivity Analysis (STF D650)
Change ENPV EIRR
64
Table 51 shows the sensitivity analysis using the GE STF D650
catalogue when the power generation is reduced by 10%, the fuel price is
increase by 10%, and when the fuel price drop by 10%
Chart Title
1,400,000,000,000.00
1,200,000,000,000.00
1,000,000,000,000.00
800,000,000,000.00
600,000,000,000.00
400,000,000,000.00
200,000,000,000.00
0.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Series1 Series2
65
Chart Title
1200000000000.00
1000000000000.00
800000000000.00
600000000000.00
400000000000.00
200000000000.00
0.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Series1 Series2
Chart Title
1,200,000,000,000.00
1,000,000,000,000.00
800,000,000,000.00
600,000,000,000.00
400,000,000,000.00
200,000,000,000.00
0.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Series1 Series2
66
This graph shows the behavior of the cash inflow and cash outflow for
design option 2 using STF D650. The breakeven point is the intersection point
in which the power plant recovers its initial capital. The breakeven point of the
plant is on the 13th year.
Table 52
Economic Analysis of the Three Catalogues (Design Option 2)
Table 52 shows the summary of the economic analysis using the three
catalogues in terms of the total cost and the payback period. It shows that
best catalogue to use in design option two is the Siemens SST 5000
catalogue.
67
CHAPTER IV
Observation
After the analysis and evaluation of all the data gathered, the following
are the observations are listed:
The proposed location of 600 MW Coal-Fired Power Plant which
is at Barangay Balanga, Lemery, Batangas was observed to be
feasible and advantageous for the construction and operation of the
proposed power plant. The transmission of the generated electricity of
the proposed power plant for the Luzon Grid will be the responsibility of
the National Grid Corporation of the Philippines (NGCP) and this
company will distribute the generated electricity to the customers of the
Batangas province electric cooperatives namely; BATELEC I,
BATELEC II, First Bay Power Corporation (FBPC) and Ibaan Electric
Engineering Corporation (IEEC) will transmit the generated electricity
to within reach provinces.
68
4. All equipment and miscellaneous facilities were satisfactorily
designed and evaluated.
5. Technical information has been at hand through the use of related
references and the use of the internet, which provides the equipment
catalogue and it is based on the manufacturer’s specifications to get
the best design possible for the proposed power plant.
69
CHAPTER V
BIBLIOGRAPHY
Department of Energy (2018) 2018 Power Statistics Retrieved June 22, 2019,
from
https://www.doe.gov.ph/sites/default/files/pdf/energy_statistics/01_201
8_
power_statistics_as_of_29_march_2019_summary.pdf?fbclid=IwAR0O
rATEnDUV_pNL9m89ceJDD4k8dRljfIpHjueFwkszSf4Ev3dYIKNInwk
Department of Energy (2018) Luzon, Visayas and Mindanao grids - Annual
System Peak Demand per Grid as of 2018 in MW Retrieved June 22,
2019, from
https://www.doe.gov.ph/sites/default/files/pdf/energy_statistics/
01_2018_power_statistics_as_of_29_march_2019_summary.pdf?fbclid
=IwAR0OrATEnDUV_pNL9m89ceJDD4k8dRljfIpHjueFwkszSf4Ev3dYI
KNInwk
Department of Energy (2018) Monthly System Peak Demand as of 2018
Retrieved June 22, 2019, from
https://www.doe.gov.ph/sites/default/files/pdf/
energy_statistics/08_2018_power_statistics_as_of_29_march_2019_m
onthly_lvm_peak_demand.pdf?fbclid=IwAR0Nr56haWzlbSsoBVd-
OVuJlQIYho4-itUjRMQIhUi4EsEoOK8VcmM7sAM
70
GE power Boiler, Retrieved Retrieved June 23, 2019,
https://www.ge.com/power/steam/boilers
https://www.engineeringtoolbox.com/ansi-steel-pipes-d_305.html
https://www.flowserve.com/en/products/pumps/vertical-pumps/wet-pit-
pumps/wet-pit-pumps-vct
71
APPENDIX A
COMPUTATIONS
72
BOILER EFFICIENCY
The losses in the boiler are made up of chimney losses(dry gas loss,
moisture loss, humidity loss), unburnt losses, radiation losses, and
unaccountable losses
1. Chimney Loss
b. Moisture Loss
( )
c. Humidity Loss
( )
73
2. Unburnt Loss
3. Radiation Loss
Radiation Loss is assumed to contribute 1% at maximum.
4. Unaccountable Loss
74
COAL ANALYSIS
( )
( )
The higher heating value with the consideration of the boiler efficiency:
( )
( )
75
Pulverized coal fired boilers run with an average of 20% excess air to
burn the fuel completely:
The actual air fuel ratio with consideration to excess air requirements
along with the humidity of the air in the location is as follows:
( )
76
Design Option 1
77
6 0.5 163.635 2775.750 278.926
7 0.1 99.6059 2498.250 237.867
8 0.005 32.8743 2119.920 237.867
9 0.005 32.8743 137.749 384.223
10 0.1 32.8768 137.845 307.504
11 0.1 99.6059 417.504 76.719
12 0.5 99.6335 417.921 307.504
13 0.5 151.831 640.085 28.578
14 2 151.999 641.724 307.504
15 2 212.377 908.498 40.715
16 5 212.935 912.028 307.504
17 5 263.941 1154.640 419.910
18 7.5 284.692 1157.856 419.910
19 7.5 290.535 1292.930 36.005
20 20 295.439 1310.326 419.910
MASS BALANCE
78
SOLVING FOR THE MASS OF THE STEAM ASSUMING A TURBINE
OUTPUT OF 300MW:
W m h h mm h h m m m (h h ) mm m m (h h6 )
m1 = 35.68721 kg/s
m2 = 36.00473 kg/s
m3 = 40.71466 kg/s
m4 = 28.57779 kg/s
m5 = 0.097780293kg/s
79
Heat added in the Boiler,
Pump Work,
80
Net Cycle Work,
Thermal efficiency,
81
FOR DESIGN OPTION 2
Actual
State Point Enthalpy (kJ/kg)
Enthalpy (kj/kg)
1 3366.37
2 3157.87 3255.865
3 3080.28 3162.80495
4 3502.65
5 3363.98 3429.1549
82
6 3092.62 3250.791403
7 2775.75 2999.019459
8 2498.25 2733.611646
9 2098.95 2397.240974
10 137.749
11 137.7942 137.8021765
12 417.92126
13 421.6766
14 640.085
15 656.47325
16 908.498
17 943.8005
18 1154.64
19 1186.79975 1192.475
20 1292.93
21 1299.77105
22 1408.06
23 1425.49108
83
Solving for using energy balance in the turbine:
84
Solving for individual work of turbines:
85
Heat added in Reheater,
Pump Work,
86
Thermal efficiency,
87
STATEPOINT CALCULATIONS
Actual
State Point Enthalpy (kJ/kg)
Enthalpy (kj/kg)
1 3366.37
2 3157.87 3255.865
3 3080.28 3162.80495
4 3502.65
5 3280.57 3384.9476
6 3082 3224.385372
7 2825.04 3012.732325
8 2693.45 2843.512693
9 2380.07 2597.888066
10 2132.64 2351.306591
11 137.749
12 137.7942 137.8021765
13 417.504
14 417.6604725
15 535.245
16 535.611805
17 915.29
18 916.38255
19 844.557
20 846.287805
21 1008.34
22 1053.015975 1060.899971
23 1292.93
24 1299.77105
25 1408.06
26 1425.49108
88
Mass balance for extracted steams in the turbines:
89
Solving for using energy balance in the turbine:
90
Heat added in the Boiler,
91
Total Heat Added,
Pump Work,
Thermal efficiency,
92
FUEL CONSUMPTION AND ENVIRONMENTAL PARAMETERS
Fuel Consumption
Environmental Parameters
93
Ash Disposal
94
Ash Disposal
95
Sulfur oxides emission,
Ash Disposal
96
Sulfur oxides emission,
Ash Disposal
97
Nitrogen oxides emission,
Ash Disposal
98
The coal storage facility has an area of 260mx125mx2=65000m 2.
Chimney
( )
99
For chimney diameter:
( )
ρo=1.171kg/m3
100
@ Statepoint 9, h=2397.241 kJ/kg; @ Statepoint 10. h=137.802kJ/kg
( ) ( )
101
ENGINEERING ECONOMIC ANALYSIS
Design Option 2
Power Demand Analysis
Return of Investment
Net Income After
Period TCI ROI
Year Tax
(Php) (Php) (%)
2019 2 316,888,599,133.8 45,118,262,840.00 14.2378939
2020 3 271,770,336,293.8 45,118,262,840.00 16.6016142
2021 4 226,652,073,453.8 45,118,262,840.00 19.9063975
2022 5 181,533,810,613.8 45,118,262,840.00 24.8539171
2023 6 136,415,547,773.8 45,118,262,840.00 33.0741352
2024 7 91,297,284,933.8 45,118,262,840.00 49.4190630
2025 8 46,179,022,093.8 45,118,262,840.00 97.7029412
102
Average 36.5422803
Payback Period
Net Income TCI Depreciation
Year
after Tax (Php) (Php) (Php)
2019 45,118,262,840.00 316,888,599,133.8 7,193,541,117.95
2020 45,118,262,840.00 271,770,336,293.8 7,193,541,117.95
2021 45,118,262,840.00 226,652,073,453.8 7,193,541,117.95
2022 45,118,262,840.00 181,533,810,613.8 7,193,541,117.95
2023 45,118,262,840.00 91,297,284,933.8 7,193,541,117.95
2024 45,118,262,840.00 46,179,022,093.8 7,193,541,117.95
Payback
Period 5 years
Sensitivity Analysis
Change ENPV EIRR
Economical Parameters
A. Land Cost
Land Cost = Total Land Area x current land cost
Land Cost = 325,000 m2 (Php2500/m2)
Land Cost = PHP 812,500,000.00
B. Equipment Cost
C. Electrical Cost
Electrical Cost = Equipment Cost x 25%
103
For Design Option 1
Electrical Cost = PHP 193,911,717,260.00 x 0.25
Electrical Cost = PHP 38,782,343,452.00
D. Building Cost
For Design Option 1
Building Cost = Equipment Cost x 33%
Building Cost = PHP 193,911,717,260.00 x 0.33
Building Cost = PHP 63,990,866,695.8
E. Miscellaneous Cost
Miscellaneous Cost = Equipment Cost x 10%
Miscellaneous Cost = PHP 193,911,717,260.00 x 0.1
Miscellaneous Cost = PHP 19,391,171,726.00
Heat Rate =
Heat Rate =
104
Fuel Cost = 7,200,000 kW-hr x
(2 units)
Fuel Cost = PHP 22,417,798.77
B. Labor Cost
Labor Cost = Fuel Cost x 20%
Labor Cost = PHP 22,417,798.77 x 20%
Labor Cost = PHP 4,483,559.754
D. Supplies Cost
Supply Cost = Fuel Cost x 10%
Supply Cost = PHP 22,417,798.77 x 10%
Supply Cost = PHP 2,241,779.87
E. Supervision Cost
Supervision Cost = Fuel Cost x 20%
Supervision Cost = PHP 22,417,798.77 x 20%
Supervision Cost = PHP 4,483,559.754
F. Operating Taxes
Operating Taxes = Fuel Cost x 10%
Operating Taxes = PHP 22,417,798.77 x 10%
Operating Taxes = PHP 2,241,779.87
H. Depreciation
105
year
Depreciation ate x 00
n
year
Depreciation ate x 00
years
Depreciation Rate = 4%
I. Revenue
Annual revenue = Power Generation Rate x Actual Plant Output
Annual Revenue = PHP 9.7599/kW-hr x (600,000 kW x 0.915)
(8760hrs/yr)
Annual Revenue = PHP 46,937,701,480.00
106
roi (Rate of Investment) = 4%
n (maximum useful life) = 25
-
- .
Future Revenue = PHP 46,937,701,480.00 x 0.
K. Payback Period
Payback Period =
107
ROI =
0, ,0 . 6
Design Option 2
Power Demand Analysis
Depreciation
Service
Life Depreciation
Book Value(Php) Salvage Value (yrs) (BV-SV)/SL
Purchased
Equipment 197,507,050,260.00 69,885,146,260.80 25 5,053,046,311.59
Instrumentation
and Control 39,501,410,052.00 13,977,029,252.16 25 1,010,609,262.31
Service
Facilities 19,750,705,026.00 6,988,514,626.08 25 505,304,631.15
Etc 29,626,057,539.00 10,482,771,939.12 25 757,956,946.73
Total 7,326,917,151.81
Return of Investment
Net Income After
Period TCI ROI
Year Tax
(Php) (Php) (%)
108
2019 2 322,748,991,923.8 45,118,262,840.00 13.97936
2020 3 277,630,729,083.8 45,118,262,840.00 16.25117
Payback Period
Net Income TCI Depreciation
after Tax (Php) (Php) (Php)
2019 4,511,826,840.00 322,748,991,923.8 7,326,917,151.81
2020 4,511,826,840.00 277,630,729,083.8 7,326,917,151.81
2021 4,511,826,840.00 232,512,466,243.8 7,326,917,151.81
2022 4,511,826,840.00 1873,94,203,403.8 7,326,917,151.81
2023 4,511,826,840.00 142,275,940,563.8 7,326,917,151.81
2024 4,511,826,840.00 97,157,677,723.8 7,326,917,151.81
2025 4,511,826,840.00 52,039414,,883.8 7,326,917,151.81
Payback
Period 6 years
Sensitivity Analysis
Economical Parameters
A. Land Cost
Land Cost = Total Land Area x current land cost
Land Cost = 325,000 m2 (Php2500/m2)
Land Cost = PHP 812,500,000.00
109
B. Equipment Cost
C. Electrical Cost
Electrical Cost = Equipment Cost x 25%
D. Building Cost
For Design Option 1
Building Cost = Equipment Cost x 33%
Building Cost = PHP 197,507,050,260.00x 0.33
Building Cost = PHP 65,177,326,585.8
E. Miscellaneous Cost
Miscellaneous Cost = Equipment Cost x 10%
Miscellaneous Cost = PHP 197,507,050,260.00x 0.1
Miscellaneous Cost = PHP 19,750,705,026.00
Operating Expenditure
A. Fuel Cost
HHV = 18311.95989 kJ/kg
Fuel Flow = 207899.2302kg/hr
Electrical Power = 300,000 kW
Heat Rate =
110
Heat Rate =
(2 units)
Fuel Cost = PHP 27,495,262.92
B. Labor Cost
Labor Cost = Fuel Cost x 20%
Labor Cost = PHP 27,495,262.92x 20%
Labor Cost = PHP 5,499,052.584
D. Supplies Cost
Supply Cost = Fuel Cost x 10%
Supply Cost = PHP 27,495,262.92x 10%
Supply Cost = PHP 2,749,526.292
E. Supervision Cost
Supervision Cost = Fuel Cost x 20%
Supervision Cost = PHP 27,495,262.92x 20%
Supervision Cost = PHP 5,499,052.584
F. Operating Taxes
Operating Taxes = Fuel Cost x 10%
111
Operating Taxes = PHP 27,495,262.92x 10%
Operating Taxes = PHP 2,749,526.292
H. Depreciation
year
Depreciation ate x 00
n
year
Depreciation ate x 00
years
Depreciation Rate = 4%
I. Revenue
Annual revenue = Power Generation Rate x Actual Plant Output
Annual Revenue = PHP 9.7599/kW-hr x (600,000 kW x 0.915)
(8760hrs/yr)
Annual Revenue = PHP 46,937,701,480.00
112
Net Present Value = Future Cash Flow – Total Capital Cost
Where:
Future Cash Flow = Future Revenue+ Salvage Value
Total Capital Cost = Initial Capital Cost +Operating Cost
K. Payback Period
113
Payback Period =
ROI =
, , . 6
Design Option 2
Power Demand Analysis
Depreciation
Service
Book Life Depreciation
Value(Php) Salvage Value (yrs) (BV-SV)/SL
Purchased
Equipment 200,126,507,160.00 72,124,936,136.72 25 5,120,062,840.93
Instrumentation 40,025,301,432.00 14424987227.34 25 1,024,012,568.18
114
and Control
Service
Facilities 20,012,650,716.00 7,212,493,613.67 25 512,006,284.09
Etc 30,018,976,074.00 10,818,740,420.50 25 768,009,426.13
Total 7,424,091,119.34
Return of Investment
Net Income After
Period TCI ROI
Tax
Year
(Php) (Php) (%)
Sensitivity Analysis
115
Increase of Fuel Price by 10% 10% 81,063,172.00 7.7361
Economical Parameters
A. Land Cost
Land Cost = Total Land Area x current land cost
Land Cost = 325,000 m2 (Php2500/m2)
Land Cost = PHP 812,500,000.00
B. Equipment Cost
C. Electrical Cost
Electrical Cost = Equipment Cost x 20%
Electrical Cost = PHP 200,126,507,160.00x 0.2
Electrical Cost = PHP 40,025,301,432.00
D. Building Cost
For Design Option 1
Building Cost = Equipment Cost x 33%
Building Cost = PHP 200,126,507,160.00x 0.33
Building Cost = PHP 66,041,747,362.8
116
E. Miscellaneous Cost
Miscellaneous Cost = Equipment Cost x 10%
Miscellaneous Cost = PHP 200,126,507,160.00x 0.1
Miscellaneous Cost = PHP 20,012,650,716.00
Heat Rate =
Heat Rate =
units)
Fuel Cost = PHP 23,960,737.41
B. Labor Cost
Labor Cost = Fuel Cost x 20%
Labor Cost = PHP 23,960,737.41x 20%
Labor Cost = PHP 4,792,147.482
117
C. Maintenance and Repair
Maintenance and Repair = Fuel Cost x 20%
Maintenance and Repair = PHP 23,960,737.41x 20%
Maintenance and Repair = PHP 4,792,147.482
D. Supplies Cost
Supply Cost = Fuel Cost x 10%
Supply Cost = PHP 23,960,737.41x 10%
Supply Cost = PHP 2,396,073.741
E. Supervision Cost
Supervision Cost = Fuel Cost x 20%
Supervision Cost = PHP 23,960,737.41x 20%
Supervision Cost = PHP 4,792,147.482
F. Operating Taxes
Operating Taxes = Fuel Cost x 10%
Operating Taxes = PHP 23,960,737.41x 10%
Operating Taxes = PHP 2,396,073.741
H. Depreciation
year
Depreciation ate x 00
n
year
Depreciation ate x 00
years
Depreciation Rate = 4%
I. Revenue
Annual revenue = Power Generation Rate x Actual Plant Output
Annual Revenue = PHP 9.7599/kW-hr x (600,000 kW x 0.915)
(8760hrs/yr)
Annual Revenue = PHP 46,937,701,480.00
119
Future Cash Flow = PHP 582,262,878,623.857
K. Payback Period
Payback Period =
ROI =
, , .
120
APPENDIX B
CATALOGUE
121
CATALOGUE FOR STEAM TURBINE
122
CATALOGUE FOR BOILER
123
CATALOGUE FOR PUMPS
124
CATALOGUE FOR DAERATOR
125
CATALOGUE FOR CLOSED FEEDWATER HEATER
126
CATALOGUE FOR PULVERIZER
127
PIPE SELECTION
128
APPENDIX C
PROJECT DOCUMENTATION
129
DOCUMENTATION
Before the selection of the final design, different design options were
made. See photos below:
130
Here are photos of the proponents analyzing and evaluating the
calculations obtained:
131
132
ORAL DEFENSE
133